Sent: 12/22/2010
E-mail Address: mayur.sonawane61@gmail.com
Subject: 13570-12

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency,samrat nagar kolhapur
Students Name (Surname_First Name_Middle Name) SONAWANE MAYUR MADHUKAR
Exam No. 13570
Working Day No. 12
Date (DD/MM/YYYY) 22/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Today we are observe further electrification, 1) Every room wire connection get connect to each main control board 2) And each main control board get connect to main meter which is placed at ground level 3) In each room space is provided at entrance ,to collect all the wire ,get connected to main meter board. .
Details of how you Planned & Executed the allotted work 1) Firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans. .
Details of the Construction Procedure / Activity / Technology learned today Constrction Procedure : 1) We are all groupmates study the Electrical drawing 2) Our quarries are asked to wire fitter 3) To measure height of switch board, foot light from bottom 4) Seperate space is provided at entrance of size 0.75*0.60M conveying all electrical wire to the ground level 5) Which are connected to main meter at basement 6) The Main Meter is connected to MSEB. .
Details of the Construction Materials learned today Construction Material : 1) 8 Module,4 Module switch board 2) PVC pipe for concealed wiring ,positive, negative, earthing wiring 3) Pana 4) Iron net which is placed on a concealed wiring to avoid cracking. 5)Diffrent types of mould or formwork as per requirement. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environment Caring Technology : To use crushing sand in place of natural sand.Therefore to minimise environment pollution. .
Details of the Construction / Engineering Drawings observed today Construction Drawings : Today we are observe Electrification Drawing- 1) Provision of switch board 2) Provision of fan point 3) Provision of tube,bulb point 4) All above connection are get connect to switch board as shown in drawing. .
Details of the Bye Laws referred today Today we are observe bye laws for, 1) Height of ventilator 2) Height of Door 3) Above values compare with actual site work. .
Details of any Managerial Skill learned today 1)The aggregate,sand, brick are placed in a suitable place to convey easy lifting of material. 2)The site incharge checked the propotions of different materials used. 3)The site incharge kept a proper record of total quantity. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR PAINTING Apply 3 coats of washable cement on 2 coat of primer including putty. Good quality primer= 0.2 kg per sq.m @ Rs.120= 0.2*120= Rs.24 Crack filling by putty= 0.30 kg per sq.m@ Rs.60 per kg= 0.30*60= Rs.18 Sand paper 120 no.= Rs.6 per sq.m cement colour = 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.7 per sq.m Labour for cement for 2 coats= Rs.20per sq.m Total cost= 24+18+6+18+7+20= Rs.95 Add 10% Profit= Rs 9.50 Total cost per sq.m= 95+9.50= Rs.104.5= say Rs.105 per sq.m .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.105/sq.m
Todays BUZZ Word SITE SAFTEY:-following saftey measure are taken by construction builders 1) to provide safety belts incase of big height buildungs then net is provided. 2) labour compensation act. 3) to provide helmate,handglows,shoes to the workers. 4) to provide labour insurance life plan. 5) to provide proper tools and plants,bracing. BASIC FACILITIS:- drinking water jar . labour kids sitting place. toilet arrangement. scooter parking arrangement. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharmal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-12

Company Name Pooja Developers & Builders
Project Name & Site Address Pooka Developers & Builders, Nagala Park, Kolhapur
Students Name (Surname_First Name_Middle Name) Hasabnis Ketaki Bhagwan
Exam No. 13527
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge To see and study the reinforcement for beams of third floor. To see the placing of formwork and shuttering for third floor.
Details of how you Planned & Executed the allotted work We first went on the formwork work of third floor. We saw how the steel of beams was being laid as per plans. We saw how the laborers place the formwork and shuttering which is a very risky work.
Details of the Construction Procedure / Activity / Technology learned today We learned how the laborers laid the reinforcement (steel) for beam of third floor.They marked the spacing between stirrups by chalk and then fix the stirrups, how the formwork was constructed for third floor.
Details of the Construction Materials learned today Material for manufacturing flyash like lime,gypsum,flyash,cement. Material for manufacturing concrete at site like 1 bag cement,weigh batched proportions of coarse and fine aggregate, proper proportion of water. material used for shutteing,formwork. Steel used for beams like mild steel,tor steel of different sizes ranging from 8mm to 30mm etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The process of proper drainage system,Proper disposal of waste in waste treatment plant is going to be adopted after completion of project.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for schedule of beams of third floor.
Details of the Bye Laws referred today 1. The number and spacing of steel for beams is placed as per bye laws. 2. The mix proportion for concrete made at site is as per bye laws.
Details of any Managerial Skill learned today 1. The site in-charge inspected the site and checked the work going on. 2. The site in-charge checked that the steel that was brought by the contractor was as per quotation.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"FULLY COMPLETE DOOR\" “T.W.Paneled door” Total cost of Providing and fixing country Teak Wood single paneled doorswith 35mm thick shutter and 25mm thick panels with fastenings and finishing the wood work with oil painting completed= Rs.3400/sq.m Labor cost= Rs.600/sq.m Total cost= 3400+600= Rs.4000/sq.m Including 10% profit= Rs.400. Total cost= 4000+400= Rs.4400/sq.m “FLUSH DOOR” Providing And fixing solid core flush door in single leaf 32mm thick decorative type of exterior grade etc. including finishing with french polish= Rs.1700/sq.m Labour cost= Rs.250/sq.m Total cost= 1700+250= Rs.1950/sq.m Including 10% profit= Rs.195. Total cost= 1950+195= Rs.2145/sq.m Rs.4400/sq.m for T.W.Paneled door. Rs.2145/sq.m for solid core flush door.
Result of RATE ANALYSIS ( Rs per Unit ) Rs 2145
Todays BUZZ Word \"MY SITE TRAINING EXPERIENCE\" >It was a different experience altogether. >Till today we learnt theories but we didnt knew how to implement them in day to day life. >During this twelve days of training we learnt how theories are implemented and what are the difficulties in implementing these theories. >I was lucky enough to complete my training under the guidance of Paras Oswal Sir of Pooja developers & Builders. >They have undertaken the project of building the first 11 storeyed skyscraper in Kolhapur. >My group members met Oswal Sir one day prior to our training prpgramme. >When we met him we were very happy that we got a an opportunity to work with fantastic personality, a man who is among one of the well-known,privileged,social worker and a good human being of Kolhapur. >I was bit tensed on first day, whether I will be able to get along with my group members but in no time we got to know each other and was very comfortable during the course of training. >we started helping each other,sharing,discussing about different procedures,systems we saw on site.we cleared each other\'s doubts. >Explaining each other was good n easy cause we could understand things in our language. >Understanding things was easy cause we could do things practically. >On the very first day we got to learn many new things like how steel for beams were laid according to plans, how concrete was placed for stair-case,how columns were made etc. >Helmets were compulsory for us. >We were new on site so labourers were looking at us like a stranger wearing helmets. >The interesting thing was that besides being the most important and biggest project of Kolhapur we were the only 5 to wear helmets on site. >The first day ended up happily. >On day 2, we introduced ourselves with the labourers we found that majority of them were from Bihar and Jharkhand. >We had to talk with them in hindi so that they could understand. >We asked our difficulties to the site incharge as well as the labourers wherever we felt and they responded us well and cleared our doubts. >On the same day we met Mr.Pramod Salvekar who was among the only two dealers of Reticulated Gas Pipeline system in Maharashtra.It was nice to meet him. >The next 2 days we saw the construction of slab by R.M.C,electrification work,plumbing work,staircase,planning of pipe system for reticulated gas pipeline. etc. >On day 5 while we were on site Oswal sir came to inspect the site. He met us, inquired that we were not having difficulties and problems and at that time he suggested us to visit his Farm house construction at Panhala and at Panchgaon. >We were so much happy after listening this, we told Sir that the next day we would visit that site. Oswal sir informed the site incharge at Panhala and made arrangement of lunch for us. >On day7, we went to Panhala reached there at 9 and met the site incharge and saw the site. >It was awesome and all the farmhouses were booked. >Then he gave us plans and we saw the whole site. >Then in the afternoon we were served lunch made on choolha in a small home. >We liked that food very much.Then we visited the site again talked with the site incharge about the project and departed from Panhala at 4. >It was just an Amazing day and a memorable one. >On the 8th day we were back on our site \"WONDER 11\". On that day we participated in a programme in which Oswal Sir launched a pioneered a new technology and their venture \"INFINITE BIO-FUELS AND AGRITECH PVT.LTD\" in which they aimed to reduce the waste like agricultutral waste,garbage etc. and used it for heating purpose. >The next day we went to the site at Panchgaon.There we saw the construction of 2 storeyed building going on >there we met the consulting engineer of Pooja group Mr.Sameer Shah. >He gave us a brief information of the overall construction of Pooja group going on >He gave us some new information and encouraged us to go for P.G. >On day 10 and 11 we studied and saw the process of manufacturing Fly ash bricks,construction of staircase by concrete made at site etc. >On the last day Day 12,the site incharge P.B.Sutar sir and Sarvalkar sir on recommendation of Oswal sir arranged lunch for us at their canteen,inspite that we told them that we had brought our lunchboxes, they made us compulsory, We were very thankful to them for their kindness. We met all the labourers for the last time we didn\'t wanted to live the site but we had too. We wanted to meet Oswal sir But he is out of town so we couldn\'t,so we departed from the site. >If the site training is again, i wish that i should get the same group members and same group \"POOJA GROUP\". >The site training gave us atleast 20% knowledge and brought us out from our book world into the practical. We thank you Pathan sir for a wonderful opportunity u gave us and we hope that u will encourage us hereafter the same way. This site training will be definitely a memorable one for me and all.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883-12

Company Name Star Tech Infra
Project Name & Site Address star aashiyana near ragendra nagar, kolhapur
Students Name (Surname_First Name_Middle Name) arora saurabh
Exam No. 10883
Working Day No. 12
Date (DD/MM/YYYY) 21/12/10
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge steel framing for footing,road compaction with the help of \"DHUMUS\". cutting of hardend plastred cumpound wall for framing work .
Details of how you Planned & Executed the allotted work we observed the steel framing work of column for footing work,it has done according to stuctural desing,framing work is done under a good supervision the rings has been tied properly ,and no. of rings n sizes of the rings are taken as it has mentioned according to the drawing. They use the tor steel for footing work.advantages of tor steel are it gives the higher bond,less crAck width due to high bond. road compaction is done with the vibrating type of compaction machine, called \"DHUMUS\". FOR THIS TYPE OF COMPACTION u ned a skilled labour.compaction is done along the margin of the road.
Details of the Construction Procedure / Activity / Technology learned today we observed the formwork for staircase,formwork for beam. we observed that we have to check the shuttering work before concerting n reinforcement. compaction of the road with vibratory compacter (duhmus). De-shuttering of the form work n precutions to be taken while de-shttring. while de-shuttering of the form work for the cloums or beam ensure that edges are protected. while de-shuttering of internal beam sides,ensure thatsupports of the slab and beam bottom should not disturbed. minimum period for the de-shuttering of column is 24hrs. minimum period for the de-shuttering sides of beam is 24hrs.
Details of the Construction Materials learned today The constuction material learnd today steel n timber. As steel is the most important component of constuction material. steel is used to make the stucture strong and to distribute the load. there are ifferent types of steel n steel bars r preesent in the market. and they are used as per the requirenment. types of the reinforcing steel bars such as plain steel ,tor seel. It is wiedly used in the in building construction in beams ,columns,slabs,for footing work etc. Disadvantages of steel framed structures is corrosion.they shouled be oil painted, an proper maintenance should be taken to protect their surfaces so that they can be used for under ground water construction. TIMBER:timber is used for temperory n permanent member in constuction work such as permanent suctural work for beams ,columns,roofing. frame work timber for framed structures and genral use in windows n doors. heavy constuction. Temperory structural work :rcc construction ,centering ,scaffolding etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Eco-friendly constuction. If proper care is not taken and environmental aspects are ignored the buildings and cities will turn to deserted sie.If they properly adopted ;green building and green cities are produced. use of eco-friendlyconstruction tecniques,natural energy sources with environmental care are essential for geern buildings/cities. each designer ,architect,engineer and builder should construct each building ;with good essential servicesy like waret supply ,sewage disposal,solid waste disposal,roads,electricity and all the concernd athorities should devlope each city to make it free from environmental pollution. following points to be implemented. 1)use of solar energy for lighting purposes 2)use of solar energy for heating purposes 3)eco-friendly house construction techniqes. 4)rain water harvesting 5)waste recycling 6)free plantation 7)use of natural material 8)se of natural ventilation and lighting. in short every attempt is to be madde to use natural resources and materials . these will increasa the comforts at low running cost . in other words gree building and green cities are created.
Details of the Construction / Engineering Drawings observed today electrical drawings electrical layout in the premises with location,levels of points an switches. position of distribution box/feeder pillars. road lights position. cable laying position below road. transformer details and locations. light points in the entire area. earthing position of each building. internal room wise electical piont details for flats.
Details of the Bye Laws referred today permission for development no develepment to be carried out without development permission and commencement certificate. NOW MUNCIPAL CORPORATION have made a law that wtihout rainwater harvesting and parking in your drawing they wont give you the permission for the devlopment.
Details of any Managerial Skill learned today 1)proper maintenence of records . 2)maintenence of the seprate files for each drawing. 3)attentiveness 4)how to tackel with the workers. 5)check out of the list of work done. 6)alterness
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS (for Flush Door) Door size=(3*7)ft for this use wood size (5\"*2.5\") for frame we use 1.5ft3 wood rate of 1 ft3 =2000 rs 1.5 *2000 = 3000 rs (82\"*32\") =60rs lipping patti =20ft* 5rs =100rs labour charge =350rs = over all charge of door aldrop(1no.)=250rs latches =150rs bijagari(3no.)=3*60=180rs handle (2no.)=2*50=100rs tower bolt (1no.)=30rs magnet (1no.)=30rs door eye (no.)=70rs hinges (24no.)=totalcost=25rs hanel screws(24no.)totla cost =20rs nails (1inch=100gm)=10rs fevicol (100gm)=40rs TOTAL COST OF DOOR OF SIZE(3*7)ft=4415rs 3*7 = 21 ft2=21/10.76m2=1.95m2 for 1m2= 4415rs/1.95m2= 2264rs/m2 RESULT FOR FLUSH DOOR =2264RS/M2
Result of RATE ANALYSIS ( Rs per Unit ) 2264rs/m2
Todays BUZZ Word First of all i would like to thank you my prof MR.Irfan patan sir for given us all such opprotunities,n working hard for us so that we students would be able to take the advantage of todays tecnology.my expireance starts wid this coz i observed that many of the students where not having the email id. after that my first day on the site was quite good.First we mate the incharge of that site we introduce our selfs to him.Then we mate the superviser of the site. I found that site incharge was quite cool,but the superviser was very srict. we explaned him all our 12 days shadule of traning.He start to explain us each n everything,n i found him very polite.first day we where little afraid, we went on visited all the places where the constuction work as going on, and started observing the work. First day we observed the basic things like what is the project,how much constuction has cumplitated,how much work is going on,n ho much work has be complite. accordingly then we strated our work for each day.daily we being on site sharpe at 9:00am then our site incharge tlod us the work n accoringly we observd the work. And daily at end of the day he helped us in buzz word n in rate analysis. he has been guied us n answere all our quires. daily after coming on site we visit all the site and carefully observed all the work and asked the quries related to that work.we saw the pcc work ,painting work, shuttering,de-shttering,formwork for staircase,steel framing for column,workers skills. i observed that what ever we learned in therotical is totaly different then what we observed at the site work.we observed how to minimize the the wastage,an saw all the inatrments and se of the instruments on the site.we saw the aquracy ,cement concentration,w/c ratio,size of aggregates and sand.wroing on thee site is tolaly diffrent than the therotical knowlege. things get manipulated little bit to compensate the error.we learned the handling of the workers ,supervision,attentiveness towards the workers. we LEARNED how the bilding is made atrractive by using the atrractive and high quality material and how they cannected to the brand so that publicity of the building is carried out. IN actual construction the FSI is 1.and if the fsi is not one to make it one we carry the TDR . AS MUNCIPAL CORPORATION made the rain water harvesing ,setback,parking made compulsory without it they dint santion the plan. OVER MY EXPERIENC OF 12 DAYS WAS VRY NICE I HAVE LEARED MANY THINGS WHICH I WAS TOTALY UNAWARE.I will never forget th ethings whic i have learned in these 12 days.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.SATISH
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-12

Company Name Star Tech Infra
Project Name & Site Address star aashiyana near rajendra nagar,kolhapur
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 12
Date (DD/MM/YYYY) 21/12/10
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge steel framing for footing,road compaction with the help of \"DHUMUS\". cutting of hardend plastred cumpound wall for framing work .
Details of how you Planned & Executed the allotted work we observed the steel framing work of column for footing work,it has done according to stuctural desing,framing work is done under a good supervision the rings has been tied properly ,and no. of rings n sizes of the rings are taken as it has mentioned according to the drawing. They use the tor steel for footing work.advantages of tor steel are it gives the higher bond,less crAck width due to high bond. road compaction is done with the vibrating type of compaction machine, called \"DHUMUS\". FOR THIS TYPE OF COMPACTION u ned a skilled labour.compaction is done along the margin of the road.
Details of the Construction Procedure / Activity / Technology learned today we observed the formwork for staircase,formwork for beam. we observed that we have to check the shuttering work before concerting n reinforcement. compaction of the road with vibratory compacter (duhmus). De-shuttering of the form work n precutions to be taken while de-shttring. while de-shuttering of the form work for the cloums or beam ensure that edges are protected. while de-shuttering of internal beam sides,ensure thatsupports of the slab and beam bottom should not disturbed. minimum period for the de-shuttering of column is 24hrs. minimum period for the de-shuttering sides of beam is 24hrs.
Details of the Construction Materials learned today The constuction material learnd today steel n timber. As steel is the most important component of constuction material. steel is used to make the stucture strong and to distribute the load. there are ifferent types of steel n steel bars r preesent in the market. and they are used as per the requirenment. types of the reinforcing steel bars such as plain steel ,tor seel. It is wiedly used in the in building construction in beams ,columns,slabs,for footing work etc. Disadvantages of steel framed structures is corrosion.they shouled be oil painted, an proper maintenance should be taken to protect their surfaces so that they can be used for under ground water construction. TIMBER:timber is used for temperory n permanent member in constuction work such as permanent suctural work for beams ,columns,roofing. frame work timber for framed structures and genral use in windows n doors. heavy constuction. Temperory structural work :rcc construction ,centering ,scaffolding etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Eco-friendly constuction. If proper care is not taken and environmental aspects are ignored the buildings and cities will turn to deserted sie.If they properly adopted ;green building and green cities are produced. use of eco-friendlyconstruction tecniques,natural energy sources with environmental care are essential for geern buildings/cities. each designer ,architect,engineer and builder should construct each building ;with good essential servicesy like waret supply ,sewage disposal,solid waste disposal,roads,electricity and all the concernd athorities should devlope each city to make it free from environmental pollution. following points to be implemented. 1)use of solar energy for lighting purposes 2)use of solar energy for heating purposes 3)eco-friendly house construction techniqes. 4)rain water harvesting 5)waste recycling 6)free plantation 7)use of natural material 8)se of natural ventilation and lighting. in short every attempt is to be madde to use natural resources and materials . these will increasa the comforts at low running cost . in other words gree building and green cities are created.
Details of the Construction / Engineering Drawings observed today electrical drawings electrical layout in the premises with location,levels of points an switches. position of distribution box/feeder pillars. road lights position. cable laying position below road. transformer details and locations. light points in the entire area. earthing position of each building. internal room wise electical piont details for flats.
Details of the Bye Laws referred today permission for development no develepment to be carried out without development permission and commencement certificate. NOW MUNCIPAL CORPORATION have made a law that wtihout rainwater harvesting and parking in your drawing they wont give you the permission for the devlopment.
Details of any Managerial Skill learned today 1)proper maintenence of records . 2)maintenence of the seprate files for each drawing. 3)attentiveness 4)how to tackel with the workers. 5)check out of the list of work done. 6)alterness
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS (for Flush Door) Door size=(3*7)ft for this use wood size (5\"*2.5\") for frame we use 1.5ft3 wood rate of 1 ft3 =2000 rs 1.5 *2000 = 3000 rs (82\"*32\") =60rs lipping patti =20ft* 5rs =100rs labour charge =350rs = over all charge of door aldrop(1no.)=250rs latches =150rs bijagari(3no.)=3*60=180rs handle (2no.)=2*50=100rs tower bolt (1no.)=30rs magnet (1no.)=30rs door eye (no.)=70rs hinges (24no.)=totalcost=25rs hanel screws(24no.)totla cost =20rs nails (1inch=100gm)=10rs fevicol (100gm)=40rs TOTAL COST OF DOOR OF SIZE(3*7)ft=4415rs 3*7 = 21 ft2=21/10.76m2=1.95m2 for 1m2= 4415rs/1.95m2= 2264rs/m2 RESULT FOR FLUSH DOOR =2264RS/M2
Result of RATE ANALYSIS ( Rs per Unit ) 2264rs/m2
Todays BUZZ Word First of all i would like to thank you my prof MR.Irfan patan sir for given us all such opprotunities,n working hard for us so that we students would be able to take the advantage of todays tecnology.my expireance starts wid this coz i observed that many of the students where not having the email id. after that my first day on the site was quite good.First we mate the incharge of that site we introduce our selfs to him.Then we mate the superviser of the site. I found that site incharge was quite cool,but the superviser was very srict. we explaned him all our 12 days shadule of traning.He start to explain us each n everything,n i found him very polite.first day we where little afraid, we went on visited all the places where the constuction work as going on, and started observing the work. First day we observed the basic things like what is the project,how much constuction has cumplitated,how much work is going on,n ho much work has be complite. accordingly then we strated our work for each day.daily we being on site sharpe at 9:00am then our site incharge tlod us the work n accoringly we observd the work. And daily at end of the day he helped us in buzz word n in rate analysis. he has been guied us n answere all our quires. daily after coming on site we visit all the site and carefully observed all the work and asked the quries related to that work.we saw the pcc work ,painting work, shuttering,de-shttering,formwork for staircase,steel framing for column,workers skills. i observed that what ever we learned in therotical is totaly different then what we observed at the site work.we observed how to minimize the the wastage,an saw all the inatrments and se of the instruments on the site.we saw the aquracy ,cement concentration,w/c ratio,size of aggregates and sand.wroing on thee site is tolaly diffrent than the therotical knowlege. things get manipulated little bit to compensate the error.we learned the handling of the workers ,supervision,attentiveness towards the workers. we LEARNED how the bilding is made atrractive by using the atrractive and high quality material and how they cannected to the brand so that publicity of the building is carried out. IN actual construction the FSI is 1.and if the fsi is not one to make it one we carry the TDR . AS MUNCIPAL CORPORATION made the rain water harvesing ,setback,parking made compulsory without it they dint santion the plan. OVER MY EXPERIENC OF 12 DAYS WAS VRY NICE I HAVE LEARED MANY THINGS WHICH I WAS TOTALY UNAWARE.I will never forget th ethings whic i have learned in these 12 days.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. SATISH
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: viju128@gmail.com
Subject: 3638-12

Company Name Star Tech Infra
Project Name & Site Address star aashiyana near rajendra nagar, kolhapur
Students Name (Surname_First Name_Middle Name) shinde vijay namdeo
Exam No. 3638
Working Day No. 12
Date (DD/MM/YYYY) 21/12/10
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge steel framing for footing,road compaction with the help of \"DHUMUS\". cutting of hardend plastred cumpound wall for framing work .
Details of how you Planned & Executed the allotted work we observed the steel framing work of column for footing work,it has done according to stuctural desing,framing work is done under a good supervision the rings has been tied properly ,and no. of rings n sizes of the rings are taken as it has mentioned according to the drawing. They use the tor steel for footing work.advantages of tor steel are it gives the higher bond,less crAck width due to high bond. road compaction is done with the vibrating type of compaction machine, called \"DHUMUS\". FOR THIS TYPE OF COMPACTION u ned a skilled labour.compaction is done along the margin of the road.
Details of the Construction Procedure / Activity / Technology learned today we observed the formwork for staircase,formwork for beam. we observed that we have to check the shuttering work before concerting n reinforcement. compaction of the road with vibratory compacter (duhmus). De-shuttering of the form work n precutions to be taken while de-shttring. while de-shuttering of the form work for the cloums or beam ensure that edges are protected. while de-shuttering of internal beam sides,ensure thatsupports of the slab and beam bottom should not disturbed. minimum period for the de-shuttering of column is 24hrs. minimum period for the de-shuttering sides of beam is 24hrs.
Details of the Construction Materials learned today The constuction material learnd today steel n timber. As steel is the most important component of constuction material. steel is used to make the stucture strong and to distribute the load. there are ifferent types of steel n steel bars r preesent in the market. and they are used as per the requirenment. types of the reinforcing steel bars such as plain steel ,tor seel. It is wiedly used in the in building construction in beams ,columns,slabs,for footing work etc. Disadvantages of steel framed structures is corrosion.they shouled be oil painted, an proper maintenance should be taken to protect their surfaces so that they can be used for under ground water construction. TIMBER:timber is used for temperory n permanent member in constuction work such as permanent suctural work for beams ,columns,roofing. frame work timber for framed structures and genral use in windows n doors. heavy constuction. Temperory structural work :rcc construction ,centering ,scaffolding etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Eco-friendly constuction. If proper care is not taken and environmental aspects are ignored the buildings and cities will turn to deserted sie.If they properly adopted ;green building and green cities are produced. use of eco-friendlyconstruction tecniques,natural energy sources with environmental care are essential for geern buildings/cities. each designer ,architect,engineer and builder should construct each building ;with good essential servicesy like waret supply ,sewage disposal,solid waste disposal,roads,electricity and all the concernd athorities should devlope each city to make it free from environmental pollution. following points to be implemented. 1)use of solar energy for lighting purposes 2)use of solar energy for heating purposes 3)eco-friendly house construction techniqes. 4)rain water harvesting 5)waste recycling 6)free plantation 7)use of natural material 8)se of natural ventilation and lighting. in short every attempt is to be madde to use natural resources and materials . these will increasa the comforts at low running cost . in other words gree building and green cities are created.
Details of the Construction / Engineering Drawings observed today electrical drawings electrical layout in the premises with location,levels of points an switches. position of distribution box/feeder pillars. road lights position. cable laying position below road. transformer details and locations. light points in the entire area. earthing position of each building. internal room wise electical piont details for flats.
Details of the Bye Laws referred today permission for development no develepment to be carried out without development permission and commencement certificate. NOW MUNCIPAL CORPORATION have made a law that wtihout rainwater harvesting and parking in your drawing they wont give you the permission for the devlopment.
Details of any Managerial Skill learned today 1)proper maintenence of records . 2)maintenence of the seprate files for each drawing. 3)attentiveness 4)how to tackel with the workers. 5)check out of the list of work done. 6)alterness
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS (for Flush Door) Door size=(3*7)ft for this use wood size (5\"*2.5\") for frame we use 1.5ft3 wood rate of 1 ft3 =2000 rs 1.5 *2000 = 3000 rs (82\"*32\") =60rs lipping patti =20ft* 5rs =100rs labour charge =350rs = over all charge of door aldrop(1no.)=250rs latches =150rs bijagari(3no.)=3*60=180rs handle (2no.)=2*50=100rs tower bolt (1no.)=30rs magnet (1no.)=30rs door eye (no.)=70rs hinges (24no.)=totalcost=25rs hanel screws(24no.)totla cost =20rs nails (1inch=100gm)=10rs fevicol (100gm)=40rs TOTAL COST OF DOOR OF SIZE(3*7)ft=4415rs 3*7 = 21 ft2=21/10.76m2=1.95m2 for 1m2= 4415rs/1.95m2= 2264rs/m2 RESULT FOR FLUSH DOOR =2264RS/M2
Result of RATE ANALYSIS ( Rs per Unit ) 2264rs/m2
Todays BUZZ Word First of all i would like to thank you my prof MR.Irfan patan sir for given us all such opprotunities,n working hard for us so that we students would be able to take the advantage of todays tecnology.my expireance starts wid this coz i observed that many of the students where not having the email id. after that my first day on the site was quite good.First we mate the incharge of that site we introduce our selfs to him.Then we mate the superviser of the site. I found that site incharge was quite cool,but the superviser was very srict. we explaned him all our 12 days shadule of traning.He start to explain us each n everything,n i found him very polite.first day we where little afraid, we went on visited all the places where the constuction work as going on, and started observing the work. First day we observed the basic things like what is the project,how much constuction has cumplitated,how much work is going on,n ho much work has be complite. accordingly then we strated our work for each day.daily we being on site sharpe at 9:00am then our site incharge tlod us the work n accoringly we observd the work. And daily at end of the day he helped us in buzz word n in rate analysis. he has been guied us n answere all our quires. daily after coming on site we visit all the site and carefully observed all the work and asked the quries related to that work.we saw the pcc work ,painting work, shuttering,de-shttering,formwork for staircase,steel framing for column,workers skills. i observed that what ever we learned in therotical is totaly different then what we observed at the site work.we observed how to minimize the the wastage,an saw all the inatrments and se of the instruments on the site.we saw the aquracy ,cement concentration,w/c ratio,size of aggregates and sand.wroing on thee site is tolaly diffrent than the therotical knowlege. things get manipulated little bit to compensate the error.we learned the handling of the workers ,supervision,attentiveness towards the workers. we LEARNED how the bilding is made atrractive by using the atrractive and high quality material and how they cannected to the brand so that publicity of the building is carried out. IN actual construction the FSI is 1.and if the fsi is not one to make it one we carry the TDR . AS MUNCIPAL CORPORATION made the rain water harvesing ,setback,parking made compulsory without it they dint santion the plan. OVER MY EXPERIENC OF 12 DAYS WAS VRY NICE I HAVE LEARED MANY THINGS WHICH I WAS TOTALY UNAWARE.I will never forget th ethings whic i have learned in these 12 days.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge mr.satish
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-12

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Builders and Developers,near jayPrabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) tekwani sagar bansilal
Exam No. 10903
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00
Site Leaving Time (HH:MM am/pm) 4.00
Details of the Work Allotted to you today by the Site In-Charge To see and study the laying of steel of beams of third floor. To see the placing of formwork and shuttering for third floor.
Details of how you Planned & Executed the allotted work We first went on the centering work of third floor.We saw how the steel of beams was been laid as per plans. We saw how the labourers place the formwork and shuttering which is a very risky work.
Details of the Construction Procedure / Activity / Technology learned today We learned how the labourers by using plans laid the steel for beams of third floor,how they marked the spacing between stirrups by chalk and then fix the stirrups, how the formwork was constructed for third floor.
Details of the Construction Materials learned today Material for manufacturing flyash like lime,gypsum,flyash,cement. Material for manufacturing concrete at site like 1 bag cement,weigh batched proportions of coarse and fine aggregate, proper proportion of water. material used for shutteing,formwork, steel used for beams like mild steel,tor steel of different sizes ranging form 8mm to 30mm etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper drainage system,Proper disposal of waste in waste treatment plant is going to be done after completion of project.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for schedule of beams for third floor.
Details of the Bye Laws referred today 1. The number and spacing of steel for beams is placed as per bye laws. 2. The mix proportion for concrete made at site is as per bye laws.
Details of any Managerial Skill learned today 1. The site incharge inspected the site and checked the work going on. 2. The site incharge checked that the steel that was brought by the contractor was as per quotataion.
RATE ANALYSIS (Detailed Stepwise Calculations required) “T.W.Panelled door” Total cost of Providing and fixing country Teak Wood single panelled doorswith 35mm thick shutter and 25mm thick panels with fastenings and finishing the wood work with oil painting completed= Rs.3400/sq.m Labour cost= Rs.600/sq.m Total cost= 3400+600= Rs.4000/sq.m Including 10% profit= Rs.400. Total cost= 4000+400= Rs.4400/sq.m “FLUSH DOOR” Providing And fixing solid core flush door in single leaf 32mm thick decorative type of exterior grade etc. including finishing with french polish= Rs.1700/sq.m Labour cost= Rs.250/sq.m Total cost= 1700+250= Rs.1950/sq.m Including 10% profit= Rs.195. Total cost= 1950+195= Rs.2145/sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4400/sq.m for T.W.Panelled door.
Todays BUZZ Word MY SITE TRAINING EXPERIENCE\" The first time Pathan sir declared that their will be site training before exams,I was very happy with that thing,throughout the exams i was just thinking about the training programme. Firstly i was happy that i was in group of Pooja builders which was constructing \"WONDER 11\" first 11 storeyed skyscraper in kolhapur. exams finished then i and my other froup members went to visit Mr.Paras Oswal sir prior to our training programme. On the last day Day 12,the site incharge P.B.Sutar sir and Sarvalkar sir on recommendation of Paras Oswal sir had arrranged afternoon\'s lunch for us at their canteen,inspite that we told them that we had brought our lunchboxes, they made us compulsory, We were very thankful to them for their kindness.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523-12

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Builders and Developers,near jayPrabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DEVKAR VIKRAM DILIP
Exam No. 13523
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge To see and study the laying of steel of beams of third floor. To see the placing of formwork and shuttering for third floor.
Details of how you Planned & Executed the allotted work We first went on the centering work of third floor.We saw how the steel of beams was been laid as per plans. We saw how the labourers place the formwork and shuttering which is a very risky work.
Details of the Construction Procedure / Activity / Technology learned today We learned how the labourers by using plans laid the steel for beams of third floor,how they marked the spacing between stirrups by chalk and then fix the stirrups, how the formwork was constructed for third floor.
Details of the Construction Materials learned today Material for manufacturing flyash like lime,gypsum,flyash,cement. Material for manufacturing concrete at site like 1 bag cement,weigh batched proportions of coarse and fine aggregate, proper proportion of water. material used for shutteing,formwork, steel used for beams like mild steel,tor steel of different sizes ranging form 8mm to 30mm etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper drainage system,Proper disposal of waste in waste treatment plant is going to be done after completion of project.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for schedule of beams for third floor.
Details of the Bye Laws referred today 1. The number and spacing of steel for beams is placed as per bye laws. 2. The mix proportion for concrete made at site is as per bye laws.
Details of any Managerial Skill learned today 1. The site incharge inspected the site and checked the work going on. 2. The site incharge checked that the steel that was brought by the contractor was as per quotataion.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"FULLY COMPLETE DOOR\" \"T.W.Panelled door\" Total cost of Providing and fixing country Teak Wood single panelled doorswith 35mm thick shutter and 25mm thick panels with fastenings and finishing the wood work with oil painting completed= Rs.3400/sq.m Labour cost= Rs.600/sq.m Total cost= 3400+600= Rs.4000/sq.m Including 10% profit= Rs.400. Total cost= 4000+400= Rs.4400/sq.m \"FLUSH DOOR\' Providing And fixing solid core flush door in single leaf 32mm thick decorative type of exterior grade etc. including finishing with french polish= Rs.1700/sq.m Labour cost= Rs.250/sq.m Total cost= 1700+250= Rs.1950/sq.m Including 10% profit= Rs.195. Total cost= 1950+195= Rs.2145/sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4400/sq.m for T.W.Panelled door.
Todays BUZZ Word MY SITE TRAINING EXPERIENCE\" The first time Pathan sir declared that their will be site training before exams,I was very happy with that thing,throughout the exams i was just thinking about the training programme. Firstly i was happy that i was in group of Pooja builders which was constructing \"WONDER 11\" first 11 storeyed skyscraper in kolhapur. exams finished then i and my other froup members went to visit Mr.Paras Oswal sir prior to our training programme. On the last day Day 12,the site incharge P.B.Sutar sir and Sarvalkar sir on recommendation of Paras Oswal sir had arrranged afternoon\'s lunch for us at their canteen,inspite that we told them that we had brought our lunchboxes, they made us compulsory, We were very thankful to them for their kindness. We met all the labourers for the last time we didn\'t wanted to live the site but we had too. We wanted to meet Paras Oswal sir But he was out of town so we couldn\'t,so we departed from the site. If their will site training again i wish that i may get the ssame group members and same group \"POOJA GROUP\".
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521-11

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Builders and Developers,near jayPrabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) BAGMARE DINESH SHRIRAM
Exam No. 13521
Working Day No. 11
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge To see and study the laying of steel of beams of third floor. To see the placing of formwork and shuttering for third floor.
Details of how you Planned & Executed the allotted work We first went on the centering work of third floor.We saw how the steel of beams was been laid as per plans. We saw how the labourers place the formwork and shuttering which is a very risky work.
Details of the Construction Procedure / Activity / Technology learned today We learned how the labourers by using plans laid the steel for beams of third floor,how they marked the spacing between stirrups by chalk and then fix the stirrups, how the formwork was constructed for third floor.
Details of the Construction Materials learned today Material for manufacturing flyash like lime,gypsum,flyash,cement. Material for manufacturing concrete at site like 1 bag cement,weigh batched proportions of coarse and fine aggregate, proper proportion of water. material used for shutteing,formwork, steel used for beams like mild steel,tor steel of different sizes ranging form 8mm to 30mm etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper drainage system,Proper disposal of waste in waste treatment plant is going to be done after completion of project.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for schedule of beams for third floor.
Details of the Bye Laws referred today 1. The number and spacing of steel for beams is placed as per bye laws. 2. The mix proportion for concrete made at site is as per bye laws.
Details of any Managerial Skill learned today 1. The site incharge inspected the site and checked the work going on. 2. The site incharge checked that the steel that was brought by the contractor was as per quotataion.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"FULLY COMPLETE DOOR\" \"T.W.Panelled door\" Total cost of Providing and fixing country Teak Wood single panelled doorswith 35mm thick shutter and 25mm thick panels with fastenings and finishing the wood work with oil painting completed= Rs.3400/sq.m Labour cost= Rs.600/sq.m Total cost= 3400+600= Rs.4000/sq.m Including 10% profit= Rs.400. Total cost= 4000+400= Rs.4400/sq.m \"FLUSH DOOR\" Providing And fixing solid core flush door in single leaf 32mm thick decorative type of exterior grade etc. including finishing with french polish= Rs.1700/sq.m Labour cost= Rs.250/sq.m Total cost= 1700+250= Rs.1950/sq.m Including 10% profit= Rs.195. Total cost= 1950+195= Rs.2145/sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4400/sq.m for T.W.Panelled door.
Todays BUZZ Word The first time Pathan sir declared that their will be site training before exams,I was very happy with that thing,throughout the exams i was just thinking about the training programme. Firstly i was happy that i was in group of Pooja builders which was constructing \"WONDER 11\" first 11 storeyed skyscraper in kolhapur. exams finished then i and my other froup members went to visit Mr.Paras Oswal sir prior to our training programme. When we met we felt very happy that we got a very fantastic personality to work with,a man who was among one of the well-known,priviledged,a social worker and a good human being of Kolhapur. We started our training on 8th Dec. During the first day itself we got to learn many new things that how steel for beams was laid according to plans, how concrete was placed for stair-case,how columns were made etc. We were new on site so labourers were seeing us like a strangers wearing helmets, the interesting thing was that besides being the most important and biggest project of kolhapur we were the only 5 to wear helmets on site. The first day ended up happily. During day 10 and 11 we studied and saw the prcess of manufacturing Fly ash bricks,construction of staircase by concrete made at site etc. On the last day Day 12,the site incharge P.B.Sutar sir and Sarvalkar sir on recommendation of Paras Oswal sir had arrranged afternoon\'s lunch for us at their canteen,inspite that we told them that we had brought our lunchboxes, they made us compulsory, We were very thankful to them for their kindness. We met all the labourers for the last time we didn\'t wanted to live the site but we had too. We wanted to meet Paras Oswal sir But he was out of town so we couldn\'t,so we departed from the site. If their will site training again i wish that i may get the same group members and same group \"POOJA GROUP\".
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-12

Company Name Vishwakarma Builders
Project Name & Site Address Vishwakarma builders,Pratibhanagar,Kolhapur.
Students Name (Surname_First Name_Middle Name) Ghorpade Amit Prakash
Exam No. 13526
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge The work alloted for today was to check slab steel.
Details of how you Planned & Executed the allotted work I planned and executted the alloted work by using slab drawing and also with help of site incharge.
Details of the Construction Procedure / Activity / Technology learned today I learned compaction procedure today.
Details of the Construction Materials learned today The compaction machine which is used for compaction.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None.
Details of the Construction / Engineering Drawings observed today I observed drawing of slab steel.
Details of the Bye Laws referred today None.
Details of any Managerial Skill learned today The managerial skill learned how save the material on site by standing at time of construction.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for T.W. Paneled Door: Main door plywood-Rs.3000 Formica-2 no.-Rs.1200 each=Rs.2400 Lining patti-Rs.7/ft.-20 ft=Rs.140 Mapping patti-Rs.10/ft-30 ft.=Rs.300 Fevicol-Rs.300/kg Door frame-Rs.2000 Labour-Rs.2000 Lump sump-Rs.200 Locks,handle,stopper=Rs.1300 Total=Rs.12000/- Contractor profit-15%=Rs.1700 Total cost-Rs.13700/-
Result of RATE ANALYSIS ( Rs per Unit ) 13700/-
Todays BUZZ Word Site training experince I get very good experince at the time of training.I study various part of thery actually on site.Also i study extra activities other than thery which are help to me on site. I see various construction machines and thair use at the time of construction.I learned actual procedure of construction of whole building from foundation to slab. I observed how building construction work is done step by step and also observed that which factors are considered at the time of construction.I observed that step footing is most commonly used today. At the time of footing columns are constructed and concreting is done above ground level.After foundation water tank and lift room is constructed.I observed that before placing the ground beam,PCC has done. Campaction procedure also i learned. Most importent part of construction,I study leveling by using level tube.And also how leveling marks are done with respect to road level. Another,I see how site incharge performed his role on site.He handle any work easily.Also he taking care of waste from construction material.Workers are handled very neaty by site incharge.He planned all daily work at morning.Aiso he give respect to director.Site incharge taking care of workers. At the time of slab casting various type of steel i observed.Also i see how extra steel adjusted in the beam and how it placing.I study formwork of slab and cover given to the slab.I observed painting,plastering,finishing. I observed that various bye laws are reffered by builders at the time of construction corresponding to building. He try to provide maximum facilities to customer.He make his building attractive for customer.He try to give maximum facilities within one project. For environmental caring various plants will be planted by builder.Also they are try to use material for constructin which is heathy for environment. So overall I get good experince of my training.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nitin Nitin Gawade sir, mob:9049505925
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-12

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Shinde Shraddha Tukaram
Exam No. 10901
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:30pm
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"Water Tank\" that was being constructed.
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Water Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts.
Details of the Construction Procedure / Activity / Technology learned today Procedure for water tank reinforcement 1. reinforcement of bottom slab along with beams should be placed & bound properly 2. vertical bars of pardi are normally erected first 3. provide chamfered bars at corners as per design 4. after casting of bottom slab horizontal reinforcement of vertical pardi should be bound with care. 5. formwork of top slab should be bound as per the design. 6. provide manhole for top slab along with vent pipe hole.
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. \"Storm Drains\" were Constructed at every border of the compound wall & was harvested. 2. \"Solar Panels\" for water heating purpose. 3. \"Crushed Sand\" was used as the composition in Construction of Septic tank.
Details of the Construction / Engineering Drawings observed today 1. water tank layout 2. building layout 3. reinforcement details
Details of the Bye Laws referred today None
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/- ------------------------------------------------------------------- # \"Rate analysis for RCC Column\" # 1. Volume Of Beam = 10 cu.m 2. Concrete Mix Proportion = 1:1.5:3 3. Volume of Dry Concrete Mix = 15.2 cu.m A. Materials: 1. Quantity Of cement = 2.763 cu.m 2. No Of bags Of cement = 81.28 3. Sand = 4.144 cu.m 4. C.A. = 8.289 cu.m 5. Steel = 1570 kg 6. Binding wire = 15.7 kg B. Cost of Material: 1. Cement = 81.28 x 230 = 18694.4/- 2. Sand = 4.144 x 850 = 3522.4/- 3. Aggregate = 8.289 x 530 = 4393.17/- 4. Steel = 1570 x 34 = 53380/- 5. Binding Wire = 15.7 x 55 = 863.5/- 6. Total = 80853.47/- C. Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 3 x 170 = 510/- 3. Mazdoor = 10 x 110 = 1100/- 4. Centering & Shuttering = 5% x 80853.57 = 4042.68/- 5. Carpenter = 10 x 250 = 2500/- Nails = 500/- 6. Blacksmith = 15 x 200 = 3000/- 7. Total Cost = 8902.68/- D. TOTAL COST = B+C = 89756.15/- E. Add 1.5% Water charges = 1346.34 F. Add 10% Contractors Profit = 8975.6 G. GRAND TOTAL =89907.6 H. RATE FOR 1 CUM = 8990.76/-
Result of RATE ANALYSIS ( Rs per Unit ) For door Rs.2109.88/- , For Column Rs 8990.76/
Todays BUZZ Word 1.find out the quantity of excavation 2.the design ,placing & preliminary Procedure of p.c.c. 3.levelling done by bubble tube. 4.The concepts related with Plumbing work 5.The circulation of pipes their arrangements as per requirements & as per function 6.level marking done with the auto level 7.Prepare the Daily Report. 8.Brick Bat Coba & Waterproofing. 9.Plumbing done on the site. 10.Water proofing 11.Mananging the labours. 12.Distributing the work given between the labours. 13.To be punctual. 14.To complete the work done given onto the site. 15. Internal & external plastering works. 16. Painting works. 17. Electrification works. 18. PLumbing and sanitations 19. Estimating and costing of various materials. 20. Line-out of building works. 21.Safty precautions on the site.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10893-12

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Kamble Ankit V.
Exam No. 10893
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:30pm
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"Water Tank\" that was being constructed.
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Water Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts.
Details of the Construction Procedure / Activity / Technology learned today Procedure for water tank reinforcement 1. reinforcement of bottom slab along with beams should be placed & bound properly 2. vertical bars of pardi are normally erected first 3. provide chamfered bars at corners as per design 4. after casting of bottom slab horizontal reinforcement of vertical pardi should be bound with care. 5. formwork of top slab should be bound as per the design. 6. provide manhole for top slab along with vent pipe hole.
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. \"Storm Drains\" were Constructed at every border of the compound wall & was harvested. 2. \"Solar Panels\" for water heating purpose. 3. \"Crushed Sand\" was used as the composition in Construction of Septic tank.
Details of the Construction / Engineering Drawings observed today 1. water tank layout 2. building layout 3. reinforcement details
Details of the Bye Laws referred today None
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/- ------------------------------------------------------------------- # \"Rate analysis for RCC Column\" # 1. Volume Of Beam = 10 cu.m 2. Concrete Mix Proportion = 1:1.5:3 3. Volume of Dry Concrete Mix = 15.2 cu.m A. Materials: 1. Quantity Of cement = 2.763 cu.m 2. No Of bags Of cement = 81.28 3. Sand = 4.144 cu.m 4. C.A. = 8.289 cu.m 5. Steel = 1570 kg 6. Binding wire = 15.7 kg B. Cost of Material: 1. Cement = 81.28 x 230 = 18694.4/- 2. Sand = 4.144 x 850 = 3522.4/- 3. Aggregate = 8.289 x 530 = 4393.17/- 4. Steel = 1570 x 34 = 53380/- 5. Binding Wire = 15.7 x 55 = 863.5/- 6. Total = 80853.47/- C. Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 3 x 170 = 510/- 3. Mazdoor = 10 x 110 = 1100/- 4. Centering & Shuttering = 5% x 80853.57 = 4042.68/- 5. Carpenter = 10 x 250 = 2500/- Nails = 500/- 6. Blacksmith = 15 x 200 = 3000/- 7. Total Cost = 8902.68/- D. TOTAL COST = B+C = 89756.15/- E. Add 1.5% Water charges = 1346.34 F. Add 10% Contractors Profit = 8975.6 G. GRAND TOTAL =89907.6 H. RATE FOR 1 CUM = 8990.76/-
Result of RATE ANALYSIS ( Rs per Unit ) For door Rs.2109.88/- , For Column Rs 8990.76/
Todays BUZZ Word 1.find out the quantity of excavation 2.the design ,placing & preliminary Procedure of p.c.c. 3.levelling done by bubble tube. 4.The concepts related with Plumbing work 5.The circulation of pipes their arrangements as per requirements & as per function 6.level marking done with the auto level 7.Prepare the Daily Report. 8.Brick Bat Coba & Waterproofing. 9.Plumbing done on the site. 10.Water proofing 11.Mananging the labours. 12.Distributing the work given between the labours. 13.To be punctual. 14.To complete the work done given onto the site. 15. Internal & external plastering works. 16. Painting works. 17. Electrification works. 18. PLumbing and sanitations 19. Estimating and costing of various materials. 20. Line-out of building works. 21.Safty precautions on the site.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: pinkrosee4u@yhaoo.com
Subject: 10878-12

Company Name Star Tech Infra
Project Name & Site Address star aashiyana near rajendra nagar ,kolhapur
Students Name (Surname_First Name_Middle Name) narnaware shikha haridas
Exam No. 10878
Working Day No. 12
Date (DD/MM/YYYY) 21/12/10
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge steel framing for footing,road compaction with the help of \"DHUMUS\". cutting of hardend plastred cumpound wall for framing work .
Details of how you Planned & Executed the allotted work we observed the steel framing work of column for footing work,it has done according to stuctural desing,framing work is done under a good supervision the rings has been tied properly ,and no. of rings n sizes of the rings are taken as it has mentioned according to the drawing. They use the tor steel for footing work.advantages of tor steel are it gives the higher bond,less crAck width due to high bond. road compaction is done with the vibrating type of compaction machine, called \"DHUMUS\". FOR THIS TYPE OF COMPACTION u ned a skilled labour.compaction is done along the margin of the road.
Details of the Construction Procedure / Activity / Technology learned today we observed the formwork for staircase,formwork for beam. we observed that we have to check the shuttering work before concerting n reinforcement. compaction of the road with vibratory compacter (duhmus). De-shuttering of the form work n precutions to be taken while de-shttring. while de-shuttering of the form work for the cloums or beam ensure that edges are protected. while de-shuttering of internal beam sides,ensure thatsupports of the slab and beam bottom should not disturbed. minimum period for the de-shuttering of column is 24hrs. minimum period for the de-shuttering sides of beam is 24hrs.
Details of the Construction Materials learned today The constuction material learnd today steel n timber. As steel is the most important component of constuction material. steel is used to make the stucture strong and to distribute the load. there are ifferent types of steel n steel bars r preesent in the market. and they are used as per the requirenment. types of the reinforcing steel bars such as plain steel ,tor seel. It is wiedly used in the in building construction in beams ,columns,slabs,for footing work etc. Disadvantages of steel framed structures is corrosion.they shouled be oil painted, an proper maintenance should be taken to protect their surfaces so that they can be used for under ground water construction. TIMBER:timber is used for temperory n permanent member in constuction work such as permanent suctural work for beams ,columns,roofing. frame work timber for framed structures and genral use in windows n doors. heavy constuction. Temperory structural work :rcc construction ,centering ,scaffolding etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Eco-friendly constuction. If proper care is not taken and environmental aspects are ignored the buildings and cities will turn to deserted sie.If they properly adopted ;green building and green cities are produced. use of eco-friendlyconstruction tecniques,natural energy sources with environmental care are essential for geern buildings/cities. each designer ,architect,engineer and builder should construct each building ;with good essential servicesy like waret supply ,sewage disposal,solid waste disposal,roads,electricity and all the concernd athorities should devlope each city to make it free from environmental pollution. following points to be implemented. 1)use of solar energy for lighting purposes 2)use of solar energy for heating purposes 3)eco-friendly house construction techniqes. 4)rain water harvesting 5)waste recycling 6)free plantation 7)use of natural material 8)se of natural ventilation and lighting. in short every attempt is to be madde to use natural resources and materials . these will increasa the comforts at low running cost . in other words gree building and green cities are created.
Details of the Construction / Engineering Drawings observed today electrical drawings electrical layout in the premises with location,levels of points an switches. position of distribution box/feeder pillars. road lights position. cable laying position below road. transformer details and locations. light points in the entire area. earthing position of each building. internal room wise electical piont details for flats.
Details of the Bye Laws referred today permission for development no develepment to be carried out without development permission and commencement certificate. NOW MUNCIPAL CORPORATION have made a law that wtihout rainwater harvesting and parking in your drawing they wont give you the permission for the devlopment.
Details of any Managerial Skill learned today 1)proper maintenence of records . 2)maintenence of the seprate files for each drawing. 3)attentiveness 4)how to tackel with the workers. 5)check out of the list of work done. 6)alterness
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS (for Flush Door) Door size=(3*7)ft for this use wood size (5\"*2.5\") for frame we use 1.5ft3 wood rate of 1 ft3 =2000 rs 1.5 *2000 = 3000 rs (82\"*32\") =60rs lipping patti =20ft* 5rs =100rs labour charge =350rs = over all charge of door aldrop(1no.)=250rs latches =150rs bijagari(3no.)=3*60=180rs handle (2no.)=2*50=100rs tower bolt (1no.)=30rs magnet (1no.)=30rs door eye (no.)=70rs hinges (24no.)=totalcost=25rs hanel screws(24no.)totla cost =20rs nails (1inch=100gm)=10rs fevicol (100gm)=40rs TOTAL COST OF DOOR OF SIZE(3*7)ft=4415rs 3*7 = 21 ft2=21/10.76m2=1.95m2 for 1m2= 4415rs/1.95m2= 2264rs/m2 RESULT FOR FLUSH DOOR =2264RS/M2
Result of RATE ANALYSIS ( Rs per Unit ) 2264rs/m2
Todays BUZZ Word First of all i would like to thank you my prof MR.Irfan patan sir for given us all such opprotunities,n working hard for us so that we students would be able to take the advantage of todays tecnology.my expireance starts wid this coz i observed that many of the students where not having the email id. after that my first day on the site was quite good.First we mate the incharge of that site we introduce our selfs to him.Then we mate the superviser of the site. I found that site incharge was quite cool,but the superviser was very srict. we explaned him all our 12 days shadule of traning.He start to explain us each n everything,n i found him very polite.first day we where little afraid, we went on visited all the places where the constuction work as going on, and started observing the work. First day we observed the basic things like what is the project,how much constuction has cumplitated,how much work is going on,n ho much work has be complite. accordingly then we strated our work for each day.daily we being on site sharpe at 9:00am then our site incharge tlod us the work n accoringly we observd the work. And daily at end of the day he helped us in buzz word n in rate analysis. he has been guied us n answere all our quires. daily after coming on site we visit all the site and carefully observed all the work and asked the quries related to that work.we saw the pcc work ,painting work, shuttering,de-shttering,formwork for staircase,steel framing for column,workers skills. i observed that what ever we learned in therotical is totaly different then what we observed at the site work.we observed how to minimize the the wastage,an saw all the inatrments and se of the instruments on the site.we saw the aquracy ,cement concentration,w/c ratio,size of aggregates and sand.wroing on thee site is tolaly diffrent than the therotical knowlege. things get manipulated little bit to compensate the error.we learned the handling of the workers ,supervision,attentiveness towards the workers. we LEARNED how the bilding is made atrractive by using the atrractive and high quality material and how they cannected to the brand so that publicity of the building is carried out. IN actual construction the FSI is 1.and if the fsi is not one to make it one we carry the TDR . AS MUNCIPAL CORPORATION made the rain water harvesing ,setback,parking made compulsory without it they dint santion the plan. OVER MY EXPERIENC OF 12 DAYS WAS VRY NICE I HAVE LEARED MANY THINGS WHICH I WAS TOTALY UNAWARE.I will never forget th ethings whic i have learned in these 12 days.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.satish
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-12

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Jape Vishwajeet Ramesh
Exam No. 10892
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"Water Tank\" that was being constructed.
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Water Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts.
Details of the Construction Procedure / Activity / Technology learned today Procedure for water tank reinforcement 1. reinforcement of bottom slab along with beams should be placed & bound properly 2. vertical bars of pardi are normally erected first 3. provide chamfered bars at corners as per design 4. after casting of bottom slab horizontal reinforcement of vertical pardi should be bound with care. 5. formwork of top slab should be bound as per the design. 6. provide manhole for top slab along with vent pipe hole.
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. \"Storm Drains\" were Constructed at every border of the compound wall & was harvested. 2. \"Solar Panels\" for water heating purpose. 3. \"Crushed Sand\" was used as the composition in Construction of Septic tank.
Details of the Construction / Engineering Drawings observed today 1. water tank layout 2. building layout 3. reinforcement details
Details of the Bye Laws referred today None
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/- ------------------------------------------------------------------- # \"Rate analysis for RCC Column\" # 1. Volume Of Beam = 10 cu.m 2. Concrete Mix Proportion = 1:1.5:3 3. Volume of Dry Concrete Mix = 15.2 cu.m A. Materials: 1. Quantity Of cement = 2.763 cu.m 2. No Of bags Of cement = 81.28 3. Sand = 4.144 cu.m 4. C.A. = 8.289 cu.m 5. Steel = 1570 kg 6. Binding wire = 15.7 kg B. Cost of Material: 1. Cement = 81.28 x 230 = 18694.4/- 2. Sand = 4.144 x 850 = 3522.4/- 3. Aggregate = 8.289 x 530 = 4393.17/- 4. Steel = 1570 x 34 = 53380/- 5. Binding Wire = 15.7 x 55 = 863.5/- 6. Total = 80853.47/- C. Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 3 x 170 = 510/- 3. Mazdoor = 10 x 110 = 1100/- 4. Centering & Shuttering = 5% x 80853.57 = 4042.68/- 5. Carpenter = 10 x 250 = 2500/- Nails = 500/- 6. Blacksmith = 15 x 200 = 3000/- 7. Total Cost = 8902.68/- D. TOTAL COST = B+C = 89756.15/- E. Add 1.5% Water charges = 1346.34 F. Add 10% Contractors Profit = 8975.6 G. GRAND TOTAL =89907.6 H. RATE FOR 1 CUM = 8990.76/-
Result of RATE ANALYSIS ( Rs per Unit ) For door Rs.2109.88/- , For Column Rs 8990.76/
Todays BUZZ Word 1.find out the quantity of excavation 2.the design ,placing & preliminary Procedure of p.c.c. 3.levelling done by bubble tube. 4.The concepts related with Plumbing work 5.The circulation of pipes their arrangements as per requirements & as per function 6.level marking done with the auto level 7.Prepare the Daily Report. 8.Brick Bat Coba & Waterproofing. 9.Plumbing done on the site. 10.Water proofing 11.Mananging the labours. 12.Distributing the work given between the labours. 13.To be punctual. 14.To complete the work done given onto the site. 15. Internal & external plastering works. 16. Painting works. 17. Electrification works. 18. PLumbing and sanitations 19. Estimating and costing of various materials. 20. Line-out of building works. 21.Safty precautions on the site.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-12

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Nagvekar Yogesh Deepak
Exam No. 10894
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"Water Tank\" that was being constructed.
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Water Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts.
Details of the Construction Procedure / Activity / Technology learned today Procedure for water tank reinforcement 1. reinforcement of bottom slab along with beams should be placed & bound properly 2. vertical bars of pardi are normally erected first 3. provide chamfered bars at corners as per design 4. after casting of bottom slab horizontal reinforcement of vertical pardi should be bound with care. 5. formwork of top slab should be bound as per the design. 6. provide manhole for top slab along with vent pipe hole.
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. \"Storm Drains\" were Constructed at every border of the compound wall & was harvested. 2. \"Solar Panels\" for water heating purpose. 3. \"Crushed Sand\" was used as the composition in Construction of Septic tank.
Details of the Construction / Engineering Drawings observed today 1. water tank layout 2. building layout 3. reinforcement details
Details of the Bye Laws referred today None
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/- ------------------------------------------------------------------- # \"Rate analysis for RCC Column\" # 1. Volume Of Beam = 10 cu.m 2. Concrete Mix Proportion = 1:1.5:3 3. Volume of Dry Concrete Mix = 15.2 cu.m A. Materials: 1. Quantity Of cement = 2.763 cu.m 2. No Of bags Of cement = 81.28 3. Sand = 4.144 cu.m 4. C.A. = 8.289 cu.m 5. Steel = 1570 kg 6. Binding wire = 15.7 kg B. Cost of Material: 1. Cement = 81.28 x 230 = 18694.4/- 2. Sand = 4.144 x 850 = 3522.4/- 3. Aggregate = 8.289 x 530 = 4393.17/- 4. Steel = 1570 x 34 = 53380/- 5. Binding Wire = 15.7 x 55 = 863.5/- 6. Total = 80853.47/- C. Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 3 x 170 = 510/- 3. Mazdoor = 10 x 110 = 1100/- 4. Centering & Shuttering = 5% x 80853.57 = 4042.68/- 5. Carpenter = 10 x 250 = 2500/- Nails = 500/- 6. Blacksmith = 15 x 200 = 3000/- 7. Total Cost = 8902.68/- D. TOTAL COST = B+C = 89756.15/- E. Add 1.5% Water charges = 1346.34 F. Add 10% Contractors Profit = 8975.6 G. GRAND TOTAL =89907.6 H. RATE FOR 1 CUM = 8990.76/-
Result of RATE ANALYSIS ( Rs per Unit ) For door Rs.2109.88/- , For Column Rs 8990.76/-
Todays BUZZ Word 1.find out the quantity of excavation 2.the design ,placing & preliminary Procedure of p.c.c. 3.levelling done by bubble tube. 4.The concepts related with Plumbing work 5.The circulation of pipes their arrangements as per requirements & as per function 6.level marking done with the auto level 7.Prepare the Daily Report. 8.Brick Bat Coba & Waterproofing. 9.Plumbing done on the site. 10.Water proofing 11.Mananging the labours. 12.Distributing the work given between the labours. 13.To be punctual. 14.To complete the work done given onto the site. 15. Internal & external plastering works. 16. Painting works. 17. Electrification works. 18. PLumbing and sanitations 19. Estimating and costing of various materials. 20. Line-out of building works. 21.Safty precautions on the site.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: cool.sushant007@gmail.com
Subject: 10880-12

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) PATIL SUSHANT DIGMBER
Exam No. 10880
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE LINE-OUT WORK OF A COLUMN.
Details of how you Planned & Executed the allotted work WE FIRST THOROUGHLY STUDIED THE CENTER LINES PLANS AND GO TO THE SPOT. NOTING DOWN THE THINGS RELATED TO WORK.
Details of the Construction Procedure / Activity / Technology learned today FIRST THE TWO EDGES OF BUILDINGS ARE TAKEN SUCH THAT THEY ARE PERPENDICULAR TO EACH OTHER AND LINE STRING IS ATTACHED TO THIS. THEY FROM THE DRAWING ACCORDING TO THE DISTANCES GIVEN FROM CENTER TO FACE OF THE COLUMN AND BY CONSIDERING THE COVER MARK THE ONE CORNER . THEN AFTER THAT PLACE THE STARTER WITH MATCHING THE POSITION THEN STARTER IS CASTED. THIS SHOULD DONE TO MARK THE EXACT POSITION OF COLUMN IN VERTICAL DIRECTION.
Details of the Construction Materials learned today NO NEW MATERIALS ARE LEARNED TODAY.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today NO NEW MATERIALS ARE LEARNED TODAY.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3000 FORMICA-2 NO. = RS 1200 EACH = RS 2400 LINING PATTI- RS 7/FT.-20 FT = RS 140 MAPPING PATTI- RS 10/FT.- 30 FT. =RS 300 FEVICOL- RS 300/KG DOOR FRAME- RS 2000 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 12000 CONTRACTOR PROFIT= 15% = RS 1700 TOTAL COST= RS 13700
Result of RATE ANALYSIS ( Rs per Unit ) 13700 RS
Todays BUZZ Word IF WE DONE OUR WORK WITH GOOD SUPERVISION AND ACCURACY THEN WE CAN SURE ABOUT THAT WE WILL NOT REQUIRED ANY TYPE OF ADMIXTURE AND CHEMICALS TO IMPROVE OUR QUALITY OF CONCRETE. BEFORE DOING ANY MAJOR WORK SUCH AS CASTING OF 10-12 COLUMNS AT A TIME THEN WE HAVE TO PREPARE FIRST TEST CUBE SPECIMENS WITH THE DECIDED PROPORTION THEN AFTER TESTING REPORTS THE PERMISSION IS GIVEN TO THE FURTHER WORK. IF YOU WANT USE ANY TYPE OF CONSTRUCTION MATERIAL ON SITE THEN IT SHOULD BE TESTED FIRST FOR ITS PERFORMANCE THEN ACCORDING TO THAT IT WILL USED . OTHERWISE THERE IS POSSIBILITY THAT IT WILLL CAUSE WASTGE OF MONEY UNECCESARILY . NOW A DAYS ACCORDING TO THE ENVIROMENTAL CONDITITONS IT IS MUST THAT WE HAVE TO APPLY SOME KIND GREEN TECNOLOGY TO THE BUILDINGS. THIS CAN BE DONE BY USING FLY ASH BRICKS , FLY ASH MIXED CEMENT IN THE CONSTRUCTION OF BUILDING. BY ADOPTING THE RAIN WATER HARVESTING TECNIQUES OR GROUND WATER RECHARGING , BY PROVIDING SEWAGE TREATMENT PLANTS AND SOLAR PANELS ARE USED TO HEAT THE WATER ALSO UTILISIG THE ELECTRICITY GENERATED BY THIS FOR PARKING OR IN COMMAN AREAS OF THE BUILDINGS. OVERALL YOU WILL REQUIRED GOOD CO-ORDINATION WITH THE PEOPLES ON THE SITE TO DO THE WORK IN GOOD MANNER. THE ENGINEER SHOULD HAVE GOOD CO-ORDINATION WITH THE SITE SUPERVISOR ON THE SITE TO GET THE DETAIL INFORMATION ABOUT THE WORK THAT WAS ALLOTED TO THEM AND WHAT IS THE PROGRESS OF WORK. THERE IS TENDENCY OF WORKERS ON THE SITE TO WORK ACCORDING TO THEIR EXPERIENCE AND NOT WITH THE INSTRUCTION GIVEN TO THEM .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: vishalsapakal124@gmail.com
Subject: 10882-12

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) SAPKAL VISHAL M.
Exam No. 10882
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe the making of beams on the second floor and take the required checks.
Details of how you Planned & Executed the allotted work We saw that the btop bars and bottom bars were as per the diameter and length given in the design detailing. After that we checked the size of stirrups and their spacing. Then after the lovuering of beam in the formwork we checked the side and bottom covers.
Details of the Construction Procedure / Activity / Technology learned today We saw that the btop bars and bottom bars were as per the diameter and length given in the design detailing. After that we checked the size of stirrups and their spacing. Then after the lovuering of beam in the formwork we checked the side and bottom covers.
Details of the Construction Materials learned today “Preparation of beam” Firstly the bottom bars were placed above the beam formwork and tied at a height of about 1ft in the supporting columns. Then the top bas were tied and then the stirrups as per the design given were inserted and tied at the four corners of stirrups were tied to the bars at the given spacing and then the beam was louvered in the form work
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today No such method is used on the site.
Details of the Bye Laws referred today Drawing of Beam sections with their schedule and detailed second floor plan
Details of any Managerial Skill learned today Size of bath and w/c - Dimensions provided on the site for bath:-2.0*1.2=2.4sqm Dimensions provided on the site for w/c:-1.2*1.0=1.2sqm As per bye law the minimum dimensions to be provided is 1.8m*1.0m and 0.9m*0.9m
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation external non-teak door“ Dimension of the door frame=0.92*2.07*0.10 Dimension of the door panel required=0.82*2.02*0.035 Quantity of hinges required=3nos Quantity of latches required=2nos Quantity of handles required=2nos Quantity of stopper required=1nos carpenter required =2nos “Rate Analysis for external non-teak door” (Considering local rates of material) 1. Cost of door frame=1*900=900/-………..(900/- per frame) 2. Cost of door panel= 1*1500=1500/-…………(1500/- per panel) 3. Cost of hinges=3*35=105/-………………..(35/- per hinge) 4. Cost of latches=2*90=180/-………(90/- per latch) 5. Cost of stopper=1*40=40/-…………(40/- per stopper) 6. Cost of handles=2*50=100/-…….(50per handle) 7. Labour charges=300/-…………(150/- per carpenter for half day) 5. Total cost=2975/- 6.10% profit of total cost for the contractor=297.5/- 7. Total cost=3272.5/- 10. Rate per door=3272.5/-
Result of RATE ANALYSIS ( Rs per Unit ) 3273/-
Todays BUZZ Word “Site training experience” On behalf of our group I am very thankful to our Civil Engg Dept and prof.I.I.Pathan for arranging such an up-to-date and successful training program for us and giving a glamorous opportunity for interacting with the real estate industry and impressive personalities. We are thankful to prof.I.I.P for giving us a site which is very perfect in maintain the accuracy and quality in construction. I have learned that how the quality and accuracy is maintained and controlled during the actual construction and casting of concrete. This program has given me the brief idea how the theoretical concepts are actually applied on the site. As site given to me was in its initial stage of construction it has helped me to learn the detailed construction procedure of basic building components like beams, columns, staircase, slab, sunk slabs, majorly the fixing of shuttering and formwork and with this maintaining the accuracy. Basic points of accuracy control which I have learned are maintaining the plumb line and level of each component from the ground floor till the stage where the further construction is done. I have learned how various working drawings are to be read and w.r.t the drawings how the actual work is to be carried out. It has helped me that how the various problems are to be tackled during the actual construction and manage the workers as per the nature of work to be executed, and also how to keep the workers busy in work during the shortage of materials on the site. At last this program has taught me how the work is to be executed in group and how to interact with each other with different ideas and concepts and co ordinate each other and help. It has given me the idea how to talk with workers at the site and capacity of how much I can stand on the site from the whole day. Once again glad to thank u sir and our civil department………
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: patilpratibha7070@yahoo.in
Subject: 10896-12

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) PATIL PRATIBHA DILIP
Exam No. 10896
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe the making of beams on the second floor and take the required checks.
Details of how you Planned & Executed the allotted work We saw that the btop bars and bottom bars were as per the diameter and length given in the design detailing. After that we checked the size of stirrups and their spacing. Then after the lovuering of beam in the formwork we checked the side and bottom covers.
Details of the Construction Procedure / Activity / Technology learned today We saw that the btop bars and bottom bars were as per the diameter and length given in the design detailing. After that we checked the size of stirrups and their spacing. Then after the lovuering of beam in the formwork we checked the side and bottom covers.
Details of the Construction Materials learned today “Preparation of beam” Firstly the bottom bars were placed above the beam formwork and tied at a height of about 1ft in the supporting columns. Then the top bas were tied and then the stirrups as per the design given were inserted and tied at the four corners of stirrups were tied to the bars at the given spacing and then the beam was louvered in the form work
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Drawing of Beam sections with their schedule and detailed second floor plan
Details of the Bye Laws referred today Size of bath and w/c - Dimensions provided on the site for bath:-2.0*1.2=2.4sqm Dimensions provided on the site for w/c:-1.2*1.0=1.2sqm As per bye law the minimum dimensions to be provided is 1.8m*1.0m and 0.9m*0.9m
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation external non-teak door“ Dimension of the door frame=0.92*2.07*0.10 Dimension of the door panel required=0.82*2.02*0.035 Quantity of hinges required=3nos Quantity of latches required=2nos Quantity of handles required=2nos Quantity of stopper required=1nos carpenter required =2nos “Rate Analysis for external non-teak door” (Considering local rates of material) 1. Cost of door frame=1*900=900/-………..(900/- per frame) 2. Cost of door panel= 1*1500=1500/-…………(1500/- per panel) 3. Cost of hinges=3*35=105/-………………..(35/- per hinge) 4. Cost of latches=2*90=180/-………(90/- per latch) 5. Cost of stopper=1*40=40/-…………(40/- per stopper) 6. Cost of handles=2*50=100/-…….(50per handle) 7. Labour charges=300/-…………(150/- per carpenter for half day) 5. Total cost=2975/- 6.10% profit of total cost for the contractor=297.5/- 7. Total cost=3272.5/- 10. Rate per door=3272.5/-
Result of RATE ANALYSIS ( Rs per Unit ) 3273/-
Todays BUZZ Word “Site training experience” On behalf of our group I am very thankful to our Civil Engg Dept and prof.I.I.Pathan for arranging such an up-to-date and successful training program for us and giving a glamorous opportunity for interacting with the real estate industry and impressive personalities. We are thankful to prof.I.I.P for giving us a site which is very perfect in maintain the accuracy and quality in construction. I have learned that how the quality and accuracy is maintained and controlled during the actual construction and casting of concrete. This program has given me the brief idea how the theoretical concepts are actually applied on the site. As site given to me was in its initial stage of construction it has helped me to learn the detailed construction procedure of basic building components like beams, columns, staircase, slab, sunk slabs, majorly the fixing of shuttering and formwork and with this maintaining the accuracy. Basic points of accuracy control which I have learned are maintaining the plumb line and level of each component from the ground floor till the stage where the further construction is done. I have learned how various working drawings are to be read and w.r.t the drawings how the actual work is to be carried out. It has helped me that how the various problems are to be tackled during the actual construction and manage the workers as per the nature of work to be executed, and also how to keep the workers busy in work during the shortage of materials on the site. At last this program has taught me how the work is to be executed in group and how to interact with each other with different ideas and concepts and co ordinate each other and help. It has given me the idea how to talk with workers at the site and capacity of how much I can stand on the site from the whole day. Once again glad to thank u sir and our civil department………
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-12

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) BABAR MORESHWAR MAHIPATI
Exam No. 10873
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe the making of beams on the second floor and take the required checks.
Details of how you Planned & Executed the allotted work We saw that the btop bars and bottom bars were as per the diameter and length given in the design detailing. After that we checked the size of stirrups and their spacing. Then after the lovuering of beam in the formwork we checked the side and bottom covers.
Details of the Construction Procedure / Activity / Technology learned today “Preparation of beam” Firstly the bottom bars were placed above the beam formwork and tied at a height of about 1ft in the supporting columns. Then the top bas were tied and then the stirrups as per the design given were inserted and tied at the four corners of stirrups were tied to the bars at the given spacing and then the beam was louvered in the form work.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method is used on the site.
Details of the Construction / Engineering Drawings observed today Drawing of Beam sections with their schedule and detailed second floor plan
Details of the Bye Laws referred today Size of bath and w/c - Dimensions provided on the site for bath:-2.0*1.2=2.4sqm Dimensions provided on the site for w/c:-1.2*1.0=1.2sqm As per bye law the minimum dimensions to be provided is 1.8m*1.0m and 0.9m*0.9m
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation external non-teak door“ Dimension of the door frame=0.92*2.07*0.10 Dimension of the door panel required=0.82*2.02*0.035 Quantity of hinges required=3nos Quantity of latches required=2nos Quantity of handles required=2nos Quantity of stopper required=1nos carpenter required =2nos “Rate Analysis for external non-teak door” (Considering local rates of material) 1. Cost of door frame=1*900=900/-………..(900/- per frame) 2. Cost of door panel= 1*1500=1500/-…………(1500/- per panel) 3. Cost of hinges=3*35=105/-………………..(35/- per hinge) 4. Cost of latches=2*90=180/-………(90/- per latch) 5. Cost of stopper=1*40=40/-…………(40/- per stopper) 6. Cost of handles=2*50=100/-…….(50per handle) 7. Labour charges=300/-…………(150/- per carpenter for half day) 5. Total cost=2975/- 6.10% profit of total cost for the contractor=297.5/- 7. Total cost=3272.5/- 10. Rate per door=3272.5/-
Result of RATE ANALYSIS ( Rs per Unit ) 3273/-
Todays BUZZ Word “Site training experience” On behalf of our group I am very thankful to our Civil Engg Dept and prof.I.I.Pathan for arranging such an up-to-date and successful training program for us and giving a glamorous opportunity for interacting with the real estate industry and impressive personalities. We are thankful to prof.I.I.P for giving us a site which is very perfect in maintain the accuracy and quality in construction. I have learned that how the quality and accuracy is maintained and controlled during the actual construction and casting of concrete. This program has given me the brief idea how the theoretical concepts are actually applied on the site. As site given to me was in its initial stage of construction it has helped me to learn the detailed construction procedure of basic building components like beams, columns, staircase, slab, sunk slabs, majorly the fixing of shuttering and formwork and with this maintaining the accuracy. Basic points of accuracy control which I have learned are maintaining the plumb line and level of each component from the ground floor till the stage where the further construction is done. I have learned how various working drawings are to be read and w.r.t the drawings how the actual work is to be carried out. It has helped me that how the various problems are to be tackled during the actual construction and manage the workers as per the nature of work to be executed, and also how to keep the workers busy in work during the shortage of materials on the site. At last this program has taught me how the work is to be executed in group and how to interact with each other with different ideas and concepts and co ordinate each other and help. It has given me the idea how to talk with workers at the site and capacity of how much I can stand on the site from the whole day. Once again glad to thank u sir and our civil department………
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-12

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) YADAV HRISHEEKESH DEEPAK
Exam No. 10885
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe the making of beams on the second floor and take the required checks.
Details of how you Planned & Executed the allotted work .We saw that the btop bars and bottom bars were as per the diameter and length given in the design detailing. After that we checked the size of stirrups and their spacing. Then after the lovuering of beam in the formwork we checked the side and bottom covers.
Details of the Construction Procedure / Activity / Technology learned today “Preparation of beam” Firstly the bottom bars were placed above the beam formwork and tied at a height of about 1ft in the supporting columns. Then the top bas were tied and then the stirrups as per the design given were inserted and tied at the four corners of stirrups were tied to the bars at the given spacing and then the beam was louvered in the formwork.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method is used on the site.
Details of the Construction / Engineering Drawings observed today Drawing of Beam sections with their schedule and detailed second floor plan
Details of the Bye Laws referred today Size of bath and w/c - Dimensions provided on the site for bath:-2.0*1.2=2.4sqm Dimensions provided on the site for w/c:-1.2*1.0=1.2sqm As per bye law the minimum dimensions to be provided is 1.8m*1.0m and 0.9m*0.9m
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation external non-teak door“ Dimension of the door frame=0.92*2.07*0.10 Dimension of the door panel required=0.82*2.02*0.035 Quantity of hinges required=3nos Quantity of latches required=2nos Quantity of handles required=2nos Quantity of stopper required=1nos carpenter required =2nos “Rate Analysis for external non-teak door” (Considering local rates of material) 1. Cost of door frame=1*900=900/-………..(900/- per frame) 2. Cost of door panel= 1*1500=1500/-…………(1500/- per panel) 3. Cost of hinges=3*35=105/-………………..(35/- per hinge) 4. Cost of latches=2*90=180/-………(90/- per latch) 5. Cost of stopper=1*40=40/-…………(40/- per stopper) 6. Cost of handles=2*50=100/-…….(50per handle) 7. Labour charges=300/-…………(150/- per carpenter for half day) 5. Total cost=2975/- 6.10% profit of total cost for the contractor=297.5/- 7. Total cost=3272.5/- 10. Rate per door=3272.5/-
Result of RATE ANALYSIS ( Rs per Unit ) 3273/-
Todays BUZZ Word “Site training experience” On behalf of our group I am very thankful to our Civil Engg Dept and prof.I.I.Pathan for arranging such an up-to-date and successful training program for us and giving a glamorous opportunity for interacting with the real estate industry and impressive personalities. We are thankful to prof.I.I.P for giving us a site which is very perfect in maintain the accuracy and quality in construction. I have learned that how the quality and accuracy is maintained and controlled during the actual construction and casting of concrete. This program has given me the brief idea how the theoretical concepts are actually applied on the site. As site given to me was in its initial stage of construction it has helped me to learn the detailed construction procedure of basic building components like beams, columns, staircase, slab, sunk slabs, majorly the fixing of shuttering and formwork and with this maintaining the accuracy. Basic points of accuracy control which I have learned are maintaining the plumb line and level of each component from the ground floor till the stage where the further construction is done. I have learned how various working drawings are to be read and w.r.t the drawings how the actual work is to be carried out. It has helped me that how the various problems are to be tackled during the actual construction and manage the workers as per the nature of work to be executed, and also how to keep the workers busy in work during the shortage of materials on the site. At last this program has taught me how the work is to be executed in group and how to interact with each other with different ideas and concepts and co ordinate each other and help. It has given me the idea how to talk with workers at the site and capacity of how much I can stand on the site from the whole day. Once again glad to thank u sir and our civil department………
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-12

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) MANGAOKAR MANOJ DATTATRAY
Exam No. 13536
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE STEEL REINFORCEMENT WORK DONE FOR THE SLAB.
Details of how you Planned & Executed the allotted work WE FIRST COLLECTED THE STEEL DRAWINGS FROM THE SITE SUPERVISOR THEN WE STUDY THOSE DRAWINGS AND COLLECTED THE INFORMATION ABOUT THE CONTENT OF DRAWINGS.
Details of the Construction Procedure / Activity / Technology learned today WE LEARN ABOUT THE SLAB REINFORCEMENT WORK. THE BARS ARE BEND AT L/4 DISTANCE SO THAT THE SAGGING MOMENT OF SLAB IS RESTRICTED BY INCREASING THE C/S OF SLAB. IN BEAMS EXTRA TOP AND CURTLEMENT IS PROVIDED WHERE THE SHEAR FORCE IS MORE.
Details of the Construction Materials learned today NO NEW MATERIALS ARE LEARNED TODAY.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today STEEL DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3500 FORMICA-2 NO. = RS 1200 EACH = RS 2000 LINING PATTI- RS 6/FT.-20 FT = RS 120 MAPPING PATTI- RS 12/FT.- 30 FT. =RS 360 FEVICOL- RS 300/KG DOOR FRAME- RS 1800 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 9580 CONTRACTOR PROFIT= 15% = RS 1437 TOTAL COST= RS 11017
Result of RATE ANALYSIS ( Rs per Unit ) 11017 RS
Todays BUZZ Word * OWN SITE TRAING EXPERIENCE * WHEN 1ST TIME I WAS GONE ON THE SITE, I WAS VERY EXCITED TO KNOW THAT ON THE SITES ACTUALLY WHAT THE WORK IS GOING ON . THAT FEELING OF WORKING AS AN ENGINEER ON SITE IS VERY DIFFERENT. WHEN WE WENT ON THE SITE WE MET THE OWNER OF THE COMPANY “ MR. RAM PUROHIT “ SIR . HE IS VERY INTRESTING PERSON .HE TOLD US THAT THIS IS A GOLDEN OPPORTUNITY TO US TO KNOW ABOUT THE ACTUAL WORK ON THE SITE AND GETTING EXPERIENCE OF SITE. HE WERE ALLOTTED US THE WORK TO SEE THE WORK FOR SLAB. WHEN WE WENT ON THE SITE THERE WERE THE BAR BINDING FOR FIRST FLOOR SLAB WAS GOING ON. WE MET A WORKER , NAME IS “ SUJITKUMAR GUPTA” HE GUIDED US ABOUT THE SIZES OF BARS , HOW TO USE THE CHART GIVEN , HOW TO KNOW ABOUT THE POSITION OF BEAMS. HE TOLD US ABOUT THE ONE WAY SLAB , TWO WAY SLAB , MAIN BAR, DISTRIBUTION BAR , EXTRA TOP I. E. END SUPPORT AND CENTER SUPPORT, CURTAILMENT ETC. AFTER WARDS WE HAVE OBSERVED THE CONSTRUCTION OF WALL, HOW TO USE THE PLUMB BOB , WHAT IS THE PROPORTION OF CEMENT AND SAND IN MORTAR, WHAT IS THE RATE OF ONE BRASS WORK . WHAT IS THE PAYMENT OF THE WORKERS FOR ONE DAY. THEN WE MET TO THE R.C.C. CONTRACTOR. HE TOLD US ABOUT THE RATE OF R.C.C. CONSTRUCTION I.E. SLAB,BEAM,COLUMN. OUR SITE ENGINEER MR. UGAVE SIR HAS GUIDED US ABOUT THE LINE OUT OF THE BUILDING . OUR SITE INCHARGE MR. CHOUGALE SIR HAS GUIDED ABOUT THE PLANNING OF THE BUILDING . WE HAVE ENJOYED THE TRAINING WORKSHOP WE GET LOT OF KNOWLEDGE ABOUT THE CONSTRUCTION ALONG WITH THE QUALITY OF TECHNICAL THINGS IT IS VERY IMPORTANT THAT HOW WILL YOU COMMUNICATE WITH THE CUSTOMERS . CIVIL ENGINEER SHOULD HAVE THIS KIND OF QUALITY WHICH WILL BE HELPFUL IN CUMMUNICATION WITH THE PEOPLE IN THE MARKETING WORLD.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-12

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE STEEL REINFORCEMENT WORK DONE FOR THE SLAB.
Details of how you Planned & Executed the allotted work WE FIRST COLLECTED THE STEEL DRAWINGS FROM THE SITE SUPERVISOR THEN WE STUDY THOSE DRAWINGS AND COLLECTED THE INFORMATION ABOUT THE CONTENT OF DRAWINGS.
Details of the Construction Procedure / Activity / Technology learned today WE LEARN ABOUT THE SLAB REINFORCEMENT WORK. THE BARS ARE BEND AT L/4 DISTANCE SO THAT THE SAGGING MOMENT OF SLAB IS RESTRICTED BY INCREASING THE C/S OF SLAB. IN BEAMS EXTRA TOP AND CURTLEMENT IS PROVIDED WHERE THE SHEAR FORCE IS MORE.
Details of the Construction Materials learned today NO NEW MATERIALS ARE LEARNED TODAY.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today NO NEW MATERIALS ARE LEARNED TODAY.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3500 FORMICA-2 NO. = RS 1200 EACH = RS 2000 LINING PATTI- RS 6/FT.-20 FT = RS 120 MAPPING PATTI- RS 12/FT.- 30 FT. =RS 360 FEVICOL- RS 300/KG DOOR FRAME- RS 1800 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 9580 CONTRACTOR PROFIT= 15% = RS 1437 TOTAL COST= RS 11017
Result of RATE ANALYSIS ( Rs per Unit ) 11017 RS
Todays BUZZ Word * OWN SITE TRAING EXPERIENCE * WHEN 1ST TIME I WAS GONE ON THE SITE, I WAS VERY EXCITED TO KNOW THAT ON THE SITES ACTUALLY WHAT THE WORK IS GOING ON . THAT FEELING OF WORKING AS AN ENGINEER ON SITE IS VERY DIFFERENT. WHEN WE WENT ON THE SITE WE MET THE OWNER OF THE COMPANY “ MR. RAM PUROHIT “ SIR . HE IS VERY INTRESTING PERSON .HE TOLD US THAT THIS IS A GOLDEN OPPORTUNITY TO US TO KNOW ABOUT THE ACTUAL WORK ON THE SITE AND GETTING EXPERIENCE OF SITE. HE WERE ALLOTTED US THE WORK TO SEE THE WORK FOR SLAB. WHEN WE WENT ON THE SITE THERE WERE THE BAR BINDING FOR FIRST FLOOR SLAB WAS GOING ON. WE MET A WORKER , NAME IS “ SUJITKUMAR GUPTA” HE GUIDED US ABOUT THE SIZES OF BARS , HOW TO USE THE CHART GIVEN , HOW TO KNOW ABOUT THE POSITION OF BEAMS. HE TOLD US ABOUT THE ONE WAY SLAB , TWO WAY SLAB , MAIN BAR, DISTRIBUTION BAR , EXTRA TOP I. E. END SUPPORT AND CENTER SUPPORT, CURTAILMENT ETC. AFTER WARDS WE HAVE OBSERVED THE CONSTRUCTION OF WALL, HOW TO USE THE PLUMB BOB , WHAT IS THE PROPORTION OF CEMENT AND SAND IN MORTAR, WHAT IS THE RATE OF ONE BRASS WORK . WHAT IS THE PAYMENT OF THE WORKERS FOR ONE DAY. THEN WE MET TO THE R.C.C. CONTRACTOR. HE TOLD US ABOUT THE RATE OF R.C.C. CONSTRUCTION I.E. SLAB,BEAM,COLUMN. OUR SITE ENGINEER MR. UGAVE SIR HAS GUIDED US ABOUT THE LINE OUT OF THE BUILDING . OUR SITE INCHARGE MR. CHOUGALE SIR HAS GUIDED ABOUT THE PLANNING OF THE BUILDING . WE HAVE ENJOYED THE TRAINING WORKSHOP WE GET LOT OF KNOWLEDGE ABOUT THE CONSTRUCTION ALONG WITH THE QUALITY OF TECHNICAL THINGS IT IS VERY IMPORTANT THAT HOW WILL YOU COMMUNICATE WITH THE CUSTOMERS . CIVIL ENGINEER SHOULD HAVE THIS KIND OF QUALITY WHICH WILL BE HELPFUL IN CUMMUNICATION WITH THE PEOPLE IN THE MARKETING WORLD.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: nitinpatil22.2010@rediffmail.com
Subject: 10879-12

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) PATIL NITIN DILIP
Exam No. 10879
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE LINE-OUT WORK OF A COLUMN.
Details of how you Planned & Executed the allotted work WE FIRST THOROUGHLY STUDIED THE CENTER LINES PLANS AND GO TO THE SPOT. NOTING DOWN THE THINGS RELATED TO WORK.
Details of the Construction Procedure / Activity / Technology learned today FIRST THE TWO EDGES OF BUILDINGS ARE TAKEN SUCH THAT THEY ARE PERPENDICULAR TO EACH OTHER AND LINE STRING IS ATTACHED TO THIS. THEY FROM THE DRAWING ACCORDING TO THE DISTANCES GIVEN FROM CENTER TO FACE OF THE COLUMN AND BY CONSIDERING THE COVER MARK THE ONE CORNER . THEN AFTER THAT PLACE THE STARTER WITH MATCHING THE POSITION THEN STARTER IS CASTED. THIS SHOULD DONE TO MARK THE EXACT POSITION OF COLUMN IN VERTICAL DIRECTION.
Details of the Construction Materials learned today NO NEW MATERIALS ARE LEARNED TODAY.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today NO NEW MATERIALS ARE LEARNED TODAY.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3000 FORMICA-2 NO. = RS 1200 EACH = RS 2400 LINING PATTI- RS 7/FT.-20 FT = RS 140 MAPPING PATTI- RS 10/FT.- 30 FT. =RS 300 FEVICOL- RS 300/KG DOOR FRAME- RS 2000 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 12000 CONTRACTOR PROFIT= 15% = RS 1700 TOTAL COST= RS 13700
Result of RATE ANALYSIS ( Rs per Unit ) 13700 RS
Todays BUZZ Word IF WE DONE OUR WORK WITH GOOD SUPERVISION AND ACCURACY THEN WE CAN SURE ABOUT THAT WE WILL NOT REQUIRED ANY TYPE OF ADMIXTURE AND CHEMICALS TO IMPROVE OUR QUALITY OF CONCRETE. BEFORE DOING ANY MAJOR WORK SUCH AS CASTING OF 10-12 COLUMNS AT A TIME THEN WE HAVE TO PREPARE FIRST TEST CUBE SPECIMENS WITH THE DECIDED PROPORTION THEN AFTER TESTING REPORTS THE PERMISSION IS GIVEN TO THE FURTHER WORK. IF YOU WANT USE ANY TYPE OF CONSTRUCTION MATERIAL ON SITE THEN IT SHOULD BE TESTED FIRST FOR ITS PERFORMANCE THEN ACCORDING TO THAT IT WILL USED . OTHERWISE THERE IS POSSIBILITY THAT IT WILLL CAUSE WASTGE OF MONEY UNECCESARILY . NOW A DAYS ACCORDING TO THE ENVIROMENTAL CONDITITONS IT IS MUST THAT WE HAVE TO APPLY SOME KIND GREEN TECNOLOGY TO THE BUILDINGS. THIS CAN BE DONE BY USING FLY ASH BRICKS , FLY ASH MIXED CEMENT IN THE CONSTRUCTION OF BUILDING. BY ADOPTING THE RAIN WATER HARVESTING TECNIQUES OR GROUND WATER RECHARGING , BY PROVIDING SEWAGE TREATMENT PLANTS AND SOLAR PANELS ARE USED TO HEAT THE WATER ALSO UTILISIG THE ELECTRICITY GENERATED BY THIS FOR PARKING OR IN COMMAN AREAS OF THE BUILDINGS. OVERALL YOU WILL REQUIRED GOOD CO-ORDINATION WITH THE PEOPLES ON THE SITE TO DO THE WORK IN GOOD MANNER. THE ENGINEER SHOULD HAVE GOOD CO-ORDINATION WITH THE SITE SUPERVISOR ON THE SITE TO GET THE DETAIL INFORMATION ABOUT THE WORK THAT WAS ALLOTED TO THEM AND WHAT IS THE PROGRESS OF WORK. THERE IS TENDENCY OF WORKERS ON THE SITE TO WORK ACCORDING TO THEIR EXPERIENCE AND NOT WITH THE INSTRUCTION GIVEN TO THEM .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-12

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) MISAL SWAPNIL SHIVAJI
Exam No. 10877
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE LINE-OUT WORK OF A COLUMN.
Details of how you Planned & Executed the allotted work WE FIRST THOROUGHLY STUDIED THE CENTER LINES PLANS AND GO TO THE SPOT. NOTING DOWN THE THINGS RELATED TO WORK.
Details of the Construction Procedure / Activity / Technology learned today FIRST THE TWO EDGES OF BUILDINGS ARE TAKEN SUCH THAT THEY ARE PERPENDICULAR TO EACH OTHER AND LINE STRING IS ATTACHED TO THIS. THEY FROM THE DRAWING ACCORDING TO THE DISTANCES GIVEN FROM CENTER TO FACE OF THE COLUMN AND BY CONSIDERING THE COVER MARK THE ONE CORNER . THEN AFTER THAT PLACE THE STARTER WITH MATCHING THE POSITION THEN STARTER IS CASTED. THIS SHOULD DONE TO MARK THE EXACT POSITION OF COLUMN IN VERTICAL DIRECTION.
Details of the Construction Materials learned today NO NEW MATERIALS ARE LEARNED TODAY.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today NO NEW MATERIALS ARE LEARNED TODAY.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3000 FORMICA-2 NO. = RS 1200 EACH = RS 2400 LINING PATTI- RS 7/FT.-20 FT = RS 140 MAPPING PATTI- RS 10/FT.- 30 FT. =RS 300 FEVICOL- RS 300/KG DOOR FRAME- RS 2000 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 12000 CONTRACTOR PROFIT= 15% = RS 1700 TOTAL COST= RS 13700
Result of RATE ANALYSIS ( Rs per Unit ) 13700 RS
Todays BUZZ Word IF WE DONE OUR WORK WITH GOOD SUPERVISION AND ACCURACY THEN WE CAN SURE ABOUT THAT WE WILL NOT REQUIRED ANY TYPE OF ADMIXTURE AND CHEMICALS TO IMPROVE OUR QUALITY OF CONCRETE. BEFORE DOING ANY MAJOR WORK SUCH AS CASTING OF 10-12 COLUMNS AT A TIME THEN WE HAVE TO PREPARE FIRST TEST CUBE SPECIMENS WITH THE DECIDED PROPORTION THEN AFTER TESTING REPORTS THE PERMISSION IS GIVEN TO THE FURTHER WORK. IF YOU WANT USE ANY TYPE OF CONSTRUCTION MATERIAL ON SITE THEN IT SHOULD BE TESTED FIRST FOR ITS PERFORMANCE THEN ACCORDING TO THAT IT WILL USED . OTHERWISE THERE IS POSSIBILITY THAT IT WILLL CAUSE WASTGE OF MONEY UNECCESARILY . NOW A DAYS ACCORDING TO THE ENVIROMENTAL CONDITITONS IT IS MUST THAT WE HAVE TO APPLY SOME KIND GREEN TECNOLOGY TO THE BUILDINGS. THIS CAN BE DONE BY USING FLY ASH BRICKS , FLY ASH MIXED CEMENT IN THE CONSTRUCTION OF BUILDING. BY ADOPTING THE RAIN WATER HARVESTING TECNIQUES OR GROUND WATER RECHARGING , BY PROVIDING SEWAGE TREATMENT PLANTS AND SOLAR PANELS ARE USED TO HEAT THE WATER ALSO UTILISIG THE ELECTRICITY GENERATED BY THIS FOR PARKING OR IN COMMAN AREAS OF THE BUILDINGS. OVERALL YOU WILL REQUIRED GOOD CO-ORDINATION WITH THE PEOPLES ON THE SITE TO DO THE WORK IN GOOD MANNER. THE ENGINEER SHOULD HAVE GOOD CO-ORDINATION WITH THE SITE SUPERVISOR ON THE SITE TO GET THE DETAIL INFORMATION ABOUT THE WORK THAT WAS ALLOTED TO THEM AND WHAT IS THE PROGRESS OF WORK. THERE IS TENDENCY OF WORKERS ON THE SITE TO WORK ACCORDING TO THEIR EXPERIENCE AND NOT WITH THE INSTRUCTION GIVEN TO THEM .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: gauravdesai75@gmail.com
Subject: 13522-12

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near JayPrabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DESAI GAURAV RAVINDRA
Exam No. 13522
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge 1. To see and study the laying of steel of beams of third floor. 2. To see the placing of formwork and shuttering for third floor.
Details of how you Planned & Executed the allotted work We first went on the centering work of third floor.We saw how the steel of beams was been laid as per plans. We saw how the labourers place the formwork and shuttering which is a very risky work.
Details of the Construction Procedure / Activity / Technology learned today We learned how the labourers by using plans laid the steel for beams of third floor,how they marked the spacing between stirrups by chalk and then fix the stirrups, how the formwork was constructed for third floor.
Details of the Construction Materials learned today 1.Material for manufacturing flyash like lime,gypsum,flyash,cement. 2.Material for manufacturing concrete at site like 1 bag cement,weigh batched proportions of coarse and fine aggregate, proper proportion of water. 3.Material used for shutteing,formwork, steel used for beams like mild steel,tor steel of different sizes ranging form 8mm to 30mm etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper drainage system,Proper disposal of waste in waste treatment plant is going to be done after completion of project.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for schedule of beams for third floor.
Details of the Bye Laws referred today 1. The number and spacing of steel for beams is placed as per bye laws. 2. The mix proportion for concrete made at site is as per bye laws.
Details of any Managerial Skill learned today 1. The site incharge inspected the site and checked the work going on. 2. The site incharge checked that the steel that was brought by the contractor was as per quotataion.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"FULLY COMPLETE DOOR\" \"T.W.Panelled door\" Total cost of Providing and fixing country Teak Wood single panelled doorswith 35mm thick shutter and 25mm thick panels with fastenings and finishing the wood work with oil painting completed= Rs.3400/sq.m Labour cost= Rs.600/sq.m Total cost= 3400+600= Rs.4000/sq.m Including 10% profit= Rs.400. Total cost= 4000+400= Rs.4400/sq.m \"FLUSH DOOR\" Providing And fixing solid core flush door in single leaf 32mm thick decorative type of exterior grade etc. including finishing with french polish= Rs.1700/sq.m Labour cost= Rs.250/sq.m Total cost= 1700+250= Rs.1950/sq.m Including 10% profit= Rs.195. Total cost= 1950+195= Rs.2145/sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4400/sq.m for T.W.Panelled door.
Todays BUZZ Word \"MY SITE TRAINING EXPERIENCE\" The first time Pathan sir declared that their will be site training before exams,I was very happy with that thing,throughout the exams i was just thinking about the training programme. Firstly i was happy that i was in group of Pooja builders which was constructing \"WONDER 11\" first 11 storeyed skyscraper in kolhapur. exams finished then i and my other froup members went to visit Mr.Paras Oswal sir prior to our training programme. When we met we felt very happy that we got a very fantastic personality to work with,a man who was among one of the well-known,priviledged,a social worker and a good human being of Kolhapur. We started our training on 8th Dec. During the first day itself we got to learn many new things that how steel for beams was laid according to plans, how concrete was placed for stair-case,how columns were made etc. We were new on site so labourers were seeing us like a strangers wearing helmets, the interesting thing was that besides being the most important and biggest project of kolhapur we were the only 5 to wear helmets on site. The first day ended up happily. At day 2, we introduced ourselves with the labourers we found that majority of them were from Bihar and Jharkhand. We had to talk with them in hindi so that they could understand. We asked our difficulties to the site incharge as well as the labourers wherever we felt and they responded us well and cleared our doubts. On the same day we met Mr.Pramod Salvekar who was among the only two dealers of Reticulated Gas Pipeline system in Maharashtra.It was nice to meet him. The next 2 days we saw the construction of slab by R.M.C,electrification work,plumbing work,staircase,palnning of pipe system for reticulted gas pipeline. etc.On day 5 while we were on site Paras Oswal sir came to inspect the the site he met us enquired that we were not having difficulties and problems and at that time he suggested us to visit his Farm house construction at Panhala and at Panchgaon. We were so much happy after listening this, we told Sir that the next day we would visit that site. Oswal sir informed the site incharge at Panhala and made arrangement of lunch for us their. On day7, we went to Panhala reached their at 9 met the site incharge saw the site it was awesome and all the farmhouses were booked. The site incharge served us tea. Then he gave us plans and we saw the whole site.Then in the afternoon we were served by lunch made on chool in a small home. We liked that food very much.Then we visited the site again talked with the site incharge about the project and at 4 we departed from Panhala. It was just an Amazing day and a memorable one. On day 8 we were back on our site \"WONDER 11\". On that day we participated in a programme in which Mr.Paras Oswal launched a pioneered a new technology and their venture \"INFINITE BIO-FUELS AND AGRITECH PVT.LTD\" in which they aimed to reduce the waste like agricultutral waste,garbage etc. and used it for heating purpose. The next day we went to the site at Panchgaon.Their we saw the construction of 2 storeyed building going on, their we met the consulting engineer of Pooja group Mr.Sameer Shah. He gave us a brief information of the overall construction of Pooja group going on he gave us some a new information and encouraged us to go for P.G, M.B.A. During day 10 and 11 we studied and saw the prcess of manufacturing Fly ash bricks,construction of staircase by concrete made at site etc. On the last day Day 12,the site incharge P.B.Sutar sir and Sarvalkar sir on recommendation of Paras Oswal sir had arrranged afternoon\'s lunch for us at their canteen,inspite that we told them that we had brought our lunchboxes, they made us compulsory, We were very thankful to them for their kindness. We met all the labourers for the last time we didn\'t wanted to live the site but we had too. We wanted to meet Paras Oswal sir But he was out of town so we couldn\'t,so we departed from the site. If their will site training again i wish that i may get the ssame group members and same group \"POOJA GROUP\". The site training gave us atleast 20% knowledge and brought us out from our bookworld into the practical. We thank u Pathan sir for a wonderful opportunity u gave us and we hope that u will encourage us hereafter the same way. This site training will be definitely a memorable one for me and all.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-11

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bhoite Vishal Rajaram
Exam No. 13555
Working Day No. 11
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Plumbing done on the site.
Details of how you Planned & Executed the allotted work - The group of 5 were divided in the 3 groups. - First we studied the plan of plumbing. - Slab plan was studied as the brick bat coba was done for water-proofing.
Details of the Construction Procedure / Activity / Technology learned today 1)Plumbing - First as per the plan the markings were done on the wall. - Then the walls were drilled as per the marking done and the size of pipe. - Then the Pipes were fitted and bores which were drilled were again refilled. 2)Water proofing - The brick bats were selected and throughly soaked in water before using it. - Bricks were layed onto it and cement mortar of proportion 1:6 was used in between them - The water-proofing material \"DR.FIXIT\" was used as per the proportions given by the incharge.
Details of the Construction Materials learned today - Brick bat-coba. - Dr. fixit.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plumbing drawing. - Floor plans.
Details of the Bye Laws referred today - For plumbing. - For water-proofing.
Details of any Managerial Skill learned today - Daily report of labours - Managing the labours - Use of materials which are avaolable on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR:- Door size:- 1.2 x 2.1m Total quantity of wood required=0.2077 cu.m cost of material:- material quantity rate cost wood 0.2077 1200 250 hold fast 6 nos. 35 210 kadikonda 2 nos. 100 200 eye hole 1 nos. 100 100 stopper 1 nos. 50 50 handle 2 nos. 150 300 Total= 1109.24 add 10% contractors profit = 110.92 Grand total = 1250 cost of labour size of door 1.2x 2.1x10.76=27.11 sq.ft cost of labour = 27.11x60=1650 Grand total=1250+ 1650=2900
Result of RATE ANALYSIS ( Rs per Unit ) Rs 2900
Todays BUZZ Word The foll. things were leant on the site:- 1) First to prepare the bills required. 2) Mananging the labours. 3) Distributing the work given between the labours. 4) To be punctual. 5) To complete the work done given onto the site. 6) To convince the customer. 7) To use the materials which are avalible on the sitye. 8) To make the payment to the labours. 9) Material managment. 10) Plumbing techniques. 11) Various brick masonary work. 12) Water-profing materials. 13) Center- line marking. 14) Safty precautions on the site. 15) Internal & external plastering works. 16) Painting works. 17) Electrification works. 18) PLumbing and sanitations 19) Estimating and costing of various materials. 20) Line-out of building works. 21) Sanitation works 22) Teamwork 23) Sensitivity 24) Way of dressing 25) Coordination with labours and clients. 26) Rain-water harvesting. 27) Environmentally friendly techniques. 28) Septic tank work. 29) Erection of Scaffolding etc...
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-11

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bauchakar Deepak Yuvraj
Exam No. 13554
Working Day No. 11
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Plumbing done on the site.
Details of how you Planned & Executed the allotted work - The group of 5 were divided in the 3 groups. - First we studied the plan of plumbing. - Slab plan was studied as the brick bat coba was done for water-proofing.
Details of the Construction Procedure / Activity / Technology learned today 1)Plumbing - First as per the plan the markings were done on the wall. - Then the walls were drilled as per the marking done and the size of pipe. - Then the Pipes were fitted and bores which were drilled were again refilled. 2)Water proofing - The brick bats were selected and throughly soaked in water before using it. - Bricks were layed onto it and cement mortar of proportion 1:6 was used in between them - The water-proofing material \"DR.FIXIT\" was used as per the proportions given by the incharge.
Details of the Construction Materials learned today - Brick bat-coba. - Dr. fixit.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plumbing drawing. - Floor plans.
Details of the Bye Laws referred today - For plumbing. - For water-proofing.
Details of any Managerial Skill learned today - Daily report of labours - Managing the labours - Use of materials which are avaolable on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR:- Door size:- 1.2 x 2.1m Total quantity of wood required=0.2077 cu.m cost of material:- material quantity rate cost wood 0.2077 1200 250 hold fast 6 nos. 35 210 kadikonda 2 nos. 100 200 eye hole 1 nos. 100 100 stopper 1 nos. 50 50 handle 2 nos. 150 300 Total= 1109.24 add 10% contractors profit = 110.92 Grand total = 1250 cost of labour size of door 1.2x 2.1x10.76=27.11 sq.ft cost of labour = 27.11x60=1650 Grand total=1250+ 1650=2900
Result of RATE ANALYSIS ( Rs per Unit ) Rs 2900
Todays BUZZ Word The foll. things were leant on the site:- 1) First to prepare the bills required. 2) Mananging the labours. 3) Distributing the work given between the labours. 4) To be punctual. 5) To complete the work done given onto the site. 6) To convince the customer. 7) To use the materials which are avalible on the sitye. 8) To make the payment to the labours. 9) Material managment. 10) Plumbing techniques. 11) Various brick masonary work. 12) Water-profing materials. 13) Center- line marking. 14) Safty precautions on the site. 15) Internal & external plastering works. 16) Painting works. 17) Electrification works. 18) PLumbing and sanitations 19) Estimating and costing of various materials. 20) Line-out of building works. 21) Sanitation works 22) Teamwork 23) Sensitivity 24) Way of dressing 25) Coordination with labours and clients. 26) Rain-water harvesting. 27) Environmentally friendly techniques. 28) Septic tank work. 29) Erection of Scaffolding etc...
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. Vivek Randive
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: salmanbaig18@gmail.com
Subject: 10896-12

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) BAIG SALMAN S.
Exam No. 10896
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe the making of beams on the second floor and take the required checks.
Details of how you Planned & Executed the allotted work We saw that the btop bars and bottom bars were as per the diameter and length given in the design detailing. After that we checked the size of stirrups and their spacing. Then after the lovuering of beam in the formwork we checked the side and bottom covers.
Details of the Construction Procedure / Activity / Technology learned today “Preparation of beam” Firstly the bottom bars were placed above the beam formwork and tied at a height of about 1ft in the supporting columns. Then the top bas were tied and then the stirrups as per the design given were inserted and tied at the four corners of stirrups were tied to the bars at the given spacing and then the beam was louvered in the formwork.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method is used on the site.
Details of the Construction / Engineering Drawings observed today Drawing of Beam sections with their schedule and detailed second floor plan
Details of the Bye Laws referred today Size of bath and w/c - Dimensions provided on the site for bath:-2.0*1.2=2.4sqm Dimensions provided on the site for w/c:-1.2*1.0=1.2sqm As per bye law the minimum dimensions to be provided is 1.8m*1.0m and 0.9m*0.9m
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation external non-teak door“ Dimension of the door frame=0.92*2.07*0.10 Dimension of the door panel required=0.82*2.02*0.035 Quantity of hinges required=3nos Quantity of latches required=2nos Quantity of handles required=2nos Quantity of stopper required=1nos carpenter required =2nos “Rate Analysis for external non-teak door” (Considering local rates of material) 1. Cost of door frame=1*900=900/-………..(900/- per frame) 2. Cost of door panel= 1*1500=1500/-…………(1500/- per panel) 3. Cost of hinges=3*35=105/-………………..(35/- per hinge) 4. Cost of latches=2*90=180/-………(90/- per latch) 5. Cost of stopper=1*40=40/-…………(40/- per stopper) 6. Cost of handles=2*50=100/-…….(50per handle) 7. Labour charges=300/-…………(150/- per carpenter for half day) 5. Total cost=2975/- 6.10% profit of total cost for the contractor=297.5/- 7. Total cost=3272.5/- 10. Rate per door=3272.5/-
Result of RATE ANALYSIS ( Rs per Unit ) 3273/-
Todays BUZZ Word “Site training experience” On behalf of our group I am very thankful to our Civil Engg Dept and prof.I.I.Pathan for arranging such an up-to-date and successful training program for us and giving a glamorous opportunity for interacting with the real estate industry and impressive personalities. We are thankful to prof.I.I.P for giving us a site which is very perfect in maintain the accuracy and quality in construction. I have learned that how the quality and accuracy is maintained and controlled during the actual construction and casting of concrete. This program has given me the brief idea how the theoretical concepts are actually applied on the site. As site given to me was in its initial stage of construction it has helped me to learn the detailed construction procedure of basic building components like beams, columns, staircase, slab, sunk slabs, majorly the fixing of shuttering and formwork and with this maintaining the accuracy. Basic points of accuracy control which I have learned are maintaining the plumb line and level of each component from the ground floor till the stage where the further construction is done. I have learned how various working drawings are to be read and w.r.t the drawings how the actual work is to be carried out. It has helped me that how the various problems are to be tackled during the actual construction and manage the workers as per the nature of work to be executed, and also how to keep the workers busy in work during the shortage of materials on the site. At last this program has taught me how the work is to be executed in group and how to interact with each other with different ideas and concepts and co ordinate each other and help. It has given me the idea how to talk with workers at the site and capacity of how much I can stand on the site from the whole day. Once again glad to thank u sir and our civil department………
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-12

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Suyvanshi patil Pratiksinh Vilas
Exam No. 13549
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Plumbing done on the site.
Details of how you Planned & Executed the allotted work - The group of 5 were divided in the 3 groups. - First we studied the plan of plumbing. - Slab plan was studied as the brick bat coba was done for water-proofing.
Details of the Construction Procedure / Activity / Technology learned today 1)Plumbing - First as per the plan the markings were done on the wall. - Then the walls were drilled as per the marking done and the size of pipe. - Then the Pipes were fitted and bores which were drilled were again refilled. 2)Water proofing - The brick bats were selected and throughly soaked in water before using it. - Bricks were layed onto it and cement mortar of proportion 1:6 was used in between them - The water-proofing material \"DR.FIXIT\" was used as per the proportions given by the incharge.
Details of the Construction Materials learned today - Brick bat-coba. - Dr. fixit.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plumbing drawing. - Floor plans.
Details of the Bye Laws referred today - For plumbing. - For water-proofing.
Details of any Managerial Skill learned today - Daily report of labours - Managing the labours - Use of materials which are avaolable on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR:- Door size:- 1.2 x 2.1m Total quantity of wood required=0.2077 cu.m cost of material:- material quantity rate cost wood 0.2077 1200 250 hold fast 6 nos. 35 210 kadikonda 2 nos. 100 200 eye hole 1 nos. 100 100 stopper 1 nos. 50 50 handle 2 nos. 150 300 Total= 1109.24 add 10% contractors profit = 110.92 Grand total = 1250 cost of labour size of door 1.2x 2.1x10.76=27.11 sq.ft cost of labour = 27.11x60=1650 Grand total=1250+ 1650=2900
Result of RATE ANALYSIS ( Rs per Unit ) Rs 2900
Todays BUZZ Word The foll. things were leant on the site:- 1) First to prepare the bills required. 2) Mananging the labours. 3) Distributing the work given between the labours. 4) To be punctual. 5) To complete the work done given onto the site. 6) To convince the customer. 7) To use the materials which are avalible on the sitye. 8) To make the payment to the labours. 9) Material managment. 10) Plumbing techniques. 11) Various brick masonary work. 12) Water-profing materials. 13) Center- line marking. 14) Safty precautions on the site. 15) Internal & external plastering works. 16) Painting works. 17) Electrification works. 18) PLumbing and sanitations 19) Estimating and costing of various materials. 20) Line-out of building works. 21) Sanitation works 22) Teamwork 23) Sensitivity 24) Way of dressing 25) Coordination with labours and clients. 26) Rain-water harvesting. 27) Environmentally friendly techniques. 28) Septic tank work. 29) Erection of Scaffolding etc...
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: v.g.ayyar@gmail.com
Subject: 13553-09

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Ayyar Vignesh Gopal
Exam No. 13553
Working Day No. 09
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Plumbing done on the site.
Details of how you Planned & Executed the allotted work - The group of 5 were divided in the 3 groups. - First we studied the plan of plumbing. - Slab plan was studied as the brick bat coba was done for water-proofing.
Details of the Construction Procedure / Activity / Technology learned today 1)Plumbing - First as per the plan the markings were done on the wall. - Then the walls were drilled as per the marking done and the size of pipe. - Then the Pipes were fitted and bores which were drilled were again refilled. 2)Water proofing - The brick bats were selected and throughly soaked in water before using it. - Bricks were layed onto it and cement mortar of proportion 1:6 was used in between them - The water-proofing material \"DR.FIXIT\" was used as per the proportions given by the incharge.
Details of the Construction Materials learned today - Brick bat-coba. - Dr. fixit.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plumbing drawing. - Floor plans.
Details of the Bye Laws referred today - For plumbing. - For water-proofing.
Details of any Managerial Skill learned today - Daily report of labours - Managing the labours - Use of materials which are avaolable on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR:- Door size:- 1.2 x 2.1m Total quantity of wood required=0.2077 cu.m cost of material:- material quantity rate cost wood 0.2077 1200 250 hold fast 6 nos. 35 210 kadikonda 2 nos. 100 200 eye hole 1 nos. 100 100 stopper 1 nos. 50 50 handle 2 nos. 150 300 Total= 1109.24 add 10% contractors profit = 110.92 Grand total = 1250 cost of labour size of door 1.2x 2.1x10.76=27.11 sq.ft cost of labour = 27.11x60=1650 Grand total=1250+ 1650=2900
Result of RATE ANALYSIS ( Rs per Unit ) Rs 2900
Todays BUZZ Word The foll. things were leant on the site:- 1) First to prepare the bills required. 2) Mananging the labours. 3) Distributing the work given between the labours. 4) To be punctual. 5) To complete the work done given onto the site. 6) To convince the customer. 7) To use the materials which are avalible on the sitye. 8) To make the payment to the labours. 9) Material managment. 10) Plumbing techniques. 11) Various brick masonary work. 12) Water-profing materials. 13) Center- line marking. 14) Safty precautions on the site. 15) Internal & external plastering works. 16) Painting works. 17) Electrification works. 18) PLumbing and sanitations 19) Estimating and costing of various materials. 20) Line-out of building works. 21) Sanitation works 22) Teamwork 23) Sensitivity 24) Way of dressing 25) Coordination with labours and clients. 26) Rain-water harvesting. 27) Environmentally friendly techniques. 28) Septic tank work. 29) Erection of Scaffolding etc...
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-12

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Sutar Namdev Rangnath
Exam No. 13571
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge Visit to MAHALAXIMI TMT STEEL PLANT. .
Details of how you Planned & Executed the allotted work Steel is the very important component material of construction industry. the skilled supervision required for steel production. the strength of bar must be tested after the production of bar. today the 20 mm diameter bar were manufactured in plant. .
Details of the Construction Procedure / Activity / Technology learned today Because of advanced equipments used in steel production industry the man work had reduced .But the supervision work at plant is more important during the production.the miner labour work is required during the process . adjustment made for changing diameter with the help of labour force. .
Details of the Construction Materials learned today Thermo mechanical treated bar(TMT) of 550 ,500 ,415 grades. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Wastage from human society in the form of steel likes steel bars ,plates , square parts of vehicles are used in steel plant a raw material.Which is useful in environment caring. .
Details of the Construction / Engineering Drawings observed today detailed drawing of MAHALAXIMI TMT STEEL PLANT. .
Details of the Bye Laws referred today 1. Zones of industrial area 2. Plot required for industry. 3. Type of structure built in industrial area zone. 4.cost of plot ,water requirement ,height of chimney ,plot boundary. .
Details of any Managerial Skill learned today Managerial skilled required in steel plant for following :- 1. To maintain the quality of raw product. 2. Technical work related with plant. 3. How to manage the laour force as per requirement. 4. To maintain the quality of product with strength & durability. 5. Keep the speed of production as pet market requirement. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR:- Door size:- 1.2 x 2.1m Total quantity of wood required=0.2077 cu.m cost of material:- material quantity rate cost wood 0.2077 1200 250 hold fast 6 nos. 35 210 kadikonda 2 nos. 100 200 eye hole 1 nos. 100 100 stopper 1 nos. 50 50 handle 2 nos. 150 300 Total= 1109.24 add 10% contractors profit = 110.92 Grand total = 1250 cost of labour size of door 1.2x 2.1x10.76=27.11 sq.ft cost of labour = 27.11x60=1650 Grand total=1250+ 1650=2900 .
Result of RATE ANALYSIS ( Rs per Unit ) 2900
Todays BUZZ Word CIVIL ENGINEERING is the one of the most challenging & creative branch of Engineering . In 21th century the scope & application of every engineering had increased . The understanding of basic fundamental things is the first stage of every field. The second stage is to tally our knowledge & understanding related with our field . For that purpose my department had arranged a 12 day training program with Field support of credai . It was started at the date of 8 December & ends today . My group of five students were allotted for training to P.B.BUILDERS & DEVELOPERS . We complete our training under the pleasures guidance of Mr. PRADIP BHARAMAL Sir , C.E.O. of P.B.BULDERS & DEVELOPERS. The every day of our training was most expensive & helpful for our knowledge . The first day of training we learn about the centre line plan & how to mark the Positions of columns. The proper orientation of column is very important in design point of building ,the theoretical concept are little impracticable for some cases. Whole second day we worked on the design ,placing & preliminary Procedure of p.c.c. The starting part of any construction project is plain cement concrete. What are the precautions ,assumptions made during construction activity, variations as per place to place.   The third day we learn how to find out the quantity of excavation . The depth of foundation varies with the changes in properties of soil . The foundation always Rest on hard strata & the maximum depth of excavation were in between 10 to 11 feet’s. This small but important points in excavation we understood first time on site. Next day we got information related with footing .approximately how much % Of steel used in footing .what precautions have to taken ,arrangement & distribution of Reinforcement ,we learn on site. At the fourth day Bharamal sir taught us how to prepare detailed estimate For bungalow .how to calculate various quantities & their rate analysis .Next three Day s we were working on the estimate. A Wednesday & Thursday we marked road level on columns of apartment with the Help of bubble tube .generally the level marking done with the dumpy level but at The time when level is not available the levelling done by bubble tube. These two day we were just working on the levelling of ground. The concepts related with Plumbing work we understood at site. the circulation of pipes their arrangements as per requirements & as per function .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: mayur.sonawane61@gmail.com
Subject: 13570-11

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Sonawane Mayur Madhukar
Exam No. 13570
Working Day No. 11
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge Visit to MAHALAXIMI TMT STEEL PLANT. .
Details of how you Planned & Executed the allotted work Steel is the very important component material of construction industry. the skilled supervision required for steel production. the strength of bar must be tested after the production of bar. today the 20 mm diameter bar were manufactured in plant. .
Details of the Construction Procedure / Activity / Technology learned today Because of advanced equipments used in steel production industry the man work had reduced .But the supervision work at plant is more important during the production.the miner labour work is required during the process . adjustment made for changing diameter with the help of labour force. .
Details of the Construction Materials learned today Thermo mechanical treated bar(TMT) of 550 ,500 ,415 grades. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Wastage from human society in the form of steel likes steel bars ,plates , square parts of vehicles are used in steel plant a raw material.Which is useful in environment caring. .
Details of the Construction / Engineering Drawings observed today detailed drawing of MAHALAXIMI TMT STEEL PLANT. .
Details of the Bye Laws referred today 1. Zones of industrial area 2. Plot required for industry. 3. Type of structure built in industrial area zone. 4.cost of plot ,water requirement ,height of chimney ,plot boundary. .
Details of any Managerial Skill learned today Managerial skilled required in steel plant for following :- 1. To maintain the quality of raw product. 2. Technical work related with plant. 3. How to manage the laour force as per requirement. 4. To maintain the quality of product with strength & durability. 5. Keep the speed of production as pet market requirement. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR:- Door size:- 1.2 x 2.1m Total quantity of wood required=0.2077 cu.m cost of material:- material quantity rate cost wood 0.2077 1200 250 hold fast 6 nos. 35 210 kadikonda 2 nos. 100 200 eye hole 1 nos. 100 100 stopper 1 nos. 50 50 handle 2 nos. 150 300 Total= 1109.24 add 10% contractors profit = 110.92 Grand total = 1250 cost of labour size of door 1.2x 2.1x10.76=27.11 sq.ft cost of labour = 27.11x60=1650 Grand total=1250+ 1650=2900 .
Result of RATE ANALYSIS ( Rs per Unit ) 2900
Todays BUZZ Word CIVIL ENGINEERING is the one of the most challenging & creative branch of Engineering . In 21th century the scope & application of every engineering had increased . The understanding of basic fundamental things is the first stage of every field. The second stage is to tally our knowledge & understanding related with our field . For that purpose my department had arranged a 12 day training program with Field support of credai . It was started at the date of 8 December & ends today . My group of five students were allotted for training to P.B.BUILDERS & DEVELOPERS . We complete our training under the pleasures guidance of Mr. PRADIP BHARAMAL Sir , C.E.O. of P.B.BULDERS & DEVELOPERS. The every day of our training was most expensive & helpful for our knowledge . The first day of training we learn about the centre line plan & how to mark the Positions of columns. The proper orientation of column is very important in design point of building ,the theoretical concept are little impracticable for some cases. Whole second day we worked on the design ,placing & preliminary Procedure of p.c.c. The starting part of any construction project is plain cement concrete. What are the precautions ,assumptions made during construction activity, variations as per place to place.   The third day we learn how to find out the quantity of excavation . The depth of foundation varies with the changes in properties of soil . The foundation always Rest on hard strata & the maximum depth of excavation were in between 10 to 11 feet’s. This small but important points in excavation we understood first time on site. Next day we got information related with footing .approximately how much % Of steel used in footing .what precautions have to taken ,arrangement & distribution of Reinforcement ,we learn on site. At the fourth day Bharamal sir taught us how to prepare detailed estimate For bungalow .how to calculate various quantities & their rate analysis .Next three Day s we were working on the estimate. A Wednesday & Thursday we marked road level on columns of apartment with the Help of bubble tube .generally the level marking done with the dumpy level but at The time when level is not available the levelling done by bubble tube. These two day we were just working on the levelling of ground. The concepts related with Plumbing work we understood at site. the circulation of pipes their arrangements as per requirements & as per function .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-12

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Shivtare Prabhakar Chandrakant
Exam No. 13569
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge Visit to MAHALAXIMI TMT STEEL PLANT. .
Details of how you Planned & Executed the allotted work Steel is the very important component material of construction industry. the skilled supervision required for steel production. the strength of bar must be tested after the production of bar. today the 20 mm diameter bar were manufactured in plant. .
Details of the Construction Procedure / Activity / Technology learned today Because of advanced equipments used in steel production industry the man work had reduced .But the supervision work at plant is more important during the production.the miner labour work is required during the process . adjustment made for changing diameter with the help of labour force. .
Details of the Construction Materials learned today Thermo mechanical treated bar(TMT) of 550 ,500 ,415 grades. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Wastage from human society in the form of steel likes steel bars ,plates , square parts of vehicles are used in steel plant a raw material.Which is useful in environment caring. .
Details of the Construction / Engineering Drawings observed today detailed drawing of MAHALAXIMI TMT STEEL PLANT. .
Details of the Bye Laws referred today 1. Zones of industrial area 2. Plot required for industry. 3. Type of structure built in industrial area zone. 4.cost of plot ,water requirement ,height of chimney ,plot boundary. .
Details of any Managerial Skill learned today Managerial skilled required in steel plant for following :- 1. To maintain the quality of raw product. 2. Technical work related with plant. 3. How to manage the laour force as per requirement. 4. To maintain the quality of product with strength & durability. 5. Keep the speed of production as pet market requirement. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR:- Door size:- 1.2 x 2.1m Total quantity of wood required=0.2077 cu.m cost of material:- material quantity rate cost wood 0.2077 1200 250 hold fast 6 nos. 35 210 kadikonda 2 nos. 100 200 eye hole 1 nos. 100 100 stopper 1 nos. 50 50 handle 2 nos. 150 300 Total= 1109.24 add 10% contractors profit = 110.92 Grand total = 1250 cost of labour size of door 1.2x 2.1x10.76=27.11 sq.ft cost of labour = 27.11x60=1650 Grand total=1250+ 1650=2900 .
Result of RATE ANALYSIS ( Rs per Unit ) 2900
Todays BUZZ Word CIVIL ENGINEERING is the one of the most challenging & creative branch of Engineering . In 21th century the scope & application of every engineering had increased . The understanding of basic fundamental things is the first stage of every field. The second stage is to tally our knowledge & understanding related with our field . For that purpose my department had arranged a 12 day training program with Field support of credai . It was started at the date of 8 December & ends today . My group of five students were allotted for training to P.B.BUILDERS & DEVELOPERS . We complete our training under the pleasures guidance of Mr. PRADIP BHARAMAL Sir , C.E.O. of P.B.BULDERS & DEVELOPERS. The every day of our training was most expensive & helpful for our knowledge . The first day of training we learn about the centre line plan & how to mark the Positions of columns. The proper orientation of column is very important in design point of building ,the theoretical concept are little impracticable for some cases. Whole second day we worked on the design ,placing & preliminary Procedure of p.c.c. The starting part of any construction project is plain cement concrete. What are the precautions ,assumptions made during construction activity, variations as per place to place.   The third day we learn how to find out the quantity of excavation . The depth of foundation varies with the changes in properties of soil . The foundation always Rest on hard strata & the maximum depth of excavation were in between 10 to 11 feet’s. This small but important points in excavation we understood first time on site. Next day we got information related with footing .approximately how much % Of steel used in footing .what precautions have to taken ,arrangement & distribution of Reinforcement ,we learn on site. At the fourth day Bharamal sir taught us how to prepare detailed estimate For bungalow .how to calculate various quantities & their rate analysis .Next three Day s we were working on the estimate. A Wednesday & Thursday we marked road level on columns of apartment with the Help of bubble tube .generally the level marking done with the dumpy level but at The time when level is not available the levelling done by bubble tube. These two day we were just working on the levelling of ground. The concepts related with Plumbing work we understood at site. the circulation of pipes their arrangements as per requirements & as per function .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-12

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) shinde sagar arvind
Exam No. 13568
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge Visit to MAHALAXIMI TMT STEEL PLANT. .
Details of how you Planned & Executed the allotted work Steel is the very important component material of construction industry. the skilled supervision required for steel production. the strength of bar must be tested after the production of bar. today the 20 mm diameter bar were manufactured in plant. .
Details of the Construction Procedure / Activity / Technology learned today Because of advanced equipments used in steel production industry the man work had reduced .But the supervision work at plant is more important during the production.the miner labour work is required during the process . adjustment made for changing diameter with the help of labour force. .
Details of the Construction Materials learned today Thermo mechanical treated bar(TMT) of 550 ,500 ,415 grades. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Wastage from human society in the form of steel likes steel bars ,plates , square parts of vehicles are used in steel plant a raw material.Which is useful in environment caring. .
Details of the Construction / Engineering Drawings observed today detailed drawing of MAHALAXIMI TMT STEEL PLANT. .
Details of the Bye Laws referred today 1. Zones of industrial area 2. Plot required for industry. 3. Type of structure built in industrial area zone. 4.cost of plot ,water requirement ,height of chimney ,plot boundary. .
Details of any Managerial Skill learned today Managerial skilled required in steel plant for following :- 1. To maintain the quality of raw product. 2. Technical work related with plant. 3. How to manage the laour force as per requirement. 4. To maintain the quality of product with strength & durability. 5. Keep the speed of production as pet market requirement. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR:- Door size:- 1.2 x 2.1m Total quantity of wood required=0.2077 cu.m cost of material:- material quantity rate cost wood 0.2077 1200 250 hold fast 6 nos. 35 210 kadikonda 2 nos. 100 200 eye hole 1 nos. 100 100 stopper 1 nos. 50 50 handle 2 nos. 150 300 Total= 1109.24 add 10% contractors profit = 110.92 Grand total = 1250 cost of labour size of door 1.2x 2.1x10.76=27.11 sq.ft cost of labour = 27.11x60=1650 Grand total=1250+ 1650=2900 .
Result of RATE ANALYSIS ( Rs per Unit ) 2900
Todays BUZZ Word CIVIL ENGINEERING is the one of the most challenging & creative branch of Engineering . In 21th century the scope & application of every engineering had increased . The understanding of basic fundamental things is the first stage of every field. The second stage is to tally our knowledge & understanding related with our field . For that purpose my department had arranged a 12 day training program with Field support of credai . It was started at the date of 8 December & ends today . My group of five students were allotted for training to P.B.BUILDERS & DEVELOPERS . We complete our training under the pleasures guidance of Mr. PRADIP BHARAMAL Sir , C.E.O. of P.B.BULDERS & DEVELOPERS. The every day of our training was most expensive & helpful for our knowledge . The first day of training we learn about the centre line plan & how to mark the Positions of columns. The proper orientation of column is very important in design point of building ,the theoretical concept are little impracticable for some cases. Whole second day we worked on the design ,placing & preliminary Procedure of p.c.c. The starting part of any construction project is plain cement concrete. What are the precautions ,assumptions made during construction activity, variations as per place to place.   The third day we learn how to find out the quantity of excavation . The depth of foundation varies with the changes in properties of soil . The foundation always Rest on hard strata & the maximum depth of excavation were in between 10 to 11 feet’s. This small but important points in excavation we understood first time on site. Next day we got information related with footing .approximately how much % Of steel used in footing .what precautions have to taken ,arrangement & distribution of Reinforcement ,we learn on site. At the fourth day Bharamal sir taught us how to prepare detailed estimate For bungalow .how to calculate various quantities & their rate analysis .Next three Day s we were working on the estimate. A Wednesday & Thursday we marked road level on columns of apartment with the Help of bubble tube .generally the level marking done with the dumpy level but at The time when level is not available the levelling done by bubble tube. These two day we were just working on the levelling of ground. The concepts related with Plumbing work we understood at site. the circulation of pipes their arrangements as per requirements & as per function .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 13567-12

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge Visit to MAHALAXIMI TMT STEEL PLANT. .
Details of how you Planned & Executed the allotted work Steel is the very important component material of construction industry. the skilled supervision required for steel production. the strength of bar must be tested after the production of bar. today the 20 mm diameter bar were manufactured in plant. .
Details of the Construction Procedure / Activity / Technology learned today Because of advanced equipments used in steel production industry the man work had reduced .But the supervision work at plant is more important during the production.the miner labour work is required during the process . adjustment made for changing diameter with the help of labour force. .
Details of the Construction Materials learned today Thermo mechanical treated bar(TMT) of 550 ,500 ,415 grades. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Wastage from human society in the form of steel likes steel bars ,plates , square parts of vehicles are used in steel plant a raw material.Which is useful in environment caring. .
Details of the Construction / Engineering Drawings observed today detailed drawing of MAHALAXIMI TMT STEEL PLANT. .
Details of the Bye Laws referred today 1. Zones of industrial area 2. Plot required for industry. 3. Type of structure built in industrial area zone. 4.cost of plot ,water requirement ,height of chimney ,plot boundary. .
Details of any Managerial Skill learned today Managerial skilled required in steel plant for following :- 1. To maintain the quality of raw product. 2. Technical work related with plant. 3. How to manage the laour force as per requirement. 4. To maintain the quality of product with strength & durability. 5. Keep the speed of production as pet market requirement. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR:- Door size:- 1.2 x 2.1m Total quantity of wood required=0.2077 cu.m cost of material:- material quantity rate cost wood 0.2077 1200 250 hold fast 6 nos. 35 210 kadikonda 2 nos. 100 200 eye hole 1 nos. 100 100 stopper 1 nos. 50 50 handle 2 nos. 150 300 Total= 1109.24 add 10% contractors profit = 110.92 Grand total = 1250 cost of labour size of door 1.2x 2.1x10.76=27.11 sq.ft cost of labour = 27.11x60=1650 Grand total=1250+ 1650=2900 .
Result of RATE ANALYSIS ( Rs per Unit ) 2900
Todays BUZZ Word CIVIL ENGINEERING is the one of the most challenging & creative branch of Engineering . In 21th century the scope & application of every engineering had increased . The understanding of basic fundamental things is the first stage of every field. The second stage is to tally our knowledge & understanding related with our field . For that purpose my department had arranged a 12 day training program with Field support of credai . It was started at the date of 8 December & ends today . My group of five students were allotted for training to P.B.BUILDERS & DEVELOPERS . We complete our training under the pleasures guidance of Mr. PRADIP BHARAMAL Sir , C.E.O. of P.B.BULDERS & DEVELOPERS. The every day of our training was most expensive & helpful for our knowledge . The first day of training we learn about the centre line plan & how to mark the Positions of columns. The proper orientation of column is very important in design point of building ,the theoretical concept are little impracticable for some cases. Whole second day we worked on the design ,placing & preliminary Procedure of p.c.c. The starting part of any construction project is plain cement concrete. What are the precautions ,assumptions made during construction activity, variations as per place to place.   The third day we learn how to find out the quantity of excavation . The depth of foundation varies with the changes in properties of soil . The foundation always Rest on hard strata & the maximum depth of excavation were in between 10 to 11 feet’s. This small but important points in excavation we understood first time on site. Next day we got information related with footing .approximately how much % Of steel used in footing .what precautions have to taken ,arrangement & distribution of Reinforcement ,we learn on site. At the fourth day Bharamal sir taught us how to prepare detailed estimate For bungalow .how to calculate various quantities & their rate analysis .Next three Day s we were working on the estimate. A Wednesday & Thursday we marked road level on columns of apartment with the Help of bubble tube .generally the level marking done with the dumpy level but at The time when level is not available the levelling done by bubble tube. These two day we were just working on the levelling of ground. The concepts related with Plumbing work we understood at site. the circulation of pipes their arrangements as per requirements & as per function .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-12

Company Name Rajesh Constructions
Project Name & Site Address cloud-9
Students Name (Surname_First Name_Middle Name) PATIL VRISHALI V.
Exam No. 13541
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 :00 A.M.
Site Leaving Time (HH:MM am/pm) 4:00 P.M.
Details of the Work Allotted to you today by the Site In-Charge filling of column by concrete of M20 grade .
Details of how you Planned & Executed the allotted work first we checked proper erection of form-work by plumb bob. all the columns were at it is fixed position. then we marked the position up to where concrete has to be filled such way we filled 16 columns .
Details of the Construction Procedure / Activity / Technology learned today Mixing of M20 grade concrete with proper propotion .
Details of the Construction Materials learned today tiling of floors- vitrified tiles, marble granite , kota , shahabadi .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of electrical motor mixer - for this mixer electric motor is used to rotate the drum of making concrete so that it prevents environment by avoiding harmful smoke.
Details of the Construction / Engineering Drawings observed today column positions & footing drawing- slab dimension drawing.
Details of the Bye Laws referred today floor to floor height- min. height - 2.7m max. height- 3m
Details of any Managerial Skill learned today punctual , helpful , & skillful
RATE ANALYSIS (Detailed Stepwise Calculations required) for teak wood door= height= 8ft. width= 3 ft. total teak wood required for thk. of 5 inch X 3 inch = 1.785 cu.ft. cost of 1 cu. ft. teak wood = 1800 Rs. total cost of teak wood door = 1.785 X 1800 = 3000 Rs./ cu. ft.
Result of RATE ANALYSIS ( Rs per Unit ) 3000 Rs./ cu. ft.
Todays BUZZ Word Well known institute in real estate & developing situated maharashtra known as ‘’CREDAI’’ & our college gave us a golden apportunity to learn practical knowledge from credai’s site training programme. Our H.O.D. Mr. m.j. patil sir also played important role to arrange this proggramme. Our sir gave us Rajesh construction’s site at nagala park known as ‘cloud-9’ which was situated at behind the mahavir college to learn the practical site training . We join the site on 8th dec. 2010 at 9 a.m. First we observe the site ethusiasstically . Our site incharge Mr. Milind Magdum sir gave different work for different days including building line out , decision for plinth level , electrification , scafolding , formwork , central line plan , steel , column ,beam , stair-case ,plastering , slab casting . Mr. Milind sir gave information about various types of cost analysis including beam , column , slab , internal external plastering , painting ,door & window cost analysis etc. We collect the drawing of steel design from site incharge & learned total steel design in that we learned what is one way slab , two way slab , cantilever slab , extraa top & bottom , curt , stirrups & it’s spacing also column footing & their sizes , top & bottom bars in beam , main steel & distribution steel also how placed we learned . Next day we checked plinth level beam & slab at site . How plinth level is taken from road by using level tube teached by our site engg. For this we fixed one rod at road level & one rod on ground level . Plinth level are helpful for to avoid derbis entering from atmoshere , insects. Plinth level is also helpfull , to avoid water entering from rain in rainy season , & in flood situations . Next 3 days we spent in exibition of kolhapur’s real estate propertites which was arranged by credai & PBAK . In this exibition we learned about marketing of our constructed flats , bunglows , which facility are provided in our project , what are the saling rates of built up area , parking area , & other charges which are applicable to occupants . What is mean by salable area , carpet area , we learned at exibition . One day we spent for observing electificaion how it is carried out at site . For that we collect the electrification plan from site office , & observed the conceled wiring . For conceled wirring PVC pipes were fitted in steel before placing concrete . Another 2 days spent for observing casting of slab . In that we observed the placing , compacting , transporting , lifting & making of concrete . Casting of slab is very fast & instataneous process for which no. of workers are required for different process . Adequate amount of admixtures are also added in concrete while making it. For this overall construction M20 grade concrete was prepared . Other day we spent for observing construction of brick wall . At our projects generally 6 inch thickness of wall was provided. In this we also learned the various types of bonds used for constructing walls . After that we observed the plastering of walls internally & externally how it is carried out . Plastering is very important for better appearance & finishing . At our project site our construction firm is adopting steel form work instead of wooden form work & use of fly ash bricks were used . Which is very good example for enviorment caring. In this 12 days we learned how to manage the labours , which precaution to be taken in site. Our project owner Mr. Rajesh Adake also gave us very good guidence for project handling & management . Mr. Rajesh Adake were very helpful l & co-operative person . Thus we completed our 12 days programme of site traning under the guidence of site engg. Mr. Magadum sir .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr Milind Magadum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-12

Company Name Rajesh Constructions
Project Name & Site Address cloud-9
Students Name (Surname_First Name_Middle Name) LAD MANOJ S.
Exam No. 13534
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 :00 A.M.
Site Leaving Time (HH:MM am/pm) 4:00 P.M.
Details of the Work Allotted to you today by the Site In-Charge filling of column by concrete of M20 grade .
Details of how you Planned & Executed the allotted work first we checked proper erection of form-work by plumb bob. all the columns were at it is fixed position. then we marked the position up to where concrete has to be filled such way we filled 16 columns .
Details of the Construction Procedure / Activity / Technology learned today Mixing of M20 grade concrete with proper propotion .
Details of the Construction Materials learned today tiling of floors- vitrified tiles, marble granite , kota , shahabadi .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of electrical motor mixer - for this mixer electric motor is used to rotate the drum of making concrete so that it prevents environment by avoiding harmful smoke.
Details of the Construction / Engineering Drawings observed today column positions & footing drawing- slab dimension drawing.
Details of the Bye Laws referred today floor to floor height- min. height - 2.7m max. height- 3m
Details of any Managerial Skill learned today punctual , helpful , & skillful
RATE ANALYSIS (Detailed Stepwise Calculations required) for teak wood door= height= 8ft. width= 3 ft. total teak wood required for thk. of 5 inch X 3 inch = 1.785 cu.ft. cost of 1 cu. ft. teak wood = 1800 Rs. total cost of teak wood door = 1.785 X 1800 = 3000 Rs./ cu. ft.
Result of RATE ANALYSIS ( Rs per Unit ) 3000 Rs./ cu. ft.
Todays BUZZ Word Well known institute in real estate & developing situated maharashtra known as ‘’CREDAI’’ & our college gave us a golden apportunity to learn practical knowledge from credai’s site training programme. Our H.O.D. Mr. m.j. patil sir also played important role to arrange this proggramme. Our sir gave us Rajesh construction’s site at nagala park known as ‘cloud-9’ which was situated at behind the mahavir college to learn the practical site training . We join the site on 8th dec. 2010 at 9 a.m. First we observe the site ethusiasstically . Our site incharge Mr. Milind Magdum sir gave different work for different days including building line out , decision for plinth level , electrification , scafolding , formwork , central line plan , steel , column ,beam , stair-case ,plastering , slab casting . Mr. Milind sir gave information about various types of cost analysis including beam , column , slab , internal external plastering , painting ,door & window cost analysis etc. We collect the drawing of steel design from site incharge & learned total steel design in that we learned what is one way slab , two way slab , cantilever slab , extraa top & bottom , curt , stirrups & it’s spacing also column footing & their sizes , top & bottom bars in beam , main steel & distribution steel also how placed we learned . Next day we checked plinth level beam & slab at site . How plinth level is taken from road by using level tube teached by our site engg. For this we fixed one rod at road level & one rod on ground level . Plinth level are helpful for to avoid derbis entering from atmoshere , insects. Plinth level is also helpfull , to avoid water entering from rain in rainy season , & in flood situations . Next 3 days we spent in exibition of kolhapur’s real estate propertites which was arranged by credai & PBAK . In this exibition we learned about marketing of our constructed flats , bunglows , which facility are provided in our project , what are the saling rates of built up area , parking area , & other charges which are applicable to occupants . What is mean by salable area , carpet area , we learned at exibition . One day we spent for observing electificaion how it is carried out at site . For that we collect the electrification plan from site office , & observed the conceled wiring . For conceled wirring PVC pipes were fitted in steel before placing concrete . Another 2 days spent for observing casting of slab . In that we observed the placing , compacting , transporting , lifting & making of concrete . Casting of slab is very fast & instataneous process for which no. of workers are required for different process . Adequate amount of admixtures are also added in concrete while making it. For this overall construction M20 grade concrete was prepared . Other day we spent for observing construction of brick wall . At our projects generally 6 inch thickness of wall was provided. In this we also learned the various types of bonds used for constructing walls . After that we observed the plastering of walls internally & externally how it is carried out . Plastering is very important for better appearance & finishing . At our project site our construction firm is adopting steel form work instead of wooden form work & use of fly ash bricks were used . Which is very good example for enviorment caring. In this 12 days we learned how to manage the labours , which precaution to be taken in site. Our project owner Mr. Rajesh Adake also gave us very good guidence for project handling & management . Mr. Rajesh Adake were very helpful l & co-operative person . Thus we completed our 12 days programme of site traning under the guidence of site engg. Mr. Magadum sir .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr Milind Magadum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-12

Company Name Rajesh Constructions
Project Name & Site Address cloud-9
Students Name (Surname_First Name_Middle Name) KOLEKAR SHYAM S.
Exam No. 13533
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 :00 A.M.
Site Leaving Time (HH:MM am/pm) 4:00 P.M.
Details of the Work Allotted to you today by the Site In-Charge filling of column by concrete of M20 grade .
Details of how you Planned & Executed the allotted work first we checked proper erection of form-work by plumb bob. all the columns were at it is fixed position. then we marked the position up to where concrete has to be filled such way we filled 16 columns .
Details of the Construction Procedure / Activity / Technology learned today Mixing of M20 grade concrete with proper propotion .
Details of the Construction Materials learned today tiling of floors- vitrified tiles, marble granite , kota , shahabadi .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of electrical motor mixer - for this mixer electric motor is used to rotate the drum of making concrete so that it prevents environment by avoiding harmful smoke.
Details of the Construction / Engineering Drawings observed today column positions & footing drawing- slab dimension drawing.
Details of the Bye Laws referred today floor to floor height- min. height - 2.7m max. height- 3m
Details of any Managerial Skill learned today punctual , helpful , & skillful
RATE ANALYSIS (Detailed Stepwise Calculations required) for teak wood door= height= 8ft. width= 3 ft. total teak wood required for thk. of 5 inch X 3 inch = 1.785 cu.ft. cost of 1 cu. ft. teak wood = 1800 Rs. total cost of teak wood door = 1.785 X 1800 = 3000 Rs./ cu. ft.
Result of RATE ANALYSIS ( Rs per Unit ) 3000 Rs./ cu. ft.
Todays BUZZ Word Well known institute in real estate & developing situated maharashtra known as ‘’CREDAI’’ & our college gave us a golden apportunity to learn practical knowledge from credai’s site training programme. Our H.O.D. Mr. m.j. patil sir also played important role to arrange this proggramme. Our sir gave us Rajesh construction’s site at nagala park known as ‘cloud-9’ which was situated at behind the mahavir college to learn the practical site training . We join the site on 8th dec. 2010 at 9 a.m. First we observe the site ethusiasstically . Our site incharge Mr. Milind Magdum sir gave different work for different days including building line out , decision for plinth level , electrification , scafolding , formwork , central line plan , steel , column ,beam , stair-case ,plastering , slab casting . Mr. Milind sir gave information about various types of cost analysis including beam , column , slab , internal external plastering , painting ,door & window cost analysis etc. We collect the drawing of steel design from site incharge & learned total steel design in that we learned what is one way slab , two way slab , cantilever slab , extraa top & bottom , curt , stirrups & it’s spacing also column footing & their sizes , top & bottom bars in beam , main steel & distribution steel also how placed we learned . Next day we checked plinth level beam & slab at site . How plinth level is taken from road by using level tube teached by our site engg. For this we fixed one rod at road level & one rod on ground level . Plinth level are helpful for to avoid derbis entering from atmoshere , insects. Plinth level is also helpfull , to avoid water entering from rain in rainy season , & in flood situations . Next 3 days we spent in exibition of kolhapur’s real estate propertites which was arranged by credai & PBAK . In this exibition we learned about marketing of our constructed flats , bunglows , which facility are provided in our project , what are the saling rates of built up area , parking area , & other charges which are applicable to occupants . What is mean by salable area , carpet area , we learned at exibition . One day we spent for observing electificaion how it is carried out at site . For that we collect the electrification plan from site office , & observed the conceled wiring . For conceled wirring PVC pipes were fitted in steel before placing concrete . Another 2 days spent for observing casting of slab . In that we observed the placing , compacting , transporting , lifting & making of concrete . Casting of slab is very fast & instataneous process for which no. of workers are required for different process . Adequate amount of admixtures are also added in concrete while making it. For this overall construction M20 grade concrete was prepared . Other day we spent for observing construction of brick wall . At our projects generally 6 inch thickness of wall was provided. In this we also learned the various types of bonds used for constructing walls . After that we observed the plastering of walls internally & externally how it is carried out . Plastering is very important for better appearance & finishing . At our project site our construction firm is adopting steel form work instead of wooden form work & use of fly ash bricks were used . Which is very good example for enviorment caring. In this 12 days we learned how to manage the labours , which precaution to be taken in site. Our project owner Mr. Rajesh Adake also gave us very good guidence for project handling & management . Mr. Rajesh Adake were very helpful l & co-operative person . Thus we completed our 12 days programme of site traning under the guidence of site engg. Mr. Magadum sir .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr Milind Magadum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: rameshkharat1987@gmail.com
Subject: 13532-12

Company Name Rajesh Constructions
Project Name & Site Address cloud-9
Students Name (Surname_First Name_Middle Name) KHARAT RAMESH LAXMAN
Exam No. 13532
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 :00 A.M.
Site Leaving Time (HH:MM am/pm) 4:00 P.M.
Details of the Work Allotted to you today by the Site In-Charge filling of column by concrete of M20 grade .
Details of how you Planned & Executed the allotted work first we checked proper erection of form-work by plumb bob. all the columns were at it is fixed position. then we marked the position up to where concrete has to be filled such way we filled 16 columns .
Details of the Construction Procedure / Activity / Technology learned today Mixing of M20 grade concrete with proper propotion .
Details of the Construction Materials learned today tiling of floors- vitrified tiles, marble granite , kota , shahabadi .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of electrical motor mixer - for this mixer electric motor is used to rotate the drum of making concrete so that it prevents environment by avoiding harmful smoke.
Details of the Construction / Engineering Drawings observed today column positions & footing drawing- slab dimension drawing.
Details of the Bye Laws referred today floor to floor height- min. height - 2.7m max. height- 3m
Details of any Managerial Skill learned today punctual , helpful , & skillful
RATE ANALYSIS (Detailed Stepwise Calculations required) for teak wood door= height= 8ft. width= 3 ft. total teak wood required for thk. of 5 inch X 3 inch = 1.785 cu.ft. cost of 1 cu. ft. teak wood = 1800 Rs. total cost of teak wood door = 1.785 X 1800 = 3000 Rs./ cu. ft.
Result of RATE ANALYSIS ( Rs per Unit ) 3000 Rs./ cu. ft.
Todays BUZZ Word Well known institute in real estate & developing situated maharashtra known as ‘’CREDAI’’ & our college gave us a golden apportunity to learn practical knowledge from credai’s site training programme. Our H.O.D. Mr. m.j. patil sir also played important role to arrange this proggramme. Our sir gave us Rajesh construction’s site at nagala park known as ‘cloud-9’ which was situated at behind the mahavir college to learn the practical site training . We join the site on 8th dec. 2010 at 9 a.m. First we observe the site ethusiasstically . Our site incharge Mr. Milind Magdum sir gave different work for different days including building line out , decision for plinth level , electrification , scafolding , formwork , central line plan , steel , column ,beam , stair-case ,plastering , slab casting . Mr. Milind sir gave information about various types of cost analysis including beam , column , slab , internal external plastering , painting ,door & window cost analysis etc. We collect the drawing of steel design from site incharge & learned total steel design in that we learned what is one way slab , two way slab , cantilever slab , extraa top & bottom , curt , stirrups & it’s spacing also column footing & their sizes , top & bottom bars in beam , main steel & distribution steel also how placed we learned . Next day we checked plinth level beam & slab at site . How plinth level is taken from road by using level tube teached by our site engg. For this we fixed one rod at road level & one rod on ground level . Plinth level are helpful for to avoid derbis entering from atmoshere , insects. Plinth level is also helpfull , to avoid water entering from rain in rainy season , & in flood situations . Next 3 days we spent in exibition of kolhapur’s real estate propertites which was arranged by credai & PBAK . In this exibition we learned about marketing of our constructed flats , bunglows , which facility are provided in our project , what are the saling rates of built up area , parking area , & other charges which are applicable to occupants . What is mean by salable area , carpet area , we learned at exibition . One day we spent for observing electificaion how it is carried out at site . For that we collect the electrification plan from site office , & observed the conceled wiring . For conceled wirring PVC pipes were fitted in steel before placing concrete . Another 2 days spent for observing casting of slab . In that we observed the placing , compacting , transporting , lifting & making of concrete . Casting of slab is very fast & instataneous process for which no. of workers are required for different process . Adequate amount of admixtures are also added in concrete while making it. For this overall construction M20 grade concrete was prepared . Other day we spent for observing construction of brick wall . At our projects generally 6 inch thickness of wall was provided. In this we also learned the various types of bonds used for constructing walls . After that we observed the plastering of walls internally & externally how it is carried out . Plastering is very important for better appearance & finishing . At our project site our construction firm is adopting steel form work instead of wooden form work & use of fly ash bricks were used . Which is very good example for enviorment caring. In this 12 days we learned how to manage the labours , which precaution to be taken in site. Our project owner Mr. Rajesh Adake also gave us very good guidence for project handling & management . Mr. Rajesh Adake were very helpful l & co-operative person . Thus we completed our 12 days programme of site traning under the guidence of site engg. Mr. Magadum sir .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr Milind Magadum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: prasadkharat@ymail.com
Subject: 13531-12

Company Name Rajesh Constructions
Project Name & Site Address cloud-9
Students Name (Surname_First Name_Middle Name) KHARAT PRASAD R.
Exam No. 13531
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 :00 A.M.
Site Leaving Time (HH:MM am/pm) 4:00 P.M.
Details of the Work Allotted to you today by the Site In-Charge filling of column by concrete of M20 grade .
Details of how you Planned & Executed the allotted work first we checked proper erection of form-work by plumb bob. all the columns were at it is fixed position. then we marked the position up to where concrete has to be filled such way we filled 16 columns .
Details of the Construction Procedure / Activity / Technology learned today Mixing of M20 grade concrete with proper propotion .
Details of the Construction Materials learned today tiling of floors- vitrified tiles, marble granite , kota , shahabadi .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of electrical motor mixer - for this mixer electric motor is used to rotate the drum of making concrete so that it prevents environment by avoiding harmful smoke.
Details of the Construction / Engineering Drawings observed today column positions & footing drawing- slab dimension drawing.
Details of the Bye Laws referred today floor to floor height- min. height - 2.7m max. height- 3m
Details of any Managerial Skill learned today punctual , helpful , & skillful
RATE ANALYSIS (Detailed Stepwise Calculations required) for teak wood door= height= 8ft. width= 3 ft. total teak wood required for thk. of 5 inch X 3 inch = 1.785 cu.ft. cost of 1 cu. ft. teak wood = 1800 Rs. total cost of teak wood door = 1.785 X 1800 = 3000 Rs./ cu. ft.
Result of RATE ANALYSIS ( Rs per Unit ) 3000 Rs./ cu. ft.
Todays BUZZ Word Well known institute in real estate & developing situated maharashtra known as ‘’CREDAI’’ & our college gave us a golden apportunity to learn practical knowledge from credai’s site training programme. Our H.O.D. Mr. m.j. patil sir also played important role to arrange this proggramme. Our sir gave us Rajesh construction’s site at nagala park known as ‘cloud-9’ which was situated at behind the mahavir college to learn the practical site training . We join the site on 8th dec. 2010 at 9 a.m. First we observe the site ethusiasstically . Our site incharge Mr. Milind Magdum sir gave different work for different days including building line out , decision for plinth level , electrification , scafolding , formwork , central line plan , steel , column ,beam , stair-case ,plastering , slab casting . Mr. Milind sir gave information about various types of cost analysis including beam , column , slab , internal external plastering , painting ,door & window cost analysis etc. We collect the drawing of steel design from site incharge & learned total steel design in that we learned what is one way slab , two way slab , cantilever slab , extraa top & bottom , curt , stirrups & it’s spacing also column footing & their sizes , top & bottom bars in beam , main steel & distribution steel also how placed we learned . Next day we checked plinth level beam & slab at site . How plinth level is taken from road by using level tube teached by our site engg. For this we fixed one rod at road level & one rod on ground level . Plinth level are helpful for to avoid derbis entering from atmoshere , insects. Plinth level is also helpfull , to avoid water entering from rain in rainy season , & in flood situations . Next 3 days we spent in exibition of kolhapur’s real estate propertites which was arranged by credai & PBAK . In this exibition we learned about marketing of our constructed flats , bunglows , which facility are provided in our project , what are the saling rates of built up area , parking area , & other charges which are applicable to occupants . What is mean by salable area , carpet area , we learned at exibition . One day we spent for observing electificaion how it is carried out at site . For that we collect the electrification plan from site office , & observed the conceled wiring . For conceled wirring PVC pipes were fitted in steel before placing concrete . Another 2 days spent for observing casting of slab . In that we observed the placing , compacting , transporting , lifting & making of concrete . Casting of slab is very fast & instataneous process for which no. of workers are required for different process . Adequate amount of admixtures are also added in concrete while making it. For this overall construction M20 grade concrete was prepared . Other day we spent for observing construction of brick wall . At our projects generally 6 inch thickness of wall was provided. In this we also learned the various types of bonds used for constructing walls . After that we observed the plastering of walls internally & externally how it is carried out . Plastering is very important for better appearance & finishing . At our project site our construction firm is adopting steel form work instead of wooden form work & use of fly ash bricks were used . Which is very good example for enviorment caring. In this 12 days we learned how to manage the labours , which precaution to be taken in site. Our project owner Mr. Rajesh Adake also gave us very good guidence for project handling & management . Mr. Rajesh Adake were very helpful l & co-operative person . Thus we completed our 12 days programme of site traning under the guidence of site engg. Mr. Magadum sir .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr Milind Magadum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-12

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) PATIL ADITYA PANDURANG
Exam No. 13538
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE STEEL REINFORCEMENT WORK DONE FOR THE SLAB.
Details of how you Planned & Executed the allotted work WE FIRST COLLECTED THE STEEL DRAWINGS FROM THE SITE SUPERVISOR THEN WE STUDY THOSE DRAWINGS AND COLLECTED THE INFORMATION ABOUT THE CONTENT OF DRAWINGS.
Details of the Construction Procedure / Activity / Technology learned today WE LEARN ABOUT THE SLAB REINFORCEMENT WORK. THE BARS ARE BEND AT L/4 DISTANCE SO THAT THE SAGGING MOMENT OF SLAB IS RESTRICTED BY INCREASING THE C/S OF SLAB. IN BEAMS EXTRA TOP AND CURTLEMENT IS PROVIDED WHERE THE SHEAR FORCE IS MORE.
Details of the Construction Materials learned today NO NEW MATERIALS ARE LEARNED TODAY.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today STEEL DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3500 FORMICA-2 NO. = RS 1200 EACH = RS 2000 LINING PATTI- RS 6/FT.-20 FT = RS 120 MAPPING PATTI- RS 12/FT.- 30 FT. =RS 360 FEVICOL- RS 300/KG DOOR FRAME- RS 1800 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 9580 CONTRACTOR PROFIT= 15% = RS 1437 TOTAL COST= RS 11017
Result of RATE ANALYSIS ( Rs per Unit ) 11017 RS
Todays BUZZ Word * OWN SITE TRAING EXPERIENCE * WHEN 1ST TIME I WAS GONE ON THE SITE, I WAS VERY EXCITED TO KNOW THAT ON THE SITES ACTUALLY WHAT THE WORK IS GOING ON . THAT FEELING OF WORKING AS AN ENGINEER ON SITE IS VERY DIFFERENT. WHEN WE WENT ON THE SITE WE MET THE OWNER OF THE COMPANY “ MR. RAM PUROHIT “ SIR . HE IS VERY INTRESTING PERSON .HE TOLD US THAT THIS IS A GOLDEN OPPORTUNITY TO US TO KNOW ABOUT THE ACTUAL WORK ON THE SITE AND GETTING EXPERIENCE OF SITE. HE WERE ALLOTTED US THE WORK TO SEE THE WORK FOR SLAB. WHEN WE WENT ON THE SITE THERE WERE THE BAR BINDING FOR FIRST FLOOR SLAB WAS GOING ON. WE MET A WORKER , NAME IS “ SUJITKUMAR GUPTA” HE GUIDED US ABOUT THE SIZES OF BARS , HOW TO USE THE CHART GIVEN , HOW TO KNOW ABOUT THE POSITION OF BEAMS. HE TOLD US ABOUT THE ONE WAY SLAB , TWO WAY SLAB , MAIN BAR, DISTRIBUTION BAR , EXTRA TOP I. E. END SUPPORT AND CENTER SUPPORT, CURTAILMENT ETC. AFTER WARDS WE HAVE OBSERVED THE CONSTRUCTION OF WALL, HOW TO USE THE PLUMB BOB , WHAT IS THE PROPORTION OF CEMENT AND SAND IN MORTAR, WHAT IS THE RATE OF ONE BRASS WORK . WHAT IS THE PAYMENT OF THE WORKERS FOR ONE DAY. THEN WE MET TO THE R.C.C. CONTRACTOR. HE TOLD US ABOUT THE RATE OF R.C.C. CONSTRUCTION I.E. SLAB,BEAM,COLUMN. OUR SITE ENGINEER MR. UGAVE SIR HAS GUIDED US ABOUT THE LINE OUT OF THE BUILDING . OUR SITE INCHARGE MR. CHOUGALE SIR HAS GUIDED ABOUT THE PLANNING OF THE BUILDING . WE HAVE ENJOYED THE TRAINING WORKSHOP WE GET LOT OF KNOWLEDGE ABOUT THE CONSTRUCTION. ALONG WITH THE QUALITY OF TECHNICAL THINGS IT IS VERY IMPORTANT THAT HOW WILL YOU COMMUNICATE WITH THE CUSTOMERS . CIVIL ENGINEER SHOULD HAVE THIS KIND OF QUALITY WHICH WILL BE HELPFUL IN CUMMUNICATION WITH THE PEOPLE IN THE MARKETING WORLD.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-12

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudeo
Exam No. 10891
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the reticulated system of L.P.G. (Only for apartment).
Details of how you Planned & Executed the allotted work First we met Mr. Prasad Salvekar who is electronic engineer and discussed the entire working of gas system. And then we see the actual fitting of gas system.
Details of the Construction Procedure / Activity / Technology learned today -First no of flats & no of people in each flat are taken into consideration. -Then fittings of gas pipes for supply of gas into the flats is done according to design. -Each flat has only one gas supply connection & separate meter is provided to measure the consumption done by the occupant -Meter readings are taken at the end of every month & according to it charges is applied.
Details of the Construction Materials learned today Non return valve.: for avoiding the back flow of gas. C.I. pipe for transmission of gas. Gas meter.:for measuring the rate of consumption of gas by the consumer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Gardens are provided nearly in each bunglow.& in the club house.for maintaining good health of the people.
Details of the Construction / Engineering Drawings observed today Gas pipeline drawing.
Details of the Bye Laws referred today Provision of lift Planning & design –the planning & design of lifts including their no. ,type , and capacity.depending on the occupancy of the building, the population of each floor .
Details of any Managerial Skill learned today CO-Operation between site engineer ,site incharge,supervisors,& workers are very well
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: Assume frame size of door 3x7 sq.feet Particular : No. or Qt. Rate Cost Material Wood 4.655 c.f.t. 1300 6052/- Accessories Aldrop 1 200 200/- Hinges 4 20 80/- Handle 2 50 100/- Chain 1 50/- 50/- Lock 1 500/- 500/- Stooper 1 25/- 25/- Polish 200ml 250/- 250/- Labour Door fitter 1 500/- 500/- Polisher 1 300/- 300/- Total 8057/- Builders profit including Service tax , VAT etc 20% 9668.4Rs./- Rate per sq. ft. = 460.4Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 460.4Rs/-per sq. ft.
Todays BUZZ Word Todays buzz word-Your own Site training experience Our group name is ‘SANGHAVI ROCKSTARS’ Akshay Desai-group Leader Nitish Mohite Suchita Patil Yogesh Dalvi Parag Dhapodkar Above are the group members. Before our Sem-5 of T.E. Civil was being to be conducted or sir Mr.Imran pathan sir who teaches us the subject B.P.D. arranged program of winter site training for T.E. civil student for getting actual site information & site experience .according to it sir devided us into various groups . My group was SUNCITY ,which is constructed by Sanghavi builders & developers who are famous for construction & various other fields for last 120 years . My group contains 5 members whose names are mentioned are above .Our training program was from 8Th Dec. to 21St Dec. 2010. our Pathan Sir provided us with helmets for safety purpose and warned us wear always shoes so that there will not be any injury . Before actual training we contact Mr. Lalit Sanghavi the owner of Sanghavi Builders & Developers and told him about our training program . He gave us the contact no. of site incharge and site engineer & he also told that he will give instructions to them. We visited the Sun City on 8Th Dec. at 9.00a.m.. There was a security guard at the gate to whom we showed the letter given by our Pathan Sir. He noted down our names manually in the register . at 9.15a.m. security guard told us that to do voting in the voting cabin . We met that person and told him about our program .According to it he made a folder of voting for us so that there will be a computarized voting of our incoming and outgoing of the project gate. These was our daily routine. Till 9.30 to 10.00 a.m. site incharge Mr.Pritam Patil & site engineer Mr.Milind Patil were coming to the site for work . We met them & always asked them for to allow us some work to see the construction process of the project . Then at each day we were told for rate analysis of various items like P.C.C. , R.C.C. Column , Beam , Slab , Plastering , Painting , etc. According to that we met concerned persons & workers & took details about the work . During taking these information we noticed that there was much difference in the actual & practical knowledge .We were told during the lectures that proportion is to be maintained during work . But on actual site there was no any proportion maintained at all. During these site training program we learnt various construction materials like, steel , plastic, bricks , vetrified tiles , granite , marble, P.O.P, P.O.P sheets, Ace paints , tractor imulsion paints, plywood , sunmica, R.C.C. pipes , septic tank , lambi , paving blocks, concrete , sand, aggregate, cement , superplasticisers , aluminium, glass,boding chemicals, expansion joints , thermocol, roofing tiles , fabrication materials, etc. During the it raining program we met various contractors like plumbing , electrification , tile, painting, window, door, P.O.P. , fabrication , labour etc.& discussed with them how to fill the tender for getting a contract in brief & took information about the type of material used , method of work in these project .Sometimes everyone was getting more information during that time we discussed particular point within ourselves & we would like to ask the queries to concerned person or worker. During our site training program we also took various photographs so that we can remember for ever . By taking the permission of our site incharge & site engineer ,we also visited the nearby sites and we saw the pile foundation work, pressure pile, formwork,column casting plinth beam casting,filling , slab casting, preparation & arrangment of reinforcement for column , beam,slab etc. according to R.C.C. design.& also we discussed about the present rates of this material in the market. Durin this we also asked them various questions like why they used that particular material for the construction. They also responded us good . We enjoyed this training by taking various information . the site engineer ,site incharge, supervisor gave us their personal experience work information . At 3.00p.m. or site engineer Mr. milind patil was teaching us how to calculate the rate analysis of a particular construction items.We used this information for calculation of rate analysis . after some days we learnt some what how to calculate the rate analysis . according to it we calculated the rate analysis and we doing tally it .with that of calculated by our site engineer . it was coming to be some what near by but not accurate . in short some rough idea about calculation of rate analysis . There is a camera security system through which an eye is kept nearly at each and every bunglow . coman facilities provided are good like Wi-Fi connection for internet ,club house ,gymnasium ,temple , garden etc. 24 hours water supply is available . At the last day i.e. on 21st Dec.2010 they gave us an send off after 4.00 p.m. During the send off we cutted a Black Forest Cake & ate pups & also gave it to the some other important persons which we came across during our site training program & also took the photographs with them.And also we enjoyed the send off party . At the end of each day we took sign. And remarks of site incharge and site engineer in our work allotment sheet and at last day we also took the sign. Of the project owner. In this way we completed our winter site training program from 8th DEC to 21st Dec 2010 & took various information about construction & we also got much more actual site i.e. field experience . from this training we learnt that how to become a successful builder in construction by talking pleasantly with the contractors and workers . We have also launched our own group web site which is ‘http://sanghavirockstar.webs.com’ where we have downloaded our information & photos taken on the site.We have also got two times report of the day & twice pic. of day . We are thankful to you for giving site training program & we are hoping that in future you will conduct such site training programmes for us. And we will like that you will keep this group till B.E.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-12

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) JAGADALE ASHWINI RAMRAO
Exam No. 13530
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE STEEL REINFORCEMENT WORK DONE FOR THE SLAB.
Details of how you Planned & Executed the allotted work WE FIRST COLLECTED THE STEEL DRAWINGS FROM THE SITE SUPERVISOR THEN WE STUDY THOSE DRAWINGS AND COLLECTED THE INFORMATION ABOUT THE CONTENT OF DRAWINGS.
Details of the Construction Procedure / Activity / Technology learned today WE LEARN ABOUT THE SLAB REINFORCEMENT WORK. THE BARS ARE BEND AT L/4 DISTANCE SO THAT THE SAGGING MOMENT OF SLAB IS RESTRICTED BY INCREASING THE C/S OF SLAB. IN BEAMS EXTRA TOP AND CURTLEMENT IS PROVIDED WHERE THE SHEAR FORCE IS MORE.
Details of the Construction Materials learned today NO NEW MATERIALS ARE LEARNED TODAY.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today STEEL DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3500 FORMICA-2 NO. = RS 1200 EACH = RS 2000 LINING PATTI- RS 6/FT.-20 FT = RS 120 MAPPING PATTI- RS 12/FT.- 30 FT. =RS 360 FEVICOL- RS 300/KG DOOR FRAME- RS 1800 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 9580 CONTRACTOR PROFIT= 15% = RS 1437 TOTAL COST= RS 11017
Result of RATE ANALYSIS ( Rs per Unit ) 11017 RS
Todays BUZZ Word * OWN SITE TRAING EXPERIENCE * WHEN 1ST TIME I WAS GONE ON THE SITE, I WAS VERY EXCITED TO KNOW THAT ON THE SITES ACTUALLY WHAT THE WORK IS GOING ON . THAT FEELING OF WORKING AS AN ENGINEER ON SITE IS VERY DIFFERENT. WHEN WE WENT ON THE SITE WE MET THE OWNER OF THE COMPANY “ MR. RAM PUROHIT “ SIR . HE IS VERY INTRESTING PERSON .HE TOLD US THAT THIS IS A GOLDEN OPPORTUNITY TO US TO KNOW ABOUT THE ACTUAL WORK ON THE SITE AND GETTING EXPERIENCE OF SITE. HE WERE ALLOTTED US THE WORK TO SEE THE WORK FOR SLAB. WHEN WE WENT ON THE SITE THERE WERE THE BAR BINDING FOR FIRST FLOOR SLAB WAS GOING ON. WE MET A WORKER , NAME IS “ SUJITKUMAR GUPTA” HE GUIDED US ABOUT THE SIZES OF BARS , HOW TO USE THE CHART GIVEN , HOW TO KNOW ABOUT THE POSITION OF BEAMS. HE TOLD US ABOUT THE ONE WAY SLAB , TWO WAY SLAB , MAIN BAR, DISTRIBUTION BAR , EXTRA TOP I. E. END SUPPORT AND CENTER SUPPORT, CURTAILMENT ETC. AFTER WARDS WE HAVE OBSERVED THE CONSTRUCTION OF WALL, HOW TO USE THE PLUMB BOB , WHAT IS THE PROPORTION OF CEMENT AND SAND IN MORTAR, WHAT IS THE RATE OF ONE BRASS WORK . WHAT IS THE PAYMENT OF THE WORKERS FOR ONE DAY. THEN WE MET TO THE R.C.C. CONTRACTOR. HE TOLD US ABOUT THE RATE OF R.C.C. CONSTRUCTION I.E. SLAB,BEAM,COLUMN. OUR SITE ENGINEER MR. UGAVE SIR HAS GUIDED US ABOUT THE LINE OUT OF THE BUILDING . OUR SITE INCHARGE MR. CHOUGALE SIR HAS GUIDED ABOUT THE PLANNING OF THE BUILDING . WE HAVE ENJOYED THE TRAINING WORKSHOP WE GET LOT OF KNOWLEDGE ABOUT THE CONSTRUCTION ALONG WITH THE QUALITY OF TECHNICAL THINGS IT IS VERY IMPORTANT THAT HOW WILL YOU COMMUNICATE WITH THE CUSTOMERS . CIVIL ENGINEER SHOULD HAVE THIS KIND OF QUALITY WHICH WILL BE HELPFUL IN CUMMUNICATION WITH THE PEOPLE IN THE MARKETING WORLD.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-12

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the reticulated system of L.P.G. (Only for apartment).
Details of how you Planned & Executed the allotted work First we met Mr. Prasad Salvekar who is electronic engineer and discussed the entire working of gas system. And then we see the actual fitting of gas system.
Details of the Construction Procedure / Activity / Technology learned today -First no of flats & no of people in each flat are taken into consideration. -Then fittings of gas pipes for supply of gas into the flats is done according to design. -Each flat has only one gas supply connection & separate meter is provided to measure the consumption done by the occupant -Meter readings are taken at the end of every month & according to it charges is applied.
Details of the Construction Materials learned today Non return valve.: for avoiding the back flow of gas. C.I. pipe for transmission of gas. Gas meter.:for measuring the rate of consumption of gas by the consumer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Gardens are provided nearly in each bunglow.& in the club house.for maintaining good health of the people.
Details of the Construction / Engineering Drawings observed today Gas pipeline drawing.
Details of the Bye Laws referred today Provision of lift Planning & design –the planning & design of lifts including their no. ,type , and capacity.depending on the occupancy of the building, the population of each floor .
Details of any Managerial Skill learned today CO-Operation between site engineer ,site incharge,supervisors,& workers are very well
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: Assume frame size of door 3x7 sq.feet Particular : No. or Qt. Rate Cost Material Wood 4.655 c.f.t. 1300 6052/- Accessories Aldrop 1 200 200/- Hinges 4 20 80/- Handle 2 50 100/- Chain 1 50/- 50/- Lock 1 500/- 500/- Stooper 1 25/- 25/- Polish 200ml 250/- 250/- Labour Door fitter 1 500/- 500/- Polisher 1 300/- 300/- Total 8057/- Builders profit including Service tax , VAT etc 20% 9668.4Rs./- Rate per sq. ft. = 460.4Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 460.4Rs/-per sq. ft.
Todays BUZZ Word Todays buzz word-Your own Site training experience Our group name is ‘SANGHAVI ROCKSTARS’ Akshay Desai-group Leader Nitish Mohite Suchita Patil Yogesh Dalvi Parag Dhapodkar Above are the group members. Before our Sem-5 of T.E. Civil was being to be conducted or sir Mr.Imran pathan sir who teaches us the subject B.P.D. arranged program of winter site training for T.E. civil student for getting actual site information & site experience .according to it sir devided us into various groups . My group was SUNCITY ,which is constructed by Sanghavi builders & developers who are famous for construction & various other fields for last 120 years . My group contains 5 members whose names are mentioned are above .Our training program was from 8Th Dec. to 21St Dec. 2010. our Pathan Sir provided us with helmets for safety purpose and warned us wear always shoes so that there will not be any injury . Before actual training we contact Mr. Lalit Sanghavi the owner of Sanghavi Builders & Developers and told him about our training program . He gave us the contact no. of site incharge and site engineer & he also told that he will give instructions to them. We visited the Sun City on 8Th Dec. at 9.00a.m.. There was a security guard at the gate to whom we showed the letter given by our Pathan Sir. He noted down our names manually in the register . at 9.15a.m. security guard told us that to do voting in the voting cabin . We met that person and told him about our program .According to it he made a folder of voting for us so that there will be a computarized voting of our incoming and outgoing of the project gate. These was our daily routine. Till 9.30 to 10.00 a.m. site incharge Mr.Pritam Patil & site engineer Mr.Milind Patil were coming to the site for work . We met them & always asked them for to allow us some work to see the construction process of the project . Then at each day we were told for rate analysis of various items like P.C.C. , R.C.C. Column , Beam , Slab , Plastering , Painting , etc. According to that we met concerned persons & workers & took details about the work . During taking these information we noticed that there was much difference in the actual & practical knowledge .We were told during the lectures that proportion is to be maintained during work . But on actual site there was no any proportion maintained at all. During these site training program we learnt various construction materials like, steel , plastic, bricks , vetrified tiles , granite , marble, P.O.P, P.O.P sheets, Ace paints , tractor imulsion paints, plywood , sunmica, R.C.C. pipes , septic tank , lambi , paving blocks, concrete , sand, aggregate, cement , superplasticisers , aluminium, glass,boding chemicals, expansion joints , thermocol, roofing tiles , fabrication materials, etc. During the it raining program we met various contractors like plumbing , electrification , tile, painting, window, door, P.O.P. , fabrication , labour etc.& discussed with them how to fill the tender for getting a contract in brief & took information about the type of material used , method of work in these project .Sometimes everyone was getting more information during that time we discussed particular point within ourselves & we would like to ask the queries to concerned person or worker. During our site training program we also took various photographs so that we can remember for ever . By taking the permission of our site incharge & site engineer ,we also visited the nearby sites and we saw the pile foundation work, pressure pile, formwork,column casting plinth beam casting,filling , slab casting, preparation & arrangment of reinforcement for column , beam,slab etc. according to R.C.C. design.& also we discussed about the present rates of this material in the market. Durin this we also asked them various questions like why they used that particular material for the construction. They also responded us good . We enjoyed this training by taking various information . the site engineer ,site incharge, supervisor gave us their personal experience work information . At 3.00p.m. or site engineer Mr. milind patil was teaching us how to calculate the rate analysis of a particular construction items.We used this information for calculation of rate analysis . after some days we learnt some what how to calculate the rate analysis . according to it we calculated the rate analysis and we doing tally it .with that of calculated by our site engineer . it was coming to be some what near by but not accurate . in short some rough idea about calculation of rate analysis . There is a camera security system through which an eye is kept nearly at each and every bunglow . coman facilities provided are good like Wi-Fi connection for internet ,club house ,gymnasium ,temple , garden etc. 24 hours water supply is available . At the last day i.e. on 21st Dec.2010 they gave us an send off after 4.00 p.m. During the send off we cutted a Black Forest Cake & ate pups & also gave it to the some other important persons which we came across during our site training program & also took the photographs with them.And also we enjoyed the send off party . At the end of each day we took sign. And remarks of site incharge and site engineer in our work allotment sheet and at last day we also took the sign. Of the project owner. In this way we completed our winter site training program from 8th DEC to 21st Dec 2010 & took various information about construction & we also got much more actual site i.e. field experience . from this training we learnt that how to become a successful builder in construction by talking pleasantly with the contractors and workers . We have also launched our own group web site which is ‘http://sanghavirockstar.webs.com’ where we have downloaded our information & photos taken on the site.We have also got two times report of the day & twice pic. of day . We are thankful to you for giving site training program & we are hoping that in future you will conduct such site training programmes for us. And we will like that you will keep this group till B.E.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-12

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the reticulated system of L.P.G. (Only for apartment).
Details of how you Planned & Executed the allotted work First we met Mr. Prasad Salvekar who is electronic engineer and discussed the entire working of gas system. And then we see the actual fitting of gas system.
Details of the Construction Procedure / Activity / Technology learned today -First no of flats & no of people in each flat are taken into consideration. -Then fittings of gas pipes for supply of gas into the flats is done according to design. -Each flat has only one gas supply connection & separate meter is provided to measure the consumption done by the occupant -Meter readings are taken at the end of every month & according to it charges is applied.
Details of the Construction Materials learned today Non return valve.: for avoiding the back flow of gas. C.I. pipe for transmission of gas. Gas meter.:for measuring the rate of consumption of gas by the consumer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Gardens are provided nearly in each bunglow.& in the club house.for maintaining good health of the people.
Details of the Construction / Engineering Drawings observed today Gas pipeline drawing.
Details of the Bye Laws referred today Provision of lift Planning & design –the planning & design of lifts including their no. ,type , and capacity.depending on the occupancy of the building, the population of each floor .
Details of any Managerial Skill learned today CO-Operation between site engineer ,site incharge,supervisors,& workers are very well
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: Assume frame size of door 3x7 sq.feet Particular : No. or Qt. Rate Cost Material Wood 4.655 c.f.t. 1300 6052/- Accessories Aldrop 1 200 200/- Hinges 4 20 80/- Handle 2 50 100/- Chain 1 50/- 50/- Lock 1 500/- 500/- Stooper 1 25/- 25/- Polish 200ml 250/- 250/- Labour Door fitter 1 500/- 500/- Polisher 1 300/- 300/- Total 8057/- Builders profit including Service tax , VAT etc 20% 9668.4Rs./- Rate per sq. ft. = 460.4Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 460.4Rs/-per sq. ft.
Todays BUZZ Word Todays buzz word-Your own Site training experience Our group name is ‘SANGHAVI ROCKSTARS’ Akshay Desai-group Leader Nitish Mohite Suchita Patil Yogesh Dalvi Parag Dhapodkar Above are the group members. Before our Sem-5 of T.E. Civil was being to be conducted or sir Mr.Imran pathan sir who teaches us the subject B.P.D. arranged program of winter site training for T.E. civil student for getting actual site information & site experience .according to it sir devided us into various groups . My group was SUNCITY ,which is constructed by Sanghavi builders & developers who are famous for construction & various other fields for last 120 years . My group contains 5 members whose names are mentioned are above .Our training program was from 8Th Dec. to 21St Dec. 2010. our Pathan Sir provided us with helmets for safety purpose and warned us wear always shoes so that there will not be any injury . Before actual training we contact Mr. Lalit Sanghavi the owner of Sanghavi Builders & Developers and told him about our training program . He gave us the contact no. of site incharge and site engineer & he also told that he will give instructions to them. We visited the Sun City on 8Th Dec. at 9.00a.m.. There was a security guard at the gate to whom we showed the letter given by our Pathan Sir. He noted down our names manually in the register . at 9.15a.m. security guard told us that to do voting in the voting cabin . We met that person and told him about our program .According to it he made a folder of voting for us so that there will be a computarized voting of our incoming and outgoing of the project gate. These was our daily routine. Till 9.30 to 10.00 a.m. site incharge Mr.Pritam Patil & site engineer Mr.Milind Patil were coming to the site for work . We met them & always asked them for to allow us some work to see the construction process of the project . Then at each day we were told for rate analysis of various items like P.C.C. , R.C.C. Column , Beam , Slab , Plastering , Painting , etc. According to that we met concerned persons & workers & took details about the work . During taking these information we noticed that there was much difference in the actual & practical knowledge .We were told during the lectures that proportion is to be maintained during work . But on actual site there was no any proportion maintained at all. During these site training program we learnt various construction materials like, steel , plastic, bricks , vetrified tiles , granite , marble, P.O.P, P.O.P sheets, Ace paints , tractor imulsion paints, plywood , sunmica, R.C.C. pipes , septic tank , lambi , paving blocks, concrete , sand, aggregate, cement , superplasticisers , aluminium, glass,boding chemicals, expansion joints , thermocol, roofing tiles , fabrication materials, etc. During the it raining program we met various contractors like plumbing , electrification , tile, painting, window, door, P.O.P. , fabrication , labour etc.& discussed with them how to fill the tender for getting a contract in brief & took information about the type of material used , method of work in these project .Sometimes everyone was getting more information during that time we discussed particular point within ourselves & we would like to ask the queries to concerned person or worker. During our site training program we also took various photographs so that we can remember for ever . By taking the permission of our site incharge & site engineer ,we also visited the nearby sites and we saw the pile foundation work, pressure pile, formwork,column casting plinth beam casting,filling , slab casting, preparation & arrangment of reinforcement for column , beam,slab etc. according to R.C.C. design.& also we discussed about the present rates of this material in the market. Durin this we also asked them various questions like why they used that particular material for the construction. They also responded us good . We enjoyed this training by taking various information . the site engineer ,site incharge, supervisor gave us their personal experience work information . At 3.00p.m. or site engineer Mr. milind patil was teaching us how to calculate the rate analysis of a particular construction items.We used this information for calculation of rate analysis . after some days we learnt some what how to calculate the rate analysis . according to it we calculated the rate analysis and we doing tally it .with that of calculated by our site engineer . it was coming to be some what near by but not accurate . in short some rough idea about calculation of rate analysis . There is a camera security system through which an eye is kept nearly at each and every bunglow . coman facilities provided are good like Wi-Fi connection for internet ,club house ,gymnasium ,temple , garden etc. 24 hours water supply is available . At the last day i.e. on 21st Dec.2010 they gave us an send off after 4.00 p.m. During the send off we cutted a Black Forest Cake & ate pups & also gave it to the some other important persons which we came across during our site training program & also took the photographs with them.And also we enjoyed the send off party . At the end of each day we took sign. And remarks of site incharge and site engineer in our work allotment sheet and at last day we also took the sign. Of the project owner. In this way we completed our winter site training program from 8th DEC to 21st Dec 2010 & took various information about construction & we also got much more actual site i.e. field experience . from this training we learnt that how to become a successful builder in construction by talking pleasantly with the contractors and workers . We have also launched our own group web site which is ‘http://sanghavirockstar.webs.com’ where we have downloaded our information & photos taken on the site.We have also got two times report of the day & twice pic. of day . We are thankful to you for giving site training program & we are hoping that in future you will conduct such site training programmes for us. And we will like that you will keep this group till B.E.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-12

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the reticulated system of L.P.G. (Only for apartment).
Details of how you Planned & Executed the allotted work First we met Mr. Prasad Salvekar who is electronic engineer and discussed the entire working of gas system. And then we see the actual fitting of gas system.
Details of the Construction Procedure / Activity / Technology learned today -First no of flats & no of people in each flat are taken into consideration. -Then fittings of gas pipes for supply of gas into the flats is done according to design. -Each flat has only one gas supply connection & separate meter is provided to measure the consumption done by the occupant -Meter readings are taken at the end of every month & according to it charges is applied.
Details of the Construction Materials learned today Non return valve.: for avoiding the back flow of gas. C.I. pipe for transmission of gas. Gas meter.:for measuring the rate of consumption of gas by the consumer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Gardens are provided nearly in each bunglow.& in the club house.for maintaining good health of the people.
Details of the Construction / Engineering Drawings observed today Gas pipeline drawing.
Details of the Bye Laws referred today Provision of lift Planning & design –the planning & design of lifts including their no. ,type , and capacity.depending on the occupancy of the building, the population of each floor .
Details of any Managerial Skill learned today CO-Operation between site engineer ,site incharge,supervisors,& workers are very well
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: Assume frame size of door 3x7 sq.feet Particular : No. or Qt. Rate Cost Material Wood 4.655 c.f.t. 1300 6052/- Accessories Aldrop 1 200 200/- Hinges 4 20 80/- Handle 2 50 100/- Chain 1 50/- 50/- Lock 1 500/- 500/- Stooper 1 25/- 25/- Polish 200ml 250/- 250/- Labour Door fitter 1 500/- 500/- Polisher 1 300/- 300/- Total 8057/- Builders profit including Service tax , VAT etc 20% 9668.4Rs./- Rate per sq. ft. = 460.4Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 460.4Rs/-per sq. ft.
Todays BUZZ Word Todays buzz word-Your own Site training experience Our group name is ‘SANGHAVI ROCKSTARS’ Akshay Desai-group Leader Nitish Mohite Suchita Patil Yogesh Dalvi Parag Dhapodkar Above are the group members. Before our Sem-5 of T.E. Civil was being to be conducted or sir Mr.Imran pathan sir who teaches us the subject B.P.D. arranged program of winter site training for T.E. civil student for getting actual site information & site experience .according to it sir devided us into various groups . My group was SUNCITY ,which is constructed by Sanghavi builders & developers who are famous for construction & various other fields for last 120 years . My group contains 5 members whose names are mentioned are above .Our training program was from 8Th Dec. to 21St Dec. 2010. our Pathan Sir provided us with helmets for safety purpose and warned us wear always shoes so that there will not be any injury . Before actual training we contact Mr. Lalit Sanghavi the owner of Sanghavi Builders & Developers and told him about our training program . He gave us the contact no. of site incharge and site engineer & he also told that he will give instructions to them. We visited the Sun City on 8Th Dec. at 9.00a.m.. There was a security guard at the gate to whom we showed the letter given by our Pathan Sir. He noted down our names manually in the register . at 9.15a.m. security guard told us that to do voting in the voting cabin . We met that person and told him about our program .According to it he made a folder of voting for us so that there will be a computarized voting of our incoming and outgoing of the project gate. These was our daily routine. Till 9.30 to 10.00 a.m. site incharge Mr.Pritam Patil & site engineer Mr.Milind Patil were coming to the site for work . We met them & always asked them for to allow us some work to see the construction process of the project . Then at each day we were told for rate analysis of various items like P.C.C. , R.C.C. Column , Beam , Slab , Plastering , Painting , etc. According to that we met concerned persons & workers & took details about the work . During taking these information we noticed that there was much difference in the actual & practical knowledge .We were told during the lectures that proportion is to be maintained during work . But on actual site there was no any proportion maintained at all. During these site training program we learnt various construction materials like, steel , plastic, bricks , vetrified tiles , granite , marble, P.O.P, P.O.P sheets, Ace paints , tractor imulsion paints, plywood , sunmica, R.C.C. pipes , septic tank , lambi , paving blocks, concrete , sand, aggregate, cement , superplasticisers , aluminium, glass,boding chemicals, expansion joints , thermocol, roofing tiles , fabrication materials, etc. During the it raining program we met various contractors like plumbing , electrification , tile, painting, window, door, P.O.P. , fabrication , labour etc.& discussed with them how to fill the tender for getting a contract in brief & took information about the type of material used , method of work in these project .Sometimes everyone was getting more information during that time we discussed particular point within ourselves & we would like to ask the queries to concerned person or worker. During our site training program we also took various photographs so that we can remember for ever . By taking the permission of our site incharge & site engineer ,we also visited the nearby sites and we saw the pile foundation work, pressure pile, formwork,column casting plinth beam casting,filling , slab casting, preparation & arrangment of reinforcement for column , beam,slab etc. according to R.C.C. design.& also we discussed about the present rates of this material in the market. Durin this we also asked them various questions like why they used that particular material for the construction. They also responded us good . We enjoyed this training by taking various information . the site engineer ,site incharge, supervisor gave us their personal experience work information . At 3.00p.m. or site engineer Mr. milind patil was teaching us how to calculate the rate analysis of a particular construction items.We used this information for calculation of rate analysis . after some days we learnt some what how to calculate the rate analysis . according to it we calculated the rate analysis and we doing tally it .with that of calculated by our site engineer . it was coming to be some what near by but not accurate . in short some rough idea about calculation of rate analysis . There is a camera security system through which an eye is kept nearly at each and every bunglow . coman facilities provided are good like Wi-Fi connection for internet ,club house ,gymnasium ,temple , garden etc. 24 hours water supply is available . At the last day i.e. on 21st Dec.2010 they gave us an send off after 4.00 p.m. During the send off we cutted a Black Forest Cake & ate pups & also gave it to the some other important persons which we came across during our site training program & also took the photographs with them.And also we enjoyed the send off party . At the end of each day we took sign. And remarks of site incharge and site engineer in our work allotment sheet and at last day we also took the sign. Of the project owner. In this way we completed our winter site training program from 8th DEC to 21st Dec 2010 & took various information about construction & we also got much more actual site i.e. field experience . from this training we learnt that how to become a successful builder in construction by talking pleasantly with the contractors and workers . We have also launched our own group web site which is ‘http://sanghavirockstar.webs.com’ where we have downloaded our information & photos taken on the site.We have also got two times report of the day & twice pic. of day . We are thankful to you for giving site training program & we are hoping that in future you will conduct such site training programmes for us. And we will like that you will keep this group till B.E.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-12

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the reticulated system of L.P.G. (Only for apartment).
Details of how you Planned & Executed the allotted work First we met Mr. Prasad Salvekar who is electronic engineer and discussed the entire working of gas system. And then we see the actual fitting of gas system.
Details of the Construction Procedure / Activity / Technology learned today -First no of flats & no of people in each flat are taken into consideration. -Then fittings of gas pipes for supply of gas into the flats is done according to design. -Each flat has only one gas supply connection & separate meter is provided to measure the consumption done by the occupant -Meter readings are taken at the end of every month & according to it charges is applied.
Details of the Construction Materials learned today Non return valve.: for avoiding the back flow of gas. C.I. pipe for transmission of gas. Gas meter.:for measuring the rate of consumption of gas by the consumer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Gardens are provided nearly in each bunglow.& in the club house.for maintaining good health of the people.
Details of the Construction / Engineering Drawings observed today Gas pipeline drawing.
Details of the Bye Laws referred today Provision of lift Planning & design –the planning & design of lifts including their no. ,type , and capacity.depending on the occupancy of the building, the population of each floor .
Details of any Managerial Skill learned today CO-Operation between site engineer ,site incharge,supervisors,& workers are very well
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: Assume frame size of door 3x7 sq.feet Particular : No. or Qt. Rate Cost Material Wood 4.655 c.f.t. 1300 6052/- Accessories Aldrop 1 200 200/- Hinges 4 20 80/- Handle 2 50 100/- Chain 1 50/- 50/- Lock 1 500/- 500/- Stooper 1 25/- 25/- Polish 200ml 250/- 250/- Labour Door fitter 1 500/- 500/- Polisher 1 300/- 300/- Total 8057/- Builders profit including Service tax , VAT etc 20% 9668.4Rs./- Rate per sq. ft. = 460.4Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 460.4Rs/-per sq. ft.
Todays BUZZ Word Todays buzz word-Your own Site training experience Our group name is ‘SANGHAVI ROCKSTARS’ Akshay Desai-group Leader Nitish Mohite Suchita Patil Yogesh Dalvi Parag Dhapodkar Above are the group members. Before our Sem-5 of T.E. Civil was being to be conducted or sir Mr.Imran pathan sir who teaches us the subject B.P.D. arranged program of winter site training for T.E. civil student for getting actual site information & site experience .according to it sir devided us into various groups . My group was SUNCITY ,which is constructed by Sanghavi builders & developers who are famous for construction & various other fields for last 120 years . My group contains 5 members whose names are mentioned are above .Our training program was from 8Th Dec. to 21St Dec. 2010. our Pathan Sir provided us with helmets for safety purpose and warned us wear always shoes so that there will not be any injury . Before actual training we contact Mr. Lalit Sanghavi the owner of Sanghavi Builders & Developers and told him about our training program . He gave us the contact no. of site incharge and site engineer & he also told that he will give instructions to them. We visited the Sun City on 8Th Dec. at 9.00a.m.. There was a security guard at the gate to whom we showed the letter given by our Pathan Sir. He noted down our names manually in the register . at 9.15a.m. security guard told us that to do voting in the voting cabin . We met that person and told him about our program .According to it he made a folder of voting for us so that there will be a computarized voting of our incoming and outgoing of the project gate. These was our daily routine. Till 9.30 to 10.00 a.m. site incharge Mr.Pritam Patil & site engineer Mr.Milind Patil were coming to the site for work . We met them & always asked them for to allow us some work to see the construction process of the project . Then at each day we were told for rate analysis of various items like P.C.C. , R.C.C. Column , Beam , Slab , Plastering , Painting , etc. According to that we met concerned persons & workers & took details about the work . During taking these information we noticed that there was much difference in the actual & practical knowledge .We were told during the lectures that proportion is to be maintained during work . But on actual site there was no any proportion maintained at all. During these site training program we learnt various construction materials like, steel , plastic, bricks , vetrified tiles , granite , marble, P.O.P, P.O.P sheets, Ace paints , tractor imulsion paints, plywood , sunmica, R.C.C. pipes , septic tank , lambi , paving blocks, concrete , sand, aggregate, cement , superplasticisers , aluminium, glass,boding chemicals, expansion joints , thermocol, roofing tiles , fabrication materials, etc. During the it raining program we met various contractors like plumbing , electrification , tile, painting, window, door, P.O.P. , fabrication , labour etc.& discussed with them how to fill the tender for getting a contract in brief & took information about the type of material used , method of work in these project .Sometimes everyone was getting more information during that time we discussed particular point within ourselves & we would like to ask the queries to concerned person or worker. During our site training program we also took various photographs so that we can remember for ever . By taking the permission of our site incharge & site engineer ,we also visited the nearby sites and we saw the pile foundation work, pressure pile, formwork,column casting plinth beam casting,filling , slab casting, preparation & arrangment of reinforcement for column , beam,slab etc. according to R.C.C. design.& also we discussed about the present rates of this material in the market. Durin this we also asked them various questions like why they used that particular material for the construction. They also responded us good . We enjoyed this training by taking various information . the site engineer ,site incharge, supervisor gave us their personal experience work information . At 3.00p.m. or site engineer Mr. milind patil was teaching us how to calculate the rate analysis of a particular construction items.We used this information for calculation of rate analysis . after some days we learnt some what how to calculate the rate analysis . according to it we calculated the rate analysis and we doing tally it .with that of calculated by our site engineer . it was coming to be some what near by but not accurate . in short some rough idea about calculation of rate analysis . There is a camera security system through which an eye is kept nearly at each and every bunglow . coman facilities provided are good like Wi-Fi connection for internet ,club house ,gymnasium ,temple , garden etc. 24 hours water supply is available . At the last day i.e. on 21st Dec.2010 they gave us an send off after 4.00 p.m. During the send off we cutted a Black Forest Cake & ate pups & also gave it to the some other important persons which we came across during our site training program & also took the photographs with them.And also we enjoyed the send off party . At the end of each day we took sign. And remarks of site incharge and site engineer in our work allotment sheet and at last day we also took the sign. Of the project owner. In this way we completed our winter site training program from 8th DEC to 21st Dec 2010 & took various information about construction & we also got much more actual site i.e. field experience . from this training we learnt that how to become a successful builder in construction by talking pleasantly with the contractors and workers . We have also launched our own group web site which is ‘http://sanghavirockstar.webs.com’ where we have downloaded our information & photos taken on the site.We have also got two times report of the day & twice pic. of day . We are thankful to you for giving site training program & we are hoping that in future you will conduct such site training programmes for us. And we will like that you will keep this group till B.E.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-12

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudeo
Exam No. 10891
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the reticulated system of L.P.G. (Only for apartment).
Details of how you Planned & Executed the allotted work First we met Mr. Prasad Salvekar who is electronic engineer and discussed the entire working of gas system. And then we see the actual fitting of gas system.
Details of the Construction Procedure / Activity / Technology learned today -First no of flats & no of people in each flat are taken into consideration. -Then fittings of gas pipes for supply of gas into the flats is done according to design. -Each flat has only one gas supply connection & separate meter is provided to measure the consumption done by the occupant -Meter readings are taken at the end of every month & according to it charges is applied.
Details of the Construction Materials learned today Non return valve.: for avoiding the back flow of gas. C.I. pipe for transmission of gas. Gas meter.:for measuring the rate of consumption of gas by the consumer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Gardens are provided nearly in each bunglow.& in the club house.for maintaining good health of the people.
Details of the Construction / Engineering Drawings observed today Gas pipeline drawing.
Details of the Bye Laws referred today Provision of lift Planning & design –the planning & design of lifts including their no. ,type , and capacity.depending on the occupancy of the building, the population of each floor .
Details of any Managerial Skill learned today CO-Operation between site engineer ,site incharge,supervisors,& workers are very well
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: Assume frame size of door 3x7 sq.feet Particular : No. or Qt. Rate Cost Material Wood 4.655 c.f.t. 1300 6052/- Accessories Aldrop 1 200 200/- Hinges 4 20 80/- Handle 2 50 100/- Chain 1 50/- 50/- Lock 1 500/- 500/- Stooper 1 25/- 25/- Polish 200ml 250/- 250/- Labour Door fitter 1 500/- 500/- Polisher 1 300/- 300/- Total 8057/- Builders profit including Service tax , VAT etc 20% 9668.4Rs./- Rate per sq. ft. = 460.4Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 460.4Rs/-per sq. ft.
Todays BUZZ Word Todays buzz word-Your own Site training experience Our group name is ‘SANGHAVI ROCKSTARS’ Akshay Desai-group Leader Nitish Mohite Suchita Patil Yogesh Dalvi Parag Dhapodkar Above are the group members. Before our Sem-5 of T.E. Civil was being to be conducted or sir Mr.Imran pathan sir who teaches us the subject B.P.D. arranged program of winter site training for T.E. civil student for getting actual site information & site experience .according to it sir devided us into various groups . My group was SUNCITY ,which is constructed by Sanghavi builders & developers who are famous for construction & various other fields for last 120 years . My group contains 5 members whose names are mentioned are above .Our training program was from 8Th Dec. to 21St Dec. 2010. our Pathan Sir provided us with helmets for safety purpose and warned us wear always shoes so that there will not be any injury . Before actual training we contact Mr. Lalit Sanghavi the owner of Sanghavi Builders & Developers and told him about our training program . He gave us the contact no. of site incharge and site engineer & he also told that he will give instructions to them. We visited the Sun City on 8Th Dec. at 9.00a.m.. There was a security guard at the gate to whom we showed the letter given by our Pathan Sir. He noted down our names manually in the register . at 9.15a.m. security guard told us that to do voting in the voting cabin . We met that person and told him about our program .According to it he made a folder of voting for us so that there will be a computarized voting of our incoming and outgoing of the project gate. These was our daily routine. Till 9.30 to 10.00 a.m. site incharge Mr.Pritam Patil & site engineer Mr.Milind Patil were coming to the site for work . We met them & always asked them for to allow us some work to see the construction process of the project . Then at each day we were told for rate analysis of various items like P.C.C. , R.C.C. Column , Beam , Slab , Plastering , Painting , etc. According to that we met concerned persons & workers & took details about the work . During taking these information we noticed that there was much difference in the actual & practical knowledge .We were told during the lectures that proportion is to be maintained during work . But on actual site there was no any proportion maintained at all. During these site training program we learnt various construction materials like, steel , plastic, bricks , vetrified tiles , granite , marble, P.O.P, P.O.P sheets, Ace paints , tractor imulsion paints, plywood , sunmica, R.C.C. pipes , septic tank , lambi , paving blocks, concrete , sand, aggregate, cement , superplasticisers , aluminium, glass,boding chemicals, expansion joints , thermocol, roofing tiles , fabrication materials, etc. During the it raining program we met various contractors like plumbing , electrification , tile, painting, window, door, P.O.P. , fabrication , labour etc.& discussed with them how to fill the tender for getting a contract in brief & took information about the type of material used , method of work in these project .Sometimes everyone was getting more information during that time we discussed particular point within ourselves & we would like to ask the queries to concerned person or worker. During our site training program we also took various photographs so that we can remember for ever . By taking the permission of our site incharge & site engineer ,we also visited the nearby sites and we saw the pile foundation work, pressure pile, formwork,column casting plinth beam casting,filling , slab casting, preparation & arrangment of reinforcement for column , beam,slab etc. according to R.C.C. design.& also we discussed about the present rates of this material in the market. Durin this we also asked them various questions like why they used that particular material for the construction. They also responded us good . We enjoyed this training by taking various information . the site engineer ,site incharge, supervisor gave us their personal experience work information . At 3.00p.m. or site engineer Mr. milind patil was teaching us how to calculate the rate analysis of a particular construction items.We used this information for calculation of rate analysis . after some days we learnt some what how to calculate the rate analysis . according to it we calculated the rate analysis and we doing tally it .with that of calculated by our site engineer . it was coming to be some what near by but not accurate . in short some rough idea about calculation of rate analysis . There is a camera security system through which an eye is kept nearly at each and every bunglow . coman facilities provided are good like Wi-Fi connection for internet ,club house ,gymnasium ,temple , garden etc. 24 hours water supply is available . At the last day i.e. on 21st Dec.2010 they gave us an send off after 4.00 p.m. During the send off we cutted a Black Forest Cake & ate pups & also gave it to the some other important persons which we came across during our site training program & also took the photographs with them.And also we enjoyed the send off party . At the end of each day we took sign. And remarks of site incharge and site engineer in our work allotment sheet and at last day we also took the sign. Of the project owner. In this way we completed our winter site training program from 8th DEC to 21st Dec 2010 & took various information about construction & we also got much more actual site i.e. field experience . from this training we learnt that how to become a successful builder in construction by talking pleasantly with the contractors and workers . We have also launched our own group web site which is ‘http://sanghavirockstar.webs.com’ where we have downloaded our information & photos taken on the site.We have also got two times report of the day & twice pic. of day . We are thankful to you for giving site training program & we are hoping that in future you will conduct such site training programmes for us. And we will like that you will keep this group till B.E.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-12

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the reticulated system of L.P.G. (Only for apartment).
Details of how you Planned & Executed the allotted work First we met Mr. Prasad Salvekar who is electronic engineer and discussed the entire working of gas system. And then we see the actual fitting of gas system.
Details of the Construction Procedure / Activity / Technology learned today -First no of flats & no of people in each flat are taken into consideration. -Then fittings of gas pipes for supply of gas into the flats is done according to design. -Each flat has only one gas supply connection & separate meter is provided to measure the consumption done by the occupant -Meter readings are taken at the end of every month & according to it charges is applied.
Details of the Construction Materials learned today Non return valve.: for avoiding the back flow of gas. C.I. pipe for transmission of gas. Gas meter.:for measuring the rate of consumption of gas by the consumer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Gardens are provided nearly in each bunglow.& in the club house.for maintaining good health of the people.
Details of the Construction / Engineering Drawings observed today Gas pipeline drawing.
Details of the Bye Laws referred today Provision of lift Planning & design –the planning & design of lifts including their no. ,type , and capacity.depending on the occupancy of the building, the population of each floor .
Details of any Managerial Skill learned today CO-Operation between site engineer ,site incharge,supervisors,& workers are very well
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: Assume frame size of door 3x7 sq.feet Particular : No. or Qt. Rate Cost Material Wood 4.655 c.f.t. 1300 6052/- Accessories Aldrop 1 200 200/- Hinges 4 20 80/- Handle 2 50 100/- Chain 1 50/- 50/- Lock 1 500/- 500/- Stooper 1 25/- 25/- Polish 200ml 250/- 250/- Labour Door fitter 1 500/- 500/- Polisher 1 300/- 300/- Total 8057/- Builders profit including Service tax , VAT etc 20% 9668.4Rs./- Rate per sq. ft. = 460.4Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 460.4Rs/-per sq. ft.
Todays BUZZ Word Todays buzz word-Your own Site training experience Our group name is ‘SANGHAVI ROCKSTARS’ Akshay Desai-group Leader Nitish Mohite Suchita Patil Yogesh Dalvi Parag Dhapodkar Above are the group members. Before our Sem-5 of T.E. Civil was being to be conducted or sir Mr.Imran pathan sir who teaches us the subject B.P.D. arranged program of winter site training for T.E. civil student for getting actual site information & site experience .according to it sir devided us into various groups . My group was SUNCITY ,which is constructed by Sanghavi builders & developers who are famous for construction & various other fields for last 120 years . My group contains 5 members whose names are mentioned are above .Our training program was from 8Th Dec. to 21St Dec. 2010. our Pathan Sir provided us with helmets for safety purpose and warned us wear always shoes so that there will not be any injury . Before actual training we contact Mr. Lalit Sanghavi the owner of Sanghavi Builders & Developers and told him about our training program . He gave us the contact no. of site incharge and site engineer & he also told that he will give instructions to them. We visited the Sun City on 8Th Dec. at 9.00a.m.. There was a security guard at the gate to whom we showed the letter given by our Pathan Sir. He noted down our names manually in the register . at 9.15a.m. security guard told us that to do voting in the voting cabin . We met that person and told him about our program .According to it he made a folder of voting for us so that there will be a computarized voting of our incoming and outgoing of the project gate. These was our daily routine. Till 9.30 to 10.00 a.m. site incharge Mr.Pritam Patil & site engineer Mr.Milind Patil were coming to the site for work . We met them & always asked them for to allow us some work to see the construction process of the project . Then at each day we were told for rate analysis of various items like P.C.C. , R.C.C. Column , Beam , Slab , Plastering , Painting , etc. According to that we met concerned persons & workers & took details about the work . During taking these information we noticed that there was much difference in the actual & practical knowledge .We were told during the lectures that proportion is to be maintained during work . But on actual site there was no any proportion maintained at all. During these site training program we learnt various construction materials like, steel , plastic, bricks , vetrified tiles , granite , marble, P.O.P, P.O.P sheets, Ace paints , tractor imulsion paints, plywood , sunmica, R.C.C. pipes , septic tank , lambi , paving blocks, concrete , sand, aggregate, cement , superplasticisers , aluminium, glass,boding chemicals, expansion joints , thermocol, roofing tiles , fabrication materials, etc. During the it raining program we met various contractors like plumbing , electrification , tile, painting, window, door, P.O.P. , fabrication , labour etc.& discussed with them how to fill the tender for getting a contract in brief & took information about the type of material used , method of work in these project .Sometimes everyone was getting more information during that time we discussed particular point within ourselves & we would like to ask the queries to concerned person or worker. During our site training program we also took various photographs so that we can remember for ever . By taking the permission of our site incharge & site engineer ,we also visited the nearby sites and we saw the pile foundation work, pressure pile, formwork,column casting plinth beam casting,filling , slab casting, preparation & arrangment of reinforcement for column , beam,slab etc. according to R.C.C. design.& also we discussed about the present rates of this material in the market. Durin this we also asked them various questions like why they used that particular material for the construction. They also responded us good . We enjoyed this training by taking various information . the site engineer ,site incharge, supervisor gave us their personal experience work information . At 3.00p.m. or site engineer Mr. milind patil was teaching us how to calculate the rate analysis of a particular construction items.We used this information for calculation of rate analysis . after some days we learnt some what how to calculate the rate analysis . according to it we calculated the rate analysis and we doing tally it .with that of calculated by our site engineer . it was coming to be some what near by but not accurate . in short some rough idea about calculation of rate analysis . There is a camera security system through which an eye is kept nearly at each and every bunglow . coman facilities provided are good like Wi-Fi connection for internet ,club house ,gymnasium ,temple , garden etc. 24 hours water supply is available . At the last day i.e. on 21st Dec.2010 they gave us an send off after 4.00 p.m. During the send off we cutted a Black Forest Cake & ate pups & also gave it to the some other important persons which we came across during our site training program & also took the photographs with them.And also we enjoyed the send off party . At the end of each day we took sign. And remarks of site incharge and site engineer in our work allotment sheet and at last day we also took the sign. Of the project owner. In this way we completed our winter site training program from 8th DEC to 21st Dec 2010 & took various information about construction & we also got much more actual site i.e. field experience . from this training we learnt that how to become a successful builder in construction by talking pleasantly with the contractors and workers . We have also launched our own group web site which is ‘http://sanghavirockstar.webs.com’ where we have downloaded our information & photos taken on the site.We have also got two times report of the day & twice pic. of day . We are thankful to you for giving site training program & we are hoping that in future you will conduct such site training programmes for us. And we will like that you will keep this group till B.E.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-12

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the reticulated system of L.P.G. (Only for apartment).
Details of how you Planned & Executed the allotted work First we met Mr. Prasad Salvekar who is electronic engineer and discussed the entire working of gas system. And then we see the actual fitting of gas system.
Details of the Construction Procedure / Activity / Technology learned today -First no of flats & no of people in each flat are taken into consideration. -Then fittings of gas pipes for supply of gas into the flats is done according to design. -Each flat has only one gas supply connection & separate meter is provided to measure the consumption done by the occupant -Meter readings are taken at the end of every month & according to it charges is applied.
Details of the Construction Materials learned today Non return valve.: for avoiding the back flow of gas. C.I. pipe for transmission of gas. Gas meter.:for measuring the rate of consumption of gas by the consumer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Gardens are provided nearly in each bunglow.& in the club house.for maintaining good health of the people.
Details of the Construction / Engineering Drawings observed today Gas pipeline drawing.
Details of the Bye Laws referred today Provision of lift Planning & design –the planning & design of lifts including their no. ,type , and capacity.depending on the occupancy of the building, the population of each floor .
Details of any Managerial Skill learned today CO-Operation between site engineer ,site incharge,supervisors,& workers are very well
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: Assume frame size of door 3x7 sq.feet Particular : No. or Qt. Rate Cost Material Wood 4.655 c.f.t. 1300 6052/- Accessories Aldrop 1 200 200/- Hinges 4 20 80/- Handle 2 50 100/- Chain 1 50/- 50/- Lock 1 500/- 500/- Stooper 1 25/- 25/- Polish 200ml 250/- 250/- Labour Door fitter 1 500/- 500/- Polisher 1 300/- 300/- Total 8057/- Builders profit including Service tax , VAT etc 20% 9668.4Rs./- Rate per sq. ft. = 460.4Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 460.4Rs/-per sq. ft.
Todays BUZZ Word Todays buzz word-Your own Site training experience Our group name is ‘SANGHAVI ROCKSTARS’ Akshay Desai-group Leader Nitish Mohite Suchita Patil Yogesh Dalvi Parag Dhapodkar Above are the group members. Before our Sem-5 of T.E. Civil was being to be conducted or sir Mr.Imran pathan sir who teaches us the subject B.P.D. arranged program of winter site training for T.E. civil student for getting actual site information & site experience .according to it sir devided us into various groups . My group was SUNCITY ,which is constructed by Sanghavi builders & developers who are famous for construction & various other fields for last 120 years . My group contains 5 members whose names are mentioned are above .Our training program was from 8Th Dec. to 21St Dec. 2010. our Pathan Sir provided us with helmets for safety purpose and warned us wear always shoes so that there will not be any injury . Before actual training we contact Mr. Lalit Sanghavi the owner of Sanghavi Builders & Developers and told him about our training program . He gave us the contact no. of site incharge and site engineer & he also told that he will give instructions to them. We visited the Sun City on 8Th Dec. at 9.00a.m.. There was a security guard at the gate to whom we showed the letter given by our Pathan Sir. He noted down our names manually in the register . at 9.15a.m. security guard told us that to do voting in the voting cabin . We met that person and told him about our program .According to it he made a folder of voting for us so that there will be a computarized voting of our incoming and outgoing of the project gate. These was our daily routine. Till 9.30 to 10.00 a.m. site incharge Mr.Pritam Patil & site engineer Mr.Milind Patil were coming to the site for work . We met them & always asked them for to allow us some work to see the construction process of the project . Then at each day we were told for rate analysis of various items like P.C.C. , R.C.C. Column , Beam , Slab , Plastering , Painting , etc. According to that we met concerned persons & workers & took details about the work . During taking these information we noticed that there was much difference in the actual & practical knowledge .We were told during the lectures that proportion is to be maintained during work . But on actual site there was no any proportion maintained at all. During these site training program we learnt various construction materials like, steel , plastic, bricks , vetrified tiles , granite , marble, P.O.P, P.O.P sheets, Ace paints , tractor imulsion paints, plywood , sunmica, R.C.C. pipes , septic tank , lambi , paving blocks, concrete , sand, aggregate, cement , superplasticisers , aluminium, glass,boding chemicals, expansion joints , thermocol, roofing tiles , fabrication materials, etc. During the it raining program we met various contractors like plumbing , electrification , tile, painting, window, door, P.O.P. , fabrication , labour etc.& discussed with them how to fill the tender for getting a contract in brief & took information about the type of material used , method of work in these project .Sometimes everyone was getting more information during that time we discussed particular point within ourselves & we would like to ask the queries to concerned person or worker. During our site training program we also took various photographs so that we can remember for ever . By taking the permission of our site incharge & site engineer ,we also visited the nearby sites and we saw the pile foundation work, pressure pile, formwork,column casting plinth beam casting,filling , slab casting, preparation & arrangment of reinforcement for column , beam,slab etc. according to R.C.C. design.& also we discussed about the present rates of this material in the market. Durin this we also asked them various questions like why they used that particular material for the construction. They also responded us good . We enjoyed this training by taking various information . the site engineer ,site incharge, supervisor gave us their personal experience work information . At 3.00p.m. or site engineer Mr. milind patil was teaching us how to calculate the rate analysis of a particular construction items.We used this information for calculation of rate analysis . after some days we learnt some what how to calculate the rate analysis . according to it we calculated the rate analysis and we doing tally it .with that of calculated by our site engineer . it was coming to be some what near by but not accurate . in short some rough idea about calculation of rate analysis . There is a camera security system through which an eye is kept nearly at each and every bunglow . coman facilities provided are good like Wi-Fi connection for internet ,club house ,gymnasium ,temple , garden etc. 24 hours water supply is available . At the last day i.e. on 21st Dec.2010 they gave us an send off after 4.00 p.m. During the send off we cutted a Black Forest Cake & ate pups & also gave it to the some other important persons which we came across during our site training program & also took the photographs with them.And also we enjoyed the send off party . At the end of each day we took sign. And remarks of site incharge and site engineer in our work allotment sheet and at last day we also took the sign. Of the project owner. In this way we completed our winter site training program from 8th DEC to 21st Dec 2010 & took various information about construction & we also got much more actual site i.e. field experience . from this training we learnt that how to become a successful builder in construction by talking pleasantly with the contractors and workers . We have also launched our own group web site which is ‘http://sanghavirockstar.webs.com’ where we have downloaded our information & photos taken on the site.We have also got two times report of the day & twice pic. of day . We are thankful to you for giving site training program & we are hoping that in future you will conduct such site training programmes for us. And we will like that you will keep this group till B.E.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-12

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the reticulated system of L.P.G. (Only for apartment).
Details of how you Planned & Executed the allotted work First we met Mr. Prasad Salvekar who is electronic engineer and discussed the entire working of gas system. And then we see the actual fitting of gas system.
Details of the Construction Procedure / Activity / Technology learned today -First no of flats & no of people in each flat are taken into consideration. -Then fittings of gas pipes for supply of gas into the flats is done according to design. -Each flat has only one gas supply connection & separate meter is provided to measure the consumption done by the occupant -Meter readings are taken at the end of every month & according to it charges is applied.
Details of the Construction Materials learned today Non return valve.: for avoiding the back flow of gas. C.I. pipe for transmission of gas. Gas meter.:for measuring the rate of consumption of gas by the consumer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Gardens are provided nearly in each bunglow.& in the club house.for maintaining good health of the people.
Details of the Construction / Engineering Drawings observed today Gas pipeline drawing.
Details of the Bye Laws referred today Provision of lift Planning & design –the planning & design of lifts including their no. ,type , and capacity.depending on the occupancy of the building, the population of each floor .
Details of any Managerial Skill learned today CO-Operation between site engineer ,site incharge,supervisors,& workers are very well
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: Assume frame size of door 3x7 sq.feet Particular : No. or Qt. Rate Cost Material Wood 4.655 c.f.t. 1300 6052/- Accessories Aldrop 1 200 200/- Hinges 4 20 80/- Handle 2 50 100/- Chain 1 50/- 50/- Lock 1 500/- 500/- Stooper 1 25/- 25/- Polish 200ml 250/- 250/- Labour Door fitter 1 500/- 500/- Polisher 1 300/- 300/- Total 8057/- Builders profit including Service tax , VAT etc 20% 9668.4Rs./- Rate per sq. ft. = 460.4Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 460.4Rs/-per sq. ft.
Todays BUZZ Word Todays buzz word-Your own Site training experience Our group name is ‘SANGHAVI ROCKSTARS’ Akshay Desai-group Leader Nitish Mohite Suchita Patil Yogesh Dalvi Parag Dhapodkar Above are the group members. Before our Sem-5 of T.E. Civil was being to be conducted or sir Mr.Imran pathan sir who teaches us the subject B.P.D. arranged program of winter site training for T.E. civil student for getting actual site information & site experience .according to it sir devided us into various groups . My group was SUNCITY ,which is constructed by Sanghavi builders & developers who are famous for construction & various other fields for last 120 years . My group contains 5 members whose names are mentioned are above .Our training program was from 8Th Dec. to 21St Dec. 2010. our Pathan Sir provided us with helmets for safety purpose and warned us wear always shoes so that there will not be any injury . Before actual training we contact Mr. Lalit Sanghavi the owner of Sanghavi Builders & Developers and told him about our training program . He gave us the contact no. of site incharge and site engineer & he also told that he will give instructions to them. We visited the Sun City on 8Th Dec. at 9.00a.m.. There was a security guard at the gate to whom we showed the letter given by our Pathan Sir. He noted down our names manually in the register . at 9.15a.m. security guard told us that to do voting in the voting cabin . We met that person and told him about our program .According to it he made a folder of voting for us so that there will be a computarized voting of our incoming and outgoing of the project gate. These was our daily routine. Till 9.30 to 10.00 a.m. site incharge Mr.Pritam Patil & site engineer Mr.Milind Patil were coming to the site for work . We met them & always asked them for to allow us some work to see the construction process of the project . Then at each day we were told for rate analysis of various items like P.C.C. , R.C.C. Column , Beam , Slab , Plastering , Painting , etc. According to that we met concerned persons & workers & took details about the work . During taking these information we noticed that there was much difference in the actual & practical knowledge .We were told during the lectures that proportion is to be maintained during work . But on actual site there was no any proportion maintained at all. During these site training program we learnt various construction materials like, steel , plastic, bricks , vetrified tiles , granite , marble, P.O.P, P.O.P sheets, Ace paints , tractor imulsion paints, plywood , sunmica, R.C.C. pipes , septic tank , lambi , paving blocks, concrete , sand, aggregate, cement , superplasticisers , aluminium, glass,boding chemicals, expansion joints , thermocol, roofing tiles , fabrication materials, etc. During the it raining program we met various contractors like plumbing , electrification , tile, painting, window, door, P.O.P. , fabrication , labour etc.& discussed with them how to fill the tender for getting a contract in brief & took information about the type of material used , method of work in these project .Sometimes everyone was getting more information during that time we discussed particular point within ourselves & we would like to ask the queries to concerned person or worker. During our site training program we also took various photographs so that we can remember for ever . By taking the permission of our site incharge & site engineer ,we also visited the nearby sites and we saw the pile foundation work, pressure pile, formwork,column casting plinth beam casting,filling , slab casting, preparation & arrangment of reinforcement for column , beam,slab etc. according to R.C.C. design.& also we discussed about the present rates of this material in the market. Durin this we also asked them various questions like why they used that particular material for the construction. They also responded us good . We enjoyed this training by taking various information . the site engineer ,site incharge, supervisor gave us their personal experience work information . At 3.00p.m. or site engineer Mr. milind patil was teaching us how to calculate the rate analysis of a particular construction items.We used this information for calculation of rate analysis . after some days we learnt some what how to calculate the rate analysis . according to it we calculated the rate analysis and we doing tally it .with that of calculated by our site engineer . it was coming to be some what near by but not accurate . in short some rough idea about calculation of rate analysis . There is a camera security system through which an eye is kept nearly at each and every bunglow . coman facilities provided are good like Wi-Fi connection for internet ,club house ,gymnasium ,temple , garden etc. 24 hours water supply is available . At the last day i.e. on 21st Dec.2010 they gave us an send off after 4.00 p.m. During the send off we cutted a Black Forest Cake & ate pups & also gave it to the some other important persons which we came across during our site training program & also took the photographs with them.And also we enjoyed the send off party . At the end of each day we took sign. And remarks of site incharge and site engineer in our work allotment sheet and at last day we also took the sign. Of the project owner. In this way we completed our winter site training program from 8th DEC to 21st Dec 2010 & took various information about construction & we also got much more actual site i.e. field experience . from this training we learnt that how to become a successful builder in construction by talking pleasantly with the contractors and workers . We have also launched our own group web site which is ‘http://sanghavirockstar.webs.com’ where we have downloaded our information & photos taken on the site.We have also got two times report of the day & twice pic. of day . We are thankful to you for giving site training program & we are hoping that in future you will conduct such site training programmes for us. And we will like that you will keep this group till B.E.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-12

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the reticulated system of L.P.G. (Only for apartment).
Details of how you Planned & Executed the allotted work First we met Mr. Prasad Salvekar who is electronic engineer and discussed the entire working of gas system. And then we see the actual fitting of gas system.
Details of the Construction Procedure / Activity / Technology learned today -First no of flats & no of people in each flat are taken into consideration. -Then fittings of gas pipes for supply of gas into the flats is done according to design. -Each flat has only one gas supply connection & separate meter is provided to measure the consumption done by the occupant -Meter readings are taken at the end of every month & according to it charges is applied.
Details of the Construction Materials learned today Non return valve.: for avoiding the back flow of gas. C.I. pipe for transmission of gas. Gas meter.:for measuring the rate of consumption of gas by the consumer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Gardens are provided nearly in each bunglow.& in the club house.for maintaining good health of the people.
Details of the Construction / Engineering Drawings observed today Gas pipeline drawing.
Details of the Bye Laws referred today Provision of lift Planning & design –the planning & design of lifts including their no. ,type , and capacity.depending on the occupancy of the building, the population of each floor .
Details of any Managerial Skill learned today CO-Operation between site engineer ,site incharge,supervisors,& workers are very well
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: Assume frame size of door 3x7 sq.feet Particular : No. or Qt. Rate Cost Material Wood 4.655 c.f.t. 1300 6052/- Accessories Aldrop 1 200 200/- Hinges 4 20 80/- Handle 2 50 100/- Chain 1 50/- 50/- Lock 1 500/- 500/- Stooper 1 25/- 25/- Polish 200ml 250/- 250/- Labour Door fitter 1 500/- 500/- Polisher 1 300/- 300/- Total 8057/- Builders profit including Service tax , VAT etc 20% 9668.4Rs./- Rate per sq. ft. = 460.4Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 460.4Rs/-per sq. ft.
Todays BUZZ Word Todays buzz word-Your own Site training experience Our group name is ‘SANGHAVI ROCKSTARS’ Akshay Desai-group Leader Nitish Mohite Suchita Patil Yogesh Dalvi Parag Dhapodkar Above are the group members. Before our Sem-5 of T.E. Civil was being to be conducted or sir Mr.Imran pathan sir who teaches us the subject B.P.D. arranged program of winter site training for T.E. civil student for getting actual site information & site experience .according to it sir devided us into various groups . My group was SUNCITY ,which is constructed by Sanghavi builders & developers who are famous for construction & various other fields for last 120 years . My group contains 5 members whose names are mentioned are above .Our training program was from 8Th Dec. to 21St Dec. 2010. our Pathan Sir provided us with helmets for safety purpose and warned us wear always shoes so that there will not be any injury . Before actual training we contact Mr. Lalit Sanghavi the owner of Sanghavi Builders & Developers and told him about our training program . He gave us the contact no. of site incharge and site engineer & he also told that he will give instructions to them. We visited the Sun City on 8Th Dec. at 9.00a.m.. There was a security guard at the gate to whom we showed the letter given by our Pathan Sir. He noted down our names manually in the register . at 9.15a.m. security guard told us that to do voting in the voting cabin . We met that person and told him about our program .According to it he made a folder of voting for us so that there will be a computarized voting of our incoming and outgoing of the project gate. These was our daily routine. Till 9.30 to 10.00 a.m. site incharge Mr.Pritam Patil & site engineer Mr.Milind Patil were coming to the site for work . We met them & always asked them for to allow us some work to see the construction process of the project . Then at each day we were told for rate analysis of various items like P.C.C. , R.C.C. Column , Beam , Slab , Plastering , Painting , etc. According to that we met concerned persons & workers & took details about the work . During taking these information we noticed that there was much difference in the actual & practical knowledge .We were told during the lectures that proportion is to be maintained during work . But on actual site there was no any proportion maintained at all. During these site training program we learnt various construction materials like, steel , plastic, bricks , vetrified tiles , granite , marble, P.O.P, P.O.P sheets, Ace paints , tractor imulsion paints, plywood , sunmica, R.C.C. pipes , septic tank , lambi , paving blocks, concrete , sand, aggregate, cement , superplasticisers , aluminium, glass,boding chemicals, expansion joints , thermocol, roofing tiles , fabrication materials, etc. During the it raining program we met various contractors like plumbing , electrification , tile, painting, window, door, P.O.P. , fabrication , labour etc.& discussed with them how to fill the tender for getting a contract in brief & took information about the type of material used , method of work in these project .Sometimes everyone was getting more information during that time we discussed particular point within ourselves & we would like to ask the queries to concerned person or worker. During our site training program we also took various photographs so that we can remember for ever . By taking the permission of our site incharge & site engineer ,we also visited the nearby sites and we saw the pile foundation work, pressure pile, formwork,column casting plinth beam casting,filling , slab casting, preparation & arrangment of reinforcement for column , beam,slab etc. according to R.C.C. design.& also we discussed about the present rates of this material in the market. Durin this we also asked them various questions like why they used that particular material for the construction. They also responded us good . We enjoyed this training by taking various information . the site engineer ,site incharge, supervisor gave us their personal experience work information . At 3.00p.m. or site engineer Mr. milind patil was teaching us how to calculate the rate analysis of a particular construction items.We used this information for calculation of rate analysis . after some days we learnt some what how to calculate the rate analysis . according to it we calculated the rate analysis and we doing tally it .with that of calculated by our site engineer . it was coming to be some what near by but not accurate . in short some rough idea about calculation of rate analysis . There is a camera security system through which an eye is kept nearly at each and every bunglow . coman facilities provided are good like Wi-Fi connection for internet ,club house ,gymnasium ,temple , garden etc. 24 hours water supply is available . At the last day i.e. on 21st Dec.2010 they gave us an send off after 4.00 p.m. During the send off we cutted a Black Forest Cake & ate pups & also gave it to the some other important persons which we came across during our site training program & also took the photographs with them.And also we enjoyed the send off party . At the end of each day we took sign. And remarks of site incharge and site engineer in our work allotment sheet and at last day we also took the sign. Of the project owner. In this way we completed our winter site training program from 8th DEC to 21st Dec 2010 & took various information about construction & we also got much more actual site i.e. field experience . from this training we learnt that how to become a successful builder in construction by talking pleasantly with the contractors and workers . We have also launched our own group web site which is ‘http://sanghavirockstar.webs.com’ where we have downloaded our information & photos taken on the site.We have also got two times report of the day & twice pic. of day . We are thankful to you for giving site training program & we are hoping that in future you will conduct such site training programmes for us. And we will like that you will keep this group till B.E.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-12

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell near kadam wadi
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 5:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To study the External Plastering Work. 2. To study Electrification. 3. To prepare the daily report work analysis
Details of how you Planned & Executed the allotted work 1. We divided ourself into two groups. 2. The first group studied the plastering work. 3. The second group studied the electrification work. 4. Then again the first group changed their work & studied the electrification work & vice versa.
Details of the Construction Procedure / Activity / Technology learned today 1. First of all the rendering of external wall surface was done for south wall . this work was carried out yesterday. 2. Then the second coat was applied today. 3. This work included applying the mortar with force on the surface, with a trowel. 4. Then using floats the mortered surface was levelled.
Details of the Construction Materials learned today 1. Mortar to be used for plastering in ratio of 1:3. 2. Anchor Wires (copper) 1sq.mm (1100V capacity)
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Electrification Working Drawings
Details of the Bye Laws referred today Bye-Law Book Page No 35 Additional Restriction on construction
Details of any Managerial Skill learned today 1. Bargaining with external agencies. 2. Study of daily report analysis.
RATE ANALYSIS (Detailed Stepwise Calculations required) # Rate Analysis For teak wood door # A) door Size = 2\'.1\" x 0.9\' B) Material required: 1. Top Rail = 0.9 kg. 2. Side rail = 2.23 kg. 3. Bottom Rail = 0.9 kg. 4. pannel = 08 sq.ft 5. Coating Powder = 08 sq.ft 6. Lock = 2 nos. 7. Screws 8. frame C) Material Cost: 1. Top Rail = 1.083 x 180 = 194.94/- 2. Side Rail = 1.73 x 180 = 311.4/- 3. Bottom Rail = 1.167 x 180 = 210.06/- 4. Frame a) Top = 0.625 x 180 = 112.5/- b) Bottom = 0.625 x 180 = 112.5/- c) Lock = 1.5 x 180 = 270/- d) InterLock = 0.8 x 180 = 144/- 5. Lock = 2 x 30 = 60/- 6. Screws, etc. = 100/- Total = 2230.40/- D) Labour Cost: 1. Skilled Labour = 1 x 250 = 250/- 2. Mazdoor = 2 x 110 = 220/- Total = 470/- E) Grand Total = C + D = 2700.54/- F) Rate Per Sq.Ft = 118.07/- G) Rate Per Sq.M = 1500.30/-
Result of RATE ANALYSIS ( Rs per Unit ) 1500.30 rs.
Todays BUZZ Word I learn most of the things by this proggrame which has follows. 1) knowing the field work. 2) how to mannage the total field. 3) how to speek, labour,worker,clint, and dep. of other member. 4) knowing the material of component of building,& quality of material. 5) environmental caring so that pepole can be healthy. 6) i learn about electrical work in that, wiring, plug, power plug, switch board etc. 7) about tiling skirting, various types of tiling, dado work & anti skiding tiles. 8) i learn about masonary work. in that brick work,stone work, their shape, size. durability & strenth 9) learn about plastering. in that, i has 2 coats. 1st one is floating,& last is finishing (12mm thick 1st coat,& 2nd coat 3mm) 10) i learn about painting it has 2 coats, before that pop apply on wall. 11) learn about water proofing system and brick bat coba. 12) learn about admixtures, protect used
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge mr.ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-12

Company Name V. S. Joshi & Associates
Project Name & Site Address vishwa enclave
Students Name (Surname_First Name_Middle Name) janbandhu rakshit d.
Exam No. 10875
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 5:00 pm
Details of the Work Allotted to you today by the Site In-Charge Checking the dimension of columns, beams, and septic tank dimension, checking the cement test available at site. And how to steel placed for concreting of beams.
Details of how you Planned & Executed the allotted work We divide in two groups, one group at 1st floor and another one is at 2nd floor, and taking all dimensions of coluns, beams, sill level height, and taking parapet wall height 1.2 meters, and cheking cement test, 1st inserted hand in full of cement bag, we feel cool, then rubbed in fingers, then feel smooth, and thoroug full of hand cement in full of water bucket, then cement float sometimes on the surface of bucket.
Details of the Construction Procedure / Activity / Technology learned today Before casting the slab, genrally for shuttering the steel plates are used, but now a days the advanced waterproof plywood (northern compnay) used, used like this ply, the ceiling surface should be smooth, good appearance and not necessory plastering for ceiling, only apply putty after that.
Details of the Construction Materials learned today Use of cement block, Size(400*200*150) and cost is 18 rps. For one brick. Used for compnund wall, parapet wall, for good appearance
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Providing septic tank common for every block in total area. And waste water directly connected to muncipal line.
Details of the Construction / Engineering Drawings observed today Observing plans of row houses, their are 6 row bunglows, in that 3 bhk flats are provided.
Details of the Bye Laws referred today Regarding by bye laws, front margin=5m, rear margin=3m, side margin=4.5m
Details of any Managerial Skill learned today How to manage total feild.
RATE ANALYSIS (Detailed Stepwise Calculations required) # Rate Analysis For teak wood door # A) door Size = 2\'.1\" x 0.9\' B) Material required: 1. Top Rail = 0.9 kg. 2. Side rail = 2.23 kg. 3. Bottom Rail = 0.9 kg. 4. pannel = 08 sq.ft 5. Coating Powder = 08 sq.ft 6. Lock = 2 nos. 7. Screws 8. frame C) Material Cost: 1. Top Rail = 1.083 x 180 = 194.94/- 2. Side Rail = 1.73 x 180 = 311.4/- 3. Bottom Rail = 1.167 x 180 = 210.06/- 4. Frame a) Top = 0.625 x 180 = 112.5/- b) Bottom = 0.625 x 180 = 112.5/- c) Lock = 1.5 x 180 = 270/- d) InterLock = 0.8 x 180 = 144/- 5. Lock = 2 x 30 = 60/- 6. Screws, etc. = 100/- Total = 2230.40/- D) Labour Cost: 1. Skilled Labour = 1 x 250 = 250/- 2. Mazdoor = 2 x 110 = 220/- Total = 470/- E) Grand Total = C + D = 2700.54/- F) Rate Per Sq.Ft = 118.07/- G) Rate Per Sq.M = 1500.30/-
Result of RATE ANALYSIS ( Rs per Unit ) 1500 RS.
Todays BUZZ Word I learn most of the things by this proggrame which has follows. 1) knowing the field work. 2) how to mannage the total field. 3) how to speek, labour,worker,clint, and dep. of other member. 4) knowing the material of component of building,& quality of material. 5) environmental caring so that pepole can be healthy. 6) i learn about electrical work in that, wiring, plug, power plug, switch board etc. 7) about tiling skirting, various types of tiling, dado work & anti skiding tiles. 8) i learn about masonary work. in that brick work,stone work, their shape, size. durability & strenth 9) learn about plastering. in that, i has 2 coats. 1st one is floating,& last is finishing (12mm thick 1st coat,& 2nd coat 3mm) 10) i learn about painting it has 2 coats, before that pop apply on wall. 11) learn about water proofing system and brick bat coba. 12) learn about admixtures, protect used
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge amol mulay
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: shinde_shital7@yahoo.com
Subject: 10884-12

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL KARANDEMALA CIRCUITHOUSE KOLHAPUR
Students Name (Surname_First Name_Middle Name) SHINDE SHITAL VILASRAO
Exam No. 10884
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00am
Details of the Work Allotted to you today by the Site In-Charge The work allotted by the site in-charge is to measure open space and decide position of column in front of gym on first floor in which garden is done.
Details of how you Planned & Executed the allotted work We first decided to divide in two groups .First groups on one side and second group on other side measure the total distance in-front of gym.Then according to drawing we mark four column of size(15*9)\".First for distance of9\'5\" and then further for distance of 9\'7\" on both side.At the corner the column is L shaped.
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished
Details of the Construction Materials learned today We learned construction material is 1. Taps 2. traps 3. P.V.C pipes 4. Cocks
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river .sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment.
Details of the Construction / Engineering Drawings observed today 1.We observed construction drawing of first floor garden in front of gym. 2.We observed construction drawing of position of column .
Details of the Bye Laws referred today Bye laws for 1. Bathroom 2. Toilet 3. Balcony 4. Portch
Details of any Managerial Skill learned today 1. Speak politely with claint. 2. To keep proper record of material. 3. To do work sincely. 4. Watch the worker carefully they do work or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR FULLY COMPLETE DOOR Sagwan door of size (1.2*2.1) Rate=1000Rs Fixtures and fasting=350Rs Wooden frame=250 RS one door Labour cost=100Rs Total cost=1900 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 1900 Rs
Todays BUZZ Word These is my first training for twelve days. I got good as well as bad experience.Good because of my group paternal are very good. They always CO-ordinate me. They help me. In 12 days training we got lots of information.e.g I know that how to place \"JALI\"before plaster.I know that why and where \"JALI\" are placed.I know that how to paint wall and use of putty.I know that how to place tile.I know that how to do eletrification and plumbing.I know that in which distance inspection chamber are situated.I know that how to slab construct.I know that when one way slab and two way slab are used. Our site in-charge are very good.They have lots of knowleadge about construction.When we asked question they gave us satisfactory answer.They always inspir us.Mr.ketan sir complated his education in \"COMMERCE\"but they have very knoweadge about construction. In site workers are very good They complate their wprk very good.The worker has unity.They always helps to other worker in their need. The only one bad experience is that I donot wear shoes in site when sir came they shouted me.In these way we got bad as well as good experince but bad experience is litter so I will rember always good experince in twelve days training.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.ketan charapale. 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-12

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders ,pratibha nagar
Students Name (Surname_First Name_Middle Name) Jadhav Swapnil Ashok
Exam No. 13529
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1)to see the slabcasting. 2)to check the plaster.
Details of how you Planned & Executed the allotted work 1)we checked the slabcasting .we checked diamention of slab, we checked provided steel. 2)we checked the plaster with the help of rope called as line dori,to know if there are any undulations in the plastered surface. the site incharge helped us a lot.
Details of the Construction Procedure / Activity / Technology learned today about the use of compaction machine.
Details of the Construction Materials learned today compaction machine.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of soil which is excavated for foundation purpose is used to fill-up the murums. Details of the Construction.
Details of the Construction / Engineering Drawings observed today slab drawing.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for T.W. Paneled Door: Main door plywood-Rs.3000 Formica-2 no.-Rs.1200 each=Rs.2400 Lining patti-Rs.7/ft.-20 ft=Rs.140 Mapping patti-Rs.10/ft-30 ft.=Rs.300 Fevicol-Rs.300/kg Door frame-Rs.2000 Labour-Rs.2000 Lump sump-Rs.200 Locks,handle,stopper=Rs.1300 Total=Rs.12000/- Contractor profit-15%=Rs.1700 Total cost-Rs.13700/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.13700/-
Todays BUZZ Word we are glad and thankfull to the dept of civil engg and HOD for the given us apportunity to understand the construction industry and work. This training programme help me in better understanding of the various therotical subject it also open us to wat construction industry and give the bref idea about the challenges and the apportunityies in the industry it help in co-relating the therotical concept and practical cosiderations it gives idea about how construction work is conducted. we the roughly understand the detail of construction procedure variou activity. program help us a lot and we are greatfull to be part of the same.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Name:Vijay Mane. Mob no: 9049505925.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-12

Company Name Deshmukh Developers
Project Name & Site Address Deshmukh Developments,Pratibha Nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Birajdar Minaxi Renuk
Exam No. 13556
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today we are note down important materials are used during construction such as admixture, waterproofing injections to the concrete ,ceramic ,vitrified tiles etc.
Details of how you Planned & Executed the allotted work We are divide the group.Two students goes to plumbing division & remaining students goes to tiles store area. We are note down important things.
Details of the Construction Procedure / Activity / Technology learned today Construction Procedure : a) City tiles Rs. 152/- Quality - PREMIUM Size - 660.4*660.4mm Coverage - 1.308 sq.meter Quantity - 3pcs. b) Kajria - Wall Tiles 30*601450 RScm Rectified wall tiles selected superbrand 6pcs Quantity Coverage 1.08 sq meter c) MYK Latricrete Wall Putty Net Weight 40 kg. Rs.1050/- d) POP-plaster of paris ceiling Net Weight- 20 kg. Rs. 110/- to 120/- e) Goyal Rubber Lubricant Rs.75/- yellow medium Bodied All Weather CPVC Fusion Compound f) MYK SCHOMBURG High performance construction chemical Net Weight- 100 litre Rs.8500/- 12 months
Details of the Construction Materials learned today Material are used as follows : 1) Admixture 2) Wall tiles 3) City tiles 4) Bagalkot cement 43 Grade Rs.200/- 5) Diamond Gypsum Stucco Plaster
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environment Caring Technology : To recharge water table by providing Rain Water Harvesting Technics.
Details of the Construction / Engineering Drawings observed today Construction Drawing : We are again carefully observe all floor plans.
Details of the Bye Laws referred today None
Details of any Managerial Skill learned today He should have more practical knowledge in case of communication with customers.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FULLY COMPLETE DOOR : WOODEN DOOR OF SIZE (1.2 * 2.1) RATE FOR WOODEN DOOR OF SIZE 1.2 * 2.1 = 750 RS WOODEN FRAME = 250 RS ALL TYPE OF FIXTURES & FASTINGS = 350 RS PER SET LABOUR = 100 RS TOTAL COST = (750+250+350+100) = 1450 RS
Result of RATE ANALYSIS ( Rs per Unit ) 1450 RS
Todays BUZZ Word BUZZ WORD OF THE DAY : First of all we are very thankful to Prof.IMARAN PATHAN SIR to arrange this fantastic site work training programm for us. On site we are visited different talented persnalities Builder Mr.Somraj Deshmukh sir,Er.Rajesh Chougule sir,Site Incharge.Mr.Abhijit Bhosale sir & Architect Mr.Milind Chougule sir etc. Including Mistry Mr. Lokande sir, Mr.Balu Gurav sir & all workers given us tremendous information to us. On site we are learned about following important things : A) Provision of reinforcement,binding of bars,top bars.bottom bars,curtailment, main bars, distribution bars,stirrups of different sizes depend upon design. B) Electrification : It should involve concealed wiring,switch board of 8Module,4 Module as required positive,negative,earthing,main circuit board,provision of electrification connection, MSEB etc. C) Slab Casting : In this work firstly all equipment are properly placed drum, lifting machine, weigh batcher,proportion of materials,platform,needle vibrator,compacting equipments,curing etc are involved in slab casting D) Plumbing : It should include hot water pipe,cold water pipe,height of shower,height of commode,Height of wash basin,flushing,extra cover is provided for hot water pipe, PVC pipe,CPVC pipe, Inspection chamber,water proofing etc. E) Brick Masonry : It should include 9\"*6\"*4\" & 9\"*4\"*3\" brick size.For one truck cost is 3000Rs for 5000 bricks.Plumb bob.right angle scale (Guna) etc F) How to communicate with custmer should be more important factor. In this way we are get more knowledge from this programm ,in future it is most useful to us. SIR, when we are work in Group then Group members are plays an very important Role.Co-ordination,Helpful Nature should be most required.My Group members co-ordination is not good.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR,ABHIJIT BHOSALE SIR MOB.NO.9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-12

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) fulari sujata shankar
Exam No. 13559
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 10.00am
Site Leaving Time (HH:MM am/pm) 05.00pm
Details of the Work Allotted to you today by the Site In-Charge today site in-charge gave us work to cheack the bar provieded for casting the slab as per drawing. .
Details of how you Planned & Executed the allotted work -firstly we divided in two group . - after that as per drawing and bar bending schedule we check the bar. - in that way we done the work. .
Details of the Construction Procedure / Activity / Technology learned today 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance.
Details of the Construction Materials learned today 1)Timber 2)glass 3)steel bars 4)Hold fast 5)Tools & planks.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Solar Panels we used for water heating purpose
Details of the Construction / Engineering Drawings observed today today we observed the drawing of slab and bar bending schedule for slab. .
Details of the Bye Laws referred today Today we are observe bye laws for, 1) Height of ventilator 2) Height of Door 3) Above values compare with actual site work
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR FULLY COMPLETE DOOR SAG WAN DOOR OF SIZE (1.2*2.1)M SAG WAN DOOR RATE OF SIZE (1.2*2.1)M = 900RS. WOODEN FRAME RATE = 250RS. ALL TYPES OF FIXTURE AND FASTING = 350RS PER SET OF ONE DOOR. LABOUR COST = 100RS . TOTAL COST FOR ONE DOOR OF SIZE (1.2*2.1) = (900+250+350+100) = 1600RS.
Result of RATE ANALYSIS ( Rs per Unit ) 1600RS.
Todays BUZZ Word Firstly we are very thankful to prof.IMRAN PATHAN sir to arrange this site training program for us. the first day of site training we visited to our engineer sir mr.sanjay shendre they gave information about their project goining on near n.c.c bhavan . after that we are goining our site and on site we met the supervisor sir mr.vivek randive. vivek sir give us all information about their project and they give the plans of building for observation and better understanding name of site is MALLHAR HEIGHTS NEAR N.C.C BHAVAN. they daily gave us to work with considering about our training, i was learn so much from vivek sir. they laerned we how to analysis rate of building cost. on site we learn lots of information which can not learn in class room or any book. on site labour also behave very co-ordinative,they give lots of information. on site i had learned about how to cast beam,colunm,slab. how to determine the qunatity of bricks,cement,sand etc this also we learned on site -how to use the plum bob and water tube for leveling purpose. - how to provide plumbing and electrification for all room with their rate analysis. -how to provide stirrups and their spacing . - how to handle the labour on site ,all these things we learn on site which is very important to us. my experince is quit nice but my group coordination is not so good,i was not happy with my group member but over all site training is so nice. these 12 days training program i got lots of information . so i thankful to sir to arrange this site training. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-12

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) fulari sujata shankar
Exam No. 13559
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 10.00am
Site Leaving Time (HH:MM am/pm) 05.00pm
Details of the Work Allotted to you today by the Site In-Charge today site in-charge gave us work to cheack the bar provieded for casting the slab as per drawing. .
Details of how you Planned & Executed the allotted work -firstly we divided in two group . - after that as per drawing and bar bending schedule we check the bar. - in that way we done the work. .
Details of the Construction Procedure / Activity / Technology learned today 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance.
Details of the Construction Materials learned today 1)Timber 2)glass 3)steel bars 4)Hold fast 5)Tools & planks.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Solar Panels we used for water heating purpose
Details of the Construction / Engineering Drawings observed today today we observed the drawing of slab and bar bending schedule for slab. .
Details of the Bye Laws referred today Today we are observe bye laws for, 1) Height of ventilator 2) Height of Door 3) Above values compare with actual site work
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR FULLY COMPLETE DOOR SAG WAN DOOR OF SIZE (1.2*2.1)M SAG WAN DOOR RATE OF SIZE (1.2*2.1)M = 900RS. WOODEN FRAME RATE = 250RS. ALL TYPES OF FIXTURE AND FASTING = 350RS PER SET OF ONE DOOR. LABOUR COST = 100RS . TOTAL COST FOR ONE DOOR OF SIZE (1.2*2.1) = (900+250+350+100) = 1600RS.
Result of RATE ANALYSIS ( Rs per Unit ) 1600RS.
Todays BUZZ Word Firstly we are very thankful to prof.IMRAN PATHAN sir to arrange this site training program for us. the first day of site training we visited to our engineer sir mr.sanjay shendre they gave information about their project goining on near n.c.c bhavan . after that we are goining our site and on site we met the supervisor sir mr.vivek randive. vivek sir give us all information about their project and they give the plans of building for observation and better understanding name of site is MALLHAR HEIGHTS NEAR N.C.C BHAVAN. they daily gave us to work with considering about our training, i was learn so much from vivek sir. they laerned we how to analysis rate of building cost. on site we learn lots of information which can not learn in class room or any book. on site labour also behave very co-ordinative,they give lots of information. on site i had learned about how to cast beam,colunm,slab. how to determine the qunatity of bricks,cement,sand etc this also we learned on site -how to use the plum bob and water tube for leveling purpose. - how to provide plumbing and electrification for all room with their rate analysis. -how to provide stirrups and their spacing . - how to handle the labour on site ,all these things we learn on site which is very important to us. my experince is quit nice but my group coordination is not so good,i was not happy with my group member but over all site training is so nice. these 12 days training program i got lots of information . so i thankful to sir to arrange this site training. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-12

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Ramchandra
Exam No. 13557
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Observe the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of form work of column. 4) Arrangement of form work of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilization of crushed sand instead of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other furniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today 1) Provision for Ramps In case of parking space provided in basement at least 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the form work of slab with respect to architectural reference. 3) Control the wastage of material. 4) communication between site in charge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88/-
Todays BUZZ Word OUR Experience- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. ,colouring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-12

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SALOKHE SUDARSHAN ANIL
Exam No. 13544
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To check the preparation required before casting the slab.
Details of how you Planned & Executed the allotted work we divide ourself into groups. one group is on floor of slab and one is near mixer ,weigh batcher.
Details of the Construction Procedure / Activity / Technology learned today before casting of slab first the centering work is checked by the structural engineer then the permission is given for the casting of slab. whether the cover blocks, chairs are provided or not it is also checked by the engineer. then the water is sprayed on the surface of slab bottom so that it can remove easily and good finishing is obtained. terrace level slab is constructed waterproof by mixing the waterproofing chemicals in the concrete. terrace slab and sunk slab is also treated with the chemicals.if slab casting during night time then proper lighting arrangement is provided.
Details of the Construction Materials learned today no new materials are learned today.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings and working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3000 FORMICA-2 NO. = RS 1200 EACH = RS 2400 LINING PATTI- RS 7/FT.-20 FT = RS 140 MAPPING PATTI- RS 10/FT.- 30 FT. =RS 300 FEVICOL- RS 300/KG DOOR FRAME- RS 2000 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 12000 CONTRACTOR PROFIT= 15% = RS 1700 TOTAL COST= RS 13700
Result of RATE ANALYSIS ( Rs per Unit ) 13700 RS
Todays BUZZ Word TO ACHIEVE OWN BRAND NAME IN THE MARKET IT REQUIRES HARD WORK , CLOSE CO-CORDINATION AND THE SUPPORT OF QALIFIED PERSONS IS REQUIRED. THERE IS SO MUCH DIFFERENCE IN OUR THEROY KNOWLEDGE WHATEVER WE ARE STUDYING DURING OUR DEGREE COURSE AND PRACTICAL IMPLEMENTATION OF THIS KNOWLEDGE ON SITE. THERE ARE LOTS OF MANEGERIAL SKILLS ARE REQUIRED TO THE HANDLE THE SITE PROPERLY. THE ENGINEER SHOULD HAVE GOOD CO-ORDINATION WITH THE SITE SUPERVISOR ON THE SITE TO GET THE DETAIL INFORMATION ABOUT THE WORK THAT WAS ALLOTED TO THEM AND WHAT IS THE PROGRESS OF WORK. THERE IS TENDENCY OF WORKERS ON THE SITE TO WORK ACCORDING TO THEIR EXPERIENCE AND NOT WITH THE INSTRUCTION GIVEN TO THEM . I OBSERVED ON THE SITE MANY TIMES , DURING MIXING OF CONCRETE WATER IS NOT ADDED ACCORDING TO THE PROPORTION GIVEN TO THEM BUT THEY ARE ADDING ACCORDING TO THEM AND SOMETIMES THEY ARE NOT USING THE WEIGH BATCHING MACHINE , THEY ARE DIRECTLY THROWN THE SAND IN THE BUCKET OF MIXERS. SO FROM THIS I LEARNED THAT FOR THE QUALITY WORK TO BE DONE , IT REQUIRES CON TINOUS REGULAR OBSERVATIONS. ENGINEER SHOULD BE PRESENT ON SITE DURING THE MOST IMPORTANTS WORKS GOING ON THE SITE SUCH AS LINE OUT , CASTING OF BEAMS , COLUMN , SLABS. BECAUSE IF THE SUPERVISOR OR WORKER PRSENT ON THE SITE FOUND ANY TECHNICAL PROBLEM RELATED TO THE WORK THEN IT SHOULD BE INSTANTLY SOLVED BY THE ENGINEER WITHOUT DELAY IN THE WORK. I HAVE SEEN MANY TIMES THAT THE WORK ALLOTED TO THE WORKERS WITH THE DRAWINGS AND IN ACTUAL EXECUTION OF WORK THERE MIGHT BE POSIBILITY OF ERRORS. SOMETIMES ALSO THERE IS POSSIBILTY OF FAULT IN THE DRAWINGS PROVIDED BY THE ARCHITECTURES. IF ENGINEER IS PRESENT ON SITE THE PRROBLEMS LIKE THIS CAN BE EASILY SOLVED. ALONG WITH THE QUALITY OF TECHNICAL THINGS IT IS VERY IMPORTANT THAT HOW WILL YOU COMMUNICATE WITH THE CUSTOMERS . CIVIL ENGINEER SHOULD HAVE THIS KIND OF QUALITY WHICH WILL BE HELPFUL IN CUMMUNICATION WITH THE PEOPLE IN THE MARKETING WORLD. IF WE DONE OUR WORK WITH GOOD SUPERVISION AND ACCURACY THEN WE CAN SURE ABOUT THAT WE WILL NOT REQUIRED ANY TYPE OF ADMIXTURE AND CHEMICALS TO IMPROVE OUR QUALITY OF CONCRETE. BEFORE DOING ANY MAJOR WORK SUCH AS CASTING OF 10-12 COLUMNS AT A TIME THEN WE HAVE TO PREPARE FIRST TEST CUBE SPECIMENS WITH THE DECIDED PROPORTION THEN AFTER TESTING REPORTS THE PERMISSION IS GIVEN TO THE FURTHER WORK. IF YOU WANT USE ANY TYPE OF CONSTRUCTION MATERIAL ON SITE THEN IT SHOULD BE TESTED FIRST FOR ITS PERFORMANCE THEN ACCORDING TO THAT IT WILL USED . OTHERWISE THERE IS POSSIBILITY THAT IT WILLL CAUSE WASTGE OF MONEY UNECCESARILY . NOW A DAYS ACCORDING TO THE ENVIROMENTAL CONDITITONS IT IS MUST THAT WE HAVE TO APPLY SOME KIND GREEN TECNOLOGY TO THE BUILDINGS. THIS CAN BE DONE BY USING FLY ASH BRICKS , FLY ASH MIXED CEMENT IN THE CONSTRUCTION OF BUILDING. BY ADOPTING THE RAIN WATER HARVESTING TECNIQUES OR GROUND WATER RECHARGING , BY PROVIDING SEWAGE TREATMENT PLANTS AND SOLAR PANELS ARE USED TO HEAT THE WATER ALSO UTILISIG THE ELECTRICITY GENERATED BY THIS FOR PARKING OR IN COMMAN AREAS OF THE BUILDINGS. OVERALL YOU WILL REQUIRED GOOD CO-ORDINATION WITH THE PEOPLES ON THE SITE TO DO THE WORK IN GOOD MANNER.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-12

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHAIKH RIZWAN KHALIL
Exam No. 13545
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To check the preparation required before casting the slab.
Details of how you Planned & Executed the allotted work we divide ourself into groups. one group is on floor of slab and one is near mixer ,weigh batcher.
Details of the Construction Procedure / Activity / Technology learned today before casting of slab first the centering work is checked by the structural engineer then the permission is given for the casting of slab. whether the cover blocks, chairs are provided or not it is also checked by the engineer. then the water is sprayed on the surface of slab bottom so that it can remove easily and good finishing is obtained. terrace level slab is constructed waterproof by mixing the waterproofing chemicals in the concrete. terrace slab and sunk slab is also treated with the chemicals.if slab casting during night time then proper lighting arrangement is provided.
Details of the Construction Materials learned today no new materials are learned today.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings and working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3000 FORMICA-2 NO. = RS 1200 EACH = RS 2400 LINING PATTI- RS 7/FT.-20 FT = RS 140 MAPPING PATTI- RS 10/FT.- 30 FT. =RS 300 FEVICOL- RS 300/KG DOOR FRAME- RS 2000 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 12000 CONTRACTOR PROFIT= 15% = RS 1700 TOTAL COST= RS 13700
Result of RATE ANALYSIS ( Rs per Unit ) 13700 RS
Todays BUZZ Word TO ACHIEVE OWN BRAND NAME IN THE MARKET IT REQUIRES HARD WORK , CLOSE CO-CORDINATION AND THE SUPPORT OF QALIFIED PERSONS IS REQUIRED. THERE IS SO MUCH DIFFERENCE IN OUR THEROY KNOWLEDGE WHATEVER WE ARE STUDYING DURING OUR DEGREE COURSE AND PRACTICAL IMPLEMENTATION OF THIS KNOWLEDGE ON SITE. THERE ARE LOTS OF MANEGERIAL SKILLS ARE REQUIRED TO THE HANDLE THE SITE PROPERLY. THE ENGINEER SHOULD HAVE GOOD CO-ORDINATION WITH THE SITE SUPERVISOR ON THE SITE TO GET THE DETAIL INFORMATION ABOUT THE WORK THAT WAS ALLOTED TO THEM AND WHAT IS THE PROGRESS OF WORK. THERE IS TENDENCY OF WORKERS ON THE SITE TO WORK ACCORDING TO THEIR EXPERIENCE AND NOT WITH THE INSTRUCTION GIVEN TO THEM . I OBSERVED ON THE SITE MANY TIMES , DURING MIXING OF CONCRETE WATER IS NOT ADDED ACCORDING TO THE PROPORTION GIVEN TO THEM BUT THEY ARE ADDING ACCORDING TO THEM AND SOMETIMES THEY ARE NOT USING THE WEIGH BATCHING MACHINE , THEY ARE DIRECTLY THROWN THE SAND IN THE BUCKET OF MIXERS. SO FROM THIS I LEARNED THAT FOR THE QUALITY WORK TO BE DONE , IT REQUIRES CON TINOUS REGULAR OBSERVATIONS. ENGINEER SHOULD BE PRESENT ON SITE DURING THE MOST IMPORTANTS WORKS GOING ON THE SITE SUCH AS LINE OUT , CASTING OF BEAMS , COLUMN , SLABS. BECAUSE IF THE SUPERVISOR OR WORKER PRSENT ON THE SITE FOUND ANY TECHNICAL PROBLEM RELATED TO THE WORK THEN IT SHOULD BE INSTANTLY SOLVED BY THE ENGINEER WITHOUT DELAY IN THE WORK. I HAVE SEEN MANY TIMES THAT THE WORK ALLOTED TO THE WORKERS WITH THE DRAWINGS AND IN ACTUAL EXECUTION OF WORK THERE MIGHT BE POSIBILITY OF ERRORS. SOMETIMES ALSO THERE IS POSSIBILTY OF FAULT IN THE DRAWINGS PROVIDED BY THE ARCHITECTURES. IF ENGINEER IS PRESENT ON SITE THE PRROBLEMS LIKE THIS CAN BE EASILY SOLVED. ALONG WITH THE QUALITY OF TECHNICAL THINGS IT IS VERY IMPORTANT THAT HOW WILL YOU COMMUNICATE WITH THE CUSTOMERS . CIVIL ENGINEER SHOULD HAVE THIS KIND OF QUALITY WHICH WILL BE HELPFUL IN CUMMUNICATION WITH THE PEOPLE IN THE MARKETING WORLD. IF WE DONE OUR WORK WITH GOOD SUPERVISION AND ACCURACY THEN WE CAN SURE ABOUT THAT WE WILL NOT REQUIRED ANY TYPE OF ADMIXTURE AND CHEMICALS TO IMPROVE OUR QUALITY OF CONCRETE. BEFORE DOING ANY MAJOR WORK SUCH AS CASTING OF 10-12 COLUMNS AT A TIME THEN WE HAVE TO PREPARE FIRST TEST CUBE SPECIMENS WITH THE DECIDED PROPORTION THEN AFTER TESTING REPORTS THE PERMISSION IS GIVEN TO THE FURTHER WORK. IF YOU WANT USE ANY TYPE OF CONSTRUCTION MATERIAL ON SITE THEN IT SHOULD BE TESTED FIRST FOR ITS PERFORMANCE THEN ACCORDING TO THAT IT WILL USED . OTHERWISE THERE IS POSSIBILITY THAT IT WILLL CAUSE WASTGE OF MONEY UNECCESARILY . NOW A DAYS ACCORDING TO THE ENVIROMENTAL CONDITITONS IT IS MUST THAT WE HAVE TO APPLY SOME KIND GREEN TECNOLOGY TO THE BUILDINGS. THIS CAN BE DONE BY USING FLY ASH BRICKS , FLY ASH MIXED CEMENT IN THE CONSTRUCTION OF BUILDING. BY ADOPTING THE RAIN WATER HARVESTING TECNIQUES OR GROUND WATER RECHARGING , BY PROVIDING SEWAGE TREATMENT PLANTS AND SOLAR PANELS ARE USED TO HEAT THE WATER ALSO UTILISIG THE ELECTRICITY GENERATED BY THIS FOR PARKING OR IN COMMAN AREAS OF THE BUILDINGS. OVERALL YOU WILL REQUIRED GOOD CO-ORDINATION WITH THE PEOPLES ON THE SITE TO DO THE WORK IN GOOD MANNER.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: shindeamol5255@yahoo.in
Subject: 13546-12

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHINDE AMOL JAGANNATH
Exam No. 13546
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To check the preparation required before casting the slab.
Details of how you Planned & Executed the allotted work we divide ourself into groups. one group is on floor of slab and one is near mixer ,weigh batcher.
Details of the Construction Procedure / Activity / Technology learned today before casting of slab first the centering work is checked by the structural engineer then the permission is given for the casting of slab. whether the cover blocks, chairs are provided or not it is also checked by the engineer. then the water is sprayed on the surface of slab bottom so that it can remove easily and good finishing is obtained. terrace level slab is constructed waterproof by mixing the waterproofing chemicals in the concrete. terrace slab and sunk slab is also treated with the chemicals.if slab casting during night time then proper lighting arrangement is provided.
Details of the Construction Materials learned today no new materials are learned today.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings and working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3000 FORMICA-2 NO. = RS 1200 EACH = RS 2400 LINING PATTI- RS 7/FT.-20 FT = RS 140 MAPPING PATTI- RS 10/FT.- 30 FT. =RS 300 FEVICOL- RS 300/KG DOOR FRAME- RS 2000 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 12000 CONTRACTOR PROFIT= 15% = RS 1700 TOTAL COST= RS 13700
Result of RATE ANALYSIS ( Rs per Unit ) 13700 RS
Todays BUZZ Word TO ACHIEVE OWN BRAND NAME IN THE MARKET IT REQUIRES HARD WORK , CLOSE CO-CORDINATION AND THE SUPPORT OF QALIFIED PERSONS IS REQUIRED. THERE IS SO MUCH DIFFERENCE IN OUR THEROY KNOWLEDGE WHATEVER WE ARE STUDYING DURING OUR DEGREE COURSE AND PRACTICAL IMPLEMENTATION OF THIS KNOWLEDGE ON SITE. THERE ARE LOTS OF MANEGERIAL SKILLS ARE REQUIRED TO THE HANDLE THE SITE PROPERLY. THE ENGINEER SHOULD HAVE GOOD CO-ORDINATION WITH THE SITE SUPERVISOR ON THE SITE TO GET THE DETAIL INFORMATION ABOUT THE WORK THAT WAS ALLOTED TO THEM AND WHAT IS THE PROGRESS OF WORK. THERE IS TENDENCY OF WORKERS ON THE SITE TO WORK ACCORDING TO THEIR EXPERIENCE AND NOT WITH THE INSTRUCTION GIVEN TO THEM . I OBSERVED ON THE SITE MANY TIMES , DURING MIXING OF CONCRETE WATER IS NOT ADDED ACCORDING TO THE PROPORTION GIVEN TO THEM BUT THEY ARE ADDING ACCORDING TO THEM AND SOMETIMES THEY ARE NOT USING THE WEIGH BATCHING MACHINE , THEY ARE DIRECTLY THROWN THE SAND IN THE BUCKET OF MIXERS. SO FROM THIS I LEARNED THAT FOR THE QUALITY WORK TO BE DONE , IT REQUIRES CON TINOUS REGULAR OBSERVATIONS. ENGINEER SHOULD BE PRESENT ON SITE DURING THE MOST IMPORTANTS WORKS GOING ON THE SITE SUCH AS LINE OUT , CASTING OF BEAMS , COLUMN , SLABS. BECAUSE IF THE SUPERVISOR OR WORKER PRSENT ON THE SITE FOUND ANY TECHNICAL PROBLEM RELATED TO THE WORK THEN IT SHOULD BE INSTANTLY SOLVED BY THE ENGINEER WITHOUT DELAY IN THE WORK. I HAVE SEEN MANY TIMES THAT THE WORK ALLOTED TO THE WORKERS WITH THE DRAWINGS AND IN ACTUAL EXECUTION OF WORK THERE MIGHT BE POSIBILITY OF ERRORS. SOMETIMES ALSO THERE IS POSSIBILTY OF FAULT IN THE DRAWINGS PROVIDED BY THE ARCHITECTURES. IF ENGINEER IS PRESENT ON SITE THE PRROBLEMS LIKE THIS CAN BE EASILY SOLVED. ALONG WITH THE QUALITY OF TECHNICAL THINGS IT IS VERY IMPORTANT THAT HOW WILL YOU COMMUNICATE WITH THE CUSTOMERS . CIVIL ENGINEER SHOULD HAVE THIS KIND OF QUALITY WHICH WILL BE HELPFUL IN CUMMUNICATION WITH THE PEOPLE IN THE MARKETING WORLD. IF WE DONE OUR WORK WITH GOOD SUPERVISION AND ACCURACY THEN WE CAN SURE ABOUT THAT WE WILL NOT REQUIRED ANY TYPE OF ADMIXTURE AND CHEMICALS TO IMPROVE OUR QUALITY OF CONCRETE. BEFORE DOING ANY MAJOR WORK SUCH AS CASTING OF 10-12 COLUMNS AT A TIME THEN WE HAVE TO PREPARE FIRST TEST CUBE SPECIMENS WITH THE DECIDED PROPORTION THEN AFTER TESTING REPORTS THE PERMISSION IS GIVEN TO THE FURTHER WORK. IF YOU WANT USE ANY TYPE OF CONSTRUCTION MATERIAL ON SITE THEN IT SHOULD BE TESTED FIRST FOR ITS PERFORMANCE THEN ACCORDING TO THAT IT WILL USED . OTHERWISE THERE IS POSSIBILITY THAT IT WILLL CAUSE WASTGE OF MONEY UNECCESARILY . NOW A DAYS ACCORDING TO THE ENVIROMENTAL CONDITITONS IT IS MUST THAT WE HAVE TO APPLY SOME KIND GREEN TECNOLOGY TO THE BUILDINGS. THIS CAN BE DONE BY USING FLY ASH BRICKS , FLY ASH MIXED CEMENT IN THE CONSTRUCTION OF BUILDING. BY ADOPTING THE RAIN WATER HARVESTING TECNIQUES OR GROUND WATER RECHARGING , BY PROVIDING SEWAGE TREATMENT PLANTS AND SOLAR PANELS ARE USED TO HEAT THE WATER ALSO UTILISIG THE ELECTRICITY GENERATED BY THIS FOR PARKING OR IN COMMAN AREAS OF THE BUILDINGS. OVERALL YOU WILL REQUIRED GOOD CO-ORDINATION WITH THE PEOPLES ON THE SITE TO DO THE WORK IN GOOD MANNER.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-12

Company Name Shivshakti Constructions
Project Name & Site Address chandramilla
Students Name (Surname_First Name_Middle Name) patil sharad shankarrav
Exam No. 10897
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of concreting of column. .
Details of how you Planned & Executed the allotted work we observed whether the labors are mixing the concrete in proper proportion .then we went on the top of the slab & there we observed how concreting of column is done. .
Details of the Construction Procedure / Activity / Technology learned today today we observed the procedure of column casting .first the formwork is prepared for the concreting of column .then the concrete ingredients are mixed in suitable proportion & concrete is prepared .then the concreting of column is done .& also the vibrating is done for reducing the voids. .
Details of the Construction Materials learned today today we discussed about the pvc pipes ,timber & glass. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today for good environment ,drainage system should be done properly . .
Details of the Construction / Engineering Drawings observed today today we observed the drawing of column. .
Details of the Bye Laws referred today in bye-laws today we referred the points of lighting & ventilation of the room. .
Details of any Managerial Skill learned today the supervisor also inspected the concreting of column .weather the concreting is done properly or not & also he checked the uniformity of the formwork before the concreting is done. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR door Window Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft. Material : Burma Teak wood : 63784.00 { Burma Teak wood for Frame & Shutter Hinges 6 nos. : 900.00 {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Glas : Rs. 38.22/ Sqft.678.41 ( 17.75 Sqft. X 38.22 = 678.41 /-) TOTAL Rs.66850.41/window Labour for Flush door15% 10027.56 Say Rs. 10000/door
Result of RATE ANALYSIS ( Rs per Unit ) 10000/door
Todays BUZZ Word we are glad & thankful to the dept.of civil engineering & hod for giving us opportunity to understand the construction industry & work .this training programme.help me in better understanding of the various therotical subjects it also open us to the what construction industry & give the brief idea about the challanges & the opportunity in industry it help in co relating the therotical concepts & practical consideration .it gives idea about how construction work is conducted .we thoroughly understand detailed construction procedures of various activities .it also helps in understanding the design procedure upto some extent .it also give opportunity to understand the drawing & we also learned how to carry out the work as per this training programme help us alot & we are greatful to be part of the same . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: buntyphonde@gmail.com
Subject: 10899-12

Company Name Shivshakti Constructions
Project Name & Site Address chandramilla
Students Name (Surname_First Name_Middle Name) phonde pravin tukaram
Exam No. 10899
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of concreting of column. .
Details of how you Planned & Executed the allotted work we observed whether the labors are mixing the concrete in proper proportion .then we went on the top of the slab & there we observed how concreting of column is done. .
Details of the Construction Procedure / Activity / Technology learned today today we observed the procedure of column casting .first the formwork is prepared for the concreting of column .then the concrete ingredients are mixed in suitable proportion & concrete is prepared .then the concreting of column is done .& also the vibrating is done for reducing the voids. .
Details of the Construction Materials learned today today we discussed about the pvc pipes ,timber & glass. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today for good environment ,drainage system should be done properly . .
Details of the Construction / Engineering Drawings observed today today we observed the drawing of column. .
Details of the Bye Laws referred today in bye-laws today we referred the points of lighting & ventilation of the room. .
Details of any Managerial Skill learned today the supervisor also inspected the concreting of column .weather the concreting is done properly or not & also he checked the uniformity of the formwork before the concreting is done. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR door Window Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft. Material : Burma Teak wood : 63784.00 { Burma Teak wood for Frame & Shutter Hinges 6 nos. : 900.00 {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Glas : Rs. 38.22/ Sqft.678.41 ( 17.75 Sqft. X 38.22 = 678.41 /-) TOTAL Rs.66850.41/window Labour for Flush door15% 10027.56 Say Rs. 10000/door
Result of RATE ANALYSIS ( Rs per Unit ) 10000/door
Todays BUZZ Word we are glad & thankful to the dept.of civil engineering & hod for giving us opportunity to understand the construction industry & work .this training programme.help me in better understanding of the various therotical subjects it also open us to the what construction industry & give the brief idea about the challanges & the opportunity in industry it help in co relating the therotical concepts & practical consideration .it gives idea about how construction work is conducted .we thoroughly understand detailed construction procedures of various activities .it also helps in understanding the design procedure upto some extent .it also give opportunity to understand the drawing & we also learned how to carry out the work as per this training programme help us alot & we are greatful to be part of the same . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-12

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Redekar Shantanu Ravindra
Exam No. 13566
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Observe the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of form work of column. 4) Arrangement of form work of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilization of crushed sand instead of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other furniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today 1) Provision for Ramps In case of parking space provided in basement at least 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the formwork of slab with respect to architectural reference. 3) Control the wastage of material. 4) communication between site in charge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88/-
Todays BUZZ Word OUR Experence- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , coloring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-12

Company Name Shivshakti Constructions
Project Name & Site Address chandramilla
Students Name (Surname_First Name_Middle Name) tambte trusha sitaram
Exam No. 10902
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of concreting of column. .
Details of how you Planned & Executed the allotted work we observed whether the labors are mixing the concrete in proper proportion .then we went on the top of the slab & there we observed how concreting of column is done. .
Details of the Construction Procedure / Activity / Technology learned today today we observed the procedure of column casting .first the formwork is prepared for the concreting of column .then the concrete ingredients are mixed in suitable proportion & concrete is prepared .then the concreting of column is done .& also the vibrating is done for reducing the voids. .
Details of the Construction Materials learned today today we discussed about the pvc pipes ,timber & glass. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today for good environment ,drainage system should be done properly . .
Details of the Construction / Engineering Drawings observed today today we observed the drawing of column. .
Details of the Bye Laws referred today in bye-laws today we referred the points of lighting & ventilation of the room. .
Details of any Managerial Skill learned today the supervisor also inspected the concreting of column .weather the concreting is done properly or not & also he checked the uniformity of the formwork before the concreting is done. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR door Window Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft. Material : Burma Teak wood : 63784.00 { Burma Teak wood for Frame & Shutter Hinges 6 nos. : 900.00 {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Glas : Rs. 38.22/ Sqft.678.41 ( 17.75 Sqft. X 38.22 = 678.41 /-) TOTAL Rs.66850.41/window Labour for Flush door15% 10027.56 Say Rs. 10000/door
Result of RATE ANALYSIS ( Rs per Unit ) 10000/door
Todays BUZZ Word we are glad & thankful to the dept.of civil engineering & hod for giving us opportunity to understand the construction industry & work .this training programme.help me in better understanding of the various therotical subjects it also open us to the what construction industry & give the brief idea about the challanges & the opportunity in industry it help in co relating the therotical concepts & practical consideration .it gives idea about how construction work is conducted .we thoroughly understand detailed construction procedures of various activities .it also helps in understanding the design procedure upto some extent .it also give opportunity to understand the drawing & we also learned how to carry out the work as per this training programme help us alot & we are greatful to be part of the same . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-12

Company Name Shivshakti Constructions
Project Name & Site Address chandramilla
Students Name (Surname_First Name_Middle Name) patil abhishek dadasaheb
Exam No. 10895
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of concreting of column. .
Details of how you Planned & Executed the allotted work we observed whether the labors are mixing the concrete in proper proportion .then we went on the top of the slab & there we observed how concreting of column is done. .
Details of the Construction Procedure / Activity / Technology learned today today we observed the procedure of column casting .first the formwork is prepared for the concreting of column .then the concrete ingredients are mixed in suitable proportion & concrete is prepared .then the concreting of column is done .& also the vibrating is done for reducing the voids. . .
Details of the Construction Materials learned today today we discussed about the pvc pipes ,timber & glass. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today for good environment ,drainage system should be done properly . .
Details of the Construction / Engineering Drawings observed today today we observed the drawing of column. .
Details of the Bye Laws referred today in bye-laws today we referred the points of lighting & ventilation of the room. .
Details of any Managerial Skill learned today the supervisor also inspected the concreting of column .weather the concreting is done properly or not & also he checked the uniformity of the formwork before the concreting is done. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR door Window Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft. Material : Burma Teak wood : 63784.00 { Burma Teak wood for Frame & Shutter Hinges 6 nos. : 900.00 {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Glas : Rs. 38.22/ Sqft.678.41 ( 17.75 Sqft. X 38.22 = 678.41 /-) TOTAL Rs.66850.41/window Labour for Flush door15% 10027.56 Say Rs. 10000/door
Result of RATE ANALYSIS ( Rs per Unit ) 10000/door
Todays BUZZ Word we are glad & thankful to the dept.of civil engineering & hod for giving us opportunity to understand the construction industry & work .this training programme.help me in better understanding of the various therotical subjects it also open us to the what construction industry & give the brief idea about the challanges & the opportunity in industry it help in co relating the therotical concepts & practical consideration .it gives idea about how construction work is conducted .we thoroughly understand detailed construction procedures of various activities .it also helps in understanding the design procedure upto some extent .it also give opportunity to understand the drawing & we also learned how to carry out the work as per this training programme help us alot & we are greatful to be part of the same . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-12

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SINGH RAJAN RAJENDRA BAHADUR
Exam No. 13548
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To check the preparation required before casting the slab.
Details of how you Planned & Executed the allotted work we divide ourself into groups. one group is on floor of slab and one is near mixer ,weigh batcher.
Details of the Construction Procedure / Activity / Technology learned today before casting of slab first the centering work is checked by the structural engineer then the permission is given for the casting of slab. whether the cover blocks, chairs are provided or not it is also checked by the engineer. then the water is sprayed on the surface of slab bottom so that it can remove easily and good finishing is obtained. terrace level slab is constructed waterproof by mixing the waterproofing chemicals in the concrete. terrace slab and sunk slab is also treated with the chemicals.if slab casting during night time then proper lighting arrangement is provided.
Details of the Construction Materials learned today no new materials are learned today.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings and working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR DOOR MAIN DOOR PLYWOOD = RS 3000 FORMICA-2 NO. = RS 1200 EACH = RS 2400 LINING PATTI- RS 7/FT.-20 FT = RS 140 MAPPING PATTI- RS 10/FT.- 30 FT. =RS 300 FEVICOL- RS 300/KG DOOR FRAME- RS 2000 LUMP-SUMP- RS 200 LOCKS,HANDLES,STOPPER= RS. 1300 TOTAL= RS 12000 CONTRACTOR PROFIT= 15% = RS 1700 TOTAL COST= RS 13700
Result of RATE ANALYSIS ( Rs per Unit ) 13700 RS
Todays BUZZ Word TO ACHIEVE OWN BRAND NAME IN THE MARKET IT REQUIRES HARD WORK , CLOSE CO-CORDINATION AND THE SUPPORT OF QALIFIED PERSONS IS REQUIRED. THERE IS SO MUCH DIFFERENCE IN OUR THEROY KNOWLEDGE WHATEVER WE ARE STUDYING DURING OUR DEGREE COURSE AND PRACTICAL IMPLEMENTATION OF THIS KNOWLEDGE ON SITE. THERE ARE LOTS OF MANEGERIAL SKILLS ARE REQUIRED TO THE HANDLE THE SITE PROPERLY. THE ENGINEER SHOULD HAVE GOOD CO-ORDINATION WITH THE SITE SUPERVISOR ON THE SITE TO GET THE DETAIL INFORMATION ABOUT THE WORK THAT WAS ALLOTED TO THEM AND WHAT IS THE PROGRESS OF WORK. THERE IS TENDENCY OF WORKERS ON THE SITE TO WORK ACCORDING TO THEIR EXPERIENCE AND NOT WITH THE INSTRUCTION GIVEN TO THEM . I OBSERVED ON THE SITE MANY TIMES , DURING MIXING OF CONCRETE WATER IS NOT ADDED ACCORDING TO THE PROPORTION GIVEN TO THEM BUT THEY ARE ADDING ACCORDING TO THEM AND SOMETIMES THEY ARE NOT USING THE WEIGH BATCHING MACHINE , THEY ARE DIRECTLY THROWN THE SAND IN THE BUCKET OF MIXERS. SO FROM THIS I LEARNED THAT FOR THE QUALITY WORK TO BE DONE , IT REQUIRES CON TINOUS REGULAR OBSERVATIONS. ENGINEER SHOULD BE PRESENT ON SITE DURING THE MOST IMPORTANTS WORKS GOING ON THE SITE SUCH AS LINE OUT , CASTING OF BEAMS , COLUMN , SLABS. BECAUSE IF THE SUPERVISOR OR WORKER PRSENT ON THE SITE FOUND ANY TECHNICAL PROBLEM RELATED TO THE WORK THEN IT SHOULD BE INSTANTLY SOLVED BY THE ENGINEER WITHOUT DELAY IN THE WORK. I HAVE SEEN MANY TIMES THAT THE WORK ALLOTED TO THE WORKERS WITH THE DRAWINGS AND IN ACTUAL EXECUTION OF WORK THERE MIGHT BE POSIBILITY OF ERRORS. SOMETIMES ALSO THERE IS POSSIBILTY OF FAULT IN THE DRAWINGS PROVIDED BY THE ARCHITECTURES. IF ENGINEER IS PRESENT ON SITE THE PRROBLEMS LIKE THIS CAN BE EASILY SOLVED. ALONG WITH THE QUALITY OF TECHNICAL THINGS IT IS VERY IMPORTANT THAT HOW WILL YOU COMMUNICATE WITH THE CUSTOMERS . CIVIL ENGINEER SHOULD HAVE THIS KIND OF QUALITY WHICH WILL BE HELPFUL IN CUMMUNICATION WITH THE PEOPLE IN THE MARKETING WORLD. IF WE DONE OUR WORK WITH GOOD SUPERVISION AND ACCURACY THEN WE CAN SURE ABOUT THAT WE WILL NOT REQUIRED ANY TYPE OF ADMIXTURE AND CHEMICALS TO IMPROVE OUR QUALITY OF CONCRETE. BEFORE DOING ANY MAJOR WORK SUCH AS CASTING OF 10-12 COLUMNS AT A TIME THEN WE HAVE TO PREPARE FIRST TEST CUBE SPECIMENS WITH THE DECIDED PROPORTION THEN AFTER TESTING REPORTS THE PERMISSION IS GIVEN TO THE FURTHER WORK. IF YOU WANT USE ANY TYPE OF CONSTRUCTION MATERIAL ON SITE THEN IT SHOULD BE TESTED FIRST FOR ITS PERFORMANCE THEN ACCORDING TO THAT IT WILL USED . OTHERWISE THERE IS POSSIBILITY THAT IT WILLL CAUSE WASTGE OF MONEY UNECCESARILY . NOW A DAYS ACCORDING TO THE ENVIROMENTAL CONDITITONS IT IS MUST THAT WE HAVE TO APPLY SOME KIND GREEN TECNOLOGY TO THE BUILDINGS. THIS CAN BE DONE BY USING FLY ASH BRICKS , FLY ASH MIXED CEMENT IN THE CONSTRUCTION OF BUILDING. BY ADOPTING THE RAIN WATER HARVESTING TECNIQUES OR GROUND WATER RECHARGING , BY PROVIDING SEWAGE TREATMENT PLANTS AND SOLAR PANELS ARE USED TO HEAT THE WATER ALSO UTILISIG THE ELECTRICITY GENERATED BY THIS FOR PARKING OR IN COMMAN AREAS OF THE BUILDINGS. OVERALL YOU WILL REQUIRED GOOD CO-ORDINATION WITH THE PEOPLES ON THE SITE TO DO THE WORK IN GOOD MANNER.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-12

Company Name Shivshakti Constructions
Project Name & Site Address chandramilla
Students Name (Surname_First Name_Middle Name) sawant amit ganpat
Exam No. 10900
Working Day No. 12
Date (DD/MM/YYYY) 21-12-2010
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of concreting of column. .
Details of how you Planned & Executed the allotted work we observed whether the labors are mixing the concrete in proper proportion .then we went on the top of the slab & there we observed how concreting of column is done. .
Details of the Construction Procedure / Activity / Technology learned today today we observed the procedure of column casting .first the formwork is prepared for the concreting of column .then the concrete ingredients are mixed in suitable proportion & concrete is prepared .then the concreting of column is done .& also the vibrating is done for reducing the voids. .
Details of the Construction Materials learned today today we discussed about the pvc pipes ,timber & glass. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today for good environment ,drainage system should be done properly . .
Details of the Construction / Engineering Drawings observed today today we observed the drawing of column. .
Details of the Bye Laws referred today in bye-laws today we referred the points of lighting & ventilation of the room. .
Details of any Managerial Skill learned today the supervisor also inspected the concreting of column .weather the concreting is done properly or not & also he checked the uniformity of the formwork before the concreting is done. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR door Window Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft. Material : Burma Teak wood : 63784.00 { Burma Teak wood for Frame & Shutter Hinges 6 nos. : 900.00 {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Glas : Rs. 38.22/ Sqft.678.41 ( 17.75 Sqft. X 38.22 = 678.41 /-) TOTAL Rs.66850.41/window Labour for Flush door15% 10027.56 Say Rs. 10000/door
Result of RATE ANALYSIS ( Rs per Unit ) 10000/door
Todays BUZZ Word we are glad & thankful to the dept.of civil engineering & hod for giving us opportunity to understand the construction industry & work .this training programme.help me in better understanding of the various therotical subjects it also open us to the what construction industry & give the brief idea about the challanges & the opportunity in industry it help in co relating the therotical concepts & practical consideration .it gives idea about how construction work is conducted .we thoroughly understand detailed construction procedures of various activities .it also helps in understanding the design procedure upto some extent .it also give opportunity to understand the drawing & we also learned how to carry out the work as per this training programme help us alot & we are greatful to be part of the same . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-12

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Mohare Vishal Bhalchandra
Exam No. 13564
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Observe the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of form work of column. 4) Arrangement of form work of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilization of crushed sand instead of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other furniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today 1) Provision for Ramps In case of parking space provided in basement at least 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the formwork of slab with respect to architectural reference. 3) Control the wastage of material. 4) communication between site in charge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88/-
Todays BUZZ Word OUR Experence- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labors to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , coloring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-12

Company Name Chougule Sawant Developers
Project Name & Site Address Shree Samarth Nagar,New Balinge
Students Name (Surname_First Name_Middle Name) Katral Raju M.
Exam No. 13562
Working Day No. 12
Date (DD/MM/YYYY) 21.12.2010
Site Reporting Time (HH:MM am/pm) 9.00AM
Site Leaving Time (HH:MM am/pm) 4.00PM
Details of the Work Allotted to you today by the Site In-Charge To observe the concreting of slab
Details of how you Planned & Executed the allotted work First site incharge gave us the details of slab drawing. Then we observed the actual concreting.
Details of the Construction Procedure / Activity / Technology learned today We saw the brickwork of 3 bhk bunglow\' ground floor. All external walls are 230mm thk. & internal walls are of 150mm thk.
Details of the Construction Materials learned today Alluminium : This material is used for making of doors & windows. It is cheap ,economical,durable as compared to the wood.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today RAIN WATER HARVESTING : 1. This system is provided to the terraces of all types of buildings. 2. This system is used to utilise the available rain water. 3. It also used for ground water recharging. 4. This system is less expensive.
Details of the Construction / Engineering Drawings observed today We observed the detailed R.C.C. drawing of slab.
Details of the Bye Laws referred today OFFICE CABIN : 1. The size of the cabins shall not be less than 3.0 sq.m. 2. The clear passages with the divided space of any floor shall not be less than 0.9m.& the distance from the farthest space in cabin to any exit shall not be more than 18.5 m.
Details of any Managerial Skill learned today We learned how to plan the various types of works simulteniously such as excavation,footing,concreting etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) DOOR : per sq.m. Wood = 180.00 Rs. Fixtures & Fastnings = 80.00 Rs. Polishing & Finishing = 60.00 Rs. Labour cost = 130.00 Rs. Add 2% wastage TOTAL = 440.00 Rs./ sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 4400.00Rs.per sq.m.
Todays BUZZ Word SITE TRANING EXPERIENCE : 1. First day we meet to the owner & to the site incharge. 2. Then site incharge gave us the brochure of project & he explain the whole project. 3. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 4. In their project there are two appartments having each seven storeys. 5. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 6. Then next day we saw the excavation for the footings of bungalows & appartment. 7. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 8. We saw the trial pits for the bungalows. 9. We observed the building line out. 10. We observed the p.c.c. of footing & then casting of steps of footing. 11. In appartments after the casting of footing ground beams are casted. 12. Then plinth beam & r.c.c. wall casted upto plinth level. 13. Then murrum filling is done. 14. Then p.c.c is done the thk of p.c.c is 75 mm . 15. After that starter for column is casted. 16. After that column reinforcement is placed & checked by the site incharge. 17. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 18. We also learned that how the reinforcement is provided for the beam. 19. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 20. In r.c.c. structre slab reinforcement is important on order to construction of floors. 21. In r.c.c. slab reinforcement is provided in the form of one way & two way. 22. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 23. In their project they provides the sewage treatment plant in order to treat the sewage water. 24. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 25. We experienced that reinforcement checking,building line out,centering of columns,checking of column shutterimg,etc. 26. First day we meet to the owner & to the site incharge. 27. Then site incharge gave us the brochure of project & he explain the whole project. 28. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 29 . In their project there are two appartments having each seven storeys. 30. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 31. Then next day we saw the excavation for the footings of bungalows & appartment. 32. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 33. We saw the trial pits for the bungalows. 34. We observed the building line out. 35. We observed the p.c.c. of footing & then casting of steps of footing. 36. In appartments after the casting of footing ground beams are casted. 37. Then plinth beam & r.c.c. wall casted upto plinth level. 38. Then murrum filling is done. 39. Then p.c.c is done the thk of p.c.c is 75 mm . 40. After that starter for column is casted. 41. After that column reinforcement is placed & checked by the site incharge. 42. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 43. We also learned that how the reinforcement is provided for the beam. 44. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 45. In r.c.c. structre slab reinforcement is important on order to construction of floors. 46. In r.c.c. slab reinforcement is provided in the form of one way & two way. 47. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 48. In their project they provides the sewage treatment plant in order to treat the sewage water. 49. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 50. We experienced that reinforcement checking,building line out,centering of columns,checking of column shutterimg,etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Swapnil Raut, Mob.No.8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-12

Company Name Chougule Sawant Developers
Project Name & Site Address Shree Samarth Nagar,New Balinge
Students Name (Surname_First Name_Middle Name) Katral Raju M.
Exam No. 13562
Working Day No. 12
Date (DD/MM/YYYY) 21.12.2010
Site Reporting Time (HH:MM am/pm) 9.00AM
Site Leaving Time (HH:MM am/pm) 4.00PM
Details of the Work Allotted to you today by the Site In-Charge To observe the concreting of slab
Details of how you Planned & Executed the allotted work First site incharge gave us the details of slab drawing. Then we observed the actual concreting.
Details of the Construction Procedure / Activity / Technology learned today We saw the brickwork of 3 bhk bunglow\' ground floor. All external walls are 230mm thk. & internal walls are of 150mm thk.
Details of the Construction Materials learned today Alluminium : This material is used for making of doors & windows. It is cheap ,economical,durable as compared to the wood.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today RAIN WATER HARVESTING : 1. This system is provided to the terraces of all types of buildings. 2. This system is used to utilise the available rain water. 3. It also used for ground water recharging. 4. This system is less expensive.
Details of the Construction / Engineering Drawings observed today We observed the detailed R.C.C. drawing of slab.
Details of the Bye Laws referred today OFFICE CABIN : 1. The size of the cabins shall not be less than 3.0 sq.m. 2. The clear passages with the divided space of any floor shall not be less than 0.9m.& the distance from the farthest space in cabin to any exit shall not be more than 18.5 m.
Details of any Managerial Skill learned today We learned how to plan the various types of works simulteniously such as excavation,footing,concreting etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) DOOR : per sq.m. Wood = 180.00 Rs. Fixtures & Fastnings = 80.00 Rs. Polishing & Finishing = 60.00 Rs. Labour cost = 130.00 Rs. Add 2% wastage TOTAL = 440.00 Rs./ sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 4400.00Rs.per sq.m.
Todays BUZZ Word SITE TRANING EXPERIENCE : 1. First day we meet to the owner & to the site incharge. 2. Then site incharge gave us the brochure of project & he explain the whole project. 3. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 4. In their project there are two appartments having each seven storeys. 5. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 6. Then next day we saw the excavation for the footings of bungalows & appartment. 7. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 8. We saw the trial pits for the bungalows. 9. We observed the building line out. 10. We observed the p.c.c. of footing & then casting of steps of footing. 11. In appartments after the casting of footing ground beams are casted. 12. Then plinth beam & r.c.c. wall casted upto plinth level. 13. Then murrum filling is done. 14. Then p.c.c is done the thk of p.c.c is 75 mm . 15. After that starter for column is casted. 16. After that column reinforcement is placed & checked by the site incharge. 17. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 18. We also learned that how the reinforcement is provided for the beam. 19. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 20. In r.c.c. structre slab reinforcement is important on order to construction of floors. 21. In r.c.c. slab reinforcement is provided in the form of one way & two way. 22. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 23. In their project they provides the sewage treatment plant in order to treat the sewage water. 24. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 25. We experienced that reinforcement checking,building line out,centering of columns,checking of column shutterimg,etc. 26. First day we meet to the owner & to the site incharge. 27. Then site incharge gave us the brochure of project & he explain the whole project. 28. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 29 . In their project there are two appartments having each seven storeys. 30. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 31. Then next day we saw the excavation for the footings of bungalows & appartment. 32. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 33. We saw the trial pits for the bungalows. 34. We observed the building line out. 35. We observed the p.c.c. of footing & then casting of steps of footing. 36. In appartments after the casting of footing ground beams are casted. 37. Then plinth beam & r.c.c. wall casted upto plinth level. 38. Then murrum filling is done. 39. Then p.c.c is done the thk of p.c.c is 75 mm . 40. After that starter for column is casted. 41. After that column reinforcement is placed & checked by the site incharge. 42. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 43. We also learned that how the reinforcement is provided for the beam. 44. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 45. In r.c.c. structre slab reinforcement is important on order to construction of floors. 46. In r.c.c. slab reinforcement is provided in the form of one way & two way. 47. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 48. In their project they provides the sewage treatment plant in order to treat the sewage water. 49. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 50. We experienced that reinforcement checking,building line out,centering of columns,checking of column shutterimg,etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Swapnil Raut, Mob.No.8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558-12

Company Name Chougule Sawant Developers
Project Name & Site Address Shree Samarth Nagar, New Balinge
Students Name (Surname_First Name_Middle Name) Chavan Shivprasad P.
Exam No. 13558
Working Day No. 12
Date (DD/MM/YYYY) 21.12.2010
Site Reporting Time (HH:MM am/pm) 9.00AM
Site Leaving Time (HH:MM am/pm) 4.00PM
Details of the Work Allotted to you today by the Site In-Charge To observe the concreting of slab
Details of how you Planned & Executed the allotted work First site incharge gave us the details of slab drawing. Then we observed the actual concreting.
Details of the Construction Procedure / Activity / Technology learned today We saw the brickwork of 3 bhk bunglow\' ground floor. All external walls are 230mm thk. & internal walls are of 150mm thk.
Details of the Construction Materials learned today Alluminium : This material is used for making of doors & windows. It is cheap ,economical,durable as compared to the wood.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today RAIN WATER HARVESTING : 1. This system is provided to the terraces of all types of buildings. 2. This system is used to utilise the available rain water. 3. It also used for ground water recharging. 4. This system is less expensive.
Details of the Construction / Engineering Drawings observed today We observed the detailed R.C.C. drawing of slab.
Details of the Bye Laws referred today OFFICE CABIN : 1. The size of the cabins shall not be less than 3.0 sq.m. 2. The clear passages with the divided space of any floor shall not be less than 0.9m.& the distance from the farthest space in cabin to any exit shall not be more than 18.5 m.
Details of any Managerial Skill learned today We learned how to plan the various types of works simulteniously such as excavation,footing,concreting etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) DOOR : per sq.m. Wood = 180.00 Rs. Fixtures & Fastnings = 80.00 Rs. Polishing & Finishing = 60.00 Rs. Labour cost = 130.00 Rs. Add 2% wastage TOTAL = 440.00 Rs./ sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 4400.00Rs.per sq.m.
Todays BUZZ Word SITE TRANING EXPERIENCE : 1. First day we meet to the owner & to the site incharge. 2. Then site incharge gave us the brochure of project & he explain the whole project. 3. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 4. In their project there are two appartments having each seven storeys. 5. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 6. Then next day we saw the excavation for the footings of bungalows & appartment. 7. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 8. We saw the trial pits for the bungalows. 9. We observed the building line out. 10. We observed the p.c.c. of footing & then casting of steps of footing. 11. In appartments after the casting of footing ground beams are casted. 12. Then plinth beam & r.c.c. wall casted upto plinth level. 13. Then murrum filling is done. 14. Then p.c.c is done the thk of p.c.c is 75 mm . 15. After that starter for column is casted. 16. After that column reinforcement is placed & checked by the site incharge. 17. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 18. We also learned that how the reinforcement is provided for the beam. 19. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 20. In r.c.c. structre slab reinforcement is important on order to construction of floors. 21. In r.c.c. slab reinforcement is provided in the form of one way & two way. 22. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 23. In their project they provides the sewage treatment plant in order to treat the sewage water. 24. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 25. We experienced that reinforcement checking,building line out,centering of columns,checking of column shutterimg,etc. 26. First day we meet to the owner & to the site incharge. 27. Then site incharge gave us the brochure of project & he explain the whole project. 28. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 29 . In their project there are two appartments having each seven storeys. 30. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 31. Then next day we saw the excavation for the footings of bungalows & appartment. 32. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 33. We saw the trial pits for the bungalows. 34. We observed the building line out. 35. We observed the p.c.c. of footing & then casting of steps of footing. 36. In appartments after the casting of footing ground beams are casted. 37. Then plinth beam & r.c.c. wall casted upto plinth level. 38. Then murrum filling is done. 39. Then p.c.c is done the thk of p.c.c is 75 mm . 40. After that starter for column is casted. 41. After that column reinforcement is placed & checked by the site incharge. 42. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 43. We also learned that how the reinforcement is provided for the beam. 44. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 45. In r.c.c. structre slab reinforcement is important on order to construction of floors. 46. In r.c.c. slab reinforcement is provided in the form of one way & two way. 47. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 48. In their project they provides the sewage treatment plant in order to treat the sewage water. 49. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 50. We experienced that reinforcement checking,building line out,centering of columns,checking of column shutterimg,etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Swapnil Raut, Mob.No.8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: Rohit_patil@rediffmail.com
Subject: 13565-12

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Patil Rohit Ashok
Exam No. 13565
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Observe the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of formwork of column. 4) Arrangement of formwork of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water proofing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilization of crushed sand instead of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other furniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today 1) Provision for Ramps In case of parking space provided in basement at least 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the form work of slab with respect to architectural reference. 3) Control the wastage of material. 4) communication between site in charge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88/-
Todays BUZZ Word OUR Experence- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , coloring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13561-12

Company Name Chougule Sawant Developers
Project Name & Site Address Shree Samarth Nagar, New Balinge
Students Name (Surname_First Name_Middle Name) Jadhav Sardar Swaroop J.
Exam No. 13561
Working Day No. 12
Date (DD/MM/YYYY) 21.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe the concreting of slab
Details of how you Planned & Executed the allotted work First site incharge gave us the details of slab drawing. Then we observed the actual concreting.
Details of the Construction Procedure / Activity / Technology learned today We saw the brickwork of 3 bhk bunglow\' ground floor. All external walls are 230mm thk. & internal walls are of 150mm thk.
Details of the Construction Materials learned today Alluminium : This material is used for making of doors & windows. It is cheap ,economical,durable as compared to the wood.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today RAIN WATER HARVESTING : 1. This system is provided to the terraces of all types of buildings. 2. This system is used to utilise the available rain water. 3. It also used for ground water recharging. 4. This system is less expensive.
Details of the Construction / Engineering Drawings observed today We observed the detailed R.C.C. drawing of slab.
Details of the Bye Laws referred today OFFICE CABIN : 1. The size of the cabins shall not be less than 3.0 sq.m. 2. The clear passages with the divided space of any floor shall not be less than 0.9m.& the distance from the farthest space in cabin to any exit shall not be more than 18.5 m.
Details of any Managerial Skill learned today We learned how to plan the various types of works simulteniously such as excavation,footing,concreting etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) DOOR : per sq.m. Wood = 180.00 Rs. Fixtures & Fastnings = 80.00 Rs. Polishing & Finishing = 60.00 Rs. Labour cost = 130.00 Rs. Add 2% wastage TOTAL = 440.00 Rs./ sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 4400.00Rs.per sq.m.
Todays BUZZ Word SITE TRANING EXPERIENCE : 1. First day we meet to the owner & to the site incharge. 2. Then site incharge gave us the brochure of project & he explain the whole project. 3. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 4. In their project there are two appartments having each seven storeys. 5. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 6. Then next day we saw the excavation for the footings of bungalows & appartment. 7. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 8. We saw the trial pits for the bungalows. 9. We observed the building line out. 10. We observed the p.c.c. of footing & then casting of steps of footing. 11. In appartments after the casting of footing ground beams are casted. 12. Then plinth beam & r.c.c. wall casted upto plinth level. 13. Then murrum filling is done. 14. Then p.c.c is done the thk of p.c.c is 75 mm . 15. After that starter for column is casted. 16. After that column reinforcement is placed & checked by the site incharge. 17. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 18. We also learned that how the reinforcement is provided for the beam. 19. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 20. In r.c.c. structre slab reinforcement is important on order to construction of floors. 21. In r.c.c. slab reinforcement is provided in the form of one way & two way. 22. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 23. In their project they provides the sewage treatment plant in order to treat the sewage water. 24. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 25. We experienced that reinforcement checking,building line out,centering of columns,checking of column shutterimg,etc. 26. First day we meet to the owner & to the site incharge. 27. Then site incharge gave us the brochure of project & he explain the whole project. 28. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 29 . In their project there are two appartments having each seven storeys. 30. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 31. Then next day we saw the excavation for the footings of bungalows & appartment. 32. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 33. We saw the trial pits for the bungalows. 34. We observed the building line out. 35. We observed the p.c.c. of footing & then casting of steps of footing. 36. In appartments after the casting of footing ground beams are casted. 37. Then plinth beam & r.c.c. wall casted upto plinth level. 38. Then murrum filling is done. 39. Then p.c.c is done the thk of p.c.c is 75 mm . 40. After that starter for column is casted. 41. After that column reinforcement is placed & checked by the site incharge. 42. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 43. We also learned that how the reinforcement is provided for the beam. 44. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 45. In r.c.c. structre slab reinforcement is important on order to construction of floors. 46. In r.c.c. slab reinforcement is provided in the form of one way & two way. 47. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 48. In their project they provides the sewage treatment plant in order to treat the sewage water. 49. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 50. We experienced that reinforcement checking,building line out,centering of columns,checking of column shutterimg,etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Swapnil Raut, Mob.No.8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-12

Company Name Chougule Sawant Developers
Project Name & Site Address shree samarth nagar, new balinge.
Students Name (Surname_First Name_Middle Name) Jade Madhavrao Anil
Exam No. 13560
Working Day No. 12
Date (DD/MM/YYYY) 21.12.2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To observe the concreting of slab
Details of how you Planned & Executed the allotted work First site incharge gave us the details of slab drawing. Then we observed the actual concreting.
Details of the Construction Procedure / Activity / Technology learned today We saw the brickwork of 3 bhk bunglow\' ground floor. All external walls are 230mm thk. & internal walls are of 150mm thk.
Details of the Construction Materials learned today Alluminium : This material is used for making of doors & windows. It is cheap ,economical,durable as compared to the wood.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today RAIN WATER HARVESTING : 1. This system is provided to the terraces of all types of buildings. 2. This system is used to utilise the available rain water. 3. It also used for ground water recharging. 4. This system is less expensive.
Details of the Construction / Engineering Drawings observed today We observed the detailed R.C.C. drawing of slab.
Details of the Bye Laws referred today OFFICE CABIN : 1. The size of the cabins shall not be less than 3.0 sq.m. 2. The clear passages with the divided space of any floor shall not be less than 0.9m.& the distance from the farthest space in cabin to any exit shall not be more than 18.5 m.
Details of any Managerial Skill learned today We learned how to plan the various types of works simulteniously such as excavation,footing,concreting etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) DOOR : per sq.m. Wood = 180.00 Rs. Fixtures & Fastnings = 80.00 Rs. Polishing & Finishing = 60.00 Rs. Labour cost = 130.00 Rs. Add 2% wastage TOTAL = 440.00 Rs./ sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 4400.00Rs.per sq.m.
Todays BUZZ Word SITE TRANING EXPERIENCE : 1. First day we meet to the owner & to the site incharge. 2. Then site incharge gave us the brochure of project & he explain the whole project. 3. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 4. In their project there are two appartments having each seven storeys. 5. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 6. Then next day we saw the excavation for the footings of bungalows & appartment. 7. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 8. We saw the trial pits for the bungalows. 9. We observed the building line out. 10. We observed the p.c.c. of footing & then casting of steps of footing. 11. In appartments after the casting of footing ground beams are casted. 12. Then plinth beam & r.c.c. wall casted upto plinth level. 13. Then murrum filling is done. 14. Then p.c.c is done the thk of p.c.c is 75 mm . 15. After that starter for column is casted. 16. After that column reinforcement is placed & checked by the site incharge. 17. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 18. We also learned that how the reinforcement is provided for the beam. 19. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 20. In r.c.c. structre slab reinforcement is important on order to construction of floors. 21. In r.c.c. slab reinforcement is provided in the form of one way & two way. 22. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 23. In their project they provides the sewage treatment plant in order to treat the sewage water. 24. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 25. We experienced that reinforcement checking,building line out,centering of 26. First day we meet to the owner & to the site incharge. 27. Then site incharge gave us the brochure of project & he explain the whole project. 28. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 29 . In their project there are two appartments having each seven storeys. 30. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 31. Then next day we saw the excavation for the footings of bungalows & appartment. 32. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 33. We saw the trial pits for the bungalows. 34. We observed the building line out. 35. We observed the p.c.c. of footing & then casting of steps of footing. 36. In appartments after the casting of footing ground beams are casted. 37. Then plinth beam & r.c.c. wall casted upto plinth level. 38. Then murrum filling is done. 39. Then p.c.c is done the thk of p.c.c is 75 mm . 40. After that starter for column is casted. 41. After that column reinforcement is placed & checked by the site incharge. 42. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 43. We also learned that how the reinforcement is provided for the beam. 44. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 45. In r.c.c. structre slab reinforcement is important on order to construction of floors. 46. In r.c.c. slab reinforcement is provided in the form of one way & two way. 47. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 48. In their project they provides the sewage treatment plant in order to treat the sewage water. 49. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 50. We experienced that reinforcement checking,building line out,centering of columns,checking of column shutterimg,etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Swapnil Raut, Mob.No.8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: pradnyatirmare@yahoo.co.in
Subject: 13572-12

Company Name Chougule Sawant Developers
Project Name & Site Address Shree Samarh Nagar, New Balinge
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya A.
Exam No. 13572
Working Day No. 12
Date (DD/MM/YYYY) 21.12.2010
Site Reporting Time (HH:MM am/pm) 9.00AM
Site Leaving Time (HH:MM am/pm) 4.00PM
Details of the Work Allotted to you today by the Site In-Charge To observe the concreting of slab
Details of how you Planned & Executed the allotted work First site incharge gave us the details of slab drawing. Then we observed the actual concreting.
Details of the Construction Procedure / Activity / Technology learned today We saw the brickwork of 3 bhk bunglow\' ground floor. All external walls are 230mm thk. & internal walls are of 150mm thk.
Details of the Construction Materials learned today Alluminium : This material is used for making of doors & windows. It is cheap ,economical,durable as compared to the wood.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today RAIN WATER HARVESTING : 1. This system is provided to the terraces of all types of buildings. 2. This system is used to utilise the available rain water. 3. It also used for ground water recharging. 4. This system is less expensive.
Details of the Construction / Engineering Drawings observed today We observed the detailed R.C.C. drawing of slab.
Details of the Bye Laws referred today OFFICE CABIN : 1. The size of the cabins shall not be less than 3.0 sq.m. 2. The clear passages with the divided space of any floor shall not be less than 0.9m.& the distance from the farthest space in cabin to any exit shall not be more than 18.5 m.
Details of any Managerial Skill learned today We learned how to plan the various types of works simulteniously such as excavation,footing,concreting etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) DOOR : per sq.m. Wood = 180.00 Rs. Fixtures & Fastnings = 80.00 Rs. Polishing & Finishing = 60.00 Rs. Labour cost = 130.00 Rs. Add 2% wastage TOTAL = 440.00 Rs./ sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 4400.00Rs.per sq.m
Todays BUZZ Word SITE TRANING EXPERIENCE : 1. First day we meet to the owner & to the site incharge. 2. Then site incharge gave us the brochure of project & he explain the whole project. 3. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 4. In their project there are two appartments having each seven storeys. 5. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 6. Then next day we saw the excavation for the footings of bungalows & appartment. 7. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 8. We saw the trial pits for the bungalows. 9. We observed the building line out. 10. We observed the p.c.c. of footing & then casting of steps of footing. 11. In appartments after the casting of footing ground beams are casted. 12. Then plinth beam & r.c.c. wall casted upto plinth level. 13. Then murrum filling is done. 14. Then p.c.c is done the thk of p.c.c is 75 mm . 15. After that starter for column is casted. 16. After that column reinforcement is placed & checked by the site incharge. 17. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 18. We also learned that how the reinforcement is provided for the beam. 19. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 20. In r.c.c. structre slab reinforcement is important on order to construction of floors. 21. In r.c.c. slab reinforcement is provided in the form of one way & two way. 22. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 23. In their project they provides the sewage treatment plant in order to treat the sewage water. 24. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 25. We experienced that reinforcement checking,building line out,centering of 26. First day we meet to the owner & to the site incharge. 27. Then site incharge gave us the brochure of project & he explain the whole project. 28. He also shows the detailed plan & r.c.c. drawings of 3 bhk bungalows,row bungalows & appartments. 29 . In their project there are two appartments having each seven storeys. 30. There are 3 types of bunglows such as 3 bhk, 2.5 bhk, 2 bhk. 31. Then next day we saw the excavation for the footings of bungalows & appartment. 32. Then we saw the detailed drawing of excavation,footing size,centerline drawing, & column position. 33. We saw the trial pits for the bungalows. 34. We observed the building line out. 35. We observed the p.c.c. of footing & then casting of steps of footing. 36. In appartments after the casting of footing ground beams are casted. 37. Then plinth beam & r.c.c. wall casted upto plinth level. 38. Then murrum filling is done. 39. Then p.c.c is done the thk of p.c.c is 75 mm . 40. After that starter for column is casted. 41. After that column reinforcement is placed & checked by the site incharge. 42. Shuttering is applied for the casting of column & checking & levelling of shuttering is done. 43. We also learned that how the reinforcement is provided for the beam. 44. In the beam reinforcement we observed about the extra top, extra bottom,curtailed bars. 45. In r.c.c. structre slab reinforcement is important on order to construction of floors. 46. In r.c.c. slab reinforcement is provided in the form of one way & two way. 47. The speciality of their project is they provide economical staircase,it means that it does not contain any reinforcement,it is made only by using angle sections. 48. In their project they provides the sewage treatment plant in order to treat the sewage water. 49. They also provides the rain water harvesting system, we observed actual rain water harvesting method of sample bunglow. 50. We experienced that reinforcement checking,building line out,centering of columns,checking of column shutterimg,etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Swapnil Raut, Mob.No.8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-12

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Observe the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of formwork of column. 4) Arrangement of formwork of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilisation of crushed sand instead of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other furniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today 1) Provision for Ramps In case of parking space provided in basement at least 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the form work of slab with respect to architectural reference. 3) Control the wastage of material. 4) communication between site in charge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88/-
Todays BUZZ Word OUR Experience- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , colouring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-12

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 12
Date (DD/MM/YYYY) 21.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the slab whether the formwork is prepared according to the drawings.
Details of how you Planned & Executed the allotted work We first of all checked the drawings and checked the steel used whether it is according to the drawings as specified by the designer whether the bars specified are mild steel bars or tor steel bars and also the sizes, with the help of the site engineer.
Details of the Construction Procedure / Activity / Technology learned today Today we learned the compaction procedure.
Details of the Construction Materials learned today 1)Compaction machine. 2)Lift to lift the materials eg.bricks.. 3)Footing of the foundation.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1)Fixing the position properly so that solar panels give the max. supply of renewable energy. 2)Proper drainage system.
Details of the Construction / Engineering Drawings observed today Slab drawings.
Details of the Bye Laws referred today Maximum cantilever porch length 4.00m according to bye laws has been followed.
Details of any Managerial Skill learned today 1.The site incharge inspected and saw the concreteing process going on. 2. The site incharge checked the proportions of different materials used.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for T.W. Paneled Door: Main door plywood-Rs.3000 Formica-2 no.-Rs.1200 each=Rs.2400 Lining patti-Rs.7/ft.-20 ft=Rs.140 Mapping patti-Rs.10/ft-30 ft.=Rs.300 Fevicol-Rs.300/kg Door frame-Rs.2000 Labour-Rs.2000 Lump sump-Rs.200 Locks,handle,stopper=Rs.1300 Total=Rs.12000/- Contractor profit-15%=Rs.1700 Total cost-Rs.13700/-
Result of RATE ANALYSIS ( Rs per Unit ) 13700
Todays BUZZ Word Your (Our) site training experience : Firstly we were divided into groups according to our exam seat numbers. we were given the sites for training accordingly which are the members of CREDAI Kolhapur. we were given the vishwakarma builders site for training. this site is located in Om Datta Chile Park,Pratibhanagar,Kolhapur. Firstly we met the CEO of the company who use to allot us the work. it was Nitin Gawade sir.he helped us a lot during our entire site training process. he used to help us with the rate analysis which was told to do everyday such as for columns, slabs, beams, plaster, painting, window, brickwork, door. our site engineer Mane sir also helped us in solving our each and every difficulty. we learnt many things on the site which we never ever had seen before. we saw how footing is done.It was stepped footing. we saw the construction of the pcc bed. we also saw how a plinth beam is constructed.we came to know how we had to check the beams if they are casted accordingly or not. we learnt the preparation of formwork for columns.and then the casting of columns we came to know the use of shikanjas.our site engineer Mane sir showed us how to check the columns.before and after they are casted with the help of plumb bob. we came to know the process of brickwork. how the starters are put and the wall is erected.then how to check the wall whether their are any undulations on the surface. we saw the plastering method which was done in two layers inner layer and outer layer.then also how to check a plaster with the help of line dori. we saw the process of electrification and that is concealed one. we saw the plumbing process too. we also saw how to cast a staircase. we saw the preparation of formwork for a slab. Just we missed one thing i.e we were not able to se the casting of a slab.the slab is going to be casted on 25th so we will be able to see the slab with the help of R.M.C\'s.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nitin Gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-12

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) dsouza agnel santan
Exam No. 13524
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge to check the reinforcement of slab
Details of how you Planned & Executed the allotted work we went to the site. we checked the details the details of the reinforcement bars according to the plan. whenever we had problem the engineer in charge of the slab helped us by clearing our doubts
Details of the Construction Procedure / Activity / Technology learned today slabs are prepared as per the design given by the structural designer. compaction machine used for compacting murum
Details of the Construction Materials learned today tor steel-8mm,10mm,12mm,16mm mild steel-8mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today reinforcement drawing for slab
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today we saw how the engineer conversed and solved the problems on site.we learned how to converse with the labourers.
RATE ANALYSIS (Detailed Stepwise Calculations required) Main door plywood-Rs.3000 Formica-2 no.-Rs.1200 each=Rs.2400 Lining patti-Rs.7/ft.-20 ft=Rs.140 Mapping patti-Rs.10/ft-30 ft.=Rs.300 Fevicol-Rs.300/kg Door frame-Rs.2000 Labour-Rs.2000 Lump sump-Rs.200 Locks,handle,stopper=Rs.1300 Total=Rs.12000/- Contractor profit-15%=Rs.1700 Total cost-Rs.13700/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.13700/-
Todays BUZZ Word >it was a very different experience for us. >till today we learned in class but we understood that in actual case everything is very different >at farst i was a bit scared cause everything was new,but later on it became much easy.the engineer helped us a lot >he cleared all my doubts. >everyday i had something new to learn. >i understood that practical knowledge is more important than just theorotical knowledge >i understood the different terms used for things like plumb bob,chair,etc >i learned the easiest way of checking the level or adjusting the level with the use of level tube >i learned the different types of steel bars used for reinforcement. >i learned the different types of cements,bricks used for construction work. >i learned mixing,transportation,placaing,compaction of concrete >i learned different types of foundations. >i saw how to use JCB for digging,filling of land,use of pump for the removal of water >i learned the process of making stirrups,bending of bars. >i learned curing of concrete n why it is necessary. >i learned how to join the bars and stirrups with each other with the help of steel wire >i learned how to prepeare the form work for beams,columns,slab.i also learned hoe to check the form work >i studied the procedure of tiling.plastering.skirting,electrification,plumbing,concealed wiring >i learned the different types of doors and windows >how to use the available material in proper way so that there is minimum waste >i learnt different manegerial skills,workers had lot of experience so even they helped us with our doubts >due to this i learned many things and it helped me to increase my knowledge
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-12

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Nilam Jaywant
Exam No. 13528
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge to check the reinforcement of slab
Details of how you Planned & Executed the allotted work we went to the site. we checked the details the details of the reinforcement bars according to the plan. whenever we had problem the engineer in charge of the slab helped us by clearing our doubts
Details of the Construction Procedure / Activity / Technology learned today slabs are prepared as per the design given by the structural designer. compaction machine used for compacting murum
Details of the Construction Materials learned today tor steel-8mm,10mm,12mm,16mm mild steel-8mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today reinforcement drawing for slab
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today we saw how the engineer conversed and solved the problems on site.we learned how to converse with the labourers.
RATE ANALYSIS (Detailed Stepwise Calculations required) Main door plywood-Rs.3000 Formica-2 no.-Rs.1200 each=Rs.2400 Lining patti-Rs.7/ft.-20 ft=Rs.140 Mapping patti-Rs.10/ft-30 ft.=Rs.300 Fevicol-Rs.300/kg Door frame-Rs.2000 Labour-Rs.2000 Lump sump-Rs.200 Locks,handle,stopper=Rs.1300 Total=Rs.12000/- Contractor profit-15%=Rs.1700 Total cost-Rs.13700/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 13700/-
Todays BUZZ Word >it was a very different experience for us. >till today we learned in class but we understood that in actual case everything is very different >at farst i was a bit scared cause everything was new,but later on it became much easy.the engineer helped us a lot >he cleared all my doubts. >everyday i had something new to learn. >i understood that practical knowledge is more important than just theorotical knowledge >i understood the different terms used for things like plumb bob,chair,etc >i learned the easiest way of checking the level or adjusting the level with the use of level tube >i learned the different types of steel bars used for reinforcement. >i learned the different types of cements,bricks used for construction work. >i learned mixing,transportation,placaing,compaction of concrete >i learned different types of foundations. >i saw how to use JCB for digging,filling of land,use of pump for the removal of water >i learned the process of making stirrups,bending of bars. >i learned curing of concrete n why it is necessary. >i learned how to join the bars and stirrups with each other with the help of steel wire >i learned how to prepeare the form work for beams,columns,slab.i also learned hoe to check the form work >i studied the procedure of tiling.plastering.skirting,electrification,plumbing,concealed wiring >i learned the different types of doors and windows >how to use the available material in proper way so that there is minimum waste >i learnt different manegerial skills,workers had lot of experience so even they helped us with our doubts >due to this i learned many things and it helped me to increase my knowledge
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-12

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) MOHARE VISHAL BHALCHANDRA
Exam No. 13564
Working Day No. 12
Date (DD/MM/YYYY) 21 - 12 - 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Obeserve the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of formwork of column. 4) Arrangment of formwork of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilisation of crushed sand insted of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other ferniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today Provision for Rmps In case of parking space provided in basement atleaste 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the formwork of slab with respect to architechural reference. 3) Control the wastage of material. 4) comunication between site encharge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88 /-
Todays BUZZ Word OUR Experence- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , colouring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-12

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) REDEKAR SHANTANU RAVINDRA
Exam No. 13566
Working Day No. 12
Date (DD/MM/YYYY) 21 - 12 - 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Obeserve the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of formwork of column. 4) Arrangment of formwork of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilisation of crushed sand insted of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other ferniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today Provision for Rmps In case of parking space provided in basement atleaste 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the formwork of slab with respect to architechural reference. 3) Control the wastage of material. 4) comunication between site encharge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88 /-
Todays BUZZ Word OUR Experence- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , colouring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: nikitashinde15@gmail.com
Subject: 13547-12

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) shinde nikita eknath
Exam No. 13547
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge 1.to check out position of door,window and ventilator 2.to check their sizes and height from floor level
Details of how you Planned & Executed the allotted work 1. for checking of this first we are refer plan of building giving detailed information of door window shedule 2.we divided in two groups 3.in which one group is checked door sizes and another checked window sizes fir all bunglows
Details of the Construction Procedure / Activity / Technology learned today plastering procedure 1.cure the surface which plastered 2.sieved sand is used 3.mix the cement with sand according to the proportion 4.apply it in two to three layer 5.finishing of surface with trowels
Details of the Construction Materials learned today 1.wall plug 2.types of paints
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1.detailed door window shedule plan 2.elevation of building 3.plan of terrace
Details of the Bye Laws referred today the height of shall not be less than 45CM above the surrounding ground level
Details of any Managerial Skill learned today 1.good communication with customer and us 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Flush door 1.rate of door =65Rs per sqft 2.leeping =10Rs per r. ft 3.labour =25Rs per sqft 4.frame =60Rs per piece 5.frame fitting =4.25Rs 6.cement =5Rs total =169.25Rs 20%CP =34Rs Total with cp =204Rs per sqft (appro) total =2195Rs per sqmt
Result of RATE ANALYSIS ( Rs per Unit ) 2195Rs
Todays BUZZ Word we are the student of D.Y. Patil institute studing in TE civil.we first visited to animesh nagar on 8 dec.2010 at 9:ooam. the supervisour Nilesh bhapkar sir avilable on site. they introduce himself and some leader person on site after some time they give some work relative to our study. every day they give differant work the following are work done we completed under guidance of superviser Nilesh bhapkar sir on every day 1.the level taking for road cutting and slop for drainage system 2.the layout plan of building 3.the calculation of flooring area available 4.tiles required for every room 5.the level required for tiles fitting 6.the cost of labour for differant types of tiles 7.the level taken for tiles fitting of stair case 8.the steels are used for slab casting and beam 9.the construction of form work for plasdtering coluring and plumbing syste 10.the mix prtopostion used for good concrete 11.the payment of labour of different field 12.the cost of painting for both external and internal 13.level required for plumbing system 14.the quality of concrete used for plastering 15.the estimation of plumbing system of building 16.the facility of rain water harvesting with doing all the work with supervicer and labour most of things we understand such that 1.we give exact information to labour 2.keep the fraiendly enviornment on site 3.detail information about quntity of labour available every day 4.market rates of various construction materials and facility shall be known 5.charges of labour also important 6.command on labour 7.we have the skill to solve every site problem 8.good communication with customer 9.the site selection is important 10./to maiontain consrtuction machinary is important 11.keep the quality of material used for construction is high which increase strength and durability 12 to getting information about public choice 13.to concentrate to give good enviornmental condition 14.the safety of labour is also important 15the facility of labour is important 16.the site should be such that the local facility should fulfilled such that marketing road facility and entertainment facility 17.in plastering the proportion of concrete is important 18.the planing and designing of the building is important 19.in case of injury the medicine facility should be available on site and evry six month T.T. injection give to every labour
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapkar sir Ph no-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-12

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) patil sachin dhanaji
Exam No. 13539
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge 1.to check out position of door,window and ventilator 2.to check their sizes and height from floor level
Details of how you Planned & Executed the allotted work 1. for checking of this first we are refer plan of building giving detailed information of door window shedule 2.we divided in two groups 3.in which one group is checked door sizes and another checked window sizes fir all bunglows
Details of the Construction Procedure / Activity / Technology learned today plastering procedure 1.cure the surface which plastered 2.sieved sand is used 3.mix the cement with sand according to the proportion 4.apply it in two to three layer 5.finishing of surface with trowels
Details of the Construction Materials learned today 1.wall plug 2.types of paints
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1.detailed door window shedule plan 2.elevation of building 3.plan of terrace
Details of the Bye Laws referred today the height of shall not be less than 45CM above the surrounding ground level
Details of any Managerial Skill learned today 1.good communication with customer and us 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Flush door 1.rate of door =65Rs per sqft 2.leeping =10Rs per r. ft 3.labour =25Rs per sqft 4.frame =60Rs per piece 5.frame fitting =4.25Rs 6.cement =5Rs total =169.25Rs 20%CP =34Rs Total with cp =204Rs per sqft (appro) total =2195Rs per sqmt
Result of RATE ANALYSIS ( Rs per Unit ) 2195Rs
Todays BUZZ Word we are the student of D.Y. Patil institute studing in TE civil.we first visited to animesh nagar on 8 dec.2010 at 9:ooam. the supervisour Nilesh bhapkar sir avilable on site. they introduce himself and some leader person on site after some time they give some work relative to our study. every day they give differant work the following are work done we completed under guidance of superviser Nilesh bhapkar sir on every day 1.the level taking for road cutting and slop for drainage system 2.the layout plan of building 3.the calculation of flooring area available 4.tiles required for every room 5.the level required for tiles fitting 6.the cost of labour for differant types of tiles 7.the level taken for tiles fitting of stair case 8.the steels are used for slab casting and beam 9.the construction of form work for plasdtering coluring and plumbing syste 10.the mix prtopostion used for good concrete 11.the payment of labour of different field 12.the cost of painting for both external and internal 13.level required for plumbing system 14.the quality of concrete used for plastering 15.the estimation of plumbing system of building 16.the facility of rain water harvesting with doing all the work with supervicer and labour most of things we understand such that 1.we give exact information to labour 2.keep the fraiendly enviornment on site 3.detail information about quntity of labour available every day 4.market rates of various construction materials and facility shall be known 5.charges of labour also important 6.command on labour 7.we have the skill to solve every site problem 8.good communication with customer 9.the site selection is important 10./to maiontain consrtuction machinary is important 11.keep the quality of material used for construction is high which increase strength and durability 12 to getting information about public choice 13.to concentrate to give good enviornmental condition 14.the safety of labour is also important 15the facility of labour is important 16.the site should be such that the local facility should fulfilled such that marketing road facility and entertainment facility 17.in plastering the proportion of concrete is important 18.the planing and designing of the building is important 19.in case of injury the medicine facility should be available on site and evry six month T.T. injection give to every labour
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapkar sir Ph no-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-12

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) patil sangram madhukar
Exam No. 13540
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge 1.to check out position of door,window and ventilator 2.to check their sizes and height from floor level
Details of how you Planned & Executed the allotted work 1. for checking of this first we are refer plan of building giving detailed information of door window shedule 2.we divided in two groups 3.in which one group is checked door sizes and another checked window sizes fir all bunglows
Details of the Construction Procedure / Activity / Technology learned today plastering procedure 1.cure the surface which plastered 2.sieved sand is used 3.mix the cement with sand according to the proportion 4.apply it in two to three layer 5.finishing of surface with trowels
Details of the Construction Materials learned today 1.wall plug 2.types of paints
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1.detailed door window shedule plan 2.elevation of building 3.plan of terrace
Details of the Bye Laws referred today the height of shall not be less than 45CM above the surrounding ground level
Details of any Managerial Skill learned today 1.good communication with customer and us 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Flush door 1.rate of door =65Rs per sqft 2.leeping =10Rs per r. ft 3.labour =25Rs per sqft 4.frame =60Rs per piece 5.frame fitting =4.25Rs 6.cement =5Rs total =169.25Rs 20%CP =34Rs Total with cp =204Rs per sqft (appro) total =2195Rs per sqmt
Result of RATE ANALYSIS ( Rs per Unit ) 2195Rs
Todays BUZZ Word we are the student of D.Y. Patil institute studing in TE civil.we first visited to animesh nagar on 8 dec.2010 at 9:ooam. the supervisour Nilesh bhapkar sir avilable on site. they introduce himself and some leader person on site after some time they give some work relative to our study. every day they give differant work the following are work done we completed under guidance of superviser Nilesh bhapkar sir on every day 1.the level taking for road cutting and slop for drainage system 2.the layout plan of building 3.the calculation of flooring area available 4.tiles required for every room 5.the level required for tiles fitting 6.the cost of labour for differant types of tiles 7.the level taken for tiles fitting of stair case 8.the steels are used for slab casting and beam 9.the construction of form work for plasdtering coluring and plumbing syste 10.the mix prtopostion used for good concrete 11.the payment of labour of different field 12.the cost of painting for both external and internal 13.level required for plumbing system 14.the quality of concrete used for plastering 15.the estimation of plumbing system of building 16.the facility of rain water harvesting with doing all the work with supervicer and labour most of things we understand such that 1.we give exact information to labour 2.keep the fraiendly enviornment on site 3.detail information about quntity of labour available every day 4.market rates of various construction materials and facility shall be known 5.charges of labour also important 6.command on labour 7.we have the skill to solve every site problem 8.good communication with customer 9.the site selection is important 10./to maiontain consrtuction machinary is important 11.keep the quality of material used for construction is high which increase strength and durability 12 to getting information about public choice 13.to concentrate to give good enviornmental condition 14.the safety of labour is also important 15the facility of labour is important 16.the site should be such that the local facility should fulfilled such that marketing road facility and entertainment facility 17.in plastering the proportion of concrete is important 18.the planing and designing of the building is important 19.in case of injury the medicine facility should be available on site and evry six month T.T. injection give to every labour
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapkar sir Ph no-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: rajendrapawar54@gmail.com
Subject: 13542-12

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) pawar rajendra eknath
Exam No. 13542
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge 1.to check out position of door,window and ventilator 2.to check their sizes and height from floor level
Details of how you Planned & Executed the allotted work 1. for checking of this first we are refer plan of building giving detailed information of door window shedule 2.we divided in two groups 3.in which one group is checked door sizes and another checked window sizes fir all bunglows
Details of the Construction Procedure / Activity / Technology learned today plastering procedure 1.cure the surface which plastered 2.sieved sand is used 3.mix the cement with sand according to the proportion 4.apply it in two to three layer 5.finishing of surface with trowels
Details of the Construction Materials learned today 1.wall plug 2.types of paints
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1.detailed door window shedule plan 2.elevation of building 3.plan of terrace
Details of the Bye Laws referred today the height of shall not be less than 45CM above the surrounding ground level
Details of any Managerial Skill learned today 1.good communication with customer and us 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Flush door 1.rate of door =65Rs per sqft 2.leeping =10Rs per r. ft 3.labour =25Rs per sqft 4.frame =60Rs per piece 5.frame fitting =4.25Rs 6.cement =5Rs total =169.25Rs 20%CP =34Rs Total with cp =204Rs per sqft (appro) total =2195Rs per sqmt
Result of RATE ANALYSIS ( Rs per Unit ) 2195Rs
Todays BUZZ Word we are the student of D.Y. Patil institute studing in TE civil.we first visited to animesh nagar on 8 dec.2010 at 9:ooam. the supervisour Nilesh bhapkar sir avilable on site. they introduce himself and some leader person on site after some time they give some work relative to our study. every day they give differant work the following are work done we completed under guidance of superviser Nilesh bhapkar sir on every day 1.the level taking for road cutting and slop for drainage system 2.the layout plan of building 3.the calculation of flooring area available 4.tiles required for every room 5.the level required for tiles fitting 6.the cost of labour for differant types of tiles 7.the level taken for tiles fitting of stair case 8.the steels are used for slab casting and beam 9.the construction of form work for plasdtering coluring and plumbing syste 10.the mix prtopostion used for good concrete 11.the payment of labour of different field 12.the cost of painting for both external and internal 13.level required for plumbing system 14.the quality of concrete used for plastering 15.the estimation of plumbing system of building 16.the facility of rain water harvesting with doing all the work with supervicer and labour most of things we understand such that 1.we give exact information to labour 2.keep the fraiendly enviornment on site 3.detail information about quntity of labour available every day 4.market rates of various construction materials and facility shall be known 5.charges of labour also important 6.command on labour 7.we have the skill to solve every site problem 8.good communication with customer 9.the site selection is important 10./to maiontain consrtuction machinary is important 11.keep the quality of material used for construction is high which increase strength and durability 12 to getting information about public choice 13.to concentrate to give good enviornmental condition 14.the safety of labour is also important 15the facility of labour is important 16.the site should be such that the local facility should fulfilled such that marketing road facility and entertainment facility 17.in plastering the proportion of concrete is important 18.the planing and designing of the building is important 19.in case of injury the medicine facility should be available on site and evry six month T.T. injection give to every labour
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapkar sir Ph no-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: vishwajit.p09@gmail.com
Subject: 13543-12

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) paymal vishwajit shamarao
Exam No. 13543
Working Day No. 12
Date (DD/MM/YYYY) 21/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge 1.to check out position of door,window and ventilator 2.to check their sizes and height from floor level
Details of how you Planned & Executed the allotted work 1. for checking of this first we are refer plan of building giving detailed information of door window shedule 2.we divided in two groups 3.in which one group is checked door sizes and another checked window sizes fir all bunglows
Details of the Construction Procedure / Activity / Technology learned today plastering procedure 1.cure the surface which plastered 2.sieved sand is used 3.mix the cement with sand according to the proportion 4.apply it in two to three layer 5.finishing of surface with trowels
Details of the Construction Materials learned today 1.wall plug 2.types of paints
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1.detailed door window shedule plan 2.elevation of building 3.plan of terrace
Details of the Bye Laws referred today the height of shall not be less than 45CM above the surrounding ground level
Details of any Managerial Skill learned today 1.good communication with customer and us 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Flush door 1.rate of door =65Rs per sqft 2.leeping =10Rs per r. ft 3.labour =25Rs per sqft 4.frame =60Rs per piece 5.frame fitting =4.25Rs 6.cement =5Rs total =169.25Rs 20%CP =34Rs Total with cp =204Rs per sqft (appro) total =2195Rs per sqmt
Result of RATE ANALYSIS ( Rs per Unit ) 2195Rs
Todays BUZZ Word we are the student of D.Y. Patil institute studing in TE civil.we first visited to animesh nagar on 8 dec.2010 at 9:ooam. the supervisour Nilesh bhapkar sir avilable on site. they introduce himself and some leader person on site after some time they give some work relative to our study. every day they give differant work the following are work done we completed under guidance of superviser Nilesh bhapkar sir on every day 1.the level taking for road cutting and slop for drainage system 2.the layout plan of building 3.the calculation of flooring area available 4.tiles required for every room 5.the level required for tiles fitting 6.the cost of labour for differant types of tiles 7.the level taken for tiles fitting of stair case 8.the steels are used for slab casting and beam 9.the construction of form work for plasdtering coluring and plumbing syste 10.the mix prtopostion used for good concrete 11.the payment of labour of different field 12.the cost of painting for both external and internal 13.level required for plumbing system 14.the quality of concrete used for plastering 15.the estimation of plumbing system of building 16.the facility of rain water harvesting with doing all the work with supervicer and labour most of things we understand such that 1.we give exact information to labour 2.keep the fraiendly enviornment on site 3.detail information about quntity of labour available every day 4.market rates of various construction materials and facility shall be known 5.charges of labour also important 6.command on labour 7.we have the skill to solve every site problem 8.good communication with customer 9.the site selection is important 10./to maiontain consrtuction machinary is important 11.keep the quality of material used for construction is high which increase strength and durability 12 to getting information about public choice 13.to concentrate to give good enviornmental condition 14.the safety of labour is also important 15the facility of labour is important 16.the site should be such that the local facility should fulfilled such that marketing road facility and entertainment facility 17.in plastering the proportion of concrete is important 18.the planing and designing of the building is important 19.in case of injury the medicine facility should be available on site and evry six month T.T. injection give to every labour
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapkar sir Ph no-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-12

Company Name Bhima Builders & Developers
Project Name & Site Address wind gate nagala park
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Ramchandra
Exam No. 13557
Working Day No. 12
Date (DD/MM/YYYY) 21 / 12 / 2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Obeserve the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of formwork of column. 4) Arrangment of formwork of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilisation of crushed sand insted of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other ferniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today Provision for Rmps In case of parking space provided in basement atleaste 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the formwork of slab with respect to architechural reference. 3) Control the wastage of material. 4) comunication between site encharge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88 /-
Todays BUZZ Word OUR Experence- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , colouring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-12

Company Name Bhima Builders & Developers
Project Name & Site Address wind gate nagala park
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Ramchandra
Exam No. 13557
Working Day No. 12
Date (DD/MM/YYYY) 21 / 12 / 2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Obeserve the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of formwork of column. 4) Arrangment of formwork of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilisation of crushed sand insted of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other ferniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today Provision for Rmps In case of parking space provided in basement atleaste 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the formwork of slab with respect to architechural reference. 3) Control the wastage of material. 4) comunication between site encharge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88 /-
Todays BUZZ Word OUR Experence- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , colouring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-12

Company Name Bhima Builders & Developers
Project Name & Site Address wind gate nagala park
Students Name (Surname_First Name_Middle Name) Mohare Vishal Bhalchandra
Exam No. 13564
Working Day No. 12
Date (DD/MM/YYYY) 21 / 12 / 2010
Site Reporting Time (HH:MM am/pm) 9;00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Obeserve the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of formwork of column. 4) Arrangment of formwork of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilisation of crushed sand insted of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other ferniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today Provision for Rmps In case of parking space provided in basement atleaste 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the formwork of slab with respect to architechural reference. 3) Control the wastage of material. 4) comunication between site encharge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88 /-
Todays BUZZ Word OUR Experence- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , colouring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-12

Company Name Bhima Builders & Developers
Project Name & Site Address wind gate nagala park
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 12
Date (DD/MM/YYYY) 21 / 12 / 2010
Site Reporting Time (HH:MM am/pm) 9;00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Obeserve the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of formwork of column. 4) Arrangment of formwork of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilisation of crushed sand insted of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other ferniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today 1) Provision for Rmps In case of parking space provided in basement atleaste 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the formwork of slab with respect to architechural reference. 3) Control the wastage of material. 4) comunication between site encharge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88 /-
Todays BUZZ Word OUR Experence- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , colouring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/21/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-12

Company Name Bhima Builders & Developers
Project Name & Site Address wind gate nagala park
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Ramchandra
Exam No. 13557
Working Day No. 12
Date (DD/MM/YYYY) 21 / 12 / 2010
Site Reporting Time (HH:MM am/pm) 9;00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) Quantity analysis of slab. 2) Preparing check list for slab casting. 3) Prepare detailed estimate of slab. 4) Finding out the requirement of M20 grade concrete for slab of proposed building. 5) Calculate the steel reinforcement required for slab.
Details of how you Planned & Executed the allotted work 1) First we divided our group in to subgroup. 2) Calculate of quantity of steel requirement for slab. 3) Other group check the dimensions of slab by using working drawing of slab. 4) Then multiply with thickness of slab and find gross quantity of steel. 5) Separately calculate quantity of concrete with above beam excluding depth.
Details of the Construction Procedure / Activity / Technology learned today 1) Obeserve the reinforce drawing on proposed building. 2) Placing of steel work on slab. 3) Removal of formwork of column. 4) Arrangment of formwork of slab & beam. 5) We observe the proses of concreting method of slab. 6) We saw the steel form of steel grade used for footing of other wing B.
Details of the Construction Materials learned today 1) Use of water profing chemical while concreting 2) Cement 43 grade O.p.C. 3) Mix proportion of cement, sand, aggregate for R.C.C. 4) Needle vibrators. 5) Tamping rod. 6) Covers 7) Steel Main bar - 16 mm dia. Anchor bar - 10 mm dia. Stirrups - 6 mm dia.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Utilisation of crushed sand insted of natural sand. 2) Water become scare in summer therefore they use water very carefully. 3) Steel windows and doors and other ferniture are done by replacing the wooden material.
Details of the Construction / Engineering Drawings observed today Plan of beam. Their are several sizes of beam. Steel requirement is different. There are straight bars, anchor bars, bent-up bars and stirrups are used.
Details of the Bye Laws referred today Provision for Rmps In case of parking space provided in basement atleaste 2 ramps of adequate width and slope shall be provided .
Details of any Managerial Skill learned today 1) Arrangement of next day work. 2) To check the formwork of slab with respect to architechural reference. 3) Control the wastage of material. 4) comunication between site encharge & workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/
Result of RATE ANALYSIS ( Rs per Unit ) 2109.88 /-
Todays BUZZ Word OUR Experence- Our site is BHIMA BUILDER’S of WINDGATE. Located at near the new palace , nagala park , Kolhapur. In that site , we have understand very much practical knowledge from the our side in charge Mr. Vikrant Pise. (Executive Engineer ) & Mr. Amit Shinde & Mr. Dhanaji. We assist them on the site. On the very first day from our training Mr. Vikrant Pise sir given us a work for a day on that work we have to work as a team, find every single information, details about that work & to study that allotted work. At the end of day our sir ask the questions on the work, which is allotted for us for particular day. On the site that is wind gate , the whole project have 88 flats with various facilities . the whole project is divided into four wings. They have facilities like swimming pool , skating track , children playing ground, garden , small scale reception hall for various function. On the site we experience the various techniques like Ready-Mix concrete , Pile Foundation both technique are manual and machine . We understand that how to calculate the quantity of steel coming on site which is order for various work on the site. We observed how steel reinforcement is done for slab work. For this work we study the various drawing regarding the structure . the drawing including no. of bars , stirrups , spacing and mainly understanding reading the working drawing. Pile foundation is done on our site regarding this foundation we observed how pile foundation is done. From the staff Bhima Builders we observed there management skill i.e. how they manage all the works , how they control there labours to complete the allotted work for that day. In office work we study how rate analysis is done for various items like slab , column, beams, plastering, doors, windows, p.c.c. , colouring, brickwork, etc. also the study the various drawing like foundation , electrification, steel design, working drawing or any other drawing. One most important thing that we observed the site that the knowledge we get from our books its lightly different from actual site work for ex. The proportion of concrete , which is 1:1.5:3 but there is slightly changes in this proportion on actual site. During this whole training program our in charge Mr. Vikrant Pise sir, Mr. Amit , Mr. Dhanaji all there people with us from these people we learn lot. They helps us any difficulty come. During there whole training program we get valuable experience about the construction of building and so we successfully complete the training period. This credit goes to our Prof. I. I. PATHAN sir , they arrange all this training program. We very thankful to them and also my team member.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10893-11

Company Name V. S. Joshi & Associates
Project Name & Site Address vishva enclave,mukta sainik vasahat, kolhapur.
Students Name (Surname_First Name_Middle Name) KAMBLE ANKIT VIJAYANAND
Exam No. 10893
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 09:00
Site Leaving Time (HH:MM am/pm) 05:30
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"P.C.C. Bed\" that was carried out for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Septic Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts.
Details of the Construction Procedure / Activity / Technology learned today 1. All the preparation works were carried out before starting the P.C.C work. 2. Then the \"Needle Vibrator\" was used as a \"Pump\" for Dewatering the bed. 3. At first petrol was used for its working & then the working was continued using Kerosene. 4. The P.C.C. mixture was prepared on a water tight surface. 5. The \"M10 Grade\" was used for preparation of P.C.C. bed. 6. The Ratio for M10 was as follow (1:3:6) 7. The procedure included the levelling of bed and dressing of the side walls. 8. The Mixture was laid dry as ground water was being accumilated in the pit. 9. Till that period the dewatering was continued. 10. Finally the P.C.C. bed was levelled using \"Panja\" & was compacted using \"Rammer\".
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate. 4. Panja. 5. Rammer. 6. Water.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. \"Storm Drains\" were Constructed at every border of the compound wall & was harvested. 2. \"Solar Panels\" for water heating purpose. 3. \"Crushed Sand\" was used as the composition in Construction of Septic tank.
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Plans. 2. P.C.C. bed details. 3. Floor Plans. 4. Site Layout. 5. Service Plans. 6. Estimation for construction of Septic Tank.
Details of the Bye Laws referred today 1. Building Line. 2. Amenity Open Spaces. 3. Features Permitted in Open spaces. 4. Parking Spaces. 5. Septic Tank.
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality.
Result of RATE ANALYSIS ( Rs per Unit ) Rs.1700.58/-
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". - First of all the total area of a particular flat is determined, - Then the various aspects such as the number of rooms, Salable area, Carpet area,F.S.I, etc.are determined. - Then the total construction cost of that particular flat is worked out. - Then the maintainance cost,independent parking cost,lift charges & deposits are worked out. - Then estimation of the other expenditures is done that includes documents cost, permission from muncipal corporation, etc. - Then total cost is removed. - Then Contractors & Builders Profit of 20% to 50% is Considered. - This is carried out by Estimation and Costing Department of builder. - The total grand cost is removed. - Then ths is kept in front of the client.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-10

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bhoite vishal rajaram
Exam No. 13555
Working Day No. 10
Date (DD/MM/YYYY) 20/12/10
Site Reporting Time (HH:MM am/pm) 10am
Site Leaving Time (HH:MM am/pm) 5pm
Details of the Work Allotted to you today by the Site In-Charge Today we are observe further electrification, 1) Every room wire connection get connect to each main control board 2) And each main control board get connect to main meter which is placed at ground level 3) In each room space is provided at entrance ,to collect all the wire ,get connected to main meter board.
Details of how you Planned & Executed the allotted work 1) Firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans .
Details of the Construction Procedure / Activity / Technology learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited
Details of the Construction / Engineering Drawings observed today layout of plumbing
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today The aggregate,sand, brick are placed in a suitable place to convey easy lifting of material . Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL WINDOW OF SIZE (1.2*1.5) ALUMINIUM FREME rate 100 rs per sq,m for 1.8sq.m = 1.8*100=180rs/ RATE FOR GLASS OF WINDOW= 60rs per sq.m. for 1.8 sq.m = 1.8*60= 108rs. FIXTURE FOR WINDOWS =40rs. LABOUR COST =50rs. TOTAL COST FOR ONE WINDOW OF SIZE (1.2*1.5) = (180+108+40+50) =378rs say 380rs. .
Result of RATE ANALYSIS ( Rs per Unit ) 380rs.
Todays BUZZ Word TODAYS BUZZ WORD the builders are determine ratesof flat or bunglow depend upon sq.foot e.g per sq.foot-2500rs. since the one flat rate about 22lakh to 25lakh it also includes construction rate,layout etc. and plus extra cost to client :- this should also inculde different important factors which have as follows:- a) service tax b) vatt tax. c) parking d) lift f) MSEB etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: vishal2844@gmail.com
Subject: 13555-10

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bhoite vishal rajaram
Exam No. 13555
Working Day No. 10
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 10.am
Site Leaving Time (HH:MM am/pm) 5.00pm
Details of the Work Allotted to you today by the Site In-Charge Today we are observe further electrification, 1) Every room wire connection get connect to each main control board 2) And each main control board get connect to main meter which is placed at ground level 3) In each room space is provided at entrance ,to collect all the wire ,get connected to main meter board.
Details of how you Planned & Executed the allotted work 1) Firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans .
Details of the Construction Procedure / Activity / Technology learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of the Construction Materials learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of the Construction / Engineering Drawings observed today Use of crushed sand is environmental freindly. As use of river sand is prohibited
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today The aggregate,sand, brick are placed in a suitable place to convey easy lifting of material . Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL WINDOW OF SIZE (1.2*1.5) ALUMINIUM FREME rate 100 rs per sq,m for 1.8sq.m = 1.8*100=180rs/ RATE FOR GLASS OF WINDOW= 60rs per sq.m. for 1.8 sq.m = 1.8*60= 108rs. FIXTURE FOR WINDOWS =40rs. LABOUR COST =50rs. TOTAL COST FOR ONE WINDOW OF SIZE (1.2*1.5) = (180+108+40+50) =378rs say 380rs. .
Result of RATE ANALYSIS ( Rs per Unit ) 380rs.
Todays BUZZ Word TODAYS BUZZ WORD the builders are determine ratesof flat or bunglow depend upon sq.foot e.g per sq.foot-2500rs. since the one flat rate about 22lakh to 25lakh it also includes construction rate,layout etc. and plus extra cost to client :- this should also inculde different important factors which have as follows:- a) service tax b) vatt tax. c) parking d) lift f) MSEB etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: vishwajit.p09@gmail.com
Subject: 13543-11

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) paymal vishwajit shamarao
Exam No. 13543
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9;00am
Site Leaving Time (HH:MM am/pm) 4;30pm
Details of the Work Allotted to you today by the Site In-Charge to calculate estimation of plumbing services of the building
Details of how you Planned & Executed the allotted work we measure the length of each pipe separately & calculate total pipe required for building (various diameter & material)
Details of the Construction Procedure / Activity / Technology learned today roller used for painting to reduce the colour & time
Details of the Construction Materials learned today 1.messonite door 2.flush door
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1. section of building 2. electrification drawing of building
Details of the Bye Laws referred today .two storeys building have width of staircase 0.75m
Details of any Managerial Skill learned today 1. good communication with customer & us 2. good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analyse for window 1 aluminium section anodiesing & 5 mm plane glass = 145rs 2 labour = 25Rs 3 transportation = 5Rs Total = 175Rs per sq. ft. Total = 1885Rs per sq. m 20% c.p. = 377Rs Total with 20% c.p = 2265Rs per sq. m.
Result of RATE ANALYSIS ( Rs per Unit ) 2265RS
Todays BUZZ Word 1. plot rate 2. construction cost per sq. ft. 3. developer profit 4. M.S.E.B. charges 5. agreement charges 6. sale tax 7. water connection charges 8. extra facilities (garden, temple,gutter,) 9. owner requriment
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nilesh bhapat ph. = 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-11

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) suryavanshipatil pratiksinh vilas
Exam No. 13549
Working Day No. 11
Date (DD/MM/YYYY) 20/12/10
Site Reporting Time (HH:MM am/pm) 10am
Site Leaving Time (HH:MM am/pm) 5pm
Details of the Work Allotted to you today by the Site In-Charge Today we are observe further electrification, 1) Every room wire connection get connect to each main control board 2) And each main control board get connect to main meter which is placed at ground level 3) In each room space is provided at entrance ,to collect all the wire ,get connected to main meter board.
Details of how you Planned & Executed the allotted work 1) Firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans .
Details of the Construction Procedure / Activity / Technology learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of the Construction Materials learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited
Details of the Construction / Engineering Drawings observed today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today The aggregate,sand, brick are placed in a suitable place to convey easy lifting of material . Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL WINDOW OF SIZE (1.2*1.5) ALUMINIUM FREME rate 100 rs per sq,m for 1.8sq.m = 1.8*100=180rs/ RATE FOR GLASS OF WINDOW= 60rs per sq.m. for 1.8 sq.m = 1.8*60= 108rs. FIXTURE FOR WINDOWS =40rs. LABOUR COST =50rs. TOTAL COST FOR ONE WINDOW OF SIZE (1.2*1.5) = (180+108+40+50) =378rs say 380rs. .
Result of RATE ANALYSIS ( Rs per Unit ) 380rs.
Todays BUZZ Word TODAYS BUZZ WORD the builders are determine ratesof flat or bunglow depend upon sq.foot e.g per sq.foot-2500rs. since the one flat rate about 22lakh to 25lakh it also includes construction rate,layout etc. and plus extra cost to client :- this should also inculde different important factors which have as follows:- a) service tax b) vatt tax. c) parking d) lift f) MSEB etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: rajendrapawar54@gmail.com
Subject: 13542-11

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) pawar rajendra eknath
Exam No. 13542
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9;00am
Site Leaving Time (HH:MM am/pm) 4;30pm
Details of the Work Allotted to you today by the Site In-Charge to calculate estimation of plumbing services of the building
Details of how you Planned & Executed the allotted work we measure the length of each pipe separately & calculate total pipe required for building (various diameter & material)
Details of the Construction Procedure / Activity / Technology learned today roller used for painting to reduce the colour & time
Details of the Construction Materials learned today 1.messonite door 2.flush door
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1. section of building 2. electrification drawing of building
Details of the Bye Laws referred today 1.two storeys building have width of staircase 0.75m
Details of any Managerial Skill learned today 1. good communication with customer & us 2. good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analyse for window 1 aluminium section anodiesing & 5 mm plane glass = 145rs 2 labour = 25Rs 3 transportation = 5Rs Total = 175Rs per sq. ft. Total = 1885Rs per sq. m 20% c.p. = 377Rs Total with 20% c.p = 2265Rs per sq. m.
Result of RATE ANALYSIS ( Rs per Unit ) 2265Rs
Todays BUZZ Word 1. plot rate 2. construction cost per sq. ft. 3. developer profit 4. M.S.E.B. charges 5. agreement charges 6. sale tax 7. water connection charges 8. extra facilities (garden, temple,gutter,) 9. owner requriment
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nilesh bhapat ph. = 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: nikitashinde15@gmail.com
Subject: 13547-11

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) shinde nikita eknath
Exam No. 13547
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9;00am
Site Leaving Time (HH:MM am/pm) 4;30pm
Details of the Work Allotted to you today by the Site In-Charge to calculate estimation of plumbing services of the building
Details of how you Planned & Executed the allotted work we measure the length of each pipe separately & calculate total pipe required for building (various diameter & material)
Details of the Construction Procedure / Activity / Technology learned today roller used for painting to reduce the colour & time
Details of the Construction Materials learned today 1.messonite door 2.flush door
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1. section of building 2. electrification drawing of building
Details of the Bye Laws referred today 1.two storeys building have width of staircase 0.75m
Details of any Managerial Skill learned today 1. good communication with customer & us 2. good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analyse for window 1 aluminium section anodiesing & 5 mm plane glass = 145rs 2 labour = 25Rs 3 transportation = 5Rs Total = 175Rs per sq. ft. Total = 1885Rs per sq. m 20% c.p. = 377Rs Total with 20% c.p = 2265Rs per sq. m.
Result of RATE ANALYSIS ( Rs per Unit ) 2265RS
Todays BUZZ Word 1. plot rate 2. construction cost per sq. ft. 3. developer profit 4. M.S.E.B. charges 5. agreement charges 6. sale tax 7. water connection charges 8. extra facilities (garden, temple,gutter,) 9. owner requriment
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nilesh bhapat ph. = 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-10

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bauchkar deepak yuvaraj
Exam No. 13554
Working Day No. 10
Date (DD/MM/YYYY) 20/12/10
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 05:00pm
Details of the Work Allotted to you today by the Site In-Charge Today we are observe further electrification, 1) Every room wire connection get connect to each main control board 2) And each main control board get connect to main meter which is placed at ground level 3) In each room space is provided at entrance ,to collect all the wire ,get connected to main meter board.
Details of how you Planned & Executed the allotted work 1)firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans.
Details of the Construction Procedure / Activity / Technology learned today fisformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. rst the supply is taken from the MSEB then it is given to the tranthen from this supply is given to the all the rooms separately to the boards provided in the rooms and from board mixers required 15 amp board according to their capacity of load. wires . of the to the equipments. such as fans, tube, bulb requires 5 amp board and various thickness are used depend upon the current carrying capacity.
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of the Construction / Engineering Drawings observed today Use of crushed sand is environmental freindly. As use of river sand is prohibited
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today The aggregate,sand, brick are placed in a suitable place to convey easy lifting of material . Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL WINDOW OF SIZE (1.2*1.5) ALUMINIUM FREME rate 100 rs per sq,m for 1.8sq.m = 1.8*100=180rs/ RATE FOR GLASS OF WINDOW= 60rs per sq.m. for 1.8 sq.m = 1.8*60= 108rs. FIXTURE FOR WINDOWS =40rs. LABOUR COST =50rs. TOTAL COST FOR ONE WINDOW OF SIZE (1.2*1.5) = (180+108+40+50) =378rs say 380rs. .
Result of RATE ANALYSIS ( Rs per Unit ) 380rs.
Todays BUZZ Word TODAYS BUZZ WORD the builders are determine ratesof flat or bunglow depend upon sq.foot e.g per sq.foot-2500rs. since the one flat rate about 22lakh to 25lakh it also includes construction rate,layout etc. and plus extra cost to client :- this should also inculde different important factors which have as follows:- a) service tax b) vatt tax. c) parking d) lift f) MSEB etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-11

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) patil sangram madhukar
Exam No. 13540
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9;00am
Site Leaving Time (HH:MM am/pm) 4;30pm
Details of the Work Allotted to you today by the Site In-Charge to calculate estimation of plumbing services of the building
Details of how you Planned & Executed the allotted work we measure the length of each pipe separately & calculate total pipe required for building (various diameter & material)
Details of the Construction Procedure / Activity / Technology learned today roller used for painting to reduce the colour & time
Details of the Construction Materials learned today 1.messonite door 2.flush door
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1. section of building 2. electrification drawing of building
Details of the Bye Laws referred today 1.two storeys building have width of staircase 0.75m
Details of any Managerial Skill learned today 1. good communication with customer & us 2. good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analyse for window 1 aluminium section anodiesing & 5 mm plane glass = 145rs 2 labour = 25Rs 3 transportation = 5Rs Total = 175Rs per sq. ft. Total = 1885Rs per sq. m 20% c.p. = 377Rs Total with 20% c.p = 2265Rs per sq. m.
Result of RATE ANALYSIS ( Rs per Unit ) 2265Rs
Todays BUZZ Word 1. plot rate 2. construction cost per sq. ft. 3. developer profit 4. M.S.E.B. charges 5. agreement charges 6. sale tax 7. water connection charges 8. extra facilities (garden, temple,gutter,) 9. owner requriment
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nilesh bhapat ph. = 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-11

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) MANGAOKAR MANOJ DATTATRAY
Exam No. 13536
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE CONSTRUCTION OF BRICK WORK.
Details of how you Planned & Executed the allotted work WE FIRST STUDIED THE WORKING DRAWING THEN GO TO THE PLACE WHERE THE WORK IS GOING ON.
Details of the Construction Procedure / Activity / Technology learned today IF ONE BRICK WALL IS CONSTRUCTED THEN THE P.C.C. LAYER IS PROVIDED NORMALLY AT DISTANCE OF 1-1.2 M . SO THAT STABILITY OF WALL SHOULD NOT GET DISTURBED. THE WORK IS CHECKED BY PLUM-BOB. TO CHECK THE ALIGNMENT OF THE BRICK WORK WHETHER IT IS DONE PROPERLY OR NOT
Details of the Construction Materials learned today BRICK , BONDING MATERIAL - CEMENT , SAND . AND ITS PROPORTION.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today WORKING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 200.00 RUBBER STRIP USED- Rs- 45 lump sump- 100 locks -2 no. - 50 Rs labour cost - 35/sq.ft total cost- 430 RS= 223.45=225 RS
Result of RATE ANALYSIS ( Rs per Unit ) 225 Rs
Todays BUZZ Word BUILDER DECIDE THE COST OF THE FLATS AND BUNGALOWS 1.FIRST THEY MEASURE THE CARPET AREA MEANS THE AREA EXCLUDING THE WALL AND THE AREA OF TERRACE ,BALCONIES AND OPEN SPACES 25% - 30% 2.PARKING AREA AND MAINTAINENCE CHARGES ARE ALSO INCLUDED WHILE CALCULATING THE COST OF FLAT.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-11

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) JAGADALE ASHWINI RAMRAO
Exam No. 13530
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE CONSTRUCTION OF BRICK WORK.
Details of how you Planned & Executed the allotted work WE FIRST STUDIED THE WORKING DRAWING THEN GO TO THE PLACE WHERE THE WORK IS GOING ON.
Details of the Construction Procedure / Activity / Technology learned today IF ONE BRICK WALL IS CONSTRUCTED THEN THE P.C.C. LAYER IS PROVIDED NORMALLY AT DISTANCE OF 1-1.2 M . SO THAT STABILITY OF WALL SHOULD NOT GET DISTURBED. THE WORK IS CHECKED BY PLUM-BOB. TO CHECK THE ALIGNMENT OF THE BRICK WORK WHETHER IT IS DONE PROPERLY OR NOT.
Details of the Construction Materials learned today BRICK , BONDING MATERIAL - CEMENT , SAND . AND ITS PROPORTION.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today WORKING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 200.00 RUBBER STRIP USED- Rs- 45 lump sump- 100 locks -2 no. - 50 Rs labour cost - 35/sq.ft total cost- 430 RS= 223.45=225 RS
Result of RATE ANALYSIS ( Rs per Unit ) 225 Rs
Todays BUZZ Word BUILDER DECIDE THE COST OF THE FLATS AND BUNGALOWS 1.FIRST THEY MEASURE THE CARPET AREA MEANS THE AREA EXCLUDING THE WALL AND THE AREA OF TERRACE ,BALCONIES AND OPEN SPACES 25% - 30% 2.PARKING AREA AND MAINTAINENCE CHARGES ARE ALSO INCLUDED WHILE CALCULATING THE COST OF FLAT.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: nitinpatil22.2010@rediffmail.com
Subject: 10879-11

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) PATIL NITIN DILIP
Exam No. 10879
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE CENTERING WORK DONE FOR THE SLAB.
Details of how you Planned & Executed the allotted work WE STUDIED THE STEEL DRAWINGS AND DIRECTLY GO TO FLOOR WHERE THE WORK IS GOING ON.
Details of the Construction Procedure / Activity / Technology learned today BARS ARE BEND AT THE DISTANCE OF L/4 TO RESTRICT SAGGING MOMENT OF SLAB BECAUSE IT INCREASES THE C/S OF SLAB OF THAT PORTION. MAIN BARS ARE NORMALLY PROVIDED PARALLEL TO SHORTER SPAN AND DISTRIBUTION BARS ARE PARALLEL TO LONGER SPAN.
Details of the Construction Materials learned today DIFFERENT SIZES OF MILD AND STEEL BARS.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today STEEL DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 175.00 RUBBER STRIP USED- Rs- 38 lump sump- 125 locks -2 no. - 100 Rs labour cost - 40/sq.ft total cost- 478 RS= 242.45=243 RS
Result of RATE ANALYSIS ( Rs per Unit ) 243 RS
Todays BUZZ Word BUILDER DECIDE THE COST OF THE FLATS AND BUNGALOWS 1.FIRST THEY MEASURE THE CARPET AREA MEANS THE AREA EXCLUDING THE WALL AND THE AREA OF TERRACE ,BALCONIES AND OPEN SPACES 25% - 30% 2.PARKING AREA AND MAINTAINENCE CHARGES ARE ALSO INCLUDED WHILE CALCULATING THE COST OF FLAT.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ketan charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-11

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) BABAR MORESHWAR MAHIPATI
Exam No. 10873
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe the centre line out of columns on the second floor and take the required checks
Details of how you Planned & Executed the allotted work We observed the fixing of two base lines perpendicular to each other. These lines were fixed at the outer face of the column considering maximum number of column in the same line with similar faces. The faces were lined out by deducting the half size of column from the distance between two adjacent parallel centre line. For cross checking we checked the size of column as per drawings given to us. Then we checked the right angle of column, and measured the diagonal distance of column
Details of the Construction Procedure / Activity / Technology learned today Cutting of reinforcement bars,bar bending for slab, making of stirrups
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Centre line plan and detailed second floor plan
Details of the Bye Laws referred today Size of bath and w/c - Dimensions provided on the site for bath:-2.0*1.2=2.4sqm Dimensions provided on the site for w/c:-1.2*1.0=1.2sqm As per bye law the minimum dimensions to be provided is 1.8m*1.0m and 0.9m*0.9m
Details of any Managerial Skill learned today Doing centre line out of the column and maintaining the accuracy in work and soft talking with workers
RATE ANALYSIS (Detailed Stepwise Calculations required) “Rate Analysis for external alluminium using cement paint” (Considering local rates of material) 1. Cost of alluminium frame=22.30*35=780/-………..(35/- per ft) 2. Cost of glass= 65*20.08=1305/-…………(65/- per sq.ft) 3. Cost of fixtures and fastenings=50/-………………..(lump sum) 4. Labour charges=300/-…………(150/- per fitter for half day) 5. Total cost=2435/- 6.10% profit of total cost for the contractor=243.5/- 7. Total cost=2678/- 10. Rate per sq.ft=133/-
Result of RATE ANALYSIS ( Rs per Unit ) 133 RS
Todays BUZZ Word The builders determine their construction rate per sq.ft. Consider their profit excluding the construction rate and the sum total of construction rate and profit is fixed as per sq.ft rate for the building. The rate fluctuates with increase and decrease of material cost. On our site rate of 2300/-per sq.ft is fixed and the cost of flat ranges from 20 lakhs to 25 lakhs. Extra cost to client-this cost is decided considering expenses of facilities provided such as type of tiles, type of paint, fittings, vatt charges, lift charges etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: patilpratibha7070@yahoo.in
Subject: 10896-11

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) PATIL PRATIBHA DILIP
Exam No. 10896
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe the centre line out of columns on the second floor and take the required checks
Details of how you Planned & Executed the allotted work We observed the fixing of two base lines perpendicular to each other. These lines were fixed at the outer face of the column considering maximum number of column in the same line with similar faces. The faces were lined out by deducting the half size of column from the distance between two adjacent parallel centre line. For cross checking we checked the size of column as per drawings given to us. Then we checked the right angle of column, and measured the diagonal distance of column
Details of the Construction Procedure / Activity / Technology learned today Cutting of reinforcement bars,bar bending for slab, making of stirrups
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Centre line plan and detailed second floor plan
Details of the Bye Laws referred today Size of bath and w/c - Dimensions provided on the site for bath:-2.0*1.2=2.4sqm Dimensions provided on the site for w/c:-1.2*1.0=1.2sqm As per bye law the minimum dimensions to be provided is 1.8m*1.0m and 0.9m*0.9m
Details of any Managerial Skill learned today Doing centre line out of the column and maintaining the accuracy in work and soft talking with workers
RATE ANALYSIS (Detailed Stepwise Calculations required) “Rate Analysis for external alluminium using cement paint” (Considering local rates of material) 1. Cost of alluminium frame=22.30*35=780/-………..(35/- per ft) 2. Cost of glass= 65*20.08=1305/-…………(65/- per sq.ft) 3. Cost of fixtures and fastenings=50/-………………..(lump sum) 4. Labour charges=300/-…………(150/- per fitter for half day) 5. Total cost=2435/- 6.10% profit of total cost for the contractor=243.5/- 7. Total cost=2678/- 10. Rate per sq.ft=133/-
Result of RATE ANALYSIS ( Rs per Unit ) 133 RS
Todays BUZZ Word The builders determine their construction rate per sq.ft. Consider their profit excluding the construction rate and the sum total of construction rate and profit is fixed as per sq.ft rate for the building. The rate fluctuates with increase and decrease of material cost. On our site rate of 2300/-per sq.ft is fixed and the cost of flat ranges from 20 lakhs to 25 lakhs. Extra cost to client-this cost is decided considering expenses of facilities provided such as type of tiles, type of paint, fittings, vatt charges, lift charges etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-11

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) patil sachin dhanaji
Exam No. 13539
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9;00am
Site Leaving Time (HH:MM am/pm) 4;30pm
Details of the Work Allotted to you today by the Site In-Charge to calculate estimation of plumbing services of the building
Details of how you Planned & Executed the allotted work we measure the length of each pipe separately & calculate total pipe required for building (various diameter & material)
Details of the Construction Procedure / Activity / Technology learned today roller used for painting to reduce the colour & time
Details of the Construction Materials learned today 1.messonite door 2.flush door
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1. section of building 2. electrification drawing of building
Details of the Bye Laws referred today 1.two storeys building have width of staircase 0.75m
Details of any Managerial Skill learned today 1. good communication with customer & us 2. good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analyse for window 1 aluminium section anodiesing & 5 mm plane glass = 145rs 2 labour = 25Rs 3 transportation = 5Rs Total = 175Rs per sq. ft. Total = 1885Rs per sq. m 20% c.p. = 377Rs Total with 20% c.p = 2265Rs per sq. m.
Result of RATE ANALYSIS ( Rs per Unit ) 2265RS
Todays BUZZ Word 1. plot rate 2. construction cost per sq. ft. 3. developer profit 4. M.S.E.B. charges 5. agreement charges 6. sale tax 7. water connection charges 8. extra facilities (garden, temple,gutter,) 9. owner requriment
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nilesh bhapat ph. = 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-11

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) patil sachin dhanaji
Exam No. 13539
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9;00am
Site Leaving Time (HH:MM am/pm) 4;30pm
Details of the Work Allotted to you today by the Site In-Charge to calculate estimation of plumbing services of the building
Details of how you Planned & Executed the allotted work we measure the length of each pipe separately & calculate total pipe required for building (various diameter & material)
Details of the Construction Procedure / Activity / Technology learned today roller used for painting to reduce the colour & time
Details of the Construction Materials learned today 1.messonite door 2.flush door
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1. section of building 2. electrification drawing of building
Details of the Bye Laws referred today 1.two storeys building have width of staircase 0.75m
Details of any Managerial Skill learned today 1. good communication with customer & us 2. good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analyse for window 1 aluminium section anodiesing & 5 mm plane glass = 145rs 2 labour = 25Rs 3 transportation = 5Rs Total = 175Rs per sq. ft. Total = 1885Rs per sq. m 20% c.p. = 377Rs Total with 20% c.p = 2265Rs per sq. m.
Result of RATE ANALYSIS ( Rs per Unit ) 2265RS
Todays BUZZ Word 1. plot rate 2. construction cost per sq. ft. 3. developer profit 4. M.S.E.B. charges 5. agreement charges 6. sale tax 7. water connection charges 8. extra facilities (garden, temple,gutter,) 9. owner requriment
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nilesh bhapat ph. = 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-11

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"P.C.C. Bed\" that was carried out for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Septic Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts.
Details of the Construction Procedure / Activity / Technology learned today 1. All the preparation works were carried out before starting the P.C.C work. 2. Then the \"Needle Vibrator\" was used as a \"Pump\" for Dewatering the bed. 3. At first petrol was used for its working & then the working was continued using Kerosene. 4. The P.C.C. mixture was prepared on a water tight surface. 5. The \"M10 Grade\" was used for preparation of P.C.C. bed. 6. The Ratio for M10 was as follow (1:3:6) 7. The procedure included the levelling of bed and dressing of the side walls. 8. The Mixture was laid dry as ground water was being accumilated in the pit. 9. Till that period the dewatering was continued. 10. Finally the P.C.C. bed was levelled using \"Panja\" & was compacted using \"Rammer\".
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate. 4. Panja. 5. Rammer. 6. Water.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. \"Storm Drains\" were Constructed at every border of the compound wall & was harvested. 2. \"Solar Panels\" for water heating purpose. 3. \"Crushed Sand\" was used as the composition in Construction of Septic tank.
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Plans. 2. P.C.C. bed details. 3. Floor Plans. 4. Site Layout. 5. Service Plans. 6. Estimation for construction of Septic Tank.
Details of the Bye Laws referred today 1. Building Line. 2. Amenity Open Spaces. 3. Features Permitted in Open spaces. 4. Parking Spaces. 5. Septic Tank.
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # Rate Analysis For Aluminium Window # A) Window Size = 5\' x 4\' B) Material required: 1. Top Rail = 1.083 kg. 2. Side rail = 1.73 kg. 3. Bottom Rail = 1.167 kg. 4. Glass Frame - Top Frame = 0.625 kg. - Bottom frame = 0.625 kg. - Lock Frame = 1.5 kg. - Interlock Frame = 0.8 kg. 5. Glass Rubber = 26\' 6. Track Rubber = 72\' 7. Roller = 4 nos. 8. Glass = 20 sq.ft 9. Coating Powder = 20 sq.ft 10. Lock = 2 nos. 11. Screws C) Material Cost: 1. Top Rail = 1.083 x 180 = 194.94/- 2. Side Rail = 1.73 x 180 = 311.4/- 3. Bottom Rail = 1.167 x 180 = 210.06/- 4. Glass Frame a) Top = 0.625 x 180 = 112.5/- b) Bottom = 0.625 x 180 = 112.5/- c) Lock = 1.5 x 180 = 270/- d) InterLock = 0.8 x 180 = 144/- 5. Glass Rubber = 26 x 2 = 52/- 6. Track Rubber = 72 x 2 = 144/- 7. Roller = 4 x 20 = 80/- 8. Glass = 20 x 25 = 500/- 9. Coating Powder = 20 x 20 = 400/- 10. Lock = 2 x 30 = 60/- 11. Screws, etc. = 100/- Total = 2691.4/- D) Labour Cost: 1. Skilled Labour = 1 x 250 = 250/- 2. Mazdoor = 2 x 110 = 220/- Total = 470/- E) Grand Total = C + D = 3161.4/- F) Rate Per Sq.Ft = 158.07/- G) Rate Per Sq.M = 1700.58/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.1700.58/-
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". - First of all the total area of a particular flat is determined, - Then the various aspects such as the number of rooms, Salable area, Carpet area,F.S.I, etc.are determined. - Then the total construction cost of that particular flat is worked out. - Then the maintainance cost,independent parking cost,lift charges & deposits are worked out. - Then estimation of the other expenditures is done that includes documents cost, permission from muncipal corporation, etc. - Then total cost is removed. - Then Contractors & Builders Profit of 20% to 50% is Considered. - This is carried out by Estimation and Costing Department of builder. - The total grand cost is removed. - Then ths is kept in front of the client.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: salmanbaig18@gmail.com
Subject: 10888-11

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) BAIG SALMAN S.
Exam No. 10888
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe the centre line out of columns on the second floor and take the required checks
Details of how you Planned & Executed the allotted work We observed the fixing of two base lines perpendicular to each other. These lines were fixed at the outer face of the column considering maximum number of column in the same line with similar faces. The faces were lined out by deducting the half size of column from the distance between two adjacent parallel centre line. For cross checking we checked the size of column as per drawings given to us. Then we checked the right angle of column, and measured the diagonal distance of column
Details of the Construction Procedure / Activity / Technology learned today Cutting of reinforcement bars,bar bending for slab, making of stirrups
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Centre line plan and detailed second floor plan
Details of the Bye Laws referred today Size of bath and w/c - Dimensions provided on the site for bath:-2.0*1.2=2.4sqm Dimensions provided on the site for w/c:-1.2*1.0=1.2sqm As per bye law the minimum dimensions to be provided is 1.8m*1.0m and 0.9m*0.9m
Details of any Managerial Skill learned today Doing centre line out of the column and maintaining the accuracy in work and soft talking with workers
RATE ANALYSIS (Detailed Stepwise Calculations required) “Rate Analysis for external alluminium using cement paint” (Considering local rates of material) 1. Cost of alluminium frame=22.30*35=780/-………..(35/- per ft) 2. Cost of glass= 65*20.08=1305/-…………(65/- per sq.ft) 3. Cost of fixtures and fastenings=50/-………………..(lump sum) 4. Labour charges=300/-…………(150/- per fitter for half day) 5. Total cost=2435/- 6.10% profit of total cost for the contractor=243.5/- 7. Total cost=2678/- 10. Rate per sq.ft=133/-
Result of RATE ANALYSIS ( Rs per Unit ) 133 RS
Todays BUZZ Word The builders determine their construction rate per sq.ft. Consider their profit excluding the construction rate and the sum total of construction rate and profit is fixed as per sq.ft rate for the building. The rate fluctuates with increase and decrease of material cost. On our site rate of 2300/-per sq.ft is fixed and the cost of flat ranges from 20 lakhs to 25 lakhs. Extra cost to client-this cost is decided considering expenses of facilities provided such as type of tiles, type of paint, fittings, vatt charges, lift charges etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: vishalsapakal@gmail.com
Subject: 10882-11

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) SAPKAL VISHAL M.
Exam No. 10882
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe the centre line out of columns on the second floor and take the required checks
Details of how you Planned & Executed the allotted work We observed the fixing of two base lines perpendicular to each other. These lines were fixed at the outer face of the column considering maximum number of column in the same line with similar faces. The faces were lined out by deducting the half size of column from the distance between two adjacent parallel centre line. For cross checking we checked the size of column as per drawings given to us. Then we checked the right angle of column, and measured the diagonal distance of column
Details of the Construction Procedure / Activity / Technology learned today Cutting of reinforcement bars,bar bending for slab, making of stirrups
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Centre line plan and detailed second floor plan
Details of the Bye Laws referred today Size of bath and w/c - Dimensions provided on the site for bath:-2.0*1.2=2.4sqm Dimensions provided on the site for w/c:-1.2*1.0=1.2sqm
Details of any Managerial Skill learned today Doing centre line out of the column and maintaining the accuracy in work and soft talking with workers
RATE ANALYSIS (Detailed Stepwise Calculations required) “Rate Analysis for external alluminium using cement paint” (Considering local rates of material) 1. Cost of alluminium frame=22.30*35=780/-………..(35/- per ft) 2. Cost of glass= 65*20.08=1305/-…………(65/- per sq.ft) 3. Cost of fixtures and fastenings=50/-………………..(lump sum) 4. Labour charges=300/-…………(150/- per fitter for half day) 5. Total cost=2435/- 6.10% profit of total cost for the contractor=243.5/- 7. Total cost=2678/- 10. Rate per sq.ft=133/-
Result of RATE ANALYSIS ( Rs per Unit ) 133 RS
Todays BUZZ Word The builders determine their construction rate per sq.ft. Consider their profit excluding the construction rate and the sum total of construction rate and profit is fixed as per sq.ft rate for the building. The rate fluctuates with increase and decrease of material cost. On our site rate of 2300/-per sq.ft is fixed and the cost of flat ranges from 20 lakhs to 25 lakhs. Extra cost to client-this cost is decided considering expenses of facilities provided such as type of tiles, type of paint, fittings, vatt charges, lift charges etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-11

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) YADAV HRISHEEKESH DILIP
Exam No. 10885
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe the centre line out of columns on the second floor and take the required checks
Details of how you Planned & Executed the allotted work We observed the fixing of two base lines perpendicular to each other. These lines were fixed at the outer face of the column considering maximum number of column in the same line with similar faces. The faces were lined out by deducting the half size of column from the distance between two adjacent parallel centre line. For cross checking we checked the size of column as per drawings given to us. Then we checked the right angle of column, and measured the diagonal distance of column
Details of the Construction Procedure / Activity / Technology learned today Cutting of reinforcement bars,bar bending for slab, making of stirrups
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Centre line plan and detailed second floor plan
Details of the Bye Laws referred today Size of bath and w/c - Dimensions provided on the site for bath:-2.0*1.2=2.4sqm Dimensions provided on the site for w/c:-1.2*1.0=1.2sqm As per bye law the minimum dimensions to be provided is 1.8m*1.0m and 0.9m*0.9m
Details of any Managerial Skill learned today Doing centre line out of the column and maintaining the accuracy in work and soft talking with workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation external alluminium window “ Dimension of the window=1.6*1.2m=1.92sqm Quantity of glass required=1.92sqm=20.08sqft Length of alluminium frame required=6.8m=22.30 ft Labour required =2nos “Rate Analysis for external alluminium using cement paint” (Considering local rates of material) 1. Cost of alluminium frame=22.30*35=780/-………..(35/- per ft) 2. Cost of glass= 65*20.08=1305/-…………(65/- per sq.ft) 3. Cost of fixtures and fastenings=50/-………………..(lump sum) 4. Labour charges=300/-…………(150/- per fitter for half day) 5. Total cost=2435/- 6.10% profit of total cost for the contractor=243.5/- 7. Total cost=2678/- 10. Rate per sq.ft=133/-
Result of RATE ANALYSIS ( Rs per Unit ) 133 RS
Todays BUZZ Word The builders determine their construction rate per sq.ft. Consider their profit excluding the construction rate and the sum total of construction rate and profit is fixed as per sq.ft rate for the building. The rate fluctuates with increase and decrease of material cost. On our site rate of 2300/-per sq.ft is fixed and the cost of flat ranges from 20 lakhs to 25 lakhs. Extra cost to client-this cost is decided considering expenses of facilities provided such as type of tiles, type of paint, fittings, vatt charges, lift charges etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-11

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 5.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"P.C.C. Bed\" that was carried out for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Septic Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts.
Details of the Construction Procedure / Activity / Technology learned today 1. All the preparation works were carried out before starting the P.C.C work. 2. Then the \"Needle Vibrator\" was used as a \"Pump\" for Dewatering the bed. 3. At first petrol was used for its working & then the working was continued using Kerosene. 4. The P.C.C. mixture was prepared on a water tight surface. 5. The \"M10 Grade\" was used for preparation of P.C.C. bed. 6. The Ratio for M10 was as follow (1:3:6) 7. The procedure included the levelling of bed and dressing of the side walls. 8. The Mixture was laid dry as ground water was being accumilated in the pit. 9. Till that period the dewatering was continued. 10. Finally the P.C.C. bed was levelled using \"Panja\" & was compacted using \"Rammer
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate. 4. Panja. 5. Rammer. 6. Water.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Plans. 2. P.C.C. bed details. 3. Floor Plans. 4. Site Layout. 5. Service Plans. 6. Estimation for construction of Septic Tank.
Details of the Bye Laws referred today 1. Building Line. 2. Amenity Open Spaces. 3. Features Permitted in Open spaces. 4. Parking Spaces. 5. Septic Tank.
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # Rate Analysis For Aluminium Window # A) Window Size = 5\' x 4\' B) Material required: 1. Top Rail = 1.083 kg. 2. Side rail = 1.73 kg. 3. Bottom Rail = 1.167 kg. 4. Glass Frame - Top Frame = 0.625 kg. - Bottom frame = 0.625 kg. - Lock Frame = 1.5 kg. - Interlock Frame = 0.8 kg. 5. Glass Rubber = 26\' 6. Track Rubber = 72\' 7. Roller = 4 nos. 8. Glass = 20 sq.ft 9. Coating Powder = 20 sq.ft 10. Lock = 2 nos. 11. Screws C) Material Cost: 1. Top Rail = 1.083 x 180 = 194.94/- 2. Side Rail = 1.73 x 180 = 311.4/- 3. Bottom Rail = 1.167 x 180 = 210.06/- 4. Glass Frame a) Top = 0.625 x 180 = 112.5/- b) Bottom = 0.625 x 180 = 112.5/- c) Lock = 1.5 x 180 = 270/- d) InterLock = 0.8 x 180 = 144/- 5. Glass Rubber = 26 x 2 = 52/- 6. Track Rubber = 72 x 2 = 144/- 7. Roller = 4 x 20 = 80/- 8. Glass = 20 x 25 = 500/- 9. Coating Powder = 20 x 20 = 400/- 10. Lock = 2 x 30 = 60/- 11. Screws, etc. = 100/- Total = 2691.4/- D) Labour Cost: 1. Skilled Labour = 1 x 250 = 250/- 2. Mazdoor = 2 x 110 = 220/- Total = 470/- E) Grand Total = C + D = 3161.4/- F) Rate Per Sq.Ft = 158.07/- G) Rate Per Sq.M = 1700.58/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.1700.58/-
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". - First of all the total area of a particular flat is determined, - Then the various aspects such as the number of rooms, Salable area, Carpet area,F.S.I, etc.are determined. - Then the total construction cost of that particular flat is worked out. - Then the maintainance cost,independent parking cost,lift charges & deposits are worked out. - Then estimation of the other expenditures is done that includes documents cost, permission from muncipal corporation, etc. - Then total cost is removed. - Then Contractors & Builders Profit of 20% to 50% is Considered. - This is carried out by Estimation and Costing Department of builder. - The total grand cost is removed. - Then ths is kept in front of the client.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-11

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) janbandhu rakshit d
Exam No. 10875
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 5.30pm
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"P.C.C. Bed\" that was carried out for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Septic Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts.
Details of the Construction Procedure / Activity / Technology learned today 1. All the preparation works were carried out before starting the P.C.C work. 2. Then the \"Needle Vibrator\" was used as a \"Pump\" for Dewatering the bed. 3. At first petrol was used for its working & then the working was continued using Kerosene. 4. The P.C.C. mixture was prepared on a water tight surface. 5. The \"M10 Grade\" was used for preparation of P.C.C. bed. 6. The Ratio for M10 was as follow (1:3:6) 7. The procedure included the levelling of bed and dressing of the side walls. 8. The Mixture was laid dry as ground water was being accumilated in the pit. 9. Till that period the dewatering was continued. 10. Finally the P.C.C. bed was levelled using \"Panja\" & was compacted using \"Rammer
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate. 4. Panja. 5. Rammer. 6. Water.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Plans. 2. P.C.C. bed details. 3. Floor Plans. 4. Site Layout. 5. Service Plans. 6. Estimation for construction of Septic Tank.
Details of the Bye Laws referred today 1. Building Line. 2. Amenity Open Spaces. 3. Features Permitted in Open spaces. 4. Parking Spaces. 5. Septic Tank.
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # Rate Analysis For Aluminium Window # A) Window Size = 5\' x 4\' B) Material required: 1. Top Rail = 1.083 kg. 2. Side rail = 1.73 kg. 3. Bottom Rail = 1.167 kg. 4. Glass Frame - Top Frame = 0.625 kg. - Bottom frame = 0.625 kg. - Lock Frame = 1.5 kg. - Interlock Frame = 0.8 kg. 5. Glass Rubber = 26\' 6. Track Rubber = 72\' 7. Roller = 4 nos. 8. Glass = 20 sq.ft 9. Coating Powder = 20 sq.ft 10. Lock = 2 nos. 11. Screws C) Material Cost: 1. Top Rail = 1.083 x 180 = 194.94/- 2. Side Rail = 1.73 x 180 = 311.4/- 3. Bottom Rail = 1.167 x 180 = 210.06/- 4. Glass Frame a) Top = 0.625 x 180 = 112.5/- b) Bottom = 0.625 x 180 = 112.5/- c) Lock = 1.5 x 180 = 270/- d) InterLock = 0.8 x 180 = 144/- 5. Glass Rubber = 26 x 2 = 52/- 6. Track Rubber = 72 x 2 = 144/- 7. Roller = 4 x 20 = 80/- 8. Glass = 20 x 25 = 500/- 9. Coating Powder = 20 x 20 = 400/- 10. Lock = 2 x 30 = 60/- 11. Screws, etc. = 100/- Total = 2691.4/- D) Labour Cost: 1. Skilled Labour = 1 x 250 = 250/- 2. Mazdoor = 2 x 110 = 220/- Total = 470/- E) Grand Total = C + D = 3161.4/- F) Rate Per Sq.Ft = 158.07/- G) Rate Per Sq.M = 1700.58/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.1700.58/-
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". - First of all the total area of a particular flat is determined, - Then the various aspects such as the number of rooms, Salable area, Carpet area,F.S.I, etc.are determined. - Then the total construction cost of that particular flat is worked out. - Then the maintainance cost,independent parking cost,lift charges & deposits are worked out. - Then estimation of the other expenditures is done that includes documents cost, permission from muncipal corporation, etc. - Then total cost is removed. - Then Contractors & Builders Profit of 20% to 50% is Considered. - This is carried out by Estimation and Costing Department of builder. - The total grand cost is removed. - Then ths is kept in front of the client.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10983-11

Company Name V. S. Joshi & Associates
Project Name & Site Address vishva enclave,mukta sainik vasahat, kolhapur.
Students Name (Surname_First Name_Middle Name) KAMBLE ANKIT VIJAYANAND
Exam No. 10983
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 09:00
Site Leaving Time (HH:MM am/pm) 05:30
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"P.C.C. Bed\" that was carried out for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Septic Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts
Details of the Construction Procedure / Activity / Technology learned today 1. All the preparation works were carried out before starting the P.C.C work. 2. Then the \"Needle Vibrator\" was used as a \"Pump\" for Dewatering the bed. 3. At first petrol was used for its working & then the working was continued using Kerosene. 4. The P.C.C. mixture was prepared on a water tight surface. 5. The \"M10 Grade\" was used for preparation of P.C.C. bed. 6. The Ratio for M10 was as follow (1:3:6) 7. The procedure included the levelling of bed and dressing of the side walls. 8. The Mixture was laid dry as ground water was being accumilated in the pit. 9. Till that period the dewatering was continued. 10. Finally the P.C.C. bed was levelled using \"Panja\" & was compacted using \"Rammer\".
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate. 4. Panja. 5. Rammer. 6. Water.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. \"Storm Drains\" were Constructed at every border of the compound wall & was harvested. 2. \"Solar Panels\" for water heating purpose. 3. \"Crushed Sand\" was used as the composition in Construction of Septic tank.
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Plans. 2. P.C.C. bed details. 3. Floor Plans. 4. Site Layout. 5. Service Plans. 6. Estimation for construction of Septic Tank.
Details of the Bye Laws referred today 1. Building Line. 2. Amenity Open Spaces. 3. Features Permitted in Open spaces. 4. Parking Spaces. 5. Septic Tank.
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # Rate Analysis For Aluminium Window # A) Window Size = 5\' x 4\' B) Material required: 1. Top Rail = 1.083 kg. 2. Side rail = 1.73 kg. 3. Bottom Rail = 1.167 kg. 4. Glass Frame - Top Frame = 0.625 kg. - Bottom frame = 0.625 kg. - Lock Frame = 1.5 kg. - Interlock Frame = 0.8 kg. 5. Glass Rubber = 26\' 6. Track Rubber = 72\' 7. Roller = 4 nos. 8. Glass = 20 sq.ft 9. Coating Powder = 20 sq.ft 10. Lock = 2 nos. 11. Screws C) Material Cost: 1. Top Rail = 1.083 x 180 = 194.94/- 2. Side Rail = 1.73 x 180 = 311.4/- 3. Bottom Rail = 1.167 x 180 = 210.06/- 4. Glass Frame a) Top = 0.625 x 180 = 112.5/- b) Bottom = 0.625 x 180 = 112.5/- c) Lock = 1.5 x 180 = 270/- d) InterLock = 0.8 x 180 = 144/- 5. Glass Rubber = 26 x 2 = 52/- 6. Track Rubber = 72 x 2 = 144/- 7. Roller = 4 x 20 = 80/- 8. Glass = 20 x 25 = 500/- 9. Coating Powder = 20 x 20 = 400/- 10. Lock = 2 x 30 = 60/- 11. Screws, etc. = 100/- Total = 2691.4/- D) Labour Cost: 1. Skilled Labour = 1 x 250 = 250/- 2. Mazdoor = 2 x 110 = 220/- Total = 470/- E) Grand Total = C + D = 3161.4/- F) Rate Per Sq.Ft = 158.07/- G) Rate Per Sq.M = 1700.58/- --------------------------------------------------------------------------- Result of RATE ANALYSIS ( Rs per Unit ) * Rs.1700.58/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.1700.58/- per meter cube
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". - First of all the total area of a particular flat is determined, - Then the various aspects such as the number of rooms, Salable area, Carpet area,F.S.I, etc.are determined. - Then the total construction cost of that particular flat is worked out. - Then the maintainance cost,independent parking cost,lift charges & deposits are worked out. - Then estimation of the other expenditures is done that includes documents cost, permission from muncipal corporation, etc. - Then total cost is removed. - Then Contractors & Builders Profit of 20% to 50% is Considered. - This is carried out by Estimation and Costing Department of builder. - The total grand cost is removed. - Then ths is kept in front of the client.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: cool.sushant007@gmail.com
Subject: 10880-11

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) PATIL SUSHANT DIGMBER
Exam No. 10880
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE CENTERING WORK DONE FOR THE SLAB.
Details of how you Planned & Executed the allotted work WE STUDIED THE STEEL DRAWINGS AND DIRECTLY GO TO FLOOR WHERE THE WORK IS GOING ON.
Details of the Construction Procedure / Activity / Technology learned today BARS ARE BEND AT THE DISTANCE OF L/4 TO RESTRICT SAGGING MOMENT OF SLAB BECAUSE IT INCREASES THE C/S OF SLAB OF THAT PORTION. MAIN BARS ARE NORMALLY PROVIDED PARALLEL TO SHORTER SPAN AND DISTRIBUTION BARS ARE PARALLEL TO LONGER SPAN.
Details of the Construction Materials learned today DIFFERENT SIZES OF MILD AND STEEL BARS.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today STEEL DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 175.00 RUBBER STRIP USED- Rs- 38 lump sump- 125 locks -2 no. - 100 Rs labour cost - 40/sq.ft total cost- 478 RS= 242.45=243 RS
Result of RATE ANALYSIS ( Rs per Unit ) 243 RS
Todays BUZZ Word BUILDER DECIDE THE COST OF THE FLATS AND BUNGALOWS 1.FIRST THEY MEASURE THE CARPET AREA MEANS THE AREA EXCLUDING THE WALL AND THE AREA OF TERRACE ,BALCONIES AND OPEN SPACES 25% - 30% 2.PARKING AREA AND MAINTAINENCE CHARGES ARE ALSO INCLUDED WHILE CALCULATING THE COST OF FLAT.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. ketan charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-11

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) PATIL ADITYA PANDURANG
Exam No. 13538
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE CONSTRUCTION OF BRICK WORK.
Details of how you Planned & Executed the allotted work WE FIRST STUDIED THE WORKING DRAWING THEN GO TO THE PLACE WHERE THE WORK IS GOING ON.
Details of the Construction Procedure / Activity / Technology learned today IF ONE BRICK WALL IS CONSTRUCTED THEN THE P.C.C. LAYER IS PROVIDED NORMALLY AT DISTANCE OF 1-1.2 M . SO THAT STABILITY OF WALL SHOULD NOT GET DISTURBED. THE WORK IS CHECKED BY PLUM-BOB. TO CHECK THE ALIGNMENT OF THE BRICK WORK WHETHER IT IS DONE PROPERLY OR NOT.
Details of the Construction Materials learned today BRICK , BONDING MATERIAL - CEMENT , SAND . AND ITS PROPORTION.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today WORKING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 200.00 RUBBER STRIP USED- Rs- 45 lump sump- 100 locks -2 no. - 50 Rs labour cost - 35/sq.ft total cost- 430 RS= 223.45=225 RS
Result of RATE ANALYSIS ( Rs per Unit ) 225 Rs
Todays BUZZ Word BUILDER DECIDE THE COST OF THE FLATS AND BUNGALOWS 1.FIRST THEY MEASURE THE CARPET AREA MEANS THE AREA EXCLUDING THE WALL AND THE AREA OF TERRACE ,BALCONIES AND OPEN SPACES 25% - 30% 2.PARKING AREA AND MAINTAINENCE CHARGES ARE ALSO INCLUDED WHILE CALCULATING THE COST OF FLAT.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-11

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE CONSTRUCTION OF BRICK WORK.
Details of how you Planned & Executed the allotted work WE FIRST STUDIED THE WORKING DRAWING THEN GO TO THE PLACE WHERE THE WORK IS GOING ON.
Details of the Construction Procedure / Activity / Technology learned today IF ONE BRICK WALL IS CONSTRUCTED THEN THE P.C.C. LAYER IS PROVIDED NORMALLY AT DISTANCE OF 1-1.2 M . SO THAT STABILITY OF WALL SHOULD NOT GET DISTURBED. THE WORK IS CHECKED BY PLUM-BOB. TO CHECK THE ALIGNMENT OF THE BRICK WORK WHETHER IT IS DONE PROPERLY OR NOT
Details of the Construction Materials learned today BRICK , BONDING MATERIAL - CEMENT , SAND . AND ITS PROPORTION.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today WORKING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 200.00 RUBBER STRIP USED- Rs- 45 lump sump- 100 locks -2 no. - 50 Rs labour cost - 35/sq.ft total cost- 430 RS= 223.45=225 RS
Result of RATE ANALYSIS ( Rs per Unit ) 225 Rs
Todays BUZZ Word BUILDER DECIDE THE COST OF THE FLATS AND BUNGALOWS 1.FIRST THEY MEASURE THE CARPET AREA MEANS THE AREA EXCLUDING THE WALL AND THE AREA OF TERRACE ,BALCONIES AND OPEN SPACES 25% - 30% 2.PARKING AREA AND MAINTAINENCE CHARGES ARE ALSO INCLUDED WHILE CALCULATING THE COST OF FLAT.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-11

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Nagvekar Yogesh Deepak
Exam No. 10894
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"P.C.C. Bed\" that was carried out for the \"Septic Tank\". ------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Septic Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts. -----------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today 1. All the preparation works were carried out before starting the P.C.C work. 2. Then the \"Needle Vibrator\" was used as a \"Pump\" for Dewatering the bed. 3. At first petrol was used for its working & then the working was continued using Kerosene. 4. The P.C.C. mixture was prepared on a water tight surface. 5. The \"M10 Grade\" was used for preparation of P.C.C. bed. 6. The Ratio for M10 was as follow (1:3:6) 7. The procedure included the levelling of bed and dressing of the side walls. 8. The Mixture was laid dry as ground water was being accumilated in the pit. 9. Till that period the dewatering was continued. 10. Finally the P.C.C. bed was levelled using \"Panja\" & was compacted using \"Rammer\". -----------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate. 4. Panja. 5. Rammer. 6. Water. -----------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. \"Storm Drains\" were Constructed at every border of the compound wall & was harvested. 2. \"Solar Panels\" for water heating purpose. 3. \"Crushed Sand\" was used as the composition in Construction of Septic tank. -----------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Plans. 2. P.C.C. bed details. 3. Floor Plans. 4. Site Layout. 5. Service Plans. 6. Estimation for construction of Septic Tank. ----------------------------------------------------------------------
Details of the Bye Laws referred today 1. Building Line. 2. Amenity Open Spaces. 3. Features Permitted in Open spaces. 4. Parking Spaces. 5. Septic Tank. --------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality. -------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # Rate Analysis For Aluminium Window # A) Window Size = 5\' x 4\' B) Material required: 1. Top Rail = 1.083 kg. 2. Side rail = 1.73 kg. 3. Bottom Rail = 1.167 kg. 4. Glass Frame - Top Frame = 0.625 kg. - Bottom frame = 0.625 kg. - Lock Frame = 1.5 kg. - Interlock Frame = 0.8 kg. 5. Glass Rubber = 26\' 6. Track Rubber = 72\' 7. Roller = 4 nos. 8. Glass = 20 sq.ft 9. Coating Powder = 20 sq.ft 10. Lock = 2 nos. 11. Screws C) Material Cost: 1. Top Rail = 1.083 x 180 = 194.94/- 2. Side Rail = 1.73 x 180 = 311.4/- 3. Bottom Rail = 1.167 x 180 = 210.06/- 4. Glass Frame a) Top = 0.625 x 180 = 112.5/- b) Bottom = 0.625 x 180 = 112.5/- c) Lock = 1.5 x 180 = 270/- d) InterLock = 0.8 x 180 = 144/- 5. Glass Rubber = 26 x 2 = 52/- 6. Track Rubber = 72 x 2 = 144/- 7. Roller = 4 x 20 = 80/- 8. Glass = 20 x 25 = 500/- 9. Coating Powder = 20 x 20 = 400/- 10. Lock = 2 x 30 = 60/- 11. Screws, etc. = 100/- Total = 2691.4/- D) Labour Cost: 1. Skilled Labour = 1 x 250 = 250/- 2. Mazdoor = 2 x 110 = 220/- Total = 470/- E) Grand Total = C + D = 3161.4/- F) Rate Per Sq.Ft = 158.07/- G) Rate Per Sq.M = 1700.58/- ---------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs.1700.58/-
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". - First of all the total area of a particular flat is determined, - Then the various aspects such as the number of rooms, Salable area, Carpet area,F.S.I, etc.are determined. - Then the total construction cost of that particular flat is worked out. - Then the maintainance cost,independent parking cost,lift charges & deposits are worked out. - Then estimation of the other expenditures is done that includes documents cost, permission from muncipal corporation, etc. - Then total cost is removed. - Then Contractors & Builders Profit of 20% to 50% is Considered. - This is carried out by Estimation and Costing Department of builder. - The total grand cost is removed. - Then ths is kept in front of the client. ----------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376) -----------------------------------------------------------------------------
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-11

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Hasabnis Ketaki Bhagwan
Exam No. 13527
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see and study the laying of steel reinforcement for beams of third floor. To see the concreting of columns of second floor.
Details of how you Planned & Executed the allotted work We first went on second floor, where the concreting of column was going on. The concrete was made at the site itself and it was brought up to second floor by skip and hoist.Then we went to the third floor to check the centering work .The steel reinforcemnt of beams were being layed .
Details of the Construction Procedure / Activity / Technology learned today We learnt the process of concreting of columns of second floor and laying of steel reinforcement for third floor,and process of manufacturing concrete at site, We also saw the curing of staircase for third floor that was casted two days before, we saw the removal of formwork for second floor.
Details of the Construction Materials learned today Reinforcement for beams. Steel bars. Tor steel: 6mm,8mm,12mm,16mm,20mm,25mm,30mm. Mild steel:6mm,8mm,12mm. Ordinary Portland Cement (O.P.C)= 43 Grade, 53 Grade. Bagalkot Supreme. Crushed sand,coarse aggregate,water.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today A new technology for recycling of garbage known as Garbage Chute system with waste water treatment plant will be adopted after the completion of construction.
Details of the Construction / Engineering Drawings observed today > Plan for second floor. > Plan for third floor with schedule of beams and columns.
Details of the Bye Laws referred today Minimum spacing between stirrups was kept by using bye laws. Height of each floor is according to bye laws.
Details of any Managerial Skill learned today > The site incharge inspected the place where concreting of columns were going on. > The site incharge has a good command over the labourers. > The site incharge checked the reinforcement of steel that was being layed for third floor.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"FULLY COMPLETE WINDOW\" Aluminium window- Double track. Aluminum-6.9 kg/sq.m Rate of aluminium=6.9*250= Rs.1725. Bagri glass 4mm thick-Rs.325/sq.m Rubber gasket= Rs.20/sq.m Fixtures= Stoppers etc.= Rs.100/sq.m Total cost= 1725+325+20+100= Rs.2170/sq.m Labour=30% Total cost= 2170+651=Rs.2821/sq.m Including 10% profit=28.21 Total cost= 2821+28.21= Rs.3103.1 /sq.m= Rs.3103/sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.3103/sq.m
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". > The builders first determine the total area of a particular flat, then they consider the number of rooms,Salable area,Carpet area,F.S.I,facilities provided etc. > Then they workout the total construction cost of that particular flat with the facilities provided i.e Rate per sq.ft, they compare this rate with present market rates. > They also consider the total one time maintainance cost,independent parking cost,Monthly lift charges,deposit for reticulated gas pipeline system(if provided any),etc. > Then they estimate the other expenditures which includes documents cost, permission from muncipal corporation,stamp duty,agreement cost,VAT,service tax,Infra charges,basic cost etc. > Then they add all the above things and value that comes will be the actual cost.Now they add their profit to this cost which may be 20% to 50%. This profit is not mentioned in the total cost. This work is done by Estimation and Costing department of builder. > The value that comes is finally the total package which is offered to the client.This cost may be reduced to a little extent while the discussions of the builder and the client.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883

Company Name Star Tech Infra
Project Name & Site Address star aashiyana near rajendra nagar.KolhAPUR
Students Name (Surname_First Name_Middle Name) arora saurabh
Exam No. 10883
Working Day No. 11
Date (DD/MM/YYYY) 20/12/10
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge Landscaping and fabrication work.
Details of how you Planned & Executed the allotted work we observed working drawing of open space,n construction for it .
Details of the Construction Procedure / Activity / Technology learned today ans3:we learned the levelling of the ground for garden devlopment,proper planning in planting of different types of bushes.n we observed d working drawing of open space.
Details of the Construction Materials learned today ans4:Quality consciousness is an important aspect of construction managment,especially when it comes to materials. All the materiaLS received at the site should be tested for quality. we observe the quality for bricks. characteristics of good bricks: it should have high strength and durability should have standard size,should have uniform colour. it should feer from cracks,should be resistent to fire,and have proper porosity.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today ans5:water after the use of human beings is converted into waste. and treatment of waste is to protect the public health and environment . treatment consist of primary treatment ,secondary treatment,disinfection and disposal of solid.
Details of the Construction / Engineering Drawings observed today ans6:we obsrved the working drawing . points to be observed in working drawing . north direction name plate direction of door opening direction of bath/wc door opening center line cheking dotte lines for chajja,rolling shutter. specificatin details in brief.
Details of the Bye Laws referred today ans7:open space-A clear openspace of 3.0m all around the building shall be provided.
Details of any Managerial Skill learned today ans8:how to handel the workers puntuality alertness regularity in work
RATE ANALYSIS (Detailed Stepwise Calculations required) ans9:window frame length 5ft * 4ft track= 20ft frame=26ft glass=2no.*2\'6\"*4\'0\" lock=2no. rubber=26ft screw=16no. 20+26+20+26=92ft Rate 120rs/ft2 Total=120*90=10800ft2 1m2=10.76ft2 =1003m2
Result of RATE ANALYSIS ( Rs per Unit ) 1003m2
Todays BUZZ Word ans10:builders determine rates of flats /bungalows depends upon the floor area cost per sq ft + constuction cost and in total of these added 20% contactor benifit . and after that what ever be the cost will come will be the cost of that flat.included tdr,trade,n all taxes .and it also depends upon the area where it is located.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SATISH 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-11

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Jape Vishwajeet Ramesh
Exam No. 10892
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge 1. Preparation of \"Daily Site Report\" of \"Labours & Construction Works\" that were carried today. 2. Study of \"P.C.C. Bed\" that was carried out for the \"Septic Tank\". ------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work 1. First Of all we all went to the \"C-Wing of Vishwa Enclave\" to collect the information regarding various construction works that were carried out. 2. Then we prepared the \"Daily Site Report\". 3. Then we all together went to the site where the \"Septic Tank\" was being constructed. 4. Then with the help of site incharge we asked our queris & cleared our doubts. -----------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today 1. All the preparation works were carried out before starting the P.C.C work. 2. Then the \"Needle Vibrator\" was used as a \"Pump\" for Dewatering the bed. 3. At first petrol was used for its working & then the working was continued using Kerosene. 4. The P.C.C. mixture was prepared on a water tight surface. 5. The \"M10 Grade\" was used for preparation of P.C.C. bed. 6. The Ratio for M10 was as follow (1:3:6) 7. The procedure included the levelling of bed and dressing of the side walls. 8. The Mixture was laid dry as ground water was being accumilated in the pit. 9. Till that period the dewatering was continued. 10. Finally the P.C.C. bed was levelled using \"Panja\" & was compacted using \"Rammer\". -----------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. Crushed Sand. 2. Cement (43-Grade). 3. Coarse Aggregate. 4. Panja. 5. Rammer. 6. Water. -----------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. \"Storm Drains\" were Constructed at every border of the compound wall & was harvested. 2. \"Solar Panels\" for water heating purpose. 3. \"Crushed Sand\" was used as the composition in Construction of Septic tank. -----------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Plans. 2. P.C.C. bed details. 3. Floor Plans. 4. Site Layout. 5. Service Plans. 6. Estimation for construction of Septic Tank. ----------------------------------------------------------------------
Details of the Bye Laws referred today 1. Building Line. 2. Amenity Open Spaces. 3. Features Permitted in Open spaces. 4. Parking Spaces. 5. Septic Tank. --------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1. Handling the labours. 2. Maintaining Cleanliness on the site 3. Way of Dressing 2 suite ones personality. 4. Sensitivity. 5. Punctuality. -------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # Rate Analysis For Aluminium Window # A) Window Size = 5\' x 4\' B) Material required: 1. Top Rail = 1.083 kg. 2. Side rail = 1.73 kg. 3. Bottom Rail = 1.167 kg. 4. Glass Frame - Top Frame = 0.625 kg. - Bottom frame = 0.625 kg. - Lock Frame = 1.5 kg. - Interlock Frame = 0.8 kg. 5. Glass Rubber = 26\' 6. Track Rubber = 72\' 7. Roller = 4 nos. 8. Glass = 20 sq.ft 9. Coating Powder = 20 sq.ft 10. Lock = 2 nos. 11. Screws C) Material Cost: 1. Top Rail = 1.083 x 180 = 194.94/- 2. Side Rail = 1.73 x 180 = 311.4/- 3. Bottom Rail = 1.167 x 180 = 210.06/- 4. Glass Frame a) Top = 0.625 x 180 = 112.5/- b) Bottom = 0.625 x 180 = 112.5/- c) Lock = 1.5 x 180 = 270/- d) InterLock = 0.8 x 180 = 144/- 5. Glass Rubber = 26 x 2 = 52/- 6. Track Rubber = 72 x 2 = 144/- 7. Roller = 4 x 20 = 80/- 8. Glass = 20 x 25 = 500/- 9. Coating Powder = 20 x 20 = 400/- 10. Lock = 2 x 30 = 60/- 11. Screws, etc. = 100/- Total = 2691.4/- D) Labour Cost: 1. Skilled Labour = 1 x 250 = 250/- 2. Mazdoor = 2 x 110 = 220/- Total = 470/- E) Grand Total = C + D = 3161.4/- F) Rate Per Sq.Ft = 158.07/- G) Rate Per Sq.M = 1700.58/- ---------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs.1700.58/-
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". - First of all the total area of a particular flat is determined, - Then the various aspects such as the number of rooms, Salable area, Carpet area,F.S.I, etc.are determined. - Then the total construction cost of that particular flat is worked out. - Then the maintainance cost,independent parking cost,lift charges & deposits are worked out. - Then estimation of the other expenditures is done that includes documents cost, permission from muncipal corporation, etc. - Then total cost is removed. - Then Contractors & Builders Profit of 20% to 50% is Considered. - This is carried out by Estimation and Costing Department of builder. - The total grand cost is removed. - Then ths is kept in front of the client. ----------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376) -----------------------------------------------------------------------------
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: viju128@gmail.com
Subject: 3638-11

Company Name Star Tech Infra
Project Name & Site Address star aashiyana near rajendra nagar.kolhapur
Students Name (Surname_First Name_Middle Name) shinde vijay namdeo
Exam No. 3638
Working Day No. 11
Date (DD/MM/YYYY) 20/12/10
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge Landscaping and fabrication work.
Details of how you Planned & Executed the allotted work we observed working drawing of open space,n construction for it .
Details of the Construction Procedure / Activity / Technology learned today ans3:we learned the levelling of the ground for garden devlopment,proper planning in planting of different types of bushes.n we observed d working drawing of open space.
Details of the Construction Materials learned today ans4:Quality consciousness is an important aspect of construction managment,especially when it comes to materials. All the materiaLS received at the site should be tested for quality. we observe the quality for bricks. characteristics of good bricks: it should have high strength and durability should have standard size,should have uniform colour. it should feer from cracks,should be resistent to fire,and have proper porosity.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today ans5:water after the use of human beings is converted into waste. and treatment of waste is to protect the public health and environment . treatment consist of primary treatment ,secondary treatment,disinfection and disposal of solid.
Details of the Construction / Engineering Drawings observed today ans6:we obsrved the working drawing . points to be observed in working drawing . north direction name plate direction of door opening direction of bath/wc door opening center line cheking dotte lines for chajja,rolling shutter. specificatin details in brief.
Details of the Bye Laws referred today ans7:open space-A clear openspace of 3.0m all around the building shall be provided.
Details of any Managerial Skill learned today ans8:how to handel the workers puntuality alertness regularity in work
RATE ANALYSIS (Detailed Stepwise Calculations required) ans9:window frame length 5ft * 4ft track= 20ft frame=26ft glass=2no.*2\'6\"*4\'0\" lock=2no. rubber=26ft screw=16no. 20+26+20+26=92ft Rate 120rs/ft2 Total=120*90=10800ft2 1m2=10.76ft2 =1003m2
Result of RATE ANALYSIS ( Rs per Unit ) 1003m2
Todays BUZZ Word ans10:builders determine rates of flats /bungalows depends upon the floor area cost per sq ft + constuction cost and in total of these added 20% contactor benifit . and after that what ever be the cost will come will be the cost of that flat.included tdr,trade,n all taxes .and it also depends upon the area where it is located.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 90110339689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: pinkrosee4u@yahoo.com
Subject: 10878-11

Company Name Star Tech Infra
Project Name & Site Address star aashiyana near rajender nagar, kolhapur
Students Name (Surname_First Name_Middle Name) narnaware shikha haridas
Exam No. 10878
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge Landscaping and fabrication work.
Details of how you Planned & Executed the allotted work we observed working drawing of open space,n construction for it .
Details of the Construction Procedure / Activity / Technology learned today we learned the levelling of the ground for garden devlopment,proper planning in planting of different types of bushes.n we observed d working drawing of open space.
Details of the Construction Materials learned today Quality consciousness is an important aspect of construction managment,especially when it comes to materials. All the materiaLS received at the site should be tested for quality. we observe the quality for bricks. characteristics of good bricks: it should have high strength and durability should have standard size,should have uniform colour. it should feer from cracks,should be resistent to fire,and have proper porosity.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today :water after the use of human beings is converted into waste. and treatment of waste is to protect the public health and environment . treatment consist of primary treatment ,secondary treatment,disinfection and disposal of solid.
Details of the Construction / Engineering Drawings observed today ans6:we obsrved the working drawing . points to be observed in working drawing . north direction name plate direction of door opening direction of bath/wc door opening center line cheking dotte lines for chajja,rolling shutter. specificatin details in brief.
Details of the Bye Laws referred today open space-A clear openspace of 3.0m all around the building shall be provided.
Details of any Managerial Skill learned today how to handel the workers puntuality alertness regularity in work
RATE ANALYSIS (Detailed Stepwise Calculations required) window frame length 5ft * 4ft track= 20ft frame=26ft glass=2no.*2\'6\"*4\'0\" lock=2no. rubber=26ft screw=16no. 20+26+20+26=92ft Rate 120rs/ft2 Total=120*90=10800ft2 1m2=10.76ft2 =1003m2
Result of RATE ANALYSIS ( Rs per Unit ) 1003m2
Todays BUZZ Word builders determine rates of flats /bungalows depends upon the floor area cost per sq ft + constuction cost and in total of these added 20% contactor benifit . and after that what ever be the cost will come will be the cost of that flat.included tdr,trade,n all taxes .and it also depends upon the area where it is located.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-11

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) jadhav nilam jaywant
Exam No. 13528
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge to see the elecrification
Details of how you Planned & Executed the allotted work 1) Firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans
Details of the Construction Procedure / Activity / Technology learned today 1) We are all groupmates study the Electrical drawing 2) Our quarries are asked to wire fitter 3) To measure height of switch board, foot light from bottom 4) Seperate space is provided at entrance of size 0.75*0.60M conveying all electrical wire to the ground level 5) Which are connected to main meter at basement 6) The Main Meter is connected to MSEB
Details of the Construction Materials learned today 1) 8 Module,4 Module switch board 2) PVC pipe for concealed wiring ,positive, negative, earthing wiring 3) Pana 4) Iron net which is placed on a concealed wiring to avoid cracking
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today electrification drawings
Details of the Bye Laws referred today no
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) 3 track- 2 glass shutter 1 s.s. net shutter sliding window(Bajari glass 3.5 mm) - Rs.175.00 rubber strip used -Rs.30 lump sump-Rs.100 Locks-2 no.-Rs.50 each. labour cost.:Rs.30/Sq.ft. total.-Rs.475/(1.5m/1.2m)=RS.241.22245/Sq.m
Result of RATE ANALYSIS ( Rs per Unit ) RS.241.22245/Sq.m
Todays BUZZ Word HOW BUILDERS DETERMINE RATES OF FLAT/BUNGALOW + EXTRA COSTS TO CLIENTS: The builders consider the following points points while determining the cost: 1)LAND COST 2)LAND DEVELOPMENT COST 3)CONSTRUCTION MATERIAL COST 4)LABOUR COST 5)ADVERTISEMENT COST 6)SECURITY COST 7)MAINTENANCE COST 8)FACILITY AREA COST(GARDEN AREA,GYM,CLUB HOUSE) 9)MANAGEMENT COST Also the Contractors or Builders add their own profit maybe 15-20%.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-11

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) jadhav swapnil ashok
Exam No. 13529
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge to see the elecrification
Details of how you Planned & Executed the allotted work 1) Firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans
Details of the Construction Procedure / Activity / Technology learned today 1) We are all groupmates study the Electrical drawing 2) Our quarries are asked to wire fitter 3) To measure height of switch board, foot light from bottom 4) Seperate space is provided at entrance of size 0.75*0.60M conveying all electrical wire to the ground level 5) Which are connected to main meter at basement 6) The Main Meter is connected to MSEB
Details of the Construction Materials learned today 1) 8 Module,4 Module switch board 2) PVC pipe for concealed wiring ,positive, negative, earthing wiring 3) Pana 4) Iron net which is placed on a concealed wiring to avoid cracking
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today electrification drawings
Details of the Bye Laws referred today no
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) 3 track- 2 glass shutter 1 s.s. net shutter sliding window(Bajari glass 3.5 mm) - Rs.175.00 rubber strip used -Rs.30 lump sump-Rs.100 Locks-2 no.-Rs.50 each. labour cost.:Rs.30/Sq.ft. total.-Rs.475/(1.5m/1.2m)=RS.241.22245/Sq.m
Result of RATE ANALYSIS ( Rs per Unit ) RS.241.22245/Sq.m
Todays BUZZ Word HOW BUILDERS DETERMINE RATES OF FLAT/BUNGALOW + EXTRA COSTS TO CLIENTS: The builders consider the following points points while determining the cost: 1)LAND COST 2)LAND DEVELOPMENT COST 3)CONSTRUCTION MATERIAL COST 4)LABOUR COST 5)ADVERTISEMENT COST 6)SECURITY COST 7)MAINTENANCE COST 8)FACILITY AREA COST(GARDEN AREA,GYM,CLUB HOUSE) 9)MANAGEMENT COST Also the Contractors or Builders add their own profit maybe 15-20%.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-11

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) dsouza agnel santan
Exam No. 13524
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge to see the electrification
Details of how you Planned & Executed the allotted work 1) Firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans
Details of the Construction Procedure / Activity / Technology learned today 1) We are all groupmates study the Electrical drawing 2) Our quarries are asked to wire fitter 3) To measure height of switch board, foot light from bottom 4) Seperate space is provided at entrance of size 0.75*0.60M conveying all electrical wire to the ground level 5) Which are connected to main meter at basement 6) The Main Meter is connected to MSEB
Details of the Construction Materials learned today 1) 8 Module,4 Module switch board 2) PVC pipe for concealed wiring ,positive, negative, earthing wiring 3) Pana 4) Iron net which is placed on a concealed wiring to avoid cracking
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today electrification drawings
Details of the Bye Laws referred today no
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) 3 track- 2 glass shutter 1 s.s. net shutter sliding window(Bajari glass 3.5 mm) - Rs.175.00 rubber strip used -Rs.30 lump sump-Rs.100 Locks-2 no.-Rs.50 each. labour cost.:Rs.30/Sq.ft. total.-Rs.475/(1.5m/1.2m)=RS.241.22245/Sq.m
Result of RATE ANALYSIS ( Rs per Unit ) RS.241.22245/Sq.m
Todays BUZZ Word HOW BUILDERS DETERMINE RATES OF FLAT/BUNGALOW + EXTRA COSTS TO CLIENTS: The builders consider the following points points while determining the cost: 1)LAND COST 2)LAND DEVELOPMENT COST 3)CONSTRUCTION MATERIAL COST 4)LABOUR COST 5)ADVERTISEMENT COST 6)SECURITY COST 7)MAINTENANCE COST 8)FACILITY AREA COST(GARDEN AREA,GYM,CLUB HOUSE) 9)MANAGEMENT COST Also the Contractors or Builders add their own profit maybe 15-20%.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-11

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) MISAL SWAPNIL SHIVAJI
Exam No. 10877
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE CENTERING WORK DONE FOR THE SLAB.
Details of how you Planned & Executed the allotted work WE STUDIED THE STEEL DRAWINGS AND DIRECTLY GO TO FLOOR WHERE THE WORK IS GOING ON.
Details of the Construction Procedure / Activity / Technology learned today BARS ARE BEND AT THE DISTANCE OF L/4 TO RESTRICT SAGGING MOMENT OF SLAB BECAUSE IT INCREASES THE C/S OF SLAB OF THAT PORTION. MAIN BARS ARE NORMALLY PROVIDED PARALLEL TO SHORTER SPAN AND DISTRIBUTION BARS ARE PARALLEL TO LONGER SPAN.
Details of the Construction Materials learned today DIFFERENT SIZES OF MILD AND STEEL BARS.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today STEEL DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 175.00 RUBBER STRIP USED- Rs- 38 lump sump- 125 locks -2 no. - 100 Rs labour cost - 40/sq.ft total cost- 478 RS= 242.45=243 RS
Result of RATE ANALYSIS ( Rs per Unit ) 243 RS
Todays BUZZ Word BUILDER DECIDE THE COST OF THE FLATS AND BUNGALOWS 1.FIRST THEY MEASURE THE CARPET AREA MEANS THE AREA EXCLUDING THE WALL AND THE AREA OF TERRACE ,BALCONIES AND OPEN SPACES 25% - 30% 2.PARKING AREA AND MAINTAINENCE CHARGES ARE ALSO INCLUDED WHILE CALCULATING THE COST OF FLAT.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ketan charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-11

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Patil Vrishali Vitthal
Exam No. 13541
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.00pm.
Details of the Work Allotted to you today by the Site In-Charge to observe the preparation of form-work for column
Details of how you Planned & Executed the allotted work we just observe accurate dimention of form work accourding to column size. we checked all columns were at the accurate position.
Details of the Construction Procedure / Activity / Technology learned today making of starter before casting of column. workers used wooden battens with proper shape for making formwork for starter
Details of the Construction Materials learned today crude oil- it is burned oil ,we get it from vehicles. used for polish the surface of formwork before casting of column is done.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of wasted oil from vehicles can be utilised as lubrickent which reduces environmental pollution
Details of the Construction / Engineering Drawings observed today design of column- 1.it consist of design details of columns 2.no.of stirrups and their respective arrangement
Details of the Bye Laws referred today min. projection of chujja-0.6m. min. projection of cantiliver balcony-1.2m.
Details of any Managerial Skill learned today politeness and friendly
RATE ANALYSIS (Detailed Stepwise Calculations required) consider size of window(window frame)=1.8m.x1.2m. type of window -aluminium glazed total alluminium required =8.4x0.4x0.3 total glass required=3.44 x 1.12 amount for alluminium =1500 Rs. amount for glass =4000 Rs. labour cost =200 Rs. total amount required =5700 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 5700 Rs./ window
Todays BUZZ Word builder include following things in estimation for selling of property- 1.rate per sq. feet eg. 2700 Rs. 2.rate for parking eg.100000 Rs. 3.rate for M.S.E.B. eg.45000 Rs. 4.doccumentary =as per comity this exchange is done by black and white system black means -by hard cash white means -by check
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: prasadkharat@ymail.com
Subject: 13531-11

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Prasad Ramachandra
Exam No. 13531
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.00pm.
Details of the Work Allotted to you today by the Site In-Charge to observe the preparation of form-work for column
Details of how you Planned & Executed the allotted work we just observe accurate dimention of form work accourding to column size. we checked all columns were at the accurate position.
Details of the Construction Procedure / Activity / Technology learned today making of starter before casting of column. workers used wooden battens with proper shape for making formwork for starter
Details of the Construction Materials learned today crude oil- it is burned oil ,we get it from vehicles. used for polish the surface of formwork before casting of column is done.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of wasted oil from vehicles can be utilised as lubrickent which reduces environmental pollution
Details of the Construction / Engineering Drawings observed today design of column- 1.it consist of design details of columns 2.no.of stirrups and their respective arrangement
Details of the Bye Laws referred today min. projection of chujja-0.6m. min. projection of cantiliver balcony-1.2m.
Details of any Managerial Skill learned today politeness and friendly
RATE ANALYSIS (Detailed Stepwise Calculations required) consider size of window(window frame)=1.8m.x1.2m. type of window -aluminium glazed total alluminium required =8.4x0.4x0.3 total glass required=3.44 x 1.12 amount for alluminium =1500 Rs. amount for glass =4000 Rs. labour cost =200 Rs. total amount required =5700 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 5700 Rs./ window
Todays BUZZ Word builder include following things in estimation for selling of property- 1.rate per sq. feet eg. 2700 Rs. 2.rate for parking eg.100000 Rs. 3.rate for M.S.E.B. eg.45000 Rs. 4.doccumentary =as per comity this exchange is done by black and white system black means -by hard cash white means -by check
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-11

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Lad Manoj Sadashive
Exam No. 13534
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.00pm.
Details of the Work Allotted to you today by the Site In-Charge to observe the preparation of form-work for column
Details of how you Planned & Executed the allotted work we just observe accurate dimention of form work accourding to column size. we checked all columns were at the accurate position.
Details of the Construction Procedure / Activity / Technology learned today making of starter before casting of column. workers used wooden battens with proper shape for making formwork for starter
Details of the Construction Materials learned today crude oil- it is burned oil ,we get it from vehicles. used for polish the surface of formwork before casting of column is done.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of wasted oil from vehicles can be utilised as lubrickent which reduces environmental pollution
Details of the Construction / Engineering Drawings observed today design of column- 1.it consist of design details of columns 2.no.of stirrups and their respective arrangement
Details of the Bye Laws referred today min. projection of chujja-0.6m. min. projection of cantiliver balcony-1.2m.
Details of any Managerial Skill learned today politeness and friendly
RATE ANALYSIS (Detailed Stepwise Calculations required) consider size of window(window frame)=1.8m.x1.2m. type of window -aluminium glazed total alluminium required =8.4x0.4x0.3 total glass required=3.44 x 1.12 amount for alluminium =1500 Rs. amount for glass =4000 Rs. labour cost =200 Rs. total amount required =5700 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 5700 Rs./ window
Todays BUZZ Word builder include following things in estimation for selling of property- 1.rate per sq. feet eg. 2700 Rs. 2.rate for parking eg.100000 Rs. 3.rate for M.S.E.B. eg.45000 Rs. 4.doccumentary =as per comity this exchange is done by black and white system black means -by hard cash white means -by check
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: rameshkharat1987@gmail.com
Subject: 13532-11

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Ramesh Laxman
Exam No. 13532
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.00pm.
Details of the Work Allotted to you today by the Site In-Charge to observe the preparation of form-work for column
Details of how you Planned & Executed the allotted work we just observe accurate dimention of form work accourding to column size. we checked all columns were at the accurate position.
Details of the Construction Procedure / Activity / Technology learned today making of starter before casting of column. workers used wooden battens with proper shape for making formwork for starter
Details of the Construction Materials learned today crude oil- it is burned oil ,we get it from vehicles. used for polish the surface of formwork before casting of column is done.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of wasted oil from vehicles can be utilised as lubrickent which reduces environmental pollution
Details of the Construction / Engineering Drawings observed today design of column- 1.it consist of design details of columns 2.no.of stirrups and their respective arrangement
Details of the Bye Laws referred today min. projection of chujja-0.6m. min. projection of cantiliver balcony-1.2m.
Details of any Managerial Skill learned today politeness and friendly
RATE ANALYSIS (Detailed Stepwise Calculations required) consider size of window(window frame)=1.8m.x1.2m. type of window -aluminium glazed total alluminium required =8.4x0.4x0.3 total glass required=3.44 x 1.12 amount for alluminium =1500 Rs. amount for glass =4000 Rs. labour cost =200 Rs. total amount required =5700 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 5700 Rs./ window
Todays BUZZ Word builder include following things in estimation for selling of property- 1.rate per sq. feet eg. 2700 Rs. 2.rate for parking eg.100000 Rs. 3.rate for M.S.E.B. eg.45000 Rs. 4.doccumentary =as per comity this exchange is done by black and white system black means -by hard cash white means -by check
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-11

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kolekar Shyam Suryakant
Exam No. 13533
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.00pm.
Details of the Work Allotted to you today by the Site In-Charge to observe the preparation of form-work for column
Details of how you Planned & Executed the allotted work we just observe accurate dimention of form work accourding to column size. we checked all columns were at the accurate position.
Details of the Construction Procedure / Activity / Technology learned today making of starter before casting of column. workers used wooden battens with proper shape for making formwork for starter
Details of the Construction Materials learned today crude oil- it is burned oil ,we get it from vehicles. used for polish the surface of formwork before casting of column is done.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of wasted oil from vehicles can be utilised as lubrickent which reduces environmental pollution
Details of the Construction / Engineering Drawings observed today design of column- 1.it consist of design details of columns 2.no.of stirrups and their respective arrangement
Details of the Bye Laws referred today min. projection of chujja-0.6m. min. projection of cantiliver balcony-1.2m.
Details of any Managerial Skill learned today politeness and friendly
RATE ANALYSIS (Detailed Stepwise Calculations required) consider size of window(window frame)=1.8m.x1.2m. type of window -aluminium glazed total alluminium required =8.4x0.4x0.3 total glass required=3.44 x 1.12 amount for alluminium =1500 Rs. amount for glass =4000 Rs. labour cost =200 Rs. total amount required =5700 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 5700 Rs./ window
Todays BUZZ Word builder include following things in estimation for selling of property- 1.rate per sq. feet eg. 2700 Rs. 2.rate for parking eg.100000 Rs. 3.rate for M.S.E.B. eg.45000 Rs. 4.doccumentary =as per comity this exchange is done by black and white system black means -by hard cash white means -by check
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: shinde_shital7@yahoo.com
Subject: 10884-11

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL KARANDEMALA CIRCUITHOUSE KOLHAPUR
Students Name (Surname_First Name_Middle Name) SHINDE SHITAL VILASRAO
Exam No. 10884
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today we observed how to place tile on room and toilet.We observed how to place door frame which is made up of granite by using chemical namely MYK \"LATICRETE\".
Details of how you Planned & Executed the allotted work First we all five member went in the hall in which tiling is done.We observed that tiling is done in such a way that the worker starts tiling from main hall. The worker first consider one face of hall&that face of hall tiling is done&from hall the goes to kitchen,bedroom for tiling. In TOILET \"NON-SLIPERING\"tiles are used. In toilet tiles are placed to a height of 2m or complete the wall to avoid effect of water on the wall.
Details of the Construction Procedure / Activity / Technology learned today We learned how to place tiles. 1. For laying tiles first thickness of bedding layer should be 20-30 mm. 2. On which tiles are placed . 3. Curing should be done at least for 1 week. 3. Use cement sand ratio 1:4 . 4. Donot use iron hammer and heavey material to press.
Details of the Construction Materials learned today We learned construction material is tiles.These tiles had different sizes. According .to owner &to look good this tiles are used.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use steel/iron bar instead of bamboos to support the slab.Because durability is more and also saving of trees .
Details of the Construction / Engineering Drawings observed today 1.We observed drawing is terrrace floor. 2.We observed drawing of gym .
Details of the Bye Laws referred today 1.Maximum cantilever porch length 4.00m according to bye laws has been followed. 2.Stair case is designed as per bye laws.
Details of any Managerial Skill learned today 1. The site in-charge inspected saw the concreteing process going on. 2. The site in-charge checked the proportions of different materials used. 3. The site in-charge kept a proper record of total quantity
RATE ANALYSIS (Detailed Stepwise Calculations required) External Window(1.2*1.5) Aluminum frame-100Rs per sq.m For 1.8sq.m-RATE-180Rs Rate for glass of window-60Rs per sq.m For 1.8sq.m Rate-60*1.8=108Rs Fixtures for external window=40Rs Labour cost =50Rs Total cost=378 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 378Rs
Todays BUZZ Word The builders are determine rates of flat or Bungalows depends upon sq. foot. per sq. =2500Rs Since the one flat rate about 22 lakhs or 25lakhs It should also include construction rate, layout etc. + extra costs to client:- These should be include different important factors. Which are as follows: 1. Service tax 2. Vatt tax 3. Parking 4. Lift 5.MSEB etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: shindeamol5255@yahoo.in
Subject: 13546-11

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHINDE AMOL
Exam No. 13546
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to check the brick work construction.
Details of how you Planned & Executed the allotted work first we collected the working drawing from the site supervisor then after studying it we go to the floor where the construction is going on.
Details of the Construction Procedure / Activity / Technology learned today before starting the brick work construction , first the working drawing is studied then according to beam, column position on the floor and above the floor. it is matched with help of plum-bob then one layer of brick is placed then it is checked by supervisor for the accurate room dimension. if it is proper then further layer of brick is placed.
Details of the Construction Materials learned today normal size brick, sand, cement.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawing.
Details of the Bye Laws referred today Roominess.
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 175.00 RUBBER STRIP USED- Rs- 38 lump sump- 125 locks -2 no. - 100 Rs labour cost - 40/sq.ft total cost- 478 RS= 242.45=243 RS
Result of RATE ANALYSIS ( Rs per Unit ) 243 RS
Todays BUZZ Word BUILDERS DETERMINE FLAT RATE BY CALCULATING CARPET AREA AND INCLUDING TERRACE BALCONIES , OPEN SPACES 30% BY ADDING THEM IT GIVES SALABLE AREA ACCORDINGLY RATE PER SQ.FT COST IS DIVIDED. THEY ARE ADDING THE COST FOR PARKING AREAS, AND MAINTENANCE CHARGES INCLUDING M.S.E.B.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-11

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHAIKH RIZWAN KHALIL
Exam No. 13545
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 10 PM
Details of the Work Allotted to you today by the Site In-Charge to check the brick work construction.
Details of how you Planned & Executed the allotted work first we collected the working drawing from the site supervisor then after studying it we go to the floor where the construction is going on.
Details of the Construction Procedure / Activity / Technology learned today before starting the brick work construction , first the working drawing is studied then according to beam, column position on the floor and above the floor. it is matched with help of plum-bob then one layer of brick is placed then it is checked by supervisor for the accurate room dimension. if it is proper then further layer of brick is placed.
Details of the Construction Materials learned today normal size brick, sand, cement.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawing.
Details of the Bye Laws referred today Roominess.
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 175.00 RUBBER STRIP USED- Rs- 38 lump sump- 125 locks -2 no. - 100 Rs labour cost - 40/sq.ft total cost- 478 RS= 242.45=243 RS
Result of RATE ANALYSIS ( Rs per Unit ) 243 RS
Todays BUZZ Word BUILDERS DETERMINE FLAT RATE BY CALCULATING CARPET AREA AND INCLUDING TERRACE BALCONIES , OPEN SPACES 30% BY ADDING THEM IT GIVES SALABLE AREA ACCORDINGLY RATE PER SQ.FT COST IS DIVIDED. THEY ARE ADDING THE COST FOR PARKING AREAS, AND MAINTENANCE CHARGES INCLUDING M.S.E.B.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-11

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SALOKHE SUDARSHAN ANIL
Exam No. 13544
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to check the brick work construction.
Details of how you Planned & Executed the allotted work first we collected the working drawing from the site supervisor then after studying it we go to the floor where the construction is going on.
Details of the Construction Procedure / Activity / Technology learned today before starting the brick work construction , first the working drawing is studied then according to beam, column position on the floor and above the floor. it is matched with help of plum-bob then one layer of brick is placed then it is checked by supervisor for the accurate room dimension. if it is proper then further layer of brick is placed.
Details of the Construction Materials learned today normal size brick, sand, cement.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawing.
Details of the Bye Laws referred today Roominess.
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 175.00 RUBBER STRIP USED- Rs- 38 lump sump- 125 locks -2 no. - 100 Rs labour cost - 40/sq.ft total cost- 478 RS= 242.45=243 RS
Result of RATE ANALYSIS ( Rs per Unit ) 243 RS
Todays BUZZ Word BUILDERS DETERMINE FLAT RATE BY CALCULATING CARPET AREA AND INCLUDING TERRACE BALCONIES , OPEN SPACES 30% BY ADDING THEM IT GIVES SALABLE AREA ACCORDINGLY RATE PER SQ.FT COST IS DIVIDED. THEY ARE ADDING THE COST FOR PARKING AREAS, AND MAINTENANCE CHARGES INCLUDING M.S.E.B.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-11

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SINGH RAJAN RAJENDRA BAHADUR
Exam No. 13548
Working Day No. 11
Date (DD/MM/YYYY) 20-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to check the brick work construction.
Details of how you Planned & Executed the allotted work first we collected the working drawing from the site supervisor then after studying it we go to the floor where the construction is going on.
Details of the Construction Procedure / Activity / Technology learned today before starting the brick work construction , first the working drawing is studied then according to beam, column position on the floor and above the floor. it is matched with help of plum-bob then one layer of brick is placed then it is checked by supervisor for the accurate room dimension. if it is proper then further layer of brick is placed.
Details of the Construction Materials learned today normal size brick, sand, cement.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawing.
Details of the Bye Laws referred today Roominess.
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW 3 TRACK - 2 GLASS SHUTTER 1 S.S. NET SHUTTER SLIDING WINDOW (3.5 MM) Rs - 175.00 RUBBER STRIP USED- Rs- 38 lump sump- 125 locks -2 no. - 100 Rs labour cost - 40/sq.ft total cost- 478 RS= 242.45=243 RS
Result of RATE ANALYSIS ( Rs per Unit ) 243 RS
Todays BUZZ Word BUILDERS DETERMINE FLAT RATE BY CALCULATING CARPET AREA AND INCLUDING TERRACE BALCONIES , OPEN SPACES 30% BY ADDING THEM IT GIVES SALABLE AREA ACCORDINGLY RATE PER SQ.FT COST IS DIVIDED. THEY ARE ADDING THE COST FOR PARKING AREAS, AND MAINTENANCE CHARGES INCLUDING M.S.E.B.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-11

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 11
Date (DD/MM/YYYY) 20.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to see the electrification through the slabs.
Details of how you Planned & Executed the allotted work we saw the electrification drawing and then with the help of the electrician we saw the process of concealed fitting.
Details of the Construction Procedure / Activity / Technology learned today concealed wiring.
Details of the Construction Materials learned today 1)circular tees used for collecting the wires together at a junction. 2)pvc pipes used to carry wires.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today Electrification drawings.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today Punctuality is necessary.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: 3 track- 2 glass shutter 1 s.s. net shutter sliding window(Bajari glass 3.5 mm) - Rs.175.00 rubber strip used -Rs.30 lump sump-Rs.100 Locks-2 no.-Rs.50 each. labour cost.:Rs.30/Sq.ft. total.-Rs.475/(1.5m/1.2m)=RS.241.22245/Sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 245/Sq.m
Todays BUZZ Word BUZZ OF THE DAY: HOW BUILDERS DETERMINE RATES OF FLAT/BUNGALOW + EXTRA COSTS TO CLIENTS: The builders consider the following points points while determining the cost: 1)LAND COST 2)LAND DEVELOPMENT COST 3)CONSTRUCTION MATERIAL COST 4)LABOUR COST 5)ADVERTISEMENT COST 6)SECURITY COST 7)MAINTENANCE COST 8)FACILITY AREA COST(GARDEN AREA,GYM,CLUB HOUSE) 9)MANAGEMENT COST Also the Contractors or Builders add their own profit maybe 15-20%.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-11

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 11
Date (DD/MM/YYYY) 20.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to see the electrification through the slabs.
Details of how you Planned & Executed the allotted work we saw the electrification drawing and then with the help of the electrician we saw the process of concealed fitting.
Details of the Construction Procedure / Activity / Technology learned today concealed wiring.
Details of the Construction Materials learned today 1)circular tees used for collecting the wires together at a junction. 2)pvc pipes used to carry wires.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today Electrification drawings.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today Punctuality is necessary.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis: 3 track- 2 glass shutter 1 s.s. net shutter sliding window(Bajari glass 3.5 mm) - Rs.175.00 rubber strip used -Rs.30 lump sump-Rs.100 Locks-2 no.-Rs.50 each. labour cost.:Rs.30/Sq.ft. total.-Rs.475/(1.5m/1.2m)=RS.241.22245/Sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 245/Sq.m
Todays BUZZ Word BUZZ OF THE DAY: HOW BUILDERS DETERMINE RATES OF FLAT/BUNGALOW + EXTRA COSTS TO CLIENTS: The builders consider the following points points while determining the cost: 1)LAND COST 2)LAND DEVELOPMENT COST 3)CONSTRUCTION MATERIAL COST 4)LABOUR COST 5)ADVERTISEMENT COST 6)SECURITY COST 7)MAINTENANCE COST 8)FACILITY AREA COST(GARDEN AREA,GYM,CLUB HOUSE) 9)MANAGEMENT COST Also the Contractors or Builders add their own profit maybe 15-20%.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-11

Company Name Star Tech Infra
Project Name & Site Address star aashiyana, rajendranagar.
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 11
Date (DD/MM/YYYY) 20/12/10
Site Reporting Time (HH:MM am/pm) 8.45am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge To see garden construction, fabrication near garden.
Details of how you Planned & Executed the allotted work We observe process carefully garden construction is in progress, They give good architechtural view to garden which is for childrens & elders.
Details of the Construction Procedure / Activity / Technology learned today fabrication attachment process, construction ofgarden.
Details of the Construction Materials learned today brick, mortor, p.c.c.,steel frames.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no
Details of the Construction / Engineering Drawings observed today drawing for garden
Details of the Bye Laws referred today bye laws for open spaces
Details of any Managerial Skill learned today how to handle workers
RATE ANALYSIS (Detailed Stepwise Calculations required) For 1sq.m. window now days, Alluminium window rate is 170Rs./sq.ft. so, 170Rs./sq.ft.*10.76 =1829Rs./sq.m.
Result of RATE ANALYSIS ( Rs per Unit ) 1829Rs./sq.m.
Todays BUZZ Word Rate of flat/bunglow is mainly depend upon land cost. because construction cost is same is all every where.(current cost is 900Rs/sq.ft.) if land cost is 300 Rs/sq.ft. total cost 1200Rs/sq.ft. contractor profit is near by 20% so total cost paid by client = 1440 Rs/sq.ft.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish mestri 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-11

Company Name Star Tech Infra
Project Name & Site Address star aashiyana, rajendranagar.
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 11
Date (DD/MM/YYYY) 20/12/10
Site Reporting Time (HH:MM am/pm) 8.45am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge To see garden construction, fabrication near garden.
Details of how you Planned & Executed the allotted work We observe process carefully garden construction is in progress, They give good architechtural view to garden which is for childrens & elders.
Details of the Construction Procedure / Activity / Technology learned today fabrication attachment process, construction ofgarden.
Details of the Construction Materials learned today brick, mortor, p.c.c.,steel frames.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no
Details of the Construction / Engineering Drawings observed today drawing for garden
Details of the Bye Laws referred today bye laws for open spaces
Details of any Managerial Skill learned today how to handle workers
RATE ANALYSIS (Detailed Stepwise Calculations required) For 1sq.m. window now days, Alluminium window rate is 170Rs./sq.ft. so, 170Rs./sq.ft.*10.76 =1829Rs./sq.m.
Result of RATE ANALYSIS ( Rs per Unit ) 1829Rs./sq.m.
Todays BUZZ Word Rate of flat/bunglow is mainly depend upon land cost. because construction cost is same is all every where.(current cost is 900Rs/sq.ft.) if land cost is 300 Rs/sq.ft. total cost 1200Rs/sq.ft. contractor profit is near by 20% so total cost paid by client = 1440 Rs/sq.ft.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish mestri 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-11

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Tambe Trusha Sitaram
Exam No. 10902
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to check column form work .& weather the curing is done for the slab & starter . .
Details of how you Planned & Executed the allotted work we observed weather the form work err-action is on placed where marking is done .& also observed weather it is in vertical or inclined. .
Details of the Construction Procedure / Activity / Technology learned today today we learn the procedure of extension of column reinforcement for next floor.first starter is placed then the steel of that particular diameter which are given in detailed drawing of column are bended at a distance .then that steel bar is then overlap with previous bar with the help of binding wire.& then stirrups are provided at a particular distance. .
Details of the Construction Materials learned today today we learned about the construction material bricks.the size of bricks is 230*15*9cm.the burned bricks are used which are all of generally same size.the price of one bricks is generally about 7 RS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rainwater harvesting technique is used. .
Details of the Construction / Engineering Drawings observed today today we observed the detailed drawing of column.in that drg we observed the sizes of bars are decreases with increasing the height of floor. .
Details of the Bye Laws referred today from bye-laws today we referred that the alternative material ,method of design & construction & tests. .
Details of any Managerial Skill learned today today we learned how to talk with the client .how to convince them for buying the flat. .
RATE ANALYSIS (Detailed Stepwise Calculations required) S.No. DESCRIPTION AMOUNT REMARK 3 Entrance Door / window (Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft.) Material : Burma Teak wood : 63784.00 Varun Timber Statement from { Burma Teak wood for Frame & Shutter Dt. 4/1/08 to 11/10/08 Total Amt Rs. 63784/-} Hinges 6 nos. : 900.00 Kolhapur Hardware {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Kolhapur Hardware {Total Amt. : 1488 / per No.} Bill NO. 144 Glass : Rs. 38.22/ Sqft. 678.41 Babji Glass Tradrs ( 17.75 Sqft. X 38.22 = 678.41 /-) Bill NO. 986 TOTAL Rs. 66850.41 per Door Labour for Flush Door 15% 10027.56 Say Rs. 10000.00 per Door .
Result of RATE ANALYSIS ( Rs per Unit ) 10000.00 per Door
Todays BUZZ Word After finalization of drawings the booking of the plots will be starts for the interested clients within the committed period the construction can be completed as per the design. During this period marketing and sells staff is involved in the achievement of their goal of selling a plots & flats to give the satisfaction to the clients. The first installment collected at the time of booking & the overall cost of plot or flat will be collected by one installment or step by step installment. The cost of flat will be decided on the following points. 1) Estimation cost of flat 2) Any extra additional charges in providing facilities 3) Total carpet area. 4) Total sellable area. 5) Parking provided. 6) Charges for electric connections. 7) Charges for water supply connection for municipal corporation. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688 jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-11

Company Name Deshmukh Developers
Project Name & Site Address Deshmukh Developments,Pratibha Nagar ,Kolhapur
Students Name (Surname_First Name_Middle Name) Birajdar Minaxi Renuk
Exam No. 13556
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge The following work is given by site incharge to us : 1.Today we are all groupmates observe how the POP- plaster of paris is applied to the ceiling
Details of how you Planned & Executed the allotted work We are planned & execute the work as follows: 1. Firstly we should go to that flat 2. To observe how much area is covered by worker & how area is still remaining 3. We are divide the group, two students are one room & remaining are in another room
Details of the Construction Procedure / Activity / Technology learned today Construction Procedure : 1.Firstly clean the ceiling neatly by brush 2.Small platform should be made for this 3.Plaster of paris has a 20kg bag 4.To take half quantity of above powder in a trowel & add equal quantity of water in it 5.To make smooth ,workable glaasy paste then to apply the ceiling 6.Then to apply two coat of plaster of paris to the ceiling
Details of the Construction Materials learned today Construction Materials are as follows : 1.Trowel 2.Brush 3.Plaster of paris powder 4.Water 5.Platform 6.Thapi 7.Cap for worker 8.Goggle for worker
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environmental Caring Technology : Mortar fallen during plastering work if collected on plastic sheet then reused within 30 minutes , it will save the material & there by saving natural materiel.
Details of the Construction / Engineering Drawings observed today Today we are observe the drawing are : - Septic Tank Layouts. - Parking Layout.
Details of the Bye Laws referred today Today we are referred Bye Laws Book for : 1.To study about minimum height of room 2.To study about maximum height of room
Details of any Managerial Skill learned today Managerial Skill : How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS OF EXTERNAL WINDOW : EXTERNAL WINDOW (1.2* 1.5) ALUMINIUM FRAME = 100 RS PER SQ. METER FOR 1.8 SQ.METER RATE =180 RS RATE FOR GLASS OF WINDOW = 60 RS PER SQ METER FOR 1.8 SQ METER RATE = 60 * 1.8 =108 RS FIXTURES FOR EXTERNAL WINDOW = 40 RS LABOUR COST = 50 RS TOTAL COST = 370 =380RS
Result of RATE ANALYSIS ( Rs per Unit ) 380 RS
Todays BUZZ Word BUZZ WORD : The builders are determine rates of flat or Bunglow depend depend upon sq meter. Per sq. meter=2500 RS Since the one flat rate about 22 lakh to 25 lakh It shoud also includes construction rate , layout etc + Extra Costs to client : This should be include different important factors.Which are as follows: 1.Service Tax 2.Vat Tax 3.Parking 4.Lift 5.MSEB etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.ABHIJIT BHOSALE MOB.NO.9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-11

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the ceiling work going in row bunglows.& the maintenance of the entire project work.
Details of how you Planned & Executed the allotted work -We saw together the ceiling work & also see the maintenance work.
Details of the Construction Procedure / Activity / Technology learned today Ceiling work -First POP sheets are bought from market for ceiling -Then lime mortar also prepared. -Then according to design ornamental ceiling work is started. -Light points ,fan points also considering during design. -After completion of ceiling work electrification work is going on.
Details of the Construction Materials learned today -POP sheets . -Lime mortar. -White cement. -Fevicol.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -Solar panels are used for water heating system that reduces the consumption of electricity . -Only some of the bungalows have used this.
Details of the Construction / Engineering Drawings observed today -Ceiling design –it is designed according to requirement of owner. -Design of gymnasium hall.-it is designed according to considering no of living in project.
Details of the Bye Laws referred today Overhead tank Every over head water storage tank is maintained in perfectly mosquito proof by providing properly fitting hinged cover and every tank is more than 1.5 m height and is provided with a permenantly fixed iron ladder to unable inspection.
Details of any Managerial Skill learned today Co-ordination between site incharge and site engineer is very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : Assume window of size 5feet * 4feet Assume it is aluminium glazed window . It is double channel window which contains two sliding panels. Grill is provided outside of the window. Particular : No. or Qt. Rate Cost Material Steel (for grill ) 10 kg. 43 430 Rs/- Aluminium frame 20 R.F.T 60 Rs/- 1200 Rs. Glass (plane Glass) 18 Sq.ft 30 Rs 540Rs/- Rubber sill 100Rs/- Rollers 8 50 400Rs/- Scew 20 1 20 Rs/- Lock 2 30 Rs/- 60 Rs/- Labour Grill Worker 1 150Rs/- 150 Rs/- Window fitter 2 150Rs/- 300Rs/ Total 3200Rs/- Add 20% profit of contractor, 3840Rs/- Builder , tax etc The cost of a window for 20 sq.ft. is Rs.3840. Therefore the cost of window for 192Rs/sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 192Rs/sq.ft.
Todays BUZZ Word Todays Buzz word :how builders determine rates of flat./bunglow + extra cost to clients 1) First a builder buys a land for construction. 2) Then he prepares a plan of the building with the help of a civil engineer or architect . 3) He starts the construction by taking permission of the local corporation. 4) Before actual start of work the builder decides the square feet rate by taking into consideration the following points: 1) Land cost 2) Land development cost 3) Construction material cost 4)Labour cost 5) Advertisement cost 6)Security cost 7) Maintenance cost 8) Corporation charges 9) Common facilities like garden , gymnasium , club house , temple, common roads. 10) Management cost 11) Various taxes like sales tax, income tax, VAT ,transportation tax, etc. 12) Construction material transportation cost. After calculating above costs builder decides the built up rate in square feet and also he adds his profit and then decides the actual square feet rate of row bungalow or flat.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-11

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the ceiling work going in row bunglows.& the maintenance of the entire project work.
Details of how you Planned & Executed the allotted work -We saw together the ceiling work & also see the maintenance work.
Details of the Construction Procedure / Activity / Technology learned today Ceiling work -First POP sheets are bought from market for ceiling -Then lime mortar also prepared. -Then according to design ornamental ceiling work is started. -Light points ,fan points also considering during design. -After completion of ceiling work electrification work is going on.
Details of the Construction Materials learned today -POP sheets . -Lime mortar. -White cement. -Fevicol.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -Solar panels are used for water heating system that reduces the consumption of electricity . -Only some of the bungalows have used this.
Details of the Construction / Engineering Drawings observed today -Ceiling design –it is designed according to requirement of owner. -Design of gymnasium hall.-it is designed according to considering no of living in project.
Details of the Bye Laws referred today Overhead tank Every over head water storage tank is maintained in perfectly mosquito proof by providing properly fitting hinged cover and every tank is more than 1.5 m height and is provided with a permenantly fixed iron ladder to unable inspection.
Details of any Managerial Skill learned today Co-ordination between site incharge and site engineer is very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : Assume window of size 5feet * 4feet Assume it is aluminium glazed window . It is double channel window which contains two sliding panels. Grill is provided outside of the window. Particular : No. or Qt. Rate Cost Material Steel (for grill ) 10 kg. 43 430 Rs/- Aluminium frame 20 R.F.T 60 Rs/- 1200 Rs. Glass (plane Glass) 18 Sq.ft 30 Rs 540Rs/- Rubber sill 100Rs/- Rollers 8 50 400Rs/- Scew 20 1 20 Rs/- Lock 2 30 Rs/- 60 Rs/- Labour Grill Worker 1 150Rs/- 150 Rs/- Window fitter 2 150Rs/- 300Rs/ Total 3200Rs/- Add 20% profit of contractor, 3840Rs/- Builder , tax etc The cost of a window for 20 sq.ft. is Rs.3840. Therefore the cost of window for 192Rs/sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 192Rs/sq.ft.
Todays BUZZ Word Todays Buzz word :how builders determine rates of flat./bunglow + extra cost to clients 1) First a builder buys a land for construction. 2) Then he prepares a plan of the building with the help of a civil engineer or architect . 3) He starts the construction by taking permission of the local corporation. 4) Before actual start of work the builder decides the square feet rate by taking into consideration the following points: 1) Land cost 2) Land development cost 3) Construction material cost 4)Labour cost 5) Advertisement cost 6)Security cost 7) Maintenance cost 8) Corporation charges 9) Common facilities like garden , gymnasium , club house , temple, common roads. 10) Management cost 11) Various taxes like sales tax, income tax, VAT ,transportation tax, etc. 12) Construction material transportation cost. After calculating above costs builder decides the built up rate in square feet and also he adds his profit and then decides the actual square feet rate of row bungalow or flat.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: buntyphonde@gmail.com
Subject: 10899-11

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Phonde Pravin Tukaram
Exam No. 10899
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to check column form work .& weather the curing is done for the slab & starter . .
Details of how you Planned & Executed the allotted work we observed weather the form work err-action is on placed where marking is done .& also observed weather it is in vertical or inclined. .
Details of the Construction Procedure / Activity / Technology learned today today we learn the procedure of extension of column reinforcement for next floor.first starter is placed then the steel of that particular diameter which are given in detailed drawing of column are bended at a distance .then that steel bar is then overlap with previous bar with the help of binding wire.& then stirrups are provided at a particular distance. .
Details of the Construction Materials learned today today we learned about the construction material bricks.the size of bricks is 230*15*9cm.the burned bricks are used which are all of generally same size.the price of one bricks is generally about 7 RS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rainwater harvesting technique is used. .
Details of the Construction / Engineering Drawings observed today today we observed the detailed drawing of column.in that drg we observed the sizes of bars are decreases with increasing the height of floor. .
Details of the Bye Laws referred today from bye-laws today we referred that the alternative material ,method of design & construction & tests. .
Details of any Managerial Skill learned today today we learned how to talk with the client .how to convince them for buying the flat. .
RATE ANALYSIS (Detailed Stepwise Calculations required) S.No. DESCRIPTION AMOUNT REMARK 3 Entrance Door / window (Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft.) Material : Burma Teak wood : 63784.00 Varun Timber Statement from { Burma Teak wood for Frame & Shutter Dt. 4/1/08 to 11/10/08 Total Amt Rs. 63784/-} Hinges 6 nos. : 900.00 Kolhapur Hardware {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Kolhapur Hardware {Total Amt. : 1488 / per No.} Bill NO. 144 Glass : Rs. 38.22/ Sqft. 678.41 Babji Glass Tradrs ( 17.75 Sqft. X 38.22 = 678.41 /-) Bill NO. 986 TOTAL Rs. 66850.41 per Door Labour for Flush Door 15% 10027.56 Say Rs. 10000.00 per Door .
Result of RATE ANALYSIS ( Rs per Unit ) 10000.00 per Door
Todays BUZZ Word After finalization of drawings the booking of the plots will be starts for the interested clients within the committed period the construction can be completed as per the design. During this period marketing and sells staff is involved in the achievement of their goal of selling a plots & flats to give the satisfaction to the clients. The first installment collected at the time of booking & the overall cost of plot or flat will be collected by one installment or step by step installment. The cost of flat will be decided on the following points. 1) Estimation cost of flat 2) Any extra additional charges in providing facilities 3) Total carpet area. 4) Total sellable area. 5) Parking provided. 6) Charges for electric connections. 7) Charges for water supply connection for municipal corporation. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688 jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-11

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the ceiling work going in row bunglows.& the maintenance of the entire project work.
Details of how you Planned & Executed the allotted work -We saw together the ceiling work & also see the maintenance work.
Details of the Construction Procedure / Activity / Technology learned today Ceiling work -First POP sheets are bought from market for ceiling -Then lime mortar also prepared. -Then according to design ornamental ceiling work is started. -Light points ,fan points also considering during design. -After completion of ceiling work electrification work is going on.
Details of the Construction Materials learned today -POP sheets . -Lime mortar. -White cement. -Fevicol.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -Solar panels are used for water heating system that reduces the consumption of electricity . -Only some of the bungalows have used this.
Details of the Construction / Engineering Drawings observed today -Ceiling design –it is designed according to requirement of owner. -Design of gymnasium hall.-it is designed according to considering no of living in project.
Details of the Bye Laws referred today Overhead tank Every over head water storage tank is maintained in perfectly mosquito proof by providing properly fitting hinged cover and every tank is more than 1.5 m height and is provided with a permenantly fixed iron ladder to unable inspection.
Details of any Managerial Skill learned today Co-ordination between site incharge and site engineer is very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : Assume window of size 5feet * 4feet Assume it is aluminium glazed window . It is double channel window which contains two sliding panels. Grill is provided outside of the window. Particular : No. or Qt. Rate Cost Material Steel (for grill ) 10 kg. 43 430 Rs/- Aluminium frame 20 R.F.T 60 Rs/- 1200 Rs. Glass (plane Glass) 18 Sq.ft 30 Rs 540Rs/- Rubber sill 100Rs/- Rollers 8 50 400Rs/- Scew 20 1 20 Rs/- Lock 2 30 Rs/- 60 Rs/- Labour Grill Worker 1 150Rs/- 150 Rs/- Window fitter 2 150Rs/- 300Rs/ Total 3200Rs/- Add 20% profit of contractor, 3840Rs/- Builder , tax etc The cost of a window for 20 sq.ft. is Rs.3840. Therefore the cost of window for 192Rs/sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 192Rs/sq.ft.
Todays BUZZ Word Todays Buzz word :how builders determine rates of flat./bunglow + extra cost to clients 1) First a builder buys a land for construction. 2) Then he prepares a plan of the building with the help of a civil engineer or architect . 3) He starts the construction by taking permission of the local corporation. 4) Before actual start of work the builder decides the square feet rate by taking into consideration the following points: 1) Land cost 2) Land development cost 3) Construction material cost 4)Labour cost 5) Advertisement cost 6)Security cost 7) Maintenance cost 8) Corporation charges 9) Common facilities like garden , gymnasium , club house , temple, common roads. 10) Management cost 11) Various taxes like sales tax, income tax, VAT ,transportation tax, etc. 12) Construction material transportation cost. After calculating above costs builder decides the built up rate in square feet and also he adds his profit and then decides the actual square feet rate of row bungalow or flat.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-11

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Sharad Shankarrao
Exam No. 10897
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to check column form work .& weather the curing is done for the slab & starter . .
Details of how you Planned & Executed the allotted work we observed weather the form work err-action is on placed where marking is done .& also observed weather it is in vertical or inclined. .
Details of the Construction Procedure / Activity / Technology learned today today we learn the procedure of extension of column reinforcement for next floor.first starter is placed then the steel of that particular diameter which are given in detailed drawing of column are bended at a distance .then that steel bar is then overlap with previous bar with the help of binding wire.& then stirrups are provided at a particular distance. .
Details of the Construction Materials learned today today we learned about the construction material bricks.the size of bricks is 230*15*9cm.the burned bricks are used which are all of generally same size.the price of one bricks is generally about 7 RS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rainwater harvesting technique is used. .
Details of the Construction / Engineering Drawings observed today today we observed the detailed drawing of column.in that drg we observed the sizes of bars are decreases with increasing the height of floor. .
Details of the Bye Laws referred today from bye-laws today we referred that the alternative material ,method of design & construction & tests. .
Details of any Managerial Skill learned today today we learned how to talk with the client .how to convince them for buying the flat. .
RATE ANALYSIS (Detailed Stepwise Calculations required) S.No. DESCRIPTION AMOUNT REMARK 3 Entrance Door / window (Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft.) Material : Burma Teak wood : 63784.00 Varun Timber Statement from { Burma Teak wood for Frame & Shutter Dt. 4/1/08 to 11/10/08 Total Amt Rs. 63784/-} Hinges 6 nos. : 900.00 Kolhapur Hardware {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Kolhapur Hardware {Total Amt. : 1488 / per No.} Bill NO. 144 Glass : Rs. 38.22/ Sqft. 678.41 Babji Glass Tradrs ( 17.75 Sqft. X 38.22 = 678.41 /-) Bill NO. 986 TOTAL Rs. 66850.41 per Door Labour for Flush Door 15% 10027.56 Say Rs. 10000.00 per Door .
Result of RATE ANALYSIS ( Rs per Unit ) 10000.00 per Door
Todays BUZZ Word After finalization of drawings the booking of the plots will be starts for the interested clients within the committed period the construction can be completed as per the design. During this period marketing and sells staff is involved in the achievement of their goal of selling a plots & flats to give the satisfaction to the clients. The first installment collected at the time of booking & the overall cost of plot or flat will be collected by one installment or step by step installment. The cost of flat will be decided on the following points. 1) Estimation cost of flat 2) Any extra additional charges in providing facilities 3) Total carpet area. 4) Total sellable area. 5) Parking provided. 6) Charges for electric connections. 7) Charges for water supply connection for municipal corporation. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-11

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the ceiling work going in row bunglows.& the maintenance of the entire project work.
Details of how you Planned & Executed the allotted work -We saw together the ceiling work & also see the maintenance work.
Details of the Construction Procedure / Activity / Technology learned today Ceiling work -First POP sheets are bought from market for ceiling -Then lime mortar also prepared. -Then according to design ornamental ceiling work is started. -Light points ,fan points also considering during design. -After completion of ceiling work electrification work is going on.
Details of the Construction Materials learned today -POP sheets . -Lime mortar. -White cement. -Fevicol.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -Solar panels are used for water heating system that reduces the consumption of electricity . -Only some of the bungalows have used this.
Details of the Construction / Engineering Drawings observed today -Ceiling design –it is designed according to requirement of owner. -Design of gymnasium hall.-it is designed according to considering no of living in project.
Details of the Bye Laws referred today Overhead tank Every over head water storage tank is maintained in perfectly mosquito proof by providing properly fitting hinged cover and every tank is more than 1.5 m height and is provided with a permenantly fixed iron ladder to unable inspection.
Details of any Managerial Skill learned today Co-ordination between site incharge and site engineer is very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : Assume window of size 5feet * 4feet Assume it is aluminium glazed window . It is double channel window which contains two sliding panels. Grill is provided outside of the window. Particular : No. or Qt. Rate Cost Material Steel (for grill ) 10 kg. 43 430 Rs/- Aluminium frame 20 R.F.T 60 Rs/- 1200 Rs. Glass (plane Glass) 18 Sq.ft 30 Rs 540Rs/- Rubber sill 100Rs/- Rollers 8 50 400Rs/- Scew 20 1 20 Rs/- Lock 2 30 Rs/- 60 Rs/- Labour Grill Worker 1 150Rs/- 150 Rs/- Window fitter 2 150Rs/- 300Rs/ Total 3200Rs/- Add 20% profit of contractor, 3840Rs/- Builder , tax etc The cost of a window for 20 sq.ft. is Rs.3840. Therefore the cost of window for 192Rs/sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 192Rs/sq.ft.
Todays BUZZ Word Todays Buzz word :how builders determine rates of flat./bunglow + extra cost to clients 1) First a builder buys a land for construction. 2) Then he prepares a plan of the building with the help of a civil engineer or architect . 3) He starts the construction by taking permission of the local corporation. 4) Before actual start of work the builder decides the square feet rate by taking into consideration the following points: 1) Land cost 2) Land development cost 3) Construction material cost 4)Labour cost 5) Advertisement cost 6)Security cost 7) Maintenance cost 8) Corporation charges 9) Common facilities like garden , gymnasium , club house , temple, common roads. 10) Management cost 11) Various taxes like sales tax, income tax, VAT ,transportation tax, etc. 12) Construction material transportation cost. After calculating above costs builder decides the built up rate in square feet and also he adds his profit and then decides the actual square feet rate of row bungalow or flat.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-11

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudeo
Exam No. 10891
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the ceiling work going in row bunglows.& the maintenance of the entire project work.
Details of how you Planned & Executed the allotted work -We saw together the ceiling work & also see the maintenance work.
Details of the Construction Procedure / Activity / Technology learned today Ceiling work -First POP sheets are bought from market for ceiling -Then lime mortar also prepared. -Then according to design ornamental ceiling work is started. -Light points ,fan points also considering during design. -After completion of ceiling work electrification work is going on.
Details of the Construction Materials learned today -POP sheets . -Lime mortar. -White cement. -Fevicol.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -Solar panels are used for water heating system that reduces the consumption of electricity . -Only some of the bungalows have used this.
Details of the Construction / Engineering Drawings observed today -Ceiling design –it is designed according to requirement of owner. -Design of gymnasium hall.-it is designed according to considering no of living in project.
Details of the Bye Laws referred today Overhead tank Every over head water storage tank is maintained in perfectly mosquito proof by providing properly fitting hinged cover and every tank is more than 1.5 m height and is provided with a permenantly fixed iron ladder to unable inspection.
Details of any Managerial Skill learned today Co-ordination between site incharge and site engineer is very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : Assume window of size 5feet * 4feet Assume it is aluminium glazed window . It is double channel window which contains two sliding panels. Grill is provided outside of the window. Particular : No. or Qt. Rate Cost Material Steel (for grill ) 10 kg. 43 430 Rs/- Aluminium frame 20 R.F.T 60 Rs/- 1200 Rs. Glass (plane Glass) 18 Sq.ft 30 Rs 540Rs/- Rubber sill 100Rs/- Rollers 8 50 400Rs/- Scew 20 1 20 Rs/- Lock 2 30 Rs/- 60 Rs/- Labour Grill Worker 1 150Rs/- 150 Rs/- Window fitter 2 150Rs/- 300Rs/ Total 3200Rs/- Add 20% profit of contractor, 3840Rs/- Builder , tax etc The cost of a window for 20 sq.ft. is Rs.3840. Therefore the cost of window for 192Rs/sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 192Rs/sq.ft.
Todays BUZZ Word Todays Buzz word :how builders determine rates of flat./bunglow + extra cost to clients 1) First a builder buys a land for construction. 2) Then he prepares a plan of the building with the help of a civil engineer or architect . 3) He starts the construction by taking permission of the local corporation. 4) Before actual start of work the builder decides the square feet rate by taking into consideration the following points: 1) Land cost 2) Land development cost 3) Construction material cost 4)Labour cost 5) Advertisement cost 6)Security cost 7) Maintenance cost 8) Corporation charges 9) Common facilities like garden , gymnasium , club house , temple, common roads. 10) Management cost 11) Various taxes like sales tax, income tax, VAT ,transportation tax, etc. 12) Construction material transportation cost. After calculating above costs builder decides the built up rate in square feet and also he adds his profit and then decides the actual square feet rate of row bungalow or flat.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-11

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the ceiling work going in row bunglows.& the maintenance of the entire project work.
Details of how you Planned & Executed the allotted work -We saw together the ceiling work & also see the maintenance work.
Details of the Construction Procedure / Activity / Technology learned today Ceiling work -First POP sheets are bought from market for ceiling -Then lime mortar also prepared. -Then according to design ornamental ceiling work is started. -Light points ,fan points also considering during design. -After completion of ceiling work electrification work is going on.
Details of the Construction Materials learned today -POP sheets . -Lime mortar. -White cement. -Fevicol.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -Solar panels are used for water heating system that reduces the consumption of electricity . -Only some of the bungalows have used this.
Details of the Construction / Engineering Drawings observed today -Ceiling design –it is designed according to requirement of owner. -Design of gymnasium hall.-it is designed according to considering no of living in project.
Details of the Bye Laws referred today Overhead tank Every over head water storage tank is maintained in perfectly mosquito proof by providing properly fitting hinged cover and every tank is more than 1.5 m height and is provided with a permenantly fixed iron ladder to unable inspection.
Details of any Managerial Skill learned today Co-ordination between site incharge and site engineer is very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : Assume window of size 5feet * 4feet Assume it is aluminium glazed window . It is double channel window which contains two sliding panels. Grill is provided outside of the window. Particular : No. or Qt. Rate Cost Material Steel (for grill ) 10 kg. 43 430 Rs/- Aluminium frame 20 R.F.T 60 Rs/- 1200 Rs. Glass (plane Glass) 18 Sq.ft 30 Rs 540Rs/- Rubber sill 100Rs/- Rollers 8 50 400Rs/- Scew 20 1 20 Rs/- Lock 2 30 Rs/- 60 Rs/- Labour Grill Worker 1 150Rs/- 150 Rs/- Window fitter 2 150Rs/- 300Rs/ Total 3200Rs/- Add 20% profit of contractor, 3840Rs/- Builder , tax etc The cost of a window for 20 sq.ft. is Rs.3840. Therefore the cost of window for 192Rs/sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 192Rs/sq.ft.
Todays BUZZ Word Todays Buzz word :how builders determine rates of flat./bunglow + extra cost to clients 1) First a builder buys a land for construction. 2) Then he prepares a plan of the building with the help of a civil engineer or architect . 3) He starts the construction by taking permission of the local corporation. 4) Before actual start of work the builder decides the square feet rate by taking into consideration the following points: 1) Land cost 2) Land development cost 3) Construction material cost 4)Labour cost 5) Advertisement cost 6)Security cost 7) Maintenance cost 8) Corporation charges 9) Common facilities like garden , gymnasium , club house , temple, common roads. 10) Management cost 11) Various taxes like sales tax, income tax, VAT ,transportation tax, etc. 12) Construction material transportation cost. After calculating above costs builder decides the built up rate in square feet and also he adds his profit and then decides the actual square feet rate of row bungalow or flat.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-11

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the ceiling work going in row bunglows.& the maintenance of the entire project work.
Details of how you Planned & Executed the allotted work -We saw together the ceiling work & also see the maintenance work.
Details of the Construction Procedure / Activity / Technology learned today Ceiling work -First POP sheets are bought from market for ceiling -Then lime mortar also prepared. -Then according to design ornamental ceiling work is started. -Light points ,fan points also considering during design. -After completion of ceiling work electrification work is going on.
Details of the Construction Materials learned today -POP sheets . -Lime mortar. -White cement. -Fevicol.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -Solar panels are used for water heating system that reduces the consumption of electricity . -Only some of the bungalows have used this.
Details of the Construction / Engineering Drawings observed today -Ceiling design –it is designed according to requirement of owner. -Design of gymnasium hall.-it is designed according to considering no of living in project.
Details of the Bye Laws referred today Overhead tank Every over head water storage tank is maintained in perfectly mosquito proof by providing properly fitting hinged cover and every tank is more than 1.5 m height and is provided with a permenantly fixed iron ladder to unable inspection.
Details of any Managerial Skill learned today Co-ordination between site incharge and site engineer is very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : Assume window of size 5feet * 4feet Assume it is aluminium glazed window . It is double channel window which contains two sliding panels. Grill is provided outside of the window. Particular : No. or Qt. Rate Cost Material Steel (for grill ) 10 kg. 43 430 Rs/- Aluminium frame 20 R.F.T 60 Rs/- 1200 Rs. Glass (plane Glass) 18 Sq.ft 30 Rs 540Rs/- Rubber sill 100Rs/- Rollers 8 50 400Rs/- Scew 20 1 20 Rs/- Lock 2 30 Rs/- 60 Rs/- Labour Grill Worker 1 150Rs/- 150 Rs/- Window fitter 2 150Rs/- 300Rs/ Total 3200Rs/- Add 20% profit of contractor, 3840Rs/- Builder , tax etc The cost of a window for 20 sq.ft. is Rs.3840. Therefore the cost of window for 192Rs/sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 192Rs/sq.ft.
Todays BUZZ Word Todays Buzz word :how builders determine rates of flat./bunglow + extra cost to clients 1) First a builder buys a land for construction. 2) Then he prepares a plan of the building with the help of a civil engineer or architect . 3) He starts the construction by taking permission of the local corporation. 4) Before actual start of work the builder decides the square feet rate by taking into consideration the following points: 1) Land cost 2) Land development cost 3) Construction material cost 4)Labour cost 5) Advertisement cost 6)Security cost 7) Maintenance cost 8) Corporation charges 9) Common facilities like garden , gymnasium , club house , temple, common roads. 10) Management cost 11) Various taxes like sales tax, income tax, VAT ,transportation tax, etc. 12) Construction material transportation cost. After calculating above costs builder decides the built up rate in square feet and also he adds his profit and then decides the actual square feet rate of row bungalow or flat.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-11

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Abhishek Dadasaheb
Exam No. 10895
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to check column form work .& weather the curing is done for the slab & starter . .
Details of how you Planned & Executed the allotted work we observed weather the form work err-action is on placed where marking is done .& also observed weather it is in vertical or inclined. .
Details of the Construction Procedure / Activity / Technology learned today today we learn the procedure of extension of column reinforcement for next floor.first starter is placed then the steel of that particular diameter which are given in detailed drawing of column are bended at a distance .then that steel bar is then overlap with previous bar with the help of binding wire.& then stirrups are provided at a particular distance. .
Details of the Construction Materials learned today today we learned about the construction material bricks.the size of bricks is 230*15*9cm.the burned bricks are used which are all of generally same size.the price of one bricks is generally about 7 RS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rainwater harvesting technique is used. .
Details of the Construction / Engineering Drawings observed today today we observed the detailed drawing of column.in that drg we observed the sizes of bars are decreases with increasing the height of floor. .
Details of the Bye Laws referred today from bye-laws today we referred that the alternative material ,method of design & construction & tests. .
Details of any Managerial Skill learned today today we learned how to talk with the client .how to convince them for buying the flat. .
RATE ANALYSIS (Detailed Stepwise Calculations required) S.No. DESCRIPTION AMOUNT REMARK 3 Entrance Door / window (Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft.) Material : Burma Teak wood : 63784.00 Varun Timber Statement from { Burma Teak wood for Frame & Shutter Dt. 4/1/08 to 11/10/08 Total Amt Rs. 63784/-} Hinges 6 nos. : 900.00 Kolhapur Hardware {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Kolhapur Hardware {Total Amt. : 1488 / per No.} Bill NO. 144 Glass : Rs. 38.22/ Sqft. 678.41 Babji Glass Tradrs ( 17.75 Sqft. X 38.22 = 678.41 /-) Bill NO. 986 TOTAL Rs. 66850.41 per Door Labour for Flush Door 15% 10027.56 Say Rs. 10000.00 per Door .
Result of RATE ANALYSIS ( Rs per Unit ) 10000.00 per Door
Todays BUZZ Word After finalization of drawings the booking of the plots will be starts for the interested clients within the committed period the construction can be completed as per the design. During this period marketing and sells staff is involved in the achievement of their goal of selling a plots & flats to give the satisfaction to the clients. The first installment collected at the time of booking & the overall cost of plot or flat will be collected by one installment or step by step installment. The cost of flat will be decided on the following points. 1) Estimation cost of flat 2) Any extra additional charges in providing facilities 3) Total carpet area. 4) Total sellable area. 5) Parking provided. 6) Charges for electric connections. 7) Charges for water supply connection for municipal corporation. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: vishal2844@gmail.com
Subject: 13555

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bhoite vishal rajaram
Exam No. 13555
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 10.am
Site Leaving Time (HH:MM am/pm) 5.00pm
Details of the Work Allotted to you today by the Site In-Charge Today we are observe further electrification, 1) Every room wire connection get connect to each main control board 2) And each main control board get connect to main meter which is placed at ground level 3) In each room space is provided at entrance ,to collect all the wire ,get connected to main meter board.
Details of how you Planned & Executed the allotted work 1) Firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans .
Details of the Construction Procedure / Activity / Technology learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of the Construction Materials learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of the Construction / Engineering Drawings observed today Use of crushed sand is environmental freindly. As use of river sand is prohibited
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today The aggregate,sand, brick are placed in a suitable place to convey easy lifting of material . Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL WINDOW OF SIZE (1.2*1.5) ALUMINIUM FREME rate 100 rs per sq,m for 1.8sq.m = 1.8*100=180rs/ RATE FOR GLASS OF WINDOW= 60rs per sq.m. for 1.8 sq.m = 1.8*60= 108rs. FIXTURE FOR WINDOWS =40rs. LABOUR COST =50rs. TOTAL COST FOR ONE WINDOW OF SIZE (1.2*1.5) = (180+108+40+50) =378rs say 380rs. .
Result of RATE ANALYSIS ( Rs per Unit ) 380rs.
Todays BUZZ Word TODAYS BUZZ WORD the builders are determine ratesof flat or bunglow depend upon sq.foot e.g per sq.foot-2500rs. since the one flat rate about 22lakh to 25lakh it also includes construction rate,layout etc. and plus extra cost to client :- this should also inculde different important factors which have as follows:- a) service tax b) vatt tax. c) parking d) lift f) MSEB etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-11

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the ceiling work going in row bunglows.& the maintenance of the entire project work.
Details of how you Planned & Executed the allotted work -We saw together the ceiling work & also see the maintenance work.
Details of the Construction Procedure / Activity / Technology learned today Ceiling work -First POP sheets are bought from market for ceiling -Then lime mortar also prepared. -Then according to design ornamental ceiling work is started. -Light points ,fan points also considering during design. -After completion of ceiling work electrification work is going on.
Details of the Construction Materials learned today -POP sheets . -Lime mortar. -White cement. -Fevicol.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -Solar panels are used for water heating system that reduces the consumption of electricity . -Only some of the bungalows have used this.
Details of the Construction / Engineering Drawings observed today -Ceiling design –it is designed according to requirement of owner. -Design of gymnasium hall.-it is designed according to considering no of living in project.
Details of the Bye Laws referred today Overhead tank Every over head water storage tank is maintained in perfectly mosquito proof by providing properly fitting hinged cover and every tank is more than 1.5 m height and is provided with a permenantly fixed iron ladder to unable inspection.
Details of any Managerial Skill learned today Co-ordination between site incharge and site engineer is very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : Assume window of size 5feet * 4feet Assume it is aluminium glazed window . It is double channel window which contains two sliding panels. Grill is provided outside of the window. Particular : No. or Qt. Rate Cost Material Steel (for grill ) 10 kg. 43 430 Rs/- Aluminium frame 20 R.F.T 60 Rs/- 1200 Rs. Glass (plane Glass) 18 Sq.ft 30 Rs 540Rs/- Rubber sill 100Rs/- Rollers 8 50 400Rs/- Scew 20 1 20 Rs/- Lock 2 30 Rs/- 60 Rs/- Labour Grill Worker 1 150Rs/- 150 Rs/- Window fitter 2 150Rs/- 300Rs/ Total 3200Rs/- Add 20% profit of contractor, 3840Rs/- Builder , tax etc The cost of a window for 20 sq.ft. is Rs.3840. Therefore the cost of window for 192Rs/sq.ft.
Result of RATE ANALYSIS ( Rs per Unit ) 192Rs/sq.ft.
Todays BUZZ Word Todays Buzz word :how builders determine rates of flat./bunglow + extra cost to clients 1) First a builder buys a land for construction. 2) Then he prepares a plan of the building with the help of a civil engineer or architect . 3) He starts the construction by taking permission of the local corporation. 4) Before actual start of work the builder decides the square feet rate by taking into consideration the following points: 1) Land cost 2) Land development cost 3) Construction material cost 4)Labour cost 5) Advertisement cost 6)Security cost 7) Maintenance cost 8) Corporation charges 9) Common facilities like garden , gymnasium , club house , temple, common roads. 10) Management cost 11) Various taxes like sales tax, income tax, VAT ,transportation tax, etc. 12) Construction material transportation cost. After calculating above costs builder decides the built up rate in square feet and also he adds his profit and then decides the actual square feet rate of row bungalow or flat.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-11

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Sawant Amit Ganpat
Exam No. 10900
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to check column form work .& weather the curing is done for the slab & starter . .
Details of how you Planned & Executed the allotted work we observed weather the form work err-action is on placed where marking is done .& also observed weather it is in vertical or inclined. .
Details of the Construction Procedure / Activity / Technology learned today today we learn the procedure of extension of column reinforcement for next floor.first starter is placed then the steel of that particular diameter which are given in detailed drawing of column are bended at a distance .then that steel bar is then overlap with previous bar with the help of binding wire.& then stirrups are provided at a particular distance. .
Details of the Construction Materials learned today today we learned about the construction material bricks.the size of bricks is 230*15*9cm.the burned bricks are used which are all of generally same size.the price of one bricks is generally about 7 RS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rainwater harvesting technique is used. .
Details of the Construction / Engineering Drawings observed today today we observed the detailed drawing of column.in that drg we observed the sizes of bars are decreases with increasing the height of floor. .
Details of the Bye Laws referred today from bye-laws today we referred that the alternative material ,method of design & construction & tests. .
Details of any Managerial Skill learned today today we learned how to talk with the client .how to convince them for buying the flat. .
RATE ANALYSIS (Detailed Stepwise Calculations required) S.No. DESCRIPTION AMOUNT REMARK 3 Entrance Door / window (Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft.) Material : Burma Teak wood : 63784.00 Varun Timber Statement from { Burma Teak wood for Frame & Shutter Dt. 4/1/08 to 11/10/08 Total Amt Rs. 63784/-} Hinges 6 nos. : 900.00 Kolhapur Hardware {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Kolhapur Hardware {Total Amt. : 1488 / per No.} Bill NO. 144 Glass : Rs. 38.22/ Sqft. 678.41 Babji Glass Tradrs ( 17.75 Sqft. X 38.22 = 678.41 /-) Bill NO. 986 TOTAL Rs. 66850.41 per Door Labour for Flush Door 15% 10027.56 Say Rs. 10000.00 per Door .
Result of RATE ANALYSIS ( Rs per Unit ) 10000.00 per Door
Todays BUZZ Word After finalization of drawings the booking of the plots will be starts for the interested clients within the committed period the construction can be completed as per the design. During this period marketing and sells staff is involved in the achievement of their goal of selling a plots & flats to give the satisfaction to the clients. The first installment collected at the time of booking & the overall cost of plot or flat will be collected by one installment or step by step installment. The cost of flat will be decided on the following points. 1) Estimation cost of flat 2) Any extra additional charges in providing facilities 3) Total carpet area. 4) Total sellable area. 5) Parking provided. 6) Charges for electric connections. 7) Charges for water supply connection for municipal corporation. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-d11

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Fulari sujata shankar
Exam No. 13559
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 10.00am
Site Leaving Time (HH:MM am/pm) 5.00pm
Details of the Work Allotted to you today by the Site In-Charge Today we are observe further electrification, 1) Every room wire connection get connect to each main control board 2) And each main control board get connect to main meter which is placed at ground level 3) In each room space is provided at entrance ,to collect all the wire ,get connected to main meter board. .
Details of how you Planned & Executed the allotted work 1) Firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans . .
Details of the Construction Procedure / Activity / Technology learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited
Details of the Construction / Engineering Drawings observed today - Electrification Plans - Septic Tank Layouts. - Parking Layout.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today The aggregate,sand, brick are placed in a suitable place to convey easy lifting of material . Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL WINDOW OF SIZE (1.2*1.5) ALUMINIUM FREME rate 100 rs per sq,m for 1.8sq.m = 1.8*100=180rs/ RATE FOR GLASS OF WINDOW= 60rs per sq.m. for 1.8 sq.m = 1.8*60= 108rs. FIXTURE FOR WINDOWS =40rs. LABOUR COST =50rs. TOTAL COST FOR ONE WINDOW OF SIZE (1.2*1.5) = (180+108+40+50) =378rs say 380rs. .
Result of RATE ANALYSIS ( Rs per Unit ) 380rs.
Todays BUZZ Word TODAYS BUZZ WORD the builders are determine ratesof flat or bunglow depend upon sq.foot e.g per sq.foot-2500rs. since the one flat rate about 22lakh to 25lakh it also includes construction rate,layout etc. and plus extra cost to client :- this should also inculde different important factors which have as follows:- a) service tax b) vatt tax. c) parking d) lift f) MSEB etc
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-11

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) Bulbule Kandoba Ramchandra
Exam No. 13557
Working Day No. 11
Date (DD/MM/YYYY) 20 - 12 - 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the sizes of beam with reference to plan. • To check the no. of bars, sizes of bars used for each beam
Details of how you Planned & Executed the allotted work To give the plan of floor beam with this plan to observe the size of beam where situate and junction of another beam.
Details of the Construction Procedure / Activity / Technology learned today Floor Beams First the workers saw the plan and w.r.t this plan they cut the size of beam and its diameter. For beam bottom bars are laid as 16 mm dia. Of 2 nos. At top 10mm dia of 2 nos. for this are joined with stirrups of 8mm diameter. This stirrups are placed near column 100mm c/c of 12 nos. both side and middle they placed 175mm c/c distance. For this reinforced beam large dia. Bars are provided at L/4 distance from column last bars. This is known as curtle bars. This curtle bars are provided for avoiding buckling and deflection.
Details of the Construction Materials learned today * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Super plasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today ALUMINUM WINDOWS AND ARTIFICAL WOOD PROVIDED FOR FURNITURE PERPOUSE.
Details of the Construction / Engineering Drawings observed today Beam Drawing- Simply supported beam Continuous beam Cantilever beam Column beam
Details of the Bye Laws referred today COVERAGE(percentage to area or room below) 1) For kitchen room - 0.25m 2) Bath room, W.C - 1m 3) Shops with width up to 3m - 0 .34m
Details of any Managerial Skill learned today *Report to the civil engineer in the absence of P.E * Remain present for all types of concreting work * Attend to the visitors and clients
RATE ANALYSIS (Detailed Stepwise Calculations required) Analysis for 6 ft X 4 ft aluminum window with powder coating. Bottom rail - 1.4 X 165 = 231 /- Top rail & side rail - 3.03 X 165 = 499.95 /- Frame patti - 1) Top patti - 1.5 X 165 = 247.50 /- 2) Lock patti - 1.0 X 165 = 165 /- 3) Interlock patti – 2.13 X 165 = 351.45 /- P.V.C - 1) Glass PVC - 36 X 2 = 72 /- - 2) Track PVC - 80 X 0.5 = 40 /- Roller - 6 X 18 = 108 /- Glass - 24 X 25 = 600 /- Lock - 2 X 40 = 80 /- Hardware - 2.5 X 24 = 60 /- Labour - 20 X 24 = 480 /- Powder coating - 25 X 24 = 600 /- Total = 3534.90 /- sq ft
Result of RATE ANALYSIS ( Rs per Unit ) 1578.80 /-
Todays BUZZ Word “ HOW BUILDER DETERMINE RATE OF FLAT + EXTRA COST TO CLIENT” Rate of flat is determine builder from following factors 1) Special courses in marketing 2) Experience in the field of marketing 3) Personality 4) Family background 5) Technical knowledge Determination of rate of flat + extra cost to client 1) Details of the areas of available units. 2) Distance of the project from various important places 3) Rates of the area for sale , garden terrace , parking etc. 4) Information of clients who have booked the units in the scheme’
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-11

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 11
Date (DD/MM/YYYY) 20 - 12 - 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the sizes of beam with reference to plan. • To check the no. of bars, sizes of bars used for each beam
Details of how you Planned & Executed the allotted work To give the plan of floor beam with this plan to observe the size of beam where situate and junction of another beam.
Details of the Construction Procedure / Activity / Technology learned today Floor Beams First the workers saw the plan and w.r.t this plan they cut the size of beam and its diameter. For beam bottom bars are laid as 16 mm dia. Of 2 nos. At top 10mm dia of 2 nos. for this are joined with stirrups of 8mm diameter. This stirrups are placed near column 100mm c/c of 12 nos. both side and middle they placed 175mm c/c distance. For this reinforced beam large dia. Bars are provided at L/4 distance from column last bars. This is known as curtle bars. This curtle bars are provided for avoiding buckling and deflection.
Details of the Construction Materials learned today * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Super plasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today ALUMINUM WINDOWS AND ARTIFICAL WOOD PROVIDED FOR FURNITURE PERPOUSE.
Details of the Construction / Engineering Drawings observed today Beam Drawing- Simply supported beam Continuous beam Cantilever beam Column beam
Details of the Bye Laws referred today COVERAGE(percentage to area or room below) 1) For kitchen room - 0.25m 2) Bath room, W.C - 1m 3) Shops with width up to 3m - 0 .34m
Details of any Managerial Skill learned today *Report to the civil engineer in the absence of P.E * Remain present for all types of concreting work * Attend to the visitors and clients
RATE ANALYSIS (Detailed Stepwise Calculations required) Analysis for 6 ft X 4 ft aluminum window with powder coating. Bottom rail - 1.4 X 165 = 231 /- Top rail & side rail - 3.03 X 165 = 499.95 /- Frame patti - 1) Top patti - 1.5 X 165 = 247.50 /- 2) Lock patti - 1.0 X 165 = 165 /- 3) Interlock patti – 2.13 X 165 = 351.45 /- P.V.C - 1) Glass PVC - 36 X 2 = 72 /- - 2) Track PVC - 80 X 0.5 = 40 /- Roller - 6 X 18 = 108 /- Glass - 24 X 25 = 600 /- Lock - 2 X 40 = 80 /- Hardware - 2.5 X 24 = 60 /- Labour - 20 X 24 = 480 /- Powder coating - 25 X 24 = 600 /- Total = 3534.90 /- sq ft
Result of RATE ANALYSIS ( Rs per Unit ) 1578.80 /-
Todays BUZZ Word “ HOW BUILDER DETERMINE RATE OF FLAT + EXTRA COST TO CLIENT” Rate of flat is determine builder from following factors 1) Special courses in marketing 2) Experience in the field of marketing 3) Personality 4) Family background 5) Technical knowledge Determination of rate of flat + extra cost to client 1) Details of the areas of available units. 2) Distance of the project from various important places 3) Rates of the area for sale , garden terrace , parking etc. 4) Information of clients who have booked the units in the scheme’
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: Rohit_Patil361@rediffmail.com
Subject: 13565-11

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Rohit Ashok
Exam No. 13565
Working Day No. 11
Date (DD/MM/YYYY) 20 - 12 - 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the sizes of beam with reference to plan. • To check the no. of bars, sizes of bars used for each beam
Details of how you Planned & Executed the allotted work To give the plan of floor beam with this plan to observe the size of beam where situate and junction of another beam.
Details of the Construction Procedure / Activity / Technology learned today Floor Beams First the workers saw the plan and w.r.t this plan they cut the size of beam and its diameter. For beam bottom bars are laid as 16 mm dia. Of 2 nos. At top 10mm dia of 2 nos. for this are joined with stirrups of 8mm diameter. This stirrups are placed near column 100mm c/c of 12 nos. both side and middle they placed 175mm c/c distance. For this reinforced beam large dia. Bars are provided at L/4 distance from column last bars. This is known as curtle bars. This curtle bars are provided for avoiding buckling and deflection.
Details of the Construction Materials learned today * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Super plasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today ALUMINUM WINDOWS AND ARTIFICAL WOOD PROVIDED FOR FURNITURE PERPOUSE.
Details of the Construction / Engineering Drawings observed today Beam Drawing- Simply supported beam Continuous beam Cantilever beam Column beam
Details of the Bye Laws referred today COVERAGE(percentage to area or room below) 1) For kitchen room - 0.25m 2) Bath room, W.C - 1m 3) Shops with width up to 3m - 0 .34m
Details of any Managerial Skill learned today *Report to the civil engineer in the absence of P.E * Remain present for all types of concreting work * Attend to the visitors and clients
RATE ANALYSIS (Detailed Stepwise Calculations required) Analysis for 6 ft X 4 ft aluminum window with powder coating. Bottom rail - 1.4 X 165 = 231 /- Top rail & side rail - 3.03 X 165 = 499.95 /- Frame patti - 1) Top patti - 1.5 X 165 = 247.50 /- 2) Lock patti - 1.0 X 165 = 165 /- 3) Interlock patti – 2.13 X 165 = 351.45 /- P.V.C - 1) Glass PVC - 36 X 2 = 72 /- - 2) Track PVC - 80 X 0.5 = 40 /- Roller - 6 X 18 = 108 /- Glass - 24 X 25 = 600 /- Lock - 2 X 40 = 80 /- Hardware - 2.5 X 24 = 60 /- Labour - 20 X 24 = 480 /- Powder coating - 25 X 24 = 600 /- Total = 3534.90 /- sq ft
Result of RATE ANALYSIS ( Rs per Unit ) 1578.80 /-
Todays BUZZ Word “ HOW BUILDER DETERMINE RATE OF FLAT + EXTRA COST TO CLIENT” Rate of flat is determine builder from following factors 1) Special courses in marketing 2) Experience in the field of marketing 3) Personality 4) Family background 5) Technical knowledge Determination of rate of flat + extra cost to client 1) Details of the areas of available units. 2) Distance of the project from various important places 3) Rates of the area for sale , garden terrace , parking etc. 4) Information of clients who have booked the units in the scheme’
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-11

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) REDEKAR SHANTANU RAVINDRA
Exam No. 13566
Working Day No. 11
Date (DD/MM/YYYY) 20 - 12 - 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the sizes of beam with reference to plan. • To check the no. of bars, sizes of bars used for each beam
Details of how you Planned & Executed the allotted work To give the plan of floor beam with this plan to observe the size of beam where situate and junction of another beam.
Details of the Construction Procedure / Activity / Technology learned today Floor Beams First the workers saw the plan and w.r.t this plan they cut the size of beam and its diameter. For beam bottom bars are laid as 16 mm dia. Of 2 nos. At top 10mm dia of 2 nos. for this are joined with stirrups of 8mm diameter. This stirrups are placed near column 100mm c/c of 12 nos. both side and middle they placed 175mm c/c distance. For this reinforced beam large dia. Bars are provided at L/4 distance from column last bars. This is known as curtle bars. This curtle bars are provided for avoiding buckling and deflection.
Details of the Construction Materials learned today * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Super plasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today ALUMINUM WINDOWS AND ARTIFICAL WOOD PROVIDED FOR FURNITURE PERPOUSE.
Details of the Construction / Engineering Drawings observed today Beam Drawing- Simply supported beam Continuous beam Cantilever beam Column beam
Details of the Bye Laws referred today COVERAGE(percentage to area or room below) 1) For kitchen room - 0.25m 2) Bath room, W.C - 1m 3) Shops with width up to 3m - 0 .34m
Details of any Managerial Skill learned today *Report to the civil engineer in the absence of P.E * Remain present for all types of concreting work * Attend to the visitors and clients
RATE ANALYSIS (Detailed Stepwise Calculations required) Analysis for 6 ft X 4 ft aluminum window with powder coating. Bottom rail - 1.4 X 165 = 231 /- Top rail & side rail - 3.03 X 165 = 499.95 /- Frame patti - 1) Top patti - 1.5 X 165 = 247.50 /- 2) Lock patti - 1.0 X 165 = 165 /- 3) Interlock patti – 2.13 X 165 = 351.45 /- P.V.C - 1) Glass PVC - 36 X 2 = 72 /- - 2) Track PVC - 80 X 0.5 = 40 /- Roller - 6 X 18 = 108 /- Glass - 24 X 25 = 600 /- Lock - 2 X 40 = 80 /- Hardware - 2.5 X 24 = 60 /- Labour - 20 X 24 = 480 /- Powder coating - 25 X 24 = 600 /- Total = 3534.90 /- sq ft
Result of RATE ANALYSIS ( Rs per Unit ) 1578.80 /-
Todays BUZZ Word “ HOW BUILDER DETERMINE RATE OF FLAT + EXTRA COST TO CLIENT” Rate of flat is determine builder from following factors 1) Special courses in marketing 2) Experience in the field of marketing 3) Personality 4) Family background 5) Technical knowledge Determination of rate of flat + extra cost to client 1) Details of the areas of available units. 2) Distance of the project from various important places 3) Rates of the area for sale , garden terrace , parking etc. 4) Information of clients who have booked the units in the scheme’
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521-11

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Bagmare Dinesh Shriram
Exam No. 13521
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To see and study the laying of steel reinforcement for beams of third floor. To see the concreting of columns of second floor.
Details of how you Planned & Executed the allotted work We first went on second floor, where the concreting of column was going on. The concrete was made at the site itself and it was brought up to that floor by skip and hoist.Then we went on the top centering work for third floor.The steel reinforcemnt of beams were being layed there.
Details of the Construction Procedure / Activity / Technology learned today We learnt the process of concreting of columns of second floor and laying of steel reinforcement for third floor,and process of manufacturing concrete at site, We also saw the curing of staircase for third floor that was casted two days before, we saw that the formwork for second floor was being removed.
Details of the Construction Materials learned today Reinforcement for beams. Steel bars. Tor steel: 6mm,8mm,12mm,16mm,20mm,25mm,30mm. Mild steel:6mm,8mm,12mm. Ordinary Portland Cement (O.P.C)= 43 Grade, 53 Grade. Bagalkot Supreme. Crushed sand,coarse aggregate,water.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today A new technology for recycling of garbage known as Garbage Chute system with a waste water treatment plant will be adopted after the completion of construction.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for third floor with schedule of beams and columns.
Details of the Bye Laws referred today Minimum spacing between stirrups was kept by using bye laws. Height of each floor is according to bye laws.
Details of any Managerial Skill learned today 1.The site incharge inspected the place where concreting of columns were going on. 2.The site incharge has a good command over the labourers. 3.The site incharge checked the reinforcement of steel that was being layed for third floor.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"FULLY COMPLETE WINDOW\" Aluminium window- Double track. Aluminum-6.9 kg/sq.m Rate of aluminium=6.9*250= Rs.1725. Bagri glass 4mm thick-Rs.325/sq.m Rubber gasket= Rs.20/sq.m Fixtures= Stoppers etc.= Rs.100/sq.m Total cost= 1725+325+20+100= Rs.2170/sq.m Labour=30% Total cost= 2170+651=Rs.2821/sq.m Including 10% profit=28.21 Total cost= 2821+28.21= Rs.3103.1 /sq.m
Result of RATE ANALYSIS ( Rs per Unit ) = Rs.3103/sq.m
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". * The builders first determine the total area of a particular flat, then they consider the number of rooms,Salable area,Carpet area,F.S.I,facilities provided etc. * Then they workout the total construction cost of that particular flat with the facilities provided i.e Rate per sq.ft, they compare this rate with present market rates. * They also consider the total one time maintainance cost,independent parking cost,Monthly lift charges,deposit for reticulated gas pipeline system(if provided any),etc. * Then they estimate the other expenditures which includes documents cost, permission from muncipal corporation,stamp duty,agreement cost,VAT,service tax,Infra charges,basic cost etc. * Then they add all the above things and value that comes will be the actual cost.Now they add their profit to this cost which may be 20% to 50%. This profit is not mentioned in the total cost. This work is done by Estimation and Costing Department of builder. * The value that comes is finally the total package which is kept in front of the client.This cost may be reduced to a little extent while the discussions of the builder and the client.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523-11

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Devkar Vikram Dilip
Exam No. 13523
Working Day No. 11
Date (DD/MM/YYYY) 29/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To see and study the laying of steel reinforcement for beams of third floor. To see the concreting of columns of second floor.
Details of how you Planned & Executed the allotted work We first went on second floor, where the concreting of column was going on. The concrete was made at the site itself and it was brought up to that floor by skip and hoist.Then we went on the top centering work for third floor.The steel reinforcemnt of beams were being layed there.
Details of the Construction Procedure / Activity / Technology learned today We learnt the process of concreting of columns of second floor and laying of steel reinforcement for third floor,and process of manufacturing concrete at site, We also saw the curing of staircase for third floor that was casted two days before, we saw that the formwork for second floor was being removed.
Details of the Construction Materials learned today Reinforcement for beams. Steel bars. Tor steel: 6mm,8mm,12mm,16mm,20mm,25mm,30mm. Mild steel:6mm,8mm,12mm. Ordinary Portland Cement (O.P.C)= 43 Grade, 53 Grade. Bagalkot Supreme. Crushed sand,coarse aggregate,water.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today A new technology for recycling of garbage known as Garbage Chute system with a waste water treatment plant will be adopted after the completion of construction.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for third floor with schedule of beams and columns.
Details of the Bye Laws referred today Minimum spacing between stirrups was kept by using bye laws. Height of each floor is according to bye laws.
Details of any Managerial Skill learned today 1.The site incharge inspected the place where concreting of columns were going on. 2.The site incharge has a good command over the labourers. 3.The site incharge checked the reinforcement of steel that was being layed for third floor.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"FULLY COMPLETE WINDOW\" Aluminium window- Double track. Aluminum-6.9 kg/sq.m Rate of aluminium=6.9*250= Rs.1725. Bagri glass 4mm thick-Rs.325/sq.m Rubber gasket= Rs.20/sq.m Fixtures= Stoppers etc.= Rs.100/sq.m Total cost= 1725+325+20+100= Rs.2170/sq.m Labour=30% Total cost= 2170+651=Rs.2821/sq.m Including 10% profit=28.21 Total cost= 2821+28.21= Rs.3103.1 /sq.m
Result of RATE ANALYSIS ( Rs per Unit ) = Rs.3103/sq.m
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". * The builders first determine the total area of a particular flat, then they consider the number of rooms,Salable area,Carpet area,F.S.I,facilities provided etc. * Then they workout the total construction cost of that particular flat with the facilities provided i.e Rate per sq.ft, they compare this rate with present market rates. * They also consider the total one time maintainance cost,independent parking cost,Monthly lift charges,deposit for reticulated gas pipeline system(if provided any),etc. * Then they estimate the other expenditures which includes documents cost, permission from muncipal corporation,stamp duty,agreement cost,VAT,service tax,Infra charges,basic cost etc. * Then they add all the above things and value that comes will be the actual cost.Now they add their profit to this cost which may be 20% to 50%. This profit is not mentioned in the total cost. This work is done by Estimation and Costing Department of builder. * The value that comes is finally the total package which is kept in front of the client.This cost may be reduced to a little extent while the discussions of the builder and the client.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-11

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) MOHARE VISHAL BHALCHANDRA
Exam No. 13564
Working Day No. 11
Date (DD/MM/YYYY) 20 - 12 - 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the sizes of beam with reference to plan. • To check the no. of bars, sizes of bars used for each beam
Details of how you Planned & Executed the allotted work To give the plan of floor beam with this plan to observe the size of beam where situate and junction of another beam.
Details of the Construction Procedure / Activity / Technology learned today Floor Beams First the workers saw the plan and w.r.t this plan they cut the size of beam and its diameter. For beam bottom bars are laid as 16 mm dia. Of 2 nos. At top 10mm dia of 2 nos. for this are joined with stirrups of 8mm diameter. This stirrups are placed near column 100mm c/c of 12 nos. both side and middle they placed 175mm c/c distance. For this reinforced beam large dia. Bars are provided at L/4 distance from column last bars. This is known as curtle bars. This curtle bars are provided for avoiding buckling and deflection.
Details of the Construction Materials learned today * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Super plasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today ALUMINUM WINDOWS AND ARTIFICAL WOOD PROVIDED FOR FURNITURE PERPOUSE.
Details of the Construction / Engineering Drawings observed today Beam Drawing- Simply supported beam Continuous beam Cantilever beam Column beam
Details of the Bye Laws referred today COVERAGE(percentage to area or room below) 1) For kitchen room - 0.25m 2) Bath room, W.C - 1m 3) Shops with width up to 3m - 0 .34m
Details of any Managerial Skill learned today *Report to the civil engineer in the absence of P.E * Remain present for all types of concreting work * Attend to the visitors and clients
RATE ANALYSIS (Detailed Stepwise Calculations required) Analysis for 6 ft X 4 ft aluminum window with powder coating. Bottom rail - 1.4 X 165 = 231 /- Top rail & side rail - 3.03 X 165 = 499.95 /- Frame patti - 1) Top patti - 1.5 X 165 = 247.50 /- 2) Lock patti - 1.0 X 165 = 165 /- 3) Interlock patti – 2.13 X 165 = 351.45 /- P.V.C - 1) Glass PVC - 36 X 2 = 72 /- - 2) Track PVC - 80 X 0.5 = 40 /- Roller - 6 X 18 = 108 /- Glass - 24 X 25 = 600 /- Lock - 2 X 40 = 80 /- Hardware - 2.5 X 24 = 60 /- Labour - 20 X 24 = 480 /- Powder coating - 25 X 24 = 600 /- Total = 3534.90 /- sqft
Result of RATE ANALYSIS ( Rs per Unit ) 1578.80 /-
Todays BUZZ Word “ HOW BUILDER DETERMINE RATE OF FLAT + EXTRA COST TO CLIENT” Rate of flat is determine builder from following factors 1) Special courses in marketing 2) Experience in the field of marketing 3) Personality 4) Family background 5) Technical knowledge Determination of rate of flat + extra cost to client 1) Details of the areas of available units. 2) Distance of the project from various important places 3) Rates of the area for sale , garden terrace , parking etc. 4) Information of clients who have booked the units in the scheme’
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-11

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Tekwani Sagar Bansilal
Exam No. 10903
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To see and study the laying of steel reinforcement for beams of third floor. To see the concreting of columns of second floor.
Details of how you Planned & Executed the allotted work We first went on second floor, where the concreting of column was going on. The concrete was made at the site itself and it was brought up to that floor by skip and hoist.Then we went on the top centering work for third floor.The steel reinforcemnt of beams were being layed there.
Details of the Construction Procedure / Activity / Technology learned today We learnt the process of concreting of columns of second floor and laying of steel reinforcement for third floor,and process of manufacturing concrete at site, We also saw the curing of staircase for third floor that was casted two days before, we saw that the formwork for second floor was being removed.
Details of the Construction Materials learned today Reinforcement for beams. Steel bars. Tor steel: 6mm,8mm,12mm,16mm,20mm,25mm,30mm. Mild steel:6mm,8mm,12mm. Ordinary Portland Cement (O.P.C)= 43 Grade, 53 Grade. Bagalkot Supreme. Crushed sand,coarse aggregate,water.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today A new technology for recycling of garbage known as Garbage Chute system with a waste water treatment plant will be adopted after the completion of construction.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for third floor with schedule of beams and columns.
Details of the Bye Laws referred today Minimum spacing between stirrups was kept by using bye laws. Height of each floor is according to bye laws.
Details of any Managerial Skill learned today 1.The site incharge inspected the place where concreting of columns were going on. 2.The site incharge has a good command over the labourers. 3.The site incharge checked the reinforcement of steel that was being layed for third floor.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"FULLY COMPLETE WINDOW\" Aluminium window- Double track. Aluminum-6.9 kg/sq.m Rate of aluminium=6.9*250= Rs.1725. Bagri glass 4mm thick-Rs.325/sq.m Rubber gasket= Rs.20/sq.m Fixtures= Stoppers etc.= Rs.100/sq.m Total cost= 1725+325+20+100= Rs.2170/sq.m Labour=30% Total cost= 2170+651=Rs.2821/sq.m Including 10% profit=28.21 Total cost= 2821+28.21= Rs.3103.1 /sq.m
Result of RATE ANALYSIS ( Rs per Unit ) = Rs.3103/sq.m
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". * The builders first determine the total area of a particular flat, then they consider the number of rooms,Salable area,Carpet area,F.S.I,facilities provided etc. * Then they workout the total construction cost of that particular flat with the facilities provided i.e Rate per sq.ft, they compare this rate with present market rates. * They also consider the total one time maintainance cost,independent parking cost,Monthly lift charges,deposit for reticulated gas pipeline system(if provided any),etc. * Then they estimate the other expenditures which includes documents cost, permission from muncipal corporation,stamp duty,agreement cost,VAT,service tax,Infra charges,basic cost etc. * Then they add all the above things and value that comes will be the actual cost.Now they add their profit to this cost which may be 20% to 50%. This profit is not mentioned in the total cost. This work is done by Estimation and Costing Department of builder. * The value that comes is finally the total package which is kept in front of the client.This cost may be reduced to a little extent while the discussions of the builder and the client.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: gauravdesai75@gmail.com
Subject: 13522-11

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near Jay prabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DESAI GAURAV RAVINDRA
Exam No. 13522
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge * To see and study the laying of steel reinforcement for beams of third floor. * To see the concreting of columns of second floor.
Details of how you Planned & Executed the allotted work We first went on second floor, where the concreting of column was going on. The concrete was made at the site itself and it was brought up to that floor by skip and hoist.Then we went on the top centering work for third floor.The steel reinforcemnt of beams were being layed there.
Details of the Construction Procedure / Activity / Technology learned today We learnt the process of concreting of columns of second floor and laying of steel reinforcement for third floor,and process of manufacturing concrete at site.We also saw the curing of staircase for third floor that was casted two days before,we saw that the formwork for second floor was being removed.
Details of the Construction Materials learned today * Reinforcement for beams. Steel bars. Tor steel: 6mm,8mm,12mm,16mm,20mm,25mm,30mm. Mild steel:6mm,8mm,12mm. * Ordinary Portland Cement (O.P.C)= 43 Grade, 53 Grade. Bagalkot Supreme. * Crushed sand,coarse aggregate,water.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today A new technology for recycling of garbage known as Garbage Chute system with a waste water treatment plant will be adopted after the completion of construction.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for third floor with schedule of beams and columns.
Details of the Bye Laws referred today * Minimum spacing between stirrups was kept by using bye laws. * Height of each floor is according to bye laws.
Details of any Managerial Skill learned today 1.The site incharge inspected the place where concreting of columns were going on. 2.The site incharge has a good command over the labourers. 3.The site incharge checked the reinforcement of steel that was being layed for third floor.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"FULLY COMPLETE WINDOW\" Aluminium window- Double track. Aluminum-6.9 kg/sq.m Rate of aluminium=6.9*250= Rs.1725. Bagri glass 4mm thick-Rs.325/sq.m Rubber gasket= Rs.20/sq.m Fixtures= Stoppers etc.= Rs.100/sq.m Total cost= 1725+325+20+100= Rs.2170/sq.m Labour=30% Total cost= 2170+651=Rs.2821/sq.m Including 10% profit=28.21 Total cost= 2821+28.21= Rs.3103.1 /sq.m= Rs.3103/sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.3103/sq.m
Todays BUZZ Word \"How Builders determine Rates of Flats/Bungalows + Extra cost to clients\". * The builders first determine the total area of a particular flat, then they consider the number of rooms,Salable area,Carpet area,F.S.I,facilities provided etc. * Then they workout the total construction cost of that particular flat with the facilities provided i.e Rate per sq.ft, they compare this rate with present market rates. * They also consider the total one time maintainance cost,independent parking cost,Monthly lift charges,deposit for reticulated gas pipeline system(if provided any),etc. * Then they estimate the other expenditures which includes documents cost, permission from muncipal corporation,stamp duty,agreement cost,VAT,service tax,Infra charges,basic cost etc. * Then they add all the above things and value that comes will be the actual cost.Now they add their profit to this cost which may be 20% to 50%. This profit is not mentioned in the total cost. This work is done by Estimation and Costing Department of builder. * The value that comes is finally the total package which is kept in front of the client.This cost may be reduced to a little extent while the discussions of the builder and the client.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-11

Company Name Bhima Builders & Developers
Project Name & Site Address wind gate nagala park
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9;00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the sizes of beam with reference to plan. • To check the no. of bars, sizes of bars used for each beam
Details of how you Planned & Executed the allotted work To give the plan of floor beam with this plan to observe the size of beam where situate and junction of another beam.
Details of the Construction Procedure / Activity / Technology learned today Floor Beams First the workers saw the plan and w.r.t this plan they cut the size of beam and its diameter. For beam bottom bars are laid as 16 mm dia. Of 2 nos. At top 10mm dia of 2 nos. for this are joined with stirrups of 8mm diameter. This stirrups are placed near column 100mm c/c of 12 nos. both side and middle they placed 175mm c/c distance. For this reinforced beam large dia. Bars are provided at L/4 distance from column last bars. This is known as curtle bars. This curtle bars are provided for avoiding buckling and deflection.
Details of the Construction Materials learned today * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Super plasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today ALUMINUM WINDOWS AND ARTIFICAL WOOD PROVIDED FOR FURNITURE PERPOUSE.
Details of the Construction / Engineering Drawings observed today Beam Drawing- Simply supported beam Continuous beam Cantilever beam Column beam
Details of the Bye Laws referred today COVERAGE(percentage to area or room below) 1) For kitchen room - 0.25m 2) Bath room, W.C - 1m 3) Shops with width up to 3m - 0 .34m
Details of any Managerial Skill learned today *Report to the civil engineer in the absence of P.E * Remain present for all types of concreting work * Attend to the visitors and clients
RATE ANALYSIS (Detailed Stepwise Calculations required) ) Rate analysis - FULLY ALUMINA WINDOW Size of window - 6’ x 4’ Three Track Aluminum window Bottom rail = 6’ x 1.4 kg = 8.4 kg = 8.4 x 165 = 1380.00 Top rail + Bottom rai = 14’ x 3.03 = 42.46 x 165 = 7006.00 Frame patti = top patti = 14’ x 1.5 =21 x 165 = 3465.00 Glass pvc = 36’ x 2 = 72.00 Track pvc = 80’ x 0.50 = 40.00 Roller = 6 no. x 18 = 108 .00 Glass 4.00 mm thik = 24 sq.ft x 25 = 600.00 Lock = 40 x 2 = 80.00 Labour = 24 x 20.00 = 480.00 Total = 13231. 00 Rs. per 24 sq.ft 1800.00 PER SQ.M
Result of RATE ANALYSIS ( Rs per Unit ) 1800/-
Todays BUZZ Word “ HOW BUILDER DETERMINE RATE OF FLAT + EXTRA COST TO CLIENT” Rate of flat is determine builder from following factors 1) Special courses in marketing 2) Experience in the field of marketing 3) Personality 4) Family background 5) Technical knowledge Determination of rate of flat + extra cost to client 1) Details of the areas of available units. 2) Distance of the project from various important places 3) Rates of the area for sale , garden terrace , parking etc. 4) Information of clients who have booked the units in the scheme’
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-11

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Shinde Sagar Arvind
Exam No. 13568
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Study of lay out drawing -Study of distribution and arrangement of plots. -Arrangement of roads. -Open spaces provided. -Notation 1)Plot Boundary 2)Open space 3)Government nominise 4)Drain Water line .
Details of how you Planned & Executed the allotted work Tally the total area of layout Calculate the 1)Total open space provided. 2)Total area under road. 3)Total area of min. size of plots. 4)Total area of max. size of plots. 5)Area of plot under govt. authority. .
Details of the Construction Procedure / Activity / Technology learned today How to prepare lay out 1)Fixed the boundary of plot 2)Draw proper road network as per a)Entrance b)Exit c)Junction with another plot. 3)Decide the min. & max. sizes of plots. 4)Leave the 10% area of plot for open space. 5)Planned and fixed the sub plots as per their sizes. 6)Leave the space for govt. nominees. 7)Tally the total area of plot to area divided into all other sub areas. .
Details of the Construction Materials learned today 1)Timber 2)glass 3)steel bars 4)Hold fast 5)Tools & planks. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Lay out drawing of any property will helpful in design in the 1)Proper drainage system. 2)Collection of total solid waste. 3)Space easily available for treatment plants. 4)Huge quantity of rain water availability. 5)Fixing the position of solar panels to give the max. supply of renewable enrgy. .
Details of the Construction / Engineering Drawings observed today Detailed layout drawings .
Details of the Bye Laws referred today -Layout drawings -Min. & max. width of roads -Area reserve for open space -Area under government nominise
Details of any Managerial Skill learned today When fixing the line out check the following things - 1)Scale. 2)Proper use of bye-laws. 3)Width of roads. 4)Equal parts of big plots into same size of small plots. 5)Accuracy in drawing while draw the line out plan. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW Window Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft. Material : Burma Teak wood : 63784.00 { Burma Teak wood for Frame & Shutter Hinges 6 nos. : 900.00 {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Glas : Rs. 38.22/ Sqft.678.41 ( 17.75 Sqft. X 38.22 = 678.41 /-) TOTAL Rs.66850.41/window Labour for Flush window 15% 10027.56 Say Rs. 10000/window .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.10000/-
Todays BUZZ Word After finalization of drawings the booking of the plots will be starts for the interested clients within the committed period the construction can be completed as per the design. During this period marketing and sells staff is involved in the achievement of their goal of selling a plots & flats to give the satisfaction to the clients. The first installment collected at the time of booking & the overall cost of plot or flat will be collected by one installment or step by step installment. The cost of flat will be decided on the following points. 1)Estimation cost of flat 2)Any extra additional charges in providing facilities 3)Total carpet area. 4)Total sellable area. 5)Parking provided. 6)Charges for electric connections. 7)Charges for water supply connection for municipal corporation. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradeep Bharmal. 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-11

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sutar Namdev Rangnath
Exam No. 13571
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Study of lay out drawing -Study of distribution and arrangement of plots. -Arrangement of roads. -Open spaces provided. -Notation 1)Plot Boundary 2)Open space 3)Government nominise 4)Drain Water line .
Details of how you Planned & Executed the allotted work Tally the total area of layout Calculate the 1)Total open space provided. 2)Total area under road. 3)Total area of min. size of plots. 4)Total area of max. size of plots. 5)Area of plot under govt. authority. .
Details of the Construction Procedure / Activity / Technology learned today How to prepare lay out 1)Fixed the boundary of plot 2)Draw proper road network as per a)Entrance b)Exit c)Junction with another plot. 3)Decide the min. & max. sizes of plots. 4)Leave the 10% area of plot for open space. 5)Planned and fixed the sub plots as per their sizes. 6)Leave the space for govt. nominees. 7)Tally the total area of plot to area divided into all other sub areas. .
Details of the Construction Materials learned today 1)Timber 2)glass 3)steel bars 4)Hold fast 5)Tools & planks. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Lay out drawing of any property will helpful in design in the 1)Proper drainage system. 2)Collection of total solid waste. 3)Space easily available for treatment plants. 4)Huge quantity of rain water availability. 5)Fixing the position of solar panels to give the max. supply of renewable enrgy. .
Details of the Construction / Engineering Drawings observed today Detailed layout drawings .
Details of the Bye Laws referred today -Layout drawings -Min. & max. width of roads -Area reserve for open space -Area under government nominise
Details of any Managerial Skill learned today When fixing the line out check the following things - 1)Scale. 2)Proper use of bye-laws. 3)Width of roads. 4)Equal parts of big plots into same size of small plots. 5)Accuracy in drawing while draw the line out plan. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW Window Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft. Material : Burma Teak wood : 63784.00 { Burma Teak wood for Frame & Shutter Hinges 6 nos. : 900.00 {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Glas : Rs. 38.22/ Sqft.678.41 ( 17.75 Sqft. X 38.22 = 678.41 /-) TOTAL Rs.66850.41/window Labour for Flush window 15% 10027.56 Say Rs. 10000/window .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.10000/-
Todays BUZZ Word After finalization of drawings the booking of the plots will be starts for the interested clients within the committed period the construction can be completed as per the design. During this period marketing and sells staff is involved in the achievement of their goal of selling a plots & flats to give the satisfaction to the clients. The first installment collected at the time of booking & the overall cost of plot or flat will be collected by one installment or step by step installment. The cost of flat will be decided on the following points. 1)Estimation cost of flat 2)Any extra additional charges in providing facilities 3)Total carpet area. 4)Total sellable area. 5)Parking provided. 6)Charges for electric connections. 7)Charges for water supply connection for municipal corporation. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradeep Bharmal. 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-11

Company Name Bhima Builders & Developers
Project Name & Site Address wind gate nagala park
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Ramchandra
Exam No. 13557
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the sizes of beam with reference to plan. • To check the no. of bars, sizes of bars used for each beam
Details of how you Planned & Executed the allotted work To give the plan of floor beam with this plan to observe the size of beam where situate and junction of another beam.
Details of the Construction Procedure / Activity / Technology learned today Floor Beams First the workers saw the plan and w.r.t this plan they cut the size of beam and its diameter. For beam bottom bars are laid as 16 mm dia. Of 2 nos. At top 10mm dia of 2 nos. for this are joined with stirrups of 8mm diameter. This stirrups are placed near column 100mm c/c of 12 nos. both side and middle they placed 175mm c/c distance. For this reinforced beam large dia. Bars are provided at L/4 distance from column last bars. This is known as curtle bars. This curtle bars are provided for avoiding buckling and deflection.
Details of the Construction Materials learned today * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Super plasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today ALUMINUM WINDOWS AND ARTIFICAL WOOD PROVIDED FOR FURNITURE PERPOUSE.
Details of the Construction / Engineering Drawings observed today Beam Drawing- Simply supported beam Continuous beam Cantilever beam Column beam
Details of the Bye Laws referred today COVERAGE(percentage to area or room below) 1) For kitchen room - 0.25m 2) Bath room, W.C - 1m 3) Shops with width up to 3m - 0 .34m
Details of any Managerial Skill learned today ) *Report to the civil engineer in the absence of P.E * Remain present for all types of concreting work * Attend to the visitors and clients
RATE ANALYSIS (Detailed Stepwise Calculations required) ) Rate analysis - FULLY ALUMINA WINDOW Size of window - 6’ x 4’ Three Track Aluminum window Bottom rail = 6’ x 1.4 kg = 8.4 kg = 8.4 x 165 = 1380.00 Top rail + Bottom rai = 14’ x 3.03 = 42.46 x 165 = 7006.00 Frame patti = top patti = 14’ x 1.5 =21 x 165 = 3465.00 Glass pvc = 36’ x 2 = 72.00 Track pvc = 80’ x 0.50 = 40.00 Roller = 6 no. x 18 = 108 .00 Glass 4.00 mm thik = 24 sq.ft x 25 = 600.00 Lock = 40 x 2 = 80.00 Labour = 24 x 20.00 = 480.00 Total = 13231. 00 Rs. per 24 sq.ft 1800.00 PER SQ.M
Result of RATE ANALYSIS ( Rs per Unit ) 1800/-
Todays BUZZ Word “ HOW BUILDER DETERMINE RATE OF FLAT + EXTRA COST TO CLIENT” Rate of flat is determine builder from following factors 1) Special courses in marketing 2) Experience in the field of marketing 3) Personality 4) Family background 5) Technical knowledge Determination of rate of flat + extra cost to client 1) Details of the areas of available units. 2) Distance of the project from various important places 3) Rates of the area for sale , garden terrace , parking etc. 4) Information of clients who have booked the units in the scheme’
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: pnfeelings@gmail.com
Subject: 13569-11

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Shivtare Prabharkar Chandrakant
Exam No. 13569
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Study of lay out drawing -Study of distribution and arrangement of plots. -Arrangement of roads. -Open spaces provided. -Notation 1)Plot Boundary 2)Open space 3)Government nominise 4)Drain Water line .
Details of how you Planned & Executed the allotted work Tally the total area of layout Calculate the 1)Total open space provided. 2)Total area under road. 3)Total area of min. size of plots. 4)Total area of max. size of plots. 5)Area of plot under govt. authority. .
Details of the Construction Procedure / Activity / Technology learned today How to prepare lay out 1)Fixed the boundary of plot 2)Draw proper road network as per a)Entrance b)Exit c)Junction with another plot. 3)Decide the min. & max. sizes of plots. 4)Leave the 10% area of plot for open space. 5)Planned and fixed the sub plots as per their sizes. 6)Leave the space for govt. nominees. 7)Tally the total area of plot to area divided into all other sub areas. .
Details of the Construction Materials learned today 1)Timber 2)glass 3)steel bars 4)Hold fast 5)Tools & planks. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Lay out drawing of any property will helpful in design in the 1)Proper drainage system. 2)Collection of total solid waste. 3)Space easily available for treatment plants. 4)Huge quantity of rain water availability. 5)Fixing the position of solar panels to give the max. supply of renewable enrgy. .
Details of the Construction / Engineering Drawings observed today Detailed layout drawings .
Details of the Bye Laws referred today -Layout drawings -Min. & max. width of roads -Area reserve for open space -Area under government nominise
Details of any Managerial Skill learned today When fixing the line out check the following things - 1)Scale. 2)Proper use of bye-laws. 3)Width of roads. 4)Equal parts of big plots into same size of small plots. 5)Accuracy in drawing while draw the line out plan. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW Window Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft. Material : Burma Teak wood : 63784.00 { Burma Teak wood for Frame & Shutter Hinges 6 nos. : 900.00 {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Glas : Rs. 38.22/ Sqft.678.41 ( 17.75 Sqft. X 38.22 = 678.41 /-) TOTAL Rs.66850.41/window Labour for Flush window 15% 10027.56 Say Rs. 10000/window .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.10000/-
Todays BUZZ Word After finalization of drawings the booking of the plots will be starts for the interested clients within the committed period the construction can be completed as per the design. During this period marketing and sells staff is involved in the achievement of their goal of selling a plots & flats to give the satisfaction to the clients. The first installment collected at the time of booking & the overall cost of plot or flat will be collected by one installment or step by step installment. The cost of flat will be decided on the following points. 1)Estimation cost of flat 2)Any extra additional charges in providing facilities 3)Total carpet area. 4)Total sellable area. 5)Parking provided. 6)Charges for electric connections. 7)Charges for water supply connection for municipal corporation. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradeep Bharmal. 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 10567-11

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 11
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Study of lay out drawing -Study of distribution and arrangement of plots. -Arrangement of roads. -Open spaces provided. -Notation 1)Plot Boundary 2)Open space 3)Government nominise 4)Drain Water line .
Details of how you Planned & Executed the allotted work Tally the total area of layout Calculate the 1)Total open space provided. 2)Total area under road. 3)Total area of min. size of plots. 4)Total area of max. size of plots. 5)Area of plot under govt. authority. .
Details of the Construction Procedure / Activity / Technology learned today How to prepare lay out 1)Fixed the boundary of plot 2)Draw proper road network as per a)Entrance b)Exit c)Junction with another plot. 3)Decide the min. & max. sizes of plots. 4)Leave the 10% area of plot for open space. 5)Planned and fixed the sub plots as per their sizes. 6)Leave the space for govt. nominees. 7)Tally the total area of plot to area divided into all other sub areas. .
Details of the Construction Materials learned today 1)Timber 2)glass 3)steel bars 4)Hold fast 5)Tools & planks. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Lay out drawing of any property will helpful in design in the 1)Proper drainage system. 2)Collection of total solid waste. 3)Space easily available for treatment plants. 4)Huge quantity of rain water availability. 5)Fixing the position of solar panels to give the max. supply of renewable enrgy. .
Details of the Construction / Engineering Drawings observed today Detailed layout drawings .
Details of the Bye Laws referred today -Layout drawings -Min. & max. width of roads -Area reserve for open space -Area under government nominise
Details of any Managerial Skill learned today When fixing the line out check the following things - 1)Scale. 2)Proper use of bye-laws. 3)Width of roads. 4)Equal parts of big plots into same size of small plots. 5)Accuracy in drawing while draw the line out plan. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW Window Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft. Material : Burma Teak wood : 63784.00 { Burma Teak wood for Frame & Shutter Hinges 6 nos. : 900.00 {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Glas : Rs. 38.22/ Sqft.678.41 ( 17.75 Sqft. X 38.22 = 678.41 /-) TOTAL Rs.66850.41/window Labour for Flush window 15% 10027.56 Say Rs. 10000/window .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.10000/-
Todays BUZZ Word After finalization of drawings the booking of the plots will be starts for the interested clients within the committed period the construction can be completed as per the design. During this period marketing and sells staff is involved in the achievement of their goal of selling a plots & flats to give the satisfaction to the clients. The first installment collected at the time of booking & the overall cost of plot or flat will be collected by one installment or step by step installment. The cost of flat will be decided on the following points. 1)Estimation cost of flat 2)Any extra additional charges in providing facilities 3)Total carpet area. 4)Total sellable area. 5)Parking provided. 6)Charges for electric connections. 7)Charges for water supply connection for municipal corporation. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradeep Bharmal. 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: mayur.sonawane61@gmail.com
Subject: 13570-10

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) SONAWANE MAYUR MADHUKAR
Exam No. 13570
Working Day No. 10
Date (DD/MM/YYYY) 20/12/2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Study of lay out drawing -Study of distribution and arrangement of plots. -Arrangement of roads. -Open spaces provided. -Notation 1)Plot Boundary 2)Open space 3)Government nominise 4)Drain Water line .
Details of how you Planned & Executed the allotted work Tally the total area of layout Calculate the 1)Total open space provided. 2)Total area under road. 3)Total area of min. size of plots. 4)Total area of max. size of plots. 5)Area of plot under govt. authority. .
Details of the Construction Procedure / Activity / Technology learned today How to prepare lay out 1)Fixed the boundary of plot 2)Draw proper road network as per a)Entrance b)Exit c)Junction with another plot. 3)Decide the min. & max. sizes of plots. 4)Leave the 10% area of plot for open space. 5)Planned and fixed the sub plots as per their sizes. 6)Leave the space for govt. nominees. 7)Tally the total area of plot to area divided into all other sub areas. .
Details of the Construction Materials learned today 1)Timber 2)glass 3)steel bars 4)Hold fast 5)Tools & planks. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Lay out drawing of any property will helpful in design in the 1)Proper drainage system. 2)Collection of total solid waste. 3)Space easily available for treatment plants. 4)Huge quantity of rain water availability. 5)Fixing the position of solar panels to give the max. supply of renewable enrgy. .
Details of the Construction / Engineering Drawings observed today Detailed layout drawings .
Details of the Bye Laws referred today -Layout drawings -Min. & max. width of roads -Area reserve for open space -Area under government nominise
Details of any Managerial Skill learned today When fixing the line out check the following things - 1)Scale. 2)Proper use of bye-laws. 3)Width of roads. 4)Equal parts of big plots into same size of small plots. 5)Accuracy in drawing while draw the line out plan. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR WINDOW Window Size : 5\'-2\" X 7\'-11\" = 40.95 Sqft. Material : Burma Teak wood : 63784.00 { Burma Teak wood for Frame & Shutter Hinges 6 nos. : 900.00 {1 Hinges = Rs. 175/ No. So for 6 Hinges 6X150= Rs. 900/- Lock & Handle : 1488.00 Glas : Rs. 38.22/ Sqft.678.41 ( 17.75 Sqft. X 38.22 = 678.41 /-) TOTAL Rs.66850.41/window Labour for Flush window 15% 10027.56 Say Rs. 10000/window .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.10000/-
Todays BUZZ Word After finalization of drawings the booking of the plots will be starts for the interested clients within the committed period the construction can be completed as per the design. During this period marketing and sells staff is involved in the achievement of their goal of selling a plots & flats to give the satisfaction to the clients. The first installment collected at the time of booking & the overall cost of plot or flat will be collected by one installment or step by step installment. The cost of flat will be decided on the following points. 1)Estimation cost of flat 2)Any extra additional charges in providing facilities 3)Total carpet area. 4)Total sellable area. 5)Parking provided. 6)Charges for electric connections. 7)Charges for water supply connection for municipal corporation. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradeep Bharmal. 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-11

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) tirmare pradnya ashok
Exam No. 13572
Working Day No. 11
Date (DD/MM/YYYY) 20.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check slab reinforcement.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings and detailed drawings of 3 bhk bungllow. Then we cheked that reinforcement is as per r.c.c. design or not with site in charge.
Details of the Construction Procedure / Activity / Technology learned today Checking of slab reinforcement ; 1. Slab is very important component of building, it should be casted with greatest care. 2. First reinforcement is prepared and placed in position by workers. 3 Then reinforcement is checked by site in charge. 4. While checking of reinforcement all the contents of r.c.c. design are checked such as , diameter of bars , their location , effectve cover , spacing of stirrups. 5. Other details are also checked such as , curtailed bars, extra top, extra bottom, resting of beams reinforcement on each other. 6. All above details are checked and mistakes are corrected.
Details of the Construction Materials learned today GLASS ; 1. Glass is commonly used construction material. 2. Glass is commonly used for making door and window panels. 3. Glass is also used improving external appearance of building i.e. glass is used in glazing of building. 4. Glass is also commonly used for other architectural purposes and ornamental works. 5. Glasses are available in different colours and textures.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Sewage which is treated in Sewage Treatment Plant is used as fertilizer in gardening,farming.
Details of the Construction / Engineering Drawings observed today R.C.C. drawings of slab, deatailed plan of 2bhk building., r.c.c drawings of sunk slab , ordinary beam, hidden beam.
Details of the Bye Laws referred today RAIN WATER PIPES ; 1. Rainwater pi[es shall be affixed to the outside of the walls of buildings or in recessess or chases cut or formed at in such walls or in such other manner as may be approved by commisioner. 2. Diameter of rain water downtake pipe is generally 75mm & 100mm.
Details of any Managerial Skill learned today We learned that how to convince the customer so that he get satisfied with the quality of work and he will be ready to buy the residential unit.
RATE ANALYSIS (Detailed Stepwise Calculations required) FULLY COMPLETED WINDOW ; rate per sq.m. Type of window ; aluminium window Aluminium = 100 Rs. Glass panels = 60 Rs other fixtures = 30 labours = 30 Rs TOTAL = 220.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 220.00 Rs.per sq,m
Todays BUZZ Word HOW BUILDERS DETERMINE RATES OF FLATS / BUNGALOW + EXTRA COST TO CLIENT ; Rates of flats and bungalows determined by builders depends on following factors ; 1. Location of building. 2. Area considered while saling the flat or bunglow i.e. a) Carpet area b) BuiLt up area. c) Super built up area d) Saleable area 3. Facilities and amenities provided. 4. Availability of materials. 5. Availability of labours. 6. Maintainance cost. 7. Stamp duty & registration charges. 8. VAT tax. 9. Service tax. 10. Class of material used in construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. Mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-11

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Jade Madhavrao Anil
Exam No. 13560
Working Day No. 11
Date (DD/MM/YYYY) 20.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check slab reinforcement.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings and detailed drawings of 3 bhk bungllow. Then we cheked that reinforcement is as per r.c.c. design or not with site in charge.
Details of the Construction Procedure / Activity / Technology learned today Checking of slab reinforcement ; 1. Slab is very important component of building, it should be casted with greatest care. 2. First reinforcement is prepared and placed in position by workers. 3 Then reinforcement is checked by site in charge. 4. While checking of reinforcement all the contents of r.c.c. design are checked such as , diameter of bars , their location , effectve cover , spacing of stirrups. 5. Other details are also checked such as , curtailed bars, extra top, extra bottom, resting of beams reinforcement on each other. 6. All above details are checked and mistakes are corrected.
Details of the Construction Materials learned today GLASS ; 1. Glass is commonly used construction material. 2. Glass is commonly used for making door and window panels. 3. Glass is also used improving external appearance of building i.e. glass is used in glazing of building. 4. Glass is also commonly used for other architectural purposes and ornamental works. 5. Glasses are available in different colours and textures.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Sewage which is treated in Sewage Treatment Plant is used as fertilizer in gardening,farming.
Details of the Construction / Engineering Drawings observed today R.C.C. drawings of slab, deatailed plan of 2bhk building., r.c.c drawings of sunk slab , ordinary beam, hidden beam.
Details of the Bye Laws referred today RAIN WATER PIPES ; 1. Rainwater pi[es shall be affixed to the outside of the walls of buildings or in recessess or chases cut or formed at in such walls or in such other manner as may be approved by commisioner. 2. Diameter of rain water downtake pipe is generally 75mm & 100mm.
Details of any Managerial Skill learned today We learned that how to convince the customer so that he get satisfied with the quality of work and he will be ready to buy the residential unit.
RATE ANALYSIS (Detailed Stepwise Calculations required) FULLY COMPLETED WINDOW ; rate per sq.m. Type of window ; aluminium window Aluminium = 100 Rs. Glass panels = 60 Rs other fixtures = 30 labours = 30 Rs TOTAL = 220.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 220.00 Rs.per sq,m
Todays BUZZ Word HOW BUILDERS DETERMINE RATES OF FLATS / BUNGALOW + EXTRA COST TO CLIENT ; Rates of flats and bungalows determined by builders depends on following factors ; 1. Location of building. 2. Area considered while saling the flat or bunglow i.e. a) Carpet area b) BuiLt up area. c) Super built up area d) Saleable area 3. Facilities and amenities provided. 4. Availability of materials. 5. Availability of labours. 6. Maintainance cost. 7. Stamp duty & registration charges. 8. VAT tax. 9. Service tax. 10. Class of material used in construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. Mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-11

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) katral raju maruti
Exam No. 13562
Working Day No. 11
Date (DD/MM/YYYY) 20.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check slab reinforcement.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings and detailed drawings of 3 bhk bungllow. Then we cheked that reinforcement is as per r.c.c. design or not with site in charge.
Details of the Construction Procedure / Activity / Technology learned today Checking of slab reinforcement ; 1. Slab is very important component of building, it should be casted with greatest care. 2. First reinforcement is prepared and placed in position by workers. 3 Then reinforcement is checked by site in charge. 4. While checking of reinforcement all the contents of r.c.c. design are checked such as , diameter of bars , their location , effectve cover , spacing of stirrups. 5. Other details are also checked such as , curtailed bars, extra top, extra bottom, resting of beams reinforcement on each other. 6. All above details are checked and mistakes are corrected.
Details of the Construction Materials learned today GLASS ; 1. Glass is commonly used construction material. 2. Glass is commonly used for making door and window panels. 3. Glass is also used improving external appearance of building i.e. glass is used in glazing of building. 4. Glass is also commonly used for other architectural purposes and ornamental works. 5. Glasses are available in different colours and textures.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Sewage which is treated in Sewage Treatment Plant is used as fertilizer in gardening,farming.
Details of the Construction / Engineering Drawings observed today R.C.C. drawings of slab, deatailed plan of 2bhk building., r.c.c drawings of sunk slab , ordinary beam, hidden beam.
Details of the Bye Laws referred today RAIN WATER PIPES ; 1. Rainwater pi[es shall be affixed to the outside of the walls of buildings or in recessess or chases cut or formed at in such walls or in such other manner as may be approved by commisioner. 2. Diameter of rain water downtake pipe is generally 75mm & 100mm.
Details of any Managerial Skill learned today We learned that how to convince the customer so that he get satisfied with the quality of work and he will be ready to buy the residential unit.
RATE ANALYSIS (Detailed Stepwise Calculations required) FULLY COMPLETED WINDOW ; rate per sq.m. Type of window ; aluminium window Aluminium = 100 Rs. Glass panels = 60 Rs other fixtures = 30 labours = 30 Rs TOTAL = 220.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 220.00 Rs.per sq,m
Todays BUZZ Word HOW BUILDERS DETERMINE RATES OF FLATS / BUNGALOW + EXTRA COST TO CLIENT ; Rates of flats and bungalows determined by builders depends on following factors ; 1. Location of building. 2. Area considered while saling the flat or bunglow i.e. a) Carpet area b) BuiLt up area. c) Super built up area d) Saleable area 3. Facilities and amenities provided. 4. Availability of materials. 5. Availability of labours. 6. Maintainance cost. 7. Stamp duty & registration charges. 8. VAT tax. 9. Service tax. 10. Class of material used in construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. Mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13561-11

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Jadhav Sardar Swaroop J.
Exam No. 13561
Working Day No. 11
Date (DD/MM/YYYY) 20.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check slab reinforcement.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings and detailed drawings of 3 bhk bungllow. Then we cheked that reinforcement is as per r.c.c. design or not with site in charge.
Details of the Construction Procedure / Activity / Technology learned today Checking of slab reinforcement ; 1. Slab is very important component of building, it should be casted with greatest care. 2. First reinforcement is prepared and placed in position by workers. 3 Then reinforcement is checked by site in charge. 4. While checking of reinforcement all the contents of r.c.c. design are checked such as , diameter of bars , their location , effectve cover , spacing of stirrups. 5. Other details are also checked such as , curtailed bars, extra top, extra bottom, resting of beams reinforcement on each other. 6. All above details are checked and mistakes are corrected.
Details of the Construction Materials learned today GLASS ; 1. Glass is commonly used construction material. 2. Glass is commonly used for making door and window panels. 3. Glass is also used improving external appearance of building i.e. glass is used in glazing of building. 4. Glass is also commonly used for other architectural purposes and ornamental works. 5. Glasses are available in different colours and textures.S
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Sewage which is treated in Sewage Treatment Plant is used as fertilizer in gardening,farming.
Details of the Construction / Engineering Drawings observed today R.C.C. drawings of slab, deatailed plan of 2bhk building., r.c.c drawings of sunk slab , ordinary beam, hidden beam.
Details of the Bye Laws referred today RAIN WATER PIPES ; 1. Rainwater pi[es shall be affixed to the outside of the walls of buildings or in recessess or chases cut or formed at in such walls or in such other manner as may be approved by commisioner. 2. Diameter of rain water downtake pipe is generally 75mm & 100mm.
Details of any Managerial Skill learned today We learned that how to convince the customer so that he get satisfied with the quality of work and he will be ready to buy the residential unit.
RATE ANALYSIS (Detailed Stepwise Calculations required) FULLY COMPLETED WINDOW ; rate per sq.m. Type of window ; aluminium window Aluminium = 100 Rs. Glass panels = 60 Rs other fixtures = 30 labours = 30 Rs TOTAL = 220.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 220.00 Rs.per sq,m
Todays BUZZ Word HOW BUILDERS DETERMINE RATES OF FLATS / BUNGALOW + EXTRA COST TO CLIENT ; Rates of flats and bungalows determined by builders depends on following factors ; 1. Location of building. 2. Area considered while saling the flat or bunglow i.e. a) Carpet area b) BuiLt up area. c) Super built up area d) Saleable area 3. Facilities and amenities provided. 4. Availability of materials. 5. Availability of labours. 6. Maintainance cost. 7. Stamp duty & registration charges. 8. VAT tax. 9. Service tax. 10. Class of material used in construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. Mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/20/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558-11

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Chavan Shivprasad Prakash
Exam No. 13558
Working Day No. 11
Date (DD/MM/YYYY) 20.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check slab reinforcement.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings and detailed drawings of 3 bhk bungllow. Then we cheked that reinforcement is as per r.c.c. design or not,with site in charge.
Details of the Construction Procedure / Activity / Technology learned today Checking of slab reinforcement ; 1. Slab is very important component of building, it should be casted with greatest care. 2. First reinforcement is prepared and placed in position by workers. 3 Then reinforcement is checked by site in charge. 4. While checking of reinforcement all the contents of r.c.c. design are checked such as , diameter of bars , their location , effectve cover , spacing of stirrups. 5. Other details are also checked such as , curtailed bars, extra top, extra bottom, resting of beams reinforcement on each other. 6. All above details are checked and mistakes are corrected.
Details of the Construction Materials learned today GLASS ; 1. Glass is commonly used construction material. 2. Glass is commonly used for making door and window panels. 3. Glass is also used improving external appearance of building i.e. glass is used in glazing of building. 4. Glass is also commonly used for other architectural purposes and ornamental works. 5. Glasses are available in different colours and textures.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Sewage which is treated in Sewage Treatment Plant is used as fertilizer in gardening,farming.
Details of the Construction / Engineering Drawings observed today R.C.C. drawings of slab, deatailed plan of 2bhk building., r.c.c drawings of sunk slab , ordinary beam, hidden beam.
Details of the Bye Laws referred today RAIN WATER PIPES ; 1. Rainwater pi[es shall be affixed to the outside of the walls of buildings or in recessess or chases cut or formed at in such walls or in such other manner as may be approved by commisioner. 2. Diameter of rain water downtake pipe is generally 75mm & 100mm.
Details of any Managerial Skill learned today We learned that how to convince the customer so that he get satisfied with the quality of work and he will be ready to buy the residential unit.
RATE ANALYSIS (Detailed Stepwise Calculations required) FULLY COMPLETED WINDOW ; rate per sq.m. Type of window ; aluminium window Aluminium = 100 Rs. Glass panels = 60 Rs other fixtures = 30 labours = 30 Rs TOTAL = 220.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 220.00 Rs. per sq,m
Todays BUZZ Word HOW BUILDERS DETERMINE RATES OF FLATS / BUNGALOW + EXTRA COST TO CLIENT ; Rates of flats and bungalows determined by builders depends on following factors ; 1. Location of building & land cost. 2. Area considered while saling the flat or bunglow i.e. a) Carpet area b) BuiLt up area. c) Super built up area d) Saleable area 3. Facilities and amenities provided. 4. Availability of materials. 5. Availability of labours. 6. Maintainance cost. 7. Stamp duty & registration charges. 8. VAT tax. 9. Service tax. 10. Class of material used in construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. Mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together.
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the consumption of more water .
Details of the Construction / Engineering Drawings observed today Up coming third phase floor plans of Sanghavi Builders & Developers
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructions given by the owner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together.
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the consumption of more water .
Details of the Construction / Engineering Drawings observed today Up coming third phase floor plans of Sanghavi Builders & Developers
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructions given by the owner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together.
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the consumption of more water .
Details of the Construction / Engineering Drawings observed today Up coming third phase floor plans of Sanghavi Builders & Developers
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructions given by the owner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together.
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the consumption of more water .
Details of the Construction / Engineering Drawings observed today Up coming third phase floor plans of Sanghavi Builders & Developers
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructions given by the owner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together.
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the consumption of more water .
Details of the Construction / Engineering Drawings observed today Up coming third phase floor plans of Sanghavi Builders & Developers
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructions given by the owner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-10

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) JAGADALE ASHVANI RAMRAO
Exam No. 13530
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge TO observe the P.C.C. work.
Details of how you Planned & Executed the allotted work two are observing compaction and two are observing batching and mixing.
Details of the Construction Procedure / Activity / Technology learned today How to mark level of P.C.C. ,for progress of P.C.C. work and what kind of preparation is required before the work.
Details of the Construction Materials learned today different type of ingredients of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today observing working drawing of various type of flats.
Details of the Bye Laws referred today cantiliver portion of cupboard - max 0.6 m
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PAINTING WORK PER SQ.M TWO COATS ARE GIVEN WHILE PAINTING FOR THAT RATE ARE AS FOLLOWS DISTEMPER 0.30 KG = 26 Rs CEMENT PRIMER 0.35 LITRE = 21 Rs TERPENTINE 0.08 LITRE = 20 Rs LABOUR COST AND OTHER EQUIPMENTS = 7 % TOATL = 75 Rs per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 75 Rs
Todays BUZZ Word SAFETY PROVIDED FOR THE WORKER ON THE SITE IS THROUGH 1.HELMET, 2.HAND GLOVES, 3.PROPER SCAFFOLDING WITH SUFFICIENT STRENGTH. FACILITIES PROVIDED ARE 1. SHADE FOR LIVING. 2. TOILET 3. WATER SUPPLY
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-10

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) PATIL ADITYA PANDURANG
Exam No. 13538
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge TO observe the P.C.C. work.
Details of how you Planned & Executed the allotted work two are observing compaction and two are observing batching and mixing.
Details of the Construction Procedure / Activity / Technology learned today How to mark level of P.C.C. ,for progress of P.C.C. work and what kind of preparation is required before the work.
Details of the Construction Materials learned today different type of ingredients of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today observing working drawing of various type of flats.
Details of the Bye Laws referred today cantiliver portion of cupboard - max 0.6 m
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PAINTING WORK PER SQ.M TWO COATS ARE GIVEN WHILE PAINTING FOR THAT RATE ARE AS FOLLOWS DISTEMPER 0.30 KG = 26 Rs CEMENT PRIMER 0.35 LITRE = 21 Rs TERPENTINE 0.08 LITRE = 20 Rs LABOUR COST AND OTHER EQUIPMENTS = 7 % TOATL = 75 Rs per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 75 Rs
Todays BUZZ Word SAFETY PROVIDED FOR THE WORKER ON THE SITE IS THROUGH 1.HELMET, 2.HAND GLOVES, 3.PROPER SCAFFOLDING WITH SUFFICIENT STRENGTH. FACILITIES PROVIDED ARE 1. SHADE FOR LIVING. 2. TOILET 3. WATER SUPPLY
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-10

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) MANGAONKAR MANOJ DATTATRAY
Exam No. 13536
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge TO observe the P.C.C. work.
Details of how you Planned & Executed the allotted work two are observing compaction and two are observing batching and mixing.
Details of the Construction Procedure / Activity / Technology learned today HOW to mark level of P.C.C. ,for progress of P.C.C. work and what kind of preparation is required before the work.
Details of the Construction Materials learned today different type of ingredients of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today observing working drawing of various type of flats.
Details of the Bye Laws referred today cantiliver portion of cupboard - max 0.6 m
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PAINTING WORK PER SQ.M TWO COATS ARE GIVEN WHILE PAINTING FOR THAT RATE ARE AS FOLLOWS DISTEMPER 0.30 KG = 26 Rs CEMENT PRIMER 0.35 LITRE = 21 Rs TERPENTINE 0.08 LITRE = 20 Rs LABOUR COST AND OTHER EQUIPMENTS = 7 % TOATL = 75 Rs per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 75 Rs
Todays BUZZ Word SAFETY PROVIDED FOR THE WORKER ON THE SITE IS THROUGH 1.HELMET, 2.HAND GLOVES, 3.PROPER SCAFFOLDING WITH SUFFICIENT STRENGTH. FACILITIES PROVIDED ARE 1. SHADE FOR LIVING. 2. TOILET 3. WATER SUPPLY
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-10

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge TO observe the P.C.C. work.
Details of how you Planned & Executed the allotted work two are observing compaction and two are observing batching and mixing.
Details of the Construction Procedure / Activity / Technology learned today How to mark level of P.C.C. ,for progress of P.C.C. work and what kind of preparation is required before the work.
Details of the Construction Materials learned today different type of ingredients of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today observing working drawing of various type of flats.
Details of the Bye Laws referred today cantiliver portion of cupboard - max 0.6 m
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PAINTING WORK PER SQ.M TWO COATS ARE GIVEN WHILE PAINTING FOR THAT RATE ARE AS FOLLOWS DISTEMPER 0.30 KG = 26 Rs CEMENT PRIMER 0.35 LITRE = 21 Rs TERPENTINE 0.08 LITRE = 20 Rs LABOUR COST AND OTHER EQUIPMENTS = 7 % TOATL = 75 Rs per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 75 Rs
Todays BUZZ Word SAFETY PROVIDED FOR THE WORKER ON THE SITE IS THROUGH 1.HELMET, 2.HAND GLOVES, 3.PROPER SCAFFOLDING WITH SUFFICIENT STRENGTH. FACILITIES PROVIDED ARE 1. SHADE FOR LIVING. 2. TOILET 3. WATER SUPPLY
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGALE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-10

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) patil pratik vilas
Exam No. 13549
Working Day No. 10
Date (DD/MM/YYYY) 18/12/10
Site Reporting Time (HH:MM am/pm) 10am
Site Leaving Time (HH:MM am/pm) 5pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses.
Details of how you Planned & Executed the allotted work 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished.
Details of the Construction Materials learned today We learnt about -pop finish work for which white cement is used . -for wall painting tractor emulation.and ace colour paint is used - paving blocks are used for the internal roads - Plastering –cement & sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater is utilised for ground water recharging through the soak pits. utilisation of crushed sand instead of natural sand.
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing: correlating with bye-laws 2)Line out plan:- contents:- a)c-c distance between all columns b)footing details c)R.C.C. column details i.e. size and reinforcement. d)Ground beam and Plinth beam details with floor level
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today They cooperated with us very well. They manage the work properly by giving proper direction to the workers
RATE ANALYSIS (Detailed Stepwise Calculations required) External painting:- painting: Assume 1*12/1000(m) volume of painting= 1*0.012= 0.012m3 cost:0.012*1200=14.4 RS labour=mason1= Rs250 labour= Rs140 total= Rs405 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13
Result of RATE ANALYSIS ( Rs per Unit ) Rs-460
Todays BUZZ Word SITE SAFETY- 1-One of the most basic things that one can do is wear a hard hat on the job site. 2-Steel-toed boots or shoes are a great way to protect the feet. Face it; we have all stubbed our toe or dropped something on our foot at one time or another. 3-Safety goggles or safety glasses are great for protecting the eyes. 4-Signs are an important part of setting up a safe construction site. 5-There should always be a well-stocked first aid kit on a job site all times. 6-By following a few basic rules can help one to be safe when working in a construction site. Without having or wearing proper safety equipment on a job site can sometimes be the difference between life and death. Remembering these basic things can make many job sites a safer place to work. FACILITIES- 1- Drinking water 2- waiting room 3- security 4- control room 5-utility room
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-10

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Shinde Shraddha Tukaram
Exam No. 10901
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - To prepare daily Report. - To Observe the excavation for Septic Tank. ---------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work - First we all went to study various construction works on the site. - Accordingly we prepared the daily site report. - Then at 10.00 am JCB was bought on the site & excavation for Septic tank was done for the Line out marked yesterday. -----------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today 1. The Line out was carried out yesterday for septic tank. 2. Today the JCB was bought on the site. 3. The JCB driver was given the instructions of how to carry the excavation. 4. Accordingly excavation was carried out. 5. A Pit of 34\' x 10\' x 6\' was dug. -----------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. Natural Sand. 2. Artificial Sand ( Crushed Sand ) 3. Coarse Aggregates. 4. Cement ( 43 & 53 grade ) -----------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. Water Harvesting for Storm water was done using Storm Drains. 2. Solar Panels were used for B-Wing. 3. Water Softner was used for softening bore water. --------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Details. 2. Excavation Details. 3. Building Layout 4. Floor Plans. ------------------------------------------------------------------------------------
Details of the Bye Laws referred today - Amenities & Facilities in layouts - Land use classifications. --------------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1. Punctuality. 2. Sensitivity. 3. Orderliness. 4. Co-ordination with Customers & Labours. -------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS for External Painting\" # 1. Applying cement paint in 2 coats on external walls A) External Painting For : 1. Right Side External Wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left side ( Verandah, WC ) = 11.61 sq.m 4. Front wall = 30.41 sq.m 5. Back wall (Kitchen) = 16.19 sq.m 6. Back Wall ( Verandah, WC ) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction = 22.70 sq.m (for doors and windows) C) Deduct 50% = 11.35 sq.m D) Net quantity = 119.6 sq.m E) Material Required: 1. Cement paint = 36 kg. F) Material Cost: 1. cement Paint = 36 x 50 = 1800/- G) Labour Cost: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Mazdoor = 10 x 120 = 1200/- 4. T & P = 1000/- TOTAL = 4400/- H) Total Cost = F + G = 6200/- I) Contractors Profit = 10% = 620/- J) Grand Total = 6820/- K) Rate Per Sq.M = 57.02/- ---------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 57.02/-
Todays BUZZ Word # \"SITE SAFETY\" # 1. Encorpating Site Safety Programs. 2. Provision of Accident Programs. 3. Provision of Emergency Telephone Numbers ( Fire, Ambulance, Police, Doctor) 4. Provision of Safety Helmets, Safety Belts, Hand Gloves, safety Goggles, Gumboots etc. 5. Provision of First Aid Kit. # \"Facilities to Workers\" # 1.Toilets to Labours. 2.Drinking Water arrangements. 3.Provision of Palnaghar for labour\'s children. 4.Seprate Parkings for vehicles belonging to labours. -----------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-10

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Janbandhu Rakshit Dulichand
Exam No. 10875
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - To prepare daily Report. - To Observe the excavation for Septic Tank. ---------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work - First we all went to study various construction works on the site. - Accordingly we prepared the daily site report. - Then at 10.00 am JCB was bought on the site & excavation for Septic tank was done for the Line out marked yesterday. -----------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today 1. The Line out was carried out yesterday for septic tank. 2. Today the JCB was bought on the site. 3. The JCB driver was given the instructions of how to carry the excavation. 4. Accordingly excavation was carried out. 5. A Pit of 34\' x 10\' x 6\' was dug. -----------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. Natural Sand. 2. Artificial Sand ( Crushed Sand ) 3. Coarse Aggregates. 4. Cement ( 43 & 53 grade ) -----------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. Water Harvesting for Storm water was done using Storm Drains. 2. Solar Panels were used for B-Wing. 3. Water Softner was used for softening bore water. --------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Details. 2. Excavation Details. 3. Building Layout 4. Floor Plans. ------------------------------------------------------------------------------------
Details of the Bye Laws referred today - Amenities & Facilities in layouts - Land use classifications. --------------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1. Punctuality. 2. Sensitivity. 3. Orderliness. 4. Co-ordination with Customers & Labours. -------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS for External Painting\" # 1. Applying cement paint in 2 coats on external walls A) External Painting For : 1. Right Side External Wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left side ( Verandah, WC ) = 11.61 sq.m 4. Front wall = 30.41 sq.m 5. Back wall (Kitchen) = 16.19 sq.m 6. Back Wall ( Verandah, WC ) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction = 22.70 sq.m (for doors and windows) C) Deduct 50% = 11.35 sq.m D) Net quantity = 119.6 sq.m E) Material Required: 1. Cement paint = 36 kg. F) Material Cost: 1. cement Paint = 36 x 50 = 1800/- G) Labour Cost: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Mazdoor = 10 x 120 = 1200/- 4. T & P = 1000/- TOTAL = 4400/- H) Total Cost = F + G = 6200/- I) Contractors Profit = 10% = 620/- J) Grand Total = 6820/- K) Rate Per Sq.M = 57.02/- ---------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 57.02/-
Todays BUZZ Word # \"SITE SAFETY\" # 1. Encorpating Site Safety Programs. 2. Provision of Accident Programs. 3. Provision of Emergency Telephone Numbers ( Fire, Ambulance, Police, Doctor) 4. Provision of Safety Helmets, Safety Belts, Hand Gloves, safety Goggles, Gumboots etc. 5. Provision of First Aid Kit. # \"Facilities to Workers\" # 1.Toilets to Labours. 2.Drinking Water arrangements. 3.Provision of Palnaghar for labour\'s children. 4.Seprate Parkings for vehicles belonging to labours. -----------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10893-10

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Kamble Ankit V.
Exam No. 10893
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - To prepare daily Report. - To Observe the excavation for Septic Tank. ---------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work - First we all went to study various construction works on the site. - Accordingly we prepared the daily site report. - Then at 10.00 am JCB was bought on the site & excavation for Septic tank was done for the Line out marked yesterday. -----------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today 1. The Line out was carried out yesterday for septic tank. 2. Today the JCB was bought on the site. 3. The JCB driver was given the instructions of how to carry the excavation. 4. Accordingly excavation was carried out. 5. A Pit of 34\' x 10\' x 6\' was dug. -----------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. Natural Sand. 2. Artificial Sand ( Crushed Sand ) 3. Coarse Aggregates. 4. Cement ( 43 & 53 grade ) -----------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. Water Harvesting for Storm water was done using Storm Drains. 2. Solar Panels were used for B-Wing. 3. Water Softner was used for softening bore water. --------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Details. 2. Excavation Details. 3. Building Layout 4. Floor Plans. ------------------------------------------------------------------------------------
Details of the Bye Laws referred today - Amenities & Facilities in layouts - Land use classifications. --------------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1. Punctuality. 2. Sensitivity. 3. Orderliness. 4. Co-ordination with Customers & Labours. -------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS for External Painting\" # 1. Applying cement paint in 2 coats on external walls A) External Painting For : 1. Right Side External Wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left side ( Verandah, WC ) = 11.61 sq.m 4. Front wall = 30.41 sq.m 5. Back wall (Kitchen) = 16.19 sq.m 6. Back Wall ( Verandah, WC ) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction = 22.70 sq.m (for doors and windows) C) Deduct 50% = 11.35 sq.m D) Net quantity = 119.6 sq.m E) Material Required: 1. Cement paint = 36 kg. F) Material Cost: 1. cement Paint = 36 x 50 = 1800/- G) Labour Cost: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Mazdoor = 10 x 120 = 1200/- 4. T & P = 1000/- TOTAL = 4400/- H) Total Cost = F + G = 6200/- I) Contractors Profit = 10% = 620/- J) Grand Total = 6820/- K) Rate Per Sq.M = 57.02/- ---------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 57.02/-
Todays BUZZ Word # \"SITE SAFETY\" # 1. Encorpating Site Safety Programs. 2. Provision of Accident Programs. 3. Provision of Emergency Telephone Numbers ( Fire, Ambulance, Police, Doctor) 4. Provision of Safety Helmets, Safety Belts, Hand Gloves, safety Goggles, Gumboots etc. 5. Provision of First Aid Kit. # \"Facilities to Workers\" # 1.Toilets to Labours. 2.Drinking Water arrangements. 3.Provision of Palnaghar for labour\'s children. 4.Seprate Parkings for vehicles belonging to labours. -----------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-10

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Nagvekar Yogesh Deepak
Exam No. 10894
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - To prepare daily Report. - To Observe the excavation for Septic Tank. ---------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work - First we all went to study various construction works on the site. - Accordingly we prepared the daily site report. - Then at 10.00 am JCB was bought on the site & excavation for Septic tank was done for the Line out marked yesterday. -----------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today 1. The Line out was carried out yesterday for septic tank. 2. Today the JCB was bought on the site. 3. The JCB driver was given the instructions of how to carry the excavation. 4. Accordingly excavation was carried out. 5. A Pit of 34\' x 10\' x 6\' was dug. -----------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. Natural Sand. 2. Artificial Sand ( Crushed Sand ) 3. Coarse Aggregates. 4. Cement ( 43 & 53 grade ) -----------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. Water Harvesting for Storm water was done using Storm Drains. 2. Solar Panels were used for B-Wing. 3. Water Softner was used for softening bore water. --------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Details. 2. Excavation Details. 3. Building Layout 4. Floor Plans. ------------------------------------------------------------------------------------
Details of the Bye Laws referred today - Amenities & Facilities in layouts - Land use classifications. --------------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1. Punctuality. 2. Sensitivity. 3. Orderliness. 4. Co-ordination with Customers & Labours. -------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS for External Painting\" # 1. Applying cement paint in 2 coats on external walls A) External Painting For : 1. Right Side External Wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left side ( Verandah, WC ) = 11.61 sq.m 4. Front wall = 30.41 sq.m 5. Back wall (Kitchen) = 16.19 sq.m 6. Back Wall ( Verandah, WC ) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction = 22.70 sq.m (for doors and windows) C) Deduct 50% = 11.35 sq.m D) Net quantity = 119.6 sq.m E) Material Required: 1. Cement paint = 36 kg. F) Material Cost: 1. cement Paint = 36 x 50 = 1800/- G) Labour Cost: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Mazdoor = 10 x 120 = 1200/- 4. T & P = 1000/- TOTAL = 4400/- H) Total Cost = F + G = 6200/- I) Contractors Profit = 10% = 620/- J) Grand Total = 6820/- K) Rate Per Sq.M = 57.02/- ---------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 57.02/-
Todays BUZZ Word # \"SITE SAFETY\" # 1. Encorpating Site Safety Programs. 2. Provision of Accident Programs. 3. Provision of Emergency Telephone Numbers ( Fire, Ambulance, Police, Doctor) 4. Provision of Safety Helmets, Safety Belts, Hand Gloves, safety Goggles, Gumboots etc. 5. Provision of First Aid Kit. # \"Facilities to Workers\" # 1.Toilets to Labours. 2.Drinking Water arrangements. 3.Provision of Palnaghar for labour\'s children. 4.Seprate Parkings for vehicles belonging to labours. -----------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376) ----------------------------------------------------------------------------------
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-10

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Jape Vishwajeet Ramesh
Exam No. 10892
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - To prepare daily Report. - To Observe the excavation for Septic Tank. ---------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work - First we all went to study various construction works on the site. - Accordingly we prepared the daily site report. - Then at 10.00 am JCB was bought on the site & excavation for Septic tank was done for the Line out marked yesterday. -----------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today 1. The Line out was carried out yesterday for septic tank. 2. Today the JCB was bought on the site. 3. The JCB driver was given the instructions of how to carry the excavation. 4. Accordingly excavation was carried out. 5. A Pit of 34\' x 10\' x 6\' was dug. -----------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. Natural Sand. 2. Artificial Sand ( Crushed Sand ) 3. Coarse Aggregates. 4. Cement ( 43 & 53 grade ) -----------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. Water Harvesting for Storm water was done using Storm Drains. 2. Solar Panels were used for B-Wing. 3. Water Softner was used for softening bore water. --------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1. Septic Tank Details. 2. Excavation Details. 3. Building Layout 4. Floor Plans. ------------------------------------------------------------------------------------
Details of the Bye Laws referred today - Amenities & Facilities in layouts - Land use classifications. --------------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1. Punctuality. 2. Sensitivity. 3. Orderliness. 4. Co-ordination with Customers & Labours. -------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS for External Painting\" # 1. Applying cement paint in 2 coats on external walls A) External Painting For : 1. Right Side External Wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left side ( Verandah, WC ) = 11.61 sq.m 4. Front wall = 30.41 sq.m 5. Back wall (Kitchen) = 16.19 sq.m 6. Back Wall ( Verandah, WC ) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction = 22.70 sq.m (for doors and windows) C) Deduct 50% = 11.35 sq.m D) Net quantity = 119.6 sq.m E) Material Required: 1. Cement paint = 36 kg. F) Material Cost: 1. cement Paint = 36 x 50 = 1800/- G) Labour Cost: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Mazdoor = 10 x 120 = 1200/- 4. T & P = 1000/- TOTAL = 4400/- H) Total Cost = F + G = 6200/- I) Contractors Profit = 10% = 620/- J) Grand Total = 6820/- K) Rate Per Sq.M = 57.02/- ---------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 57.02/-
Todays BUZZ Word # \"SITE SAFETY\" # 1. Encorpating Site Safety Programs. 2. Provision of Accident Programs. 3. Provision of Emergency Telephone Numbers ( Fire, Ambulance, Police, Doctor) 4. Provision of Safety Helmets, Safety Belts, Hand Gloves, safety Goggles, Gumboots etc. 5. Provision of First Aid Kit. # \"Facilities to Workers\" # 1.Toilets to Labours. 2.Drinking Water arrangements. 3.Provision of Palnaghar for labour\'s children. 4.Seprate Parkings for vehicles belonging to labours. -----------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376) ----------------------------------------------------------------------------------
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-09

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bhoite vishal rajaram
Exam No. 13555
Working Day No. 09
Date (DD/MM/YYYY) 18/12/10
Site Reporting Time (HH:MM am/pm) 10am
Site Leaving Time (HH:MM am/pm) 5pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses.
Details of how you Planned & Executed the allotted work 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today We learnt about -pop finish work for which white cement is used . -for wall painting tractor emulation.and ace colour paint is used - paving blocks are used for the internal roads - Plastering –cement & sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater is utilised for ground water recharging through the soak pits. utilisation of crushed sand instead of natural sand.
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing: correlating with bye-laws 2)Line out plan:- contents:- a)c-c distance between all columns b)footing details c)R.C.C. column details i.e. size and reinforcement. d)Ground beam and Plinth beam details with floor level
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today They cooperated with us very well. They manage the work properly by giving proper direction to the workers
RATE ANALYSIS (Detailed Stepwise Calculations required) External painting:- painting: Assume 1*12/1000(m) volume of painting= 1*0.012= 0.012m3 cost:0.012*1200=14.4 RS labour=mason1= Rs250 labour= Rs140 total= Rs405 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13
Result of RATE ANALYSIS ( Rs per Unit ) Rs-460
Todays BUZZ Word SITE SAFETY- 1-One of the most basic things that one can do is wear a hard hat on the job site. 2-Steel-toed boots or shoes are a great way to protect the feet. Face it; we have all stubbed our toe or dropped something on our foot at one time or another. 3-Safety goggles or safety glasses are great for protecting the eyes. 4-Signs are an important part of setting up a safe construction site. 5-There should always be a well-stocked first aid kit on a job site all times. 6-By following a few basic rules can help one to be safe when working in a construction site. Without having or wearing proper safety equipment on a job site can sometimes be the difference between life and death. Remembering these basic things can make many job sites a safer place to work. FACILITIES- 1- Drinking water 2- waiting room 3- security 4- control room 5-utility room
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-09

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bauchakar deepak yuvaraj
Exam No. 13554
Working Day No. 09
Date (DD/MM/YYYY) 18/12/10
Site Reporting Time (HH:MM am/pm) 10am
Site Leaving Time (HH:MM am/pm) 5pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses.
Details of how you Planned & Executed the allotted work 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished
Details of the Construction Materials learned today We learnt about -pop finish work for which white cement is used . -for wall painting tractor emulation.and ace colour paint is used - paving blocks are used for the internal roads - Plastering –cement & sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater is utilised for ground water recharging through the soak pits. utilisation of crushed sand instead of natural sand.
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing: correlating with bye-laws 2)Line out plan:- contents:- a)c-c distance between all columns b)footing details c)R.C.C. column details i.e. size and reinforcement. d)Ground beam and Plinth beam details with floor level
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today They cooperated with us very well. They manage the work properly by giving proper direction to the workers
RATE ANALYSIS (Detailed Stepwise Calculations required) External painting:- painting: Assume 1*12/1000(m) volume of painting= 1*0.012= 0.012m3 cost:0.012*1200=14.4 RS labour=mason1= Rs250 labour= Rs140 total= Rs405 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13
Result of RATE ANALYSIS ( Rs per Unit ) Rs-460
Todays BUZZ Word SITE SAFETY- 1-One of the most basic things that one can do is wear a hard hat on the job site. 2-Steel-toed boots or shoes are a great way to protect the feet. Face it; we have all stubbed our toe or dropped something on our foot at one time or another. 3-Safety goggles or safety glasses are great for protecting the eyes. 4-Signs are an important part of setting up a safe construction site. 5-There should always be a well-stocked first aid kit on a job site all times. 6-By following a few basic rules can help one to be safe when working in a construction site. Without having or wearing proper safety equipment on a job site can sometimes be the difference between life and death. Remembering these basic things can make many job sites a safer place to work. FACILITIES- 1- Drinking water 2- waiting room 3- security 4- control room 5-utility room
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-09

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bauchakar deepak yuvaraj
Exam No. 13554
Working Day No. 09
Date (DD/MM/YYYY) 18/12/10
Site Reporting Time (HH:MM am/pm) 10am
Site Leaving Time (HH:MM am/pm) 5pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses.
Details of how you Planned & Executed the allotted work 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished
Details of the Construction Materials learned today We learnt about -pop finish work for which white cement is used . -for wall painting tractor emulation.and ace colour paint is used - paving blocks are used for the internal roads - Plastering –cement & sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater is utilised for ground water recharging through the soak pits. utilisation of crushed sand instead of natural sand.
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing: correlating with bye-laws 2)Line out plan:- contents:- a)c-c distance between all columns b)footing details c)R.C.C. column details i.e. size and reinforcement. d)Ground beam and Plinth beam details with floor level
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today They cooperated with us very well. They manage the work properly by giving proper direction to the workers
RATE ANALYSIS (Detailed Stepwise Calculations required) External painting:- painting: Assume 1*12/1000(m) volume of painting= 1*0.012= 0.012m3 cost:0.012*1200=14.4 RS labour=mason1= Rs250 labour= Rs140 total= Rs405 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13
Result of RATE ANALYSIS ( Rs per Unit ) Rs-460
Todays BUZZ Word SITE SAFETY- 1-One of the most basic things that one can do is wear a hard hat on the job site. 2-Steel-toed boots or shoes are a great way to protect the feet. Face it; we have all stubbed our toe or dropped something on our foot at one time or another. 3-Safety goggles or safety glasses are great for protecting the eyes. 4-Signs are an important part of setting up a safe construction site. 5-There should always be a well-stocked first aid kit on a job site all times. 6-By following a few basic rules can help one to be safe when working in a construction site. Without having or wearing proper safety equipment on a job site can sometimes be the difference between life and death. Remembering these basic things can make many job sites a safer place to work. FACILITIES- 1- Drinking water 2- waiting room 3- security 4- control room 5-utility room
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: nikitashinde15@gmail.com
Subject: 13547-10

Company Name S. N. Builders
Project Name & Site Address Animesh nagar, Daduji chaugle nagar,ujlayvadi.
Students Name (Surname_First Name_Middle Name) Shinde nikita eknath
Exam No. 13547
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 8:55am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge To observe- 1.Leveling of drainage pipe 2.Fitting of septic tank.
Details of how you Planned & Executed the allotted work 1.For the purpose of proper slope provide to the drainage line we measure the level of surface by using level tube. 2.That time we observed that surface have not required slop. 3.Then proper slop is provide.
Details of the Construction Procedure / Activity / Technology learned today 1.Cera cladding-cera cladding is done using drilling screw. 2.Wallputti is used before painting.
Details of the Construction Materials learned today 1.Shingles-used for roof covering. 2.Simas half pedestal wash basin. 3.Singel bowl with drain board sink.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1.Proper positions are given to the windows and doors which gives suficient ventilation and sun light,
Details of the Construction / Engineering Drawings observed today 1.Section of plan- Today we observed section plan for banglow number 7 and 8. For each plan there is tthree sections are provided. First section is gives details of staircace. Second is going through toilet. Third is gives idea of extention and balconies. 2.Plumbing and service plans.
Details of the Bye Laws referred today Minimum nominal diameter of pipe shall be 100mm.direction of flow from a branch connection shall not make an angle exeeding 45 degree with the direction of flow in the main pipe.
Details of any Managerial Skill learned today 1.Good communication with customer and us. 2.Good command on labour.
RATE ANALYSIS (Detailed Stepwise Calculations required) For external painting- 1.Primer,1lit=1x250=250 Rs 2.Paint,2lit=2x250=500 Rs 3.Labour=160 Rs Total=910 Rs with CP 20%=182Rs Total=10.92 per sq.ft. =120 Rs per sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 120 Rs
Todays BUZZ Word 1.For the purpose of safety following instruments are provided to workers, heal-met, belt, gumboot, hand glause. mask. 2.Also construction instrument are properly maintained. 3.medicince,firstaid box made available. 4.T.T.injection for every six month.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat,9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-10

Company Name S. N. Builders
Project Name & Site Address Animesh nagar, Daduji chaugle nagar,ujlayvadi.
Students Name (Surname_First Name_Middle Name) Patil sachin dhanaji
Exam No. 13539
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge To observe- 1.Leveling of drainage pipe 2.Fitting of septic tank.
Details of how you Planned & Executed the allotted work 1.For the purpose of proper slope provide to the drainage line we measure the level of surface by using level tube. 2.That time we observed that surface have not required slop. 3.Then proper slop is provide.
Details of the Construction Procedure / Activity / Technology learned today 1.Cera cladding-cera cladding is done using drilling screw. 2.Wallputti is used before painting.
Details of the Construction Materials learned today 1.Shingles-used for roof covering. 2.Simas half pedestal wash basin. 3.Singel bowl with drain board sink.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1.Proper positions are given to the windows and doors which gives suficient ventilation and sun light,
Details of the Construction / Engineering Drawings observed today 1.Section of plan- Today we observed section plan for banglow number 7 and 8. For each plan there is tthree sections are provided. First section is gives details of staircace. Second is going through toilet. Third is gives idea of extention and balconies. 2.Plumbing and service plans.
Details of the Bye Laws referred today Minimum nominal diameter of pipe shall be 100mm.direction of flow from a branch connection shall not make an angle exeeding 45 degree with the direction of flow in the main pipe.
Details of any Managerial Skill learned today 1.Good communication with customer and us. 2.Good command on labour.
RATE ANALYSIS (Detailed Stepwise Calculations required) For external painting- 1.Primer,1lit=1x250=250 Rs 2.Paint,2lit=2x250=500 Rs 3.Labour=160 Rs Total=910 Rs with CP 20%=182Rs Total=10.92 per sq.ft. =120 Rs per sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 120 Rs
Todays BUZZ Word 1.For the purpose of safety following instruments are provided to workers, heal-met, belt, gumboot, hand glause. mask. 2.Also construction instrument are properly maintained. 3.medicince,firstaid box made available. 4.T.T.injection for every six month.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat,9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-10

Company Name S. N. Builders
Project Name & Site Address Animesh nagar, Daduji chaugle nagar,ujlayvadi.
Students Name (Surname_First Name_Middle Name) Patil sangram madhukar
Exam No. 13540
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge To observe- 1.Leveling of drainage pipe 2.Fitting of septic tank.
Details of how you Planned & Executed the allotted work 1.For the purpose of proper slope provide to the drainage line we measure the level of surface by using level tube. 2.That time we observed that surface have not required slop. 3.Then proper slop is provide
Details of the Construction Procedure / Activity / Technology learned today 1.Cera cladding-cera cladding is done using drilling screw. 2.Wallputti is used before painting.
Details of the Construction Materials learned today 1.Shingles-used for roof covering. 2.Simas half pedestal wash basin. 3.Singel bowl with drain board sink
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1.Proper positions are given to the windows and doors which gives suficient ventilation and sun light,
Details of the Construction / Engineering Drawings observed today 1.Section of plan- Today we observed section plan for banglow number 7 and 8. For each plan there is tthree sections are provided. First section is gives details of staircace. Second is going through toilet. Third is gives idea of extention and balconies. 2.Plumbing and service plans.
Details of the Bye Laws referred today Minimum nominal diameter of pipe shall be 100mm.direction of flow from a branch connection shall not make an angle exeeding 45 degree with the direction of flow in the main pipe.
Details of any Managerial Skill learned today 1.Good communication with customer and us. 2.Good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) For external painting- 1.Primer,1lit=1x250=250 Rs 2.Paint,2lit=2x250=500 Rs 3.Labour=160 Rs Total=910 Rs with CP 20%=182Rs Total=10.92 per sq.ft. =120 Rs per sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 120 Rs
Todays BUZZ Word 1.For the purpose of safety following instruments are provided to workers, heal-met, belt, gumboot, hand glause. mask. 2.Also construction instrument are properly maintained. 3.medicince,firstaid box made available. 4.T.T.injection for every six month.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat,9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vishwajit.p09@gmail.com
Subject: 13543-10

Company Name S. N. Builders
Project Name & Site Address Animesh nagar, Daduji chaugle nagar,ujlayvadi.
Students Name (Surname_First Name_Middle Name) Paymal vishwajit shamrao
Exam No. 13543
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge To observe- 1.Leveling of drainage pipe 2.Fitting of septic tank.
Details of how you Planned & Executed the allotted work 1.For the purpose of proper slope provide to the drainage line we measure the level of surface by using level tube. 2.That time we observed that surface have not required slop. 3.Then proper slop is provide
Details of the Construction Procedure / Activity / Technology learned today 1.Cera cladding-cera cladding is done using drilling screw. 2.Wallputti is used before painting.
Details of the Construction Materials learned today 1.Shingles-used for roof covering. 2.Simas half pedestal wash basin. 3.Singel bowl with drain board sink
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1.Proper positions are given to the windows and doors which gives suficient ventilation and sun light,
Details of the Construction / Engineering Drawings observed today 1.Section of plan- Today we observed section plan for banglow number 7 and 8. For each plan there is tthree sections are provided. First section is gives details of staircace. Second is going through toilet. Third is gives idea of extention and balconies. 2.Plumbing and service plans.
Details of the Bye Laws referred today Minimum nominal diameter of pipe shall be 100mm.direction of flow from a branch connection shall not make an angle exeeding 45 degree with the direction of flow in the main pipe.
Details of any Managerial Skill learned today 1.Good communication with customer and us. 2.Good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) For external painting- 1.Primer,1lit=1x250=250 Rs 2.Paint,2lit=2x250=500 Rs 3.Labour=160 Rs Total=910 Rs with CP 20%=182Rs Total=10.92 per sq.ft. =120 Rs per sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 120 Rs
Todays BUZZ Word 1.For the purpose of safety following instruments are provided to workers, heal-met, belt, gumboot, hand glause. mask. 2.Also construction instrument are properly maintained. 3.medicince,firstaid box made available. 4.T.T.injection for every six month.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat,9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: cool.sushant007@gmail.com
Subject: 10880-10

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil sushant digambar
Exam No. 10880
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the painting work.
Details of how you Planned & Executed the allotted work we see the internal painting & the putti work & how the rollers are to be used for fast & smooth apperance .
Details of the Construction Procedure / Activity / Technology learned today HAND ROLLERS ARE USED FOR PAINTING.
Details of the Construction Materials learned today TYPES OF PAINTS & VARIOUS EQUIPMENTS FOR PAINTING.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today STEEL DRAWINGS OF WATER TANK
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) external painting - per sq m 2 coats are given while painting for that rate are as follows. distemper = 0.30 kg = 27 Rs cement primer = 0.32 litre = 20 Rs terpentine = 0.08 litre = 24 Rs labour cost and other equipments = 7 % total cost = 74 Rs per sq. m
Result of RATE ANALYSIS ( Rs per Unit ) 74 RS
Todays BUZZ Word SITE SAFETY 1. HAND GLOVES ARE PROVIDED . 2. HELMETS ARE PROVIDED 3. NETS ARE PROVIDED AROUND THE SCAFFOLDING. FACILITIES PROVIDED 1.TEMPORARY SHEDS FOR LIVING. 2. ELECTRICITY SUPPLY . 3. WATER SUPPLY. 4. TOILET. 5. TEA.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.KETAN CHARAPALE MO.9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: Rathod2211@gmail.com
Subject: 10881-10

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) RATHOD SUNIL.R.
Exam No. 10881
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the painting work.
Details of how you Planned & Executed the allotted work we see the internal painting & the putti work & how the rollers are to be used for fast & smooth apperance .
Details of the Construction Procedure / Activity / Technology learned today HAND ROLLERS ARE USED FOR PAINTING.
Details of the Construction Materials learned today TYPES OF PAINTS & VARIOUS EQUIPMENTS FOR PAINTING.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today STEEL DRAWINGS OF WATER TANK
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) external painting - per sq m 2 coats are given while painting for that rate are as follows. distemper = 0.30 kg = 27 Rs cement primer = 0.32 litre = 20 Rs terpentine = 0.08 litre = 24 Rs labour cost and other equipments = 7 % total cost = 74 Rs per sq. m
Result of RATE ANALYSIS ( Rs per Unit ) 74 RS
Todays BUZZ Word SITE SAFETY 1. HAND GLOVES ARE PROVIDED . 2. HELMETS ARE PROVIDED 3. NETS ARE PROVIDED AROUND THE SCAFFOLDING. FACILITIES PROVIDED 1.TEMPORARY SHEDS FOR LIVING. 2. ELECTRICITY SUPPLY . 3. WATER SUPPLY. 4. TOILET. 5. TEA.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.KETAN CHARAPALE MO.9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: shinde_shital7@yahoo.com
Subject: 10884-10

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) shinde shital vilasrao
Exam No. 10884
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the painting work.
Details of how you Planned & Executed the allotted work we see the internal painting & the putti work & how the rollers are to be used for fast & smooth apperance .
Details of the Construction Procedure / Activity / Technology learned today HAND ROLLERS ARE USED FOR PAINTING.
Details of the Construction Materials learned today TYPES OF PAINTS & VARIOUS EQUIPMENTS FOR PAINTING.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today STEEL DRAWINGS OF WATER TANK
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) external painting - per sq m 2 coats are given while painting for that rate are as follows. distemper = 0.30 kg = 27 Rs cement primer = 0.32 litre = 20 Rs terpentine = 0.08 litre = 24 Rs labour cost and other equipments = 7 % total cost = 74 Rs per sq. m
Result of RATE ANALYSIS ( Rs per Unit ) 74 RS
Todays BUZZ Word SITE SAFETY 1. HAND GLOVES ARE PROVIDED . 2. HELMETS ARE PROVIDED 3. NETS ARE PROVIDED AROUND THE SCAFFOLDING. FACILITIES PROVIDED 1.TEMPORARY SHEDS FOR LIVING. 2. ELECTRICITY SUPPLY . 3. WATER SUPPLY. 4. TOILET. 5. TEA.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.KETAN CHARAPALE MO.9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-10

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) misal swapnil shivaji
Exam No. 10877
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the painting work.
Details of how you Planned & Executed the allotted work we see the internal painting & the putti work & how the rollers are to be used for fast & smooth apperance .
Details of the Construction Procedure / Activity / Technology learned today HAND ROLLERS ARE USED FOR PAINTING.
Details of the Construction Materials learned today TYPES OF PAINTS & VARIOUS EQUIPMENTS FOR PAINTING.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today STEEL DRAWINGS OF WATER TANK
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) external painting - per sq m 2 coats are given while painting for that rate are as follows. distemper = 0.30 kg = 27 Rs cement primer = 0.32 litre = 20 Rs terpentine = 0.08 litre = 24 Rs labour cost and other equipments = 7 % total cost = 74 Rs per sq. m
Result of RATE ANALYSIS ( Rs per Unit ) 74 RS
Todays BUZZ Word SITE SAFETY 1. HAND GLOVES ARE PROVIDED . 2. HELMETS ARE PROVIDED 3. NETS ARE PROVIDED AROUND THE SCAFFOLDING. FACILITIES PROVIDED 1.TEMPORARY SHEDS FOR LIVING. 2. ELECTRICITY SUPPLY . 3. WATER SUPPLY. 4. TOILET. 5. TEA.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.KETAN CHARAPALE MO.9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: shindeamol5255@yahoo.in
Subject: 13546-10

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) shinde amol
Exam No. 13546
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the waterproofing treatment done.
Details of how you Planned & Executed the allotted work we directly consult the waterproofing contractor and discuss about the procedure adopted for waterproofing treatment.
Details of the Construction Procedure / Activity / Technology learned today treatment of tank in two ways 1.box type or rough shahabad treatment.-tile is provided on the walls with gap and in this gap chemical and cement slurry is provided. 2.Crystalline treatment.- holes made in the walls and chemical injected with the pressure and due to this voids are filled with crystalline solids.
Details of the Construction Materials learned today various types of water proofing chemicals.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today details drawing of ground water storage tank
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) external painting - per sq m 2 coats are given while painting for that rate are as follows. distemper = 0.30 kg = 25 Rs cement primer = 0.32 litre = 20 Rs terpentine = 0.08 litre = 20 Rs labour cost and other equipments = 7 % total cost = 70 Rs per sq. m
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word SITE SAFETY 1. HAND GLOVES . 2. HELMETS 3. NETS ARE PROVIDED AROUND THE SCAFFOLDING. FACILITIES PROVIDED 1.TEMPORARY SHELTER. 2. ELECTRICITY . 3. WATER SUPPLY. 4. TOILET. 5. TEA.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-10

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHAIKH RIZWAN KHALIL
Exam No. 13545
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the waterproofing treatment done.
Details of how you Planned & Executed the allotted work we directly consult the waterproofing contractor and discuss about the procedure adopted for waterproofing treatment.
Details of the Construction Procedure / Activity / Technology learned today treatment of tank in two ways 1.box type or rough shahabad treatment.-tile is provided on the walls with gap and in this gap chemical and cement slurry is provided. 2.Crystalline treatment.- holes made in the walls and chemical injected with the pressure and due to this voids are filled with crystalline solids.
Details of the Construction Materials learned today various types of water proofing chemicals.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today details drawing of ground water storage tank
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) external painting - per sq m 2 coats are given while painting for that rate are as follows. distemper = 0.30 kg = 25 Rs cement primer = 0.32 litre = 20 Rs terpentine = 0.08 litre = 20 Rs labour cost and other equipments = 7 % total cost = 70 Rs per sq. m
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word SITE SAFETY 1. HAND GLOVES . 2. HELMETS 3. NETS ARE PROVIDED AROUND THE SCAFFOLDING. FACILITIES PROVIDED 1.TEMPORARY SHELTER. 2. ELECTRICITY . 3. WATER SUPPLY. 4. TOILET. 5. TEA.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-10

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Hasabnis Ketaki Bhagwan
Exam No. 13527
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge > To study the casting of column of second floor. > To study and observe the centering work for third floor. > To study and observe the casting of R.C.C PARDHI(pit) for Lift.
Details of how you Planned & Executed the allotted work We observed how the casting of column is being done. Also observed how they prepared concrete at the site and transferred it with the help of skip and hoist to the second floor.We saw the centering work for third floor. We saw how the labourers were providing stirrups and laying steel bars according to the plans.
Details of the Construction Procedure / Activity / Technology learned today We learnt the process of manufacturing flyash bricks.We studied the process of casting columns. We studied how the centering work is done for third floor.
Details of the Construction Materials learned today Steel bars. Tor steel: 6 mm, 8 mm, 12 mm, 16 mm, 20 mm, 25 mm, 30 mm. Mild steel: 6 mm, 8 mm, 12 mm. Ordinary Portland Cement (O.P.C) – 43 Grade, 53 Grade. Bagalkot Supreme
Details of Environment Caring Technology / Methodology / Procedure / Product learned today If the shuttering is properly sealed by using adhesive or any other materialthe leakage of concrete and water through it may be reduced and economy can be achieved.
Details of the Construction / Engineering Drawings observed today > Plan for second floor. > Plan for third floor showing schedule of beams and columns
Details of the Bye Laws referred today > Minimum width and depth of columns for construction above second floor. > Proportions of different materials for manufacturing concrete on site.
Details of any Managerial Skill learned today > We observed how the site incharge inspected the casting of column work. > We observed how the site incharge checked the centering work. > We observed how the site incharge checked whether the steel provided for column was correct or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for \"EXTERNAL PAINTING\". Approved Apex exterior grade paint. Cost of Paint for 1 litre= Rs.225 = Rs.21 per sq.m Approved quality primer= Rs.80 per litre= Rs.8 per sq.m Birla putty= Rs.6 per sq.m Labour Rs.19 per sq.m Total cost= 21+8+6+19= Rs.54 Add 10% profit=Rs.5.40 Total cost=54+5.40= Rs.59.40 per sq.m= say Rs.60 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.60 per sq.m
Todays BUZZ Word \"SITE SAFETY AND BASIC FACILITY TO WORKERS AT SITE\" SITE SAFETY: 1.The labourers working with electrical fittings should wear proper gloves and they should ensure that the machine they are using is properly insulated. 2.Sand should be kept in buckets for use in case of fire. 3.The labourers which are working on centering work must ensure that the formwork and centering work is properly placed and is firm to provide support. 4.The labourers that work on zulla for painting of exterior walls of building should ensure that the rope is fixed tight or held tight otherwise it may lead to severe injury or even death. 5.The nails which are removed after removal of formwork should be dumped at proper place otherwise they may lead to injury. FACILITIES: 1.The facility of first aid kit should be provided at the site. 2.Emergency contact numbers of Fire fighter,Ambulance,Police must be placed on a board at a central place where it can be easily seen by everybody. 3.Protective footwear should be provided to labourers. 4.Safety Helmets should be provided for labourers where work is going at different levels. 5.Safety belts should be provided to labourers who work on height,exterior sides of the building. 6.Hand gloves used for material handling,gas cutting,welding etc. 7.Safety goggles used for welding,geinding,pavement breaking etc. 8.Gumboots for ashpalting,concreting works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SARVALKAR Cell NO.9822036748.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-10

Company Name V. S. Joshi & Associates
Project Name & Site Address VVishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) janbandhu rakshit janbandhu
Exam No. 10875
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 5.30PM
Details of the Work Allotted to you today by the Site In-Charge 1) to checking the dimensions of beam 2) to checking the dimensions of rcc.septic tank 3) checking how to apply paint on internal wall
Details of how you Planned & Executed the allotted work 1) we seen painting in that first they apply primer on the putty. then finish the wall or rubbed by ghissi. for smooth surface 2) then apply oil paint of one coat on the wall by roller 3) after that the final coat apply 4) then we measure the dimenation of septic tank 5) for beam dimenation we go through by plan sheet
Details of the Construction Procedure / Activity / Technology learned today 1) for apply paint on the wall used rollers consist of long pipe for oprating 2) used steel formwrk except wood material by safety of labour and long time durability
Details of the Construction Materials learned today 1) protect admixture used for casting the rcc beam of septic tank 2) used s.s. fastenings for doors and windows and kitchen trowly
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today 1) we seen the drawing of beam in main building plan . their are many different sizes of beams are provided
Details of the Bye Laws referred today 1) the minimum cler height of canopy be 2.2m 2) for fire protection requirements . the open space on all side up to 6m
Details of any Managerial Skill learned today none
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR EXTERNAL PAINTING\" # A) Application of washable oil Bond Distemper 3 Coat for: 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bedroom = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bathroom = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m B) Deduction = 37 sq.m.....(For doors, windows) Deduct 50 % = 218.21 - 37/2 = 199.71 sq.m C) Material Required : 1. Dry Distemper = 0.2 x 199.71 = 40 kg 2. Glue = 1 kg D) Cost of Material: 1. Dry Distemper = 40 x 430 = 17200/- 2. Glue = 1.36 x 450 = 612/- TOTAL = 17812/- E) Cost Of Labour: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 120 = 1800/- 4. T & P = 1000/- TOTAL = 5000/- F) Total Cost = D + E = 22972/- G) Add 10 % Contractors Profit = 2245.2/- H) Grand Total = 25217/- I) Rate Per sq.m = 155.26/-
Result of RATE ANALYSIS ( Rs per Unit ) 155.26/-
Todays BUZZ Word 1)provided helmet to all workers 2)insurance of workers provided by contractors 3)toilet block provided 4)for living, arrangment of roof given on the site 5)electricity is also provided 6)payment given at the end of week
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge amol mule
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) REDEKAR SHANTANU RAVINDRA
Exam No. 13566
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only.
Result of RATE ANALYSIS ( Rs per Unit ) 61.00 /-
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. VIKRANT PISE. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: rajendrapawar54@gmail.com
Subject: 13542-10

Company Name S. N. Builders
Project Name & Site Address Animesh nagar, Daduji chaugle nagar,ujlayvadi.
Students Name (Surname_First Name_Middle Name) Pawar rajendra eknath
Exam No. 13542
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge To observe- 1.Leveling of drainage pipe 2.Fitting of septic tank.
Details of how you Planned & Executed the allotted work 1.For the purpose of proper slope provide to the drainage line we measure the level of surface by using level tube. 2.That time we observed that surface have not required slop. 3.Then proper slop is provide.
Details of the Construction Procedure / Activity / Technology learned today 1.Cera cladding-cera cladding is done using drilling screw. 2.Wallputti is used before painting
Details of the Construction Materials learned today 1.Shingles-used for roof covering. 2.Simas half pedestal wash basin. 3.Singel bowl with drain board sink.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1.Proper positions are given to the windows and doors which gives suficient ventilation and sun light,
Details of the Construction / Engineering Drawings observed today 1.Section of plan- Today we observed section plan for banglow number 7 and 8. For each plan there is tthree sections are provided. First section is gives details of staircace. Second is going through toilet. Third is gives idea of extention and balconies. 2.Plumbing and service plans.
Details of the Bye Laws referred today Minimum nominal diameter of pipe shall be 100mm.direction of flow from a branch connection shall not make an angle exeeding 45 degree with the direction of flow in the main pipe.
Details of any Managerial Skill learned today 1.Good communication with customer and us. 2.Good command on labour.
RATE ANALYSIS (Detailed Stepwise Calculations required) For external painting- 1.Primer,1lit=1x250=250 Rs 2.Paint,2lit=2x250=500 Rs 3.Labour=160 Rs Total=910 Rs with CP 20%=182Rs Total=10.92 per sq.ft. =120 Rs per sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 120 Rs
Todays BUZZ Word 1.For the purpose of safety following instruments are provided to workers, heal-met, belt, gumboot, hand glause. mask. 2.Also construction instrument are properly maintained. 3.medicince,firstaid box made available. 4.T.T.injection for every six month.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat,9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: patilpratibha7070@yahoo.in
Subject: 10896

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage,sardar park,devkar panand,kolhapur
Students Name (Surname_First Name_Middle Name) patil pratibha dilip
Exam No. 10896
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of starters of the second floor columns on the markings done during the line out, and checking the starters in all respective aspects.
Details of how you Planned & Executed the allotted work We observed the fixing of starter frame having the height of 10cm.we checked the size of column as per drawings given to us. Then we checked the right angle of column, and for cross checking we measured the diagonal distance of column.
Details of the Construction Procedure / Activity / Technology learned today Fixing of centring plates for slab we observed the placing of the spans at the distance of 30cm from the side beams which were supported using the steel props and placed parallel to each other at equal distance above this spans the centring plates were fixed. We also saw the checking level of the centring plates in usual manner.
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not yet adopted
Details of the Construction / Engineering Drawings observed today 1.Center line plan 2.detailed second floor plan
Details of the Bye Laws referred today Size of habitable room- Hall dimensions provided on the site:-3.0*4.0=12sqm As per bye law the minimum area to be provided is 10sqm.
Details of any Managerial Skill learned today Keen inspection of the work going on and maintaining the accuracy in work. Self awareness and checking of unloading of material and maintaining record of it.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for painting external wall “ Dimension of the wall =3.0*6.0m=18sqm=188.28 sqft Quantity of lime for white wash in two coats=1kg Quantity of cement paint in two coats=2.5kg Painter required =2nos “Rate Analysis for external painting using cement paint” (Considering local rates of material) 1. Cost of cement paint=2.5*70=175/-………..(70/- per kg) 2. Cost of lime=1*40=40.....(40/- per kg) 3. Cost of surface cleaning=188.3*3=565/-………………..(3/- per sq.ft) 4. Labour charges=300/-…………(150/- per painter for half day) 5. Total cost=1080/- 6.10% profit of total cost for the contractor=108/- 7. Total cost=1188/- 8. Rate per sq.ft=6.30/-
Result of RATE ANALYSIS ( Rs per Unit ) 6.30/-
Todays BUZZ Word “Site safety and basic facilities provided to the labours” For maintaining the safety of labours our site director has provided the labours with hand gloves and gum boots to Use during concreting.eye protecting goggles are given to the labours which do the cutting of steel bars using the cutter. First aid box with antibiotic tubes tablets, band aid, saffron and glucose packets. The labours are given temporary accommodation near the site. Separate bathroom and w/c are constructed near by for maintaining the sanitation condition. A water tank of 1000litres is given to the labours
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-10

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Shivtare Prabhakar Chandrakant
Exam No. 13569
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge Determination of detailed estimate of BANGLOW. Find out the total cost of banglow. .
Details of how you Planned & Executed the allotted work We complite our work in following steps:- first student find the value of p.c.c. excavation murum filling second student found the p.c.c below flooring brick work third student found the internal plaster external plaster fourth student found the slab beam column .
Details of the Construction Procedure / Activity / Technology learned today 1)How to calculate the estimate 2)Which point have to consider in each value. 3)Direction of estimation . 4)How yo handle D.S.R. .
Details of the Construction Materials learned today IT is not a construction material but very important in the point of view of civil engineering, it is D.S.R. (District schedule rate) .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper estimate of any project is also save the money but also helpful for environment which saves the natural resources also in form of material. .
Details of the Construction / Engineering Drawings observed today Detailed drawing of bangalow detailed R.c.c. drawing .
Details of the Bye Laws referred today Method & procedure of submission of drawing. Step wise distribution of work in municiple council. Drawing sansioning authority.
Details of any Managerial Skill learned today proper management of work is very important in every project which helps to achieve profit & compete project in time. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis Surface area =100 sq m Object cost per sq.m quantity total cost in Rs. RS. Surface finish 11 100 1100 Two coat of 75 100 7500 White wash Two coat of 85 100 8500 Cement colour Labour 33 100 3300 Scaffolding 03 100 300 TOTAL COST IN Rs. = 20700 Cost per sq.m in Rs.= 207
Result of RATE ANALYSIS ( Rs per Unit ) 207
Todays BUZZ Word SITE SAFETY :- Construction engineer must adopt safety precautions as an integral part for Safety of labour and all other working engineers also. For safety of labours following decisions have to taken 1) To eliminate the factors affecting the safety program the program should be discussed to find solutions in between working labour. 2) Proper maintenance have to taken. 3) Proper method have to taken. 4) Proper guide line have to taken . The following sevices should be provided to labours:- 1) Safety goggles 2) Protective footwear 3) Hand gloves 4) Helmet 5) First aid box
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-10

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage,sardar park,devkar panand,kolhapur
Students Name (Surname_First Name_Middle Name) babar moreshwar mahipati
Exam No. 10873
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of starters of the second floor columns on the markings done during the line out, and checking the starters in all respective aspects.
Details of how you Planned & Executed the allotted work We observed the fixing of starter frame having the height of 10cm.we checked the size of column as per drawings given to us. Then we checked the right angle of column, and for cross checking we measured the diagonal distance of column.
Details of the Construction Procedure / Activity / Technology learned today Fixing of centring plates for slab we observed the placing of the spans at the distance of 30cm from the side beams which were supported using the steel props and placed parallel to each other at equal distance above this spans the centring plates were fixed. We also saw the checking level of the centring plates in usual manner.
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not yet adopted
Details of the Construction / Engineering Drawings observed today 1.Center line plan 2.detailed second floor plan
Details of the Bye Laws referred today Size of habitable room- Hall dimensions provided on the site:-3.0*4.0=12sqm As per bye law the minimum area to be provided is 10sqm.
Details of any Managerial Skill learned today Keen inspection of the work going on and maintaining the accuracy in work. Self awareness and checking of unloading of material and maintaining record of it.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for painting external wall “ Dimension of the wall =3.0*6.0m=18sqm=188.28 sqft Quantity of lime for white wash in two coats=1kg Quantity of cement paint in two coats=2.5kg Painter required =2nos “Rate Analysis for external painting using cement paint” (Considering local rates of material) 1. Cost of cement paint=2.5*70=175/-………..(70/- per kg) 2. Cost of lime=1*40=40.....(40/- per kg) 3. Cost of surface cleaning=188.3*3=565/-………………..(3/- per sq.ft) 4. Labour charges=300/-…………(150/- per painter for half day) 5. Total cost=1080/- 6.10% profit of total cost for the contractor=108/- 7. Total cost=1188/- 8. Rate per sq.ft=6.30/-
Result of RATE ANALYSIS ( Rs per Unit ) 6.30/-
Todays BUZZ Word “Site safety and basic facilities provided to the labours” For maintaining the safety of labours our site director has provided the labours with hand gloves and gum boots to Use during concreting.eye protecting goggles are given to the labours which do the cutting of steel bars using the cutter. First aid box with antibiotic tubes tablets, band aid, saffron and glucose packets. The labours are given temporary accommodation near the site. Separate bathroom and w/c are constructed near by for maintaining the sanitation condition. A water tank of 1000litres is given to the labours
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vishalsapakal124@gmail.com
Subject: 10882-10

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage,sardar park,devkar panand,kolhapur
Students Name (Surname_First Name_Middle Name) sapakal vishal manohar
Exam No. 10882
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of starters of the second floor columns on the markings done during the line out, and checking the starters in all respective aspects.
Details of how you Planned & Executed the allotted work We observed the fixing of starter frame having the height of 10cm.we checked the size of column as per drawings given to us. Then we checked the right angle of column, and for cross checking we measured the diagonal distance of column.
Details of the Construction Procedure / Activity / Technology learned today Fixing of centring plates for slab we observed the placing of the spans at the distance of 30cm from the side beams which were supported using the steel props and placed parallel to each other at equal distance above this spans the centring plates were fixed. We also saw the checking level of the centring plates in usual manner.
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not yet adopted
Details of the Construction / Engineering Drawings observed today 1.Center line plan 2.detailed second floor plan
Details of the Bye Laws referred today Size of habitable room- Hall dimensions provided on the site:-3.0*4.0=12sqm As per bye law the minimum area to be provided is 10sqm.
Details of any Managerial Skill learned today Keen inspection of the work going on and maintaining the accuracy in work. Self awareness and checking of unloading of material and maintaining record of it.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for painting external wall “ Dimension of the wall =3.0*6.0m=18sqm=188.28 sqft Quantity of lime for white wash in two coats=1kg Quantity of cement paint in two coats=2.5kg Painter required =2nos “Rate Analysis for external painting using cement paint” (Considering local rates of material) 1. Cost of cement paint=2.5*70=175/-………..(70/- per kg) 2. Cost of lime=1*40=40.....(40/- per kg) 3. Cost of surface cleaning=188.3*3=565/-………………..(3/- per sq.ft) 4. Labour charges=300/-…………(150/- per painter for half day) 5. Total cost=1080/- 6.10% profit of total cost for the contractor=108/- 7. Total cost=1188/- 8. Rate per sq.ft=6.30/-
Result of RATE ANALYSIS ( Rs per Unit ) 6.30/-
Todays BUZZ Word “Site safety and basic facilities provided to the labours” For maintaining the safety of labours our site director has provided the labours with hand gloves and gum boots to Use during concreting.eye protecting goggles are given to the labours which do the cutting of steel bars using the cutter. First aid box with antibiotic tubes tablets, band aid, saffron and glucose packets. The labours are given temporary accommodation near the site. Separate bathroom and w/c are constructed near by for maintaining the sanitation condition. A water tank of 1000litres is given to the labours
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-10

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage,sardar park,devkar panand,kolhapur
Students Name (Surname_First Name_Middle Name) yadav hrishikesh manohar
Exam No. 10885
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of starters of the second floor columns on the markings done during the line out, and checking the starters in all respective aspects.
Details of how you Planned & Executed the allotted work We observed the fixing of starter frame having the height of 10cm.we checked the size of column as per drawings given to us. Then we checked the right angle of column, and for cross checking we measured the diagonal distance of column.
Details of the Construction Procedure / Activity / Technology learned today Fixing of centring plates for slab we observed the placing of the spans at the distance of 30cm from the side beams which were supported using the steel props and placed parallel to each other at equal distance above this spans the centring plates were fixed. We also saw the checking level of the centring plates in usual manner.
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not yet adopted
Details of the Construction / Engineering Drawings observed today 1.Center line plan 2.detailed second floor plan
Details of the Bye Laws referred today Size of habitable room- Hall dimensions provided on the site:-3.0*4.0=12sqm As per bye law the minimum area to be provided is 10sqm.
Details of any Managerial Skill learned today Keen inspection of the work going on and maintaining the accuracy in work. Self awareness and checking of unloading of material and maintaining record of it.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for painting external wall “ Dimension of the wall =3.0*6.0m=18sqm=188.28 sqft Quantity of lime for white wash in two coats=1kg Quantity of cement paint in two coats=2.5kg Painter required =2nos “Rate Analysis for external painting using cement paint” (Considering local rates of material) 1. Cost of cement paint=2.5*70=175/-………..(70/- per kg) 2. Cost of lime=1*40=40.....(40/- per kg) 3. Cost of surface cleaning=188.3*3=565/-………………..(3/- per sq.ft) 4. Labour charges=300/-…………(150/- per painter for half day) 5. Total cost=1080/- 6.10% profit of total cost for the contractor=108/- 7. Total cost=1188/- 8. Rate per sq.ft=6.30/-
Result of RATE ANALYSIS ( Rs per Unit ) 6.30/-
Todays BUZZ Word “Site safety and basic facilities provided to the labours” For maintaining the safety of labours our site director has provided the labours with hand gloves and gum boots to Use during concreting.eye protecting goggles are given to the labours which do the cutting of steel bars using the cutter. First aid box with antibiotic tubes tablets, band aid, saffron and glucose packets. The labours are given temporary accommodation near the site. Separate bathroom and w/c are constructed near by for maintaining the sanitation condition. A water tank of 1000litres is given to the labours
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-10

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Sutar Namdev Rangnath
Exam No. 13571
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge Determination of detailed estimate of BANGLOW. Find out the total cost of banglow. .
Details of how you Planned & Executed the allotted work We complite our work in following steps:- first student find the value of p.c.c. excavation murum filling second student found the p.c.c below flooring brick work third student found the internal plaster external plaster fourth student found the slab beam column .
Details of the Construction Procedure / Activity / Technology learned today 1)How to calculate the estimate 2)Which point have to consider in each value. 3)Direction of estimation . 4)How yo handle D.S.R. .
Details of the Construction Materials learned today IT is not a construction material but very important in the point of view of civil engineering, it is D.S.R. (District schedule rate) .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper estimate of any project is also save the money but also helpful for environment which saves the natural resources also in form of material. .
Details of the Construction / Engineering Drawings observed today Detailed drawing of bangalow detailed R.c.c. drawing .
Details of the Bye Laws referred today Method & procedure of submission of drawing. Step wise distribution of work in municiple council. Drawing sansioning authority. .
Details of any Managerial Skill learned today proper management of work is very important in every project which helps to achieve profit & compete project in time. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis Surface area =100 sq m Object cost per sq.m quantity total cost in Rs. RS. Surface finish 11 100 1100 Two coat of 75 100 7500 White wash Two coat of 85 100 8500 Cement colour Labour 33 100 3300 Scaffolding 03 100 300 TOTAL COST IN Rs. = 20700 Cost per sq.m in Rs.= 207
Result of RATE ANALYSIS ( Rs per Unit ) 207
Todays BUZZ Word SITE SAFETY :- Construction engineer must adopt safety precautions as an integral part for Safety of labour and all other working engineers also. For safety of labours following decisions have to taken 1) To eliminate the factors affecting the safety program the program should be discussed to find solutions in between working labour. 2) Proper maintenance have to taken. 3) Proper method have to taken. 4) Proper guide line have to taken . The following sevices should be provided to labours:- 1) Safety goggles 2) Protective footwear 3) Hand gloves 4) Helmet 5) First aid box
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: salmanbaig18@gmail.com
Subject: 10888-10

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage,sardar park,devkar panand,kolhapur
Students Name (Surname_First Name_Middle Name) Baig salman samd
Exam No. 10888
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of starters of the second floor columns on the markings done during the line out, and checking the starters in all respective aspects.
Details of how you Planned & Executed the allotted work We observed the fixing of starter frame having the height of 10cm.we checked the size of column as per drawings given to us. Then we checked the right angle of column, and for cross checking we measured the diagonal distance of column.
Details of the Construction Procedure / Activity / Technology learned today Fixing of centring plates for slab we observed the placing of the spans at the distance of 30cm from the side beams which were supported using the steel props and placed parallel to each other at equal distance above this spans the centring plates were fixed. We also saw the checking level of the centring plates in usual manner.
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not yet adopted
Details of the Construction / Engineering Drawings observed today 1.Center line plan 2.detailed second floor plan
Details of the Bye Laws referred today Size of habitable room- Hall dimensions provided on the site:-3.0*4.0=12sqm As per bye law the minimum area to be provided is 10sqm.
Details of any Managerial Skill learned today Keen inspection of the work going on and maintaining the accuracy in work. Self awareness and checking of unloading of material and maintaining record of it.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for painting external wall “ Dimension of the wall =3.0*6.0m=18sqm=188.28 sqft Quantity of lime for white wash in two coats=1kg Quantity of cement paint in two coats=2.5kg Painter required =2nos “Rate Analysis for external painting using cement paint” (Considering local rates of material) 1. Cost of cement paint=2.5*70=175/-………..(70/- per kg) 2. Cost of lime=1*40=40.....(40/- per kg) 3. Cost of surface cleaning=188.3*3=565/-………………..(3/- per sq.ft) 4. Labour charges=300/-…………(150/- per painter for half day) 5. Total cost=1080/- 6.10% profit of total cost for the contractor=108/- 7. Total cost=1188/- 8. Rate per sq.ft=6.30/-
Result of RATE ANALYSIS ( Rs per Unit ) 6.30/-
Todays BUZZ Word “Site safety and basic facilities provided to the labours” For maintaining the safety of labours our site director has provided the labours with hand gloves and gum boots to Use during concreting.eye protecting goggles are given to the labours which do the cutting of steel bars using the cutter. First aid box with antibiotic tubes tablets, band aid, saffron and glucose packets. The labours are given temporary accommodation near the site. Separate bathroom and w/c are constructed near by for maintaining the sanitation condition. A water tank of 1000litres is given to the labours
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 13567-10

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge Determination of detailed estimate of BANGLOW. Find out the total cost of banglow. .
Details of how you Planned & Executed the allotted work We complite our work in following steps:- first student find the value of p.c.c. excavation murum filling second student found the p.c.c below flooring brick work third student found the internal plaster external plaster fourth student found the slab beam column .
Details of the Construction Procedure / Activity / Technology learned today 1)How to calculate the estimate 2)Which point have to consider in each value. 3)Direction of estimation . 4)How yo handle D.S.R. .
Details of the Construction Materials learned today IT is not a construction material but very important in the point of view of civil engineering, it is D.S.R. (District schedule rate) .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper estimate of any project is also save the money but also helpful for environment which saves the natural resources also in form of material. .
Details of the Construction / Engineering Drawings observed today Detailed drawing of bangalow detailed R.c.c. drawing .
Details of the Bye Laws referred today Method & procedure of submission of drawing. Step wise distribution of work in municiple council. Drawing sansioning authority.
Details of any Managerial Skill learned today proper management of work is very important in every project which helps to achieve profit & compete project in time. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis Surface area =100 sq m Object cost per sq.m quantity total cost in Rs. RS. Surface finish 11 100 1100 Two coat of 75 100 7500 White wash Two coat of 85 100 8500 Cement colour Labour 33 100 3300 Scaffolding 03 100 300 TOTAL COST IN Rs. = 20700 Cost per sq.m in Rs.= 207
Result of RATE ANALYSIS ( Rs per Unit ) RS.207.00
Todays BUZZ Word SITE SAFETY :- Construction engineer must adopt safety precautions as an integral part for Safety of labour and all other working engineers also. For safety of labours following decisions have to taken 1) To eliminate the factors affecting the safety program the program should be discussed to find solutions in between working labour. 2) Proper maintenance have to taken. 3) Proper method have to taken. 4) Proper guide line have to taken . The following sevices should be provided to labours:- 1) Safety goggles 2) Protective footwear 3) Hand gloves 4) Helmet 5) First aid box
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bhalmal
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-10

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Patil Vrishali Vitthal
Exam No. 13541
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.00pm.
Details of the Work Allotted to you today by the Site In-Charge to observe the startup setting for columns
Details of how you Planned & Executed the allotted work we get the slab dimention plan ,from it we fix the column position on the slab floor. we distribute our work in part and execut allouted work
Details of the Construction Procedure / Activity / Technology learned today adition of steel bars to increase the column height
Details of the Construction Materials learned today starter- it is used to increase the fixetion of column at its own place
Details of Environment Caring Technology / Methodology / Procedure / Product learned today all the brocken arrows are burid in feeling to reduce the env.waste
Details of the Construction / Engineering Drawings observed today drawing of slab dimention-it consist of all the dimentions of beams ,columns,hidden beams
Details of the Bye Laws referred today thickness of slab should be min.150mm. rise of step =min.150mm. tread=min 250mm.
Details of any Managerial Skill learned today polliteness and helpfull,punctual
RATE ANALYSIS (Detailed Stepwise Calculations required) consider area to be painted=1 brass amount of white wash=0.5 lit=150Rs. amount of oil paint =1.5 lit.=400Rs. no. of coats=4 labour cost per brass 100 Rs. contractor profit 15%=97.5 Rs. total ammount required for per brass =747.5 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 747.5 Rs.for one brass
Todays BUZZ Word following wears should made mandatory to workers- 1.hand gloves 2.helmate 3.gum boot 4.goggle provided fasilities- 1.sanitory 2.living hutes 3.fresh water supply for drinking
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: prasadkharat@ymail.com
Subject: 13531-10

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Prasad Ramachandra
Exam No. 13531
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.00pm.
Details of the Work Allotted to you today by the Site In-Charge to observe the startup setting for columns
Details of how you Planned & Executed the allotted work we get the slab dimention plan ,from it we fix the column position on the slab floor. we distribute our work in part and execut allouted work
Details of the Construction Procedure / Activity / Technology learned today adition of steel bars to increase the column height
Details of the Construction Materials learned today starter- it is used to increase the fixetion of column at its own place
Details of Environment Caring Technology / Methodology / Procedure / Product learned today all the brocken arrows are burid in feeling to reduce the env.waste
Details of the Construction / Engineering Drawings observed today drawing of slab dimention-it consist of all the dimentions of beams ,columns,hidden beams
Details of the Bye Laws referred today thickness of slab should be min.150mm. rise of step =min.150mm. tread=min 250mm.
Details of any Managerial Skill learned today polliteness and helpfull,punctual
RATE ANALYSIS (Detailed Stepwise Calculations required) consider area to be painted=1 brass amount of white wash=0.5 lit=150Rs. amount of oil paint =1.5 lit.=400Rs. no. of coats=4 labour cost per brass 100 Rs. contractor profit 15%=97.5 Rs. total ammount required for per brass =747.5 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 747.5 Rs.for one brass
Todays BUZZ Word following wears should made mandatory to workers- 1.hand gloves 2.helmate 3.gum boot 4.goggle provided fasilities- 1.sanitory 2.living hutes 3.fresh water supply for drinking
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-10

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Lad Manoj Sadashiv
Exam No. 13534
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.00pm.
Details of the Work Allotted to you today by the Site In-Charge to observe the startup setting for columns
Details of how you Planned & Executed the allotted work we get the slab dimention plan ,from it we fix the column position on the slab floor. we distribute our work in part and execut allouted work
Details of the Construction Procedure / Activity / Technology learned today adition of steel bars to increase the column height
Details of the Construction Materials learned today starter- it is used to increase the fixetion of column at its own place
Details of Environment Caring Technology / Methodology / Procedure / Product learned today all the brocken arrows are burid in feeling to reduce the env.waste
Details of the Construction / Engineering Drawings observed today drawing of slab dimention-it consist of all the dimentions of beams ,columns,hidden beams
Details of the Bye Laws referred today thickness of slab should be min.150mm. rise of step =min.150mm. tread=min 250mm.
Details of any Managerial Skill learned today polliteness and helpfull,punctual
RATE ANALYSIS (Detailed Stepwise Calculations required) consider area to be painted=1 brass amount of white wash=0.5 lit=150Rs. amount of oil paint =1.5 lit.=400Rs. no. of coats=4 labour cost per brass 100 Rs. contractor profit 15%=97.5 Rs. total ammount required for per brass =747.5 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 747.5 Rs.for one brass
Todays BUZZ Word following wears should made mandatory to workers- 1.hand gloves 2.helmate 3.gum boot 4.goggle provided fasilities- 1.sanitory 2.living hutes 3.fresh water supply for drinking
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: rameshkharat1987@gmail.com
Subject: 13532-10

Company Name Rajesh Constructions
Project Name & Site Address cloude 9
Students Name (Surname_First Name_Middle Name) Kharat Ramesh Laxman
Exam No. 13532
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the startup setting for columns
Details of how you Planned & Executed the allotted work we get the slab dimention plan ,from it we fix the column position on the slab floor. we distribute our work in part and execut allouted work
Details of the Construction Procedure / Activity / Technology learned today adition of steel bars to increase the column height
Details of the Construction Materials learned today starter- it is used to increase the fixetion of column at its own place
Details of Environment Caring Technology / Methodology / Procedure / Product learned today all the brocken arrows are burid in feeling to reduce the env.waste
Details of the Construction / Engineering Drawings observed today drawing of slab dimention-it consist of all the dimentions of beams ,columns,hidden beams
Details of the Bye Laws referred today thickness of slab should be min.150mm. rise of step =min.150mm. tread=min 250mm.
Details of any Managerial Skill learned today polliteness and helpfull,punctual
RATE ANALYSIS (Detailed Stepwise Calculations required) consider area to be painted=1 brass amount of white wash=0.5 lit=150Rs. amount of oil paint =1.5 lit.=400Rs. no. of coats=4 labour cost per brass 100 Rs. contractor profit 15%=97.5 Rs. total ammount required for per brass =747.5 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 747.5 Rs.for one brass
Todays BUZZ Word following wears should made mandatory to workers- 1.hand gloves 2.helmate 3.gum boot 4.goggle provided fasilities- 1.sanitory 2.living hutes 3.fresh water supply for drinking
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-10

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kolekar Shyam Suryakant
Exam No. 13533
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.00pm.
Details of the Work Allotted to you today by the Site In-Charge to observe the startup setting for columns
Details of how you Planned & Executed the allotted work we get the slab dimention plan ,from it we fix the column position on the slab floor. we distribute our work in part and execut allouted work
Details of the Construction Procedure / Activity / Technology learned today adition of steel bars to increase the column height
Details of the Construction Materials learned today starter- it is used to increase the fixetion of column at its own place
Details of Environment Caring Technology / Methodology / Procedure / Product learned today all the brocken arrows are burid in feeling to reduce the env.waste
Details of the Construction / Engineering Drawings observed today drawing of slab dimention-it consist of all the dimentions of beams ,columns,hidden beams
Details of the Bye Laws referred today thickness of slab should be min.150mm. rise of step =min.150mm. tread=min 250mm.
Details of any Managerial Skill learned today polliteness and helpfull,punctual
RATE ANALYSIS (Detailed Stepwise Calculations required) consider area to be painted=1 brass amount of white wash=0.5 lit=150Rs. amount of oil paint =1.5 lit.=400Rs. no. of coats=4 labour cost per brass 100 Rs. contractor profit 15%=97.5 Rs. total ammount required for per brass =747.5 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 747.5 Rs.for one brass
Todays BUZZ Word following wears should made mandatory to workers- 1.hand gloves 2.helmate 3.gum boot 4.goggle provided fasilities- 1.sanitory 2.living hutes 3.fresh water supply for drinking
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-10

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Swapnil Ashok
Exam No. 13529
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to see how the work of foundation is done.
Details of how you Planned & Executed the allotted work firstly a ditch is created with the help of jcb machine or manually. then pcc bed is created. then stepped footing or pile footing is done.
Details of the Construction Procedure / Activity / Technology learned today construction of the underground water tank.
Details of the Construction Materials learned today pvc pipes 75 mm,100mm.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today column drawings.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should get the work completed from the workers by remaining present at the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) External; painting: 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.1 liter = 30.00 Rs Labour cost and other equipments = 7% TOTAL = 80.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 80
Todays BUZZ Word safety precautions: 1)helmet-a helmet should be used to prevent accidents after falling down or if something falls in the head. 2)Hand gloves-hand should be used while mixing of concrete, so that the cement will not have any reaction over the skin.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-10

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Dsouz Agnel Santan
Exam No. 13524
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to see how the work of foundation is done.
Details of how you Planned & Executed the allotted work firstly a ditch is created with the help of jcb machine or manually. then pcc bed is created. then stepped footing or pile footing is done.
Details of the Construction Procedure / Activity / Technology learned today construction of the underground water tank.
Details of the Construction Materials learned today pvc pipes 75 mm,100mm.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today column drawings.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should get the work completed from the workers by remaining present at the site
RATE ANALYSIS (Detailed Stepwise Calculations required) External; painting: 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.1 liter = 30.00 Rs Labour cost and other equipments = 7% TOTAL = 80.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 80
Todays BUZZ Word safety precautions: 1)helmet-a helmet should be used to prevent accidents after falling down or if something falls in the head. 2)Hand gloves-hand should be used while mixing of concrete, so that the cement will not have any reaction over the skin.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-10

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Nilam Jaywant
Exam No. 13528
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to see how the work of foundation is done.
Details of how you Planned & Executed the allotted work firstly a ditch is created with the help of jcb machine or manually. then pcc bed is created. then stepped footing or pile footing is done.
Details of the Construction Procedure / Activity / Technology learned today construction of the underground water tank.
Details of the Construction Materials learned today pvc pipes 75 mm,100mm.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today column drawings.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should get the work completed from the workers by remaining present at the site
RATE ANALYSIS (Detailed Stepwise Calculations required) External; painting: 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.1 liter = 30.00 Rs Labour cost and other equipments = 7% TOTAL = 80.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 80
Todays BUZZ Word safety precautions: 1)helmet-a helmet should be used to prevent accidents after falling down or if something falls in the head. 2)Hand gloves-hand should be used while mixing of concrete, so that the cement will not have any reaction over the skin.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-10

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SALOKHE SUDARSHAN ANIL
Exam No. 13544
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the waterproofing treatment done.
Details of how you Planned & Executed the allotted work we directly consult the waterproofing contractor and discuss about the procedure adopted for waterproofing treatment.
Details of the Construction Procedure / Activity / Technology learned today treatment of tank in two ways 1.box type or rough shahabad treatment.-tile is provided on the walls with gap and in this gap chemical and cement slurry is provided. 2.Crystalline treatment.- holes made in the walls and chemical injected with the pressure and due to this voids are filled with crystalline solids.
Details of the Construction Materials learned today various types of water proofing chemicals.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today details drawing of ground water storage tank
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) external painting - per sq m 2 coats are given while painting for that rate are as follows. distemper = 0.30 kg = 25 Rs cement primer = 0.32 litre = 20 Rs terpentine = 0.08 litre = 20 Rs labour cost and other equipments = 7 % total cost = 70 Rs per sq. m
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word SITE SAFETY 1. HAND GLOVES . 2. HELMETS 3. NETS ARE PROVIDED AROUND THE SCAFFOLDING. FACILITIES PROVIDED 1.TEMPORARY SHELTER. 2. ELECTRICITY . 3. WATER SUPPLY. 4. TOILET. 5. TEA.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-10

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) fulari sujata shankar
Exam No. 13559
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 10.00am
Site Leaving Time (HH:MM am/pm) 05.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements. .
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished, .
Details of the Construction Materials learned today 1. Use of waterproofing chemical while concreteing algae proof 200 ml. 2. Different types of bricks. 1. Hollow Bricks for temporary structure. 2. Wire cut Bricks for attractive elevation and good strength. 3. Cement 43 grade Bagalkot supreme. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today We discussed about waste water treatment plant which treat the water from w.c. & bath. This plant is not being implemented now . But planned. .
Details of the Construction / Engineering Drawings observed today contents:- 1)c-c distance between all columns 2)footing details 3)R.C.C. column details i.e. size and reinforcement. 4)Ground beam and Plinth beam details with floor level ..
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur. .
Details of any Managerial Skill learned today 1. The site incharge inspected saw the concreteing process going on. 2. The site incharge checked the propotions of different materials used. 3. The site incharge kept a proper record of total quantity .
RATE ANALYSIS (Detailed Stepwise Calculations required) Providing applying three coats of washable cement colour over 2 coat of primer including crack filling by putty etc. complete. 1 Good quality primer= 0.2 kg per sq.m @ Rs.120= 0.2*120= Rs.24 Crack filling by putty= 0.30 kg per sq.m@ Rs.60 per kg= 0.30*60= Rs.18 Sand paper 120 no.= Rs.6 per sq.m cement colour = 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.7 per sq.m Labour for cement for 2 coats= Rs.20per sq.m Total cost= 24+18+6+18+7+20= Rs.93 Add 10% Profit= Rs 9.30 Total cost per sq.m= 93+9.30= Rs.102.30= say Rs.105 per sq.m Result of RATE ANALYSIS ( Rs per Unit ): Rs.105 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.105 per sq.m
Todays BUZZ Word SITE SAFTEY:-following saftey measure are taken by construction builders 1) to provide safety belts incase of big height buildungs then net is provided. 2) labour compensation act. 3) to provide helmate,handglows,shoes to the workers. 4) to provide labour insurance life plan. 5) to provide proper tools and plants,bracing. BASIC FACILITIS:- drinking water jar . labour kids sitting place. toilet arrangement. scooter parking arrangement.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-10

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SINGH RAJAN RAJENDRA BAHADUR
Exam No. 13548
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the waterproofing treatment done.
Details of how you Planned & Executed the allotted work we directly consult the waterproofing contractor and discuss about the procedure adopted for waterproofing treatment.
Details of the Construction Procedure / Activity / Technology learned today treatment of tank in two ways 1.box type or rough shahabad treatment.-tile is provided on the walls with gap and in this gap chemical and cement slurry is provided. 2.Crystalline treatment.- holes made in the walls and chemical injected with the pressure and due to this voids are filled with crystalline solids.
Details of the Construction Materials learned today various types of water proofing chemicals.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today details drawing of ground water storage tank
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today NONE
RATE ANALYSIS (Detailed Stepwise Calculations required) external painting - per sq m 2 coats are given while painting for that rate are as follows. distemper = 0.30 kg = 25 Rs cement primer = 0.32 litre = 20 Rs terpentine = 0.08 litre = 20 Rs labour cost and other equipments = 7 % total cost = 70 Rs per sq. m
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word SITE SAFETY 1. HAND GLOVES . 2. HELMETS 3. NETS ARE PROVIDED AROUND THE SCAFFOLDING. FACILITIES PROVIDED 1.TEMPORARY SHELTER. 2. ELECTRICITY . 3. WATER SUPPLY. 4. TOILET. 5. TEA.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-10

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to see how the work of foundation is done.
Details of how you Planned & Executed the allotted work firstly a ditch is created with the help of jcb machine or manually. then pcc bed is created. then stepped footing or pile footing is done.
Details of the Construction Procedure / Activity / Technology learned today construction of the underground water tank.
Details of the Construction Materials learned today pvc pipes 75 mm,100mm.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today column drawings.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should get the work completed from the workers by remaining present at the site
RATE ANALYSIS (Detailed Stepwise Calculations required) External; painting: 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.1 liter = 30.00 Rs Labour cost and other equipments = 7% TOTAL = 80.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 80
Todays BUZZ Word safety precautions: 1)helmet-a helmet should be used to prevent accidents after falling down or if something falls in the head. 2)Hand gloves-hand should be used while mixing of concrete, so that the cement will not have any reaction over the skin.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the form work of R.C.C. staircase for wing D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carefully check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today CONCRETE Cement, sand , aggregate , and water STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. •Admixture- super plasticizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly Ash used for concreting of R.C.C. work, so that directly affecting on increasing strength of concrete and reduce SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today •Plan of R.C.C. stair case and beam •Drawing of R.C.C. column. •Drawing of footing. •Slab reinforcement drawing •Cantilever slab drawing.
Details of the Bye Laws referred today •The max. height shall be 1.5 m above the center line of the front street. •The compound wall up to 2.4m height may be permitted if the top 0.9m is of open construction. •In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today •Check the daily progress report . •Remain present for all types of concreting work •Average the next day work in advanced •Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For external Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement pain Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only .
Result of RATE ANALYSIS ( Rs per Unit ) 61.00/-
Todays BUZZ Word •Determine and incorporate a suitable course of action in day to day activity for the effective implementation of safety program. •Identify any unsafe working condition / location by inspecting the site twice a week . •Investigate all accidents and reinforce the safety program with additional precautions •Keep the first-aid / firefighting equipment / safety appliances on the site and ensure that they are maintained in good condition. •Site supervisors should give safety instructions to the workers every day. EQUIPMENTS- •Safety helmets •Safety belts •Hand gloves •Safety goggles •Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: agydsouza@gmail.com
Subject: 13524-10

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Dsouz Agnel Santan
Exam No. 13524
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to see how the work of foundation is done.
Details of how you Planned & Executed the allotted work firstly a ditch is created with the help of jcb machine or manually. then pcc bed is created. then stepped footing or pile footing is done.
Details of the Construction Procedure / Activity / Technology learned today construction of the underground water tank.
Details of the Construction Materials learned today pvc pipes 75 mm,100mm.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today column drawings.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should get the work completed from the workers by remaining present at the site
RATE ANALYSIS (Detailed Stepwise Calculations required) External; painting: 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.1 liter = 30.00 Rs Labour cost and other equipments = 7% TOTAL = 80.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 80
Todays BUZZ Word safety precautions: 1)helmet-a helmet should be used to prevent accidents after falling down or if something falls in the head. 2)Hand gloves-hand should be used while mixing of concrete, so that the cement will not have any reaction over the skin.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-10

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to see how the work of foundation is done.
Details of how you Planned & Executed the allotted work firstly a ditch is created with the help of jcb machine or manually. then pcc bed is created. then stepped footing or pile footing is done.
Details of the Construction Procedure / Activity / Technology learned today construction of the underground water tank.
Details of the Construction Materials learned today pvc pipes 75 mm,100mm.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today column drawings.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should get the work completed from the workers by remaining present at the site
RATE ANALYSIS (Detailed Stepwise Calculations required) External; painting: 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.1 liter = 30.00 Rs Labour cost and other equipments = 7% TOTAL = 80.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 80
Todays BUZZ Word safety precautions: 1)helmet-a helmet should be used to prevent accidents after falling down or if something falls in the head. 2)Hand gloves-hand should be used while mixing of concrete, so that the cement will not have any reaction over the skin.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir: mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near JayPrabha Studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DEVKAR VIKRAM DILIP
Exam No. 13523
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge 1. To see and study the casting of column of second floor. 2. To see and study the centering work for third floor. 3. To see and study the casting of R.C.C PARDHI(pit) for Lift.
Details of how you Planned & Executed the allotted work We went on site in group.We saw the casting of column going on and how they manufactured concrete at the site and transferred it with the help of skip and hoist to the second floor.We saw the centering work for third floor we went on the top of centering work.We saw how the labourers were providing stirrups,laying of steel bars according to the plans.
Details of the Construction Procedure / Activity / Technology learned today We learnt the process of manufacturing flyash bricks.We studied the procedure of casting columns. We studied how the centering work is done for third floor.
Details of the Construction Materials learned today Steel bars. Tor steel: 6 mm, 8 mm, 12 mm, 16 mm, 20 mm, 25 mm, 30 mm. Mild steel: 6 mm, 8 mm, 12 mm. Ordinary Portland Cement (O.P.C) = 43 Grade, 53 Grade. Bagalkot Supreme
Details of Environment Caring Technology / Methodology / Procedure / Product learned today If the shuttering is properly sealed by using adhesive or any other thing the leakage of concrete and water through it may be reduced and economy can be achieved.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for third floor showing schedule of beams and columns.
Details of the Bye Laws referred today 1.Minimum width and depth of columns for construction above second floor. 2.Proportions of different materials for manufacturing concrete on site.
Details of any Managerial Skill learned today 1.The site incharge inspected the casting of column going on. 2.The site incharge checked the centering work. 3.The site incharge checked whether the steel provided for column was correct or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for \"EXTERNAL PAINTING\". Approved Apex exterior grade paint. Cost of Paint for 1 litre= Rs.225 = Rs.21 per sq.m Approved quality primer= Rs.80 per litre= Rs.8 per sq.m Birla putty= Rs.6 per sq.m Labour Rs.19 per sq.m Total cost= 21+8+6+19= Rs.54 Add 10% profit=Rs.5.40 Total cost=54+5.40= Rs.59.40 per sq.m= say Rs.60 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.60 per sq.m
Todays BUZZ Word \"SITE SAFETY AND BASIC FACILITY TO WORKERS AT SITE\" SITE SAFETY: 1.The labourers working with electrical fittings should wear proper gloves and they should ensure that the machine they are using is properly insulated. 2.Sand should be kept in buckets for use in case of fire. 3.The labourers which are working on centering work must be ensured that the formwork and centering work is properly placed at is firm to provide support. 4.The labours that work on zulla for painting of exterior walls of building should ensure that the rope is fixed tight or held tight otherwise it may lead to severe injury or even death. 5.The nails which are removed after removal of formwork should be dumped at proper place otherwise they may lead to injury. FACILITIES: 1.The facility of first aid kit should be provided at the site. 2.Emergency contact numbers of Fire fighter,Ambulance,Police must be placed on a board at a central place where it can be easily detected. 3.Protective footwear should be provided to labourers. 4.Safety Helmets should be provided for labourers where work is going at different levels. 5.Safety belts should be provided to labourers that work on height,exterior sides of the building. 6.Hand gloves used for material handling,gas cutting,welding etc. 7.Safety goggles used for welding,geinding,pavement breaking etc. 8.Gumboots for ashpalting,concreting works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SARVALKAR PH NO.9822036748.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-10

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4
Details of the Work Allotted to you today by the Site In-Charge to see how the work of foundation is done.
Details of how you Planned & Executed the allotted work firstly a ditch is created with the help of jcb machine or manually. then pcc bed is created. then stepped footing or pile footing is done.
Details of the Construction Procedure / Activity / Technology learned today construction of the underground water tank.
Details of the Construction Materials learned today pvc pipes 75 mm,100mm.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today column drawings.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should get the work completed from the workers by remaining present at the site
RATE ANALYSIS (Detailed Stepwise Calculations required) External; painting: 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.1 liter = 30.00 Rs Labour cost and other equipments = 7% TOTAL = 80.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 80
Todays BUZZ Word safety precautions: 1)helmet-a helmet should be used to prevent accidents after falling down or if something falls in the head. 2)Hand gloves-hand should be used while mixing of concrete, so that the cement will not have any reaction over the skin.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir: mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) MOHARE VISHAL BHALCHANDRA
Exam No. 13564
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only.
Result of RATE ANALYSIS ( Rs per Unit ) 61.00 /-
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. VIKRANT PISE. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521-10

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near JayPrabha Studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) BAGMARE DINESH SHRIRAM
Exam No. 13521
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge 1. To see and study the casting of column of second floor. 2. To see and study the centering work for third floor. 3. To see and study the casting of R.C.C PARDHI(pit) for Lift.
Details of how you Planned & Executed the allotted work We went on site in group.We saw the casting of column going on and how they manufactured concrete at the site and transferred it with the help of skip and hoist to the second floor.We saw the centering work for third floor we went on the top of centering work.We saw how the labourers were providing stirrups,laying of steel bars according to the plans.
Details of the Construction Procedure / Activity / Technology learned today We learnt the process of manufacturing flyash bricks.We studied the procedure of casting columns. We studied how the centering work is done for third floor.
Details of the Construction Materials learned today Steel bars. Tor steel: 6 mm, 8 mm, 12 mm, 16 mm, 20 mm, 25 mm, 30 mm. Mild steel: 6 mm, 8 mm, 12 mm. Ordinary Portland Cement (O.P.C) – 43 Grade, 53 Grade. Bagalkot Supreme
Details of Environment Caring Technology / Methodology / Procedure / Product learned today If the shuttering is properly sealed by using adhesive or any other thing the leakage of concrete and water through it may be reduced and economy can be achieved.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for third floor showing schedule of beams and columns.
Details of the Bye Laws referred today 1.Minimum width and depth of columns for construction above second floor. 2.Proportions of different materials for manufacturing concrete on site.
Details of any Managerial Skill learned today 1.The site incharge inspected the casting of column going on. 2.The site incharge checked the centering work. 3.The site incharge checked whether the steel provided for column was correct or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for \"EXTERNAL PAINTING\". Approved Apex exterior grade paint. Cost of Paint for 1 litre= Rs.225 = Rs.21 per sq.m Approved quality primer= Rs.80 per litre= Rs.8 per sq.m Birla putty= Rs.6 per sq.m Labour Rs.19 per sq.m Total cost= 21+8+6+19= Rs.54 Add 10% profit=Rs.5.40 Total cost=54+5.40= Rs.59.40 per sq.m= say Rate analysis for \"EXTERNAL PAINTING\". Approved Apex exterior grade paint. Cost of Paint for 1 litre= Rs.225 = Rs.21 per sq.m Approved quality primer= Rs.80 per litre= Rs.8 per sq.m Birla putty= Rs.6 per sq.m Labour Rs.19 per sq.m Total cost= 21+8+6+19= Rs.54 Add 10% profit=Rs.5.40 Total cost=54+5.40= Rs.59.40 per sq.m= say Rs.60 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.60 per sq.m
Todays BUZZ Word \"SITE SAFETY AND BASIC FACILITY TO WORKERS AT SITE\" SITE SAFETY: 1.The labourers working with electrical fittings should wear proper gloves and they should ensure that the machine they are using is properly insulated. 2.Sand should be kept in buckets for use in case of fire. 3.The labourers which are working on centering work must be ensured that the formwork and centering work is properly placed at is firm to provide support. 4.The labours that work on zulla for painting of exterior walls of building should ensure that the rope is fixed tight or held tight otherwise it may lead to severe injury or even death. 5.The nails which are removed after removal of formwork should be dumped at proper place otherwise they may lead to injury. FACILITIES: 1.The facility of first aid kit should be provided at the site. 2.Emergency contact numbers of Fire fighter,Ambulance,Police must be placed on a board at a central place where it can be easily detected. 3.Protective footwear should be provided to labourers. 4.Safety Helmets should be provided for labourers where work is going at different levels. 5.Safety belts should be provided to labourers that work on height,exterior sides of the building. 6.Hand gloves used for material handling,gas cutting,welding etc. 7.Safety goggles used for welding,geinding,pavement breaking etc. 8.Gumboots for ashpalting,concreting works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SARVALKAR PH NO.9822036748.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-06

Company Name Deshmukh Developers
Project Name & Site Address Deshmukh Developments,Pratibha Nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Birajdar Minaxi Renuk
Exam No. 13556
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today the site incharge give us the work that, 1. To observe how waterproofing is done 2. What are the types of waterproffing
Details of how you Planned & Executed the allotted work 1.Firstly we are go to that place & to ask worker how the waterproofing is done 2.We are discuss about in which place water proofing is required 3.It is required in bathrooms, toilet, water tanks,balcony,terrace etc
Details of the Construction Procedure / Activity / Technology learned today Construction Procedure : The worker was told us all information neatly & in detail as follows : 1. There are two treatments which are a. Box type or shabad Treatment b. Crystalline Treatment 2. Grouting is done in a two ways one is Pressure Grouting second is Gravity Grouting 3. Grouting chemical slurry is mixed with cement & apply to RCC Padadi 4. To seal the voids . Drill the chemical inject depend upon nature of concrete 5. To make hole, fill the hole with concrete pipe 1/2\" is used & cement, chemical poured into it then the pipe taken out the water tank 6. In crystalline grouting it fill fine voids
Details of the Construction Materials learned today Material used are as follows : 1.Applying brush 2.Trowel 3.Waterproofing chemical 4.Platform
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environment Caring Technology : To use water proofing chemical in cement concrete to avoid dampness.
Details of the Construction / Engineering Drawings observed today We are observe all plan drawings where water proofing is required.
Details of the Bye Laws referred today None.
Details of any Managerial Skill learned today He should be aware of basic facilities of workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PAINTING : WALL PUTTY = MATERIAL = 4.O0 RS SQ FEET LABOUR = 3 RS COLOUR = 2.5.00 RS PER SQ FEET LABOUR = 2.5.00 RS PER SQ FEET (4.00 + 2)* 100 SQ FEET = 600 RS + ( 2.5 + 2.5 ) * 100 SQ FEET = 500 RS 10.00 = 1000 RS 1 M2 = 130 RS
Result of RATE ANALYSIS ( Rs per Unit ) 130 RS
Todays BUZZ Word SITE SAFETY : Following safety measures are taken by construction Builders: 1.To provide labour insurance Life Plan 2.Labour Compensation Act 3.To provide helmet,handglows,shoes to the workers 4.To provide proper tools & plants,bracing, two row scaffolding 5.To provide safety belts, in case of big height buildings then net is provided. BASIC FACILITIES : 1.To provide scooter/ cycle parking arrangment 2.To provide drinking water jar 3.To provide labour kids sitting place 4.Toilet arrangement
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.ABHIJIT BHOSALE MOB NO. 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-10

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near JayPrabha Studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) TEKWANI SAGAR BANSILAL
Exam No. 10903
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge 1. To see and study the casting of column of second floor. 2. To see and study the centering work for third floor. 3. To see and study the casting of R.C.C PARDHI(pit) for Lift.
Details of how you Planned & Executed the allotted work We went on site in group.We saw the casting of column going on and how they manufactured concrete at the site and transferred it with the help of skip and hoist to the second floor.We saw the centering work for third floor we went on the top of centering work.We saw how the labourers were providing stirrups,laying of steel bars according to the plans.
Details of the Construction Procedure / Activity / Technology learned today We learnt the process of manufacturing flyash bricks.We studied the procedure of casting columns. We studied how the centering work is done for third floor.
Details of the Construction Materials learned today Steel bars. Tor steel: 6 mm, 8 mm, 12 mm, 16 mm, 20 mm, 25 mm, 30 mm. Mild steel: 6 mm, 8 mm, 12 mm. Ordinary Portland Cement (O.P.C) = 43 Grade, 53 Grade. Bagalkot Supreme
Details of Environment Caring Technology / Methodology / Procedure / Product learned today If the shuttering is properly sealed by using adhesive or any other thing the leakage of concrete and water through it may be reduced and economy can be achieved.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for third floor showing schedule of beams and columns
Details of the Bye Laws referred today 1.Minimum width and depth of columns for construction above second floor. 2.Proportions of different materials for manufacturing concrete on site.
Details of any Managerial Skill learned today 1.The site incharge inspected the casting of column going on. 2.The site incharge checked the centering work. 3.The site incharge checked whether the steel provided for column was correct or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for \"EXTERNAL PAINTING\". Approved Apex exterior grade paint. Cost of Paint for 1 litre= Rs.225 = Rs.21 per sq.m Approved quality primer= Rs.80 per litre= Rs.8 per sq.m Birla putty= Rs.6 per sq.m Labour Rs.19 per sq.m Total cost= 21+8+6+19= Rs.54 Add 10% profit=Rs.5.40 Total cost=54+5.40= Rs.59.40 per sq.m= say Rs.60 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.60 per sq.m
Todays BUZZ Word \"SITE SAFETY AND BASIC FACILITY TO WORKERS AT SITE\" SITE SAFETY: 1.The labourers working with electrical fittings should wear proper gloves and they should ensure that the machine they are using is properly insulated. 2.Sand should be kept in buckets for use in case of fire. 3.The labourers which are working on centering work must be ensured that the formwork and centering work is properly placed at is firm to provide support. 4.The labours that work on zulla for painting of exterior walls of building should ensure that the rope is fixed tight or held tight otherwise it may lead to severe injury or even death. 5.The nails which are removed after removal of formwork should be dumped at proper place otherwise they may lead to injury. FACILITIES: 1.The facility of first aid kit should be provided at the site. 2.Emergency contact numbers of Fire fighter,Ambulance,Police must be placed on a board at a central place where it can be easily detected. 3.Protective footwear should be provided to labourers. 4.Safety Helmets should be provided for labourers where work is going at different levels. 5.Safety belts should be provided to labourers that work on height,exterior sides of the building. 6.Hand gloves used for material handling,gas cutting,welding etc. 7.Safety goggles used for welding,geinding,pavement breaking etc. 8.Gumboots for ashpalting,concreting works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SARVALKAR PH NO.9822036748.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudeo
Exam No. 10891
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00PM
Details of the Work Allotted to you today by the Site In-Charge 1)Condute wiring 2)Tile flooring 3)Parapet wall construction. .
Details of how you Planned & Executed the allotted work We see all work together . .
Details of the Construction Procedure / Activity / Technology learned today Condute wiring- 1)First plaster wall is Brock up to 1.5 inches according drawing of condute . 2)then PVC pipe are fixed in it with the help of bracket . 3)then pipe covered with mortar paste in leveled surface. Flooring- 1)first surface is prepared 2)sand & cement mix in proportion & spreed on surface in leveled 3)gental slop is maintain for preparing a base . 4)on it cement slurry is spread & fit a vitrified tile 5)at fixing time tile is hammer by wooden block . Parapet wall- 1)first mortar paste are prepared in proportion 2) brick are immersed in water 3)because reduce water absorbing capacity 4)first mortar are spread in levelled surface 5)then brick are placed on it & fix with help of plumb bob 6)first corner are fix then middle portion is prepared. .
Details of the Construction Materials learned today Brick ,vitrified tile, steel, super-plastisizer wi-fi connection system , camera system .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cock are used in all opening.which is necessary for green building. .
Details of the Construction / Engineering Drawings observed today We see the plans of Upcoming Project. .
Details of the Bye Laws referred today An independent & ventilated well lighted meter room is provided on ground floor. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 2 coats are given while painting that rate are as follows ; Distemper = 0.50 kg = 35.00 Rs (Rs70 /kg) Cement Primer = 0.35 liter = 21.00 Rs (Rs 60/kg) Turpentine 0.09 liter = 22.00 Rs (Rs25/ 100ml) Labour cost and other equipments = 9% TOTAL = 90.00 Rs. per sq.m .
Result of RATE ANALYSIS ( Rs per Unit ) 90.00 Rs. per sq.m
Todays BUZZ Word Safety: 1)First AID kits 2)Personal protective kits 3)safety belts used for worker working at height on exterior of building . 4)Hand gloves 5)gumboot-for preparing concrete material. 6)helpmate Facilities - 1)Drinking water 2)toilet provided for labor 3)insurance policy for labor. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil (9890997979)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10786-10

Company Name Star Tech Infra
Project Name & Site Address star aashiyana, rajendranagar.
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4.30pm
Details of the Work Allotted to you today by the Site In-Charge observed road consruction,and casting of beam and flooring work.
Details of how you Planned & Executed the allotted work we jus obsrved the work how the flooring is done what precoutions should be taken while placing the tiles,how to adjust the error if any. beam:while casting the beam we observed shutring work,rebaring work,steel framing,and then concreting. road:while constructing road we obsrved levlling of road,compaction of road by using the plain type of roller
Details of the Construction Procedure / Activity / Technology learned today Flooring:they used vetrifide tiles,of size (2*2)feet.vetrifide tiles dosnt need polishing,and skirting size is 50mm,flooring work stars from entry of door an then continued till end ofthe room.tiles r placed at right angle toeach other. to maintain the color they used the white cement. an acordingly cement color is changed to match the color wid the tiles. so that it should look gud. beam:while casting the beam the shutring work should be proper there should notbe any gap if there while concreting there will occur lekage an leads honey combing,and strenght will reduce. so shutring work should be check before placing the concrete.an d it should withstand the load. steel bars should be properly placed acording to there position.rebaring is done by drilling the hole accoring to the dimetre of the steel bar.The position of the steel bars are adusted and cast few mm away from surface so that steel bars shouldd not get corrode. road:levelling of road is done in manner in the middle of the road the thick is more then rear side. if we observed the road from the rear side it wil look like mountian. The thickness in the midle wil be more such thing is done for the proper percolation .so that there should not be stagnant of water water should drain properly.
Details of the Construction Materials learned today tar. vitrified tiles,mortor. concrete,steel.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today sectional drawing mention the finished floor level of all stories mention the height of sills, doors, windows,openings,lofts&rooling shutters clearly from finished floar levels details of elevations, cornics, drop pardi and projection of slabAt terrace level with referance to building line thicness of water proofing treatment for toilets and terrace
Details of the Bye Laws referred today buidling regulations setback line, building line, control line height of building built up area
Details of any Managerial Skill learned today levelling of road is done in manner in the middle of the road the thick is more then rear side. if we observed the road from the rear side it wil look like mountian. The thickness in the midle wil be more such thing is done for the proper percolation .so that there should not be stagnant of water water should drain properly
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for 1 m2 external painting if we use cement color for external paint 1 kg cement paint =1 lit = 25 Rs it use for 50 Ft2 area labour rate = 2.5 Rs/1 Ft2 primer 1 lit = 80 Rs materil cost = 25 + 80 = 105 Rs labour = 125 Rs total cost = 20 Rs so, 1 m2 cost = 49.50 Rs = 50 Rs/ 1m2
Result of RATE ANALYSIS ( Rs per Unit ) 50 Rs/sq.m.
Todays BUZZ Word A construction engg. must adopted safety precaution as an integral part of his job 1) the basic funtion of managment is planning and programing 2)lowering of operational cost and reduction in no. of accient on the site should be its ultimate objective 3)the accident prevention program has to be well planned and efectively monitored and controlled 4)accidents can be min. by insuring the implementation of the safety court at all levels in the construction project enlist are some datas 5)site engg along with the contractors must work out a safety program 6)all the working spots should be inspecte periodically for ddefect in any flaws in the program and to monitor its performance 7)all accident must be investigated to reinforce the safety program 8)accidents statistics shoul be compllied 9)site offices should have a list of the following emergency telephone no. fire 101,ambulance 102,police 100, 10)everyone should participate insure the implementation at the safety precaution
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: Rohit_patil361@rediffmail.com
Subject: 13565-10

Company Name Bhima Builders & Developers
Project Name & Site Address wind gate, near new palace,kop.
Students Name (Surname_First Name_Middle Name) PATIL ROHIT ASHOK
Exam No. 13565
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only .
Result of RATE ANALYSIS ( Rs per Unit ) 61.00/- for 1m2
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. VIKRANT PISE 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) MOHARE VISHAL BHALCHANDRA
Exam No. 13564
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only.
Result of RATE ANALYSIS ( Rs per Unit ) 61.00 /-
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. VIKRANT PISE. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the form work of R.C.C. staircase for wing D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the form work properly we carefully check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today •CONCRETE Cement, sand , aggregate , and water •STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasticizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly Ash used for concreting of R.C.C. work, so that directly affecting on increasing strength of concrete and reduces SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall up to 2.4m height may be permitted if the top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For external Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only .
Result of RATE ANALYSIS ( Rs per Unit ) 61.00/-
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effective implementation of safety program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / firefighting equipment / safety appliances on the site and ensure that they are maintained in good condition. • Site supervisors should give safety instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safety belts • Hand gloves • Safety goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) MOHARE VISHAL BHALCHANDRA
Exam No. 13564
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only.
Result of RATE ANALYSIS ( Rs per Unit ) 61.00 /-
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. VIKRANT PISE. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-10

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Tambe Trusha Sitaram
Exam No. 10902
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of construction of starter to the column. .
Details of how you Planned & Executed the allotted work we observed how the measurements are taken for constructing the starter .& how the concrete is mixed & poured into it. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of how the construction of starter is given to the column.first the measurement are taken & marked at the portion.& the concrete is mixed in suitable proportion & poured in it.starter is given to the column for the sake of maintaining proper & uniform size of the column. .
Details of the Construction Materials learned today today we discussed about the cement .cement is finely ground material having adhesive & cohesive properties which is used as binding material for the ingredient of cement concrete .joseph aspden ,a british bricklayer inverted cement in 1824. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no such technology we learned today. .
Details of the Construction / Engineering Drawings observed today today we observed the drawing of electrification. .
Details of the Bye Laws referred today in bye-laws today we referred the requirement of individual exits at each floor. .
Details of any Managerial Skill learned today the site in-charge should keep the record of material quantity used on the site. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 2 coats are given while painting that rate are as follows ; Distemper = 0.50 kg = 35.00 Rs (Rs70 /kg) Cement Primer = 0.35 liter = 21.00 Rs (Rs 60/kg) Turpentine 0.09 liter = 22.00 Rs (Rs25/ 100ml) Labour cost and other equipments = 9% TOTAL = 90.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 90.00 Rs. per sq.m
Todays BUZZ Word 1)First AID kits 2)Personal protective kits 3)safety belts used for worker working at height on exterior of building . 4)Hand gloves 5)gumboot-for preparing concrete material. 6)helpmate Facilities - 1)Drinking water 2)toilet provided for labor 3)insurance policy for labor. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: gauravdesai75@gmail.com
Subject: 13522-10

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near JayPrabha Studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DESAI GAURAV RAVINDRA
Exam No. 13522
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge 1. To see and study the casting of column of second floor. 2. To see and study the centering work for third floor. 3. To see and study the casting of R.C.C PARDHI(pit) for Lift.
Details of how you Planned & Executed the allotted work We went on site in group.We saw the casting of column going on and how they manufactured concrete at the site and transferred it with the help of skip and hoist to the second floor.We saw the centering work for third floor we went on the top of centering work.We saw how the labourers were providing stirrups,laying of steel bars according to the plans.
Details of the Construction Procedure / Activity / Technology learned today We learnt the process of manufacturing flyash bricks.We studied the procedure of casting columns.We studied how the centering work is done for third floor.
Details of the Construction Materials learned today Steel bars used for casting columns; Tor steel: 6mm,8mm,12mm,16mm,20mm,25mm,30 mm. Mild steel:6mm,8mm,12mm. Ordinary Portland Cement (O.P.C)= 43 Grade,53 Grade. Bagalkot Supreme.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today If the shuttering is properly sealed by using adhesive or any other thing the leakage of concrete and water through it may be reduced and economy can be achieved.
Details of the Construction / Engineering Drawings observed today 1. Plan for second floor. 2. Plan for third floor showing schedule of beams and columns.
Details of the Bye Laws referred today 1.Minimum width and depth of columns for construction above second floor. 2.Proportions of different materials for manufacturing concrete on site.
Details of any Managerial Skill learned today 1.The site incharge inspected the casting of column going on. 2.The site incharge checked the centering work. 3.The site incharge checked whether the steel(bars) provided for column was correct or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for \"EXTERNAL PAINTING\". Approved Apex exterior grade paint. Cost of Paint for 1 litre= Rs.225 = Rs.21 per sq.m Approved quality primer= Rs.80 per litre= Rs.8 per sq.m Birla putty= Rs.6 per sq.m Labour Rs.19 per sq.m Total cost= 21+8+6+19= Rs.54 Add 10% profit=Rs.5.40 Total cost=54+5.40= Rs.59.40 per sq.m= say Rs.60 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.60 per sq.m for apex exterior grade paint.
Todays BUZZ Word \"SITE SAFETY AND BASIC FACILITY TO WORKERS AT SITE\" SITE SAFETY: 1.The labourers working with electrical fittings should wear proper gloves and they should ensure that the machine they are using is properly insulated. 2.Sand should be kept in buckets for use in case of fire. 3.The labourers which are working on centering work must be ensured that the formwork and centering work is properly placed at is firm to provide support. 4.The labours that work on zulla for painting of exterior walls of building should ensure that the rope is fixed tight or held tight otherwise it may lead to severe injury or even death. 5.The nails which are removed after removal of formwork should be dumped at proper place otherwise they may lead to injury. FACILITIES: 1.The facility of first aid kit should be provided at the site. 2.Emergency contact numbers of Fire fighter,Ambulance,Police must be placed on a board at a central place where it can be easily detected. 3.Protective footwear should be provided to labourers. 4.Safety Helmets should be provided for labourers where work is going at different levels. 5.Safety belts should be provided to labourers that work on height,exterior sides of the building. 6.Hand gloves used for material handling,gas cutting,welding etc. 7.Safety goggles used for welding,geinding,pavement breaking etc. 8.Gumboots for ashpalting,concreting works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SARVALKAR PH NO.9822036748.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-10

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Shinde Sagar Arvind
Exam No. 13568
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of construction of starter to the column. .
Details of how you Planned & Executed the allotted work we observed how the measurements are taken for constructing the starter .& how the concrete is mixed & poured into it. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of how the construction of starter is given to the column.first the measurement are taken & marked at the portion.& the concrete is mixed in suitable proportion & poured in it.starter is given to the column for the sake of maintaining proper & uniform size of the column. .
Details of the Construction Materials learned today today we discussed about the cement .cement is finely ground material having adhesive & cohesive properties which is used as binding material for the ingredient of cement concrete .joseph aspden ,a british bricklayer inverted cement in 1824. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel for shuttering can prevent trees. .
Details of the Construction / Engineering Drawings observed today Center-line plan. .
Details of the Bye Laws referred today in bye-laws today we referred the requirement of individual exits at each floor. .
Details of any Managerial Skill learned today the site in-charge should keep the record of material quantity used on the site. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 2 coats are given while painting that rate are as follows ; Distemper = 0.50 kg = 35.00 Rs (Rs70 /kg) Cement Primer = 0.35 liter = 21.00 Rs (Rs 60/kg) Turpentine 0.09 liter = 22.00 Rs (Rs25/ 100ml) Labour cost and other equipments = 9% TOTAL = 90.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 90.00 Rs. per sq.m
Todays BUZZ Word 1)First AID kits 2)Personal protective kits 3)safety belts used for worker working at height on exterior of building . 4)Hand gloves 5)gumboot-for preparing concrete material. 6)helpmate Facilities - 1)Drinking water 2)toilet provided for labor 3)insurance policy for labor. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.P.Bharmal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) REDEKAR SHANTANU RAVINDRA
Exam No. 13566
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only.
Result of RATE ANALYSIS ( Rs per Unit ) 61.00 /-
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. VIKRANT PISE. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together.
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today Up coming third phase floor plans of Sanghavi Builders & Developers
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together.
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today Up coming third phase floor plans of Sanghavi Builders & Developers
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together.
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today Up coming third phase floor plans of Sanghavi Builders & Developers
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-10

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Sharad Shankarrao
Exam No. 10897
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of construction of starter to the column. .
Details of how you Planned & Executed the allotted work we observed how the measurements are taken for constructing the starter .& how the concrete is mixed & poured into it. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of how the construction of starter is given to the column.first the measurement are taken & marked at the portion.& the concrete is mixed in suitable proportion & poured in it.starter is given to the column for the sake of maintaining proper & uniform size of the column. .
Details of the Construction Materials learned today today we discussed about the cement .cement is finely ground material having adhesive & cohesive properties which is used as binding material for the ingredient of cement concrete .joseph aspden ,a british bricklayer inverted cement in 1824. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no such technology we learned today. .
Details of the Construction / Engineering Drawings observed today today we observed the drawing of electrification. .
Details of the Bye Laws referred today in bye-laws today we referred the requirement of individual exits at each floor. .
Details of any Managerial Skill learned today the site in-charge should keep the record of material quantity used on the site. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 2 coats are given while painting that rate are as follows ; Distemper = 0.50 kg = 35.00 Rs (Rs70 /kg) Cement Primer = 0.35 liter = 21.00 Rs (Rs 60/kg) Turpentine 0.09 liter = 22.00 Rs (Rs25/ 100ml) Labour cost and other equipments = 9% TOTAL = 90.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 90.00 Rs. per sq.m
Todays BUZZ Word 1)First AID kits 2)Personal protective kits 3)safety belts used for worker working at height on exterior of building . 4)Hand gloves 5)gumboot-for preparing concrete material. 6)helpmate Facilities - 1)Drinking water 2)toilet provided for labor 3)insurance policy for labor. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) MOHARE VISHAL BHALCHANDRA
Exam No. 13564
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only.
Result of RATE ANALYSIS ( Rs per Unit ) 61.00
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. VIKRANT PISE. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-10

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Abhishek Dadasaheb
Exam No. 10895
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of construction of starter to the column. .
Details of how you Planned & Executed the allotted work we observed how the measurements are taken for constructing the starter .& how the concrete is mixed & poured into it. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of how the construction of starter is given to the column.first the measurement are taken & marked at the portion.& the concrete is mixed in suitable proportion & poured in it.starter is given to the column for the sake of maintaining proper & uniform size of the column. .
Details of the Construction Materials learned today today we discussed about the cement .cement is finely ground material having adhesive & cohesive properties which is used as binding material for the ingredient of cement concrete .joseph aspden ,a british bricklayer inverted cement in 1824. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no such technology we learned today. .
Details of the Construction / Engineering Drawings observed today today we observed the drawing of electrification. .
Details of the Bye Laws referred today in bye-laws today we referred the requirement of individual exits at each floor. .
Details of any Managerial Skill learned today the site in-charge should keep the record of material quantity used on the site. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 2 coats are given while painting that rate are as follows ; Distemper = 0.50 kg = 35.00 Rs (Rs70 /kg) Cement Primer = 0.35 liter = 21.00 Rs (Rs 60/kg) Turpentine 0.09 liter = 22.00 Rs (Rs25/ 100ml) Labour cost and other equipments = 9% TOTAL = 90.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 90.00 Rs. per sq.m
Todays BUZZ Word 1)First AID kits 2)Personal protective kits 3)safety belts used for worker working at height on exterior of building . 4)Hand gloves 5)gumboot-for preparing concrete material. 6)helpmate Facilities - 1)Drinking water 2)toilet provided for labor 3)insurance policy for labor. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-10

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Sawant Amit Ganpat
Exam No. 10900
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of construction of starter to the column. .
Details of how you Planned & Executed the allotted work we observed how the measurements are taken for constructing the starter .& how the concrete is mixed & poured into it. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of how the construction of starter is given to the column.first the measurement are taken & marked at the portion.& the concrete is mixed in suitable proportion & poured in it.starter is given to the column for the sake of maintaining proper & uniform size of the column. .
Details of the Construction Materials learned today today we discussed about the cement .cement is finely ground material having adhesive & cohesive properties which is used as binding material for the ingredient of cement concrete .joseph aspden ,a british bricklayer inverted cement in 1824. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no such technology we learned today. .
Details of the Construction / Engineering Drawings observed today today we observed the drawing of electrification. .
Details of the Bye Laws referred today in bye-laws today we referred the requirement of individual exits at each floor. .
Details of any Managerial Skill learned today the site in-charge should keep the record of material quantity used on the site. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 2 coats are given while painting that rate are as follows ; Distemper = 0.50 kg = 35.00 Rs (Rs70 /kg) Cement Primer = 0.35 liter = 21.00 Rs (Rs 60/kg) Turpentine 0.09 liter = 22.00 Rs (Rs25/ 100ml) Labour cost and other equipments = 9% TOTAL = 90.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 90.00 Rs. per sq.m
Todays BUZZ Word 1)First AID kits 2)Personal protective kits 3)safety belts used for worker working at height on exterior of building . 4)Hand gloves 5)gumboot-for preparing concrete material. 6)helpmate Facilities - 1)Drinking water 2)toilet provided for labor 3)insurance policy for labor. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today The floor plans of upcoming third phase .I.T. destination of Sanghavi Builders & Developers .
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today The floor plans of upcoming third phase .I.T. destination of Sanghavi Builders & Developers .
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today The floor plans of upcoming third phase .I.T. destination of Sanghavi Builders & Developers .
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) REDEKAR SHANTANU RAVINDRA
Exam No. 13566
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today material • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only.
Result of RATE ANALYSIS ( Rs per Unit ) 61.00
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. VIKRANT PISE. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today The floor plans of upcoming third phase .I.T. destination of Sanghavi Builders & Developers .
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today The floor plans of upcoming third phase .I.T. destination of Sanghavi Builders & Developers .
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today The floor plans of upcoming third phase .I.T. destination of Sanghavi Builders & Developers .
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) MOHARE VISHAL BHALCHANDRA
Exam No. 13564
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only.
Result of RATE ANALYSIS ( Rs per Unit ) 61.00
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise. No. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today The floor plans of upcoming third phase .I.T. destination of Sanghavi Builders & Developers .
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the conduit working. -To see the flooring work . - Extra reinforcement cutting - Parapet wall construction.
Details of how you Planned & Executed the allotted work We see all the work together
Details of the Construction Procedure / Activity / Technology learned today Procedure :For conduit wiring : 1) They make a small slot of size 1.5\" depth. 2) Then conduit pipes are placed in these slot along with wires. 3)Then at the end of conduit pipe swich boards are fitted on the wall. Procedure for flooring : First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. Procedure for parapet construction: 1) First bricks are kept immersed so that they do not absorb water from mortar when they are used for constuction. 2)Then mortar is prepared . 3)Mortar is placed on the surface & bricks are laid . 4)With the help of line dori bricks are placed in one horizontal straight line. 5)Then second and third course are laid until required are achieved. 6) Then at top of this P.C.C.Coping is done.
Details of the Construction Materials learned today Bricks, Wi-fi connection for internet. Cement mortar, Concrete ,vertified tiles, etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cocks are used for entire project which reduces the conumption of more water .
Details of the Construction / Engineering Drawings observed today The floor plans of upcoming third phase .I.T. destination of Sanghavi Builders & Developers .
Details of the Bye Laws referred today Meter Room: An independent and ventilated well lighted meter room is provided on ground floor according to the requirements of the electric supply undertaking .
Details of any Managerial Skill learned today Mr. Pritam Patil neglects the instructons given by theowner Mr. Lalit Sanghavi & avoids him .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis : For external colouring work: Assume quantity 20sq.m. Particular : No. or Qt. Rate Cost Material Paint(Apex) 3kg. 150 450Rs/- Bruss 2 50 100 Rs/- Labour Painter 4 250 1000Rs/- Helpers 2 170 340Rs/- Total 1890Rs/- Builders profit including 2268Rs/- Service tax , VAT etc 20 % Rate per sq.m. = 113.4 Rs/- per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 113.4 Rs/- per sq.m
Todays BUZZ Word Todays Buzz word Site Safety& Basic facilities to workers at site: The precautionary measures for avoiding accidents on site are called safety measures. Following are the facilities which are provided to the workers on site during construction: 1) First Aid kit - Dressing cotton - General medicines - Triangular bandage - 25mm roller bandage - 75 mm roller bandage - Potassium permanganate - Iodine bottle - Packet of cotton wool - Scissors - Dettol - Safety pins - Knife - Blade - 2) Personal protective kit: - Safety precautions play vital role in protecting workmen from injury while executing he work. - Safety helmets : Used where work is in progress at different levels - Safety belts: Used by those working at the height , on the exterior of the building . - Hand gloves : Used for material handling gas cutter, welding machines etc - Safety goggles: Used for gas welding , grinding , pavement brokingetc. - Gum Boots : Used during asphalting , cutting of hard rock , concreting works etc. 3)Site offices have a list of the following emergency telephone numbers : - Fire : 101 -ambulance: 105 - Police : 100 - Nearest doctor : XXXXXXX 4) accidents can be minimized by ensuring the implementation of the codes at all levels in the construction process. Out of the above facilities only Hand gloves, Safety goggles, Gum Boots , Safety belts , first Aid kit are provided . Safety helmets are not provided on the site for workers.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: Rohit_patil361@rediffmail.com
Subject: 13565-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, NEAR NEW PALACE, NAGALA PARK
Students Name (Surname_First Name_Middle Name) PATIL ROHIT ASHOK
Exam No. 13565
Working Day No. 10
Date (DD/MM/YYYY) 19/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carefully check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only .
Result of RATE ANALYSIS ( Rs per Unit ) 61.00/- for 1 m2
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) MOHARE VISHAL BHALCHANDRA
Exam No. 13564
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super - plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only.
Result of RATE ANALYSIS ( Rs per Unit ) 61.00
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise. No. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address saghavi construction
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4PM
Details of the Work Allotted to you today by the Site In-Charge 1)to see condute wiring. 2)flooring of balcony. 3)Parapet wall construction. .
Details of how you Planned & Executed the allotted work we see all the work together. .
Details of the Construction Procedure / Activity / Technology learned today Condute wiring- 1)First plaster wall is brock up to 1.5 inches according drawing of condute. 2)then PVC pipe are fixed in it with the help of barcket 3)then pipe are fixed in it & levelled with mortar. Parapet wall construction- 1)First mortar paste are prepared in praportion 2)Brick are immersed in water. 3)Becouse reduce water absorbing capacity. 4)First mortar ara spread in levelled surface 5)then brick are placed on it & fix with help of plumb bob Flooring- 1)First surface is prepared 2)sand & cement mix in proportion & spread on surface level . 3)gental slop is preparing for base . 4)on it cement slurry is spread & fix the vitrified tiles. .
Details of the Construction Materials learned today Brick, concrete ,steel, plumbing accessory wi-fi conection system.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cock are used in all opening. .
Details of the Construction / Engineering Drawings observed today Up coming project plan is seen .
Details of the Bye Laws referred today An independent & ventilated well lighted meter room is provided on ground floor. .
Details of any Managerial Skill learned today Gesture & posture of person has impact on other workers. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 2 coat are apply in outer surface of building. Distemper- =0.50kg =35.00 Rs (Rs70/kg) cement- =0.35litr =21.00 Rs (60Rs/kg) Turpentine- =0.90litr =22.00 Rs labour cost- =9% Total=90.00Rs per sq m. .
Result of RATE ANALYSIS ( Rs per Unit ) Rs 90.00 per sq m.
Todays BUZZ Word 1)first AID provided for worker 2)safty belt provided for worker working on outside of building. 3)hand glove provided 4)gumboot Facilitis 1)drinking water 2)toilet 3) life insurance
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) REDEKAR SHANTANU RAVINDRA
Exam No. 13566
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today • Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only.
Result of RATE ANALYSIS ( Rs per Unit ) 61.00
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise. No. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-10

Company Name Bhima Builders & Developers
Project Name & Site Address wind gate , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Bulbule
Exam No. 13557
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge • To check the formwork of R.C.C. staircase for wing –D • To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work • From observing the plan of R.C.C. staircase check the all formwork is properly • After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. • First we check the billing of total steel coming from manufacturing industry. • Then we workout the total length of bars, total number of bars and size of each bar exactaly • Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. • By using this formula we gives the wt, of each bar in kg. per meter length. • Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today • CONCRETE – Cement, sand , aggregate , and water • STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. • Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today • Plan of R.C.C. stair case and beam • Drawing of R.C.C. column. • Drawing of footing. • Slab reinforcement drawing • Cantilever slab drawing.
Details of the Bye Laws referred today • The max. height shall be 1.5 m above the center line of the front street. • The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. • In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today • Check the daily progress report . • Remain present for all types of concreting work • Average the next day work in advanced • Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area- Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00 150.00 Water 3.0 lit Lump-su ---- Polish paper 2 no. 20.00 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only .
Result of RATE ANALYSIS ( Rs per Unit ) 61.00 Rs. PER M2
Todays BUZZ Word • Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. • Identify any unsafe working condition / location by inspecting the site twice a week . • Investigate all accidents and reinforce the safety program with additional precautions • Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. • Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- • Safety helmets • Safty belts • Hand gloves • Safty goggles • Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-10

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Ramchandra
Exam No. 13557
Working Day No. 10
Date (DD/MM/YYYY) 18/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge •To check the formwork of R.C.C. staircase for wing –D •To workout the quantity of steel bars coming on site.
Details of how you Planned & Executed the allotted work •From observing the plan of R.C.C. staircase check the all formwork is properly •After checking the formwork properly we carelly check the all leakages.
Details of the Construction Procedure / Activity / Technology learned today Workout the total quantity of steel coming on site in TRUCK. •First we check the billing of total steel coming from manufacturing industry. •Then we workout the total length of bars, total number of bars and size of each bar exactaly •Then by using empirical formula = (d)2 / 162 Where , d = diameter of steel bar. •By using this formula we gives the wt, of each bar in kg. per meter length. •Like that , we calculate the total wt. of steel in a truck in TONNE.
Details of the Construction Materials learned today •CONCRETE – Cement, sand , aggregate , and water •STEEL BARS- Main bar- 18 mm dia. Distribution bar- 12 mm dia. Stirrups- 8mm dia. •Admixture- super – plasisizer
Details of Environment Caring Technology / Methodology / Procedure / Product learned today •Fly –Ash used for concreting of R.C.C. work, so that directaly affecting on increasing strength of concrete and reduse SURFACE POLLUTION.
Details of the Construction / Engineering Drawings observed today •Plan of R.C.C. stair case and beam •Drawing of R.C.C. column. •Drawing of footing. •Slab reinforcement drawing •Cantilever slab drawing.
Details of the Bye Laws referred today BOUNDARY WALL- •The max. height shall be 1.5 m above the center line of the front street. •The compound wall upto 2.4m height may be permitted if te top 0.9m is of open construction. •In case corner plot , the ht. of the boundary wall shall be restricted to 0.75 m for a length of 10.0m on the front side of the inter section and the remaining height oh 0.75m.
Details of any Managerial Skill learned today •Check the daily progress report . •Remain present for all types of concreting work •Average the next day work in advanced •Then, prepare the requirement of material , etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) For extarnal Painting 10.00m2 surface area - Sr.no ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 Cement paint Cement paint 3.0 kg. 50.00kg 150.0 Water 3.0 lit Lump-sum ---- Polish paper 2 no. 20.00per 1 40.00 TOTAL = 190.00 Sr.no ITEM LABOUR QUANTITY RATE PER AMOUNT 1 Cement paint Painter 1 no. 300.00 300.00 Bhisti 1 no. 120.00 120.00 TOTAL = 420.00 TOTAL AMOUNT FOR EXTERNAL PAINTING PER 10 M2 = 610.00 Rs. Only. FOR 1M2 PAINTING = 61.00 Rs. Only .
Result of RATE ANALYSIS ( Rs per Unit ) 61.00 Rs. only
Todays BUZZ Word •Determine and incorporate a suitable course of action in day to day activity for the effctive implementation of safty program. •Identify any unsafe working condition / location by inspecting the site twice a week . •Investigate all accidents and reinforce the safety program with additional precautions •Keep the first-aid / fire fighting equipment / safety appliances on the site and ensure that they arte maintained in good condition. •Site supervisors should give safty instructions to the workers every day. EQUIPMENTS- •Safety helmets •Safty belts •Hand gloves •Safty goggles •Gum boots
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge 1)Condute wiring 2)Tile flooring 3)Parapet wall construction. .
Details of how you Planned & Executed the allotted work We see all work together . .
Details of the Construction Procedure / Activity / Technology learned today Condute wiring- 1)First plaster wall is Brock up to 1.5 inches according drawing of condute . 2)then PVC pipe are fixed in it with the help of bracket . 3)then pipe covered with mortar paste in leveled surface. Flooring- 1)first surface is prepared 2)sand & cement mix in proportion & spreed on surface in leveled 3)gental slop is maintain for preparing a base . 4)on it cement slurry is spread & fit a vitrified tile 5)at fixing time tile is hammer by wooden block . Parapet wall- 1)first mortar paste are prepared in proportion 2) brick are immersed in water 3)because reduce water absorbing capacity 4)first mortar are spread in levelled surface 5)then brick are placed on it & fix with help of plumb bob 6)first corner are fix then middle portion is prepared. .
Details of the Construction Materials learned today Brick ,vitrified tile, steel, super-plastisizer wi-fi connection system , camera system .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cock are used in all opening.which is necessary for green building. .
Details of the Construction / Engineering Drawings observed today Upcoming project plan see-2nd & 3rd phase .
Details of the Bye Laws referred today An independent & ventilated well lighted meter room is provided on ground floor. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 2 coats are given while painting that rate are as follows ; Distemper = 0.50 kg = 35.00 Rs (Rs70 /kg) Cement Primer = 0.35 liter = 21.00 Rs (Rs 60/kg) Turpentine 0.09 liter = 22.00 Rs (Rs25/ 100ml) Labour cost and other equipments = 9% TOTAL = 90.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 90.00 Rs. per sq.m
Todays BUZZ Word 1)First AID kits 2)Personal protective kits 3)safety belts used for worker working at height on exterior of building . 4)Hand gloves 5)gumboot-for preparing concrete material. 6)helpmate Facilities - 1)Drinking water 2)toilet provided for labor 3)insurance policy for labor. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-10

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 10
Date (DD/MM/YYYY) 18-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge 1)Condute wiring 2)Tile flooring 3)Parapet wall construction. .
Details of how you Planned & Executed the allotted work We see all work together . .
Details of the Construction Procedure / Activity / Technology learned today Condute wiring- 1)First plaster wall is Brock up to 1.5 inches according drawing of condute . 2)then PVC pipe are fixed in it with the help of bracket . 3)then pipe covered with mortar paste in leveled surface. Flooring- 1)first surface is prepared 2)sand & cement mix in proportion & spreed on surface in leveled 3)gental slop is maintain for preparing a base . 4)on it cement slurry is spread & fit a vitrified tile 5)at fixing time tile is hammer by wooden block . Parapet wall- 1)first mortar paste are prepared in proportion 2) brick are immersed in water 3)because reduce water absorbing capacity 4)first mortar are spread in levelled surface 5)then brick are placed on it & fix with help of plumb bob 6)first corner are fix then middle portion is prepared.
Details of the Construction Materials learned today Brick ,vitrified tile, steel, super-plastisizer wi-fi connection system , camera system .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Low discharge cock are used in all opening.which is necessary for green building. .
Details of the Construction / Engineering Drawings observed today Upcoming project plan is seen- which is 2nd & 3rd phase. .
Details of the Bye Laws referred today An independent & ventilated well lighted meter room is provided on ground floor. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 2 coats are given while painting that rate are as follows ; Distemper = 0.50 kg = 35.00 Rs (Rs70 /kg) Cement Primer = 0.35 liter = 21.00 Rs (Rs 60/kg) Turpentine 0.09 liter = 22.00 Rs (Rs25/ 100ml) Labour cost and other equipments = 9% TOTAL = 90.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 90.00 Rs. per sq.m
Todays BUZZ Word 1)First AID kits 2)Personal protective kits 3)safety belts used for worker working at height on exterior of building . 4)Hand gloves 5)gumboot-for preparing concrete material. 6)helpmate Facilities - 1)Drinking water 2)toilet provided for labor 3)insurance policy for labor.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-10

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.rajendar nagar kolhapur
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 10
Date (DD/MM/YYYY) 18/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge today we observed road consruction,and casting of beam and flooring work.
Details of how you Planned & Executed the allotted work we jus obsrved the work how the flooring is done what precoutions should be taken while placing the tiles,how to adjust the error if any. beam:while casting the beam we observed shutring work,rebaring work,steel framing,and then concreting. road:while constructing road we obsrved levlling of road,compaction of road by using the plain type of roller.
Details of the Construction Procedure / Activity / Technology learned today Flooring:they used vetrifide tiles,of size (2*2)feet.vetrifide tiles dosnt need polishing,and skirting size is 50mm,flooring work stars from entry of door an then continued till end ofthe room.tiles r placed at right angle toeach other. to maintain the color they used the white cement. an acordingly cement color is changed to match the color wid the tiles. so that it should look gud. beam:while casting the beam the shutring work should be proper there should notbe any gap if there while concreting there will occur lekage an leads honey combing,and strenght will reduce. so shutring work should be check before placing the concrete.an d it should withstand the load. steel bars should be properly placed acording to there position.rebaring is done by drilling the hole accoring to the dimetre of the steel bar.The position of the steel bars are adusted and cast few mm away from surface so that steel bars shouldd not get corrode. road:levelling of road is done in manner in the middle of the road the thick is more then rear side. if we observed the road from the rear side it wil look like mountian. The thickness in the midle wil be more such thing is done for the proper percolation .so that there should not be stagnant of water water should drain properly.
Details of the Construction Materials learned today most of the organization and enggs consider store keeping is the minor activitiy in the constuction field.however reachers indicates that store keeping is one of the most important activity in any construction site. coz 65% is the material cost which can go up due to negligenc.the store keeper can control this wastage .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today sectional drawing mention the finished floor level of all stories mention the height of sills, doors, windows,openings,lofts&rooling shutters clearly from finished floar levels details of elevations, cornics, drop pardi and projection of slabAt terrace level with referance to building line thicness of water proofing treatment for toilets and terrace
Details of the Bye Laws referred today buidling regulations setback line, building line, control line height of building built up area
Details of any Managerial Skill learned today levelling of road is done in manner in the middle of the road the thick is more then rear side. if we observed the road from the rear side it wil look like mountian. The thickness in the midle wil be more such thing is done for the proper percolation .so that there should not be stagnant of water water should drain properly.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for 1 m2 external painting if we use cement color for external paint 1 kg cement paint =1 lit = 25 Rs it use for 50 Ft2 area labour rate = 2.5 Rs/1 Ft2 primer 1 lit = 80 Rs materil cost = 25 + 80 = 105 Rs labour = 125 Rs total cost = 20 Rs so, 1 m2 cost = 49.50 Rs = 50 Rs/ 1m2
Result of RATE ANALYSIS ( Rs per Unit ) 50 Rs/ 1m2
Todays BUZZ Word a construction engg. must adopted safety precaution as an integral part of his job 1) the basic funtion of managment is planning and programing 2)lowering of operational cost and reduction in no. of accient on the site should be its ultimate objective 3)the accident prevention program has to be well planned and efectively monitored and controlled 4)accidents can be min. by insuring the implementation of the safety court at all levels in the construction project enlist are some datas 5)site engg along with the contractors must work out a safety program 6)all the working spots should be inspecte periodically for ddefect in any flaws in the program and to monitor its performance 7)all accident must be investigated to reinforce the safety program 8)accidents statistics shoul be compllied 9)site offices should have a list of the following emergency telephone no. fire 101,ambulance 102,police 100, 10)everyone should participate insure the implementati
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 901109689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: pinkrosee4u@yahoo.com
Subject: 10878-10

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr. rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) narnaware shikha haridas
Exam No. 10878
Working Day No. 10
Date (DD/MM/YYYY) 18/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge today we observed road consruction,and casting of beam and flooring work.
Details of how you Planned & Executed the allotted work we jus obsrved the work how the flooring is done what precoutions should be taken while placing the tiles,how to adjust the error if any. beam:while casting the beam we observed shutring work,rebaring work,steel framing,and then concreting. road:while constructing road we obsrved levlling of road,compaction of road by using the plain type of roller.
Details of the Construction Procedure / Activity / Technology learned today Flooring:they used vetrifide tiles,of size (2*2)feet.vetrifide tiles dosnt need polishing,and skirting size is 50mm,flooring work stars from entry of door an then continued till end ofthe room.tiles r placed at right angle toeach other. to maintain the color they used the white cement. an acordingly cement color is changed to match the color wid the tiles. so that it should look gud. beam:while casting the beam the shutring work should be proper there should notbe any gap if there while concreting there will occur lekage an leads honey combing,and strenght will reduce. so shutring work should be check before placing the concrete.an d it should withstand the load. steel bars should be properly placed acording to there position.rebaring is done by drilling the hole accoring to the dimetre of the steel bar.The position of the steel bars are adusted and cast few mm away from surface so that steel bars shouldd not get corrode. road:levelling of road is done in manner in the middle of the road the thick is more then rear side. if we observed the road from the rear side it wil look like mountian. The thickness in the midle wil be more such thing is done for the proper percolation .so that there should not be stagnant of water water should drain properly.
Details of the Construction Materials learned today most of the organization and enggs consider store keeping is the minor activitiy in the constuction field.however reachers indicates that store keeping is one of the most important activity in any construction site. coz 65% is the material cost which can go up due to negligenc.the store keeper can control this wastage .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today sectional drawing mention the finished floor level of all stories mention the height of sills, doors, windows,openings,lofts&rooling shutters clearly from finished floar levels details of elevations, cornics, drop pardi and projection of slabAt terrace level with referance to building line thicness of water proofing treatment for toilets and terrace
Details of the Bye Laws referred today buidling regulations setback line, building line, control line height of building built up area
Details of any Managerial Skill learned today levelling of road is done in manner in the middle of the road the thick is more then rear side. if we observed the road from the rear side it wil look like mountian. The thickness in the midle wil be more such thing is done for the proper percolation .so that there should not be stagnant of water water should drain properly.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for 1 m2 external painting if we use cement color for external paint 1 kg cement paint =1 lit = 25 Rs it use for 50 Ft2 area labour rate = 2.5 Rs/1 Ft2 primer 1 lit = 80 Rs materil cost = 25 + 80 = 105 Rs labour = 125 Rs total cost = 20 Rs so, 1 m2 cost = 49.50 Rs = 50 Rs/ 1m2
Result of RATE ANALYSIS ( Rs per Unit ) 50 Rs/ 1m2
Todays BUZZ Word a construction engg. must adopted safety precaution as an integral part of his job 1) the basic funtion of managment is planning and programing 2)lowering of operational cost and reduction in no. of accient on the site should be its ultimate objective 3)the accident prevention program has to be well planned and efectively monitored and controlled 4)accidents can be min. by insuring the implementation of the safety court at all levels in the construction project enlist are some datas 5)site engg along with the contractors must work out a safety program 6)all the working spots should be inspecte periodically for ddefect in any flaws in the program and to monitor its performance 7)all accident must be investigated to reinforce the safety program 8)accidents statistics shoul be compllied 9)site offices should have a list of the following emergency telephone no. fire 101,ambulance 102,police 100, 10)everyone should participate insure the implementati
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 901109689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: viju128@gmail.com
Subject: 3638-10

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.rajendar nagar kolhapur
Students Name (Surname_First Name_Middle Name) shinde vijay namdeo
Exam No. 3638
Working Day No. 10
Date (DD/MM/YYYY) 18/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge today we observed road consruction,and casting of beam and flooring work.
Details of how you Planned & Executed the allotted work we jus obsrved the work how the flooring is done what precoutions should be taken while placing the tiles,how to adjust the error if any. beam:while casting the beam we observed shutring work,rebaring work,steel framing,and then concreting. road:while constructing road we obsrved levlling of road,compaction of road by using the plain type of roller.
Details of the Construction Procedure / Activity / Technology learned today Flooring:they used vetrifide tiles,of size (2*2)feet.vetrifide tiles dosnt need polishing,and skirting size is 50mm,flooring work stars from entry of door an then continued till end ofthe room.tiles r placed at right angle toeach other. to maintain the color they used the white cement. an acordingly cement color is changed to match the color wid the tiles. so that it should look gud. beam:while casting the beam the shutring work should be proper there should notbe any gap if there while concreting there will occur lekage an leads honey combing,and strenght will reduce. so shutring work should be check before placing the concrete.an d it should withstand the load. steel bars should be properly placed acording to there position.rebaring is done by drilling the hole accoring to the dimetre of the steel bar.The position of the steel bars are adusted and cast few mm away from surface so that steel bars shouldd not get corrode. road:levelling of road is done in manner in the middle of the road the thick is more then rear side. if we observed the road from the rear side it wil look like mountian. The thickness in the midle wil be more such thing is done for the proper percolation .so that there should not be stagnant of water water should drain properly.
Details of the Construction Materials learned today most of the organization and enggs consider store keeping is the minor activitiy in the constuction field.however reachers indicates that store keeping is one of the most important activity in any construction site. coz 65% is the material cost which can go up due to negligenc.the store keeper can control this wastage .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today sectional drawing mention the finished floor level of all stories mention the height of sills, doors, windows,openings,lofts&rooling shutters clearly from finished floar levels details of elevations, cornics, drop pardi and projection of slabAt terrace level with referance to building line thicness of water proofing treatment for toilets and terrace
Details of the Bye Laws referred today buidling regulations setback line, building line, control line height of building built up area
Details of any Managerial Skill learned today levelling of road is done in manner in the middle of the road the thick is more then rear side. if we observed the road from the rear side it wil look like mountian. The thickness in the midle wil be more such thing is done for the proper percolation .so that there should not be stagnant of water water should drain properly.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for 1 m2 external painting if we use cement color for external paint 1 kg cement paint =1 lit = 25 Rs it use for 50 Ft2 area labour rate = 2.5 Rs/1 Ft2 primer 1 lit = 80 Rs materil cost = 25 + 80 = 105 Rs labour = 125 Rs total cost = 20 Rs so, 1 m2 cost = 49.50 Rs = 50 Rs/ 1m2
Result of RATE ANALYSIS ( Rs per Unit ) 50 Rs/ 1m2
Todays BUZZ Word a construction engg. must adopted safety precaution as an integral part of his job 1) the basic funtion of managment is planning and programing 2)lowering of operational cost and reduction in no. of accient on the site should be its ultimate objective 3)the accident prevention program has to be well planned and efectively monitored and controlled 4)accidents can be min. by insuring the implementation of the safety court at all levels in the construction project enlist are some datas 5)site engg along with the contractors must work out a safety program 6)all the working spots should be inspecte periodically for ddefect in any flaws in the program and to monitor its performance 7)all accident must be investigated to reinforce the safety program 8)accidents statistics shoul be compllied 9)site offices should have a list of the following emergency telephone no. fire 101,ambulance 102,police 100, 10)everyone should participate insure the implementati
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 901109689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-10

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Tirmare pradya A.
Exam No. 13572
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To see concreting in ground beams.
Details of how you Planned & Executed the allotted work 1. First we had seen detailed drawings of building, R.C.C. drawing of ground beam. 2. Then we had seen actual work on site with site in charge.
Details of the Construction Procedure / Activity / Technology learned today 1. First formwork is prepared as per size of ground beam. 2. Then this formwork is placed in its position. Below this P.C,C, layer of 75mm thick is given previously. 3. Then reinforcement is placed as per the R.C.C. drawing . 4. Then it is checked by the site in charge. 5. Then concreting is done as per specification. 6. Then vibration is done.
Details of the Construction Materials learned today M-SEAL DR. FIXIT : 1. This is waterproofing chemical. 2. It is commonly used while making concrete for slab. 3. Its dosage is fixed as per specification of this product. 4. It is in liquid form. 5. Due to this material floors can be made completely watertight.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today GARDENING : Large area is reserved for gardening. Different species of grass & plants is to be planted. It creates healthy environment conditions in that locality.
Details of the Construction / Engineering Drawings observed today Detailed drawings & centerline plan of 2BHK bungllows,R.C.C. drawings of ground beam.
Details of the Bye Laws referred today HEIGHT OF MEZZANINE FLOOR : 1. Minimum height of mezzanine floor = 2.2 m. 2. Headroom under mezzanine floor shall not be less than 2.2 m.
Details of any Managerial Skill learned today Utilisation of labour & proper distribution of work, to complete the work perfectly & speedily.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PAINTING : per sq.m. Two coats of primer & two coats of distemper are given for external painting. Distemper = 0.40 kg = 45.00 Rs. Cement primer = 0.45 lit. = 35.00 Rs. Turpentine = 0.11 lit. = 30.00 Rs. Labour cost & other equipments = 7% TOTAL = 120.00 Rs.per sq.m.
Result of RATE ANALYSIS ( Rs per Unit ) 120.00 Rs.per sq.m.
Todays BUZZ Word Basic facilities to workers at site : 1. Temparary sheds for workers. 2. Availibility of drinking water storage. 3. Boxes for keeping equipments. 4. First aid kit. 5. There should be a tee stall.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut, Mob. No. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-10

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) katral raju maruti
Exam No. 13562
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To see concreting in ground beams.
Details of how you Planned & Executed the allotted work 1. First we had seen detailed drawings of building, R.C.C. drawing of ground beam. 2. Then we had seen actual work on site with site in charge.
Details of the Construction Procedure / Activity / Technology learned today 1. First formwork is prepared as per size of ground beam. 2. Then this formwork is placed in its position. Below this P.C,C, layer of 75mm thick is given previously. 3. Then reinforcement is placed as per the R.C.C. drawing . 4. Then it is checked by the site in charge. 5. Then concreting is done as per specification. 6. Then vibration is done.
Details of the Construction Materials learned today M-SEAL DR. FIXIT : 1. This is waterproofing chemical. 2. It is commonly used while making concrete for slab. 3. Its dosage is fixed as per specification of this product. 4. It is in liquid form. 5. Due to this material floors can be made completely watertight.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today GARDENING : Large area is reserved for gardening. Different species of grass & plants is to be planted. It creates healthy environment conditions in that locality.
Details of the Construction / Engineering Drawings observed today Detailed drawings & centerline plan of 2BHK bungllows,R.C.C. drawings of ground beam.
Details of the Bye Laws referred today HEIGHT OF MEZZANINE FLOOR : 1. Minimum height of mezzanine floor = 2.2 m. 2. Headroom under mezzanine floor shall not be less than 2.2 m.
Details of any Managerial Skill learned today Utilisation of labour & proper distribution of work, to complete the work perfectly & speedily.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PAINTING : per sq.m. Two coats of primer & two coats of distemper are given for external painting. Distemper = 0.40 kg = 45.00 Rs. Cement primer = 0.45 lit. = 35.00 Rs. Turpentine = 0.11 lit. = 30.00 Rs. Labour cost & other equipments = 7% TOTAL = 120.00 Rs.per sq.m.
Result of RATE ANALYSIS ( Rs per Unit ) 120.00 Rs.per sq.m.
Todays BUZZ Word Basic facilities to workers at site : 1. Temparary sheds for workers. 2. Availibility of drinking water storage. 3. Boxes for keeping equipments. 4. First aid kit. 5. There should be a tee stall.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut, Mob. No. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883-10

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr. rajenra nagar kolhapur
Students Name (Surname_First Name_Middle Name) saurabh arora
Exam No. 10883
Working Day No. 10
Date (DD/MM/YYYY) 18/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge today we observed road consruction,and casting of beam and flooring work.
Details of how you Planned & Executed the allotted work we jus obsrved the work how the flooring is done what precoutions should be taken while placing the tiles,how to adjust the error if any. beam:while casting the beam we observed shutring work,rebaring work,steel framing,and then concreting. road:while constructing road we obsrved levlling of road,compaction of road by using the plain type of roller.
Details of the Construction Procedure / Activity / Technology learned today Flooring:they used vetrifide tiles,of size (2*2)feet.vetrifide tiles dosnt need polishing,and skirting size is 50mm,flooring work stars from entry of door an then continued till end ofthe room.tiles r placed at right angle toeach other. to maintain the color they used the white cement. an acordingly cement color is changed to match the color wid the tiles. so that it should look gud. beam:while casting the beam the shutring work should be proper there should notbe any gap if there while concreting there will occur lekage an leads honey combing,and strenght will reduce. so shutring work should be check before placing the concrete.an d it should withstand the load. steel bars should be properly placed acording to there position.rebaring is done by drilling the hole accoring to the dimetre of the steel bar.The position of the steel bars are adusted and cast few mm away from surface so that steel bars shouldd not get corrode. road:levelling of road is done in manner in the middle of the road the thick is more then rear side. if we observed the road from the rear side it wil look like mountian. The thickness in the midle wil be more such thing is done for the proper percolation .so that there should not be stagnant of water water should drain properly.
Details of the Construction Materials learned today most of the organization and enggs consider store keeping is the minor activitiy in the constuction field.however reachers indicates that store keeping is one of the most important activity in any construction site. coz 65% is the material cost which can go up due to negligenc.the store keeper can control this wastage .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today sectional drawing mention the finished floor level of all stories mention the height of sills, doors, windows,openings,lofts&rooling shutters clearly from finished floar levels details of elevations, cornics, drop pardi and projection of slabAt terrace level with referance to building line thicness of water proofing treatment for toilets and terrace
Details of the Bye Laws referred today buidling regulations setback line, building line, control line height of building built up area
Details of any Managerial Skill learned today levelling of road is done in manner in the middle of the road the thick is more then rear side. if we observed the road from the rear side it wil look like mountian. The thickness in the midle wil be more such thing is done for the proper percolation .so that there should not be stagnant of water water should drain properly.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for 1 m2 external painting if we use cement color for external paint 1 kg cement paint =1 lit = 25 Rs it use for 50 Ft2 area labour rate = 2.5 Rs/1 Ft2 primer 1 lit = 80 Rs materil cost = 25 + 80 = 105 Rs labour = 125 Rs total cost = 20 Rs so, 1 m2 cost = 49.50 Rs = 50 Rs/ 1m2
Result of RATE ANALYSIS ( Rs per Unit ) 50 Rs/ 1m2
Todays BUZZ Word a construction engg. must adopted safety precaution as an integral part of his job 1) the basic funtion of managment is planning and programing 2)lowering of operational cost and reduction in no. of accient on the site should be its ultimate objective 3)the accident prevention program has to be well planned and efectively monitored and controlled 4)accidents can be min. by insuring the implementation of the safety court at all levels in the construction project enlist are some datas 5)site engg along with the contractors must work out a safety program 6)all the working spots should be inspecte periodically for ddefect in any flaws in the program and to monitor its performance 7)all accident must be investigated to reinforce the safety program 8)accidents statistics shoul be compllied 9)site offices should have a list of the following emergency telephone no. fire 101,ambulance 102,police 100, 10)everyone should participate insure the implementati
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 901109689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13561-10

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Jadhav Sardar Swaroop J.
Exam No. 13561
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To see concreting in ground beams.
Details of how you Planned & Executed the allotted work 1. First we had seen detailed drawings of building, R.C.C. drawing of ground beam. 2. Then we had seen actual work on site with site in charge.
Details of the Construction Procedure / Activity / Technology learned today 1. First formwork is prepared as per size of ground beam. 2. Then this formwork is placed in its position. Below this P.C,C, layer of 75mm thick is given previously. 3. Then reinforcement is placed as per the R.C.C. drawing . 4. Then it is checked by the site in charge. 5. Then concreting is done as per specification. 6. Then vibration is done.
Details of the Construction Materials learned today M-SEAL DR. FIXIT : 1. This is waterproofing chemical. 2. It is commonly used while making concrete for slab. 3. Its dosage is fixed as per specification of this product. 4. It is in liquid form. 5. Due to this material floors can be made completely watertight.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today GARDENING : Large area is reserved for gardening. Different species of grass & plants is to be planted. It creates healthy environment conditions in that locality.
Details of the Construction / Engineering Drawings observed today Detailed drawings & centerline plan of 2BHK bungllows,R.C.C. drawings of ground beam.
Details of the Bye Laws referred today HEIGHT OF MEZZANINE FLOOR : 1. Minimum height of mezzanine floor = 2.2 m. 2. Headroom under mezzanine floor shall not be less than 2.2 m.
Details of any Managerial Skill learned today Utilisation of labour & proper distribution of work, to complete the work perfectly & speedily.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PAINTING : per sq.m. Two coats of primer & two coats of distemper are given for external painting. Distemper = 0.40 kg = 45.00 Rs. Cement primer = 0.45 lit. = 35.00 Rs. Turpentine = 0.11 lit. = 30.00 Rs. Labour cost & other equipments = 7% TOTAL = 120.00 Rs.per sq.m.
Result of RATE ANALYSIS ( Rs per Unit ) 120.00 Rs.per sq.m.
Todays BUZZ Word Basic facilities to workers at site : 1. Temparary sheds for workers. 2. Availibility of drinking water storage. 3. Boxes for keeping equipments. 4. First aid kit. 5. There should be a tee stall.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut, Mob. No. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-10

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Jade Madhavrao Anil
Exam No. 13560
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To see concreting in ground beams.
Details of how you Planned & Executed the allotted work 1. First we had seen detailed drawings of building, R.C.C. drawing of ground beam. 2. Then we had seen actual work on site with site in charge.
Details of the Construction Procedure / Activity / Technology learned today 1. First formwork is prepared as per size of ground beam. 2. Then this formwork is placed in its position. Below this P.C,C, layer of 75mm thick is given previously. 3. Then reinforcement is placed as per the R.C.C. drawing . 4. Then it is checked by the site in charge. 5. Then concreting is done as per specification. 6. Then vibration is done.
Details of the Construction Materials learned today M-SEAL DR. FIXIT : 1. This is waterproofing chemical. 2. It is commonly used while making concrete for slab. 3. Its dosage is fixed as per specification of this product. 4. It is in liquid form. 5. Due to this material floors can be made completely watertight.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today GARDENING : Large area is reserved for gardening. Different species of grass & plants is to be planted. It creates healthy environment conditions in that locality.
Details of the Construction / Engineering Drawings observed today Detailed drawings & centerline plan of 2BHK bungllows,R.C.C. drawings of ground beam.
Details of the Bye Laws referred today HEIGHT OF MEZZANINE FLOOR : 1. Minimum height of mezzanine floor = 2.2 m. 2. Headroom under mezzanine floor shall not be less than 2.2 m.
Details of any Managerial Skill learned today Utilisation of labour & proper distribution of work, to complete the work perfectly & speedily.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PAINTING : per sq.m. Two coats of primer & two coats of distemper are given for external painting. Distemper = 0.40 kg = 45.00 Rs. Cement primer = 0.45 lit. = 35.00 Rs. Turpentine = 0.11 lit. = 30.00 Rs. Labour cost & other equipments = 7% TOTAL = 120.00 Rs.per sq.m.
Result of RATE ANALYSIS ( Rs per Unit ) 120.00 Rs.per sq.m.
Todays BUZZ Word Basic facilities to workers at site : 1. Temparary sheds for workers. 2. Availibility of drinking water storage. 3. Boxes for keeping equipments. 4. First aid kit. 5. There should be a tee stall.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut, Mob. No. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/18/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558-10

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Chavan Shivprasad Prakash
Exam No. 13558
Working Day No. 10
Date (DD/MM/YYYY) 18.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To see concreting in ground beams.
Details of how you Planned & Executed the allotted work 1. First we had seen detailed drawings of building, R.C.C. drawing of ground beam. 2. Then we had seen actual work on site with site in charge.
Details of the Construction Procedure / Activity / Technology learned today done. CONCRETING IN GROUND BEAMS ; 1. First formwork is prepared as per size of ground beam. 2. Then this formwork is placed in its position. Below this P.C,C, layer of 75mm thick is given previously. 3. Then reinforcement is placed as per the R.C.C. drawing . 4. Then it is checked by the site in charge. 5. Then concreting is done as per specification. 6. Then vibration is done.
Details of the Construction Materials learned today M-SEAL DR. FIXIT : 1. This is waterproofing chemical. 2. It is commonly used while making concrete for slab. 3. Its dosage is fixed as per specification of this product. 4. It is in liquid form. 5. Due to this material floors can be made completely watertight.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today GARDENING : Large area is reserved for gardening. Different species of grass & plants is to be planted. It creates healthy environment conditions in that locality.
Details of the Construction / Engineering Drawings observed today Detailed drawings & centerline plan of 2BHK bungllows,R.C.C. drawings of ground beam.
Details of the Bye Laws referred today HEIGHT OF MEZZANINE FLOOR : 1. Minimum height of mezzanine floor = 2.2 m. 2. Headroom under mezzanine floor shall not be less than 2.2 m.
Details of any Managerial Skill learned today Utilisation of labour & proper distribution of work, to complete the work perfectly & speedily.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PAINTING : per sq.m. Two coats of primer & two coats of distemper are given for external painting. Distemper = 0.40 kg = 45.00 Rs. Cement primer = 0.45 lit. = 35.00 Rs. Turpentine = 0.11 lit. = 30.00 Rs. Labour cost & other equipments = 7% TOTAL = 120.00 Rs.per sq.m.
Result of RATE ANALYSIS ( Rs per Unit ) 120.00 Rs.per sq.m.
Todays BUZZ Word SITE SAFETY & BASIC FACILITIES TO WORKERS AT SITE : Site safety : 1. Use of helmate. 2. Use of gumboots for concreting workers. 3. Use of hand gloves for concreting workers. 4. Strong & rigid lift should be errected. 5. Strong & rigid errection of formwork,scaffolding. 6. First aid kit. 7. Use of safety belts. 8. Safety goggles for welding, grinding etc. 9. Fire fighting equipments. 10. Accidents statistics should be complied. Basic facilities to workers at site : 1. Temparary sheds for workers. 2. Availibility of drinking water storage. 3. Boxes for keeping equipments. 4. First aid kit. 5. There should be a tee stall.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut, Mob. No. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: profiipathan@gmail.com
Subject: Testing 18.12.2010 - 1

Company Name Star Tech Infra
Project Name & Site Address p
Students Name (Surname_First Name_Middle Name) p
Exam No. p
Working Day No. p
Date (DD/MM/YYYY) p
Site Reporting Time (HH:MM am/pm) p
Site Leaving Time (HH:MM am/pm) p
Details of the Work Allotted to you today by the Site In-Charge p
Details of how you Planned & Executed the allotted work p
Details of the Construction Procedure / Activity / Technology learned today p
Details of the Construction Materials learned today p
Details of Environment Caring Technology / Methodology / Procedure / Product learned today p
Details of the Construction / Engineering Drawings observed today p
Details of the Bye Laws referred today p
Details of any Managerial Skill learned today p
RATE ANALYSIS (Detailed Stepwise Calculations required) p
Result of RATE ANALYSIS ( Rs per Unit ) p
Todays BUZZ Word p
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Camera
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge p
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-09

Company Name Bhima Builders & Developers
Project Name & Site Address Wind gate S.R No.83 Near New Palace Kolhapur
Students Name (Surname_First Name_Middle Name) Mohare Vishal Bhalchandra
Exam No. 13564
Working Day No. 09
Date (DD/MM/YYYY) 17/12/10
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check the formwork of the slab.
Details of how you Planned & Executed the allotted work a) First we observe the details plans of beam, column formwork b) Then we check the formwork as per plans. c) Then we check the formwork of leakages etc.
Details of the Construction Procedure / Activity / Technology learned today a) On ground for clean the site below cantilever slab b) Then P.C.C. bed is apply to cleaned site. c) Steel props are stand vertical on p.c.c. bed. d) Top of props Steel square fixed with nails. e) Then steel plates are situated on this props on all sides. f) Plywood is placed to this plates as size of cantilever slab. g) Reinforcement is placed on this formwork. h) Side cover placed at bottom and sides i) Concrete is poured in it and tamping is done. j) The top surface is leveled with float rod
Details of the Construction Materials learned today * Concrete- * Cement 43 grade. * Admixture- superplasticizer. * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. distribution bar 12mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel props useing for supportting member replaced by BAMBU..
Details of the Construction / Engineering Drawings observed today Cantilever slab drawing. Their projection from main slab Size of beams which slab supported Type of slab Depth of slab
Details of the Bye Laws referred today BALCONY - Balcony of a maximum width of 1.2m. shall be permitted free of F.S.I. at any floor excluding ground and terrace floor not more than 10% percent of the total F.S.I.
Details of any Managerial Skill learned today To check the formwork to beam as in drawing. To check dimensions of slab from main slab. To check any gaps between horizontal formwork. To check the props which support. To check the concreting procedure
RATE ANALYSIS (Detailed Stepwise Calculations required) PER 10 M2 PAINTING - SR.NO. ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 WHITE WASH LIME 0.75 KG 20.00/- 15.00/- WATER 2.50 LIT. lum sum GLUE 25 GM. 450.00/- 11.00/- POLISH PAPER 1 NO. 15.00/- 15.00/- 2 DISTEMPER APP. DISTEMPER 2.0 KG. 400.00/- 800.00/- WATER 1.50 LIT. lum sum GLUE 50 GM. 450.00/- 22.50/- POLISH PAPER 1 NO. 15.00/- 15.00/- 3 OIL PAINT WOOD PRIMER 0.80 LIT. 120.00/- 96.00/- For door TERPNTINE 0.40 LIT. 45.00/- 18.00/- PUTTY 5 KG. 270.00/- 1350.00/- POLISH PAPER 2 NOS. 15.00/- 30.00/- FOR WINDOW ZINC CHROMET PRIMER 1 LIT. 170.00/- 170.00/- OIL PAINT 1 LIT. 120.00/- 120.00/- TERPENTINE 0.25 LIT. 45.00/- 12.00/- ------------------------------------------ ---------------------------------- TOTAL = 2675.00/-
Result of RATE ANALYSIS ( Rs per Unit ) 267.5 /-
Todays BUZZ Word CONSTRUCTION MACHINERIES:- SR.NO. NAME DECRIPTION CAPACITY 1 wheel barrows, trolly shifting, any type up to 1.5 tone of material 2 small capacity concreting at upper up to 1/5 cement cocrete mixer floor bag. 3 form vibretor casting slab ----------- 4 dumper transporting material 2 brass 5 loader compaction up to 3.5 tone 6 sand washing concreting up to 1.5 m3
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: rathod2211@gmail.com
Subject: 10893-09

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell,karande mala
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge - Final Line Out for Septic Tank - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Electrification.
Details of how you Planned & Executed the allotted work - We first 5 members went in a group to prepare Daily Report. - Then we Studied the brick bat coba of Flat No 701 & Flat No 702 in Terrace of Bedrooms. - Then we went to flat no 608, 609 to study electrification.
Details of the Construction Procedure / Activity / Technology learned today The following construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested.
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Solar Panels we used for water heating purpose - Septic Tank is being constructed for C Wing \" Vishwa Enclave\".
Details of the Construction / Engineering Drawings observed today - Electrification Plans - Septic Tank Layouts. - Parking Layout.
Details of the Bye Laws referred today - Meter room - Common antena for television transmission reception.
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR INTERNAL PAINTING\" # A) Application of washable oil Bond Distemper 3 Coat for: 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bedroom = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bathroom = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m B) Deduction = 37 sq.m.....(For doors, windows) Deduct 50 % = 218.21 - 37/2 = 199.71 sq.m C) Material Required : 1. Dry Distemper = 0.2 x 199.71 = 40 kg 2. Glue = 1 kg D) Cost of Material: 1. Dry Distemper = 40 x 430 = 17200/- 2. Glue = 1.36 x 450 = 612/- TOTAL = 17812/- E) Cost Of Labour: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Male Mazdoor = 12 x 120 = 1440/- 4. T & P = 1000/- TOTAL = 4640/- F) Total Cost = D + E = 22452/- G) Add 10 % Contractors Profit = 2245.2/- H) Grand Total = 24697.2/- I) Rate Per sq.m = 123.66/-
Result of RATE ANALYSIS ( Rs per Unit ) 123.66/-
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: shinde_shital7@yahoo.com
Subject: 10884-09

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell,karande mala
Students Name (Surname_First Name_Middle Name) shinde shital vilasrao
Exam No. 10884
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge - Final Line Out for Septic Tank - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Electrification.
Details of how you Planned & Executed the allotted work - We first 5 members went in a group to prepare Daily Report. - Then we Studied the brick bat coba of Flat No 701 & Flat No 702 in Terrace of Bedrooms. - Then we went to flat no 608, 609 to study electrification
Details of the Construction Procedure / Activity / Technology learned today The following construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested.
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Solar Panels we used for water heating purpose - Septic Tank is being constructed for C Wing \" Vishwa Enclave\".
Details of the Construction / Engineering Drawings observed today - Electrification Plans - Septic Tank Layouts. - Parking Layout.
Details of the Bye Laws referred today - Meter room - Common antena for television transmission reception
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR INTERNAL PAINTING\" # A) Application of washable oil Bond Distemper 3 Coat for: 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bedroom = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bathroom = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m B) Deduction = 37 sq.m.....(For doors, windows) Deduct 50 % = 218.21 - 37/2 = 199.71 sq.m C) Material Required : 1. Dry Distemper = 0.2 x 199.71 = 40 kg 2. Glue = 1 kg D) Cost of Material: 1. Dry Distemper = 40 x 430 = 17200/- 2. Glue = 1.36 x 450 = 612/- TOTAL = 17812/- E) Cost Of Labour: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Male Mazdoor = 12 x 120 = 1440/- 4. T & P = 1000/- TOTAL = 4640/- F) Total Cost = D + E = 22452/- G) Add 10 % Contractors Profit = 2245.2/- H) Grand Total = 24697.2/- I) Rate Per sq.m = 123.66/-
Result of RATE ANALYSIS ( Rs per Unit ) 123.66/-
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10893-09

Company Name V. S. Joshi & Associates
Project Name & Site Address VVishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) kamble ankit
Exam No. 10893
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 5.30PM
Details of the Work Allotted to you today by the Site In-Charge - Final Line Out for Septic Tank - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Electrification.
Details of how you Planned & Executed the allotted work - We first 5 members went in a group to prepare Daily Report. - Then we Studied the brick bat coba of Flat No 701 & Flat No 702 in Terrace of Bedrooms. - Then we went to flat no 608, 609 to study electrification
Details of the Construction Procedure / Activity / Technology learned today The following construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested.
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Solar Panels we used for water heating purpose - Septic Tank is being constructed for C Wing \" Vishwa Enclave\".
Details of the Construction / Engineering Drawings observed today - Electrification Plans - Septic Tank Layouts. - Parking Layout.
Details of the Bye Laws referred today - Meter room - Common antena for television transmission reception
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR INTERNAL PAINTING\" # A) Application of washable oil Bond Distemper 3 Coat for: 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bedroom = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bathroom = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m B) Deduction = 37 sq.m.....(For doors, windows) Deduct 50 % = 218.21 - 37/2 = 199.71 sq.m C) Material Required : 1. Dry Distemper = 0.2 x 199.71 = 40 kg 2. Glue = 1 kg D) Cost of Material: 1. Dry Distemper = 40 x 430 = 17200/- 2. Glue = 1.36 x 450 = 612/- TOTAL = 17812/- E) Cost Of Labour: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Male Mazdoor = 12 x 120 = 1440/- 4. T & P = 1000/- TOTAL = 4640/- F) Total Cost = D + E = 22452/- G) Add 10 % Contractors Profit = 2245.2/- H) Grand Total = 24697.2/- I) Rate Per sq.m = 123.66/-
Result of RATE ANALYSIS ( Rs per Unit ) 123.66/-
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-09

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell,karande mala
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge - Final Line Out for Septic Tank - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Electrification.
Details of how you Planned & Executed the allotted work - We first 5 members went in a group to prepare Daily Report. - Then we Studied the brick bat coba of Flat No 701 & Flat No 702 in Terrace of Bedrooms. - Then we went to flat no 608, 609 to study electrification
Details of the Construction Procedure / Activity / Technology learned today The following construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested.
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Solar Panels we used for water heating purpose - Septic Tank is being constructed for C Wing \" Vishwa Enclave\".
Details of the Construction / Engineering Drawings observed today - Electrification Plans - Septic Tank Layouts. - Parking Layout.
Details of the Bye Laws referred today - Meter room - Common antena for television transmission reception
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR INTERNAL PAINTING\" # A) Application of washable oil Bond Distemper 3 Coat for: 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bedroom = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bathroom = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m B) Deduction = 37 sq.m.....(For doors, windows) Deduct 50 % = 218.21 - 37/2 = 199.71 sq.m C) Material Required : 1. Dry Distemper = 0.2 x 199.71 = 40 kg 2. Glue = 1 kg D) Cost of Material: 1. Dry Distemper = 40 x 430 = 17200/- 2. Glue = 1.36 x 450 = 612/- TOTAL = 17812/- E) Cost Of Labour: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Male Mazdoor = 12 x 120 = 1440/- 4. T & P = 1000/- TOTAL = 4640/- F) Total Cost = D + E = 22452/- G) Add 10 % Contractors Profit = 2245.2/- H) Grand Total = 24697.2/- I) Rate Per sq.m = 123.66/-
Result of RATE ANALYSIS ( Rs per Unit ) 123.66/-
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge KETAN CHARPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-09

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) PATIL ADITYA PANDURANG
Exam No. 13538
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J Chougule Mob no - 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-09

Company Name V. S. Joshi & Associates
Project Name & Site Address VVishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) janbandhu rakshit janbandhu
Exam No. 10875
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 5.30PM
Details of the Work Allotted to you today by the Site In-Charge - Final Line Out for Septic Tank - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Electrification.
Details of how you Planned & Executed the allotted work - We first 5 members went in a group to prepare Daily Report. - Then we Studied the brick bat coba of Flat No 701 & Flat No 702 in Terrace of Bedrooms. - Then we went to flat no 608, 609 to study electrification
Details of the Construction Procedure / Activity / Technology learned today The following construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested.
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Solar Panels we used for water heating purpose - Septic Tank is being constructed for C Wing \" Vishwa Enclave\".
Details of the Construction / Engineering Drawings observed today - Electrification Plans - Septic Tank Layouts. - Parking Layout.
Details of the Bye Laws referred today - Meter room - Common antena for television transmission reception
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR INTERNAL PAINTING\" # A) Application of washable oil Bond Distemper 3 Coat for: 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bedroom = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bathroom = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m B) Deduction = 37 sq.m.....(For doors, windows) Deduct 50 % = 218.21 - 37/2 = 199.71 sq.m C) Material Required : 1. Dry Distemper = 0.2 x 199.71 = 40 kg 2. Glue = 1 kg D) Cost of Material: 1. Dry Distemper = 40 x 430 = 17200/- 2. Glue = 1.36 x 450 = 612/- TOTAL = 17812/- E) Cost Of Labour: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Male Mazdoor = 12 x 120 = 1440/- 4. T & P = 1000/- TOTAL = 4640/- F) Total Cost = D + E = 22452/- G) Add 10 % Contractors Profit = 2245.2/- H) Grand Total = 24697.2/- I) Rate Per sq.m = 123.66/-
Result of RATE ANALYSIS ( Rs per Unit ) 123.66/-
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-09

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Hasabnis Ketaki Bhagwan
Exam No. 13527
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To visit and study the construction site at Kandalgaon by Pooja Builders.
Details of how you Planned & Executed the allotted work We all went in group to the site. We met the site incharge. He gave us the plans of the building. We observed the work and construction work was going on.
Details of the Construction Procedure / Activity / Technology learned today We saw the construction of stair-case,slab,beams,columns. We saw the curing process.
Details of the Construction Materials learned today 1. Cement-43 grade,53 grade Bagalkot supreme. 2. Flyash Bricks. 3. Tor steel,Mild steel bars for construction of beams and columns.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The water used at the site was brought in a tank by paying hard cash.So the labourers were using the water carefully without doing wastage.
Details of the Construction / Engineering Drawings observed today > Plan for 1st and 2nd floor. > Plan for furniture and electrification.
Details of the Bye Laws referred today > The stair case was designed according to the sizes provided in bye-laws. > The bye law specifications regarding minimum sizes of different rooms have been followed.
Details of any Managerial Skill learned today > The structural Enggineer visited the site to inspect the work quality. > The site incharge kept proper record of all the work going on.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"INTERNAL PAINTING\". Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m Result of RATE ANALYSIS ( Rs per Unit ): Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge AMAR DHAMAKLE, CELL NO.9922244154.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-08

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bauchkar deepak yuvaraj
Exam No. 13554
Working Day No. 08
Date (DD/MM/YYYY) 17/12/10
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 05:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flats to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today \"PROCEDURE FOR EXTERNAL PLASTERING\" - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days.
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall.
Details of the Bye Laws referred today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-09

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) MANGAONKAR MANOJ DATTATRAY
Exam No. 13536
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J Chougule Mob no - 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-09

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) JAGADALE ASHVANI RAMRAO
Exam No. 13530
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J Chougule Mob no - 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-09

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. J.J Chougule Mob no - 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-09

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Shinde Shraddha Tukaram
Exam No. 10901
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - Final Line Out for Septic Tank - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Electrification. ------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work - We first 5 members went in a group to prepare Daily Report. - Then we Studied the brick bat coba of Flat No 701 & Flat No 702 in Terrace of Bedrooms. - Then we went to flat no 608, 609 to study electrification. -------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today The following construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested. -------------------------------------------------------------------------------------
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire. ------------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Solar Panels we used for water heating purpose - Septic Tank is being constructed for C Wing \" Vishwa Enclave\". ------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today - Electrification Plans - Septic Tank Layouts. - Parking Layout. ----------------------------------------------------------------------------
Details of the Bye Laws referred today - Meter room - Common antena for television transmission reception.
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR INTERNAL PAINTING\" # A) Application of washable oil Bond Distemper 3 Coat for: 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bedroom = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bathroom = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m B) Deduction = 37 sq.m.....(For doors, windows) Deduct 50 % = 218.21 - 37/2 = 199.71 sq.m C) Material Required : 1. Dry Distemper = 0.2 x 199.71 = 40 kg 2. Glue = 1 kg D) Cost of Material: 1. Dry Distemper = 40 x 430 = 17200/- 2. Glue = 1.36 x 450 = 612/- TOTAL = 17812/- E) Cost Of Labour: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Male Mazdoor = 12 x 120 = 1440/- 4. T & P = 1000/- TOTAL = 4640/- F) Total Cost = D + E = 22452/- G) Add 10 % Contractors Profit = 2245.2/- H) Grand Total = 24697.2/- I) Rate Per sq.m = 123.66/- -------------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) 123.66/-
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: patilpratibha7070@yahoo.in
Subject: 10896-09

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) patil pratibha dilip
Exam No. 10896
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. RAJIV JAGTAP
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-09

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) babar moreshwar mahipati
Exam No. 10873
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. RAJIV JAGTAP
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-08

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bhoite Vishal Rajaram
Exam No. 13555
Working Day No. 08
Date (DD/MM/YYYY) 17/12/10
Site Reporting Time (HH:MM am/pm) 10AM
Site Leaving Time (HH:MM am/pm) 5PM
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flats to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today \"PROCEDURE FOR EXTERNAL PLASTERING\" - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days.
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall.
Details of the Bye Laws referred today 1) Parapet. 2) Balcony. 3) Corridor.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: vishalsapakal124@gmail.com
Subject: 10882-09

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) sapakal vishal manohar
Exam No. 10882
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. RAJIV JAGTAP
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-09

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Jape Vishwajeet Ramesh
Exam No. 10892
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - Final Line Out for Septic Tank - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Electrification. ------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work - We first 5 members went in a group to prepare Daily Report. - Then we Studied the brick bat coba of Flat No 701 & Flat No 702 in Terrace of Bedrooms. - Then we went to flat no 608, 609 to study electrification. -------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today The following construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested. -------------------------------------------------------------------------------------
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire. ------------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Solar Panels we used for water heating purpose - Septic Tank is being constructed for C Wing \" Vishwa Enclave\". ------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today - Electrification Plans - Septic Tank Layouts. - Parking Layout. ----------------------------------------------------------------------------
Details of the Bye Laws referred today - Meter room - Common antena for television transmission reception. ----------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality. ---------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR INTERNAL PAINTING\" # A) Application of washable oil Bond Distemper 3 Coat for: 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bedroom = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bathroom = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m B) Deduction = 37 sq.m.....(For doors, windows) Deduct 50 % = 218.21 - 37/2 = 199.71 sq.m C) Material Required : 1. Dry Distemper = 0.2 x 199.71 = 40 kg 2. Glue = 1 kg D) Cost of Material: 1. Dry Distemper = 40 x 430 = 17200/- 2. Glue = 1.36 x 450 = 612/- TOTAL = 17812/- E) Cost Of Labour: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Male Mazdoor = 12 x 120 = 1440/- 4. T & P = 1000/- TOTAL = 4640/- F) Total Cost = D + E = 22452/- G) Add 10 % Contractors Profit = 2245.2/- H) Grand Total = 24697.2/- I) Rate Per sq.m = 123.66/- -------------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) 123.66/-
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-09

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Nagvekar Yogesh Deepak
Exam No. 10894
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - Final Line Out for Septic Tank - Prepare the Daily Report. - Brick Bat Coba & Waterproofing. - Electrification. ------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work - We first 5 members went in a group to prepare Daily Report. - Then we Studied the brick bat coba of Flat No 701 & Flat No 702 in Terrace of Bedrooms. - Then we went to flat no 608, 609 to study electrification. -------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today The following construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested. -------------------------------------------------------------------------------------
Details of the Construction Materials learned today 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire. ------------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Solar Panels we used for water heating purpose - Septic Tank is being constructed for C Wing \" Vishwa Enclave\". ------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today - Electrification Plans - Septic Tank Layouts. - Parking Layout. ----------------------------------------------------------------------------
Details of the Bye Laws referred today - Meter room - Common antena for television transmission reception.
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR INTERNAL PAINTING\" # A) Application of washable oil Bond Distemper 3 Coat for: 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bedroom = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bathroom = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m B) Deduction = 37 sq.m.....(For doors, windows) Deduct 50 % = 218.21 - 37/2 = 199.71 sq.m C) Material Required : 1. Dry Distemper = 0.2 x 199.71 = 40 kg 2. Glue = 1 kg D) Cost of Material: 1. Dry Distemper = 40 x 430 = 17200/- 2. Glue = 1.36 x 450 = 612/- TOTAL = 17812/- E) Cost Of Labour: 1. Painter (Head) = 2 x 250 = 500/- 2. Painter = 10 x 170 = 1700/- 3. Male Mazdoor = 12 x 120 = 1440/- 4. T & P = 1000/- TOTAL = 4640/- F) Total Cost = D + E = 22452/- G) Add 10 % Contractors Profit = 2245.2/- H) Grand Total = 24697.2/- I) Rate Per sq.m = 123.66/- -------------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rate Per sq.m = 123.66/-
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine. ----------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr Amol A. Mulay (9922507376) ---------------------------------------------------------------------------------
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-09

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) yadav hrisheekesh deepak
Exam No. 10885
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. RAJIV JAGTAP
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: salmanbaig18@gmail.com
Subject: 10888-09

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) baig salman samad
Exam No. 10888
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. RAJIV JAGTAP
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-09

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Lad Manoj Sadashiv
Exam No. 13534
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the work of slab casting.
Details of how you Planned & Executed the allotted work we divide ourself in two groups two member of our group were at slab floor where slab casting was going on. remaining were at mixing station. we observed carefully the mix proportion. we note all the data in our note book.
Details of the Construction Procedure / Activity / Technology learned today removel of side formwork the side formwork can be removed after 24 hrs there is no nessity of sideform afterone day. curing prosses curing prosess is very important prosess in construction
Details of the Construction Materials learned today join material- Dr fixit is mostly used jointing chemical in construction
Details of Environment Caring Technology / Methodology / Procedure / Product learned today steel plates used for formwork. use of wooden plates leads to more deforestration
Details of the Construction / Engineering Drawings observed today R.C.C steel structure design it consist of all thea details of steel design of columns beams,slab
Details of the Bye Laws referred today min size of W.C= 0.9m,x 1.25m
Details of any Managerial Skill learned today co-oprative and time management
RATE ANALYSIS (Detailed Stepwise Calculations required) let area of internal wall to be painted = 1 brass amount of primar required =0.5 lit.=160 Rs. amount of oil paint required for further two coat =1 lit. =350 Rs. painter pay = 80 per brass. total amount required= 590 RS per brass
Result of RATE ANALYSIS ( Rs per Unit ) 590 RS./brass
Todays BUZZ Word construction machines 1.vibrator - for proper compaction 2.JCB- for excavation of columns, footings, plinth filling etc. 3.cutter-for cutting steel bars of required size. 4.transit mixer-used to transport concreat from R.M.C. plant to site
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-09

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Patil Vrishali Vitthal
Exam No. 13541
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the work of slab casting.
Details of how you Planned & Executed the allotted work we divide ourself in two groups two member of our group were at slab floor where slab casting was going on. remaining were at mixing station. we observed carefully the mix proportion. we note all the data in our note book.
Details of the Construction Procedure / Activity / Technology learned today removel of side formwork the side formwork can be removed after 24 hrs there is no nessity of sideform afterone day. curing prosses curing prosess is very important prosess in construction
Details of the Construction Materials learned today join material- Dr fixit is mostly used jointing chemical in construction
Details of Environment Caring Technology / Methodology / Procedure / Product learned today steel plates used for formwork. use of wooden plates leads to more deforestration
Details of the Construction / Engineering Drawings observed today R.C.C steel structure design it consist of all thea details of steel design of columns beams,slab
Details of the Bye Laws referred today min size of W.C= 0.9m,x 1.25m
Details of any Managerial Skill learned today co-oprative and time management
RATE ANALYSIS (Detailed Stepwise Calculations required) let area of internal wall to be painted = 1 brass amount of primar required =0.5 lit.=160 Rs. amount of oil paint required for further two coat =1 lit. =350 Rs. painter pay = 80 per brass. total amount required= 590 RS per brass
Result of RATE ANALYSIS ( Rs per Unit ) 590 RS./brass
Todays BUZZ Word construction machines 1.vibrator - for proper compaction 2.JCB- for excavation of columns, footings, plinth filling etc. 3.cutter-for cutting steel bars of required size. 4.transit mixer-used to transport concreat from R.M.C. plant to site
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: shindesagara@gmail.com
Subject: 13570-09

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sonavne Mayur Madhukar
Exam No. 13570
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of Drainage system of public building:- Calculation of total length of pipe required. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required,fix the position of each Trap. 3)Third student placed the pipe on marked alignment with their respective length & direction,position of foul gas pipe were fixed. 4)Fourth student made the connections at each & every junction, note down the types of trap provided. 5)Fifth student checked the work as per drawing & requirements. 6)The main outlet drainage pipe were connected to main sewage line. .
Details of the Construction Procedure / Activity / Technology learned today Supervision of Drainage system of public building:- a)Drainage system should be design for the daily outgoing of water. b)First mark changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. c)Then mark the alignment,every junction of pipe on inner & outer side of wall. d)Drilled the hole in wall as per diameter of pipe required. e)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. f)Every junction of pipe should be well jointed & free from leakages . g)Good binding material should be used for connecting two pipes. h)Elbows,T,collers should be used at correct place. i)The no. of joints should be avoided. j)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. k)Provide the trap as per requirement nahani trap for bathroom , Gully trap at every change in vertical direction. l)Normal slope was design for each connection for removal of solid waste. m)To avoid the leakages the separate drainage line were arranged from joint of Wc pan to trap . n)Correct position & design requirements of manhole were checked. .
Details of the Construction Materials learned today Pipes used for drainage work:- PVC PIPE,NAHANI TRAP ,GUULY TRAP,WC PANS ,P Q S TRAPS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Generally the waste water from municiple sewage line dropped in nearer river or any huge water source.The waste water includes the various types of bacteria , chemicals ,other harmful things which damages to river environment. If waste water is treated at released place then it will more helpful for environment & treated water can be used again & again. .
Details of the Construction / Engineering Drawings observed today Layout for waste water system. Various traps used in drainage system according to their function. .
Details of the Bye Laws referred today Minimum & maximum dimensions of municiple sewage line. Various diameters of pipe & type of pipe used in waste water system. .
Details of any Managerial Skill learned today To check the material supplied by supplier to clarify the mistakes if any. So as to keep supply continuous and efficient.Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that. .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS (Detailed Stepwise Calculations required): Rate analysis for internal painting:- Surface area of wall= 50 sq.m Rate per sq m =Rs.25/- Total =1250/- Wastage 5% 6 Scaffolding 15 Labour 70 Total=91 .
Result of RATE ANALYSIS ( Rs per Unit ) 100/-sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4)
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.P.Bharamal .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523-09

Company Name Chougule Sawant Developers
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) devkar vikram dilip
Exam No. 13523
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To visit and study the constrruction site at Kandalgaon of Pooja Builders
Details of how you Planned & Executed the allotted work We all went in group to the site. On the site we met with the site incharge then he gave us the plans of the building. then according to plans we started examining the building.
Details of the Construction Procedure / Activity / Technology learned today We saw the construction of stair-case,slab,beams,columns. We saw the curing process.
Details of the Construction Materials learned today 1. Cement-43 grade,53 grade Bagalkot supreme. 2. Flyash Bricks. 3. Tor steel,Mild steel bars for construction of beams and columns.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The water used at the site was brought from the tank by paying it,so the labourers used the water economically without doing wastage.
Details of the Construction / Engineering Drawings observed today 1. Plan for 1st and 2nd floor. 2. Plan for furniture and electrification
Details of the Bye Laws referred today 1. The stair case was designed according to the sizes provided by bye-laws. 2. The bye law specifications regarding minimum sizes of different rooms have been followed.
Details of any Managerial Skill learned today 1. The structural Enggineer visited the site he inspected the site. 2. The site incharge kept a proper record of all the work going on.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"INTERNAL PAINTING\". Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge AMAR DHAMAKLE PH NO.9922244154
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: rameshkharat1987@gmail.com
Subject: 13532-09

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Ramesh Laxman
Exam No. 13532
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the work of slab casting.
Details of how you Planned & Executed the allotted work we divide ourself in two groups two member of our group were at slab floor where slab casting was going on. remaining were at mixing station. we observed carefully the mix proportion. we note all the data in our note book.
Details of the Construction Procedure / Activity / Technology learned today removel of side formwork the side formwork can be removed after 24 hrs there is no nessity of sideform afterone day. curing prosses curing prosess is very important prosess in construction
Details of the Construction Materials learned today join material- Dr fixit is mostly used jointing chemical in construction
Details of Environment Caring Technology / Methodology / Procedure / Product learned today steel plates used for formwork. use of wooden plates leads to more deforestration
Details of the Construction / Engineering Drawings observed today R.C.C steel structure design it consist of all the details of steel design of columns beams,slab
Details of the Bye Laws referred today min size of W.C= 0.9m,x 1.25m
Details of any Managerial Skill learned today co-oprative and time management
RATE ANALYSIS (Detailed Stepwise Calculations required) let area of internal wall to be painted = 1 brass amount of primar required =0.5 lit.=160 Rs. amount of oil paint required for further two coat =1 lit. =350 Rs. painter pay = 80 per brass. total amount required= 590 RS per brass
Result of RATE ANALYSIS ( Rs per Unit ) 590 RS./brass
Todays BUZZ Word construction machines 1.vibrator - for proper compaction 2.JCB- for excavation of columns, footings, plinth filling etc. 3.cutter-for cutting steel bars of required size. 4.transit mixer-used to transport concreat from R.M.C. plant to site
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: prasadkharat@ymail.com
Subject: 13531-09

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Prasad Ramachandra
Exam No. 13531
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the work of slab casting.
Details of how you Planned & Executed the allotted work we divide ourself in two groups two member of our group were at slab floor where slab casting was going on. remaining were at mixing station. we observed carefully the mix proportion. we note all the data in our note book.
Details of the Construction Procedure / Activity / Technology learned today removel of side formwork the side formwork can be removed after 24 hrs there is no nessity of sideform afterone day. curing prosses curing prosess is very important prosess in construction
Details of the Construction Materials learned today join material- Dr fixit is mostly used jointing chemical in construction
Details of Environment Caring Technology / Methodology / Procedure / Product learned today steel plates used for formwork. use of wooden plates leads to more deforestration
Details of the Construction / Engineering Drawings observed today R.C.C steel structure design it consist of all the details of steel design of columns beams,slab
Details of the Bye Laws referred today min size of W.C= 0.9m,x 1.25m
Details of any Managerial Skill learned today co-oprative and time management
RATE ANALYSIS (Detailed Stepwise Calculations required) let area of internal wall to be painted = 1 brass amount of primar required =0.5 lit.=160 Rs. amount of oil paint required for further two coat =1 lit. =350 Rs. painter pay = 80 per brass. total amount required= 590 RS per brass
Result of RATE ANALYSIS ( Rs per Unit ) 590 RS./brass
Todays BUZZ Word construction machines 1.vibrator - for proper compaction 2.JCB- for excavation of columns, footings, plinth filling etc. 3.cutter-for cutting steel bars of required size. 4.transit mixer-used to transport concreat from R.M.C. plant to site
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521-09

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) bagmare dinesh shriram
Exam No. 13521
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To visit and study the constrruction site at Kandalgaon of Pooja Builders
Details of how you Planned & Executed the allotted work We all went in group to the site. On the site we met with the site incharge then he gave us the plans of the building. then according to plans we started examining the building.
Details of the Construction Procedure / Activity / Technology learned today We saw the construction of stair-case,slab,beams,columns. We saw the curing process.
Details of the Construction Materials learned today 1. Cement-43 grade,53 grade Bagalkot supreme. 2. Flyash Bricks. 3. Tor steel,Mild steel bars for construction of beams and columns.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The water used at the site was brought from the tank by paying it,so the labourers used the water economically without doing wastage.
Details of the Construction / Engineering Drawings observed today 1. Plan for 1st and 2nd floor. 2. Plan for furniture and electrification.
Details of the Bye Laws referred today 1. The stair case was designed according to the sizes provided by bye-laws. 2. The bye law specifications regarding minimum sizes of different rooms have been followed.
Details of any Managerial Skill learned today 1. The structural Enggineer visited the site he inspected the site. 2. The site incharge kept a proper record of all the work going on.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"INTERNAL PAINTING\". Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge AMAR DHAMAKLE PH NO.9922244154
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-09

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) fulari sujata shankar
Exam No. 13559
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 10.00am
Site Leaving Time (HH:MM am/pm) 5.00pm
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\"
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flats to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor in charge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today Supervision of Drainage system of public building:- a)Drainage system should be design for the daily outgoing of water. b)First mark changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. c)Then mark the alignment,every junction of pipe on inner & outer side of wall. d)Drilled the hole in wall as per diameter of pipe required. e)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. f)Every junction of pipe should be well jointed & free from leakages . g)Good binding material should be used for connecting two pipes. h)Elbows,T,collers should be used at correct place. i)The no. of joints should be avoided. j)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. k)Provide the trap as per requirement nahani trap for bathroom , Gully trap at every change in vertical direction. l)Normal slope was design for each connection for removal of solid waste. m)To avoid the leakages the separate drainage line were arranged from joint of Wc pan to trap . n)Correct position & design requirements of manhole were checked. .
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Generally the waste water from municiple sewage line dropped in nearer river or any huge water source.The waste water includes the various types of bacteria , chemicals ,other harmful things which damages to river environment. If waste water is treated at released place then it will more helpful for environment & treated water can be used again & again. .
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall. .
Details of the Bye Laws referred today 1) Parapet. 2) Balcony. 3) Corridor.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m Result of RATE ANALYSIS ( Rs per Unit ): Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-09

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kolekar Shyam Suryakant
Exam No. 13533
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the work of slab casting.
Details of how you Planned & Executed the allotted work we divide ourself in two groups two member of our group were at slab floor where slab casting was going on. remaining were at mixing station. we observed carefully the mix proportion. we note all the data in our note book.
Details of the Construction Procedure / Activity / Technology learned today removel of side formwork the side formwork can be removed after 24 hrs there is no nessity of sideform afterone day. curing prosses curing prosess is very important prosess in construction
Details of the Construction Materials learned today join material- Dr fixit is mostly used jointing chemical in construction
Details of Environment Caring Technology / Methodology / Procedure / Product learned today steel plates used for formwork. use of wooden plates leads to more deforestration
Details of the Construction / Engineering Drawings observed today R.C.C steel structure design it consist of all the details of steel design of columns beams,slab
Details of the Bye Laws referred today min size of W.C= 0.9m,x 1.25m
Details of any Managerial Skill learned today co-oprative and time management
RATE ANALYSIS (Detailed Stepwise Calculations required) let area of internal wall to be painted = 1 brass amount of primar required =0.5 lit.=160 Rs. amount of oil paint required for further two coat =1 lit. =350 Rs. painter pay = 80 per brass. total amount required= 590 RS per brass
Result of RATE ANALYSIS ( Rs per Unit ) 590 RS./brass
Todays BUZZ Word construction machines 1.vibrator - for proper compaction 2.JCB- for excavation of columns, footings, plinth filling etc. 3.cutter-for cutting steel bars of required size. 4.transit mixer-used to transport concreat from R.M.C. plant to site
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: nitinpatil22.2010@rediffmail.com
Subject: 10879-09

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil nitin dilip
Exam No. 10879
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: cool.sushant007@gmail.com
Subject: 10880-09

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil sushant digambar
Exam No. 10880
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-09

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) misal swapnil shivaji
Exam No. 10877
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-09

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHAIKH RIZWAN KHALIL
Exam No. 13545
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-09

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SALOKHE SUDARSHAN ANIL
Exam No. 13544
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge TO observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-09

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SINGH RAJAN RAJENDRA BAHADUR
Exam No. 13548
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe how the casting of slab is done.
Details of how you Planned & Executed the allotted work we first divide ourself into groups . one group is on the floor of casting of slab and one near mixing machinery. then noting down the things related to that.
Details of the Construction Procedure / Activity / Technology learned today After the installation of all the machinery required for casting of slab. then after deciding the proportion required the mixing of material is started and with the help of lift and bucket arrangement the material is placed at the required place. after placing compaction is done using needle vibrator. after 1 days , curing is done. and side formwork is removed. slab formwork is removed after 15 days and beam formwork is removed after 21 days.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panels are used.
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m Result of RATE ANALYSIS ( Rs per Unit ): 70
Result of RATE ANALYSIS ( Rs per Unit ) 70 Rs
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-09

Company Name Deshmukh Developers
Project Name & Site Address Deshmukh Developments,Pratibha Nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Birajdar Minaxi Renuk
Exam No. 13556
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today the site incharge give us the work to observe how the slab casting is carried out 1) How the machneries are placed 2) What proportion materials are used to make a concrete
Details of how you Planned & Executed the allotted work 1) We are planned two students are stand where concrete is made by using weigh batcher 2) And two students are stands where slab casting work is carried out 3) We are divide the groups 4) And to observe the work carefully
Details of the Construction Procedure / Activity / Technology learned today Construction Procedure : 1) Scaffolding is done for lifting the concrete material 2) Near this revolving drum with material conveyor is placed 3) Then behind it the weigh batcher is placed on firm level ground 4) Near the lifting machine platform is made on which the material is placed 5) This concrete is carried by women workers where slab casting work is done 6) The concrete is levelled and maintained slab thickness various equipment are used 7) After 4-5 hours the curing must be done to avoid cracks in a slab
Details of the Construction Materials learned today Materials used today are as follows : 1) Trowel, showel, surface, ghoda, raisa, panga, handglows 2) 170kg sand,220kg aggregate, 25 litre water,1 bottle admixture are used in one concrete mix 3) Above all material are mixed for one minute
Details of Environment Caring Technology / Methodology / Procedure / Product learned today To use solar power energy therefore save the electric current ,natural gas. Since the cost is reduced ,no any maintainance is required, it is suitable one.
Details of the Construction / Engineering Drawings observed today Today we are observe beam & slab detail sheet : 1) To observe position of bars are placed in a slab 2) To observe type of beam continous, cantilever etc.
Details of the Bye Laws referred today Today we are refer Bye Laws for: 1) To study about width of parking for four wheeler, two wheeler 2) Minimum Width = 6.0m wide 3) At least three entrance and exit are provided for residential appartment
Details of any Managerial Skill learned today Managerial skill : He has a good communication skill when talk with customers and workers
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS OF INTERNAL PAINTING : WALL PUTTY = MATERIAL 2.50 RS SQ FEET LABOUR = 2.00 RS / SQ FEET COLOUR = 2.00 RS /SQ FEET LABOUR = 2.00 RS /SQ FEET (2.50 + 2) * 100 SQ FEET = 450 RS + (2+2) *100 SQ FEET = 400 RS 9.29 = 950 RS 1 M2 = 102.26 = 103 RS
Result of RATE ANALYSIS ( Rs per Unit ) 103 RS
Todays BUZZ Word \" CONSTRUCTION MACHINERIES \" 1)COSMOS MACHNERIES-01 : This is used for lifting the large amount of brick at required floor. The iron rectangular conveyor jointed to cables which is lift the bricks from lower level to higher required level. Cables are lifted by hook. The capacity of conveyor is about 40-50 brick at once a time. The Machine is placed in a proper manner such way that sand bags,heavy loads placed on it to avoid sliding,overturning of machneries. Once the machine is fixed it can not move at any cost. It is operated on electric current meter. In this way the bricks are lifted by COSMOS MACHNERIES. 2) COSMOS MACHNERIES- 02 : This is used for lifting the cement bags & sand bags. Rectangular conveyor is jointed to cable & cable is lifted by hook. The capacity if machine to lift cement bags is about 125kg of cement. And the capacity to lift sand bags is about 6-7 bags at once a time. The COSMOS Machneries is operted on generator. The machine is attached to near by column & firmly fixed to avoid unwanted accident. In this way the sand, cement bags lifted at required level. 3) Drilling machine, Cutting machine, smoother machine are used on site.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Abhijit Bhosale Mob no. 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-09

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Bulbule
Exam No. 13557
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the formwork of the slab.
Details of how you Planned & Executed the allotted work a) First we observe the details plans of beam, column formwork b) Then we check the formwork as per plans. c) Then we check the formwork of leakages etc.
Details of the Construction Procedure / Activity / Technology learned today Cantilever slab a) On ground for clean the site below cantilever slab b) Then P.C.C. bed is apply to cleaned site. c) Steel props are stand vertical on p.c.c. bed. d) Top of props Steel square fixed with nails. e) Then steel plates are situated on this props on all sides. f) Plywood is placed to this plates as size of cantilever slab. g) Reinforcement is placed on this formwork. h) Side cover placed at bottom and sides i) Concrete is poured in it and tamping is done. j) The top surface is leveled with float rod
Details of the Construction Materials learned today * Concrete- * Cement 43 grade. * Admixture- superplasticizer. * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. distribution bar 12mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel props useing for supportting member replaced by BAMBU..
Details of the Construction / Engineering Drawings observed today Cantilever slab drawing. Their projection from main slab Size of beams which slab supported Type of slab Depth of slab
Details of the Bye Laws referred today BALCONY - Balcony of a maximum width of 1.2m. shall be permitted free of F.S.I. at any floor excluding ground and terrace floor not more than 10% percent of the total F.S.I.
Details of any Managerial Skill learned today To check the formwork to beam as in drawing. To check dimensions of slab from main slab. To check any gaps between horizontal formwork. To check the props which support. To check the concreting procedure.
RATE ANALYSIS (Detailed Stepwise Calculations required) PER 10 M2 PAINTING - SR.NO. ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 WHITE WASH LIME 0.75 KG 20.00/- 15.00/- WATER 2.50 LIT. lum sum GLUE 25 GM. 450.00/- 11.00/- POLISH PAPER 1 NO. 15.00/- 15.00/- 2 DISTEMPER DISTEMPER 2.0 KG. 400.00/- 800.00/- WATER 1.50 LIT. lum sum GLUE 50 GM. 450.00/- 22.50/- POLISH PAPER 1 NO. 15.00/- 15.00/- 3 OIL PAINT WOOD PRIMER 0.80 LIT. 120.00/- 96.00/- For door TERPNTINE 0.40 LIT. 45.00/- 18.00/- PUTTY 5 KG. 270.00/- 1350.00/- POLISH PAPER 2 NOS. 15.00/- 30.00/- FOR WINDOW ZINC CHROMET PRIMER 1 LIT. 170.00/- 170.00/- OIL PAINT 1 LIT. 120.00/- 120.00/- TERPENTINE 0.25 LIT. 45.00/- 12.00/- ------------------------------------------ ---------------------------- TOTAL = 2675.00/-
Result of RATE ANALYSIS ( Rs per Unit ) 2675.00 per m2
Todays BUZZ Word CONSTRUCTION MACHINERIES:- SR.NO. NAME DECRIPTION CAPACITY 1 wheel barrows, trolly shifting, any type up to 1.5 tone of material 2 small capacity concreting at upper up to 1/5 cement cocrete mixer floor bag. 3 form vibretor casting slab ----------- 4 dumper transporting material 2 brass 5 loader compaction up to 3.5 tone 6 sand washing concreting up to 1.5 m3
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-09

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Suyvanshi patil Pratiksinh Vilas
Exam No. 13549
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flats to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today \"PROCEDURE FOR EXTERNAL PLASTERING\" - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days.
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall.
Details of the Bye Laws referred today 1) Parapet. 2) Balcony. 3) Corridor.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-09

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudev
Exam No. 10891
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge 1)To see expansion joint in row bungalow . 2)To see p.c.c. coba on parapet wall. 3)TO attend the client which come for pazatation. .
Details of how you Planned & Executed the allotted work We see all work together & observed all work . .
Details of the Construction Procedure / Activity / Technology learned today Expansion joint- 1)Expansion joint in between bungalow is constructed from bottom to top by using material of Tharmocole in between throughout to wall column slab to parapet wall. P.c.c coba- 1)concrete is spread on parapet wall in leveled surface 2)After curing mortar with cement paste are used for finishing & than cure 3)maintain slope of p.c.c. coba in inward of terrace .
Details of the Construction Materials learned today mortar, concrete tharmocole ,brick ,cement paste. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today paving block used for to avoid soil erosion on ground surface. .
Details of the Construction / Engineering Drawings observed today terrace plan,terrace drainage drawing. .
Details of the Bye Laws referred today Parapet wall provided 1.2m according to bye-laws. .
Details of any Managerial Skill learned today the project should be properly managed & handled by giving proper direction to the workers so as to complete the project in time & to achieve quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-09

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Suyvanshi patil Pratiksinh Vilas
Exam No. 13549
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 05:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flats to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today \"PROCEDURE FOR EXTERNAL PLASTERING\" - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days.
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall.
Details of the Bye Laws referred today 1) Parapet. 2) Balcony. 3) Corridor.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-09

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Suyvanshi patil Pratiksinh Vilas
Exam No. 13549
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 05:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flats to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today \"PROCEDURE FOR EXTERNAL PLASTERING\" - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days.
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall.
Details of the Bye Laws referred today 1) Parapet. 2) Balcony. 3) Corridor.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: Rohit_patil361@rediffmail.com
Subject: 13565-09

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Patil Rohit Ashok
Exam No. 13565
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the formwork of the slab.
Details of how you Planned & Executed the allotted work a) First we observe the details plans of beam, column formwork b) Then we check the formwork as per plans. c) Then we check the formwork of leakages etc.
Details of the Construction Procedure / Activity / Technology learned today Cantilever slab a) On ground for clean the site below cantilever slab b) Then P.C.C. bed is apply to cleaned site. c) Steel props are stand vertical on p.c.c. bed. d) Top of props Steel square fixed with nails. e) Then steel plates are situated on this props on all sides. f) Plywood is placed to this plates as size of cantilever slab. g) Reinforcement is placed on this formwork. h) Side cover placed at bottom and sides i) Concrete is poured in it and tamping is done. j) The top surface is leveled with float rod
Details of the Construction Materials learned today * Concrete- * Cement 43 grade. * Admixture- superplasticizer. * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. distribution bar 12mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel props useing for supportting member replaced by BAMBU..
Details of the Construction / Engineering Drawings observed today Cantilever slab drawing. Their projection from main slab Size of beams which slab supported Type of slab Depth of slab
Details of the Bye Laws referred today BALCONY - Balcony of a maximum width of 1.2m. shall be permitted free of F.S.I. at any floor excluding ground and terrace floor not more than 10% percent of the total F.S.I.
Details of any Managerial Skill learned today To check the formwork to beam as in drawing. To check dimensions of slab from main slab. To check any gaps between horizontal formwork. To check the props which support. To check the concreting procedure.
RATE ANALYSIS (Detailed Stepwise Calculations required) PER 10 M2 PAINTING - SR.NO. ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 WHITE WASH LIME 0.75 KG 20.00/- 15.00/- WATER 2.50 LIT. lum sum GLUE 25 GM. 450.00/- 11.00/- POLISH PAPER 1 NO. 15.00/- 15.00/- 2 DISTEMPER APP. DISTEMPER 2.0 KG. 400.00/- 800.00/- WATER 1.50 LIT. lum sum GLUE 50 GM. 450.00/- 22.50/- POLISH PAPER 1 NO. 15.00/- 15.00/- 3 OIL PAINT WOOD PRIMER 0.80 LIT. 120.00/- 96.00/- For door TERPNTINE 0.40 LIT. 45.00/- 18.00/- PUTTY 5 KG. 270.00/- 1350.00/- POLISH PAPER 2 NOS. 15.00/- 30.00/- FOR WINDOW ZINC CHROMET PRIMER 1 LIT. 170.00/- 170.00/- OIL PAINT 1 LIT. 120.00/- 120.00/- TERPENTINE 0.25 LIT. 45.00/- 12.00/- ------------------------------------------ ---------------------------------- TOTAL = 2675.00/-
Result of RATE ANALYSIS ( Rs per Unit ) 2675.00 per m2
Todays BUZZ Word CONSTRUCTION MACHINERIES:- SR.NO. NAME DECRIPTION CAPACITY 1 wheel barrows, trolly shifting, any type up to 1.5 tone of material 2 small capacity concreting at upper up to 1/5 cement cocrete mixer floor bag. 3 form vibretor casting slab ----------- 4 dumper transporting material 2 brass 5 loader compaction up to 3.5 tone 6 sand washing concreting up to 1.5 m3
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: v.g.ayyar@gmail.com
Subject: 13553-09

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Ayyar Vignesh Gopal
Exam No. 13553
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flats to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today \"PROCEDURE FOR EXTERNAL PLASTERING\" - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days.
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall.
Details of the Bye Laws referred today 1) Parapet. 2) Balcony. 3) Corridor.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-09

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the formwork of the slab.
Details of how you Planned & Executed the allotted work a) First we observe the details plans of beam, column formwork b) Then we check the formwork as per plans. c) Then we check the formwork of leakages etc.
Details of the Construction Procedure / Activity / Technology learned today Cantilever slab a) On ground for clean the site below cantilever slab b) Then P.C.C. bed is apply to cleaned site. c) Steel props are stand vertical on p.c.c. bed. d) Top of props Steel square fixed with nails. e) Then steel plates are situated on this props on all sides. f) Plywood is placed to this plates as size of cantilever slab. g) Reinforcement is placed on this formwork. h) Side cover placed at bottom and sides i) Concrete is poured in it and tamping is done. j) The top surface is leveled with float rod
Details of the Construction Materials learned today * Concrete- * Cement 43 grade. * Admixture- superplasticizer. * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. distribution bar 12mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel props useing for supportting member replaced by BAMBU..
Details of the Construction / Engineering Drawings observed today Cantilever slab drawing. Their projection from main slab Size of beams which slab supported Type of slab Depth of slab
Details of the Bye Laws referred today BALCONY - Balcony of a maximum width of 1.2m. shall be permitted free of F.S.I. at any floor excluding ground and terrace floor not more than 10% percent of the total F.S.I.
Details of any Managerial Skill learned today To check the formwork to beam as in drawing. To check dimensions of slab from main slab. To check any gaps between horizontal formwork. To check the props which support. To check the concreting procedure.
RATE ANALYSIS (Detailed Stepwise Calculations required) PER 10 M2 PAINTING - SR.NO. ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 WHITE WASH LIME 0.75 KG 20.00/- 15.00/- WATER 2.50 LIT. lum sum GLUE 25 GM. 450.00/- 11.00/- POLISH PAPER 1 NO. 15.00/- 15.00/- 2 DISTEMPER APP. DISTEMPER 2.0 KG. 400.00/- 800.00/- WATER 1.50 LIT. lum sum GLUE 50 GM. 450.00/- 22.50/- POLISH PAPER 1 NO. 15.00/- 15.00/- 3 OIL PAINT WOOD PRIMER 0.80 LIT. 120.00/- 96.00/- For door TERPNTINE 0.40 LIT. 45.00/- 18.00/- PUTTY 5 KG. 270.00/- 1350.00/- POLISH PAPER 2 NOS. 15.00/- 30.00/- FOR WINDOW ZINC CHROMET PRIMER 1 LIT. 170.00/- 170.00/- OIL PAINT 1 LIT. 120.00/- 120.00/- TERPENTINE 0.25 LIT. 45.00/- 12.00/- ------------------------------------------ ---------------------------------- TOTAL = 2675.00/-
Result of RATE ANALYSIS ( Rs per Unit ) 2675.00 per m2
Todays BUZZ Word CONSTRUCTION MACHINERIES:- SR.NO. NAME DECRIPTION CAPACITY 1 wheel barrows, trolly shifting, any type up to 1.5 tone of material 2 small capacity concreting at upper up to 1/5 cement cocrete mixer floor bag. 3 form vibretor casting slab ----------- 4 dumper transporting material 2 brass 5 loader compaction up to 3.5 tone 6 sand washing concreting up to 1.5 m3
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: vishal.mohare67@gmial.com
Subject: 13564-09

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Mohare Vishal Bhalchandra
Exam No. 13564
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the formwork of the slab.
Details of how you Planned & Executed the allotted work a) First we observe the details plans of beam, column formwork b) Then we check the formwork as per plans. c) Then we check the formwork of leakages etc.
Details of the Construction Procedure / Activity / Technology learned today Cantilever slab a) On ground for clean the site below cantilever slab b) Then P.C.C. bed is apply to cleaned site. c) Steel props are stand vertical on p.c.c. bed. d) Top of props Steel square fixed with nails. e) Then steel plates are situated on this props on all sides. f) Plywood is placed to this plates as size of cantilever slab. g) Reinforcement is placed on this formwork. h) Side cover placed at bottom and sides i) Concrete is poured in it and tamping is done. j) The top surface is leveled with float rod
Details of the Construction Materials learned today * Concrete- * Cement 43 grade. * Admixture- superplasticizer. * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. distribution bar 12mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel props useing for supportting member replaced by BAMBU..
Details of the Construction / Engineering Drawings observed today Cantilever slab drawing. Their projection from main slab Size of beams which slab supported Type of slab Depth of slab
Details of the Bye Laws referred today BALCONY - Balcony of a maximum width of 1.2m. shall be permitted free of F.S.I. at any floor excluding ground and terrace floor not more than 10% percent of the total F.S.I.
Details of any Managerial Skill learned today To check the formwork to beam as in drawing. To check dimensions of slab from main slab. To check any gaps between horizontal formwork. To check the props which support. To check the concreting procedure.
RATE ANALYSIS (Detailed Stepwise Calculations required) PER 10 M2 PAINTING - SR.NO. ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 WHITE WASH LIME 0.75 KG 20.00/- 15.00/- WATER 2.50 LIT. lum sum GLUE 25 GM. 450.00/- 11.00/- POLISH PAPER 1 NO. 15.00/- 15.00/- 2 DISTEMPER APP. DISTEMPER 2.0 KG. 400.00/- 800.00/- WATER 1.50 LIT. lum sum GLUE 50 GM. 450.00/- 22.50/- POLISH PAPER 1 NO. 15.00/- 15.00/- 3 OIL PAINT WOOD PRIMER 0.80 LIT. 120.00/- 96.00/- For door TERPNTINE 0.40 LIT. 45.00/- 18.00/- PUTTY 5 KG. 270.00/- 1350.00/- POLISH PAPER 2 NOS. 15.00/- 30.00/- FOR WINDOW ZINC CHROMET PRIMER 1 LIT. 170.00/- 170.00/- OIL PAINT 1 LIT. 120.00/- 120.00/- TERPENTINE 0.25 LIT. 45.00/- 12.00/- ------------------------------------------ ---------------------------------- TOTAL = 2675.00/-
Result of RATE ANALYSIS ( Rs per Unit ) 2675.00 per m2
Todays BUZZ Word CONSTRUCTION MACHINERIES:- SR.NO. NAME DECRIPTION CAPACITY 1 wheel barrows, trolly shifting, any type up to 1.5 tone of material 2 small capacity concreting at upper up to 1/5 cement cocrete mixer floor bag. 3 form vibretor casting slab ----------- 4 dumper transporting material 2 brass 5 loader compaction up to 3.5 tone 6 sand washing concreting up to 1.5 m3
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-09

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Sharad Shankarrao
Exam No. 10897
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of curing of slab by pending method. .
Details of how you Planned & Executed the allotted work we observed how the mortar is prepared i.e whether it is on correct proportion or not to avoid leakage from it.& then we observed how the ponds were made. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of curing by pounding method .in this method first mortar is prepared in suitable proportion the surface which is to be used for curing is cleaned first.the ponding method is commonly adopted for curing of concrete slabs or pavement .this method consist of storing water to a depth off 50mm on the surface by constructing small ponds. .
Details of the Construction Materials learned today today we discussed about the aggregates .aggregates provide 70-80% of concrete volume .therefore it must be strong durable & of proper shape .also it should be well graded & should not be chemically reactive.aggregates are cheaper than cement &give volume stability & durability to concrete. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today for ground water recharging ,rain water should be used through the soak pits. .
Details of the Construction / Engineering Drawings observed today today we referred the plumbing drawing. .
Details of the Bye Laws referred today in bye-laws today we referred width & no.of exits for various occupancies .
Details of any Managerial Skill learned today the project should be properly managed & handled by giving proper direction to the workers so as to complete the project in time & to achieve quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Drum Width In. (cm) Width In. (cm) Inside Turn Radius In. (cm) Pneumatic Tire Rollers n/a 72 (183.0) 108 (274.5) Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4) .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-09

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Abhishek Dadasaheb
Exam No. 10895
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of curing of slab by pending method. .
Details of how you Planned & Executed the allotted work we observed how the mortar is prepared i.e whether it is on correct proportion or not to avoid leakage from it.& then we observed how the ponds were made. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of curing by pounding method .in this method first mortar is prepared in suitable proportion the surface which is to be used for curing is cleaned first.the ponding method is commonly adopted for curing of concrete slabs or pavement .this method consist of storing water to a depth off 50mm on the surface by constructing small ponds. .
Details of the Construction Materials learned today today we discussed about the aggregates .aggregates provide 70-80% of concrete volume .therefore it must be strong durable & of proper shape .also it should be well graded & should not be chemically reactive.aggregates are cheaper than cement &give volume stability & durability to concrete. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today for ground water recharging ,rain water should be used through the soak pits. .
Details of the Construction / Engineering Drawings observed today today we referred the plumbing drawing. .
Details of the Bye Laws referred today in bye-laws today we referred width & no.of exits for various occupancies .
Details of any Managerial Skill learned today the project should be properly managed & handled by giving proper direction to the workers so as to complete the project in time & to achieve quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Drum Width In. (cm) Width In. (cm) Inside Turn Radius In. (cm) Pneumatic Tire Rollers n/a 72 (183.0) 108 (274.5) Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4) .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: buntyphonde@gmail.com
Subject: 10899-09

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Phonde Pravin Tukaram
Exam No. 10899
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of curing of slab by pending method. .
Details of how you Planned & Executed the allotted work we observed how the mortar is prepared i.e whether it is on correct proportion or not to avoid leakage from it.& then we observed how the ponds were made. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of curing by pounding method .in this method first mortar is prepared in suitable proportion the surface which is to be used for curing is cleaned first.the ponding method is commonly adopted for curing of concrete slabs or pavement .this method consist of storing water to a depth off 50mm on the surface by constructing small ponds. .
Details of the Construction Materials learned today today we discussed about the aggregates .aggregates provide 70-80% of concrete volume .therefore it must be strong durable & of proper shape .also it should be well graded & should not be chemically reactive.aggregates are cheaper than cement &give volume stability & durability to concrete. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today for ground water recharging ,rain water should be used through the soak pits. .
Details of the Construction / Engineering Drawings observed today today we referred the plumbing drawing. .
Details of the Bye Laws referred today in bye-laws today we referred width & no.of exits for various occupancies .
Details of any Managerial Skill learned today the project should be properly managed & handled by giving proper direction to the workers so as to complete the project in time & to achieve quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Drum Width In. (cm) Width In. (cm) Inside Turn Radius In. (cm) Pneumatic Tire Rollers n/a 72 (183.0) 108 (274.5) Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4) .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-09

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Tambe Trusha Sitaram
Exam No. 10902
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of curing of slab by pending method. .
Details of how you Planned & Executed the allotted work we observed how the mortar is prepared i.e whether it is on correct proportion or not to avoid leakage from it.& then we observed how the ponds were made. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of curing by pounding method .in this method first mortar is prepared in suitable proportion the surface which is to be used for curing is cleaned first.the ponding method is commonly adopted for curing of concrete slabs or pavement .this method consist of storing water to a depth off 50mm on the surface by constructing small ponds. .
Details of the Construction Materials learned today today we discussed about the aggregates .aggregates provide 70-80% of concrete volume .therefore it must be strong durable & of proper shape .also it should be well graded & should not be chemically reactive.aggregates are cheaper than cement &give volume stability & durability to concrete. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today for ground water recharging ,rain water should be used through the soak pits. .
Details of the Construction / Engineering Drawings observed today today we referred the plumbing drawing. .
Details of the Bye Laws referred today in bye-laws today we referred width & no.of exits for various occupancies .
Details of any Managerial Skill learned today the project should be properly managed & handled by giving proper direction to the workers so as to complete the project in time & to achieve quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Drum Width In. (cm) Width In. (cm) Inside Turn Radius In. (cm) Pneumatic Tire Rollers n/a 72 (183.0) 108 (274.5) Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4) .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-09

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83, NEW NAGALA PARK, KOP.
Students Name (Surname_First Name_Middle Name) Redekar Shantanu Ravindra
Exam No. 13566
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the formwork of the slab.
Details of how you Planned & Executed the allotted work a) First we observe the details plans of beam, column formwork b) Then we check the formwork as per plans. c) Then we check the formwork of leakages etc.
Details of the Construction Procedure / Activity / Technology learned today Cantilever slab a) On ground for clean the site below cantilever slab b) Then P.C.C. bed is apply to cleaned site. c) Steel props are stand vertical on p.c.c. bed. d) Top of props Steel square fixed with nails. e) Then steel plates are situated on this props on all sides. f) Plywood is placed to this plates as size of cantilever slab. g) Reinforcement is placed on this formwork. h) Side cover placed at bottom and sides i) Concrete is poured in it and tamping is done. j) The top surface is leveled with float rod
Details of the Construction Materials learned today * Concrete- * Cement 43 grade. * Admixture- superplasticizer. * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. distribution bar 12mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel props useing for supportting member replaced by BAMBU..
Details of the Construction / Engineering Drawings observed today Cantilever slab drawing. Their projection from main slab Size of beams which slab supported Type of slab Depth of slab
Details of the Bye Laws referred today BALCONY - Balcony of a maximum width of 1.2m. shall be permitted free of F.S.I. at any floor excluding ground and terrace floor not more than 10% percent of the total F.S.I.
Details of any Managerial Skill learned today To check the formwork to beam as in drawing. To check dimensions of slab from main slab. To check any gaps between horizontal formwork. To check the props which support. To check the concreting procedure.
RATE ANALYSIS (Detailed Stepwise Calculations required) PER 10 M2 PAINTING - SR.NO. ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 WHITE WASH LIME 0.75 KG 20.00/- 15.00/- WATER 2.50 LIT. lum sum GLUE 25 GM. 450.00/- 11.00/- POLISH PAPER 1 NO. 15.00/- 15.00/- 2 DISTEMPER APP. DISTEMPER 2.0 KG. 400.00/- 800.00/- WATER 1.50 LIT. lum sum GLUE 50 GM. 450.00/- 22.50/- POLISH PAPER 1 NO. 15.00/- 15.00/- 3 OIL PAINT WOOD PRIMER 0.80 LIT. 120.00/- 96.00/- For door TERPNTINE 0.40 LIT. 45.00/- 18.00/- PUTTY 5 KG. 270.00/- 1350.00/- POLISH PAPER 2 NOS. 15.00/- 30.00/- FOR WINDOW ZINC CHROMET PRIMER 1 LIT. 170.00/- 170.00/- OIL PAINT 1 LIT. 120.00/- 120.00/- TERPENTINE 0.25 LIT. 45.00/- 12.00/- ------------------------------------------ ---------------------------------- TOTAL = 2675.00/-
Result of RATE ANALYSIS ( Rs per Unit ) 2675.00 PER M2
Todays BUZZ Word CONSTRUCTION MACHINERIES:- SR.NO. NAME DECRIPTION CAPACITY 1 wheel barrows, trolly shifting, any type up to 1.5 tone of material 2 small capacity concreting at upper up to 1/5 cement cocrete mixer floor bag. 3 form vibretor casting slab ----------- 4 dumper transporting material 2 brass 5 loader compaction up to 3.5 tone 6 sand washing concreting up to 1.5 m3
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-09

Company Name Bhima Builders & Developers
Project Name & Site Address WIND-GATE, R.S. 83 , near new palace, new nagala park, kop.
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Ramchandra
Exam No. 13557
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the formwork of the slab.
Details of how you Planned & Executed the allotted work a) First we observe the details plans of beam, column formwork b) Then we check the formwork as per plans. c) Then we check the formwork of leakages etc.
Details of the Construction Procedure / Activity / Technology learned today Cantilever slab a) On ground for clean the site below cantilever slab b) Then P.C.C. bed is apply to cleaned site. c) Steel props are stand vertical on p.c.c. bed. d) Top of props Steel square fixed with nails. e) Then steel plates are situated on this props on all sides. f) Plywood is placed to this plates as size of cantilever slab. g) Reinforcement is placed on this formwork. h) Side cover placed at bottom and sides i) Concrete is poured in it and tamping is done. j) The top surface is leveled with float rod
Details of the Construction Materials learned today * Cement 43 grade. * Admixture- superplasticizer. * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. distribution bar 12mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel props useing for supportting member replaced by BAMBU..
Details of the Construction / Engineering Drawings observed today Cantilever slab drawing. Their projection from main slab Size of beams which slab supported Type of slab Depth of slab
Details of the Bye Laws referred today BALCONY - Balcony of a maximum width of 1.2m. shall be permitted free of F.S.I. at any floor excluding ground and terrace floor not more than 10% percent of the total F.S.I.
Details of any Managerial Skill learned today To check the formwork to beam as in drawing. To check dimensions of slab from main slab. To check any gaps between horizontal formwork. To check the props which support. To check the concreting procedure.
RATE ANALYSIS (Detailed Stepwise Calculations required) PER 10 M2 PAINTING - SR.NO. ITEM MATERIAL QUANTITY RATE PER AMOUNT 1 WHITE WASH LIME 0.75 KG 20.00/- 15.00/- WATER 2.50 LIT. lum sum GLUE 25 GM. 450.00/- 11.00/- POLISH PAPER 1 NO. 15.00/- 15.00/- 2 DISTEMPER APP. DISTEMPER 2.0 KG. 400.00/- 800.00/- WATER 1.50 LIT. lum sum GLUE 50 GM. 450.00/- 22.50/- POLISH PAPER 1 NO. 15.00/- 15.00/- 3 OIL PAINT WOOD PRIMER 0.80 LIT. 120.00/- 96.00/- For door TERPNTINE 0.40 LIT. 45.00/- 18.00/- PUTTY 5 KG. 270.00/- 1350.00/- POLISH PAPER 2 NOS. 15.00/- 30.00/- FOR WINDOW ZINC CHROMET PRIMER 1 LIT. 170.00/- 170.00/- OIL PAINT 1 LIT. 120.00/- 120.00/- TERPENTINE 0.25 LIT. 45.00/- 12.00/- ------------------------------------------ ---------------------------------- TOTAL = 2675.00/-
Result of RATE ANALYSIS ( Rs per Unit ) 2675.00 PER 10.0 M2
Todays BUZZ Word CONSTRUCTION MACHINERIES:- SR.NO. NAME DECRIPTION CAPACITY 1 wheel barrows, trolly shifting, any type up to 1.5 tone of material 2 small capacity concreting at upper up to 1/5 cement cocrete mixer floor bag. 3 form vibretor casting slab ----------- 4 dumper transporting material 2 brass 5 loader compaction up to 3.5 tone 6 sand washing concreting up to 1.5 m3
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: shindeamol5255@yahoo.in
Subject: 13546-09

Company Name Deshmukh Developers
Project Name & Site Address Goldenshelter
Students Name (Surname_First Name_Middle Name) Shinde Amol Jagannath
Exam No. 13546
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to supervise concreting operation. .
Details of how you Planned & Executed the allotted work we had given the proportion of concrete & according to it we were inspecting whether the labors are taking correct proportion or not.afterwards we gone to the spot where slab was going on.& there we supervised the concreting operation of slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of making cubes of concrete which are used for testing of its strength.firstly oiling is done from the inside of the mould in which concrete is to be filled.then the concrete which is to be tested is filled properly.&then it is taken to the laboratory for testing. .
Details of the Construction Materials learned today today we learned the p.v.c material of which the pipes are used on the site .the pipes are used to fix it in the slab for electric purpose. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today today we discussed the cutting of trees which is done at time of developing new site.& it should be planted afterward at the time of completion of work. .
Details of the Construction / Engineering Drawings observed today R.C.C. Slab Drawing .
Details of the Bye Laws referred today today we referred the open spaces,area,f.s.i & height limitation for the ares in bye-laws. .
Details of any Managerial Skill learned today proper communication between the supervisor & the labors is required for the sake of completing the work in given time &also for the purpose of doing quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m .
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Drum Width In. (cm) Width In. (cm) Inside Turn Radius In. (cm) Pneumatic Tire Rollers n/a 72 (183.0) 108 (274.5) Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4) .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr Bhosle. .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-09

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge 1)To observe the expansion joint betweeh two row bunglows. 2)To observe the paraphet coping construction . 3) To give the information about flats and row bunglows to the clients or customers.
Details of how you Planned & Executed the allotted work First we go in D-8 Wing and we see expansion joint between two bunglows. Then we see detail construction and finishing of paraphet coping. Then we gave detail information about row bunglows and flats to the customers .
Details of the Construction Procedure / Activity / Technology learned today Procedure: 1)Thermocol is placed throughout the foundation to the parapet wall. 2) This is done in order to reduce the thermal expansion between the structure. 3) It is placed when slab is continous upto 100m . Procedure for paraphet : 1) First concrete is prepared for the coping. 2)Then gently it is placed over the parapet wall . 3) Then finishing is done with the help of trowel and screed.
Details of the Construction Materials learned today Thermocol : for reducing the thermal expansion. Cement paste ,Cement mortar , Brick .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Paving blocks are used for roads to avoid soil erosion
Details of the Construction / Engineering Drawings observed today Terrace drainage drawing .
Details of the Bye Laws referred today Parapet wall 1.2m according to byelaws
Details of any Managerial Skill learned today Our site incharge was not present in the office . In the absence of his we showed the flats & row bunglows to the visiting clients and gave information . These clients also cooperated with very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS (Detailed Stepwise Calculations required): INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-09

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Tekwani Sagar Bansilal
Exam No. 10903
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To visit and study the constrruction site at Kandalgaon of Pooja Builders.
Details of how you Planned & Executed the allotted work We all went in group to the site. On the site we met with the site incharge then he gave us the plans of the building. then according to plans we started examining the building.
Details of the Construction Procedure / Activity / Technology learned today We saw the construction of stair-case,slab,beams,columns. We saw the curing process.
Details of the Construction Materials learned today 1. Cement-43 grade,53 grade Bagalkot supreme. 2. Flyash Bricks. 3. Tor steel,Mild steel bars for construction of beams and columns.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The water used at the site was brought from the tank by paying it,so the labourers used the water economically without doing wastage.
Details of the Construction / Engineering Drawings observed today 1. Plan for 1st and 2nd floor. 2. Plan for furniture and electrification.
Details of the Bye Laws referred today 1. The stair case was designed according to the sizes provided by bye-laws. 2. The bye law specifications regarding minimum sizes of different rooms have been followed.
Details of any Managerial Skill learned today 1. The structural Enggineer visited the site he inspected the site. 2. The site incharge kept a proper record of all the work going on.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"INTERNAL PAINTING\". Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge AMAR DHAMAKLE PH NO.9922244154
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-09

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Sawant Amit Ganpat
Exam No. 10900
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the work of curing of slab by pending method. .
Details of how you Planned & Executed the allotted work we observed how the mortar is prepared i.e whether it is on correct proportion or not to avoid leakage from it.& then we observed how the ponds were made. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of curing by pounding method .in this method first mortar is prepared in suitable proportion the surface which is to be used for curing is cleaned first.the ponding method is commonly adopted for curing of concrete slabs or pavement .this method consist of storing water to a depth off 50mm on the surface by constructing small ponds. .
Details of the Construction Materials learned today today we discussed about the aggregates .aggregates provide 70-80% of concrete volume .therefore it must be strong durable & of proper shape .also it should be well graded & should not be chemically reactive.aggregates are cheaper than cement &give volume stability & durability to concrete. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today for ground water recharging ,rain water should be used through the soak pits. .
Details of the Construction / Engineering Drawings observed today today we referred the plumbing drawing. .
Details of the Bye Laws referred today in bye-laws today we referred width & no.of exits for various occupancies .
Details of any Managerial Skill learned today the project should be properly managed & handled by giving proper direction to the workers so as to complete the project in time & to achieve quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Drum Width In. (cm) Width In. (cm) Inside Turn Radius In. (cm) Pneumatic Tire Rollers n/a 72 (183.0) 108 (274.5) Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4)  
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-09

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge 1)To see expansion joint in row bungalow . 2)To see p.c.c. coba on parapet wall. 3)TO attend the client which come for pazatation. .
Details of how you Planned & Executed the allotted work We see all work together & observed all work . .
Details of the Construction Procedure / Activity / Technology learned today Expansion joint- 1)Expansion joint in between bungalow is constructed from bottom to top by using material of Tharmocole in between throughout to wall column slab to parapet wall. P.c.c coba- 1)concrete is spread on parapet wall in leveled surface 2)After curing mortar with cement paste are used for finishing & than cure 3)maintain slope of p.c.c. coba in inward of terrace .
Details of the Construction Materials learned today mortar, concrete tharmocole ,brick ,cement paste. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today paving block used for to avoid soil erosion on ground surface. .
Details of the Construction / Engineering Drawings observed today terrace plan,terrace drainage drawing. .
Details of the Bye Laws referred today Parapet wall provided 1.2m according to bye-laws. .
Details of any Managerial Skill learned today the project should be properly managed & handled by giving proper direction to the workers so as to complete the project in time & to achieve quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Drum Width In. (cm) Width In. (cm) Inside Turn Radius In. (cm) Pneumatic Tire Rollers n/a 72 (183.0) 108 (274.5) Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4)  
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Pritam Patil (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-09

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge 1)To observe the expansion joint betweeh two row bunglows. 2)To observe the paraphet coping construction . 3) To give the information about flats and row bunglows to the clients or customers.
Details of how you Planned & Executed the allotted work First we go in D-8 Wing and we see expansion joint between two bunglows. Then we see detail construction and finishing of paraphet coping. Then we gave detail information about row bunglows and flats to the customers .
Details of the Construction Procedure / Activity / Technology learned today Procedure: 1)Thermocol is placed throughout the foundation to the parapet wall. 2) This is done in order to reduce the thermal expansion between the structure. 3) It is placed when slab is continous upto 100m . Procedure for paraphet : 1) First concrete is prepared for the coping. 2)Then gently it is placed over the parapet wall . 3) Then finishing is done with the help of trowel and screed.
Details of the Construction Materials learned today Thermocol : for reducing the thermal expansion. Cement paste ,Cement mortar , Brick .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Paving blocks are used for roads to avoid soil erosion
Details of the Construction / Engineering Drawings observed today Terrace drainage drawing .
Details of the Bye Laws referred today Parapet wall 1.2m according to byelaws
Details of any Managerial Skill learned today Our site incharge was not present in the office . In the absence of his we showed the flats & row bunglows to the visiting clients and gave information . These clients also cooperated with very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS (Detailed Stepwise Calculations required): INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-09

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge 1)To observe the expansion joint betweeh two row bunglows. 2)To observe the paraphet coping construction . 3) To give the information about flats and row bunglows to the clients or customers.
Details of how you Planned & Executed the allotted work First we go in D-8 Wing and we see expansion joint between two bunglows. Then we see detail construction and finishing of paraphet coping. Then we gave detail information about row bunglows and flats to the customers .
Details of the Construction Procedure / Activity / Technology learned today Procedure: 1)Thermocol is placed throughout the foundation to the parapet wall. 2) This is done in order to reduce the thermal expansion between the structure. 3) It is placed when slab is continous upto 100m . Procedure for paraphet : 1) First concrete is prepared for the coping. 2)Then gently it is placed over the parapet wall . 3) Then finishing is done with the help of trowel and screed.
Details of the Construction Materials learned today Thermocol : for reducing the thermal expansion. Cement paste ,Cement mortar , Brick .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Paving blocks are used for roads to avoid soil erosion
Details of the Construction / Engineering Drawings observed today Terrace drainage drawing .
Details of the Bye Laws referred today Parapet wall 1.2m according to byelaws
Details of any Managerial Skill learned today Our site incharge was not present in the office . In the absence of his we showed the flats & row bunglows to the visiting clients and gave information . These clients also cooperated with very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS (Detailed Stepwise Calculations required): INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs. per sq.m
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-09

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Swapnil Ashok
Exam No. 13529
Working Day No. 09
Date (DD/MM/YYYY) 17.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to observe the construction of underground watertank.
Details of how you Planned & Executed the allotted work we saw the preparation of formwork and the chemicals used to avoid the leakage.
Details of the Construction Procedure / Activity / Technology learned today we learnt how the electrification is done.
Details of the Construction Materials learned today column breaker.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today electrification drawings.
Details of the Bye Laws referred today OVERHEAD WATER TANK : 1. Every overhead water tank should be maintained in perfectly mosquito- proof condition by providing properly fitted cover.
Details of any Managerial Skill learned today none.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-09

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Nilam Jaywant
Exam No. 13528
Working Day No. 09
Date (DD/MM/YYYY) 17.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to observe the construction of underground watertank.
Details of how you Planned & Executed the allotted work we saw the preparation of formwork and the chemicals used to avoid the leakage.
Details of the Construction Procedure / Activity / Technology learned today we learnt how the electrification is done.
Details of the Construction Materials learned today column breaker.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today electrification drawings.
Details of the Bye Laws referred today OVERHEAD WATER TANK : 1. Every overhead water tank should be maintained in perfectly mosquito- proof condition by providing properly fitted cover.
Details of any Managerial Skill learned today none.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-09

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 09
Date (DD/MM/YYYY) 17.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to observe the construction of underground watertank.
Details of how you Planned & Executed the allotted work we saw the preparation of formwork and the chemicals used to avoid the leakage.
Details of the Construction Procedure / Activity / Technology learned today we learnt how the electrification is done.
Details of the Construction Materials learned today column breaker.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today electrification drawings.
Details of the Bye Laws referred today OVERHEAD WATER TANK : 1. Every overhead water tank should be maintained in perfectly mosquito- proof condition by providing properly fitted cover.
Details of any Managerial Skill learned today none.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-09

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Dsouza Agnel Santan
Exam No. 13524
Working Day No. 09
Date (DD/MM/YYYY) 17.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to observe the construction of underground watertank.
Details of how you Planned & Executed the allotted work we saw the preparation of formwork and the chemicals used to avoid the leakage.
Details of the Construction Procedure / Activity / Technology learned today we learnt how the electrification is done.
Details of the Construction Materials learned today column breaker.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today electrification drawings.
Details of the Bye Laws referred today OVERHEAD WATER TANK : 1. Every overhead water tank should be maintained in perfectly mosquito- proof condition by providing properly fitted cover.
Details of any Managerial Skill learned today none.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-09

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 09
Date (DD/MM/YYYY) 17.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge to observe the construction of underground watertank.
Details of how you Planned & Executed the allotted work we saw the preparation of formwork and the chemicals used to avoid the leakage.
Details of the Construction Procedure / Activity / Technology learned today we learnt how the electrification is done.
Details of the Construction Materials learned today column breaker.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today electrification drawings.
Details of the Bye Laws referred today OVERHEAD WATER TANK : 1. Every overhead water tank should be maintained in perfectly mosquito- proof condition by providing properly fitted cover.
Details of any Managerial Skill learned today none.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: gauravdesai75@gmail.com
Subject: 13522-09

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near JayPrabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DESAI GAURAV RAVINDRA
Exam No. 13522
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To visit and study the constrruction site at Kandalgaon of Pooja Builders.
Details of how you Planned & Executed the allotted work We all went in group to the site. On the site we met with the site incharge then he gave us the plans of the building. then according to plans we started examining the building.
Details of the Construction Procedure / Activity / Technology learned today We saw the construction of stair-case,slab,beams,columns. We saw the curing process.
Details of the Construction Materials learned today 1. Cement-43 grade,53 grade Bagalkot supreme. 2. Flyash Bricks. 3. Tor steel,Mild steel bars for construction of beams and columns.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The water used at the site was brought from the tank by paying it,so the labourers used the water economically without doing wastage.
Details of the Construction / Engineering Drawings observed today 1. Plan for 1st and 2nd floor. 2. Plan for furniture and electrification.
Details of the Bye Laws referred today 1. The stair case was designed according to the sizes provided by bye-laws. 2. The bye law specifications regarding minimum sizes of different rooms have been followed.
Details of any Managerial Skill learned today 1. The structural Enggineer visited the site he inspected the site. 2. The site incharge kept a proper record of all the work going on.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for \"INTERNAL PAINTING\". Providing applying two coats of washable Oil-Bound Distemper of approved colour over 1 coat of primer including crack filling by putty etc. complete. Good quality O.B.D primer= 0.2 kg per sq.m @ Rs.70= 0.2*70= Rs.14. Crack filling by putty= 0.30 kg per sq.m@ Rs.30 per kg= 0.30*30= Rs.9. Sand paper 120 no.= Rs.3 per sq.m O.B.D= 0.2 kg per sq.m @ Rs.90 per kg.= 0.2*90= Rs.18. Labour for surface preparation and primer coat= Rs.3 per sq.m Labour for O.B.D for 2 coats= Rs.5 per sq.m Total cost= 14+9+3+18+3+5= Rs.52. Add 10% Profit= Rs.5.20. Total cost per sq.m= 52+5.20= Rs.57.20 = say Rs.57 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.57 per sq.m
Todays BUZZ Word \"CONSTRUCTION MACHINERIES\". 1.Machine for manufacturing Fly-ash bricks. 1.Size of brick manufactured 230*150*150mm. 2.Capacity of bricks to manufacture at one time- 10 bricks. 2.Mixer of Ready Mix Concrete. 1.Capacity= 6 cu.m 3.Vibrator-Surface Vibrator nad Needle Vibrator. 4.Piling machine for pile foundation. 5.Tile polishing machine. 6.Tile cutting hand machine. 7.Drilling machine. 8.Water Supply Pump. 9.Steel abr cutting Machine. 10.Skip and Hoist. 11.Concrete Pumps. 12.Electric motors. 13.Dumpers. 14.Block making machines. 15.Diesel engine,Dewatering pumps. 16.Trolleys. 17.Pulleys. 18.Weigh abtchers,Weigh balance. 19.Vibrating tables. 20.Welding machine.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge AMAR DHAMAKLE PH NO.9922244154.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-09

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) patil sachin dhanaji
Exam No. 13539
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 8:50am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge calculation of steel required for slab ,beam and column
Details of how you Planned & Executed the allotted work we reffer 1.plan of building 2.RCC design of slab and beam 3.calculation of bar required for respective component
Details of the Construction Procedure / Activity / Technology learned today breaking the concrete by electrical concrete breacker
Details of the Construction Materials learned today types of paint types of painting material
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today 1.plan of building 2.RCC design for slab and beam
Details of the Bye Laws referred today parapet wall and hand drails provided on the edges of terrace or balcony shall not be less than 1.15M abov the finished floor level and not more than 1.30M
Details of any Managerial Skill learned today good communiction with customer and command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Internal painting 1.wall putty - 16 Kg x 17.5Rs =280Rs 2.oil paint-2.5 Lit x 200Rs =500Rs 3.labours =200Rs Total =980Rs with CP 20% =1176Rs Total =11.76Rs per sq.ft Total =130.66Rs per sq.mt =131 Rs (approxi)
Result of RATE ANALYSIS ( Rs per Unit ) 131Rs
Todays BUZZ Word machinery 1.concrete mixer a)with loading hopper -type tilting drum -capacity 10/7 cuft(300/200Liters ) b)without loading hopper -type tilting drum -capacity 10/7cuft(300/200Liters) c)stationary model -capacity 10/7cuft(300/200Liters ) 2.Needle vibrater HP-1.5 RPM-3000 needle -30/40/60MM 3.Earth compacter with safety cover and fibre wheel -compaction capacity =4 Tonne -weight=240Kg 4.lift a)tower hoist -capacity -one bag gross bed -maximum height -65feet b)column lift -capacity -180Kg -power-3HP 5.weigh batcher -capacity -2hopper of 250 Kg -weight=350Kg approximately 6.cube mold 150x150x150 MM 7.wheel barrow -capacity -one forth bag
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: vishwajit.p09@gmail.com
Subject: 13543-09

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) paymal vishwajit shamarao
Exam No. 13543
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge calculation of steel required for slab ,beam and column
Details of how you Planned & Executed the allotted work we reffer 1.plan of building 2.RCC design of slab and beam 3.calculation of bar required for respective component
Details of the Construction Procedure / Activity / Technology learned today breaking the concrete by electrical concrete breacker
Details of the Construction Materials learned today types of paint types of painting material
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today 1.plan of building 2.RCC design for slab and beam
Details of the Bye Laws referred today parapet wall and hand drails provided on the edges of terrace or balcony shall not be less than 1.15M abov the finished floor level and not more than 1.30M
Details of any Managerial Skill learned today good communiction with customer and command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Internal painting 1.wall putty - 16 Kg x 17.5Rs =280Rs 2.oil paint-2.5 Lit x 200Rs =500Rs 3.labours =200Rs Total =980Rs with CP 20% =1176Rs Total =11.76Rs per sq.ft Total =130.66Rs per sq.mt =131 Rs (approxi)
Result of RATE ANALYSIS ( Rs per Unit ) 131Rs
Todays BUZZ Word machinery 1.concrete mixer a)with loading hopper -type tilting drum -capacity 10/7 cuft(300/200Liters ) b)without loading hopper -type tilting drum -capacity 10/7cuft(300/200Liters) c)stationary model -capacity 10/7cuft(300/200Liters ) 2.Needle vibrater HP-1.5 RPM-3000 needle -30/40/60MM 3.Earth compacter with safety cover and fibre wheel -compaction capacity =4 Tonne -weight=240Kg 4.lift a)tower hoist -capacity -one bag gross bed -maximum height -65feet b)column lift -capacity -180Kg -power-3HP 5.weigh batcher -capacity -2hopper of 250 Kg -weight=350Kg approximately 6.cube mold 150x150x150 MM 7.wheel barrow -capacity -one forth bag
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883-08

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) saurabh arora
Exam No. 10883
Working Day No. 07
Date (DD/MM/YYYY) 17-12-10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge to see internal road construction
Details of how you Planned & Executed the allotted work we saw carefully road constrction first they paving material then compacted with roller
Details of the Construction Procedure / Activity / Technology learned today construction of TAR road
Details of the Construction Materials learned today Tar, aggegates LOE oil,cement
Details of Environment Caring Technology / Methodology / Procedure / Product learned today peving blocks
Details of the Construction / Engineering Drawings observed today drawing of roads
Details of the Bye Laws referred today bye laws regarding ventilation and accomodation requirments of buildings habitable room area= 9.5m2 habitable room width= 2.4m room height = 2.75m window area for wall on open side = 10% of floar area total door & window area = 1/7 th of room area total ventilation area = 0.1m2 for 10m3 of room space
Details of any Managerial Skill learned today how to supervise the work and handle the workers while constructing the road
RATE ANALYSIS (Detailed Stepwise Calculations required) Stepwise Calculations required): oil bond 1lit oil bond for 125 ft2 = 250 Rs primer 1 lit = 80 Rs labour 1 Ft2 = 3.5 Rs material cost = 250 + 80 = 330 Rs labour cost = 437.50 Rs Total cost = 768 Rs For 1Ft2 = 6.15 Rs for 1 m2 = 6.15 * 10.76 = 66 Rs/ 1 m2 Result of RATE ANALYSIS ( Rs per Unit ): 66 Rs/ 1 m2
Result of RATE ANALYSIS ( Rs per Unit ) 66rs/1m2
Todays BUZZ Word \"Construction machineries \" 1 concrete mixer 2 concrete nidle vibrator 3 concrete lift 4 diesel pump or deatering pump 5 surface vibrator 6 electrical motor 7 block making machine 8 block pallets 9 test cube mold 10 slump cone apparatus 11 rebound hammer 12 surveying instrumennts 13 tripod stand 14 levelling staff 15 weight batching 16 road roller 17 earth rammer 18 drilling machine 19 tile polishing matchine 20 tile cutting machine 21 water pressure pump
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 901103969389
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13561-09

Company Name Chougule Sawant Developers
Project Name & Site Address SHREE SAMARTH NAGAR,New balinga
Students Name (Surname_First Name_Middle Name) Jadhav Sardar Swaroop J.
Exam No. 13561
Working Day No. 09
Date (DD/MM/YYYY) 17.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe concreting of lifts.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings and detailed drwaing of lift. Then we observe actual site work with site in charge.
Details of the Construction Procedure / Activity / Technology learned today CONCRETING OF LIFTS : 1. Location of lift is fixed from detailed drawing & by line dori method. 2. Then formwork is placed as per sizes of lifts. 3. Then reinforced is placed in formwork as per R.C.C. design. 4. Concreting is done as per specifications. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today TIMBER : 1. It is important construction material. 2. Timber is used for formwork, in line out work,in scaffolding. 3. Timber is also used for making door,window frames & panels. 4. Timber is also used for furniture work.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today SOLAR PANELS : 1. Solar panels is used for boiling the water by using solar energy. 2. Solar energy is most clean & environment friendly energy. 3. Solar panels are costly but they can boil the water efficiently. 4. Due to use of solar panels natural resources are saved & pollution is also minimised.
Details of the Construction / Engineering Drawings observed today R.C.C. DRAWINGS OF LIFTS & DETAILED DRAWINGS OF LIFT,CENTER LINE PLAN OF APARTMENT.
Details of the Bye Laws referred today OVERHEAD WATER TANK : 1. Every overhead water storage tank shall be maintained in perfectly mosquoto- proof condition by providing properly fitting hinged cover. 2. Every tank more than 1.5m above the finished floor level provided with permanently fixed iron ladder tio enable inspection by anti-maleria staff
Details of any Managerial Skill learned today To on site one column was casted improperly. Site in charge tells to contractor that whole column is demolished and casted again. So we learned that though work of high cost is completed improperly, it should be corrected to acheive safety and economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs.per sq.m.
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut, Mo.No. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-09

Company Name Chougule Sawant Developers
Project Name & Site Address SHREE SAMARTH NAGAR,New balinga
Students Name (Surname_First Name_Middle Name) Katral Raju Maruti
Exam No. 13562
Working Day No. 09
Date (DD/MM/YYYY) 17.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe concreting of lifts.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings and detailed drwaing of lift. Then we observe actual site work with site in charge.
Details of the Construction Procedure / Activity / Technology learned today CONCRETING OF LIFTS : 1. Location of lift is fixed from detailed drawing & by line dori method. 2. Then formwork is placed as per sizes of lifts. 3. Then reinforced is placed in formwork as per R.C.C. design. 4. Concreting is done as per specifications. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today TIMBER : 1. It is important construction material. 2. Timber is used for formwork, in line out work,in scaffolding. 3. Timber is also used for making door,window frames & panels. 4. Timber is also used for furniture work.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today SOLAR PANELS : 1. Solar panels is used for boiling the water by using solar energy. 2. Solar energy is most clean & environment friendly energy. 3. Solar panels are costly but they can boil the water efficiently. 4. Due to use of solar panels natural resources are saved & pollution is also minimised.
Details of the Construction / Engineering Drawings observed today R.C.C. DRAWINGS OF LIFTS & DETAILED DRAWINGS OF LIFT,CENTER LINE PLAN OF APARTMENT.
Details of the Bye Laws referred today OVERHEAD WATER TANK : 1. Every overhead water storage tank shall be maintained in perfectly mosquoto- proof condition by providing properly fitting hinged cover. 2. Every tank more than 1.5m above the finished floor level provided with permanently fixed iron ladder tio enable inspection by anti-maleria staff
Details of any Managerial Skill learned today To on site one column was casted improperly. Site in charge tells to contractor that whole column is demolished and casted again. So we learned that though work of high cost is completed improperly, it should be corrected to acheive safety and economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs.per sq.m.
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut, Mo.No. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-09

Company Name Chougule Sawant Developers
Project Name & Site Address SHREE SAMARTH NAGAR,New balinga
Students Name (Surname_First Name_Middle Name) JADE MADHAVRAO ANIL
Exam No. 13560
Working Day No. 09
Date (DD/MM/YYYY) 17.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe concreting of lifts.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings and detailed drwaing of lift. Then we observe actual site work with site in charge.
Details of the Construction Procedure / Activity / Technology learned today CONCRETING OF LIFTS : 1. Location of lift is fixed from detailed drawing & by line dori method. 2. Then formwork is placed as per sizes of lifts. 3. Then reinforced is placed in formwork as per R.C.C. design. 4. Concreting is done as per specifications. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today TIMBER : 1. It is important construction material. 2. Timber is used for formwork, in line out work,in scaffolding. 3. Timber is also used for making door,window frames & panels. 4. Timber is also used for furniture work.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today SOLAR PANELS : 1. Solar panels is used for boiling the water by using solar energy. 2. Solar energy is most clean & environment friendly energy. 3. Solar panels are costly but they can boil the water efficiently. 4. Due to use of solar panels natural resources are saved & pollution is also minimised.
Details of the Construction / Engineering Drawings observed today R.C.C. DRAWINGS OF LIFTS & DETAILED DRAWINGS OF LIFT,CENTER LINE PLAN OF APARTMENT.
Details of the Bye Laws referred today OVERHEAD WATER TANK : 1. Every overhead water storage tank shall be maintained in perfectly mosquoto- proof condition by providing properly fitting hinged cover. 2. Every tank more than 1.5m above the finished floor level provided with permanently fixed iron ladder tio enable inspection by anti-maleria staff
Details of any Managerial Skill learned today To on site one column was casted improperly. Site in charge tells to contractor that whole column is demolished and casted again. So we learned that though work of high cost is completed improperly, it should be corrected to acheive safety and economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs.per sq.m.
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut, Mo.No. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-09

Company Name Chougule Sawant Developers
Project Name & Site Address SHREE SAMARTH NAGAR,New balinga
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya Ashok
Exam No. 13572
Working Day No. 09
Date (DD/MM/YYYY) 17.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe concreting of lifts.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings and detailed drwaing of lift. Then we observe actual site work with site in charge.
Details of the Construction Procedure / Activity / Technology learned today CONCRETING OF LIFTS : 1. Location of lift is fixed from detailed drawing & by line dori method. 2. Then formwork is placed as per sizes of lifts. 3. Then reinforced is placed in formwork as per R.C.C. design. 4. Concreting is done as per specifications. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today TIMBER : 1. It is important construction material. 2. Timber is used for formwork, in line out work,in scaffolding. 3. Timber is also used for making door,window frames & panels. 4. Timber is also used for furniture work.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today SOLAR PANELS : 1. Solar panels is used for boiling the water by using solar energy. 2. Solar energy is most clean & environment friendly energy. 3. Solar panels are costly but they can boil the water efficiently. 4. Due to use of solar panels natural resources are saved & pollution is also minimised.
Details of the Construction / Engineering Drawings observed today R.C.C. DRAWINGS OF LIFTS & DETAILED DRAWINGS OF LIFT,CENTER LINE PLAN OF APARTMENT.
Details of the Bye Laws referred today OVERHEAD WATER TANK : 1. Every overhead water storage tank shall be maintained in perfectly mosquoto- proof condition by providing properly fitting hinged cover. 2. Every tank more than 1.5m above the finished floor level provided with permanently fixed iron ladder tio enable inspection by anti-maleria staff
Details of any Managerial Skill learned today To on site one column was casted improperly. Site in charge tells to contractor that whole column is demolished and casted again. So we learned that though work of high cost is completed improperly, it should be corrected to acheive safety and economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs.per sq.m.
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut, Mo.No. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558-09

Company Name Chougule Sawant Developers
Project Name & Site Address SHREE SAMARTH NAGAR,New balinga
Students Name (Surname_First Name_Middle Name) Chavan Shivprasad Chavan
Exam No. 13558
Working Day No. 09
Date (DD/MM/YYYY) 17.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe concreting of lifts.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings and detailed drwaing of lift. Then we observe actual site work with site in charge.
Details of the Construction Procedure / Activity / Technology learned today CONCRETING OF LIFTS : 1. Location of lift is fixed from detailed drawing & by line dori method. 2. Then formwork is placed as per sizes of lifts. 3. Then reinforced is placed in formwork as per R.C.C. design. 4. Concreting is done as per specifications. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today TIMBER : 1. It is important construction material. 2. Timber is used for formwork, in line out work,in scaffolding. 3. Timber is also used for making door,window frames & panels. 4. Timber is also used for furniture work.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today SOLAR PANELS : 1. Solar panels is used for boiling the water by using solar energy. 2. Solar energy is most clean & environment friendly energy. 3. Solar panels are costly but they can boil the water efficiently. 4. Due to use of solar panels natural resources are saved & pollution is also minimised.
Details of the Construction / Engineering Drawings observed today R.C.C. DRAWINGS OF LIFTS & DETAILED DRAWINGS OF LIFT,CENTER LINE PLAN OF APARTMENT.
Details of the Bye Laws referred today OVERHEAD WATER TANK : 1. Every overhead water storage tank shall be maintained in perfectly mosquoto- proof condition by providing properly fitting hinged cover. 2. Every tank more than 1.5m above the finished floor level provided with permanently fixed iron ladder tio enable inspection by anti-maleria staff.
Details of any Managerial Skill learned today To on site one column was casted improperly. Site in charge tells to contractor that whole column is demolished and casted again. So we learned that though work of high cost is completed improperly, it should be corrected to acheive safety and economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PAINTING ; per sq.m 2 coats are given while painting fpor that rate are as follows ; Distemper = 0.30 kg = 25.00 Rs Cement Primer = 0.32 liter = 20.00 Rs Turpentine 0.08 liter = 20.00 Rs Labour cost and other equipments = 7% TOTAL = 70.00 Rs. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) 70.00 Rs.per sq.m.
Todays BUZZ Word CONSTRUCTION MACHINERIES : 1. Concrete mixer : used for mixing of concrete. max. capacity 800 lit. 2. Pumps : used to lift water from excavation pits. capacity is 10 hp 3. J.C.B. : used for excavating soil capacity is 6000 kg. 4. Dumper : used for dumping the excavated soil. capacity is 300 cu.ft. 5. Vibrator ; used for vibrating the concrete. max. pressure 10 N/mm.sq. 6. Transit mixer : used for transportation of ready mix concrete. min. capacity is 5 cu.m. 7. Weigh Batcher : used for batching the concrete weigh batchers with different capacities are available in market. 8. Lift : used for vertical transportation of construction materials. 9. Cranes : used in large projects for displacements of excavated soil 10. Belt conveyer : used for horizontal transportation of construction materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut, Mo.No. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: saurabh.arrora.yo@gmail.com
Subject: 10883-09

Company Name Star Tech Infra
Project Name & Site Address star ashiyana nr ragedra nagar kolhapur
Students Name (Surname_First Name_Middle Name) saurabh arrora
Exam No. 10883
Working Day No. 08
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge to see internal road construction
Details of how you Planned & Executed the allotted work we saw carefully road constrction first they paving material then compacted with roller
Details of the Construction Procedure / Activity / Technology learned today construction of TAR road
Details of the Construction Materials learned today Tar, aggegates LOE oil,cement
Details of Environment Caring Technology / Methodology / Procedure / Product learned today peving blocks
Details of the Construction / Engineering Drawings observed today drawing of roads
Details of the Bye Laws referred today bye laws regarding ventilation and accomodation requirments of buildings habitable room area= 9.5m2 habitable room width= 2.4m room height = 2.75m window area for wall on open side = 10% of floar area total door & window area = 1/7 th of room area total ventilation area = 0.1m2 for 10m3 of room space
Details of any Managerial Skill learned today how to supervise the work and handle the workers while constructing the road
RATE ANALYSIS (Detailed Stepwise Calculations required) oil bond 1lit oil bond for 125 ft2 = 250 Rs primer 1 lit = 80 Rs labour 1 Ft2 = 3.5 Rs material cost = 250 + 80 = 330 Rs labour cost = 437.50 Rs Total cost = 768 Rs For 1Ft2 = 6.15 Rs for 1 m2 = 6.15 * 10.76 = 66 Rs/ 1 m2
Result of RATE ANALYSIS ( Rs per Unit ) 66 Rs/ 1 m2
Todays BUZZ Word \"Construction machineries \" 1 concrete mixer 2 concrete nidle vibrator 3 concrete lift 4 diesel pump or deatering pump 5 surface vibrator 6 electrical motor 7 block making machine 8 block pallets 9 test cube mold 10 slump cone apparatus 11 rebound hammer 12 surveying instrumennts 13 tripod stand 14 levelling staff 15 weight batching 16 road roller 17 earth rammer 18 drilling machine 19 tile polishing matchine 20 tile cutting machine 21 water pressure pump
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish sir 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-09

Company Name Star Tech Infra
Project Name & Site Address star ashiyana nr ragedra nagar kolhapur
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge to see internal road construction
Details of how you Planned & Executed the allotted work we saw carefully road constrction first they paving material then compacted with roller
Details of the Construction Procedure / Activity / Technology learned today construction of TAR road
Details of the Construction Materials learned today Tar, aggegates LOE oil,cement
Details of Environment Caring Technology / Methodology / Procedure / Product learned today peving blocks
Details of the Construction / Engineering Drawings observed today drawing of roads
Details of the Bye Laws referred today bye laws regarding ventilation and accomodation requirments of buildings habitable room area= 9.5m2 habitable room width= 2.4m room height = 2.75m window area for wall on open side = 10% of floar area total door & window area = 1/7 th of room area total ventilation area = 0.1m2 for 10m3 of room space
Details of any Managerial Skill learned today how to supervise the work and handle the workers while constructing the road
RATE ANALYSIS (Detailed Stepwise Calculations required) oil bond 1lit oil bond for 125 ft2 = 250 Rs primer 1 lit = 80 Rs labour 1 Ft2 = 3.5 Rs material cost = 250 + 80 = 330 Rs labour cost = 437.50 Rs Total cost = 768 Rs For 1Ft2 = 6.15 Rs for 1 m2 = 6.15 * 10.76 = 66 Rs/ 1 m2
Result of RATE ANALYSIS ( Rs per Unit ) 66 Rs/ 1 m2
Todays BUZZ Word \"Construction machineries \" 1 concrete mixer 2 concrete nidle vibrator 3 concrete lift 4 diesel pump or deatering pump 5 surface vibrator 6 electrical motor 7 block making machine 8 block pallets 9 test cube mold 10 slump cone apparatus 11 rebound hammer 12 surveying instrumennts 13 tripod stand 14 levelling staff 15 weight batching 16 road roller 17 earth rammer 18 drilling machine 19 tile polishing matchine 20 tile cutting machine 21 water pressure pump
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish sir 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: viju128@gmail.com
Subject: 3638-09

Company Name Star Tech Infra
Project Name & Site Address star ashiyana near ragendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) shinde vijay namdeo
Exam No. 3638
Working Day No. 09
Date (DD/MM/YYYY) 17/12/2010
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge to see internal road construction
Details of how you Planned & Executed the allotted work we saw carefully road constrction first they paving material then compacted with roller
Details of the Construction Procedure / Activity / Technology learned today construction of TAR road
Details of the Construction Materials learned today Tar, aggegates LOE oil,cement
Details of Environment Caring Technology / Methodology / Procedure / Product learned today peving blocks
Details of the Construction / Engineering Drawings observed today drawing of roads
Details of the Bye Laws referred today bye laws regarding ventilation and accomodation requirments of buildings habitable room area= 9.5m2 habitable room width= 2.4m room height = 2.75m window area for wall on open side = 10% of floar area total door & window area = 1/7 th of room area total ventilation area = 0.1m2 for 10m3 of room space
Details of any Managerial Skill learned today how to supervise the work and handle the workers while constructing the road
RATE ANALYSIS (Detailed Stepwise Calculations required) oil bond 1lit oil bond for 125 ft2 = 250 Rs primer 1 lit = 80 Rs labour 1 Ft2 = 3.5 Rs material cost = 250 + 80 = 330 Rs labour cost = 437.50 Rs Total cost = 768 Rs For 1Ft2 = 6.15 Rs for 1 m2 = 6.15 * 10.76 = 66 Rs/ 1 m2
Result of RATE ANALYSIS ( Rs per Unit ) 66 Rs/ 1 m2
Todays BUZZ Word \"Construction machineries \" 1 concrete mixer 2 concrete nidle vibrator 3 concrete lift 4 diesel pump or deatering pump 5 surface vibrator 6 electrical motor 7 block making machine 8 block pallets 9 test cube mold 10 slump cone apparatus 11 rebound hammer 12 surveying instrumennts 13 tripod stand 14 levelling staff 15 weight batching 16 road roller 17 earth rammer 18 drilling machine 19 tile polishing matchine 20 tile cutting machine 21 water pressure pump
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish sir 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: pinkrosee4u@yahoo.com
Subject: 10878-09

Company Name Star Tech Infra
Project Name & Site Address star ashiyana near ragenra nagar kolhapur
Students Name (Surname_First Name_Middle Name) narnaware shikha haridas
Exam No. 10878
Working Day No. 09
Date (DD/MM/YYYY) 1712/2010
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge to see internal road construction
Details of how you Planned & Executed the allotted work we saw carefully road constrction first they paving material then compacted with roller
Details of the Construction Procedure / Activity / Technology learned today construction of TAR road
Details of the Construction Materials learned today Tar, aggegates LOE oil,cement
Details of Environment Caring Technology / Methodology / Procedure / Product learned today peving blocks
Details of the Construction / Engineering Drawings observed today drawing of roads
Details of the Bye Laws referred today bye laws regarding ventilation and accomodation requirments of buildings habitable room area= 9.5m2 habitable room width= 2.4m room height = 2.75m window area for wall on open side = 10% of floar area total door & window area = 1/7 th of room area total ventilation area = 0.1m2 for 10m3 of room space
Details of any Managerial Skill learned today how to supervise the work and handle the workers while constructing the road
RATE ANALYSIS (Detailed Stepwise Calculations required) oil bond 1lit oil bond for 125 ft2 = 250 Rs primer 1 lit = 80 Rs labour 1 Ft2 = 3.5 Rs material cost = 250 + 80 = 330 Rs labour cost = 437.50 Rs Total cost = 768 Rs For 1Ft2 = 6.15 Rs for 1 m2 = 6.15 * 10.76 = 66 Rs/ 1 m2
Result of RATE ANALYSIS ( Rs per Unit ) 66 Rs/ 1 m2
Todays BUZZ Word \"Construction machineries \" 1 concrete mixer 2 concrete nidle vibrator 3 concrete lift 4 diesel pump or deatering pump 5 surface vibrator 6 electrical motor 7 block making machine 8 block pallets 9 test cube mold 10 slump cone apparatus 11 rebound hammer 12 surveying instrumennts 13 tripod stand 14 levelling staff 15 weight batching 16 road roller 17 earth rammer 18 drilling machine 19 tile polishing matchine 20 tile cutting machine 21 water pressure pump \"Construction machineries \" 1 concrete mixer 2 concrete nidle vibrator 3 concrete lift 4 diesel pump or deatering pump 5 surface vibrator 6 electrical motor 7 block making machine 8 block pallets 9 test cube mold 10 slump cone apparatus 11 rebound hammer 12 surveying instrumennts 13 tripod stand 14 levelling staff 15 weight batching 16 road roller 17 earth rammer 18 drilling machine 19 tile polishing matchine 20 tile cutting machine 21 water pressure pump \"Construction machineries \" 1 concrete mixer 2 concrete nidle vibrator 3 concrete lift 4 diesel pump or deatering pump 5 surface vibrator 6 electrical motor 7 block making machine 8 block pallets 9 test cube mold 10 slump cone apparatus 11 rebound hammer 12 surveying instrumennts 13 tripod stand 14 levelling staff 15 weight batching 16 road roller 17 earth rammer 18 drilling machine 19 tile polishing matchine 20 tile cutting machine 21 water pressure pump
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish sir 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: mayur.sonavne61@gmail.com
Subject: 13570-09

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sonavne Mayur Madhukar
Exam No. 13570
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of Drainage system of public building:- Calculation of total length of pipe required. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required,fix the position of each Trap. 3)Third student placed the pipe on marked alignment with their respective length & direction,position of foul gas pipe were fixed. 4)Fourth student made the connections at each & every junction, note down the types of trap provided. 5)Fifth student checked the work as per drawing & requirements. 6)The main outlet drainage pipe were connected to main sewage line. .
Details of the Construction Procedure / Activity / Technology learned today Supervision of Drainage system of public building:- a)Drainage system should be design for the daily outgoing of water. b)First mark changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. c)Then mark the alignment,every junction of pipe on inner & outer side of wall. d)Drilled the hole in wall as per diameter of pipe required. e)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. f)Every junction of pipe should be well jointed & free from leakages . g)Good binding material should be used for connecting two pipes. h)Elbows,T,collers should be used at correct place. i)The no. of joints should be avoided. j)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. k)Provide the trap as per requirement nahani trap for bathroom , Gully trap at every change in vertical direction. l)Normal slope was design for each connection for removal of solid waste. m)To avoid the leakages the separate drainage line were arranged from joint of Wc pan to trap . n)Correct position & design requirements of manhole were checked. .
Details of the Construction Materials learned today Pipes used for drainage work:- PVC PIPE,NAHANI TRAP ,GUULY TRAP,WC PANS ,P Q S TRAPS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Generally the waste water from municiple sewage line dropped in nearer river or any huge water source.The waste water includes the various types of bacteria , chemicals ,other harmful things which damages to river environment. If waste water is treated at released place then it will more helpful for environment & treated water can be used again & again. .
Details of the Construction / Engineering Drawings observed today Layout for waste water system. Various traps used in drainage system according to their function. .
Details of the Bye Laws referred today Minimum & maximum dimensions of municiple sewage line. Various diameters of pipe & type of pipe used in waste water system. .
Details of any Managerial Skill learned today To check the material supplied by supplier to clarify the mistakes if any. So as to keep supply continuous and efficient.Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for internal painting:- Surface area of wall= 50 sq.m Rate per sq m =Rs.25/- Total =1250/- Wastage 5% 6 Scaffolding 15 Labour 70 Total=91 .
Result of RATE ANALYSIS ( Rs per Unit ) 100/-sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4)
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-09

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sutar Namdev Rangnath
Exam No. 13571
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of Drainage system of public building:- Calculation of total length of pipe required. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required,fix the position of each Trap. 3)Third student placed the pipe on marked alignment with their respective length & direction,position of foul gas pipe were fixed. 4)Fourth student made the connections at each & every junction, note down the types of trap provided. 5)Fifth student checked the work as per drawing & requirements. 6)The main outlet drainage pipe were connected to main sewage line. .
Details of the Construction Procedure / Activity / Technology learned today Supervision of Drainage system of public building:- a)Drainage system should be design for the daily outgoing of water. b)First mark changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. c)Then mark the alignment,every junction of pipe on inner & outer side of wall. d)Drilled the hole in wall as per diameter of pipe required. e)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. f)Every junction of pipe should be well jointed & free from leakages . g)Good binding material should be used for connecting two pipes. h)Elbows,T,collers should be used at correct place. i)The no. of joints should be avoided. j)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. k)Provide the trap as per requirement nahani trap for bathroom , Gully trap at every change in vertical direction. l)Normal slope was design for each connection for removal of solid waste. m)To avoid the leakages the separate drainage line were arranged from joint of Wc pan to trap . n)Correct position & design requirements of manhole were checked. .
Details of the Construction Materials learned today Pipes used for drainage work:- PVC PIPE,NAHANI TRAP ,GUULY TRAP,WC PANS ,P Q S TRAPS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Generally the waste water from municiple sewage line dropped in nearer river or any huge water source.The waste water includes the various types of bacteria , chemicals ,other harmful things which damages to river environment. If waste water is treated at released place then it will more helpful for environment & treated water can be used again & again. .
Details of the Construction / Engineering Drawings observed today Layout for waste water system. Various traps used in drainage system according to their function. .
Details of the Bye Laws referred today Minimum & maximum dimensions of municiple sewage line. Various diameters of pipe & type of pipe used in waste water system. .
Details of any Managerial Skill learned today To check the material supplied by supplier to clarify the mistakes if any. So as to keep supply continuous and efficient.Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for internal painting:- Surface area of wall= 50 sq.m Rate per sq m =Rs.25/- Total =1250/- Wastage 5% 6 Scaffolding 15 Labour 70 Total=91 .
Result of RATE ANALYSIS ( Rs per Unit ) 100/-sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4)
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-09

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Shivtare Prabharkar Chandrakant
Exam No. 13569
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of Drainage system of public building:- Calculation of total length of pipe required. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required,fix the position of each Trap. 3)Third student placed the pipe on marked alignment with their respective length & direction,position of foul gas pipe were fixed. 4)Fourth student made the connections at each & every junction, note down the types of trap provided. 5)Fifth student checked the work as per drawing & requirements. 6)The main outlet drainage pipe were connected to main sewage line. .
Details of the Construction Procedure / Activity / Technology learned today Supervision of Drainage system of public building:- a)Drainage system should be design for the daily outgoing of water. b)First mark changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. c)Then mark the alignment,every junction of pipe on inner & outer side of wall. d)Drilled the hole in wall as per diameter of pipe required. e)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. f)Every junction of pipe should be well jointed & free from leakages . g)Good binding material should be used for connecting two pipes. h)Elbows,T,collers should be used at correct place. i)The no. of joints should be avoided. j)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. k)Provide the trap as per requirement nahani trap for bathroom , Gully trap at every change in vertical direction. l)Normal slope was design for each connection for removal of solid waste. m)To avoid the leakages the separate drainage line were arranged from joint of Wc pan to trap . n)Correct position & design requirements of manhole were checked. .
Details of the Construction Materials learned today Pipes used for drainage work:- PVC PIPE,NAHANI TRAP ,GUULY TRAP,WC PANS ,P Q S TRAPS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Generally the waste water from municiple sewage line dropped in nearer river or any huge water source.The waste water includes the various types of bacteria , chemicals ,other harmful things which damages to river environment. If waste water is treated at released place then it will more helpful for environment & treated water can be used again & again. .
Details of the Construction / Engineering Drawings observed today Layout for waste water system. Various traps used in drainage system according to their function. .
Details of the Bye Laws referred today Minimum & maximum dimensions of municiple sewage line. Various diameters of pipe & type of pipe used in waste water system. .
Details of any Managerial Skill learned today To check the material supplied by supplier to clarify the mistakes if any. So as to keep supply continuous and efficient.Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for internal painting:- Surface area of wall= 50 sq.m Rate per sq m =Rs.25/- Total =1250/- Wastage 5% 6 Scaffolding 15 Labour 70 Total=91 .
Result of RATE ANALYSIS ( Rs per Unit ) 100/-sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4)
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-09

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Shinde Sagar Arvind
Exam No. 13568
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of Drainage system of public building:- Calculation of total length of pipe required. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required,fix the position of each Trap. 3)Third student placed the pipe on marked alignment with their respective length & direction,position of foul gas pipe were fixed. 4)Fourth student made the connections at each & every junction, note down the types of trap provided. 5)Fifth student checked the work as per drawing & requirements. 6)The main outlet drainage pipe were connected to main sewage line. .
Details of the Construction Procedure / Activity / Technology learned today Supervision of Drainage system of public building:- a)Drainage system should be design for the daily outgoing of water. b)First mark changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. c)Then mark the alignment,every junction of pipe on inner & outer side of wall. d)Drilled the hole in wall as per diameter of pipe required. e)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. f)Every junction of pipe should be well jointed & free from leakages . g)Good binding material should be used for connecting two pipes. h)Elbows,T,collers should be used at correct place. i)The no. of joints should be avoided. j)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. k)Provide the trap as per requirement nahani trap for bathroom , Gully trap at every change in vertical direction. l)Normal slope was design for each connection for removal of solid waste. m)To avoid the leakages the separate drainage line were arranged from joint of Wc pan to trap . n)Correct position & design requirements of manhole were checked. .
Details of the Construction Materials learned today Pipes used for drainage work:- PVC PIPE,NAHANI TRAP ,GUULY TRAP,WC PANS ,P Q S TRAPS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Generally the waste water from municiple sewage line dropped in nearer river or any huge water source.The waste water includes the various types of bacteria , chemicals ,other harmful things which damages to river environment. If waste water is treated at released place then it will more helpful for environment & treated water can be used again & again. .
Details of the Construction / Engineering Drawings observed today Layout for waste water system. Various traps used in drainage system according to their function. .
Details of the Bye Laws referred today Minimum & maximum dimensions of municiple sewage line. Various diameters of pipe & type of pipe used in waste water system. .
Details of any Managerial Skill learned today To check the material supplied by supplier to clarify the mistakes if any. So as to keep supply continuous and efficient.Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for internal painting:- Surface area of wall= 50 sq.m Rate per sq m =Rs.25/- Total =1250/- Wastage 5% 6 Scaffolding 15 Labour 70 Total=91 .
Result of RATE ANALYSIS ( Rs per Unit ) 100/-sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4)
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/17/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 13567-09

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 09
Date (DD/MM/YYYY) 17-12-2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of Drainage system of public building:- Calculation of total length of pipe required. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required,fix the position of each Trap. 3)Third student placed the pipe on marked alignment with their respective length & direction,position of foul gas pipe were fixed. 4)Fourth student made the connections at each & every junction, note down the types of trap provided. 5)Fifth student checked the work as per drawing & requirements. 6)The main outlet drainage pipe were connected to main sewage line. .
Details of the Construction Procedure / Activity / Technology learned today Supervision of Drainage system of public building:- a)Drainage system should be design for the daily outgoing of water. b)First mark changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. c)Then mark the alignment,every junction of pipe on inner & outer side of wall. d)Drilled the hole in wall as per diameter of pipe required. e)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. f)Every junction of pipe should be well jointed & free from leakages . g)Good binding material should be used for connecting two pipes. h)Elbows,T,collers should be used at correct place. i)The no. of joints should be avoided. j)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. k)Provide the trap as per requirement nahani trap for bathroom , Gully trap at every change in vertical direction. l)Normal slope was design for each connection for removal of solid waste. m)To avoid the leakages the separate drainage line were arranged from joint of Wc pan to trap . n)Correct position & design requirements of manhole were checked. .
Details of the Construction Materials learned today Pipes used for drainage work:- PVC PIPE,NAHANI TRAP ,GUULY TRAP,WC PANS ,P Q S TRAPS. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Generally the waste water from municiple sewage line dropped in nearer river or any huge water source.The waste water includes the various types of bacteria , chemicals ,other harmful things which damages to river environment. If waste water is treated at released place then it will more helpful for environment & treated water can be used again & again. .
Details of the Construction / Engineering Drawings observed today Layout for waste water system. Various traps used in drainage system according to their function. .
Details of the Bye Laws referred today Minimum & maximum dimensions of municiple sewage line. Various diameters of pipe & type of pipe used in waste water system. .
Details of any Managerial Skill learned today To check the material supplied by supplier to clarify the mistakes if any. So as to keep supply continuous and efficient.Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for internal painting:- Surface area of wall= 50 sq.m Rate per sq m =Rs.25/- Total =1250/- Wastage 5% 6 Scaffolding 15 Labour 70 Total=91 .
Result of RATE ANALYSIS ( Rs per Unit ) 100/-sq.m
Todays BUZZ Word Use of machinery in building construction helps to achieve better quality , Better speed , & reduction in manual labour . CONSTRUCTION EQUIPMENT: a)Concrete mixer b) Concrete vibrator 1) Screed vibrator 2) Needle vibrator 3) Table vibrato c)Lift & hoist d) Trolley f) Pully g) Weigh bathers h)Weigh balance i) Dumpers k) Half bag concrete mixer l) Concrete buckets m) Concrete pumps n)Tile polishing machines o)Excavators. SPECIFICATIONS OF VARIOUS TYPES OF CONSTRUCTION EQUIPMENTS :- Type Model Height Capacity Crawler Cranes 50PL 187 (57.0) 50 (45.4) Crawler Cranes 60L 236 (7 1.9) 60 (54.4)
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523-08

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near Jayprabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DEVKAR VIKRAM DILIP
Exam No. 13523
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge 1.To see and study the process of manufacturing fly-ash bricks. 2.To see and study the furniture and electrification work going on site.
Details of how you Planned & Executed the allotted work We first went at the place where the fly-ash bricks were manufactured then we saw how they manufacture the bricks,Proportions taken,equipments used etc.
Details of the Construction Procedure / Activity / Technology learned today 1.To manufacture fly-ash bricks of size 230*150*150mm. 2.Electrification and Furniture work going on.
Details of the Construction Materials learned today Materials required for manufacturing fly ash bricks. 1.Lime 2.Gypsum. 3.Cement. 4.Stone dust.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Today we learnt a new technology. A program was organised by Paras Oswal sir in which he introduced us to their new venture INFINITE BIO-FUELS AND AGRITECH PVT.LTD. in the specialised fireld of Biomass energy and Agroproducts.Thus they are going to use Renewable energy resources. Mr.Subhash Niyogi showed us the us of pellets of waste from agriculture can be used as a fuel for burning purpose. This will reduce the waste and help to produce fuels which can be used for industrial as well as residential pupose.This process will generate smoke about less than one third of smoke that is generated by normal burning. other materials like bagasse,plastic wsates and other organic wastes will be used.The project will have capacity to process 200 ton of waste.This project will be located within 10 km area from the city.They are also introducing this technique in mobile type. in which thier van will go to the place where the waste are gathered and they will treat that waste their itself.This project will be set up within 6 months and expecting a positive response from the public. Pooja group again pioneered a new technology in the construction industry of Kolhapur.
Details of the Construction / Engineering Drawings observed today Plan for third floor showing schedule of beams and columns. Plan for electrification.
Details of the Bye Laws referred today Bricks were manufactured according to sizes provided by bye laws.
Details of any Managerial Skill learned today 1.The site incharge inspected the work. 2.The site incharge guided the labour.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for TILING. Ceramic tile of 600mm*600mm*7mm. Market Rate-Rs.50/sq.ft. i.e Rs.538/sq.m Cement= 0.22 bag/sq.m Cost of cement= 0.22*265= Rs.58.30. Transportation of tile.= Rs.2 per sq.m Labour= Rs.20 per sq.ft Labour cost per sq.m= Rs.215.20. Total cost= 538+58.30+2+215.20= Rs.813.50. Including 10% profit.= 81.35. Total cost per sq.m= 813.50+81.35= Rs.894.85.
Result of RATE ANALYSIS ( Rs per Unit ) Rs.894.85 per sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENT. A) CONTRACTS:- UNIT PRICE (ITEM WISE) CONTRACT LUMP SUM ( FIRM FIXED PRICE) CONTRACT LABOUR CONTRACT COST + CONTRACT PROJECT MANAGAMENT CONTRACT 1. Cost Plus Fixed Percentage Contract: For certain types of construction involving new technology or extremely pressing needs, the owner is sometimes forced to assume all risks of cost overruns. The contractor will receive the actual direct job cost plus a fixed percentage, and have little incentive to reduce job cost. Furthermore, if there are pressing needs to complete the project, overtime payments to workers are common and will further increase the job cost. Unless there are compelling reasons, such as the urgency in the construction of military installations, the owner should not use this type of contract. 2.Cost Plus Fixed Fee Contract: Under this type of contract, the contractor will receive the actual direct job cost plus a fixed fee, and will have some incentive to complete the job quickly since its fee is fixed regardless of the duration of the project. However, the owner still assumes the risks of direct job cost overrun while the contractor may risk the erosion of its profits if the project is dragged on beyond the expected time. 3.Cost Plus Variable Percentage Contract: For this type of contract, the contractor agrees to a penalty if the actual cost exceeds the estimated job cost, or a reward if the actual cost is below the estimated job cost. In return for taking the risk on its own estimate, the contractor is allowed a variable percentage of the direct job-cost for its fee. Furthermore, the project duration is usually specified and the contractor must abide by the deadline for completion. This type of contract allocates considerable risk for cost overruns to the owner, but also provides incentives to contractors to reduce costs as much as possible. 4.Target Estimate Contract: This is another form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is greater than or less than the contractor’s estimated direct job cost. Usually, the percentages of savings or overrun to be shared by the owner and the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion dates. 5.Guaranteed Maximum Cost Contract: When the project scope is well defined, an owner may choose to ask the contractor to take all the risks, both in terms of actual project cost and project time. Any work change orders from the owner must be extremely minor if at all, since performance specifications are provided to the owner at the outset of construction. The owner and the contractor agree to a project cost guaranteed by the contractor as maximum. There may be or may not be additional provisions to share any savings if any in the contract. This type of contract is particularly suitable for turnkey operation. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521-08

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near Jayprabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) BAGMARE DINESH SHRIRAM
Exam No. 13521
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge 1.To see and study the process of manufacturing fly-ash bricks. 2.To see and study the furniture and electrification work going on site.
Details of how you Planned & Executed the allotted work We first went at the place where the fly-ash bricks were manufactured then we saw how they manufacture the bricks,Proportions taken,equipments used etc.
Details of the Construction Procedure / Activity / Technology learned today 1.To manufacture fly-ash bricks of size 230*150*150mm. 2.Electrification and Furniture work going on.
Details of the Construction Materials learned today Materials required for manufacturing fly ash bricks. 1.Lime 2.Gypsum. 3.Cement. 4.Stone dust.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Today we learnt a new technology. A program was organised by Paras Oswal sir in which he introduced us to their new venture INFINITE BIO-FUELS AND AGRITECH PVT.LTD. in the specialised fireld of Biomass energy and Agroproducts.Thus they are going to use Renewable energy resources. Mr.Subhash Niyogi showed us the us of pellets of waste from agriculture can be used as a fuel for burning purpose. This will reduce the waste and help to produce fuels which can be used for industrial as well as residential pupose.This process will generate smoke about less than one third of smoke that is generated by normal burning. other materials like bagasse,plastic wsates and other organic wastes will be used.The project will have capacity to process 200 ton of waste.This project will be located within 10 km area from the city.They are also introducing this technique in mobile type. in which thier van will go to the place where the waste are gathered and they will treat that waste their itself.This project will be set up within 6 months and expecting a positive response from the public. Pooja group again pioneered a new technology in the construction industry of Kolhapur.
Details of the Construction / Engineering Drawings observed today Plan for third floor showing schedule of beams and columns. Plan for electrification.
Details of the Bye Laws referred today Bricks were manufactured according to sizes provided by bye laws.
Details of any Managerial Skill learned today 1.The site incharge inspected the work. 2.The site incharge guided the labour.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for TILING. Ceramic tile of 600mm*600mm*7mm. Market Rate-Rs.50/sq.ft. i.e Rs.538/sq.m Cement= 0.22 bag/sq.m Cost of cement= 0.22*265= Rs.58.30. Transportation of tile.= Rs.2 per sq.m Labour= Rs.20 per sq.ft Labour cost per sq.m= Rs.215.20. Total cost= 538+58.30+2+215.20= Rs.813.50. Including 10% profit.= 81.35. Total cost per sq.m= 813.50+81.35= Rs.894.85.
Result of RATE ANALYSIS ( Rs per Unit ) Rs.894.85 per sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENT. A) CONTRACTS:- UNIT PRICE (ITEM WISE) CONTRACT LUMP SUM ( FIRM FIXED PRICE) CONTRACT LABOUR CONTRACT COST + CONTRACT PROJECT MANAGAMENT CONTRACT 1. Cost Plus Fixed Percentage Contract: For certain types of construction involving new technology or extremely pressing needs, the owner is sometimes forced to assume all risks of cost overruns. The contractor will receive the actual direct job cost plus a fixed percentage, and have little incentive to reduce job cost. Furthermore, if there are pressing needs to complete the project, overtime payments to workers are common and will further increase the job cost. Unless there are compelling reasons, such as the urgency in the construction of military installations, the owner should not use this type of contract. 2.Cost Plus Fixed Fee Contract: Under this type of contract, the contractor will receive the actual direct job cost plus a fixed fee, and will have some incentive to complete the job quickly since its fee is fixed regardless of the duration of the project. However, the owner still assumes the risks of direct job cost overrun while the contractor may risk the erosion of its profits if the project is dragged on beyond the expected time. 3.Cost Plus Variable Percentage Contract: For this type of contract, the contractor agrees to a penalty if the actual cost exceeds the estimated job cost, or a reward if the actual cost is below the estimated job cost. In return for taking the risk on its own estimate, the contractor is allowed a variable percentage of the direct job-cost for its fee. Furthermore, the project duration is usually specified and the contractor must abide by the deadline for completion. This type of contract allocates considerable risk for cost overruns to the owner, but also provides incentives to contractors to reduce costs as much as possible. 4.Target Estimate Contract: This is another form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is greater than or less than the contractor’s estimated direct job cost. Usually, the percentages of savings or overrun to be shared by the owner and the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion dates. 5.Guaranteed Maximum Cost Contract: When the project scope is well defined, an owner may choose to ask the contractor to take all the risks, both in terms of actual project cost and project time. Any work change orders from the owner must be extremely minor if at all, since performance specifications are provided to the owner at the outset of construction. The owner and the contractor agree to a project cost guaranteed by the contractor as maximum. There may be or may not be additional provisions to share any savings if any in the contract. This type of contract is particularly suitable for turnkey operation. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-08

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near Jayprabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) TEKWANI SAGAR BANSILAL
Exam No. 10903
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1.To see and study the process of manufacturing fly-ash bricks. 2.To see and study the furniture and electrification work going on site.
Details of how you Planned & Executed the allotted work We first went at the place where the fly-ash bricks were manufactured then we saw how they manufacture the bricks,Proportions taken,equipments used etc.
Details of the Construction Procedure / Activity / Technology learned today 1.To manufacture fly-ash bricks of size 230*150*150mm. 2.Electrification and Furniture work going on.
Details of the Construction Materials learned today Materials required for manufacturing fly ash bricks. 1.Lime 2.Gypsum. 3.Cement. 4.Stone dust.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Today we learnt a new technology. A program was organised by Paras Oswal sir in which he introduced us to their new venture INFINITE BIO-FUELS AND AGRITECH PVT.LTD. in the specialised fireld of Biomass energy and Agroproducts.Thus they are going to use Renewable energy resources. Mr.Subhash Niyogi showed us the us of pellets of waste from agriculture can be used as a fuel for burning purpose. This will reduce the waste and help to produce fuels which can be used for industrial as well as residential pupose.This process will generate smoke about less than one third of smoke that is generated by normal burning. other materials like bagasse,plastic wsates and other organic wastes will be used.The project will have capacity to process 200 ton of waste.This project will be located within 10 km area from the city.They are also introducing this technique in mobile type. in which thier van will go to the place where the waste are gathered and they will treat that waste their itself.This project will be set up within 6 months and expecting a positive response from the public. Pooja group again pioneered a new technology in the construction industry of Kolhapur.
Details of the Construction / Engineering Drawings observed today Plan for third floor showing schedule of beams and columns. Plan for electrification.
Details of the Bye Laws referred today Bricks were manufactured according to sizes provided by bye laws.
Details of any Managerial Skill learned today 1.The site incharge inspected the work. 2.The site incharge guided the labour.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for TILING. Ceramic tile of 600mm*600mm*7mm. Market Rate-Rs.50/sq.ft. i.e Rs.538/sq.m Cement= 0.22 bag/sq.m Cost of cement= 0.22*265= Rs.58.30. Transportation of tile.= Rs.2 per sq.m Labour= Rs.20 per sq.ft Labour cost per sq.m= Rs.215.20. Total cost= 538+58.30+2+215.20= Rs.813.50. Including 10% profit.= 81.35. Total cost per sq.m= 813.50+81.35= Rs.894.85.
Result of RATE ANALYSIS ( Rs per Unit ) Rs.894.85 per sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENT. A) CONTRACTS:- UNIT PRICE (ITEM WISE) CONTRACT LUMP SUM ( FIRM FIXED PRICE) CONTRACT LABOUR CONTRACT COST + CONTRACT PROJECT MANAGAMENT CONTRACT 1. Cost Plus Fixed Percentage Contract: For certain types of construction involving new technology or extremely pressing needs, the owner is sometimes forced to assume all risks of cost overruns. The contractor will receive the actual direct job cost plus a fixed percentage, and have little incentive to reduce job cost. Furthermore, if there are pressing needs to complete the project, overtime payments to workers are common and will further increase the job cost. Unless there are compelling reasons, such as the urgency in the construction of military installations, the owner should not use this type of contract. 2.Cost Plus Fixed Fee Contract: Under this type of contract, the contractor will receive the actual direct job cost plus a fixed fee, and will have some incentive to complete the job quickly since its fee is fixed regardless of the duration of the project. However, the owner still assumes the risks of direct job cost overrun while the contractor may risk the erosion of its profits if the project is dragged on beyond the expected time. 3.Cost Plus Variable Percentage Contract: For this type of contract, the contractor agrees to a penalty if the actual cost exceeds the estimated job cost, or a reward if the actual cost is below the estimated job cost. In return for taking the risk on its own estimate, the contractor is allowed a variable percentage of the direct job-cost for its fee. Furthermore, the project duration is usually specified and the contractor must abide by the deadline for completion. This type of contract allocates considerable risk for cost overruns to the owner, but also provides incentives to contractors to reduce costs as much as possible. 4.Target Estimate Contract: This is another form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is greater than or less than the contractor’s estimated direct job cost. Usually, the percentages of savings or overrun to be shared by the owner and the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion dates. 5.Guaranteed Maximum Cost Contract: When the project scope is well defined, an owner may choose to ask the contractor to take all the risks, both in terms of actual project cost and project time. Any work change orders from the owner must be extremely minor if at all, since performance specifications are provided to the owner at the outset of construction. The owner and the contractor agree to a project cost guaranteed by the contractor as maximum. There may be or may not be additional provisions to share any savings if any in the contract. This type of contract is particularly suitable for turnkey operation. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10893-08

Company Name V. S. Joshi & Associates
Project Name & Site Address VVishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) kamble ankit
Exam No. 10893
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 5.30PM
Details of the Work Allotted to you today by the Site In-Charge 1) We had to determine the number of construction works to prepare the daily report. 2)We were also alloted to prepare line out for Septic Tank & Underground Tank.
Details of how you Planned & Executed the allotted work 1) We all five members made our team & went towards the site where the line out for the Septic Tank was to be Executed. 2) At first 3 members prepared the line out for the septic tank. 3) The remaining 2 members prepared the line out for underground Water Tank.
Details of the Construction Procedure / Activity / Technology learned today # \"PRELIMINARY LINE OUT\" # - Decide on a permanent structure that was considerd during contouring work. - Locate the structure on the plan. - As per drawings measure the various distances from this structure. - Mark straight lines on grounds parallel to compound wall. - Set up the Theodolite on any corner & by taking perpendicular measurements finalize all four corners of Septic Tank
Details of the Construction Materials learned today 1. Concrete Blocks. 2. Line Dori. 3. Pegs. 4. Lifting Cranes.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Storm Water Drains were made which were Discharged in a pit for ground water recharge.
Details of the Construction / Engineering Drawings observed today - Septic Tank Details. - Details of Anaerobic Filter Process. - Underground Water Storage Tank Details. - Service Layout.
Details of the Bye Laws referred today - Building Services. (pg 118) - Septic Tank (pg 104)
Details of any Managerial Skill learned today - Sensitivity. - Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) -# \"RATE ANALYSIS FOR TILED FLOORING\" #- A. Material Required: ( 100 sq.m) 1 Vitrified Tiles (605 x 605 mm): No of tiles = 280 nos. 2. Lime Cement Mortor (1:2:4) (20 mm thk) Total Quantity in wet condition = 2 cu.m Quantity in Dry Condition = 2.5 cu.m 3. Cement = 0.357 = 11 bags. Extra Cement for neat Cement Slurry = 11+6 = 17 bags. 4. Sand = 0.357 x 4 = 1.428 cu.m 5. Lime = 0.357 x 2 = 0.714 cu.m B. Cost Of Material: 1. Commet Tile = 280 x 140 = 39200/- 2. Cement = 17 x 230 = 3910/- 3. Sand = 1.428 x 850 = 1213.8/- 4. lime = 0.714 x 6000 = 4284/- 5. Polishing stone = 500/- 6. Auxilic Acid Powder = 150/- TOTAL = 49257.8/- C. Cost Of Labour: 1. Mistri = 2 x 250 = 500/- 2. Mason = 15 x 170 = 2550/- 3. Male Mazdoor = 12 x 140 = 1680/- 4. Female Mazdoor = 10 x 120 = 1200/- 5. Bhisti = 2 x 130 = 260/- 6. Polisher = 4 x 130 = 520/- 7. T & P = 500/- TOTAL = 7210/- D. Total Cost = B + C = 56467.8/- E. Add 2% water charges = 1129.356/- F. Add 15% contractors Profit = 8470. 17/- G. Grand Toatal = 66067.326/- H. Cost Per Sq.M = 660.67/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.660.67/-
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge amol mule
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: shinde_shital7@yahoo.com
Subject: 10884-08

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell,karande mala
Students Name (Surname_First Name_Middle Name) shinde shital vilasrao
Exam No. 10884
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) We had to determine the number of construction works to prepare the daily report. 2)We were also alloted to prepare line out for Septic Tank & Underground Tank.
Details of how you Planned & Executed the allotted work 1) We all five members made our team & went towards the site where the line out for the Septic Tank was to be Executed. 2) At first 3 members prepared the line out for the septic tank. 3) The remaining 2 members prepared the line out for underground Water Tank.
Details of the Construction Procedure / Activity / Technology learned today # \"PRELIMINARY LINE OUT\" # - Decide on a permanent structure that was considerd during contouring work. - Locate the structure on the plan. - As per drawings measure the various distances from this structure. - Mark straight lines on grounds parallel to compound wall. - Set up the Theodolite on any corner & by taking perpendicular measurements finalize all four corners of Septic Tank
Details of the Construction Materials learned today 1. Concrete Blocks. 2. Line Dori. 3. Pegs. 4. Lifting Cranes.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Storm Water Drains were made which were Discharged in a pit for ground water recharge.
Details of the Construction / Engineering Drawings observed today - Septic Tank Details. - Details of Anaerobic Filter Process. - Underground Water Storage Tank Details. - Service Layout.
Details of the Bye Laws referred today - Building Services. (pg 118) - Septic Tank (pg 104)
Details of any Managerial Skill learned today - Sensitivity. - Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) -# \"RATE ANALYSIS FOR TILED FLOORING\" #- A. Material Required: ( 100 sq.m) 1 Vitrified Tiles (605 x 605 mm): No of tiles = 280 nos. 2. Lime Cement Mortor (1:2:4) (20 mm thk) Total Quantity in wet condition = 2 cu.m Quantity in Dry Condition = 2.5 cu.m 3. Cement = 0.357 = 11 bags. Extra Cement for neat Cement Slurry = 11+6 = 17 bags. 4. Sand = 0.357 x 4 = 1.428 cu.m 5. Lime = 0.357 x 2 = 0.714 cu.m B. Cost Of Material: 1. Commet Tile = 280 x 140 = 39200/- 2. Cement = 17 x 230 = 3910/- 3. Sand = 1.428 x 850 = 1213.8/- 4. lime = 0.714 x 6000 = 4284/- 5. Polishing stone = 500/- 6. Auxilic Acid Powder = 150/- TOTAL = 49257.8/- C. Cost Of Labour: 1. Mistri = 2 x 250 = 500/- 2. Mason = 15 x 170 = 2550/- 3. Male Mazdoor = 12 x 140 = 1680/- 4. Female Mazdoor = 10 x 120 = 1200/- 5. Bhisti = 2 x 130 = 260/- 6. Polisher = 4 x 130 = 520/- 7. T & P = 500/- TOTAL = 7210/- D. Total Cost = B + C = 56467.8/- E. Add 2% water charges = 1129.356/- F. Add 15% contractors Profit = 8470. 17/- G. Grand Toatal = 66067.326/- H. Cost Per Sq.M = 660.67/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.660.67/-
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-08

Company Name V. S. Joshi & Associates
Project Name & Site Address VVishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) janbandhu rakshit janbandhu
Exam No. 10875
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 5.30PM
Details of the Work Allotted to you today by the Site In-Charge 1) We had to determine the number of construction works to prepare the daily report. 2)We were also alloted to prepare line out for Septic Tank & Underground Tank.
Details of how you Planned & Executed the allotted work 1) We all five members made our team & went towards the site where the line out for the Septic Tank was to be Executed. 2) At first 3 members prepared the line out for the septic tank. 3) The remaining 2 members prepared the line out for underground Water Tank.
Details of the Construction Procedure / Activity / Technology learned today # \"PRELIMINARY LINE OUT\" # - Decide on a permanent structure that was considerd during contouring work. - Locate the structure on the plan. - As per drawings measure the various distances from this structure. - Mark straight lines on grounds parallel to compound wall. - Set up the Theodolite on any corner & by taking perpendicular measurements finalize all four corners of Septic Tank
Details of the Construction Materials learned today 1. Concrete Blocks. 2. Line Dori. 3. Pegs. 4. Lifting Cranes.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Storm Water Drains were made which were Discharged in a pit for ground water recharge.
Details of the Construction / Engineering Drawings observed today - Septic Tank Details. - Details of Anaerobic Filter Process. - Underground Water Storage Tank Details. - Service Layout.
Details of the Bye Laws referred today - Building Services. (pg 118) - Septic Tank (pg 104)
Details of any Managerial Skill learned today - Sensitivity. - Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) -# \"RATE ANALYSIS FOR TILED FLOORING\" #- A. Material Required: ( 100 sq.m) 1 Vitrified Tiles (605 x 605 mm): No of tiles = 280 nos. 2. Lime Cement Mortor (1:2:4) (20 mm thk) Total Quantity in wet condition = 2 cu.m Quantity in Dry Condition = 2.5 cu.m 3. Cement = 0.357 = 11 bags. Extra Cement for neat Cement Slurry = 11+6 = 17 bags. 4. Sand = 0.357 x 4 = 1.428 cu.m 5. Lime = 0.357 x 2 = 0.714 cu.m B. Cost Of Material: 1. Commet Tile = 280 x 140 = 39200/- 2. Cement = 17 x 230 = 3910/- 3. Sand = 1.428 x 850 = 1213.8/- 4. lime = 0.714 x 6000 = 4284/- 5. Polishing stone = 500/- 6. Auxilic Acid Powder = 150/- TOTAL = 49257.8/- C. Cost Of Labour: 1. Mistri = 2 x 250 = 500/- 2. Mason = 15 x 170 = 2550/- 3. Male Mazdoor = 12 x 140 = 1680/- 4. Female Mazdoor = 10 x 120 = 1200/- 5. Bhisti = 2 x 130 = 260/- 6. Polisher = 4 x 130 = 520/- 7. T & P = 500/- TOTAL = 7210/- D. Total Cost = B + C = 56467.8/- E. Add 2% water charges = 1129.356/- F. Add 15% contractors Profit = 8470. 17/- G. Grand Toatal = 66067.326/- H. Cost Per Sq.M = 660.67/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.660.67/-
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge AMOL MULE
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-08

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell,karande mala
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) We had to determine the number of construction works to prepare the daily report. 2)We were also alloted to prepare line out for Septic Tank & Underground Tank.
Details of how you Planned & Executed the allotted work 1) We all five members made our team & went towards the site where the line out for the Septic Tank was to be Executed. 2) At first 3 members prepared the line out for the septic tank. 3) The remaining 2 members prepared the line out for underground Water Tank.
Details of the Construction Procedure / Activity / Technology learned today # \"PRELIMINARY LINE OUT\" # - Decide on a permanent structure that was considerd during contouring work. - Locate the structure on the plan. - As per drawings measure the various distances from this structure. - Mark straight lines on grounds parallel to compound wall. - Set up the Theodolite on any corner & by taking perpendicular measurements finalize all four corners of Septic Tank
Details of the Construction Materials learned today 1. Concrete Blocks. 2. Line Dori. 3. Pegs. 4. Lifting Cranes.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Storm Water Drains were made which were Discharged in a pit for ground water recharge.
Details of the Construction / Engineering Drawings observed today - Septic Tank Details. - Details of Anaerobic Filter Process. - Underground Water Storage Tank Details. - Service Layout.
Details of the Bye Laws referred today - Building Services. (pg 118) - Septic Tank (pg 104)
Details of any Managerial Skill learned today - Sensitivity. - Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) -# \"RATE ANALYSIS FOR TILED FLOORING\" #- A. Material Required: ( 100 sq.m) 1 Vitrified Tiles (605 x 605 mm): No of tiles = 280 nos. 2. Lime Cement Mortor (1:2:4) (20 mm thk) Total Quantity in wet condition = 2 cu.m Quantity in Dry Condition = 2.5 cu.m 3. Cement = 0.357 = 11 bags. Extra Cement for neat Cement Slurry = 11+6 = 17 bags. 4. Sand = 0.357 x 4 = 1.428 cu.m 5. Lime = 0.357 x 2 = 0.714 cu.m B. Cost Of Material: 1. Commet Tile = 280 x 140 = 39200/- 2. Cement = 17 x 230 = 3910/- 3. Sand = 1.428 x 850 = 1213.8/- 4. lime = 0.714 x 6000 = 4284/- 5. Polishing stone = 500/- 6. Auxilic Acid Powder = 150/- TOTAL = 49257.8/- C. Cost Of Labour: 1. Mistri = 2 x 250 = 500/- 2. Mason = 15 x 170 = 2550/- 3. Male Mazdoor = 12 x 140 = 1680/- 4. Female Mazdoor = 10 x 120 = 1200/- 5. Bhisti = 2 x 130 = 260/- 6. Polisher = 4 x 130 = 520/- 7. T & P = 500/- TOTAL = 7210/- D. Total Cost = B + C = 56467.8/- E. Add 2% water charges = 1129.356/- F. Add 15% contractors Profit = 8470. 17/- G. Grand Toatal = 66067.326/- H. Cost Per Sq.M = 660.67/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.660.67/-
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-08

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near Jayprabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) hasabnis ketaki bhagwan
Exam No. 13527
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge 1.To see and study the process of manufacturing fly-ash bricks. 2.To see and study the furniture and electrification work going on site.
Details of how you Planned & Executed the allotted work We first went at the place where the fly-ash bricks were manufactured then we saw how they manufacture the bricks,Proportions taken,equipments used etc.
Details of the Construction Procedure / Activity / Technology learned today 1.To manufacture fly-ash bricks of size 230*150*150mm. 2.Electrification and Furniture work going on.
Details of the Construction Materials learned today Materials required for manufacturing fly ash bricks. 1.Lime 2.Gypsum. 3.Cement. 4.Stone dust.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Today we learnt a new technology. A program was organised by Paras Oswal sir in which he introduced us to their new venture INFINITE BIO-FUELS AND AGRITECH PVT.LTD. in the specialised fireld of Biomass energy and Agroproducts.Thus they are going to use Renewable energy resources. Mr.Subhash Niyogi showed us the us of pellets of waste from agriculture can be used as a fuel for burning purpose. This will reduce the waste and help to produce fuels which can be used for industrial as well as residential pupose.This process will generate smoke about less than one third of smoke that is generated by normal burning. other materials like bagasse,plastic wsates and other organic wastes will be used.The project will have capacity to process 200 ton of waste.This project will be located within 10 km area from the city.They are also introducing this technique in mobile type. in which thier van will go to the place where the waste are gathered and they will treat that waste their itself.This project will be set up within 6 months and expecting a positive response from the public. Pooja group again pioneered a new technology in the construction industry of Kolhapur.
Details of the Construction / Engineering Drawings observed today Plan for third floor showing schedule of beams and columns. Plan for electrification.
Details of the Bye Laws referred today Bricks were manufactured according to sizes provided by bye laws.
Details of any Managerial Skill learned today 1.The site incharge inspected the work. 2.The site incharge guided the labour.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for TILING. Ceramic tile of 600mm*600mm*7mm. Market Rate-Rs.50/sq.ft. i.e Rs.538/sq.m Cement= 0.22 bag/sq.m Cost of cement= 0.22*265= Rs.58.30. Transportation of tile.= Rs.2 per sq.m Labour= Rs.20 per sq.ft Labour cost per sq.m= Rs.215.20. Total cost= 538+58.30+2+215.20= Rs.813.50. Including 10% profit.= 81.35. Total cost per sq.m= 813.50+81.35= Rs.894.85.
Result of RATE ANALYSIS ( Rs per Unit ) Rs.894.85 per sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENT. A) CONTRACTS:- UNIT PRICE (ITEM WISE) CONTRACT LUMP SUM ( FIRM FIXED PRICE) CONTRACT LABOUR CONTRACT COST + CONTRACT PROJECT MANAGAMENT CONTRACT 1. Cost Plus Fixed Percentage Contract: For certain types of construction involving new technology or extremely pressing needs, the owner is sometimes forced to assume all risks of cost overruns. The contractor will receive the actual direct job cost plus a fixed percentage, and have little incentive to reduce job cost. Furthermore, if there are pressing needs to complete the project, overtime payments to workers are common and will further increase the job cost. Unless there are compelling reasons, such as the urgency in the construction of military installations, the owner should not use this type of contract. 2.Cost Plus Fixed Fee Contract: Under this type of contract, the contractor will receive the actual direct job cost plus a fixed fee, and will have some incentive to complete the job quickly since its fee is fixed regardless of the duration of the project. However, the owner still assumes the risks of direct job cost overrun while the contractor may risk the erosion of its profits if the project is dragged on beyond the expected time. 3.Cost Plus Variable Percentage Contract: For this type of contract, the contractor agrees to a penalty if the actual cost exceeds the estimated job cost, or a reward if the actual cost is below the estimated job cost. In return for taking the risk on its own estimate, the contractor is allowed a variable percentage of the direct job-cost for its fee. Furthermore, the project duration is usually specified and the contractor must abide by the deadline for completion. This type of contract allocates considerable risk for cost overruns to the owner, but also provides incentives to contractors to reduce costs as much as possible. 4.Target Estimate Contract: This is another form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is greater than or less than the contractor’s estimated direct job cost. Usually, the percentages of savings or overrun to be shared by the owner and the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion dates. 5.Guaranteed Maximum Cost Contract: When the project scope is well defined, an owner may choose to ask the contractor to take all the risks, both in terms of actual project cost and project time. Any work change orders from the owner must be extremely minor if at all, since performance specifications are provided to the owner at the outset of construction. The owner and the contractor agree to a project cost guaranteed by the contractor as maximum. There may be or may not be additional provisions to share any savings if any in the contract. This type of contract is particularly suitable for turnkey operation. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: gauravdesai75@gmail.com
Subject: 13522-08

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders,Near Jayprabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DESAI GAURAV RAVINDRA
Exam No. 13522
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge 1.To see and study the process of manufacturing fly-ash bricks. 2.To see and study the furniture and electrification work going on site.
Details of how you Planned & Executed the allotted work We first went at the place where the fly-ash bricks were manufactured then we saw how they manufacture the bricks,Proportions taken,equipments used etc.
Details of the Construction Procedure / Activity / Technology learned today 1.To manufacture fly-ash bricks of size 230*150*150mm. 2.Electrification and Furniture work going on.
Details of the Construction Materials learned today Materials required for manufacturing fly ash bricks. 1.Lime 2.Gypsum. 3.Cement. 4.Stone dust.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Today we learnt a new technology. A program was organised by Paras Oswal sir in which he introduced us to their new venture INFINITE BIO-FUELS AND AGRITECH PVT.LTD. in the specialised fireld of Biomass energy and Agroproducts.Thus they are going to use Renewable energy resources. Mr.Subhash Niyogi showed us the us of pellets of waste from agriculture can be used as a fuel for burning purpose. This will reduce the waste and help to produce fuels which can be used for industrial as well as residential pupose.This process will generate smoke about less than one third of smoke that is generated by normal burning. other materials like bagasse,plastic wsates and other organic wastes will be used.The project will have capacity to process 200 ton of waste.This project will be located within 10 km area from the city.They are also introducing this technique in mobile type. in which thier van will go to the place where the waste are gathered and they will treat that waste their itself.This project will be set up within 6 months and expecting a positive response from the public. Pooja group again pioneered a new technology in the construction industry of Kolhapur.
Details of the Construction / Engineering Drawings observed today Plan for third floor showing schedule of beams and columns. Plan for electrification.
Details of the Bye Laws referred today Bricks were manufactured according to sizes provided by bye laws.
Details of any Managerial Skill learned today 1.The site incharge inspected the work. 2.The site incharge guided the labour.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for TILING. Ceramic tile of 600mm*600mm*7mm. Market Rate-Rs.50/sq.ft. i.e Rs.538/sq.m Cement= 0.22 bag/sq.m Cost of cement= 0.22*265= Rs.58.30. Transportation of tile.= Rs.2 per sq.m Labour= Rs.20 per sq.ft Labour cost per sq.m= Rs.215.20. Total cost= 538+58.30+2+215.20= Rs.813.50. Including 10% profit.= 81.35. Total cost per sq.m= 813.50+81.35= Rs.894.85.
Result of RATE ANALYSIS ( Rs per Unit ) Rs.894.85 per sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENT. A) CONTRACTS:- UNIT PRICE (ITEM WISE) CONTRACT LUMP SUM ( FIRM FIXED PRICE) CONTRACT LABOUR CONTRACT COST + CONTRACT PROJECT MANAGAMENT CONTRACT 1. Cost Plus Fixed Percentage Contract: For certain types of construction involving new technology or extremely pressing needs, the owner is sometimes forced to assume all risks of cost overruns. The contractor will receive the actual direct job cost plus a fixed percentage, and have little incentive to reduce job cost. Furthermore, if there are pressing needs to complete the project, overtime payments to workers are common and will further increase the job cost. Unless there are compelling reasons, such as the urgency in the construction of military installations, the owner should not use this type of contract. 2.Cost Plus Fixed Fee Contract: Under this type of contract, the contractor will receive the actual direct job cost plus a fixed fee, and will have some incentive to complete the job quickly since its fee is fixed regardless of the duration of the project. However, the owner still assumes the risks of direct job cost overrun while the contractor may risk the erosion of its profits if the project is dragged on beyond the expected time. 3.Cost Plus Variable Percentage Contract: For this type of contract, the contractor agrees to a penalty if the actual cost exceeds the estimated job cost, or a reward if the actual cost is below the estimated job cost. In return for taking the risk on its own estimate, the contractor is allowed a variable percentage of the direct job-cost for its fee. Furthermore, the project duration is usually specified and the contractor must abide by the deadline for completion. This type of contract allocates considerable risk for cost overruns to the owner, but also provides incentives to contractors to reduce costs as much as possible. 4.Target Estimate Contract: This is another form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is greater than or less than the contractor’s estimated direct job cost. Usually, the percentages of savings or overrun to be shared by the owner and the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion dates. 5.Guaranteed Maximum Cost Contract: When the project scope is well defined, an owner may choose to ask the contractor to take all the risks, both in terms of actual project cost and project time. Any work change orders from the owner must be extremely minor if at all, since performance specifications are provided to the owner at the outset of construction. The owner and the contractor agree to a project cost guaranteed by the contractor as maximum. There may be or may not be additional provisions to share any savings if any in the contract. This type of contract is particularly suitable for turnkey operation. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-08

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) JAGADALE ASHVANI RAMRAO
Exam No. 13530
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. LEVELLING ; To calculate reduced levels of footings as area is very large hence to check level of footings is same or not. 2. To observe casting of staircase.
Details of how you Planned & Executed the allotted work 1. First we had set instrument by levelling and centering it. 2. Then we measured height of instrument. 3. Then we had taken back sight and fore sight readings. 4. Then we had calculated reduced levels of points by H.I. method.
Details of the Construction Procedure / Activity / Technology learned today 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today Crushed sand ; 1. This is important ingredient of concrete. 2. It acts as binding agent in concrete, it forms bulk of concrete with aggregate. 3. It also is used in mortar for fly ash brick masonry. 4. Crush sand is made by fine grounding of stones. 5. Rate of crushed sand is 2200.00Rs per brass. 6. Test results has prooved that crush sand gives more strength than normal sand.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river .sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment.
Details of the Construction / Engineering Drawings observed today Center line plan, staircase drwaings,working drawings of plinth beam.
Details of the Bye Laws referred today Lift width provided on the site is 1.20m.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGULE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-08

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) JAGADALE ASHVANI RAMRAO
Exam No. 13530
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. LEVELLING ; To calculate reduced levels of footings as area is very large hence to check level of footings is same or not. 2. To observe casting of staircase.
Details of how you Planned & Executed the allotted work 1. First we had set instrument by levelling and centering it. 2. Then we measured height of instrument. 3. Then we had taken back sight and fore sight readings. 4. Then we had calculated reduced levels of points by H.I. method.
Details of the Construction Procedure / Activity / Technology learned today 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today Crushed sand ; 1. This is important ingredient of concrete. 2. It acts as binding agent in concrete, it forms bulk of concrete with aggregate. 3. It also is used in mortar for fly ash brick masonry. 4. Crush sand is made by fine grounding of stones. 5. Rate of crushed sand is 2200.00Rs per brass. 6. Test results has prooved that crush sand gives more strength than normal sand.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river .sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment.
Details of the Construction / Engineering Drawings observed today Center line plan, staircase drwaings,working drawings of plinth beam.
Details of the Bye Laws referred today Lift width provided on the site is 1.20m.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGULE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-08

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Patil Vrishali Vitthal
Exam No. 13541
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the slab casting
Details of how you Planned & Executed the allotted work we divide our self in two groups 1 for observing procedure of compacting & another for checking quantity of sand & agg.
Details of the Construction Procedure / Activity / Technology learned today mixing of agg. ,sand , cement thoroughly to prepare quality concrete.
Details of the Construction Materials learned today admixture - super plasticizer - it increases workability of concrete
Details of Environment Caring Technology / Methodology / Procedure / Product learned today decrease water wastage at the time of washing of formwork of slabv
Details of the Construction / Engineering Drawings observed today r.c.c. stell design provided by str. consultant.
Details of the Bye Laws referred today parapet wall- min. height - 0.9m max height = 1.2m
Details of any Managerial Skill learned today politeness & co-operative
RATE ANALYSIS (Detailed Stepwise Calculations required) for 100 sq.ft. area of tiling- consider size of 1 tile = 2ft.x2ft. cost of one tile = 3oo Rs./tile no. of tile = 25 no.s total cost of tile = 7500 Rs. white cement = 600 Rs./bag sand require to level 1 brass = 4000 Rs/brass mason = 350 Rs. bigary = 150 Rs. total cost = 12600Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 12600 Rs. for 100 sq.ft. area of tiling.
Todays BUZZ Word contracts taken by different contractors as below= 1. labour contractor- contracts are taken on the basis of per labour & agreements are done by builder . 2. plumbing contractor - all the works of plumbing & fittings of pipe, taps .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-08

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) PATIL ADITYA PANDURANG
Exam No. 13538
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. LEVELLING ; To calculate reduced levels of footings as area is very large hence to check level of footings is same or not. 2. To observe casting of staircase.
Details of how you Planned & Executed the allotted work 1. First we had set instrument by levelling and centering it. 2. Then we measured height of instrument. 3. Then we had taken back sight and fore sight readings. 4. Then we had calculated reduced levels of points by H.I. method.
Details of the Construction Procedure / Activity / Technology learned today 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today Crushed sand ; 1. This is important ingredient of concrete. 2. It acts as binding agent in concrete, it forms bulk of concrete with aggregate. 3. It also is used in mortar for fly ash brick masonry. 4. Crush sand is made by fine grounding of stones. 5. Rate of crushed sand is 2200.00Rs per brass. 6. Test results has prooved that crush sand gives more strength than normal sand.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river .sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment.
Details of the Construction / Engineering Drawings observed today Center line plan, staircase drwaings,working drawings of plinth beam.
Details of the Bye Laws referred today Lift width provided on the site is 1.20m.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGULE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-08

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) MANGAONKAR MANOJ DATTATRAY
Exam No. 13536
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. LEVELLING ; To calculate reduced levels of footings as area is very large hence to check level of footings is same or not. 2. To observe casting of staircase.
Details of how you Planned & Executed the allotted work 1. First we had set instrument by levelling and centering it. 2. Then we measured height of instrument. 3. Then we had taken back sight and fore sight readings. 4. Then we had calculated reduced levels of points by H.I. method.
Details of the Construction Procedure / Activity / Technology learned today 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today Crushed sand ; 1. This is important ingredient of concrete. 2. It acts as binding agent in concrete, it forms bulk of concrete with aggregate. 3. It also is used in mortar for fly ash brick masonry. 4. Crush sand is made by fine grounding of stones. 5. Rate of crushed sand is 2200.00Rs per brass. 6. Test results has prooved that crush sand gives more strength than normal sand.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river .sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment.
Details of the Construction / Engineering Drawings observed today Center line plan, staircase drwaings,working drawings of plinth beam.
Details of the Bye Laws referred today Lift width provided on the site is 1.20m.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGULE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-08

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. LEVELLING ; To calculate reduced levels of footings as area is very large hence to check level of footings is same or not. 2. To observe casting of staircase.
Details of how you Planned & Executed the allotted work Levelling ; 1. First we had set instrument by levelling and centering it. 2. Then we measured height of instrument. 3. Then we had taken back sight and fore sight readings. 4. Then we had calculated reduced levels of points by H.I. method.
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today Crushed sand ; 1. This is important ingredient of concrete. 2. It acts as binding agent in concrete, it forms bulk of concrete with aggregate. 3. It also is used in mortar for fly ash brick masonry. 4. Crush sand is made by fine grounding of stones. 5. Rate of crushed sand is 2200.00Rs per brass. 6. Test results has prooved that crush sand gives more strength than normal sand.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river .sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment.
Details of the Construction / Engineering Drawings observed today Center line plan, staircase drwaings,working drawings of plinth beam.
Details of the Bye Laws referred today Lift width provided on the site is 1.20m.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGULE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-08

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Lad Manoj Sadashiv
Exam No. 13534
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the slab casting
Details of how you Planned & Executed the allotted work we divide our self in two groups 1 for observing procedure of compacting & another for checking quantity of sand & agg.
Details of the Construction Procedure / Activity / Technology learned today mixing of agg. ,sand , cement thoroughly to prepare quality concrete.
Details of the Construction Materials learned today admixture - super plasticizer - it increases workability of concrete
Details of Environment Caring Technology / Methodology / Procedure / Product learned today decrease water wastage at the time of washing of formwork of slab
Details of the Construction / Engineering Drawings observed today r.c.c. stell design provided by str. consultant.
Details of the Bye Laws referred today parapet wall- min. height - 0.9m max height = 1.2m
Details of any Managerial Skill learned today politeness & co-operative
RATE ANALYSIS (Detailed Stepwise Calculations required) for 100 sq.ft. area of tiling- consider size of 1 tile = 2ft.x2ft. cost of one tile = 3oo Rs./tile no. of tile = 25 no.s total cost of tile = 7500 Rs. white cement = 600 Rs./bag sand require to level 1 brass = 4000 Rs/brass mason = 350 Rs. bigary = 150 Rs. total cost = 12600Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 12600 Rs. for 100 sq.ft. area of tiling.
Todays BUZZ Word contracts taken by different contractors as below= 1. labour contractor- contracts are taken on the basis of per labour & agreements are done by builder . 2. plumbing contractor - all the works of plumbing & fittings of pipe, taps .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr Milind Magdum 9850508689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: rameshkharat1987@gmail.com
Subject: 13532-08

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Ramesh Laxman
Exam No. 13532
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the slab casting
Details of how you Planned & Executed the allotted work we divide our self in two groups 1 for observing procedure of compacting & another for checking quantity of sand & agg.
Details of the Construction Procedure / Activity / Technology learned today mixing of agg. ,sand , cement thoroughly to prepare quality concrete.
Details of the Construction Materials learned today admixture - super plasticizer - it increases workability of concrete
Details of Environment Caring Technology / Methodology / Procedure / Product learned today decrease water wastage at the time of washing of formwork of slab
Details of the Construction / Engineering Drawings observed today r.c.c. stell design provided by str. consultant.
Details of the Bye Laws referred today parapet wall- min. height - 0.9m max height = 1.2m
Details of any Managerial Skill learned today politeness & co-operative
RATE ANALYSIS (Detailed Stepwise Calculations required) for 100 sq.ft. area of tiling- consider size of 1 tile = 2ft.x2ft. cost of one tile = 3oo Rs./tile no. of tile = 25 no.s total cost of tile = 7500 Rs. white cement = 600 Rs./bag sand require to level 1 brass = 4000 Rs/brass mason = 350 Rs. bigary = 150 Rs. total cost = 12600Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 12600 Rs. for 100 sq.ft. area of tiling.
Todays BUZZ Word contracts taken by different contractors as below= 1. labour contractor- contracts are taken on the basis of per labour & agreements are done by builder . 2. plumbing contractor - all the works of plumbing & fittings of pipe, taps .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Milind Magdum MOb.- 9850508689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-08

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave, mukt sainik vasahat,kolhapur
Students Name (Surname_First Name_Middle Name) Shinde Shraddha Tukaram
Exam No. 10901
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 5.30pm
Details of the Work Allotted to you today by the Site In-Charge The work allotted to us today by the site in charge are as follows: 1) To visit whole site and investigate work going on the site. 2) To fill up the daily report form. 3) To prepare line out for septic tank & underground water tank in the given area on the site.
Details of how you Planned & Executed the allotted work -First of all,we started proceeding towards our site by observing work going on in the site. -One by one, we investigated all the flats and noted down details of the work going on. -Accordingly we observed all the seven floors. -From observation we filled up the daily report. -Further we proceeded to set out the line out work of septic tank by studying the plan layout of septic tank.
Details of the Construction Procedure / Activity / Technology learned today -For setting out line out of septic tank,first from given plan of septic tank, we marked one line of given dimension with the help of measurement tape. -From that line we marked all the points of corners of septic tank. -Chalk pit was used to denote those points of corners. -Small steel rods were fixed on those points. -For checking out whether the lines are straight or not or properly measured or not,Pythagoras theorem was used. -On one side the tape was held at 3\' from corner & 4\' on other side from that corner & diagonal in between was measured as 5\'. -If it does not come to 5\',then it is not in proper straight line. thus, the string held between both points is fixed accordingly.
Details of the Construction Materials learned today Today we learned construction materials like: -Concrete blocks used for compound walls. -Lifting crane to lift cement bags,sand etc from ground floor up to to the upper floor.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environment product learned today is: \"KERACEM ECO Pronto\"- They have used this product for tier construction purpose. This product is ready to use,Eco friendly,normal setting & rapid drying mineral screed to be covered with adhesive,ideal for use in green building. Low CO2 emissions,contains recycled raw materials.
Details of the Construction / Engineering Drawings observed today Today, we observed following drawings: -Septic tank -Anaerobic filter process detail -Underground water storage tank -Service layout
Details of the Bye Laws referred today Bye laws referred today are: -Septic tank shall have minimum internal width of 75cm. length of tank shall be 2-4 times width. -Septic tank may be constructed of brick work, stone, masonry, concrete. -Minimum nominal diameter of pipe shall be 100mm.Further at junctions of pipes in manholes,direction of flow from branch connection shall not make an angle exceeding 45degrrs with direction of flow in main pipe.
Details of any Managerial Skill learned today Today, sir had inspected the construction site to see whether the labors were doing their work properly or not,whether they were present on site or not and gave instructions about work carried on site. this will help him for giving payment of labors according to their work done.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for tiling: Vitrified tile flooring over 20mm lime mortar bed. A)Material required for 100sq.m. 1.Vitrified tile(605mmx605mm) No. of tiles=100/(0.605x0.605)=280nos. 2.Lime cement mortar(1:2:4)(20mm thk) Total qty. in wet condition=0.02x100=2cu.m. Qty. in dry condition (increase by 25%) =2+((25/100)x2)=2.5cu.m. 3.Cement=2.5/(1+2+4)=0.357=11bags Extra cement for neat cement slurry=11+6=17bags 4.Sand=0.357x4=1.428cu.m. 5.Lime=2x0.357=0.714cu.m. B)Cost of material: 1.Comet tile=280x140=Rs.39200 2.Cement=17x230=Rs.3910 3.Sand=1.428x850=Rs.1213.8 4.Lime=0.714x6000=Rs.4284 5.Polishing stone=Rs.500 6.Oxalic acid powder=Rs.150 TOTAL=Rs.49258 C)Cost of labor: 1.Mistry=2x250=Rs.500 2.Mason=15x170=Rs.2550 3.Male mazdoor=12x140=Rs.1680 4.Female mazdoor=10x120=Rs.1200 5.Bhisti=2x130=Rs.260 6.Polisher=4x130=Rs.520 7.T & P=Rs.500 TOTAL=Rs.7210 D)Total=B+C=Rs.56468 E)Add 2% water charges=Rs.1129.36 F)Add 15% contractor\'s profit=Rs.8470.2 G)Grand total=Rs.66067.56 H)Cost per sq.m.=Rs.33033.78
Result of RATE ANALYSIS ( Rs per Unit ) Rs.33033.78 per sq.m.
Todays BUZZ Word Today\'s buzz word: Contracts & agreement A contract is an agreement which can be enforced by law. Essential requirements of a valid contract are: -lawful subject matter -legally competent parties -valid consideration -free consent -provisions of law with regard to form Forms of contracts are: -Lump-sum contract -Unit price or item rate contract -Cost-plus or percentage contract
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Amol Mulay
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: patilpratibha7070@yahoo.in
Subject: 10896-08

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) patil pratibha dilip
Exam No. 10896
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the staging for open terrace provided at alternate floors using spans supported on steel props to support the slab of height 6.0m from the stilt floor level to the second floor slab bottom. Checking the levels, and height from floor level to the slab bottom at various places.
Details of how you Planned & Executed the allotted work Firstly we have checked the dimensions of open terrace over which the plates were being placed. Then we checked the height of slab bottom from stilt floor level. Then we observed the placing of the spans which were supported using the steel props and placed parallel to each other at equal distance above this spans planks were placed and props were erected over this spans and planks. We also checked the level of the centring plates in usual manner.
Details of the Construction Procedure / Activity / Technology learned today “Line out of columns at the second floor” one base line is tied at the face of column that are in line and the other base line is fixed at the face of building which is in straight line. With reference to this two base line the faces of column are marked by calculating the distance by deducting or adding the distance from the centre of column to its face as per required considering the position of column.
Details of the Construction Materials learned today No new material is used on the site
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today Detailed centre line plan
Details of the Bye Laws referred today Lift width provided on the site is 1.20m.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: vishalsapakal124@gmail.com
Subject: 10882-08

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) sapakal vishal manohar
Exam No. 10888
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the staging for open terrace provided at alternate floors using spans supported on steel props to support the slab of height 6.0m from the stilt floor level to the second floor slab bottom. Checking the levels, and height from floor level to the slab bottom at various places.
Details of how you Planned & Executed the allotted work Firstly we have checked the dimensions of open terrace over which the plates were being placed. Then we checked the height of slab bottom from stilt floor level. Then we observed the placing of the spans which were supported using the steel props and placed parallel to each other at equal distance above this spans planks were placed and props were erected over this spans and planks. We also checked the level of the centring plates in usual manner.
Details of the Construction Procedure / Activity / Technology learned today “Line out of columns at the second floor” one base line is tied at the face of column that are in line and the other base line is fixed at the face of building which is in straight line. With reference to this two base line the faces of column are marked by calculating the distance by deducting or adding the distance from the centre of column to its face as per required considering the position of column.
Details of the Construction Materials learned today No new material is used on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today Detailed centre line plan
Details of the Bye Laws referred today Lift width provided on the site is 1.20m.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: prasadkharat@ymail.com
Subject: 13531-08

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Prasad Ramachandra
Exam No. 13531
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the slab casting
Details of how you Planned & Executed the allotted work we divide our self in two groups 1 for observing procedure of compacting & another for checking quantity of sand & agg.
Details of the Construction Procedure / Activity / Technology learned today mixing of agg. ,sand , cement thoroughly to prepare quality concrete.
Details of the Construction Materials learned today admixture - super plasticizer - it increases workability of concrete
Details of Environment Caring Technology / Methodology / Procedure / Product learned today decrease water wastage at the time of washing of formwork of slab
Details of the Construction / Engineering Drawings observed today r.c.c. stell design provided by str. consultant.
Details of the Bye Laws referred today parapet wall- min. height - 0.9m max height = 1.2m
Details of any Managerial Skill learned today politeness & co-operative
RATE ANALYSIS (Detailed Stepwise Calculations required) for 100 sq.ft. area of tiling- consider size of 1 tile = 2ft.x2ft. cost of one tile = 3oo Rs./tile no. of tile = 25 no.s total cost of tile = 7500 Rs. white cement = 600 Rs./bag sand require to level 1 brass = 4000 Rs/brass mason = 350 Rs. bigary = 150 Rs. total cost = 12600Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 12600 Rs. for 100 sq.ft. area of tiling.
Todays BUZZ Word contracts taken by different contractors as below= 1. labour contractor- contracts are taken on the basis of per labour & agreements are done by builder . 2. plumbing contractor - all the works of plumbing & fittings of pipe, taps .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Milind Magdum MOb.- 9850508689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-08

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kolekar Shyam Suryakant
Exam No. 13533
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the slab casting
Details of how you Planned & Executed the allotted work we divide our self in two groups 1 for observing procedure of compacting & another for checking quantity of sand & agg.
Details of the Construction Procedure / Activity / Technology learned today mixing of agg. ,sand , cement thoroughly to prepare quality concrete.
Details of the Construction Materials learned today admixture - super plasticizer - it increases workability of concrete
Details of Environment Caring Technology / Methodology / Procedure / Product learned today decrease water wastage at the time of washing of formwork of slab
Details of the Construction / Engineering Drawings observed today r.c.c. stell design provided by str. consultant.
Details of the Bye Laws referred today parapet wall- min. height - 0.9m max height = 1.2m
Details of any Managerial Skill learned today politeness & co-operative
RATE ANALYSIS (Detailed Stepwise Calculations required) for 100 sq.ft. area of tiling- consider size of 1 tile = 2ft.x2ft. cost of one tile = 3oo Rs./tile no. of tile = 25 no.s total cost of tile = 7500 Rs. white cement = 600 Rs./bag sand require to level 1 brass = 4000 Rs/brass mason = 350 Rs. bigary = 150 Rs. total cost = 12600Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 12600 Rs. for 100 sq.ft. area of tiling.
Todays BUZZ Word contracts taken by different contractors as below= 1. labour contractor- contracts are taken on the basis of per labour & agreements are done by builder . 2. plumbing contractor - all the works of plumbing & fittings of pipe, taps .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Milind Magdum MOb.- 9850508689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-08

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Sharad Shankarrao
Exam No. 10897
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the construction of partition wall of fly ash bricks. .
Details of how you Planned & Executed the allotted work we observed how the mortar is prepared for filling in between the bricks & what proportion is taken for preparing the mortar .we also observed how the correct alignment of wall is taken. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of how the partition in 1:6 proportion for filling in between the bricks .the mortar is applied to the floor for preparing first layer .then the bricks are laid on it by filling the joints in between them by mortar. .
Details of the Construction Materials learned today today we discussed about the plate which are used for form work .the plates used here on the site are of size 3ft*2ft.for the support of plates ,props,or bamboos are used. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no such technology learned today. .
Details of the Construction / Engineering Drawings observed today today we observed the general drawing of the building for referring the column position & where partition walls are to be constructed. .
Details of the Bye Laws referred today in bye-laws today we referred the sizes of habitable rooms for the minimum size & width of the room. .
Details of any Managerial Skill learned today the material which comes on the site shall be checked by the supervisor & to clarify the same to the supplies for any damages or defectiveness. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-08

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Abhishek Dadasaheb
Exam No. 10895
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the construction of partition wall of fly ash bricks. .
Details of how you Planned & Executed the allotted work we observed how the mortar is prepared for filling in between the bricks & what proportion is taken for preparing the mortar .we also observed how the correct alignment of wall is taken. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of how the partition in 1:6 proportion for filling in between the bricks .the mortar is applied to the floor for preparing first layer .then the bricks are laid on it by filling the joints in between them by mortar. .
Details of the Construction Materials learned today today we discussed about the plate which are used for form work .the plates used here on the site are of size 3ft*2ft.for the support of plates ,props,or bamboos are used. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no such technology learned today. .
Details of the Construction / Engineering Drawings observed today today we observed the general drawing of the building for referring the column position & where partition walls are to be constructed. .
Details of the Bye Laws referred today in bye-laws today we referred the sizes of habitable rooms for the minimum size & width of the room. .
Details of any Managerial Skill learned today the material which comes on the site shall be checked by the supervisor & to clarify the same to the supplies for any damages or defectiveness. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: buntyphonde@gmail.com
Subject: 10899-08

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Phonde Pravin Tukaram
Exam No. 10899
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the construction of partition wall of fly ash bricks. .
Details of how you Planned & Executed the allotted work we observed how the mortar is prepared for filling in between the bricks & what proportion is taken for preparing the mortar .we also observed how the correct alignment of wall is taken. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of how the partition in 1:6 proportion for filling in between the bricks .the mortar is applied to the floor for preparing first layer .then the bricks are laid on it by filling the joints in between them by mortar. .
Details of the Construction Materials learned today today we discussed about the plate which are used for form work .the plates used here on the site are of size 3ft*2ft.for the support of plates ,props,or bamboos are used. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no such technology learned today. .
Details of the Construction / Engineering Drawings observed today today we observed the general drawing of the building for referring the column position & where partition walls are to be constructed. .
Details of the Bye Laws referred today in bye-laws today we referred the sizes of habitable rooms for the minimum size & width of the room. .
Details of any Managerial Skill learned today the material which comes on the site shall be checked by the supervisor & to clarify the same to the supplies for any damages or defectiveness. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-08

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Tambe Trusha Sitaram
Exam No. 10902
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the construction of partition wall of fly ash bricks. .
Details of how you Planned & Executed the allotted work we observed how the mortar is prepared for filling in between the bricks & what proportion is taken for preparing the mortar .we also observed how the correct alignment of wall is taken. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of how the partition in 1:6 proportion for filling in between the bricks .the mortar is applied to the floor for preparing first layer .then the bricks are laid on it by filling the joints in between them by mortar. .
Details of the Construction Materials learned today today we discussed about the plate which are used for form work .the plates used here on the site are of size 3ft*2ft.for the support of plates ,props,or bamboos are used. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no such technology learned today. .
Details of the Construction / Engineering Drawings observed today today we observed the general drawing of the building for referring the column position & where partition walls are to be constructed. .
Details of the Bye Laws referred today in bye-laws today we referred the sizes of habitable rooms for the minimum size & width of the room. .
Details of any Managerial Skill learned today the material which comes on the site shall be checked by the supervisor & to clarify the same to the supplies for any damages or defectiveness. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: salmanbaig18@gmail.com
Subject: 10888-08

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) baig salman samad
Exam No. 10888
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the staging for open terrace provided at alternate floors using spans supported on steel props to support the slab of height 6.0m from the stilt floor level to the second floor slab bottom. Checking the levels, and height from floor level to the slab bottom at various places.
Details of how you Planned & Executed the allotted work Firstly we have checked the dimensions of open terrace over which the plates were being placed. Then we checked the height of slab bottom from stilt floor level. Then we observed the placing of the spans which were supported using the steel props and placed parallel to each other at equal distance above this spans planks were placed and props were erected over this spans and planks. We also checked the level of the centring plates in usual manner.
Details of the Construction Procedure / Activity / Technology learned today “Line out of columns at the second floor” one base line is tied at the face of column that are in line and the other base line is fixed at the face of building which is in straight line. With reference to this two base line the faces of column are marked by calculating the distance by deducting or adding the distance from the centre of column to its face as per required considering the position of column.
Details of the Construction Materials learned today NONE
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No new material is used on the site.
Details of the Construction / Engineering Drawings observed today Detailed centre line plan
Details of the Bye Laws referred today Lift width provided on the site is 1.20m.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-08

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) babar moreshwar mahipati
Exam No. 10873
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the staging for open terrace provided at alternate floors using spans supported on steel props to support the slab of height 6.0m from the stilt floor level to the second floor slab bottom. Checking the levels, and height from floor level to the slab bottom at various places.
Details of how you Planned & Executed the allotted work Firstly we have checked the dimensions of open terrace over which the plates were being placed. Then we checked the height of slab bottom from stilt floor level. Then we observed the placing of the spans which were supported using the steel props and placed parallel to each other at equal distance above this spans planks were placed and props were erected over this spans and planks. We also checked the level of the centring plates in usual manner.
Details of the Construction Procedure / Activity / Technology learned today “Line out of columns at the second floor” one base line is tied at the face of column that are in line and the other base line is fixed at the face of building which is in straight line. With reference to this two base line the faces of column are marked by calculating the distance by deducting or adding the distance from the centre of column to its face as per required considering the position of column.
Details of the Construction Materials learned today NONE
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No new material is used on the site.
Details of the Construction / Engineering Drawings observed today Detailed centre line plan
Details of the Bye Laws referred today Lift width provided on the site is 1.20m.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-08

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) yadav hrisheekesh deepak
Exam No. 10885
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the staging for open terrace provided at alternate floors using spans supported on steel props to support the slab of height 6.0m from the stilt floor level to the second floor slab bottom. Checking the levels, and height from floor level to the slab bottom at various places.
Details of how you Planned & Executed the allotted work Firstly we have checked the dimensions of open terrace over which the plates were being placed. Then we checked the height of slab bottom from stilt floor level. Then we observed the placing of the spans which were supported using the steel props and placed parallel to each other at equal distance above this spans planks were placed and props were erected over this spans and planks. We also checked the level of the centring plates in usual manner.
Details of the Construction Procedure / Activity / Technology learned today “Line out of columns at the second floor” one base line is tied at the face of column that are in line and the other base line is fixed at the face of building which is in straight line. With reference to this two base line the faces of column are marked by calculating the distance by deducting or adding the distance from the centre of column to its face as per required considering the position of column.
Details of the Construction Materials learned today NONE
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No new material is used on the site.
Details of the Construction / Engineering Drawings observed today Detailed centre line plan
Details of the Bye Laws referred today Lift width provided on the site is 1.20m.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: cool.sushant007@gmail.com
Subject: 10880-08

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil sushant digambar
Exam No. 10880
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge TO check the arrangement required before casting the slab.
Details of how you Planned & Executed the allotted work we first divided our group members . three are on the ground floor and two the top floor where the casting of slab is to be done. then noted down the things related to the work.
Details of the Construction Procedure / Activity / Technology learned today If the area of floor is more, then usually the concreting is done in two parts. location is to be decided from where the material is lifted . then scaffolding is prepared according to the position. then mixer is placed near to it and weigh batching machine is placed near to that in levelled position. on the floor where the concreting is to be done, the place from where the material is to be taken is provided with non porous steel plates.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.KETAN CHARAPALE 9552597474.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-08

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) misal swapnil shivaji
Exam No. 10877
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge TO check the arrangement required before casting the slab.
Details of how you Planned & Executed the allotted work we first divided our group members . three are on the ground floor and two the top floor where the casting of slab is to be done. then noted down the things related to the work.
Details of the Construction Procedure / Activity / Technology learned today If the area of floor is more, then usually the concreting is done in two parts. location is to be decided from where the material is lifted . then scaffolding is prepared according to the position. then mixer is placed near to it and weigh batching machine is placed near to that in levelled position. on the floor where the concreting is to be done, the place from where the material is to be taken is provided with non porous steel plates.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today none
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge MR.KETAN CHARAPALE 9552597474.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: nitinpatil22.2010@rediffmail.com
Subject: 10879-08

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil nitin dilip
Exam No. 10879
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge TO check the arrangement required before casting the slab.
Details of how you Planned & Executed the allotted work we first divided our group members . three are on the ground floor and two the top floor where the casting of slab is to be done. then noted down the things related to the work.
Details of the Construction Procedure / Activity / Technology learned today If the area of floor is more, then usually the concreting is done in two parts. location is to be decided from where the material is lifted . then scaffolding is prepared according to the position. then mixer is placed near to it and weigh batching machine is placed near to that in levelled position. on the floor where the concreting is to be done, the place from where the material is to be taken is provided with non porous steel plates.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.KETAN CHARAPALE 9552597474.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-08

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHAIKH RIZWAN KHALIL
Exam No. 13545
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge TO check the arrangement required before casting the slab.
Details of how you Planned & Executed the allotted work we first divided our group members . three are on the ground floor and two the top floor where the casting of slab is to be done. then noted down the things related to the work.
Details of the Construction Procedure / Activity / Technology learned today If the area of floor is more, then usually the concreting is done in two parts. location is to be decided from where the material is lifted . then scaffolding is prepared according to the position. then mixer is placed near to it and weigh batching machine is placed near to that in levelled position. on the floor where the concreting is to be done, the place from where the material is to be taken is provided with non porous steel plates.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Ketan Charapale 9552597474 Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-08

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SALOKHE SUDARSHAN ANIL
Exam No. 13544
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge TO check the arrangement required before casting the slab.
Details of how you Planned & Executed the allotted work WE first divided our group members . three are on the ground floor and two the top floor where the casting of slab is to be done. then noted down the things related to the work.
Details of the Construction Procedure / Activity / Technology learned today If the area of floor is more, then usually the concreting is done in two parts. location is to be decided from where the material is lifted . then scaffolding is prepared according to the position. then mixer is placed near to it and weigh batching machine is placed near to that in levelled position. on the floor where the concreting is to be done, the place from where the material is to be taken is provided with non porous steel plates.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-08

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) BIRAJDAR MINAXI R.
Exam No. 13556
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge TO check the arrangement required before casting the slab.
Details of how you Planned & Executed the allotted work we first divided our group members . three are on the ground floor and two the top floor where the casting of slab is to be done. then noted down the things related to the work.
Details of the Construction Procedure / Activity / Technology learned today If the area of floor is more, then usually the concreting is done in two parts. location is to be decided from where the material is lifted . then scaffolding is prepared according to the position. then mixer is placed near to it and weigh batching machine is placed near to that in levelled position. on the floor where the concreting is to be done, the place from where the material is to be taken is provided with non porous steel plates.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-08

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SINGH RAJAN RAJENDRA BAHADUR
Exam No. 13548
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge TO check the arrangement required before casting the slab.
Details of how you Planned & Executed the allotted work we first divided our group members . three are on the ground floor and two the top floor where the casting of slab is to be done. then noted down the things related to the work.
Details of the Construction Procedure / Activity / Technology learned today If the area of floor is more, then usually the concreting is done in two parts. location is to be decided from where the material is lifted . then scaffolding is prepared according to the position. then mixer is placed near to it and weigh batching machine is placed near to that in levelled position. on the floor where the concreting is to be done, the place from where the material is to be taken is provided with non porous steel plates.
Details of the Construction Materials learned today concrete ingredients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Working drawings.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for tiling using lime cement mortar of 1:2:4“ Dimension of the room in which tiling is done =3.0*5.0m Mosaic Tile size=0.38*0.38 Lime cement mortar of 1:2:4 is used in thickness of 20mm:- 1. Surface area of flooring =15 sq.m 2. Quantity of lime mortar in wet condition =15*(0.02) =0.3 cu.m Add 25% of total volume for dry condition=0.3+0.3*025. = 0.375 cu.m 3. Quantity of cement =0.375/1+2+4 =0.0534 cu.m =0.0534/0.035=1.54=2 bags 4. Quantity of sand =0.0534*4=0.2136 cu.m. 5. quantity of lime =0.0534*2 =0.1068 cu.m “Rate Analysis for mosaic tiling using lime cement mortar of 1:2:4” (Considering local rates of material) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.2136*1600=342/-…………(1600/- per cu.m) 3.cost of lime = 0.1068*5500=583/-…………(5500/- per cu.m) 4.cost of tiles=104*50=5200/-………………..(50/- per piece) 5.Labour charges=1010/- 6. Total cost= 7386/- 8.10% profit of total cost for the contractor=738.6/- 9. Total cost=8124/- 10. Rate per sq.m=542/-
Result of RATE ANALYSIS ( Rs per Unit ) 542/-
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-08

Company Name Bhima Builders & Developers
Project Name & Site Address SKY VILLE OPP. SHIVAJI UNIVERSITY
Students Name (Surname_First Name_Middle Name) BULBULE KHANDOBA RAMCHANDRA
Exam No. 13557
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge a) To understand about ground level slab. b) To understand about steel formwork of slab.
Details of how you Planned & Executed the allotted work a) First we observe the actual plan of steel formwork of slab. b) Then observe the steel work on actual site. c) Then check the steel formwork according to steel formwork drawing.
Details of the Construction Procedure / Activity / Technology learned today a) Murum filling by pocland(JCB). b) To understand the proportion of R.M.C c) We observed placing of R.M.C by using piping.
Details of the Construction Materials learned today a) Tilting mixer. b) Piping system used for placing of concrete. c) Needle vibrator. d) R.M.C e) Tamping rod. f) Roller. g) JCB
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Nothing.
Details of the Construction / Engineering Drawings observed today a) Slab reinforcement drawing. b) Footing drawing. c) Column & beam reinforcement drawing.
Details of the Bye Laws referred today Maximum size of footing & slab may be provided by using by laws.
Details of any Managerial Skill learned today a) Control on the wastage of materials. b) Co-ordination between different agencies to ensure smooth working of the project.
RATE ANALYSIS (Detailed Stepwise Calculations required) a) Material required for 100sq.m tiles ( 20cm x 20cm) No.of tiles= 100/(0.2 x 0.2)= 2500 Nos. Lime cement morter ( 1:2:4) Total quantity of wet condition = 0.02 x 100 = 2 m3 Total quantity of dry condition ( Increase 25%) = 2+(25/100)x2 = 2.5m3 Cement quantity = 2.5/(1+2+4) = 0.357m3 Cement Bags = 0.357/0.035 = 9.92 10 bags Sand quantity = 4 x 0.357= 1.43 m3 Lime quantity = 2 x 0.357= 0.714 m3 Extra cement for jionts & cement slurry= 6 bags Total cement bags= 16 bags MATERIALS QTY RATE AMOUNT Tiles 2500 no\'s 700/- per m2 70,000/- Cement 16 bags 250/- per bag 4000/- Sand 1.428 m3 850/- per m3 1216/- Lime 0.714 m3 6000/- per m3 4296/- Polishing stone 500/- 500/- --------- TOTAL 80012/- LABOUR NO. RATE AMOUNT Mistry 1 300/- 300/- Mason 15 250/- 3750/- Male mazdor 12 180/- 2160/- Female mazdor 10 160/- 1600/- Bhisti 2 120/- 240/- Polisher 90 120/- 10800/- ---------- TOTAL 18,850/- TOTAL = 18850+80012 = 98862/- Add 1x1/2% water charges= 1490/- 10% cement profit = 9890/- TOTAL = 98862+1490+9890 = 110250/- PER m2 Cost per sq m = 110250/100 = 110.25 per sq m
Result of RATE ANALYSIS ( Rs per Unit ) 110.25/- per m2
Todays BUZZ Word Types-: 1) Item rate contract 2) Built up area basis contract 3) Lump sum contract 1) Item rate contract-: In this contract there may be one or more contractors. But for billing and measurements purposes the work is split into various items. 2) Built up area basis contract-: In this method the proposed rate is workout on the basis of estimated material cost,labour cost and overhead expenses. 3) Lump sum contract-: Normally,petty works are given on a lump sum basis which includes 100% completion of a perticular work in the decided lump sum amount.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-08

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Jape Vishwajeet Ramesh
Exam No. 10892
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 0430pm
Details of the Work Allotted to you today by the Site In-Charge 1) We had to determine the number of construction works to prepare the daily report. 2)We were also alloted to prepare line out for Septic Tank & Underground Tank. -------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work 1) We all five members made our team & went towards the site where the line out for the Septic Tank was to be Executed. 2) At first 3 members prepared the line out for the septic tank. 3) The remaining 2 members prepared the line out for underground Water Tank. -------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today # \"PRELIMINARY LINE OUT\" # - Decide on a permanent structure that was considerd during contouring work. - Locate the structure on the plan. - As per drawings measure the various distances from this structure. - Mark straight lines on grounds parallel to compound wall. - Set up the Theodolite on any corner & by taking perpendicular measurements finalize all four corners of Septic Tank -------------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. Concrete Blocks. 2. Line Dori. 3. Pegs. 4. Lifting Cranes. ------------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Storm Water Drains were made which were Discharged in a pit for ground water recharge. ---------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today - Septic Tank Details. - Details of Anaerobic Filter Process. - Underground Water Storage Tank Details. - Service Layout. -------------------------------------------------------------------------------------
Details of the Bye Laws referred today - Building Services. (pg 118) - Septic Tank (pg 104) --------------------------------------------------------------------------------------
Details of any Managerial Skill learned today - Sensitivity. - Punctuality. --------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) -# \"RATE ANALYSIS FOR TILED FLOORING\" #- A. Material Required: ( 100 sq.m) 1 Vitrified Tiles (605 x 605 mm): No of tiles = 280 nos. 2. Lime Cement Mortor (1:2:4) (20 mm thk) Total Quantity in wet condition = 2 cu.m Quantity in Dry Condition = 2.5 cu.m 3. Cement = 0.357 = 11 bags. Extra Cement for neat Cement Slurry = 11+6 = 17 bags. 4. Sand = 0.357 x 4 = 1.428 cu.m 5. Lime = 0.357 x 2 = 0.714 cu.m B. Cost Of Material: 1. Commet Tile = 280 x 140 = 39200/- 2. Cement = 17 x 230 = 3910/- 3. Sand = 1.428 x 850 = 1213.8/- 4. lime = 0.714 x 6000 = 4284/- 5. Polishing stone = 500/- 6. Auxilic Acid Powder = 150/- TOTAL = 49257.8/- C. Cost Of Labour: 1. Mistri = 2 x 250 = 500/- 2. Mason = 15 x 170 = 2550/- 3. Male Mazdoor = 12 x 140 = 1680/- 4. Female Mazdoor = 10 x 120 = 1200/- 5. Bhisti = 2 x 130 = 260/- 6. Polisher = 4 x 130 = 520/- 7. T & P = 500/- TOTAL = 7210/- D. Total Cost = B + C = 56467.8/- E. Add 2% water charges = 1129.356/- F. Add 15% contractors Profit = 8470. 17/- G. Grand Toatal = 66067.326/- H. Cost Per Sq.M = 660.67/- ----------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs.660.67/-
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-08

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Nagvekar Yogesh Deepak
Exam No. 10894
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:30pm
Details of the Work Allotted to you today by the Site In-Charge 1) We had to determine the number of construction works to prepare the daily report. 2)We were also alloted to prepare line out for Septic Tank & Underground Tank. -------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work 1) We all five members made our team & went towards the site where the line out for the Septic Tank was to be Executed. 2) At first 3 members prepared the line out for the septic tank. 3) The remaining 2 members prepared the line out for underground Water Tank. -------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today # \"PRELIMINARY LINE OUT\" # - Decide on a permanent structure that was considerd during contouring work. - Locate the structure on the plan. - As per drawings measure the various distances from this structure. - Mark straight lines on grounds parallel to compound wall. - Set up the Theodolite on any corner & by taking perpendicular measurements finalize all four corners of Septic Tank -------------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. Concrete Blocks. 2. Line Dori. 3. Pegs. 4. Lifting Cranes. ------------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - Storm Water Drains were made which were Discharged in a pit for ground water recharge. ---------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today - Septic Tank Details. - Details of Anaerobic Filter Process. - Underground Water Storage Tank Details. - Service Layout. -------------------------------------------------------------------------------------
Details of the Bye Laws referred today - Building Services. (pg 118) - Septic Tank (pg 104) --------------------------------------------------------------------------------------
Details of any Managerial Skill learned today - Sensitivity. - Punctuality. --------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) -# \"RATE ANALYSIS FOR TILED FLOORING\" #- A. Material Required: ( 100 sq.m) 1 Vitrified Tiles (605 x 605 mm): No of tiles = 280 nos. 2. Lime Cement Mortor (1:2:4) (20 mm thk) Total Quantity in wet condition = 2 cu.m Quantity in Dry Condition = 2.5 cu.m 3. Cement = 0.357 = 11 bags. Extra Cement for neat Cement Slurry = 11+6 = 17 bags. 4. Sand = 0.357 x 4 = 1.428 cu.m 5. Lime = 0.357 x 2 = 0.714 cu.m B. Cost Of Material: 1. Commet Tile = 280 x 140 = 39200/- 2. Cement = 17 x 230 = 3910/- 3. Sand = 1.428 x 850 = 1213.8/- 4. lime = 0.714 x 6000 = 4284/- 5. Polishing stone = 500/- 6. Auxilic Acid Powder = 150/- TOTAL = 49257.8/- C. Cost Of Labour: 1. Mistri = 2 x 250 = 500/- 2. Mason = 15 x 170 = 2550/- 3. Male Mazdoor = 12 x 140 = 1680/- 4. Female Mazdoor = 10 x 120 = 1200/- 5. Bhisti = 2 x 130 = 260/- 6. Polisher = 4 x 130 = 520/- 7. T & P = 500/- TOTAL = 7210/- D. Total Cost = B + C = 56467.8/- E. Add 2% water charges = 1129.356/- F. Add 15% contractors Profit = 8470. 17/- G. Grand Toatal = 66067.326/- H. Cost Per Sq.M = 660.67/- ----------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs.660.67/-
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-08

Company Name Bhima Builders & Developers
Project Name & Site Address SKY VILLE OPP. SHIVAJI UNIVERSITY
Students Name (Surname_First Name_Middle Name) REDEKAR SHANTANU RAVINDRA
Exam No. 13566
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge a) To understand about ground level slab. b) To understand about steel formwork of slab.
Details of how you Planned & Executed the allotted work a) First we observe the actual plan of steel formwork of slab. b) Then observe the steel work on actual site. c) Then check the steel formwork according to steel formwork drawing.
Details of the Construction Procedure / Activity / Technology learned today a) Murum filling by pocland(JCB). b) To understand the proportion of R.M.C c) We observed placing of R.M.C by using piping.
Details of the Construction Materials learned today a) Tilting mixer. b) Piping system used for placing of concrete. c) Needle vibrator. d) R.M.C e) Tamping rod. f) Roller. g) JCB
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Nothing.
Details of the Construction / Engineering Drawings observed today a) Slab reinforcement drawing. b) Footing drawing. c) Column & beam reinforcement drawing.
Details of the Bye Laws referred today Maximum size of footing & slab may be provided by using by laws.
Details of any Managerial Skill learned today a) Control on the wastage of materials. b) Co-ordination between different agencies to ensure smooth working of the project.
RATE ANALYSIS (Detailed Stepwise Calculations required) a) Material required for 100sq.m tiles ( 20cm x 20cm) No.of tiles= 100/(0.2 x 0.2)= 2500 Nos. Lime cement morter ( 1:2:4) Total quantity of wet condition = 0.02 x 100 = 2 m3 Total quantity of dry condition ( Increase 25%) = 2+(25/100)x2 = 2.5m3 Cement quantity = 2.5/(1+2+4) = 0.357m3 Cement Bags = 0.357/0.035 = 9.92 10 bags Sand quantity = 4 x 0.357= 1.43 m3 Lime quantity = 2 x 0.357= 0.714 m3 Extra cement for jionts & cement slurry= 6 bags Total cement bags= 16 bags MATERIALS QTY RATE AMOUNT Tiles 2500 no\'s 700/- per m2 70,000/- Cement 16 bags 250/- per bag 4000/- Sand 1.428 m3 850/- per m3 1216/- Lime 0.714 m3 6000/- per m3 4296/- Polishing stone 500/- 500/- --------- TOTAL 80012/- LABOUR NO. RATE AMOUNT Mistry 1 300/- 300/- Mason 15 250/- 3750/- Male mazdor 12 180/- 2160/- Female mazdor 10 160/- 1600/- Bhisti 2 120/- 240/- Polisher 90 120/- 10800/- ---------- TOTAL 18,850/- TOTAL = 18850+80012 = 98862/- Add 1x1/2% water charges= 1490/- 10% cement profit = 9890/- TOTAL = 98862+1490+9890 = 110250/- PER m2 Cost per sq m = 110250/100 = 110.25 per sq m
Result of RATE ANALYSIS ( Rs per Unit ) 110.25/- per m2
Todays BUZZ Word Types-: 1) Item rate contract 2) Built up area basis contract 3) Lump sum contract 1) Item rate contract-: In this contract there may be one or more contractors. But for billing and measurements purposes the work is split into various items. 2) Built up area basis contract-: In this method the proposed rate is workout on the basis of estimated material cost,labour cost and overhead expenses. 3) Lump sum contract-: Normally,petty works are given on a lump sum basis which includes 100% completion of a perticular work in the decided lump sum amount.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-08

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Sawant Amit Ganpat
Exam No. 10900
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise the construction of partition wall of fly ash bricks. .
Details of how you Planned & Executed the allotted work we observed how the mortar is prepared for filling in between the bricks & what proportion is taken for preparing the mortar .we also observed how the correct alignment of wall is taken. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of how the partition in 1:6 proportion for filling in between the bricks .the mortar is applied to the floor for preparing first layer .then the bricks are laid on it by filling the joints in between them by mortar. .
Details of the Construction Materials learned today today we discussed about the plate which are used for form work .the plates used here on the site are of size 3ft*2ft.for the support of plates ,props,or bamboos are used. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no such technology learned today. .
Details of the Construction / Engineering Drawings observed today today we observed the general drawing of the building for referring the column position & where partition walls are to be constructed. .
Details of the Bye Laws referred today in bye-laws today we referred the sizes of habitable rooms for the minimum size & width of the room. .
Details of any Managerial Skill learned today the material which comes on the site shall be checked by the supervisor & to clarify the same to the supplies for any damages or defectiveness. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-08

Company Name Bhima Builders & Developers
Project Name & Site Address SKY VILLE OPP. SHIVAJI UNIVERSITY
Students Name (Surname_First Name_Middle Name) MOHARE VISHAL BHALCHANDRA
Exam No. 13564
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge a) To understand about ground level slab. b) To understand about steel formwork of slab.
Details of how you Planned & Executed the allotted work a) First we observe the actual plan of steel formwork of slab. b) Then observe the steel work on actual site. c) Then check the steel formwork according to steel formwork drawing.
Details of the Construction Procedure / Activity / Technology learned today a) Murum filling by pocland(JCB). b) To understand the proportion of R.M.C c) We observed placing of R.M.C by using piping.
Details of the Construction Materials learned today a) Tilting mixer. b) Piping system used for placing of concrete. c) Needle vibrator. d) R.M.C e) Tamping rod. f) Roller. g) JCB
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Nothing.
Details of the Construction / Engineering Drawings observed today a) Slab reinforcement drawing. b) Footing drawing. c) Column & beam reinforcement drawing.
Details of the Bye Laws referred today Maximum size of footing & slab may be provided by using by laws.
Details of any Managerial Skill learned today a) Control on the wastage of materials. b) Co-ordination between different agencies to ensure smooth working of the project.
RATE ANALYSIS (Detailed Stepwise Calculations required) a) Material required for 100sq.m tiles ( 20cm x 20cm) No.of tiles= 100/(0.2 x 0.2)= 2500 Nos. Lime cement morter ( 1:2:4) Total quantity of wet condition = 0.02 x 100 = 2 m3 Total quantity of dry condition ( Increase 25%) = 2+(25/100)x2 = 2.5m3 Cement quantity = 2.5/(1+2+4) = 0.357m3 Cement Bags = 0.357/0.035 = 9.92 10 bags Sand quantity = 4 x 0.357= 1.43 m3 Lime quantity = 2 x 0.357= 0.714 m3 Extra cement for jionts & cement slurry= 6 bags Total cement bags= 16 bags MATERIALS QTY RATE AMOUNT Tiles 2500 no\'s 700/- per m2 70,000/- Cement 16 bags 250/- per bag 4000/- Sand 1.428 m3 850/- per m3 1216/- Lime 0.714 m3 6000/- per m3 4296/- Polishing stone 500/- 500/- --------- TOTAL 80012/- LABOUR NO. RATE AMOUNT Mistry 1 300/- 300/- Mason 15 250/- 3750/- Male mazdor 12 180/- 2160/- Female mazdor 10 160/- 1600/- Bhisti 2 120/- 240/- Polisher 90 120/- 10800/- ---------- TOTAL 18,850/- TOTAL = 18850+80012 = 98862/- Add 1x1/2% water charges= 1490/- 10% cement profit = 9890/- TOTAL = 98862+1490+9890 = 110250/- PER m2 Cost per sq m = 110250/100 = 110.25 per sq m
Result of RATE ANALYSIS ( Rs per Unit ) 110.25/- per m2
Todays BUZZ Word Types-: 1) Item rate contract 2) Built up area basis contract 3) Lump sum contract 1) Item rate contract-: In this contract there may be one or more contractors. But for billing and measurements purposes the work is split into various items. 2) Built up area basis contract-: In this method the proposed rate is workout on the basis of estimated material cost,labour cost and overhead expenses. 3) Lump sum contract-: Normally,petty works are given on a lump sum basis which includes 100% completion of a perticular work in the decided lump sum amount.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-08

Company Name Bhima Builders & Developers
Project Name & Site Address SKY VILLE OPP. SHIVAJI UNIVERSITY
Students Name (Surname_First Name_Middle Name) KHADE AMARDEEP BHAGWAN
Exam No. 13563
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge a) To understand about ground level slab. b) To understand about steel formwork of slab.
Details of how you Planned & Executed the allotted work a) First we observe the actual plan of steel formwork of slab. b) Then observe the steel work on actual site. c) Then check the steel formwork according to steel formwork drawing.
Details of the Construction Procedure / Activity / Technology learned today a) Murum filling by pocland(JCB). b) To understand the proportion of R.M.C c) We observed placing of R.M.C by using piping.
Details of the Construction Materials learned today a) Tilting mixer. b) Piping system used for placing of concrete. c) Needle vibrator. d) R.M.C e) Tamping rod. f) Roller. g) JCB
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Nothing.
Details of the Construction / Engineering Drawings observed today a) Slab reinforcement drawing. b) Footing drawing. c) Column & beam reinforcement drawing.
Details of the Bye Laws referred today Maximum size of footing & slab may be provided by using by laws.
Details of any Managerial Skill learned today a) Control on the wastage of materials. b) Co-ordination between different agencies to ensure smooth working of the project.
RATE ANALYSIS (Detailed Stepwise Calculations required) a) Material required for 100sq.m tiles ( 20cm x 20cm) No.of tiles= 100/(0.2 x 0.2)= 2500 Nos. Lime cement morter ( 1:2:4) Total quantity of wet condition = 0.02 x 100 = 2 m3 Total quantity of dry condition ( Increase 25%) = 2+(25/100)x2 = 2.5m3 Cement quantity = 2.5/(1+2+4) = 0.357m3 Cement Bags = 0.357/0.035 = 9.92 10 bags Sand quantity = 4 x 0.357= 1.43 m3 Lime quantity = 2 x 0.357= 0.714 m3 Extra cement for jionts & cement slurry= 6 bags Total cement bags= 16 bags MATERIALS QTY RATE AMOUNT Tiles 2500 no\'s 700/- per m2 70,000/- Cement 16 bags 250/- per bag 4000/- Sand 1.428 m3 850/- per m3 1216/- Lime 0.714 m3 6000/- per m3 4296/- Polishing stone 500/- 500/- --------- TOTAL 80012/- LABOUR NO. RATE AMOUNT Mistry 1 300/- 300/- Mason 15 250/- 3750/- Male mazdor 12 180/- 2160/- Female mazdor 10 160/- 1600/- Bhisti 2 120/- 240/- Polisher 90 120/- 10800/- ---------- TOTAL 18,850/- TOTAL = 18850+80012 = 98862/- Add 1x1/2% water charges= 1490/- 10% cement profit = 9890/- TOTAL = 98862+1490+9890 = 110250/- PER m2 Cost per sq m = 110250/100 = 110.25 per sq m
Result of RATE ANALYSIS ( Rs per Unit ) 110.25/- per m2
Todays BUZZ Word Types-: 1) Item rate contract 2) Built up area basis contract 3) Lump sum contract 1) Item rate contract-: In this contract there may be one or more contractors. But for billing and measurements purposes the work is split into various items. 2) Built up area basis contract-: In this method the proposed rate is workout on the basis of estimated material cost,labour cost and overhead expenses. 3) Lump sum contract-: Normally,petty works are given on a lump sum basis which includes 100% completion of a perticular work in the decided lump sum amount.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: Rohit_patil361@rediffmail.com
Subject: 13565-08

Company Name Bhima Builders & Developers
Project Name & Site Address SKY VILLE OPP. SHIVAJI UNIVERSITY
Students Name (Surname_First Name_Middle Name) PATIL ROHIT ASHOK
Exam No. 13565
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge a) To understand about ground level slab. b) To understand about steel form work of slab.
Details of how you Planned & Executed the allotted work a) First we observe the actual plan of steel form work of slab. b) Then observe the steel work on actual site. c) Then check the steel form work according to steel form work drawing
Details of the Construction Procedure / Activity / Technology learned today a) Murum filling by pock land(J.C.B). b) To understand the proportion of R.M.C c) We observed placing of R.M.C by using piping.
Details of the Construction Materials learned today a) Tilting mixer. b) Piping system used for placing of concrete. c) Needle vibrator. d) R.M.C e) Tamping rod. f) Roller. g) JCB
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Nothing.
Details of the Construction / Engineering Drawings observed today a) Slab reinforcement drawing. b) Footing drawing. c) Column & beam reinforcement drawing.
Details of the Bye Laws referred today Maximum size of footing & slab may be provided by using by laws.
Details of any Managerial Skill learned today a) Control on the wastage of materials. b) Co-ordination between different agencies to ensure smooth working of the project.
RATE ANALYSIS (Detailed Stepwise Calculations required) a) Material required for 100sq.m tiles ( 20cm x 20cm) No.of tiles= 100/(0.2 x 0.2)= 2500 Nos. Lime cement morter ( 1:2:4) Total quantity of wet condition = 0.02 x 100 = 2 m3 Total quantity of dry condition ( Increase 25%) = 2+(25/100)x2 = 2.5m3 Cement quantity = 2.5/(1+2+4) = 0.357m3 Cement Bags = 0.357/0.035 = 9.92 10 bags Sand quantity = 4 x 0.357= 1.43 m3 Lime quantity = 2 x 0.357= 0.714 m3 Extra cement for jionts & cement slurry= 6 bags Total cement bags= 16 bags MATERIALS QTY RATE AMOUNT Tiles 2500 no\'s 700/- per m2 70,000/- Cement 16 bags 250/- per bag 4000/- Sand 1.428 m3 850/- per m3 1216/- Lime 0.714 m3 6000/- per m3 4296/- Polishing stone 500/- 500/- --------- TOTAL 80012/- LABOUR NO. RATE AMOUNT Mistry 1 300/- 300/- Mason 15 250/- 3750/- Male mazdor 12 180/- 2160/- Female mazdor 10 160/- 1600/- Bhisti 2 120/- 240/- Polisher 90 120/- 10800/- ---------- TOTAL 18,850/- TOTAL = 18850+80012 = 98862/- Add 1x1/2% water charges= 1490/- 10% cement profit = 9890/- TOTAL = 98862+1490+9890 = 110250/- PER m2 Cost per sq m = 110250/100 = 110.25 per sq m
Result of RATE ANALYSIS ( Rs per Unit ) 110.25/- per m2
Todays BUZZ Word Contracts & Aggrements Types-: 1) Item rate contract 2) Built up area basis contract 3) Lump sum contract 1) Item rate contract-: In this contract there may be one or more contractors. But for billing and measurements purposes the work is split into various items. 2) Built up area basis contract-: In this method the proposed rate is workout on the basis of estimated material cost,labour cost and overhead expenses. 3) Lump sum contract-: Normally,petty works are given on a lump sum basis which includes 100% completion of a perticular work in the decided lump sum amount.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-07

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bhoite Vishal Rajaram
Exam No. 13555
Working Day No. 07
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge The foll.work has been alloted- 1) Told us to study the electrical layout 2) Study the positions and requirments of the electrical points according to layout. 3) After studing the plan the electrical points were fixed. 4) To check the electrical materials
Details of how you Planned & Executed the allotted work The planning was done in foll. manner- 1) We first in group studied the plan. 2) After that as per the group of labours we divided ourselves in two groups. 3) One group took the height of electrical points and the other group marked the position of electrical points.
Details of the Construction Procedure / Activity / Technology learned today The foll. construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested.
Details of the Construction Materials learned today The foll. materials were observed today:- 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today 1) Floor plans 2) Electrical layouts for each floor.
Details of the Bye Laws referred today 1)Meter room 2) Common antena for television transmission reception.
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 sq.m Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- Sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs 1000
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-07

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bauchakar Deepak Yuvraj
Exam No. 13554
Working Day No. 07
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge The foll.work has been alloted- 1) Told us to study the electrical layout 2) Study the positions and requirments of the electrical points according to layout. 3) After studing the plan the electrical points were fixed. 4) To check the electrical materials
Details of how you Planned & Executed the allotted work The planning was done in foll. manner- 1) We first in group studied the plan. 2) After that as per the group of labours we divided ourselves in two groups. 3) One group took the height of electrical points and the other group marked the position of electrical points.
Details of the Construction Procedure / Activity / Technology learned today The foll. construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested.
Details of the Construction Materials learned today The foll. materials were observed today:- 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today 1) Floor plans 2) Electrical layouts for each floor.
Details of the Bye Laws referred today 1)Meter room 2) Common antena for television transmission reception.
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 sq.m Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- Sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs 1000
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-08

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Suyvanshi patil Pratiksinh Vilas
Exam No. 13549
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge The foll.work has been alloted- 1) Told us to study the electrical layout 2) Study the positions and requirments of the electrical points according to layout. 3) After studing the plan the electrical points were fixed. 4) To check the electrical materials
Details of how you Planned & Executed the allotted work The planning was done in foll. manner- 1) We first in group studied the plan. 2) After that as per the group of labours we divided ourselves in two groups. 3) One group took the height of electrical points and the other group marked the position of electrical points.
Details of the Construction Procedure / Activity / Technology learned today The foll. construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested.
Details of the Construction Materials learned today The foll. materials were observed today:- 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today 1) Floor plans 2) Electrical layouts for each floor.
Details of the Bye Laws referred today 1)Meter room 2) Common antena for television transmission reception.
Details of any Managerial Skill learned today 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 sq.m Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- Sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs 1000
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the pile foundation in cloud 9 project. -To see the casting of slab in cloud 9 project. -To meet plumber contractor and take all details about plumbing.
Details of how you Planned & Executed the allotted work 1) First we visited cloud 9 project and see the pressure pile working and took all details. 2) Then we see the casting of 3rd floor slab of cloud 9project. 3)Then we came back to our project and met Mr.Dhavale plumber contractor. 4)He gave us an lecture on types of plumbing and working of plumbing.
Details of the Construction Procedure / Activity / Technology learned today Pressure pile : 1)First according to plan location of piles are decided. 2)Then machinery are setup and pile excavation is started. 3) Around the pile casing is placed and pile is formed. Slab: 1) First formwork is prepared for slab. 2)Then reinforcement arrangement is done according to R.C.C. Design. 3) Then concrete is prepared . 4)Lift is constructed for transportation of concrete from ground level to required floor level. 5) Then concrete is placed and compacted with the help of surface vibrator compaction is done .
Details of the Construction Materials learned today Crushed sand , surface vibrator, concrete M-20, superplasticers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain water harvesting is done for row bunglows only. 1.5\" diameter pipe is used for downtake of water. From these the rainwater recharges the ground water table.
Details of the Construction / Engineering Drawings observed today Detail layout of pressure pile foundation.
Details of the Bye Laws referred today External wall 230mm is provided. Internal wall 100mm is provided.
Details of any Managerial Skill learned today We met Mr.Raju Dhavale and he gave us detail information about plumbing fixtures and material and working. He gave us information as a teacher.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILES : Cement = 0.22 * 255 = 56 Rs/- Sand = 1.35 C.F.T. * 43 = 58 Rs/- Tile = 1 sq.m * 430 Rs/-= 430 Rs/- Labour = 1sq.m . * 75 =75 Rs/- Total = 610Rs/- Builders profit including Service tax , VAT etc. = 732Rs/- per sq.m. 20 % Vetrified tiles are used . In each box contains 4 tiles of Rs. 300
Result of RATE ANALYSIS ( Rs per Unit ) 732Rs/- sq.m
Todays BUZZ Word CONTRACTS & AGREEMENT: Contracts: Type of contracts: 1) Item rate contract. 2) Built up area basis contract. 3) Lump sum contract. 1)Item rate contract: In these type of contract, there may be one or more contractors. But for billing & measurement purposes , the work is split into various items. 2) Built up area basis contract.: These method has proved to be the most easy method . Hence , it is the most popular method. The work is split into various items i.e. R.C.C. ,masonry ,tiling , plumbing etc.This works are entrusted to small but specialized petty contractors on labour rates only. 3)Lump sum contract: Petty works are given on a lump sum basis, which includes 100% completion of a particular activity or work in the decided lump sum amount. AGREEMENT: Agreement is a legal document which acts as a legal binding between both the parties. - Agreements acts as a basic document of arbitaration in case of a dispute. - Most agreements have similar conditions for all the work activities , differing mainly in the scope of work , mode of measurements and payment terms. Advantages of an agreement : - Confirms the rates of various items. - Provides legal binding and supports to both the paries in case of dispute. - Contractor gets an idea about the scope of work, other conditions & mode of measurements before commencing the work . - Contractor understands the work procedure & the quality expected . - The agreement helps reach an understanding between both parties before the work begins.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: v.g.ayyar@gmail.com
Subject: 13553-08

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Ayyar Vignesh Gopal
Exam No. 13553
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge The foll.work has been alloted- 1) Told us to study the electrical layout 2) Study the positions and requirments of the electrical points according to layout. 3) After studing the plan the electrical points were fixed. 4) To check the electrical materials
Details of how you Planned & Executed the allotted work The planning was done in foll. manner- 1) We first in group studied the plan. 2) After that as per the group of labours we divided ourselves in two groups. 3) One group took the height of electrical points and the other group marked the position of electrical points.
Details of the Construction Procedure / Activity / Technology learned today The foll. construction procedure was observed on the Site:- 1) Earthing: - A pit of 90*90*90 cm was dug at a height of 1.5m below the G.L - 15cm layer of charcoal was filled for the resistance of soil. - A Copper Galvanised Iron wire was attached to the earthing plate and was left in the pit. - Then the pit was filled with soil and water was poured onto it to maintain the safe value of safe resistance. 2) Casing-Caping wiring - A suitable casing was selected to fit no. of wires in the route. - The bunch of wires was inserted in the casing and then capping channel was pressed onto it. - Then the casing was fixed on the walls as per the lines marked. - The wires were inserted in the casing channel and were allowed to pass the other end of casing. - Then the board and accessories were fixed accordingly. - The current supply was started and all points were tested.
Details of the Construction Materials learned today The foll. materials were observed today:- 1) PVC pipes. 2) Wooden blocks. 3) Switch boards. 4) Distribution box. 5)Casing & Caping wiring 6) Copper Galvainised wire.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today The foll. Drawings were observed 1) Floor plans 2) Electrical layouts for each floor.
Details of the Bye Laws referred today The foll Bye-Laws were reffered:- 1)Meter room 2) Common antena for television transmission reception.
Details of any Managerial Skill learned today The foll. manegerials skills were learnt today :- 1) To get the work done for the labours. 2) Sensitivness. 3) Punctuality.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 sq.m Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- Sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs 1000
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-08

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Swapnil Ashok
Exam No. 13529
Working Day No. 08
Date (DD/MM/YYYY) 16.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1)to see the brickwork. 2)to check the plaster.
Details of how you Planned & Executed the allotted work 1)we checked the brickwork with the help of plumb bob. 2)we checked the plaster with the help of rope called as line dori,to know if there are any undulations in the plastered surface. the site incharge helped us a lot.
Details of the Construction Procedure / Activity / Technology learned today how to check the brickwork with the help of plumb bob.
Details of the Construction Materials learned today 1)use of plumb bob. 2)use of line dori.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of soil which is excavated for foundation purpose is used to fill-up the murums.
Details of the Construction / Engineering Drawings observed today beam drawings.
Details of the Bye Laws referred today parking:- 1)four vehicle parking-2.5*5.5 m 2)two wheeler parking-1.5*3 m
Details of any Managerial Skill learned today After completion of the formwork the slab should be checked,wether there is any undulation in the slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILLING ; rate per sq.m CEMENT = 3.0 kg = 20.00 Rs. SAND = 0.3 cu.m. = 150.00 Rs. TILE (size 0.45m.* 0.3m.) = 10 numbers = 620.00 Rs. Labour = 125.00 Rs. TOTAL = 745.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 745
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-08

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Nilam Jaywant
Exam No. 13528
Working Day No. 08
Date (DD/MM/YYYY) 16.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1)to see the brickwork. 2)to check the plaster.
Details of how you Planned & Executed the allotted work 1)we checked the brickwork with the help of plumb bob. 2)we checked the plaster with the help of rope called as line dori,to know if there are any undulations in the plastered surface. the site incharge helped us a lot.
Details of the Construction Procedure / Activity / Technology learned today how to check the brickwork with the help of plumb bob.
Details of the Construction Materials learned today 1)use of plumb bob. 2)use of line dori.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of soil which is excavated for foundation purpose is used to fill-up the murums.
Details of the Construction / Engineering Drawings observed today beam drawings.
Details of the Bye Laws referred today parking:- 1)four vehicle parking-2.5*5.5 m 2)two wheeler parking-1.5*3 m
Details of any Managerial Skill learned today After completion of the formwork the slab should be checked,wether there is any undulation in the slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILLING ; rate per sq.m CEMENT = 3.0 kg = 20.00 Rs. SAND = 0.3 cu.m. = 150.00 Rs. TILE (size 0.45m.* 0.3m.) = 10 numbers = 620.00 Rs. Labour = 125.00 Rs. TOTAL = 745.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 745
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the pile foundation in cloud 9 project. -To see the casting of slab in cloud 9 project. -To meet plumber contractor and take all details about plumbing.
Details of how you Planned & Executed the allotted work 1) First we visited cloud 9 project and see the pressure pile working and took all details. 2) Then we see the casting of 3rd floor slab of cloud 9project. 3)Then we came back to our project and met Mr.Dhavale plumber contractor. 4)He gave us an lecture on types of plumbing and working of plumbing.
Details of the Construction Procedure / Activity / Technology learned today Pressure pile : 1)First according to plan location of piles are decided. 2)Then machinery are setup and pile excavation is started. 3) Around the pile casing is placed and pile is formed. Slab: 1) First formwork is prepared for slab. 2)Then reinforcement arrangement is done according to R.C.C. Design. 3) Then concrete is prepared . 4)Lift is constructed for transportation of concrete from ground level to required floor level. 5) Then concrete is placed and compacted with the help of surface vibrator compaction is done .
Details of the Construction Materials learned today Crushed sand , surface vibrator, concrete M-20, superplasticers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain water harvesting is done for row bunglows only. 1.5\" diameter pipe is used for downtake of water. From these the rainwater recharges the ground water table.
Details of the Construction / Engineering Drawings observed today Detail layout of pressure pile foundation.
Details of the Bye Laws referred today External wall 230mm is provided. Internal wall 100mm is provided.
Details of any Managerial Skill learned today We met Mr.Raju Dhavale and he gave us detail information about plumbing fixtures and material and working. He gave us information as a teacher.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILES : Cement = 0.22 * 255 = 56 Rs/- Sand = 1.35 C.F.T. * 43 = 58 Rs/- Tile = 1 sq.m * 430 Rs/-= 430 Rs/- Labour = 1sq.m . * 75 =75 Rs/- Total = 610Rs/- Builders profit including Service tax , VAT etc. = 732Rs/- per sq.m. 20 % Vetrified tiles are used . In each box contains 4 tiles of Rs. 300
Result of RATE ANALYSIS ( Rs per Unit ) 732Rs/- sq.m
Todays BUZZ Word CONTRACTS & AGREEMENT: Contracts: Type of contracts: 1) Item rate contract. 2) Built up area basis contract. 3) Lump sum contract. 1)Item rate contract: In these type of contract, there may be one or more contractors. But for billing & measurement purposes , the work is split into various items. 2) Built up area basis contract.: These method has proved to be the most easy method . Hence , it is the most popular method. The work is split into various items i.e. R.C.C. ,masonry ,tiling , plumbing etc.This works are entrusted to small but specialized petty contractors on labour rates only. 3)Lump sum contract: Petty works are given on a lump sum basis, which includes 100% completion of a particular activity or work in the decided lump sum amount. AGREEMENT: Agreement is a legal document which acts as a legal binding between both the parties. - Agreements acts as a basic document of arbitaration in case of a dispute. - Most agreements have similar conditions for all the work activities , differing mainly in the scope of work , mode of measurements and payment terms. Advantages of an agreement : - Confirms the rates of various items. - Provides legal binding and supports to both the paries in case of dispute. - Contractor gets an idea about the scope of work, other conditions & mode of measurements before commencing the work . - Contractor understands the work procedure & the quality expected . - The agreement helps reach an understanding between both parties before the work begins.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-08

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 08
Date (DD/MM/YYYY) 16.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1)to see the brickwork. 2)to check the plaster.
Details of how you Planned & Executed the allotted work 1)we checked the brickwork with the help of plumb bob. 2)we checked the plaster with the help of rope called as line dori,to know if there are any undulations in the plastered surface. the site incharge helped us a lot.
Details of the Construction Procedure / Activity / Technology learned today how to check the brickwork with the help of plumb bob.
Details of the Construction Materials learned today 1)use of plumb bob. 2)use of line dori.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of soil which is excavated for foundation purpose is used to fill-up the murums.
Details of the Construction / Engineering Drawings observed today beam drawings.
Details of the Bye Laws referred today parking:- 1)four vehicle parking-2.5*5.5 m 2)two wheeler parking-1.5*3 m
Details of any Managerial Skill learned today After completion of the formwork the slab should be checked,wether there is any undulation in the slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILLING ; rate per sq.m CEMENT = 3.0 kg = 20.00 Rs. SAND = 0.3 cu.m. = 150.00 Rs. TILE (size 0.45m.* 0.3m.) = 10 numbers = 620.00 Rs. Labour = 125.00 Rs. TOTAL = 745.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 745
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-08

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Dsouza Agnel Santan
Exam No. 13524
Working Day No. 08
Date (DD/MM/YYYY) 16.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1)to see the brickwork. 2)to check the plaster.
Details of how you Planned & Executed the allotted work 1)we checked the brickwork with the help of plumb bob. 2)we checked the plaster with the help of rope called as line dori,to know if there are any undulations in the plastered surface. the site incharge helped us a lot.
Details of the Construction Procedure / Activity / Technology learned today how to check the brickwork with the help of plumb bob.
Details of the Construction Materials learned today 1)use of plumb bob. 2)use of line dori.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of soil which is excavated for foundation purpose is used to fill-up the murums.
Details of the Construction / Engineering Drawings observed today beam drawings.
Details of the Bye Laws referred today parking:- 1)four vehicle parking-2.5*5.5 m 2)two wheeler parking-1.5*3 m
Details of any Managerial Skill learned today After completion of the formwork the slab should be checked,wether there is any undulation in the slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILLING ; rate per sq.m CEMENT = 3.0 kg = 20.00 Rs. SAND = 0.3 cu.m. = 150.00 Rs. TILE (size 0.45m.* 0.3m.) = 10 numbers = 620.00 Rs. Labour = 125.00 Rs. TOTAL = 745.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 745
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-08

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 08
Date (DD/MM/YYYY) 16.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1)to see the brickwork. 2)to check the plaster.
Details of how you Planned & Executed the allotted work 1)we checked the brickwork with the help of plumb bob. 2)we checked the plaster with the help of rope called as line dori,to know if there are any undulations in the plastered surface. the site incharge helped us a lot.
Details of the Construction Procedure / Activity / Technology learned today how to check the brickwork with the help of plumb bob.
Details of the Construction Materials learned today 1)use of plumb bob. 2)use of line dori.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of soil which is excavated for foundation purpose is used to fill-up the murums.
Details of the Construction / Engineering Drawings observed today beam drawings.
Details of the Bye Laws referred today parking:- 1)four vehicle parking-2.5*5.5 m 2)two wheeler parking-1.5*3 m
Details of any Managerial Skill learned today After completion of the formwork the slab should be checked,wether there is any undulation in the slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILLING ; rate per sq.m CEMENT = 3.0 kg = 20.00 Rs. SAND = 0.3 cu.m. = 150.00 Rs. TILE (size 0.45m.* 0.3m.) = 10 numbers = 620.00 Rs. Labour = 125.00 Rs. TOTAL = 745.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 745
Todays BUZZ Word 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the pile foundation in cloud 9 project. -To see the casting of slab in cloud 9 project. -To meet plumber contractor and take all details about plumbing.
Details of how you Planned & Executed the allotted work 1) First we visited cloud 9 project and see the pressure pile working and took all details. 2) Then we see the casting of 3rd floor slab of cloud 9project. 3)Then we came back to our project and met Mr.Dhavale plumber contractor. 4)He gave us an lecture on types of plumbing and working of plumbing.
Details of the Construction Procedure / Activity / Technology learned today Pressure pile : 1)First according to plan location of piles are decided. 2)Then machinery are setup and pile excavation is started. 3) Around the pile casing is placed and pile is formed. Slab: 1) First formwork is prepared for slab. 2)Then reinforcement arrangement is done according to R.C.C. Design. 3) Then concrete is prepared . 4)Lift is constructed for transportation of concrete from ground level to required floor level. 5) Then concrete is placed and compacted with the help of surface vibrator compaction is done .
Details of the Construction Materials learned today Crushed sand , surface vibrator, concrete M-20, superplasticers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain water harvesting is done for row bunglows only. 1.5\" diameter pipe is used for downtake of water. From these the rainwater recharges the ground water table.
Details of the Construction / Engineering Drawings observed today Detail layout of pressure pile foundation.
Details of the Bye Laws referred today External wall 230mm is provided. Internal wall 100mm is provided.
Details of any Managerial Skill learned today We met Mr.Raju Dhavale and he gave us detail information about plumbing fixtures and material and working. He gave us information as a teacher.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILES : Cement = 0.22 * 255 = 56 Rs/- Sand = 1.35 C.F.T. * 43 = 58 Rs/- Tile = 1 sq.m * 430 Rs/-= 430 Rs/- Labour = 1sq.m . * 75 =75 Rs/- Total = 610Rs/- Builders profit including Service tax , VAT etc. = 732Rs/- per sq.m. 20 % Vetrified tiles are used . In each box contains 4 tiles of Rs. 300
Result of RATE ANALYSIS ( Rs per Unit ) 732Rs/- sq.m
Todays BUZZ Word CONTRACTS & AGREEMENT: Contracts: Type of contracts: 1) Item rate contract. 2) Built up area basis contract. 3) Lump sum contract. 1)Item rate contract: In these type of contract, there may be one or more contractors. But for billing & measurement purposes , the work is split into various items. 2) Built up area basis contract.: These method has proved to be the most easy method . Hence , it is the most popular method. The work is split into various items i.e. R.C.C. ,masonry ,tiling , plumbing etc.This works are entrusted to small but specialized petty contractors on labour rates only. 3)Lump sum contract: Petty works are given on a lump sum basis, which includes 100% completion of a particular activity or work in the decided lump sum amount. AGREEMENT: Agreement is a legal document which acts as a legal binding between both the parties. - Agreements acts as a basic document of arbitaration in case of a dispute. - Most agreements have similar conditions for all the work activities , differing mainly in the scope of work , mode of measurements and payment terms. Advantages of an agreement : - Confirms the rates of various items. - Provides legal binding and supports to both the paries in case of dispute. - Contractor gets an idea about the scope of work, other conditions & mode of measurements before commencing the work . - Contractor understands the work procedure & the quality expected . - The agreement helps reach an understanding between both parties before the work begins.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the pile foundation in cloud 9 project. -To see the casting of slab in cloud 9 project. -To meet plumber contractor and take all details about plumbing.
Details of how you Planned & Executed the allotted work 1) First we visited cloud 9 project and see the pressure pile working and took all details. 2) Then we see the casting of 3rd floor slab of cloud 9project. 3)Then we came back to our project and met Mr.Dhavale plumber contractor. 4)He gave us an lecture on types of plumbing and working of plumbing.
Details of the Construction Procedure / Activity / Technology learned today Pressure pile : 1)First according to plan location of piles are decided. 2)Then machinery are setup and pile excavation is started. 3) Around the pile casing is placed and pile is formed. Slab: 1) First formwork is prepared for slab. 2)Then reinforcement arrangement is done according to R.C.C. Design. 3) Then concrete is prepared . 4)Lift is constructed for transportation of concrete from ground level to required floor level. 5) Then concrete is placed and compacted with the help of surface vibrator compaction is done .
Details of the Construction Materials learned today Crushed sand , surface vibrator, concrete M-20, superplasticers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain water harvesting is done for row bunglows only. 1.5\" diameter pipe is used for downtake of water. From these the rainwater recharges the ground water table.
Details of the Construction / Engineering Drawings observed today Detail layout of pressure pile foundation.
Details of the Bye Laws referred today External wall 230mm is provided. Internal wall 100mm is provided.
Details of any Managerial Skill learned today We met Mr.Raju Dhavale and he gave us detail information about plumbing fixtures and material and working. He gave us information as a teacher.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILES : Cement = 0.22 * 255 = 56 Rs/- Sand = 1.35 C.F.T. * 43 = 58 Rs/- Tile = 1 sq.m * 430 Rs/-= 430 Rs/- Labour = 1sq.m . * 75 =75 Rs/- Total = 610Rs/- Builders profit including Service tax , VAT etc. = 732Rs/- per sq.m. 20 % Vetrified tiles are used . In each box contains 4 tiles of Rs. 300
Result of RATE ANALYSIS ( Rs per Unit ) 732Rs/- sq.m
Todays BUZZ Word CONTRACTS & AGREEMENT: Contracts: Type of contracts: 1) Item rate contract. 2) Built up area basis contract. 3) Lump sum contract. 1)Item rate contract: In these type of contract, there may be one or more contractors. But for billing & measurement purposes , the work is split into various items. 2) Built up area basis contract.: These method has proved to be the most easy method . Hence , it is the most popular method. The work is split into various items i.e. R.C.C. ,masonry ,tiling , plumbing etc.This works are entrusted to small but specialized petty contractors on labour rates only. 3)Lump sum contract: Petty works are given on a lump sum basis, which includes 100% completion of a particular activity or work in the decided lump sum amount. AGREEMENT: Agreement is a legal document which acts as a legal binding between both the parties. - Agreements acts as a basic document of arbitaration in case of a dispute. - Most agreements have similar conditions for all the work activities , differing mainly in the scope of work , mode of measurements and payment terms. Advantages of an agreement : - Confirms the rates of various items. - Provides legal binding and supports to both the paries in case of dispute. - Contractor gets an idea about the scope of work, other conditions & mode of measurements before commencing the work . - Contractor understands the work procedure & the quality expected . - The agreement helps reach an understanding between both parties before the work begins.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the pile foundation in cloud 9 project. -To see the casting of slab in cloud 9 project. -To meet plumber contractor and take all details about plumbing.
Details of how you Planned & Executed the allotted work 1) First we visited cloud 9 project and see the pressure pile working and took all details. 2) Then we see the casting of 3rd floor slab of cloud 9project. 3)Then we came back to our project and met Mr.Dhavale plumber contractor. 4)He gave us an lecture on types of plumbing and working of plumbing.
Details of the Construction Procedure / Activity / Technology learned today Pressure pile : 1)First according to plan location of piles are decided. 2)Then machinery are setup and pile excavation is started. 3) Around the pile casing is placed and pile is formed. Slab: 1) First formwork is prepared for slab. 2)Then reinforcement arrangement is done according to R.C.C. Design. 3) Then concrete is prepared . 4)Lift is constructed for transportation of concrete from ground level to required floor level. 5) Then concrete is placed and compacted with the help of surface vibrator compaction is done .
Details of the Construction Materials learned today Crushed sand , surface vibrator, concrete M-20, superplasticers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain water harvesting is done for row bunglows only. 1.5\" diameter pipe is used for downtake of water. From these the rainwater recharges the ground water table.
Details of the Construction / Engineering Drawings observed today Detail layout of pressure pile foundation.
Details of the Bye Laws referred today External wall 230mm is provided. Internal wall 100mm is provided.
Details of any Managerial Skill learned today We met Mr.Raju Dhavale and he gave us detail information about plumbing fixtures and material and working. He gave us information as a teacher.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILES : Cement = 0.22 * 255 = 56 Rs/- Sand = 1.35 C.F.T. * 43 = 58 Rs/- Tile = 1 sq.m * 430 Rs/-= 430 Rs/- Labour = 1sq.m . * 75 =75 Rs/- Total = 610Rs/- Builders profit including Service tax , VAT etc. = 732Rs/- per sq.m. 20 % Vetrified tiles are used . In each box contains 4 tiles of Rs. 300
Result of RATE ANALYSIS ( Rs per Unit ) 732Rs/- sq.m
Todays BUZZ Word CONTRACTS & AGREEMENT: Contracts: Type of contracts: 1) Item rate contract. 2) Built up area basis contract. 3) Lump sum contract. 1)Item rate contract: In these type of contract, there may be one or more contractors. But for billing & measurement purposes , the work is split into various items. 2) Built up area basis contract.: These method has proved to be the most easy method . Hence , it is the most popular method. The work is split into various items i.e. R.C.C. ,masonry ,tiling , plumbing etc.This works are entrusted to small but specialized petty contractors on labour rates only. 3)Lump sum contract: Petty works are given on a lump sum basis, which includes 100% completion of a particular activity or work in the decided lump sum amount. AGREEMENT: Agreement is a legal document which acts as a legal binding between both the parties. - Agreements acts as a basic document of arbitaration in case of a dispute. - Most agreements have similar conditions for all the work activities , differing mainly in the scope of work , mode of measurements and payment terms. Advantages of an agreement : - Confirms the rates of various items. - Provides legal binding and supports to both the paries in case of dispute. - Contractor gets an idea about the scope of work, other conditions & mode of measurements before commencing the work . - Contractor understands the work procedure & the quality expected . - The agreement helps reach an understanding between both parties before the work begins.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: mayur.sonawane61@gmail.com
Subject: 13570-08

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , Samrat nagar , kolhapur
Students Name (Surname_First Name_Middle Name) SONAWANE MAYUR MADHUKAR
Exam No. 13570
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing work needs a skilled supervision which include following points:- a)First changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. b)Then mark the alignment,every junction of pipe on inner & outer side of wall. c)Drilled the hole in wall as per diameter of pipe required. d)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. e)Every junction of pipe should be well jointed & free from leakages . f)Good binding material should be used for connecting two pipes. g)Elbows,T,collers should be used at correct place. h)The no. of joints should be avoided. i)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. .
Details of the Construction Materials learned today Various types of pipe used for plumbing work:- PVC,SWR,ELBOWS,T,COLLERS,HALFTURN,VALVES,NAHANITRAPS,P TRAP,CONCEALED VALVE. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper design ,management & accuracy in work avoid the wastage of water through leakages & uneconomical use of water,which is the very important need of human life. .
Details of the Construction / Engineering Drawings observed today Detail plumbing drawing for appartment or for any residential building. in which requirement of various diameters ,no.of pipes. .
Details of the Bye Laws referred today Minimum & maximum water requirement for public building. Diameters of pipe for various purposes. Domestic water demand in liter per day per person. .
Details of any Managerial Skill learned today How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/-sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the pile foundation in cloud 9 project. -To see the casting of slab in cloud 9 project. -To meet plumber contractor and take all details about plumbing.
Details of how you Planned & Executed the allotted work 1) First we visited cloud 9 project and see the pressure pile working and took all details. 2) Then we see the casting of 3rd floor slab of cloud 9project. 3)Then we came back to our project and met Mr.Dhavale plumber contractor. 4)He gave us an lecture on types of plumbing and working of plumbing.
Details of the Construction Procedure / Activity / Technology learned today Pressure pile : 1)First according to plan location of piles are decided. 2)Then machinery are setup and pile excavation is started. 3) Around the pile casing is placed and pile is formed. Slab: 1) First formwork is prepared for slab. 2)Then reinforcement arrangement is done according to R.C.C. Design. 3) Then concrete is prepared . 4)Lift is constructed for transportation of concrete from ground level to required floor level. 5) Then concrete is placed and compacted with the help of surface vibrator compaction is done .
Details of the Construction Materials learned today Crushed sand , surface vibrator, concrete M-20, superplasticers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain water harvesting is done for row bunglows only. 1.5\" diameter pipe is used for downtake of water. From these the rainwater recharges the ground water table.
Details of the Construction / Engineering Drawings observed today Detail layout of pressure pile foundation.
Details of the Bye Laws referred today External wall 230mm is provided. Internal wall 100mm is provided.
Details of any Managerial Skill learned today We met Mr.Raju Dhavale and he gave us detail information about plumbing fixtures and material and working. He gave us information as a teacher.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILES : Cement = 0.22 * 255 = 56 Rs/- Sand = 1.35 C.F.T. * 43 = 58 Rs/- Tile = 1 sq.m * 430 Rs/-= 430 Rs/- Labour = 1sq.m . * 75 =75 Rs/- Total = 610Rs/- Builders profit including Service tax , VAT etc. = 732Rs/- per sq.m. 20 % Vetrified tiles are used . In each box contains 4 tiles of Rs. 300
Result of RATE ANALYSIS ( Rs per Unit ) 732Rs/- sq.m
Todays BUZZ Word CONTRACTS & AGREEMENT: Contracts: Type of contracts: 1) Item rate contract. 2) Built up area basis contract. 3) Lump sum contract. 1)Item rate contract: In these type of contract, there may be one or more contractors. But for billing & measurement purposes , the work is split into various items. 2) Built up area basis contract.: These method has proved to be the most easy method . Hence , it is the most popular method. The work is split into various items i.e. R.C.C. ,masonry ,tiling , plumbing etc.This works are entrusted to small but specialized petty contractors on labour rates only. 3)Lump sum contract: Petty works are given on a lump sum basis, which includes 100% completion of a particular activity or work in the decided lump sum amount. AGREEMENT: Agreement is a legal document which acts as a legal binding between both the parties. - Agreements acts as a basic document of arbitaration in case of a dispute. - Most agreements have similar conditions for all the work activities , differing mainly in the scope of work , mode of measurements and payment terms. Advantages of an agreement : - Confirms the rates of various items. - Provides legal binding and supports to both the paries in case of dispute. - Contractor gets an idea about the scope of work, other conditions & mode of measurements before commencing the work . - Contractor understands the work procedure & the quality expected . - The agreement helps reach an understanding between both parties before the work begins.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the pile foundation in cloud 9 project. -To see the casting of slab in cloud 9 project. -To meet plumber contractor and take all details about plumbing.
Details of how you Planned & Executed the allotted work 1) First we visited cloud 9 project and see the pressure pile working and took all details. 2) Then we see the casting of 3rd floor slab of cloud 9project. 3)Then we came back to our project and met Mr.Dhavale plumber contractor. 4)He gave us an lecture on types of plumbing and working of plumbing.
Details of the Construction Procedure / Activity / Technology learned today Pressure pile : 1)First according to plan location of piles are decided. 2)Then machinery are setup and pile excavation is started. 3) Around the pile casing is placed and pile is formed. Slab: 1) First formwork is prepared for slab. 2)Then reinforcement arrangement is done according to R.C.C. Design. 3) Then concrete is prepared . 4)Lift is constructed for transportation of concrete from ground level to required floor level. 5) Then concrete is placed and compacted with the help of surface vibrator compaction is done .
Details of the Construction Materials learned today Crushed sand , surface vibrator, concrete M-20, superplasticers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain water harvesting is done for row bunglows only. 1.5\" diameter pipe is used for downtake of water. From these the rainwater recharges the ground water table.
Details of the Construction / Engineering Drawings observed today Detail layout of pressure pile foundation.
Details of the Bye Laws referred today External wall 230mm is provided. Internal wall 100mm is provided.
Details of any Managerial Skill learned today We met Mr.Raju Dhavale and he gave us detail information about plumbing fixtures and material and working. He gave us information as a teacher.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILES : Cement = 0.22 * 255 = 56 Rs/- Sand = 1.35 C.F.T. * 43 = 58 Rs/- Tile = 1 sq.m * 430 Rs/-= 430 Rs/- Labour = 1sq.m . * 75 =75 Rs/- Total = 610Rs/- Builders profit including Service tax , VAT etc. = 732Rs/- per sq.m. 20 % Vetrified tiles are used . In each box contains 4 tiles of Rs. 300
Result of RATE ANALYSIS ( Rs per Unit ) 732Rs/- sq.m
Todays BUZZ Word CONTRACTS & AGREEMENT: Contracts: Type of contracts: 1) Item rate contract. 2) Built up area basis contract. 3) Lump sum contract. 1)Item rate contract: In these type of contract, there may be one or more contractors. But for billing & measurement purposes , the work is split into various items. 2) Built up area basis contract.: These method has proved to be the most easy method . Hence , it is the most popular method. The work is split into various items i.e. R.C.C. ,masonry ,tiling , plumbing etc.This works are entrusted to small but specialized petty contractors on labour rates only. 3)Lump sum contract: Petty works are given on a lump sum basis, which includes 100% completion of a particular activity or work in the decided lump sum amount. AGREEMENT: Agreement is a legal document which acts as a legal binding between both the parties. - Agreements acts as a basic document of arbitaration in case of a dispute. - Most agreements have similar conditions for all the work activities , differing mainly in the scope of work , mode of measurements and payment terms. Advantages of an agreement : - Confirms the rates of various items. - Provides legal binding and supports to both the paries in case of dispute. - Contractor gets an idea about the scope of work, other conditions & mode of measurements before commencing the work . - Contractor understands the work procedure & the quality expected . - The agreement helps reach an understanding between both parties before the work begins.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the pile foundation in cloud 9 project. -To see the casting of slab in cloud 9 project. -To meet plumber contractor and take all details about plumbing.
Details of how you Planned & Executed the allotted work 1) First we visited cloud 9 project and see the pressure pile working and took all details. 2) Then we see the casting of 3rd floor slab of cloud 9project. 3)Then we came back to our project and met Mr.Dhavale plumber contractor. 4)He gave us an lecture on types of plumbing and working of plumbing.
Details of the Construction Procedure / Activity / Technology learned today Pressure pile : 1)First according to plan location of piles are decided. 2)Then machinery are setup and pile excavation is started. 3) Around the pile casing is placed and pile is formed. Slab: 1) First formwork is prepared for slab. 2)Then reinforcement arrangement is done according to R.C.C. Design. 3) Then concrete is prepared . 4)Lift is constructed for transportation of concrete from ground level to required floor level. 5) Then concrete is placed and compacted with the help of surface vibrator compaction is done .
Details of the Construction Materials learned today Crushed sand , surface vibrator, concrete M-20, superplasticers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain water harvesting is done for row bunglows only. 1.5\" diameter pipe is used for downtake of water. From these the rainwater recharges the ground water table.
Details of the Construction / Engineering Drawings observed today Detail layout of pressure pile foundation.
Details of the Bye Laws referred today External wall 230mm is provided. Internal wall 100mm is provided.
Details of any Managerial Skill learned today We met Mr.Raju Dhavale and he gave us detail information about plumbing fixtures and material and working. He gave us information as a teacher.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILES : Cement = 0.22 * 255 = 56 Rs/- Sand = 1.35 C.F.T. * 43 = 58 Rs/- Tile = 1 sq.m * 430 Rs/-= 430 Rs/- Labour = 1sq.m . * 75 =75 Rs/- Total = 610Rs/- Builders profit including Service tax , VAT etc. = 732Rs/- per sq.m. 20 % Vetrified tiles are used . In each box contains 4 tiles of Rs. 300
Result of RATE ANALYSIS ( Rs per Unit ) 732Rs/- sq.m.
Todays BUZZ Word CONTRACTS & AGREEMENT: Contracts: Type of contracts: 1) Item rate contract. 2) Built up area basis contract. 3) Lump sum contract. 1)Item rate contract: In these type of contract, there may be one or more contractors. But for billing & measurement purposes , the work is split into various items. 2) Built up area basis contract.: These method has proved to be the most easy method . Hence , it is the most popular method. The work is split into various items i.e. R.C.C. ,masonry ,tiling , plumbing etc.This works are entrusted to small but specialized petty contractors on labour rates only. 3)Lump sum contract: Petty works are given on a lump sum basis, which includes 100% completion of a particular activity or work in the decided lump sum amount. AGREEMENT: Agreement is a legal document which acts as a legal binding between both the parties. - Agreements acts as a basic document of arbitaration in case of a dispute. - Most agreements have similar conditions for all the work activities , differing mainly in the scope of work , mode of measurements and payment terms. Advantages of an agreement : - Confirms the rates of various items. - Provides legal binding and supports to both the paries in case of dispute. - Contractor gets an idea about the scope of work, other conditions & mode of measurements before commencing the work . - Contractor understands the work procedure & the quality expected . - The agreement helps reach an understanding between both parties before the work begins.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see the pile foundation in cloud 9 project. -To see the casting of slab in cloud 9 project. -To meet plumber contractor and take all details about plumbing.
Details of how you Planned & Executed the allotted work 1) First we visited cloud 9 project and see the pressure pile working and took all details. 2) Then we see the casting of 3rd floor slab of cloud 9project. 3)Then we came back to our project and met Mr.Dhavale plumber contractor. 4)He gave us an lecture on types of plumbing and working of plumbing.
Details of the Construction Procedure / Activity / Technology learned today Pressure pile : 1)First according to plan location of piles are decided. 2)Then machinery are setup and pile excavation is started. 3) Around the pile casing is placed and pile is formed. Slab: 1) First formwork is prepared for slab. 2)Then reinforcement arrangement is done according to R.C.C. Design. 3) Then concrete is prepared . 4)Lift is constructed for transportation of concrete from ground level to required floor level. 5) Then concrete is placed and compacted with the help of surface vibrator compaction is done .
Details of the Construction Materials learned today Crushed sand , surface vibrator, concrete M-20, superplasticers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain water harvesting is done for row bunglows only. 1.5\" diameter pipe is used for downtake of water. From these the rainwater recharges the ground water table.
Details of the Construction / Engineering Drawings observed today Detail layout of pressure pile foundation.
Details of the Bye Laws referred today External wall 230mm is provided. Internal wall 100mm is provided.
Details of any Managerial Skill learned today We met Mr.Raju Dhavale and he gave us detail information about plumbing fixtures and material and working. He gave us information as a teacher.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILES : Cement = 0.22 * 255 = 56 Rs/- Sand = 1.35 C.F.T. * 43 = 58 Rs/- Tile = 1 sq.m * 430 Rs/-= 430 Rs/- Labour = 1sq.m . * 75 =75 Rs/- Total = 610Rs/- Builders profit including Service tax , VAT etc. = 732Rs/- per sq.m. 20 % Vetrified tiles are used . In each box contains 4 tiles of Rs. 300
Result of RATE ANALYSIS ( Rs per Unit ) 732Rs/- sq.m
Todays BUZZ Word CONTRACTS & AGREEMENT: Contracts: Type of contracts: 1) Item rate contract. 2) Built up area basis contract. 3) Lump sum contract. 1)Item rate contract: In these type of contract, there may be one or more contractors. But for billing & measurement purposes , the work is split into various items. 2) Built up area basis contract.: These method has proved to be the most easy method . Hence , it is the most popular method. The work is split into various items i.e. R.C.C. ,masonry ,tiling , plumbing etc.This works are entrusted to small but specialized petty contractors on labour rates only. 3)Lump sum contract: Petty works are given on a lump sum basis, which includes 100% completion of a particular activity or work in the decided lump sum amount. AGREEMENT: Agreement is a legal document which acts as a legal binding between both the parties. - Agreements acts as a basic document of arbitaration in case of a dispute. - Most agreements have similar conditions for all the work activities , differing mainly in the scope of work , mode of measurements and payment terms. Advantages of an agreement : - Confirms the rates of various items. - Provides legal binding and supports to both the paries in case of dispute. - Contractor gets an idea about the scope of work, other conditions & mode of measurements before commencing the work . - Contractor understands the work procedure & the quality expected . - The agreement helps reach an understanding between both parties before the work begins.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-08

Company Name Shendre Associates
Project Name & Site Address mallhar heights near n.c.c bhavan
Students Name (Surname_First Name_Middle Name) fulari sujata shankar
Exam No. 13559
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 09.50am
Site Leaving Time (HH:MM am/pm) 5.00pm
Details of the Work Allotted to you today by the Site In-Charge -today site incharge give work of extra work of lintel and loft as per owner requirment for rate anaylsis of these loft and lintel. .
Details of how you Planned & Executed the allotted work -firstly we measure the all extra work done in all flat. -then measure the sizes of loft& lintel.and determine the quantity of cement,sand and steel. -as per procedure we done the work. .
Details of the Construction Procedure / Activity / Technology learned today -on site we learn the how to done ext. plastering. -firstly they made the mortar with (1:3) proportion . -and with help of trowel they done plastering with 20mm thickness. .
Details of the Construction Materials learned today Various types of pipe used for plumbing work:- PVC,SWR,ELBOWS,T,COLLERS,HALFTURN,VALVES,NAHANITRAPS,P TRAP,CONCEALED VALVE.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today mortar fallen during plastering work if collected on plastic sheet then reused within 30 minitus , it will save the material & there by saving natural materiel. .
Details of the Construction / Engineering Drawings observed today Detail plumbing drawing for appartment or for any residential building. in which requirement of various diameters ,no.of pipes. .
Details of the Bye Laws referred today Parking height2.4m provided according to bylaws. .
Details of any Managerial Skill learned today To check the material supplied by supplyer to clarrify the mistakes if any. So as to keep supply contineous and efficient.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 . Result of RATE ANALYSIS ( Rs per Unit ): 1000/- m2
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.vivek randive mo. no 8805494033
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-08

Company Name S. N. Builders
Project Name & Site Address animesh nagar,
Students Name (Surname_First Name_Middle Name) patil sangram madhukar
Exam No. 13540
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge observation of tiles fitting
Details of how you Planned & Executed the allotted work 1.we fix level for floor and stair 2.calculate size of tiles cuttimg for each rise 3.size of material fill under tiles according to level required
Details of the Construction Procedure / Activity / Technology learned today we learn 1.cutting of tiles to required size 2.raw materials is used to fill under tiles 3.dry cement is mixed with that material for binding 4.the cement paste is spread on fill and tiles are fixed 5.white cement is used to bind the tiles
Details of the Construction Materials learned today 1.types of tiles -marbonate -kadappa -marble 2.door fitting materials -handle ,lock ,tower bolt
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today plan of building internal design of building
Details of the Bye Laws referred today septic tank shall have minimum internal width 75CM and minimum depth 1M below the water level
Details of any Managerial Skill learned today good communication with customer and us 2.good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) marbonate tiles 1.marbonate tiles=36Rs 2.sand -1.7x17RS=29Rs 3.cement-1x5RS=5Rs 4.transport=1Rs 5labour =9.0Rs 6.5%wastage=4Rs total=84Rs per sqft Total=876Rs per sqmt
Result of RATE ANALYSIS ( Rs per Unit ) 876Rs
Todays BUZZ Word developer 1.size of plot information 2.according to plan decide the bed room ,hall, kitchen etc 3.internal component-types of tiles,doors,internal fitting etc 4.decide amount -advance -pay in five to six installment 5.aggreement of sale 6.document of plot 7.date of declaration and completion certificate 8.permiton later 9.aggreement copy
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no.-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-08

Company Name S. N. Builders
Project Name & Site Address animesh nagar,
Students Name (Surname_First Name_Middle Name) patil sachin dhanaji
Exam No. 13539
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 8:50
Site Leaving Time (HH:MM am/pm) 4:30
Details of the Work Allotted to you today by the Site In-Charge observation of tiles fitting
Details of how you Planned & Executed the allotted work 1.we fix level for floor and stair 2.calculate size of tiles cuttimg for each rise 3.size of material fill under tiles according to level required
Details of the Construction Procedure / Activity / Technology learned today we learn 1.cutting of tiles to required size 2.raw materials is used to fill under tiles 3.dry cement is mixed with that material for binding 4.the cement paste is spread on fill and tiles are fixed 5.white cement is used to bind the tiles
Details of the Construction Materials learned today 1.types of tiles -marbonate -kadappa -marble 2.door fitting materials -handle ,lock ,tower bolt
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today plan of building internal design of building
Details of the Bye Laws referred today septic tank shall have minimum internal width 75CM and minimum depth 1M below the water level
Details of any Managerial Skill learned today good communication with customer and us 2.good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) marbonate tiles 1.marbonate tiles=36Rs 2.sand -1.7x17RS=29Rs 3.cement-1x5RS=5Rs 4.transport=1Rs 5labour =9.0Rs 6.5%wastage=4Rs total=84Rs per sqft Total=876Rs per sqmt
Result of RATE ANALYSIS ( Rs per Unit ) 876Rs
Todays BUZZ Word developer 1.size of plot information 2.according to plan decide the bed room ,hall, kitchen etc 3.internal component-types of tiles,doors,internal fitting etc 4.decide amount -advance -pay in five to six installment 5.aggreement of sale 6.document of plot 7.date of declaration and completion certificate 8.permiton later 9.aggreement copy
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no.-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: nikitashinde15@gmail.com
Subject: 13547-08

Company Name S. N. Builders
Project Name & Site Address animesh nagar,
Students Name (Surname_First Name_Middle Name) shinde nikita eknath
Exam No. 13547
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge observation of tiles fitting
Details of how you Planned & Executed the allotted work 1.we fix level for floor and stair 2.calculate size of tiles cuttimg for each rise 3.size of material fill under tiles according to level required
Details of the Construction Procedure / Activity / Technology learned today we learn 1.cutting of tiles to required size 2.raw materials is used to fill under tiles 3.dry cement is mixed with that material for binding 4.the cement paste is spread on fill and tiles are fixed 5.white cement is used to bind the tiles
Details of the Construction Materials learned today 1.types of tiles -marbonate -kadappa -marble 2.door fitting materials -handle ,lock ,tower bolt
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today plan of building internal design of building
Details of the Bye Laws referred today septic tank shall have minimum internal width 75CM and minimum depth 1M below the water level
Details of any Managerial Skill learned today good communication with customer and us 2.good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) marbonate tiles 1.marbonate tiles=36Rs 2.sand -1.7x17RS=29Rs 3.cement-1x5RS=5Rs 4.transport=1Rs 5labour =9.0Rs 6.5%wastage=4Rs total=84Rs per sqft Total=876Rs per sqmt
Result of RATE ANALYSIS ( Rs per Unit ) 876Rs
Todays BUZZ Word developer 1.size of plot information 2.according to plan decide the bed room ,hall, kitchen etc 3.internal component-types of tiles,doors,internal fitting etc 4.decide amount -advance -pay in five to six installment 5.aggreement of sale 6.document of plot 7.date of declaration and completion certificate 8.permiton later 9.aggreement copy
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no.-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: rajendrapawar54@gmail.com
Subject: 13542-08

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) pawar rajendra eknath
Exam No. 13542
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9:ooam
Site Leaving Time (HH:MM am/pm) 4:30Pm
Details of the Work Allotted to you today by the Site In-Charge observation of tiles fitting
Details of how you Planned & Executed the allotted work 1.we fix level for floor and stair 2.calculate size of tiles cuttimg for each rise 3.size of material fill under tiles according to level required
Details of the Construction Procedure / Activity / Technology learned today we learn 1.cutting of tiles to required size 2.raw materials is used to fill under tiles 3.dry cement is mixed with that material for binding 4.the cement paste is spread on fill and tiles are fixed 5.white cement is used to bind the tiles
Details of the Construction Materials learned today 1.types of tiles -marbonate -kadappa -marble 2.door fitting materials -handle ,lock ,tower bolt
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today plan of building internal design of building
Details of the Bye Laws referred today septic tank shall have minimum internal width 75CM and minimum depth 1M below the water level
Details of any Managerial Skill learned today good communication with customer and us 2.good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) marbonate tiles 1.marbonate tiles=36Rs 2.sand -1.7x17RS=29Rs 3.cement-1x5RS=5Rs 4.transport=1Rs 5labour =9.0Rs 6.5%wastage=4Rs total=84Rs per sqft Total=876Rs per sqmt
Result of RATE ANALYSIS ( Rs per Unit ) 876Rs
Todays BUZZ Word developer 1.size of plot information 2.according to plan decide the bed room ,hall, kitchen etc 3.internal component-types of tiles,doors,internal fitting etc 4.decide amount -advance -pay in five to six installment 5.aggreement of sale 6.document of plot 7.date of declaration and completion certificate 8.permiton later 9.aggreement copy
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no.-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: vishwajit.p09@gmail.com
Subject: 13543-08

Company Name S. N. Builders
Project Name & Site Address animesh nagar,
Students Name (Surname_First Name_Middle Name) paymal vishwajit shamarao
Exam No. 13543
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9:00Am
Site Leaving Time (HH:MM am/pm) 4:30Pm
Details of the Work Allotted to you today by the Site In-Charge observation of tiles fitting
Details of how you Planned & Executed the allotted work 1.we fix level for floor and stair 2.calculate size of tiles cuttimg for each rise 3.size of material fill under tiles according to level required
Details of the Construction Procedure / Activity / Technology learned today we learn 1.cutting of tiles to required size 2.raw materials is used to fill under tiles 3.dry cement is mixed with that material for binding 4.the cement paste is spread on fill and tiles are fixed 5.white cement is used to bind the tiles
Details of the Construction Materials learned today 1.types of tiles -marbonate -kadappa -marble 2.door fitting materials -handle ,lock ,tower bolt
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today plan of building internal design of building
Details of the Bye Laws referred today septic tank shall have minimum internal width 75CM and minimum depth 1M below the water level
Details of any Managerial Skill learned today good communication with customer and us 2.good command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) marbonate tiles 1.marbonate tiles=36Rs 2.sand -1.7x17RS=29Rs 3.cement-1x5RS=5Rs 4.transport=1Rs 5labour =9.0Rs 6.5%wastage=4Rs total=84Rs per sqft Total=876Rs per sqmt
Result of RATE ANALYSIS ( Rs per Unit ) 876Rs
Todays BUZZ Word developer 1.size of plot information 2.according to plan decide the bed room ,hall, kitchen etc 3.internal component-types of tiles,doors,internal fitting etc 4.decide amount -advance -pay in five to six installment 5.aggreement of sale 6.document of plot 7.date of declaration and completion certificate 8.permiton later 9.aggreement copy
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no.-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: shindeamol5255@yahoo.in
Subject: 13546-08

Company Name Deshmukh Developers
Project Name & Site Address Goldenshelter
Students Name (Surname_First Name_Middle Name) Shinde Amol Jagannath
Exam No. 13546
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing work needs a skilled supervision which include following points:- a)First changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. b)Then mark the alignment,every junction of pipe on inner & outer side of wall. c)Drilled the hole in wall as per diameter of pipe required. d)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. e)Every junction of pipe should be well jointed & free from leakages . f)Good binding material should be used for connecting two pipes. g)Elbows,T,collers should be used at correct place. h)The no. of joints should be avoided. i)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. .
Details of the Construction Materials learned today Various types of pipe used for plumbing work:- CPVC,SWR,ELBOWS,T,COLLERS,HALFTURN,VALVES,NAHANITRAPS,P TRAP,CONCEALED VALVE. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper design ,management & accuracy in work avoid the wastage of water through leakages & uneconomical use of water,which is the very important need of human life. .
Details of the Construction / Engineering Drawings observed today Detail plumbing drawing for appartment or for any residential building. in which requirement of various diameters ,no.of pipes. .
Details of the Bye Laws referred today Minimum & maximum water requirement for public building. Diameters of pipe for various purposes. Domestic water demand in liter per day per person. .
Details of any Managerial Skill learned today How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Bhosle. .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: mayur.sonavne61@gmail.com
Subject: 13570-08

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sonavne Mayur Madhukar
Exam No. 13570
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing work needs a skilled supervision which include following points:- a)First changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. b)Then mark the alignment,every junction of pipe on inner & outer side of wall. c)Drilled the hole in wall as per diameter of pipe required. d)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. e)Every junction of pipe should be well jointed & free from leakages . f)Good binding material should be used for connecting two pipes. g)Elbows,T,collers should be used at correct place. h)The no. of joints should be avoided. i)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. .
Details of the Construction Materials learned today Various types of pipe used for plumbing work:- CPVC,SWR,ELBOWS,T,COLLERS,HALFTURN,VALVES,NAHANITRAPS,P TRAP,CONCEALED VALVE. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper design ,management & accuracy in work avoid the wastage of water through leakages & uneconomical use of water,which is the very important need of human life. .
Details of the Construction / Engineering Drawings observed today Detail plumbing drawing for appartment or for any residential building. in which requirement of various diameters ,no.of pipes. .
Details of the Bye Laws referred today Minimum & maximum water requirement for public building. Diameters of pipe for various purposes. Domestic water demand in liter per day per person. .
Details of any Managerial Skill learned today How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudev
Exam No. 10891
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9.00AM
Site Leaving Time (HH:MM am/pm) 4:00PM
Details of the Work Allotted to you today by the Site In-Charge Slab casting ,Pressure pile foundation .
Details of how you Planned & Executed the allotted work We go on side & check all necessary equipments & material & planed arranging. .
Details of the Construction Procedure / Activity / Technology learned today IN PILE - in pile excavation pressure pile is driven in earth pile are in circular in shape which is hammer on earth surface up to hight 25-20 ft by machine (pressure)after two impact core is filled with soil which is taken out & remove soil this procedure till continue until hard strata is obtained. SLAB CASTING-First we see bar bending . according to drawing plan of steel. then we check framework. m20 concrete are used for slab casting. lift are used for lifting concrete.
Details of the Construction Materials learned today Crushed agg.,steel concrete .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater harvesting is done in only bungalow. .
Details of the Construction / Engineering Drawings observed today Steel drawing, pile foundation plan .
Details of the Bye Laws referred today dimension of internal plumbing pipe according to pipe. .
Details of any Managerial Skill learned today How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil. (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-08

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge Slab casting ,Pressure pile foundation .
Details of how you Planned & Executed the allotted work We go on side & check all necessary equipments & material & planed arranging. .
Details of the Construction Procedure / Activity / Technology learned today IN PILE - in pile excavation pressure pile is driven in earth pile are in circular in shape which is hammer on earth surface up to hight 25-20 ft by machine (pressure)after two impact core is filled with soil which is taken out & remove soil this procedure till continue until hard strata is obtained. SLAB CASTING-First we see bar bending . according to drawing plan of steel. then we check framework. m20 concrete are used for slab casting. lift are used for lifting concrete.
Details of the Construction Materials learned today Crushed agg.,steel concrete .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater harvesting is done in only bungalow. .
Details of the Construction / Engineering Drawings observed today Steel drawing, pile foundation plan .
Details of the Bye Laws referred today dimension of internal plumbing pipe according to pipe. .
Details of any Managerial Skill learned today How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Pritam Patil. (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-08

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) tirmare pradnya ashok
Exam No. 13572
Working Day No. 08
Date (DD/MM/YYYY) 16.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Todays work is to observe and check the slab centering work. Slab is to be casted on 21 december.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings of slab,beams. Then we check actual centering work with the site incharge and corrected the faults.
Details of the Construction Procedure / Activity / Technology learned today Estabilishment of slab formwork ; 1. First beam moulds are prepared and placed in position. 2. Then slab bottom is casted as per size and it is rested on steel props. 3. Then side moulds are prepared and casted as per size of slab. 4. Reinforcement is placed in its position as per structural design. 5. Then reinfocement checked by site incharge.
Details of the Construction Materials learned today Plasticizer ; 1. It is admixture used in preparing concrete with high strength and low water- cement ratio. 2. Plsticizers are high range water reducing admixtures. 3. These are generally carboxylic acid and their salts. 4. Commonly used plasticizer is GLENIUM-51.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today REUSE OF EXCAVATED SOIL ; 1. As areal extent of site is large, quantity of soil is excavated for purpose of levelling of surface and foundation work. 2. This excavated soil is used for aggrcultural purposes. 3. This saves excessive soil errosion by farmers to some extent.
Details of the Construction / Engineering Drawings observed today R.C.C. drawings of beams and slab, Detailed plan of 3 bhk row bungllow which gives details of sunk slab, drainage deatails.
Details of the Bye Laws referred today Type of vehicle and minimum parking space for them are as follows. 1. Motor = 2.5m * 5.5m 2. Scooter or motorcycle = 3 sq.m 3. Bicycle = 1.4 sq.m 4. Transport vehicle = 3.75m * 7.5m
Details of any Managerial Skill learned today We learned that working in group that is working by making good co-ordination with all workers and officers makes comlition of work quickly and perfectly.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILLING ; rate per sq.m CEMENT = 3.0 kg = 20.00 Rs. SAND = 0.3 cu.m. = 150.00 Rs. TILE (size 0.6m.* 0.6m.) = 3 numbers = 135.00 Rs. Labour = 125.00 Rs. TOTAL = 450.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 450.00 Rs per sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENTS ; Following information,documents and conditions are given in contracts and aggreements, 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-08

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) katral raju maruti
Exam No. 13562
Working Day No. 08
Date (DD/MM/YYYY) 16.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Todays work is to observe and check the slab centering work. Slab is to be casted on 21 december.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings of slab,beams. Then we check actual centering work with the site incharge and corrected the faults.
Details of the Construction Procedure / Activity / Technology learned today Estabilishment of slab formwork ; 1. First beam moulds are prepared and placed in position. 2. Then slab bottom is casted as per size and it is rested on steel props. 3. Then side moulds are prepared and casted as per size of slab. 4. Reinforcement is placed in its position as per structural design. 5. Then reinfocement checked by site incharge.
Details of the Construction Materials learned today Plasticizer ; 1. It is admixture used in preparing concrete with high strength and low water- cement ratio. 2. Plsticizers are high range water reducing admixtures. 3. These are generally carboxylic acid and their salts. 4. Commonly used plasticizer is GLENIUM-51.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today REUSE OF EXCAVATED SOIL ; 1. As areal extent of site is large, quantity of soil is excavated for purpose of levelling of surface and foundation work. 2. This excavated soil is used for aggrcultural purposes. 3. This saves excessive soil errosion by farmers to some extent.
Details of the Construction / Engineering Drawings observed today R.C.C. drawings of beams and slab, Detailed plan of 3 bhk row bungllow which gives details of sunk slab, drainage deatails.
Details of the Bye Laws referred today Type of vehicle and minimum parking space for them are as follows. 1. Motor = 2.5m * 5.5m 2. Scooter or motorcycle = 3 sq.m 3. Bicycle = 1.4 sq.m 4. Transport vehicle = 3.75m * 7.5m
Details of any Managerial Skill learned today We learned that working in group that is working by making good co-ordination with all workers and officers makes comlition of work quickly and perfectly.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILLING ; rate per sq.m CEMENT = 3.0 kg = 20.00 Rs. SAND = 0.3 cu.m. = 150.00 Rs. TILE (size 0.6m.* 0.6m.) = 3 numbers = 135.00 Rs. Labour = 125.00 Rs. TOTAL = 450.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 450.00 Rs per sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENTS ; Following information,documents and conditions are given in contracts and aggreements, 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-08

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Jade Madhavrao Anil
Exam No. 13560
Working Day No. 08
Date (DD/MM/YYYY) 16.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Todays work is to observe and check the slab centering work. Slab is to be casted on 21 december.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings of slab,beams. Then we check actual centering work with the site incharge and corrected the faults.
Details of the Construction Procedure / Activity / Technology learned today Estabilishment of slab formwork ; 1. First beam moulds are prepared and placed in position. 2. Then slab bottom is casted as per size and it is rested on steel props. 3. Then side moulds are prepared and casted as per size of slab. 4. Reinforcement is placed in its position as per structural design. 5. Then reinfocement checked by site incharge.
Details of the Construction Materials learned today Plasticizer ; 1. It is admixture used in preparing concrete with high strength and low water- cement ratio. 2. Plsticizers are high range water reducing admixtures. 3. These are generally carboxylic acid and their salts. 4. Commonly used plasticizer is GLENIUM-51.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today REUSE OF EXCAVATED SOIL ; 1. As areal extent of site is large, quantity of soil is excavated for purpose of levelling of surface and foundation work. 2. This excavated soil is used for aggrcultural purposes. 3. This saves excessive soil errosion by farmers to some extent.
Details of the Construction / Engineering Drawings observed today R.C.C. drawings of beams and slab, Detailed plan of 3 bhk row bungllow which gives details of sunk slab, drainage deatails.
Details of the Bye Laws referred today Type of vehicle and minimum parking space for them are as follows. 1. Motor = 2.5m * 5.5m 2. Scooter or motorcycle = 3 sq.m 3. Bicycle = 1.4 sq.m 4. Transport vehicle = 3.75m * 7.5m
Details of any Managerial Skill learned today We learned that working in group that is working by making good co-ordination with all workers and officers makes comlition of work quickly and perfectly.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILLING ; rate per sq.m CEMENT = 3.0 kg = 20.00 Rs. SAND = 0.3 cu.m. = 150.00 Rs. TILE (size 0.6m.* 0.6m.) = 3 numbers = 135.00 Rs. Labour = 125.00 Rs. TOTAL = 450.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 450.00 Rs per sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENTS ; Following information,documents and conditions are given in contracts and aggreements, 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13562-08

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Jadhav Sardar Swaroop J.
Exam No. 13561
Working Day No. 08
Date (DD/MM/YYYY) 16.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Todays work is to observe and check the slab centering work. Slab is to be casted on 21 december.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings of slab,beams. Then we check actual centering work with the site incharge and corrected the faults.
Details of the Construction Procedure / Activity / Technology learned today Estabilishment of slab formwork ; 1. First beam moulds are prepared and placed in position. 2. Then slab bottom is casted as per size and it is rested on steel props. 3. Then side moulds are prepared and casted as per size of slab. 4. Reinforcement is placed in its position as per structural design. 5. Then reinfocement checked by site incharge.
Details of the Construction Materials learned today Plasticizer ; 1. It is admixture used in preparing concrete with high strength and low water- cement ratio. 2. Plsticizers are high range water reducing admixtures. 3. These are generally carboxylic acid and their salts. 4. Commonly used plasticizer is GLENIUM-51.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today REUSE OF EXCAVATED SOIL ; 1. As areal extent of site is large, quantity of soil is excavated for purpose of levelling of surface and foundation work. 2. This excavated soil is used for aggrcultural purposes. 3. This saves excessive soil errosion by farmers to some extent.
Details of the Construction / Engineering Drawings observed today R.C.C. drawings of beams and slab, Detailed plan of 3 bhk row bungllow which gives details of sunk slab, drainage deatails.
Details of the Bye Laws referred today Type of vehicle and minimum parking space for them are as follows. 1. Motor = 2.5m * 5.5m 2. Scooter or motorcycle = 3 sq.m 3. Bicycle = 1.4 sq.m 4. Transport vehicle = 3.75m * 7.5m
Details of any Managerial Skill learned today We learned that working in group that is working by making good co-ordination with all workers and officers makes comlition of work quickly and perfectly.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILLING ; rate per sq.m CEMENT = 3.0 kg = 20.00 Rs. SAND = 0.3 cu.m. = 150.00 Rs. TILE (size 0.6m.* 0.6m.) = 3 numbers = 135.00 Rs. Labour = 125.00 Rs. TOTAL = 450.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 450.00 Rs per sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENTS ; Following information,documents and conditions are given in contracts and aggreements, 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558-08

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Chavan Shivprasad Prakash
Exam No. 13558
Working Day No. 08
Date (DD/MM/YYYY) 16.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Todays work is to observe and check the slab centering work. Slab is to be casted on 21 december.
Details of how you Planned & Executed the allotted work First we had seen R.C.C. drawings of slab,beams. Then we check actual centering work with the site incharge and corrected the faults.
Details of the Construction Procedure / Activity / Technology learned today Estabilishment of slab formwork ; 1. First beam moulds are prepared and placed in position. 2. Then slab bottom is casted as per size and it is rested on steel props. 3. Then side moulds are prepared and casted as per size of slab. 4. Reinforcement is placed in its position as per structural design. 5. Then reinfocement checked by site incharge.
Details of the Construction Materials learned today Plasticizer ; 1. It is admixture used in preparing concrete with high strength and low water- cement ratio. 2. Plsticizers are high range water reducing admixtures. 3. These are generally carboxylic acid and their salts. 4. Commonly used plasticizer is GLENIUM-51.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today REUSE OF EXCAVATED SOIL ; 1. As areal extent of site is large, quantity of soil is excavated for purpose of levelling of surface and foundation work. 2. This excavated soil is used for aggrcultural purposes. 3. This saves excessive soil errosion by farmers to some extent.
Details of the Construction / Engineering Drawings observed today R.C.C. drawings of beams and slab, Detailed plan of 3 bhk row bungllow which gives details of sunk slab, drainage deatails.
Details of the Bye Laws referred today PARKING SPACES ; Type of vehicle and minimum parking space for them are as follows. 1. Motor = 2.5m * 5.5m 2. Scooter or motorcycle = 3 sq.m 3. Bicycle = 1.4 sq.m 4. Transport vehicle = 3.75m * 7.5m
Details of any Managerial Skill learned today We learned that working in group that is working by making good co-ordination with all workers and officers makes comlition of work quickly and perfectly.
RATE ANALYSIS (Detailed Stepwise Calculations required) TILLING ; rate per sq.m CEMENT = 3.0 kg = 20.00 Rs. SAND = 0.3 cu.m. = 150.00 Rs. TILE (size 0.6m.* 0.6m.) = 3 numbers = 135.00 Rs. Labour = 125.00 Rs. TOTAL = 450.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 450.00 Rs per sq.m
Todays BUZZ Word CONTRACTS AND AGREEMENTS ; Following information,documents and conditions are given in contracts and aggreements, 1. Name & address of both owner & contractor. 2. Stamp with apropriate value. 3. Type of work ,address & building name. 4. Detailed specifications of work. 5. Drawings & sketches about typical work. 6. Progress of work . 7. Quality of work. 8. Rejection of work. 9. Standards of work & materials. 10. Additions & altarations 11. Supervision of work. 11. Subletting. 12. Payments terms. 13. Arbitrations 14. Final bill. 15. Temparary labour houses(sheds).
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-08

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 08
Date (DD/MM/YYYY) 16/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge our site incharge told us to watch flooring and how rebarring is done he told us to see how flooring is laid
Details of how you Planned & Executed the allotted work we planned to patiently to see the laying of pcc and flooring done and make the base horizontal with help of instrument like trowel etc for rebarring we saw drilling machine and chemical used for setting time we planne to clean the drilled hole matching with dia. of steel used
Details of the Construction Procedure / Activity / Technology learned today binding material-:fischer drilling machine with diffrent types of drilling knob
Details of the Construction Materials learned today material newly used were binding material-:fischer drilling machine with diffrent types of drilling knob
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today section with floors
Details of the Bye Laws referred today floor heights
Details of any Managerial Skill learned today how to use vetrified technology and minimize wastage
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for 1m2 flooring for class1 vetrifie tiles tile size 0.6m by 0.6m rate of tile 40rs(160ft2) cement require =0.6*0.6*0.15=0.054*250rs=13.50rs sand require=0.6*0.6*0.025=12.70rs labour rate=9rs/ft2*2ft*2ft=36rs/ft2 total cost=186.20+36=222.20rs =222.20/0.36 =616rs
Result of RATE ANALYSIS ( Rs per Unit ) 616rs/m2
Todays BUZZ Word contract and agreement 1)aggrement with rcc contractor 2)aggrement for masonary an lasteering work 3)aggrement with tiling contractor 4)aggrement for water proofing work 5)aggrement with plumbing contractor 6)aggrement with electrical contractor 7)aggrement with carpentry contractor 8)aggrement with the tv or telphone work contractor 9)aggrement with panting contractor 10)aggrement with road contractor 11)landscaping work contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: viju128@gmail.com
Subject: 3638-08

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) shinde vijay namdeo
Exam No. 3638
Working Day No. 08
Date (DD/MM/YYYY) 16/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge our site incharge told us to watch flooring and how rebarring is done he told us to see how flooring is laid
Details of how you Planned & Executed the allotted work we planned to patiently to see the laying of pcc and flooring done and make the base horizontal with help of instrument like trowel etc for rebarring we saw drilling machine and chemical used for setting time we planne to clean the drilled hole matching with dia. of steel used
Details of the Construction Procedure / Activity / Technology learned today binding material-:fischer drilling machine with diffrent types of drilling knob
Details of the Construction Materials learned today material newly used were binding material-:fischer drilling machine with diffrent types of drilling knob
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today section with floors
Details of the Bye Laws referred today floor heights
Details of any Managerial Skill learned today how to use vetrified technology and minimize wastage
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for 1m2 flooring for class1 vetrifie tiles tile size 0.6m by 0.6m rate of tile 40rs(160ft2) cement require =0.6*0.6*0.15=0.054*250rs=13.50rs sand require=0.6*0.6*0.025=12.70rs labour rate=9rs/ft2*2ft*2ft=36rs/ft2 total cost=186.20+36=222.20rs =222.20/0.36 =616rs
Result of RATE ANALYSIS ( Rs per Unit ) 616rs/m2
Todays BUZZ Word contract and agreement 1)aggrement with rcc contractor 2)aggrement for masonary an lasteering work 3)aggrement with tiling contractor 4)aggrement for water proofing work 5)aggrement with plumbing contractor 6)aggrement with electrical contractor 7)aggrement with carpentry contractor 8)aggrement with the tv or telphone work contractor 9)aggrement with panting contractor 10)aggrement with road contractor 11)landscaping work contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: pinkrosee4u@yahoo.com
Subject: 10878-08

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr. rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) narnaware shikha haridas
Exam No. 10878
Working Day No. 08
Date (DD/MM/YYYY) 16/12/10
Site Reporting Time (HH:MM am/pm) 9AM
Site Leaving Time (HH:MM am/pm) 4PM
Details of the Work Allotted to you today by the Site In-Charge our site incharge told us to watch flooring and how rebarring is done he told us to see how flooring is laid
Details of how you Planned & Executed the allotted work we planned to patiently to see the laying of pcc and flooring done and make the base horizontal with help of instrument like trowel etc for rebarring we saw drilling machine and chemical used for setting time we planne to clean the drilled hole matching with dia. of steel used
Details of the Construction Procedure / Activity / Technology learned today binding material-:fischer drilling machine with diffrent types of drilling knob
Details of the Construction Materials learned today material newly used were binding material-:fischer drilling machine with diffrent types of drilling knob
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today section with floors
Details of the Bye Laws referred today floor heights
Details of any Managerial Skill learned today how to use vetrified technology and minimize wastage
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for 1m2 flooring for class1 vetrifie tiles tile size 0.6m by 0.6m rate of tile 40rs(160ft2) cement require =0.6*0.6*0.15=0.054*250rs=13.50rs sand require=0.6*0.6*0.025=12.70rs labour rate=9rs/ft2*2ft*2ft=36rs/ft2 total cost=186.20+36=222.20rs =222.20/0.36 =616rs
Result of RATE ANALYSIS ( Rs per Unit ) 616rs/m2
Todays BUZZ Word contract and agreement 1)aggrement with rcc contractor 2)aggrement for masonary an lasteering work 3)aggrement with tiling contractor 4)aggrement for water proofing work 5)aggrement with plumbing contractor 6)aggrement with electrical contractor 7)aggrement with carpentry contractor 8)aggrement with the tv or telphone work contractor 9)aggrement with panting contractor 10)aggrement with road contractor 11)landscaping work contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 1088-08

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.rajnra nagar kolhapur
Students Name (Surname_First Name_Middle Name) saurabh arora
Exam No. 10883
Working Day No. 07
Date (DD/MM/YYYY) 16/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge our site incharge told us to watch flooring and how rebarring is done he told us to see how flooring is laid
Details of how you Planned & Executed the allotted work we planned to patiently to see the laying of pcc and flooring done and make the base horizontal with help of instrument like trowel etc for rebarring we saw drilling machine and chemical used for setting time we planne to clean the drilled hole matching with dia. of steel used
Details of the Construction Procedure / Activity / Technology learned today binding material-:fischer drilling machine with diffrent types of drilling knob
Details of the Construction Materials learned today material newly used were binding material-:fischer drilling machine with diffrent types of drilling knob
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today section with floors
Details of the Bye Laws referred today floor heights
Details of any Managerial Skill learned today how to use vetrified technology and minimize wastage
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for 1m2 flooring for class1 vetrifie tiles tile size 0.6m by 0.6m rate of tile 40rs(160ft2) cement require =0.6*0.6*0.15=0.054*250rs=13.50rs sand require=0.6*0.6*0.025=12.70rs labour rate=9rs/ft2*2ft*2ft=36rs/ft2 total cost=186.20+36=222.20rs =222.20/0.36 =616rs
Result of RATE ANALYSIS ( Rs per Unit ) 616rs/m2
Todays BUZZ Word contract and agreement 1)aggrement with rcc contractor 2)aggrement for masonary an lasteering work 3)aggrement with tiling contractor 4)aggrement for water proofing work 5)aggrement with plumbing contractor 6)aggrement with electrical contractor 7)aggrement with carpentry contractor 8)aggrement with the tv or telphone work contractor 9)aggrement with panting contractor 10)aggrement with road contractor 11)landscaping work contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 13567-08

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing work needs a skilled supervision which include following points:- a)First changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. b)Then mark the alignment,every junction of pipe on inner & outer side of wall. c)Drilled the hole in wall as per diameter of pipe required. d)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. e)Every junction of pipe should be well jointed & free from leakages . f)Good binding material should be used for connecting two pipes. g)Elbows,T,collers should be used at correct place. h)The no. of joints should be avoided. i)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. .
Details of the Construction Materials learned today Various types of pipe used for plumbing work:- PVC,SWR,ELBOWS,T,COLLERS,HALFTURN,VALVES,NAHANITRAPS,P TRAP,CONCEALED VALVE. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper design ,management & accuracy in work avoid the wastage of water through leakages & uneconomical use of water,which is the very important need of human life. .
Details of the Construction / Engineering Drawings observed today Detail plumbing drawing for appartment or for any residential building. in which requirement of various diameters ,no.of pipes. .
Details of the Bye Laws referred today Minimum & maximum water requirement for public building. Diameters of pipe for various purposes. Domestic water demand in liter per day per person. .
Details of any Managerial Skill learned today How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-08

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Shinde Sagar Arvind
Exam No. 13568
Working Day No. 08
Date (DD/MM/YYYY) 16-12-2010
Site Reporting Time (HH:MM am/pm) 09.00am
Site Leaving Time (HH:MM am/pm) 04.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing work needs a skilled supervision which include following points:- a)First changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. b)Then mark the alignment,every junction of pipe on inner & outer side of wall. c)Drilled the hole in wall as per diameter of pipe required. d)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. e)Every junction of pipe should be well jointed & free from leakages . f)Good binding material should be used for connecting two pipes. g)Elbows,T,collers should be used at correct place. h)The no. of joints should be avoided. i)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. .
Details of the Construction Materials learned today Various types of pipe used for plumbing work:- CPVC,SWR,ELBOWS,T,COLLERS,HALFTURN,VALVES,NAHANITRAPS,P TRAP,CONCEALED VALVE. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper design ,management & accuracy in work avoid the wastage of water through leakages & uneconomical use of water,which is the very important need of human life. .
Details of the Construction / Engineering Drawings observed today Detail plumbing drawing for appartment or for any residential building. in which requirement of various diameters ,no.of pipes. .
Details of the Bye Laws referred today Minimum & maximum water requirement for public building. Diameters of pipe for various purposes. Domestic water demand in liter per day per person. .
Details of any Managerial Skill learned today How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-08

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Shivtare Prabharkar Chandrakant
Exam No. 13569
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing work needs a skilled supervision which include following points:- a)First changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. b)Then mark the alignment,every junction of pipe on inner & outer side of wall. c)Drilled the hole in wall as per diameter of pipe required. d)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. e)Every junction of pipe should be well jointed & free from leakages . f)Good binding material should be used for connecting two pipes. g)Elbows,T,collers should be used at correct place. h)The no. of joints should be avoided. i)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. .
Details of the Construction Materials learned today Various types of pipe used for plumbing work:- PVC,SWR,ELBOWS,T,COLLERS,HALFTURN,VALVES,NAHANITRAPS,P TRAP,CONCEALED VALVE. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper design ,management & accuracy in work avoid the wastage of water through leakages & uneconomical use of water,which is the very important need of human life. .
Details of the Construction / Engineering Drawings observed today Detail plumbing drawing for appartment or for any residential building. in which requirement of various diameters ,no.of pipes. .
Details of the Bye Laws referred today Minimum & maximum water requirement for public building. Diameters of pipe for various purposes. Domestic water demand in liter per day per person. .
Details of any Managerial Skill learned today How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: mayur.sonavne61@gmail.com
Subject: 13570-08

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sonavne Mayur Madhukar
Exam No. 13570
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing work needs a skilled supervision which include following points:- a)First changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. b)Then mark the alignment,every junction of pipe on inner & outer side of wall. c)Drilled the hole in wall as per diameter of pipe required. d)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. e)Every junction of pipe should be well jointed & free from leakages . f)Good binding material should be used for connecting two pipes. g)Elbows,T,collers should be used at correct place. h)The no. of joints should be avoided. i)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. .
Details of the Construction Materials learned today Various types of pipe used for plumbing work:- PVC,SWR,ELBOWS,T,COLLERS,HALFTURN,VALVES,NAHANITRAPS,P TRAP,CONCEALED VALVE. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper design ,management & accuracy in work avoid the wastage of water through leakages & uneconomical use of water,which is the very important need of human life. .
Details of the Construction / Engineering Drawings observed today Detail plumbing drawing for appartment or for any residential building. in which requirement of various diameters ,no.of pipes. .
Details of the Bye Laws referred today Minimum & maximum water requirement for public building. Diameters of pipe for various purposes. Domestic water demand in liter per day per person. .
Details of any Managerial Skill learned today How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/16/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-08

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sutar Namdev Rangnath
Exam No. 13571
Working Day No. 08
Date (DD/MM/YYYY) 16/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plumbing work:- Plumbing work is important for every residential,commertial & public building. Most of the repair & leakages occurred in plumbing & sanitary works. Careful supervision improves the good circulation & avoid the losses. .
Details of how you Planned & Executed the allotted work Work was distributed as per the site requirement:- 1)First student marked the alignment on wall as per connection & junction. 2)Second student found out the diameter & no.of pipes required. 3)Third student placed the pipe on marked alignment with their respective length & direction. 4)Fourth student made the connections at each & every junction. 5)Fifth student checked the work as per drawing & requirements. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing work needs a skilled supervision which include following points:- a)First changes in alignment,direction of flow ,height of building,no. of floors,no.of connection required should be decided. b)Then mark the alignment,every junction of pipe on inner & outer side of wall. c)Drilled the hole in wall as per diameter of pipe required. d)Place the pipe on marked alignment & fixed to wall with the hooks or any other attaching material. e)Every junction of pipe should be well jointed & free from leakages . f)Good binding material should be used for connecting two pipes. g)Elbows,T,collers should be used at correct place. h)The no. of joints should be avoided. i)Testing of pipe & connections should taken at end of work, if any leakage found then it must be repaired at same time. .
Details of the Construction Materials learned today Various types of pipe used for plumbing work:- PVC,SWR,ELBOWS,T,COLLERS,HALFTURN,VALVES,NAHANITRAPS,P TRAP,CONCEALED VALVE. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Proper design ,management & accuracy in work avoid the wastage of water through leakages & uneconomical use of water,which is the very important need of human life. .
Details of the Construction / Engineering Drawings observed today Detail plumbing drawing for appartment or for any residential building. in which requirement of various diameters ,no.of pipes. .
Details of the Bye Laws referred today Minimum & maximum water requirement for public building. Diameters of pipe for various purposes. Domestic water demand in liter per day per person. .
Details of any Managerial Skill learned today How to manage the work as per scheduled with in given time ,money, & in labour force.simultaneously the quality & overall cost of work was not avoided. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Vetrified Tile 8mm thk Flooring - 1.00 m2 Material Vetrified Tiles 600/- Wastage 5% 30/- Cement 0.25 bag * 240/- 60/- Sand 0.03 m3 * 915/- 27/- P.O.P. Per m2 10/- Labour 107/- Total 834/- 2% Electricity and curing 16/- 20% Tax, overhead and Profit 170/- Total = 1020/- Say - 1000/- m2 .
Result of RATE ANALYSIS ( Rs per Unit ) 1000/- m2
Todays BUZZ Word CONTRACTS AND AGREEMENT A) CONTRACTS:- There are three major types of contracts 1)Item rate contracts: - In this type of contracts ,there may be one or more contractors .But for billing and measurement Purposes ,the work is split I to various items . -The rate are finalized for different items at certain level which cover the cost of labour , transport , tools, materials ,plants etc. -The addition increase in rate is sanction for additional lead & lifts . 2) Built up area basis contracts :- - This method has proved to be most easy method , hence it is most popular method. - If contract is with material plus labour . - For a particular project details specification of work is finalized . 3) Lump sum contracts :- - Normally ,petty works are given on a lump sum basis , which includes 100% completion of A particular activity in the decided lump sum amount . - In such contract no measurement is required for billing only the stage on % of work done can be mentioned for intermediate payment. AGREEMENT:- -Agreement always made in three copies . 1) First copy – with client 2) Second copy – for office record 3) Third copy - with sub registrar -Client & P.A.H. should be sign on all the pages of the agreement . -Agreement should be done on a Rs. 20 stamp paper with in six month. -Agreement should be register with the concerned authority . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-07

Company Name V. S. Joshi & Associates
Project Name & Site Address V.S,Joshi Associates, mukta sainik vasahat, kolhapur
Students Name (Surname_First Name_Middle Name) Shinde Shraddha Tukaram
Exam No. 10901
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flat No. 308, to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR EXTERNAL PLASTERING\" # - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days.
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Fly Ash Bricks were used. 2) Rain Water Harvesting was installed in A-Wing. 3) Storm Water Collection Chamber was constructed.
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall. 4) Services Layout.
Details of the Bye Laws referred today Bye-Laws book - Requirements of Buildings 1) Parapet. 2) Balcony. 3) Corridor.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR EXTERNAL PLASTER\" # A) External Plaster for: (C.M. = 1:4) 1. Right side external wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left Side (Verandah, WC ) = 11.61 sq.m 4. Front Wall = 30.41 sq.m 5. Back Wall = 16.19 sq.m 6. Back Wall (Verandah, WC) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction for: 1. D1 = 2.6 sq.m 2. D2 = 2.2 sq.m 3. W1 = 11.2 sq.m 4. W2 = 2.8 sq.m 5. W3 = 0.9 sq.m 6. Grill = 3.0 sq.m TOTAL = 22.70 sq.m C) Deduct 50% = (22.70/2) = 11.35 sq.m D) Net Quantity = 119.6 sq.m E) Materials Required: 1. Area Of Plastering = 119.6 sq.m 2. Volume Of Plaster = 1.43 cu.m 3. Add 50% for Voids & 10% for uneveness = 2.288 cu.m 4. Cement = 14 bags 5. Sand = 1.83 cu.m F) Cost of Materials: 1. Cement = 14 x 230 = 3220/- 2. Sand = 1.83 x 850 = 1555.5/- TOTAL = 4775.5/- G) Cost of labour: 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 2 x 110 = 220/- 5. Scaffolding = 500/- 6. T&P = 500/- TOTAL = 5270/- H) TOTAL COST = F + G = 10045.5/- I) Add 2% for Water Charges = 200.91/- J) Add 15% for Contractors Profit = 1506.825/- K) Grand TOTAL = 11753.235/- L) Rate Per sq.m = 98.27/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.98.27/-
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10893-07

Company Name V. S. Joshi & Associates
Project Name & Site Address VVishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) kamble ankit
Exam No. 10893
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 5.30PM
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flat No. 308, to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR EXTERNAL PLASTERING\" # - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days.
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Fly Ash Bricks were used. 2) Rain Water Harvesting was installed in A-Wing. 3) Storm Water Collection Chamber was constructed.
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall. 4) Services Layout.
Details of the Bye Laws referred today Bye-Laws book - Requirements of Buildings 1) Parapet. 2) Balcony. 3) Corridor.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR EXTERNAL PLASTER\" # A) External Plaster for: (C.M. = 1:4) 1. Right side external wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left Side (Verandah, WC ) = 11.61 sq.m 4. Front Wall = 30.41 sq.m 5. Back Wall = 16.19 sq.m 6. Back Wall (Verandah, WC) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction for: 1. D1 = 2.6 sq.m 2. D2 = 2.2 sq.m 3. W1 = 11.2 sq.m 4. W2 = 2.8 sq.m 5. W3 = 0.9 sq.m 6. Grill = 3.0 sq.m TOTAL = 22.70 sq.m C) Deduct 50% = (22.70/2) = 11.35 sq.m D) Net Quantity = 119.6 sq.m E) Materials Required: 1. Area Of Plastering = 119.6 sq.m 2. Volume Of Plaster = 1.43 cu.m 3. Add 50% for Voids & 10% for uneveness = 2.288 cu.m 4. Cement = 14 bags 5. Sand = 1.83 cu.m F) Cost of Materials: 1. Cement = 14 x 230 = 3220/- 2. Sand = 1.83 x 850 = 1555.5/- TOTAL = 4775.5/- G) Cost of labour: 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 2 x 110 = 220/- 5. Scaffolding = 500/- 6. T&P = 500/- TOTAL = 5270/- H) TOTAL COST = F + G = 10045.5/- I) Add 2% for Water Charges = 200.91/- J) Add 15% for Contractors Profit = 1506.825/- K) Grand TOTAL = 11753.235/- L) Rate Per sq.m = 98.27/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.98.27/-
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge amol mule
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-07

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell,karande mala
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flat No. 308, to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR EXTERNAL PLASTERING\" # - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days.
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Fly Ash Bricks were used. 2) Rain Water Harvesting was installed in A-Wing. 3) Storm Water Collection Chamber was constructed.
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall. 4) Services Layout.
Details of the Bye Laws referred today Bye-Laws book - Requirements of Buildings 1) Parapet. 2) Balcony. 3) Corridor.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR EXTERNAL PLASTER\" # A) External Plaster for: (C.M. = 1:4) 1. Right side external wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left Side (Verandah, WC ) = 11.61 sq.m 4. Front Wall = 30.41 sq.m 5. Back Wall = 16.19 sq.m 6. Back Wall (Verandah, WC) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction for: 1. D1 = 2.6 sq.m 2. D2 = 2.2 sq.m 3. W1 = 11.2 sq.m 4. W2 = 2.8 sq.m 5. W3 = 0.9 sq.m 6. Grill = 3.0 sq.m TOTAL = 22.70 sq.m C) Deduct 50% = (22.70/2) = 11.35 sq.m D) Net Quantity = 119.6 sq.m E) Materials Required: 1. Area Of Plastering = 119.6 sq.m 2. Volume Of Plaster = 1.43 cu.m 3. Add 50% for Voids & 10% for uneveness = 2.288 cu.m 4. Cement = 14 bags 5. Sand = 1.83 cu.m F) Cost of Materials: 1. Cement = 14 x 230 = 3220/- 2. Sand = 1.83 x 850 = 1555.5/- TOTAL = 4775.5/- G) Cost of labour: 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 2 x 110 = 220/- 5. Scaffolding = 500/- 6. T&P = 500/- TOTAL = 5270/- H) TOTAL COST = F + G = 10045.5/- I) Add 2% for Water Charges = 200.91/- J) Add 15% for Contractors Profit = 1506.825/- K) Grand TOTAL = 11753.235/- L) Rate Per sq.m = 98.27/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.98.27/-
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-07

Company Name V. S. Joshi & Associates
Project Name & Site Address VVishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) janbandhu rakshit janbandhu
Exam No. 10875
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 5.30PM
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\".
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flat No. 308, to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure.
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR EXTERNAL PLASTERING\" # - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days.
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Fly Ash Bricks were used. 2) Rain Water Harvesting was installed in A-Wing. 3) Storm Water Collection Chamber was constructed.
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall. 4) Services Layout.
Details of the Bye Laws referred today Bye-Laws book - Requirements of Buildings 1) Parapet. 2) Balcony. 3) Corridor.
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR EXTERNAL PLASTER\" # A) External Plaster for: (C.M. = 1:4) 1. Right side external wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left Side (Verandah, WC ) = 11.61 sq.m 4. Front Wall = 30.41 sq.m 5. Back Wall = 16.19 sq.m 6. Back Wall (Verandah, WC) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction for: 1. D1 = 2.6 sq.m 2. D2 = 2.2 sq.m 3. W1 = 11.2 sq.m 4. W2 = 2.8 sq.m 5. W3 = 0.9 sq.m 6. Grill = 3.0 sq.m TOTAL = 22.70 sq.m C) Deduct 50% = (22.70/2) = 11.35 sq.m D) Net Quantity = 119.6 sq.m E) Materials Required: 1. Area Of Plastering = 119.6 sq.m 2. Volume Of Plaster = 1.43 cu.m 3. Add 50% for Voids & 10% for uneveness = 2.288 cu.m 4. Cement = 14 bags 5. Sand = 1.83 cu.m F) Cost of Materials: 1. Cement = 14 x 230 = 3220/- 2. Sand = 1.83 x 850 = 1555.5/- TOTAL = 4775.5/- G) Cost of labour: 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 2 x 110 = 220/- 5. Scaffolding = 500/- 6. T&P = 500/- TOTAL = 5270/- H) TOTAL COST = F + G = 10045.5/- I) Add 2% for Water Charges = 200.91/- J) Add 15% for Contractors Profit = 1506.825/- K) Grand TOTAL = 11753.235/- L) Rate Per sq.m = 98.27/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.98.27/-
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge AMOL MULE
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-07

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Jape Vishwajeet Ramesh
Exam No. 10892
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\". --------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flat No. 308, to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure. -------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR EXTERNAL PLASTERING\" # - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days. ------------------------------------------------------------------------------------
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob. -------------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Fly Ash Bricks were used. 2) Rain Water Harvesting was installed in A-Wing. 3) Storm Water Collection Chamber was constructed. -------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall. 4) Services Layout. -------------------------------------------------------------------------------------
Details of the Bye Laws referred today Bye-Laws book - Requirements of Buildings 1) Parapet. 2) Balcony. 3) Corridor. -------------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site. ---------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR EXTERNAL PLASTER\" # A) External Plaster for: (C.M. = 1:4) 1. Right side external wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left Side (Verandah, WC ) = 11.61 sq.m 4. Front Wall = 30.41 sq.m 5. Back Wall = 16.19 sq.m 6. Back Wall (Verandah, WC) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction for: 1. D1 = 2.6 sq.m 2. D2 = 2.2 sq.m 3. W1 = 11.2 sq.m 4. W2 = 2.8 sq.m 5. W3 = 0.9 sq.m 6. Grill = 3.0 sq.m TOTAL = 22.70 sq.m C) Deduct 50% = (22.70/2) = 11.35 sq.m D) Net Quantity = 119.6 sq.m E) Materials Required: 1. Area Of Plastering = 119.6 sq.m 2. Volume Of Plaster = 1.43 cu.m 3. Add 50% for Voids & 10% for uneveness = 2.288 cu.m 4. Cement = 14 bags 5. Sand = 1.83 cu.m F) Cost of Materials: 1. Cement = 14 x 230 = 3220/- 2. Sand = 1.83 x 850 = 1555.5/- TOTAL = 4775.5/- G) Cost of labour: 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 2 x 110 = 220/- 5. Scaffolding = 500/- 6. T&P = 500/- TOTAL = 5270/- H) TOTAL COST = F + G = 10045.5/- I) Add 2% for Water Charges = 200.91/- J) Add 15% for Contractors Profit = 1506.825/- K) Grand TOTAL = 11753.235/- L) Rate Per sq.m = 98.27/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.98.27/-
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works. -------------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-07

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Nagvekar Yogesh Deepak
Exam No. 10894
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge 1) To Study the various under construction works like Plastering,etc. 2) To Study Estimation of quantity for the \"Septic Tank\". --------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work 1) We all together (5 members) in our group went to Flat No. 308, to study the various aspects required before & after Plastering work. 2) We asked all our queries to the contractor incharge of Plastering. 3) Accordingly we noted the procedure. -------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR EXTERNAL PLASTERING\" # - For quality results consider bulcage of sand before plastering. - Take sand proportion in 1:5 for first coat. - The mixed mortor should be used within half an hour. - Apply Plaster to the same face level & finish the same with the help of float & Trowel. - Check the surface with Lime Dori. - Roughen the surface with wires for better bonding to second coat. - Apply the second coat. - Remove the scaffolding & fill the holes with Cement Mortor & wet brick pieces. - Clean all the surface of the adjacent walls windows, rcc grills. - Curing should carried out for minimum 15 days. ------------------------------------------------------------------------------------
Details of the Construction Materials learned today 1) Cement. 2) Sand. 3) Sanla. 4) Spade. 5) PVC Pipe. 6) Metal Float. 7) Plumb-bob. -------------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) Fly Ash Bricks were used. 2) Rain Water Harvesting was installed in A-Wing. 3) Storm Water Collection Chamber was constructed. -------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1) Septic Tank Drawings. 2) Details of Perforated RCC Slab. 3) Details of Upflow Filter & Baffle Wall. 4) Services Layout. -------------------------------------------------------------------------------------
Details of the Bye Laws referred today Bye-Laws book - Requirements of Buildings 1) Parapet. 2) Balcony. 3) Corridor. -------------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1) Handling Labours. 2) Check the Materials on site. ---------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR EXTERNAL PLASTER\" # A) External Plaster for: (C.M. = 1:4) 1. Right side external wall = 39.85 sq.m 2. Left side external wall = 16.20 sq.m 3. Left Side (Verandah, WC ) = 11.61 sq.m 4. Front Wall = 30.41 sq.m 5. Back Wall = 16.19 sq.m 6. Back Wall (Verandah, WC) = 16.69 sq.m TOTAL = 130.95 sq.m B) Deduction for: 1. D1 = 2.6 sq.m 2. D2 = 2.2 sq.m 3. W1 = 11.2 sq.m 4. W2 = 2.8 sq.m 5. W3 = 0.9 sq.m 6. Grill = 3.0 sq.m TOTAL = 22.70 sq.m C) Deduct 50% = (22.70/2) = 11.35 sq.m D) Net Quantity = 119.6 sq.m E) Materials Required: 1. Area Of Plastering = 119.6 sq.m 2. Volume Of Plaster = 1.43 cu.m 3. Add 50% for Voids & 10% for uneveness = 2.288 cu.m 4. Cement = 14 bags 5. Sand = 1.83 cu.m F) Cost of Materials: 1. Cement = 14 x 230 = 3220/- 2. Sand = 1.83 x 850 = 1555.5/- TOTAL = 4775.5/- G) Cost of labour: 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 2 x 110 = 220/- 5. Scaffolding = 500/- 6. T&P = 500/- TOTAL = 5270/- H) TOTAL COST = F + G = 10045.5/- I) Add 2% for Water Charges = 200.91/- J) Add 15% for Contractors Profit = 1506.825/- K) Grand TOTAL = 11753.235/- L) Rate Per sq.m = 98.27/- -------------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs.98.27/-
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works. -------------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: salmanbaig18@gmail.com
Subject: 10888-07

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) baig salman samad
Exam No. 10888
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of centring plates using spans supported on steel props. Checking their levels,and height from floor level to the slab bottom.
Details of how you Planned & Executed the allotted work Firstly we checked the dimensions of room over which the plates were being placed the height of slab bottom from floor level. Then we observed the placing of plates over the spans which were supported using the steel props. We checked the level of slab by placing three wooden blocks of same thickness in line dori and then kept the line dori over the face of blocks and checked whether all the blocks are in the same level or no and instructed the workers to adjust the props either by raising or lowering them at the required point.
Details of the Construction Procedure / Activity / Technology learned today Checking plumb line of the column Two plumbs are tied at the length face and one plumb at the width face of the column. The column is supported with the help of props from both the faces. The distance between the plumb line and the column shuttering is measured. It is kept equal throughout the length of plumb line and this distance is adjusted by loosening or tightening the props from the opposite sides. In this way the column is erected in plumb line and for cross checking by measuring the size of column its cover, diagonal length ; then checking the sides are in right angle or no.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Balcony width provided on the site is 1.20m. As per bye law the widths 1.20m maximum.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for external wall plastering using cement mortar of 1:3“ Dimensions of typical part of wall=3.0*4.0m Plastering is done in two coats of 12mm thickness 1. surface area of wall =12 sq.m 2.Quantity of cement mortar (1:3)=12*(0.012*2) =0.288 cu.m Add 5o% of total volumefor voids and10%for uneveness =0.288+0.288*0.60. = 0.4608 cu.m 3. Quantity of cement =0.4608/1+3 =0.1152 cu.m =0.1152/0.035=3bags 4. Quantity of sand=0.1152*3=0.3456 cu.m. “Rate Analysis for external wall plastering using cement mortar of 1:3” (Considering local rates of material) 1. Cost of cement=3*250=750/-………..(250/- per bag) 2. Cost of sand=0.3456*1600=553/-…………(1600/- per cu.m) 3.Labour charges=680/- 4. Total cost= 1983/- 8.10% profit of total cost for the contractor=198.3/- 9. Total cost=2181.3/-
Result of RATE ANALYSIS ( Rs per Unit ) 182/-
Todays BUZZ Word 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: bsalman75@yahoo.com
Subject: 10888-07

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) baig salman samad
Exam No. 10888
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of centring plates using spans supported on steel props. Checking their levels,and height from floor level to the slab bottom.
Details of how you Planned & Executed the allotted work Firstly we checked the dimensions of room over which the plates were being placed the height of slab bottom from floor level. Then we observed the placing of plates over the spans which were supported using the steel props. We checked the level of slab by placing three wooden blocks of same thickness in line dori and then kept the line dori over the face of blocks and checked whether all the blocks are in the same level or no and instructed the workers to adjust the props either by raising or lowering them at the required point.
Details of the Construction Procedure / Activity / Technology learned today Checking plumb line of the column Two plumbs are tied at the length face and one plumb at the width face of the column. The column is supported with the help of props from both the faces. The distance between the plumb line and the column shuttering is measured. It is kept equal throughout the length of plumb line and this distance is adjusted by loosening or tightening the props from the opposite sides. In this way the column is erected in plumb line and for cross checking by measuring the size of column its cover, diagonal length ; then checking the sides are in right angle or no.
Details of the Construction Materials learned today NONE
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Balcony width provided on the site is 1.20m. As per bye law the widths 1.20m maximum.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for external wall plastering using cement mortar of 1:3“ Dimensions of typical part of wall=3.0*4.0m Plastering is done in two coats of 12mm thickness 1. surface area of wall =12 sq.m 2.Quantity of cement mortar (1:3)=12*(0.012*2) =0.288 cu.m Add 5o% of total volumefor voids and10%for uneveness =0.288+0.288*0.60. = 0.4608 cu.m 3. Quantity of cement =0.4608/1+3 =0.1152 cu.m =0.1152/0.035=3bags 4. Quantity of sand=0.1152*3=0.3456 cu.m. “Rate Analysis for external wall plastering using cement mortar of 1:3” (Considering local rates of material) 1. Cost of cement=3*250=750/-………..(250/- per bag) 2. Cost of sand=0.3456*1600=553/-…………(1600/- per cu.m) 3.Labour charges=680/- 4. Total cost= 1983/- 8.10% profit of total cost for the contractor=198.3/- 9. Total cost=2181.3/-
Result of RATE ANALYSIS ( Rs per Unit ) 182/-
Todays BUZZ Word 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-07

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Patil Vrishali Vitthal
Exam No. 13541
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to test cement ,to calculate sand corse and fine agg.in brass
Details of how you Planned & Executed the allotted work we insert our hand in hand bag and check weather it is lump free or not. we thrown hand full of cement in to water and check weather it is flotting or not. by measuring lenth ,breadth,and depth we calculate agg. in brass
Details of the Construction Procedure / Activity / Technology learned today main beam and lateral beam- main beams are provided in short span and lateral beams are provided in long span
Details of the Construction Materials learned today internal finishes-granite tiles for kitchen katta vitrifide tiles for better apperance in flooring
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of portland pozzolana cement wich consist of pozzolanic material emits less heat andgives higher strenth than ordinary portland cement
Details of the Construction / Engineering Drawings observed today obsertvation of second floor plan- 3 bhk flats facing road side and 2 bhk flats are at rear side
Details of the Bye Laws referred today height of building is depends on width of road- for 8m.wide road 12m. height is permissible
Details of any Managerial Skill learned today co-operative and intelligent
RATE ANALYSIS (Detailed Stepwise Calculations required) double coat plaster(external) assume 10sq.m, area thk.of plaster = 20mm. = 0.02m. total volume =0.2 cu.m. add 50% for dry volume no of bags of cement =(0.2*1.5)/(1+4) =0.060 cu.m. =0.060/0.035 =1.71 =2 bags sand= 0.060*4 =0.240 cu.m. amount =0.240*1060 Rs.per cu.m. =254.40 Rs. Labour =450Rs. for double coat total =444.6+254.40+450 =1149+15% contractors profit =1149+172.35 =1321.35Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1321.35Rs.per 10 sq.m.wall area
Todays BUZZ Word billing department- it is department of consruction site in wich all the details of perchacing of contruction material is done
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-07

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Lad Manoj Sadashiv
Exam No. 13534
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to test cement ,to calculate sand corse and fine agg.in brass
Details of how you Planned & Executed the allotted work we insert our hand in hand bag and check weather it is lump free or not. we thrown hand full of cement in to water and check weather it is flotting or not. by measuring lenth ,breadth,and depth we calculate agg. in brass
Details of the Construction Procedure / Activity / Technology learned today main beam and lateral beam- main beams are provided in short span and lateral beams are provided in long span
Details of the Construction Materials learned today internal finishes-granite tiles for kitchen katta vitrifide tiles for better apperance in flooring
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of portland pozzolana cement wich consist of pozzolanic material emits less heat andgives higher strenth than ordinary portland cement
Details of the Construction / Engineering Drawings observed today obsertvation of second floor plan- 3 bhk flats facing road side and 2 bhk flats are at rear side
Details of the Bye Laws referred today height of building is depends on width of road- for 8m.wide road 12m. height is permissible
Details of any Managerial Skill learned today co-operative and intelligent
RATE ANALYSIS (Detailed Stepwise Calculations required) double coat plaster(external) assume 10sq.m, area thk.of plaster = 20mm. = 0.02m. total volume =0.2 cu.m. add 50% for dry volume no of bags of cement =(0.2*1.5)/(1+4) =0.060 cu.m. =0.060/0.035 =1.71 =2 bags sand= 0.060*4 =0.240 cu.m. amount =0.240*1060 Rs.per cu.m. =254.40 Rs. Labour =450Rs. for double coat total =444.6+254.40+450 =1149+15% contractors profit =1149+172.35 =1321.35Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1321.35Rs.per 10 sq.m.wall area
Todays BUZZ Word billing department- it is department of consruction site in wich all the details of perchacing of contruction material is done
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-07

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Hasabnis Ketaki Bhagwan
Exam No. 13527
Working Day No. 7
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To visit the Farm house at Panhala and study the construction work going on as recommended by Paras Oswal sir.
Details of how you Planned & Executed the allotted work All group members went to Panhala. We met the site incharge over there .He gave us the plan of site. We studied the plans and saw the full site. The construction process is going on as per plan.
Details of the Construction Procedure / Activity / Technology learned today 1. We saw the process of concreting of roofing slab, filling work, the foundation work,plinth work. 2. We saw the masonary work. 3. Spring bar in roofing slab,Footing work,steel grid used for footing,
Details of the Construction Materials learned today 1. Use of waterproofing chemical while concreteing - algae proof (200 ml). 2. Different types of bricks. 1. Hollow Bricks for temporary structure. 2. Wire cut Bricks for attractive elevation and good strength. 3. Cement 43 grade Bagalkot supreme.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental friendly, as use of river sand is prohibited
Details of the Construction / Engineering Drawings observed today 1. Plan of different farm-houses of areas 900 sq.ft , 1000reasq.ft and 1200 sq.ft. 2. Contour plan
Details of the Bye Laws referred today 1.According to bye laws maximum cantilever porch length should be 4.00m, which has been followed. 2.Stair case is designed as per bye laws.
Details of any Managerial Skill learned today 1. The site incharge inspected concreteing process going on. 2. The site incharge checked the propotions of different materials used. 3. The site incharge kept a proper record of total quantity
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for EXTERNAL PLASTER. Considering 25 mm thick plaster in two coats. Mortar = 1:4. Cement=0.22 Cost of Cement= 0.22*265= Rs.58.30. Sand=0.025. Cost of sand= 0.025*2120= Rs.53. Labour= Rs.65. Total Cost= 58.30+53+65= Rs.176.30. For each sq.m add Rs.15 extra for water proofing. Total cost= 176.30+15= Rs.191.30. Considering 10% profit= 19.13. Total cost of external plaster= 191.13+19.13= Rs.210.43. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.210.43. per sq.m
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SALIM MOMIN Cell NO.9225816079.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: nitinpatil22.2010@rediffmail.com
Subject: 10879-07

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil nitin dilip
Exam No. 10879
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of centring plates using spans supported on steel props. Checking their levels,and height from floor level to theab bottom.
Details of how you Planned & Executed the allotted work Firstly we checked the dimensions of room over which the plates were being placed the height of slab bottom from floor level. Then we observed the placing of plates over the spans which were supported using the steel props. We checked the level of slab by placing three wooden blocks of same thickness in line dori and then kept the line dori over the face of blocks and checked whether all the blocks are in the same level or no and instructed the workers to adjust the props either by raising or lowering them at the required point.
Details of the Construction Procedure / Activity / Technology learned today Checking plumb line of the column Two plumbs are tied at the length face and one plumb at the width face of the column. The column is supported with the help of props from both the faces. The distance between the plumb line and the column shuttering is measured. It is kept equal throughout the length of plumb line and this distance is adjusted by loosening or tightening the props from the opposite sides. In this way the column is erected in plumb line and for cross checking by measuring the size of column its cover, diagonal length ; then checking the sides are in right angle or no.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Balcony width provided on the site is 1.20m. As per bye law the widths 1.20m maximum.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for external wall plastering using cement mortar of 1:3“ Dimensions of typical part of wall=3.0*4.0m Plastering is done in two coats of 12mm thickness 1. surface area of wall =12 sq.m 2.Quantity of cement mortar (1:3)=12*(0.012*2) =0.288 cu.m Add 5o% of total volumefor voids and10%for uneveness =0.288+0.288*0.60. = 0.4608 cu.m 3. Quantity of cement =0.4608/1+3 =0.1152 cu.m =0.1152/0.035=3bags 4. Quantity of sand=0.1152*3=0.3456 cu.m. “Rate Analysis for external wall plastering using cement mortar of 1:3” (Considering local rates of material) 1. Cost of cement=3*250=750/-………..(250/- per bag) 2. Cost of sand=0.3456*1600=553/-…………(1600/- per cu.m) 3.Labour charges=680/- 4. Total cost= 1983/- 8.10% profit of total cost for the contractor=198.3/- 9. Total cost=2181.3/-
Result of RATE ANALYSIS ( Rs per Unit ) 182/-
Todays BUZZ Word 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: rameshkharat1987@gmail.com
Subject: 13532-07

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Ramesh Laxman
Exam No. 13532
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to test cement ,to calculate sand corse and fine agg.in brass
Details of how you Planned & Executed the allotted work we insert our hand in hand bag and check weather it is lump free or not. we thrown hand full of cement in to water and check weather it is flotting or not. by measuring lenth ,breadth,and depth we calculate agg. in brass
Details of the Construction Procedure / Activity / Technology learned today main beam and lateral beam- main beams are provided in short span and lateral beams are provided in long span
Details of the Construction Materials learned today internal finishes-granite tiles for kitchen katta vitrifide tiles for better apperance in flooring
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of portland pozzolana cement wich consist of pozzolanic material emits less heat andgives higher strenth than ordinary portland cement
Details of the Construction / Engineering Drawings observed today obsertvation of second floor plan- 3 bhk flats facing road side and 2 bhk flats are at rear side
Details of the Bye Laws referred today height of building is depends on width of road- for 8m.wide road 12m. height is permissible
Details of any Managerial Skill learned today co-operative and intelligent
RATE ANALYSIS (Detailed Stepwise Calculations required) double coat plaster(external) assume 10sq.m, area thk.of plaster = 20mm. = 0.02m. total volume =0.2 cu.m. add 50% for dry volume no of bags of cement =(0.2*1.5)/(1+4) =0.060 cu.m. =0.060/0.035 =1.71 =2 bags sand= 0.060*4 =0.240 cu.m. amount =0.240*1060 Rs.per cu.m. =254.40 Rs. Labour =450Rs. for double coat total =444.6+254.40+450 =1149+15% contractors profit =1149+172.35 =1321.35Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1321.35Rs.per 10 sq.m.wall area
Todays BUZZ Word billing department- it is department of consruction site in wich all the details of perchacing of contruction material is done
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: vishalsapakal124@gmail.com
Subject: 10882-07

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) sapakal vishal manohar
Exam No. 10882
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of centring plates using spans supported on steel props. Checking their levels,and height from floor level to theab bottom.
Details of how you Planned & Executed the allotted work Firstly we checked the dimensions of room over which the plates were being placed the height of slab bottom from floor level. Then we observed the placing of plates over the spans which were supported using the steel props. We checked the level of slab by placing three wooden blocks of same thickness in line dori and then kept the line dori over the face of blocks and checked whether all the blocks are in the same level or no and instructed the workers to adjust the props either by raising or lowering them at the required point.
Details of the Construction Procedure / Activity / Technology learned today Checking plumb line of the column Two plumbs are tied at the length face and one plumb at the width face of the column. The column is supported with the help of props from both the faces. The distance between the plumb line and the column shuttering is measured. It is kept equal throughout the length of plumb line and this distance is adjusted by loosening or tightening the props from the opposite sides. In this way the column is erected in plumb line and for cross checking by measuring the size of column its cover, diagonal length ; then checking the sides are in right angle or no.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Balcony width provided on the site is 1.20m. As per bye law the widths 1.20m maximum.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for external wall plastering using cement mortar of 1:3“ Dimensions of typical part of wall=3.0*4.0m Plastering is done in two coats of 12mm thickness 1. surface area of wall =12 sq.m 2.Quantity of cement mortar (1:3)=12*(0.012*2) =0.288 cu.m Add 5o% of total volumefor voids and10%for uneveness =0.288+0.288*0.60. = 0.4608 cu.m 3. Quantity of cement =0.4608/1+3 =0.1152 cu.m =0.1152/0.035=3bags 4. Quantity of sand=0.1152*3=0.3456 cu.m. “Rate Analysis for external wall plastering using cement mortar of 1:3” (Considering local rates of material) 1. Cost of cement=3*250=750/-………..(250/- per bag) 2. Cost of sand=0.3456*1600=553/-…………(1600/- per cu.m) 3.Labour charges=680/- 4. Total cost= 1983/- 8.10% profit of total cost for the contractor=198.3/- 9. Total cost=2181.3/-
Result of RATE ANALYSIS ( Rs per Unit ) 182/-
Todays BUZZ Word 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: patilpratibha7070@yahoo.in
Subject: 10896-07

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) patil pratibha dilip
Exam No. 10896
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of centring plates using spans supported on steel props. Checking their levels,and height from floor level to theab bottom.
Details of how you Planned & Executed the allotted work Firstly we checked the dimensions of room over which the plates were being placed the height of slab bottom from floor level. Then we observed the placing of plates over the spans which were supported using the steel props. We checked the level of slab by placing three wooden blocks of same thickness in line dori and then kept the line dori over the face of blocks and checked whether all the blocks are in the same level or no and instructed the workers to adjust the props either by raising or lowering them at the required point.
Details of the Construction Procedure / Activity / Technology learned today Checking plumb line of the column Two plumbs are tied at the length face and one plumb at the width face of the column. The column is supported with the help of props from both the faces. The distance between the plumb line and the column shuttering is measured. It is kept equal throughout the length of plumb line and this distance is adjusted by loosening or tightening the props from the opposite sides. In this way the column is erected in plumb line and for cross checking by measuring the size of column its cover, diagonal length ; then checking the sides are in right angle or no.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Balcony width provided on the site is 1.20m. As per bye law the widths 1.20m maximum.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for external wall plastering using cement mortar of 1:3“ Dimensions of typical part of wall=3.0*4.0m Plastering is done in two coats of 12mm thickness 1. surface area of wall =12 sq.m 2.Quantity of cement mortar (1:3)=12*(0.012*2) =0.288 cu.m Add 5o% of total volumefor voids and10%for uneveness =0.288+0.288*0.60. = 0.4608 cu.m 3. Quantity of cement =0.4608/1+3 =0.1152 cu.m =0.1152/0.035=3bags 4. Quantity of sand=0.1152*3=0.3456 cu.m. “Rate Analysis for external wall plastering using cement mortar of 1:3” (Considering local rates of material) 1. Cost of cement=3*250=750/-………..(250/- per bag) 2. Cost of sand=0.3456*1600=553/-…………(1600/- per cu.m) 3.Labour charges=680/- 4. Total cost= 1983/- 8.10% profit of total cost for the contractor=198.3/- 9. Total cost=2181.3/-
Result of RATE ANALYSIS ( Rs per Unit ) 182/-
Todays BUZZ Word 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? Yes
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: prasadkharat@ymail.com
Subject: 13531-07

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Prasad Ramachandra
Exam No. 13531
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to test cement ,to calculate sand corse and fine agg.in brass
Details of how you Planned & Executed the allotted work we insert our hand in hand bag and check weather it is lump free or not. we thrown hand full of cement in to water and check weather it is flotting or not. by measuring lenth ,breadth,and depth we calculate agg. in brass
Details of the Construction Procedure / Activity / Technology learned today main beam and lateral beam- main beams are provided in short span and lateral beams are provided in long span
Details of the Construction Materials learned today internal finishes-granite tiles for kitchen katta vitrifide tiles for better apperance in flooring
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of portland pozzolana cement wich consist of pozzolanic material emits less heat andgives higher strenth than ordinary portland cement
Details of the Construction / Engineering Drawings observed today obsertvation of second floor plan- 3 bhk flats facing road side and 2 bhk flats are at rear side
Details of the Bye Laws referred today height of building is depends on width of road- for 8m.wide road 12m. height is permissible
Details of any Managerial Skill learned today co-operative and intelligent
RATE ANALYSIS (Detailed Stepwise Calculations required) double coat plaster(external) assume 10sq.m, area thk.of plaster = 20mm. = 0.02m. total volume =0.2 cu.m. add 50% for dry volume no of bags of cement =(0.2*1.5)/(1+4) =0.060 cu.m. =0.060/0.035 =1.71 =2 bags sand= 0.060*4 =0.240 cu.m. amount =0.240*1060 Rs.per cu.m. =254.40 Rs. Labour =450Rs. for double coat total =444.6+254.40+450 =1149+15% contractors profit =1149+172.35 =1321.35Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1321.35Rs.per 10 sq.m.wall area
Todays BUZZ Word billing department- it is department of consruction site in wich all the details of perchacing of contruction material is done
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-07

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) yadav hrisheekesh deepak
Exam No. 10885
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of centring plates using spans supported on steel props. Checking their levels,and height from floor level to theab bottom.
Details of how you Planned & Executed the allotted work Firstly we checked the dimensions of room over which the plates were being placed the height of slab bottom from floor level. Then we observed the placing of plates over the spans which were supported using the steel props. We checked the level of slab by placing three wooden blocks of same thickness in line dori and then kept the line dori over the face of blocks and checked whether all the blocks are in the same level or no and instructed the workers to adjust the props either by raising or lowering them at the required point.
Details of the Construction Procedure / Activity / Technology learned today Checking plumb line of the column Two plumbs are tied at the length face and one plumb at the width face of the column. The column is supported with the help of props from both the faces. The distance between the plumb line and the column shuttering is measured. It is kept equal throughout the length of plumb line and this distance is adjusted by loosening or tightening the props from the opposite sides. In this way the column is erected in plumb line and for cross checking by measuring the size of column its cover, diagonal length ; then checking the sides are in right angle or no.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Balcony width provided on the site is 1.20m. As per bye law the widths 1.20m maximum.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for external wall plastering using cement mortar of 1:3“ Dimensions of typical part of wall=3.0*4.0m Plastering is done in two coats of 12mm thickness 1. surface area of wall =12 sq.m 2.Quantity of cement mortar (1:3)=12*(0.012*2) =0.288 cu.m Add 5o% of total volumefor voids and10%for uneveness =0.288+0.288*0.60. = 0.4608 cu.m 3. Quantity of cement =0.4608/1+3 =0.1152 cu.m =0.1152/0.035=3bags 4. Quantity of sand=0.1152*3=0.3456 cu.m. “Rate Analysis for external wall plastering using cement mortar of 1:3” (Considering local rates of material) 1. Cost of cement=3*250=750/-………..(250/- per bag) 2. Cost of sand=0.3456*1600=553/-…………(1600/- per cu.m) 3.Labour charges=680/- 4. Total cost= 1983/- 8.10% profit of total cost for the contractor=198.3/- 9. Total cost=2181.3/-
Result of RATE ANALYSIS ( Rs per Unit ) 182/-
Todays BUZZ Word 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-07

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kolekar Shyam Suryakant
Exam No. 13533
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to test cement ,to calculate sand corse and fine agg.in brass
Details of how you Planned & Executed the allotted work we insert our hand in hand bag and check weather it is lump free or not. we thrown hand full of cement in to water and check weather it is flotting or not. by measuring lenth ,breadth,and depth we calculate agg. in brass
Details of the Construction Procedure / Activity / Technology learned today main beam and lateral beam- main beams are provided in short span and lateral beams are provided in long span
Details of the Construction Materials learned today internal finishes-granite tiles for kitchen katta vitrifide tiles for better apperance in flooring
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of portland pozzolana cement wich consist of pozzolanic material emits less heat andgives higher strenth than ordinary portland cement
Details of the Construction / Engineering Drawings observed today obsertvation of second floor plan- 3 bhk flats facing road side and 2 bhk flats are at rear side
Details of the Bye Laws referred today height of building is depends on width of road- for 8m.wide road 12m. height is permissible
Details of any Managerial Skill learned today co-operative and intelligent
RATE ANALYSIS (Detailed Stepwise Calculations required) double coat plaster(external) assume 10sq.m, area thk.of plaster = 20mm. = 0.02m. total volume =0.2 cu.m. add 50% for dry volume no of bags of cement =(0.2*1.5)/(1+4) =0.060 cu.m. =0.060/0.035 =1.71 =2 bags sand= 0.060*4 =0.240 cu.m. amount =0.240*1060 Rs.per cu.m. =254.40 Rs. Labour =450Rs. for double coat total =444.6+254.40+450 =1149+15% contractors profit =1149+172.35 =1321.35Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1321.35Rs.per 10 sq.m.wall area
Todays BUZZ Word billing department- it is department of consruction site in wich all the details of perchacing of contruction material is done
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-07

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) fulari sujata shankar
Exam No. 13559
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 10.00am
Site Leaving Time (HH:MM am/pm) 5.30pm
Details of the Work Allotted to you today by the Site In-Charge 1) To check the work of plumbing. 2) The materials that came on the site are to be checked as per the check list. 3) The work of water-proofing to be done by the labours. .
Details of how you Planned & Executed the allotted work Planning was done in foll. manner:- 1) We were divided in three groups. 2) We planned to do the work each part. - First group for an hour had gone to check the plumbing work. - Second had gone for water-proofing work - Than third group checked the materials that was unloaded during site. 3) We all than changed the duty so that indivisual so that one can experience all the duties. .
Details of the Construction Procedure / Activity / Technology learned today - To get work done by the labours. - To do the plumbing work as per design drawing given to the site. - To prepare the work before plumbing. .
Details of the Construction Materials learned today - PVC pipes of various diameters. - Bends of pipes. - Elbows of pipes. - For Water-proofing we used \"DR.FIXIT\". .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today mortar fallen during plastering work if collected on plastic sheet then reused within 30 minitus , it will save the material & there by saving natural materiel. .
Details of the Construction / Engineering Drawings observed today - Plumbing drawing. - Floor plans . - Parking plan. .
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment. .
Details of any Managerial Skill learned today - Handling the labours - Checking materials as per the check-list. \'
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012= 0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012= 0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)= 0.0195 cement=0.0195/1+3= 0.00487m3 no of bag=0.005/0.035=0.142= 0.15bag cost=0.015*260= Rs39 Sand=0.005*3= 0.015m3. cost=0.015*1125=16.87 material cost=39.0+16.875= Rs55.87 labour=mason1= Rs250 labour= Rs140 total= Rs890 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13 ( Rs per Unit ): Rs980.58 Result of RATE ANALYSIS ( Rs per Unit ): Rs.980.58 .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: bsalman75@yahoo.com
Subject: 10888-07

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) baig salman samad
Exam No. 10888
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of centring plates using spans supported on steel props. Checking their levels,and height from floor level to the slab bottom.
Details of how you Planned & Executed the allotted work Firstly we checked the dimensions of room over which the plates were being placed the height of slab bottom from floor level. Then we observed the placing of plates over the spans which were supported using the steel props. We checked the level of slab by placing three wooden blocks of same thickness in line dori and then kept the line dori over the face of blocks and checked whether all the blocks are in the same level or no and instructed the workers to adjust the props either by raising or lowering them at the required point.
Details of the Construction Procedure / Activity / Technology learned today Checking plumb line of the column Two plumbs are tied at the length face and one plumb at the width face of the column. The column is supported with the help of props from both the faces. The distance between the plumb line and the column shuttering is measured. It is kept equal throughout the length of plumb line and this distance is adjusted by loosening or tightening the props from the opposite sides. In this way the column is erected in plumb line and for cross checking by measuring the size of column its cover, diagonal length ; then checking the sides are in right angle or no.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Balcony width provided on the site is 1.20m. As per bye law the widths 1.20m maximum.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for external wall plastering using cement mortar of 1:3“ Dimensions of typical part of wall=3.0*4.0m Plastering is done in two coats of 12mm thickness 1. surface area of wall =12 sq.m 2.Quantity of cement mortar (1:3)=12*(0.012*2) =0.288 cu.m Add 5o% of total volumefor voids and10%for uneveness =0.288+0.288*0.60. = 0.4608 cu.m 3. Quantity of cement =0.4608/1+3 =0.1152 cu.m =0.1152/0.035=3bags 4. Quantity of sand=0.1152*3=0.3456 cu.m. “Rate Analysis for external wall plastering using cement mortar of 1:3” (Considering local rates of material) 1. Cost of cement=3*250=750/-………..(250/- per bag) 2. Cost of sand=0.3456*1600=553/-…………(1600/- per cu.m) 3.Labour charges=680/- 4. Total cost= 1983/- 8.10% profit of total cost for the contractor=198.3/- 9. Total cost=2181.3/-
Result of RATE ANALYSIS ( Rs per Unit ) 182/-
Todays BUZZ Word 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: vishalsapakal@gmail.com
Subject: 10882-07

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) sapakal vishal manohar
Exam No. 10882
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of centring plates using spans supported on steel props. Checking their levels,and height from floor level to the slab bottom.
Details of how you Planned & Executed the allotted work Firstly we checked the dimensions of room over which the plates were being placed the height of slab bottom from floor level. Then we observed the placing of plates over the spans which were supported using the steel props. We checked the level of slab by placing three wooden blocks of same thickness in line dori and then kept the line dori over the face of blocks and checked whether all the blocks are in the same level or no and instructed the workers to adjust the props either by raising or lowering them at the required point.
Details of the Construction Procedure / Activity / Technology learned today Checking plumb line of the column Two plumbs are tied at the length face and one plumb at the width face of the column. The column is supported with the help of props from both the faces. The distance between the plumb line and the column shuttering is measured. It is kept equal throughout the length of plumb line and this distance is adjusted by loosening or tightening the props from the opposite sides. In this way the column is erected in plumb line and for cross checking by measuring the size of column its cover, diagonal length ; then checking the sides are in right angle or no.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Balcony width provided on the site is 1.20m. As per bye law the widths 1.20m maximum.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for external wall plastering using cement mortar of 1:3“ Dimensions of typical part of wall=3.0*4.0m Plastering is done in two coats of 12mm thickness 1. surface area of wall =12 sq.m 2.Quantity of cement mortar (1:3)=12*(0.012*2) =0.288 cu.m Add 5o% of total volumefor voids and10%for uneveness =0.288+0.288*0.60. = 0.4608 cu.m 3. Quantity of cement =0.4608/1+3 =0.1152 cu.m =0.1152/0.035=3bags 4. Quantity of sand=0.1152*3=0.3456 cu.m. “Rate Analysis for external wall plastering using cement mortar of 1:3” (Considering local rates of material) 1. Cost of cement=3*250=750/-………..(250/- per bag) 2. Cost of sand=0.3456*1600=553/-…………(1600/- per cu.m) 3.Labour charges=680/- 4. Total cost= 1983/- 8.10% profit of total cost for the contractor=198.3/- 9. Total cost=2181.3/-
Result of RATE ANALYSIS ( Rs per Unit ) 182/-
Todays BUZZ Word 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-07

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) babar moreshwar mahipati
Exam No. 10873
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of centring plates using spans supported on steel props. Checking their levels,and height from floor level to the slab bottom.
Details of how you Planned & Executed the allotted work Firstly we checked the dimensions of room over which the plates were being placed the height of slab bottom from floor level. Then we observed the placing of plates over the spans which were supported using the steel props. We checked the level of slab by placing three wooden blocks of same thickness in line dori and then kept the line dori over the face of blocks and checked whether all the blocks are in the same level or no and instructed the workers to adjust the props either by raising or lowering them at the required point.
Details of the Construction Procedure / Activity / Technology learned today Checking plumb line of the column Two plumbs are tied at the length face and one plumb at the width face of the column. The column is supported with the help of props from both the faces. The distance between the plumb line and the column shuttering is measured. It is kept equal throughout the length of plumb line and this distance is adjusted by loosening or tightening the props from the opposite sides. In this way the column is erected in plumb line and for cross checking by measuring the size of column its cover, diagonal length ; then checking the sides are in right angle or no.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Balcony width provided on the site is 1.20m. As per bye law the widths 1.20m maximum.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for external wall plastering using cement mortar of 1:3“ Dimensions of typical part of wall=3.0*4.0m Plastering is done in two coats of 12mm thickness 1. surface area of wall =12 sq.m 2.Quantity of cement mortar (1:3)=12*(0.012*2) =0.288 cu.m Add 5o% of total volumefor voids and10%for uneveness =0.288+0.288*0.60. = 0.4608 cu.m 3. Quantity of cement =0.4608/1+3 =0.1152 cu.m =0.1152/0.035=3bags 4. Quantity of sand=0.1152*3=0.3456 cu.m. “Rate Analysis for external wall plastering using cement mortar of 1:3” (Considering local rates of material) 1. Cost of cement=3*250=750/-………..(250/- per bag) 2. Cost of sand=0.3456*1600=553/-…………(1600/- per cu.m) 3.Labour charges=680/- 4. Total cost= 1983/- 8.10% profit of total cost for the contractor=198.3/- 9. Total cost=2181.3/-
Result of RATE ANALYSIS ( Rs per Unit ) 182/-
Todays BUZZ Word 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523-07

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Builders and Developers, Near Jay-prabha studio,Kolhapur
Students Name (Surname_First Name_Middle Name) devkar vikram dilip
Exam No. 13523
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge To visit and study the construction work going on of Farm house at Panhala as recommended by Paras Oswal sir.
Details of how you Planned & Executed the allotted work We went to Panhala in group. Their we met the site incharge he showed us the plans of farm house and gave us. Then we studied the plans and saw the site and checked that all the construction process going on as per plan.
Details of the Construction Procedure / Activity / Technology learned today We saw the process of concreting of roofing slab, filling work, the foundation work,plinth work going on.We saw the masonry work construction.Spring bar in roofing slab,Footing work,steel grid used for footing,
Details of the Construction Materials learned today 1. Use of waterproofing chemical while concreteing algae proof 200 ml. 2. Different types of bricks. 1. Hollow Bricks for temporary structure. 2. Wire cut Bricks for attractive elevation and good strength. 3. Cement 43 grade Bagalkot supreme.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited
Details of the Construction / Engineering Drawings observed today 1. Plan of farm-house of 900 sq.ft 1000sq.ft and 1200 sq.ft. 2. Contour plan.
Details of the Bye Laws referred today 1.Maximum cantilever porch length 4.00m according to bye laws has been followed. 2.Stair case is designed as per bye laws.
Details of any Managerial Skill learned today 1. The site incharge inspected saw the concreteing process going on. 2. The site incharge checked the propotions of different materials used. 3. The site incharge kept a proper record of total quantity
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for EXTERNAL PLASTER. Considering 25 mm thick plaster in two coats. Mortar = 1:4. Cement=0.22 Cost of Cement= 0.22*265= Rs.58.30. Sand=0.025. Cost of sand= 0.025*2120= Rs.53. Labour= Rs.65. Total Cost= 58.30+53+65= Rs.176.30. For each sq.m add Rs.15 extra for water proofing. Total cost= 176.30+15= Rs.191.30. Considering 10% profit= 19.13. Total cost of external plaster= 191.13+19.13= Rs.210.43. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.210.43. per sq.m
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SALIM MOMIN PH NO.9225816079.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-07

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) yadav hrisheekesh deepak
Exam No. 10885
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of centring plates using spans supported on steel props. Checking their levels,and height from floor level to the slab bottom.
Details of how you Planned & Executed the allotted work Firstly we checked the dimensions of room over which the plates were being placed the height of slab bottom from floor level. Then we observed the placing of plates over the spans which were supported using the steel props. We checked the level of slab by placing three wooden blocks of same thickness in line dori and then kept the line dori over the face of blocks and checked whether all the blocks are in the same level or no and instructed the workers to adjust the props either by raising or lowering them at the required point.
Details of the Construction Procedure / Activity / Technology learned today Checking plumb line of the column Two plumbs are tied at the length face and one plumb at the width face of the column. The column is supported with the help of props from both the faces. The distance between the plumb line and the column shuttering is measured. It is kept equal throughout the length of plumb line and this distance is adjusted by loosening or tightening the props from the opposite sides. In this way the column is erected in plumb line and for cross checking by measuring the size of column its cover, diagonal length ; then checking the sides are in right angle or no.
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Balcony width provided on the site is 1.20m. As per bye law the widths 1.20m maximum.
Details of any Managerial Skill learned today Efficient adjustment in keeping the workers busy in work during the shortage of maerial at the site and delay in the supply of material by the distributor.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for external wall plastering using cement mortar of 1:3“ Dimensions of typical part of wall=3.0*4.0m Plastering is done in two coats of 12mm thickness 1. surface area of wall =12 sq.m 2.Quantity of cement mortar (1:3)=12*(0.012*2) =0.288 cu.m Add 5o% of total volumefor voids and10%for uneveness =0.288+0.288*0.60. = 0.4608 cu.m 3. Quantity of cement =0.4608/1+3 =0.1152 cu.m =0.1152/0.035=3bags 4. Quantity of sand=0.1152*3=0.3456 cu.m. “Rate Analysis for external wall plastering using cement mortar of 1:3” (Considering local rates of material) 1. Cost of cement=3*250=750/-………..(250/- per bag) 2. Cost of sand=0.3456*1600=553/-…………(1600/- per cu.m) 3.Labour charges=680/- 4. Total cost= 1983/- 8.10% profit of total cost for the contractor=198.3/- 9. Total cost=2181.3/-
Result of RATE ANALYSIS ( Rs per Unit ) 182/-
Todays BUZZ Word 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-07

Company Name Deshmukh Developers
Project Name & Site Address Deshmukh Developments,Pratibha Nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) B
Exam No. 13556
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today the site incharge to give us the work that, 1) To check whether steel reinforcement bars are binded properly & placed in correct position 2) And also to observe slab body whether it is one way,two way, or cantiliver
Details of how you Planned & Executed the allotted work Firstly we are go to that floor , 1) To study beam and slab details drawing sheet carefully 2) Our quarries ask to supervisor Sujitkumar, he is done it\'s work fantastically 3) To study about diameter of bars, diameter & length of stirrups which are used in beam
Details of the Construction Procedure / Activity / Technology learned today Construction Procedure : 1) In beam different diameter of top bars, bottom bars, straight or cutailment i.e extra bottom are provided 2) And also extra top i.e E.S end support, C.S central support bars are provided 3) Stirrups are provided at a distance of 150mm from center, 200mm from end support 4) Concrete rounded cover is provided for maintaining stabilization in beams 5) In beam making work stirrups are binded with into bars which is placed on steel chair. Chair means two steel sections are provided
Details of the Construction Materials learned today Construction Material : 1) Different diameter steel bars such as 8mm, 10mm, 12mm, 16mm,24mm etc 2) Only mild steel stirrups @ 150mm,@200mm are provided 3) Theya is a equipment which is attached to column for making different sizes of stirrups .Measurement is given on it 4) For AB large stirrups -4.5\', small stirrups-22\" and for hide beam size 1\'5\" stirrups are used 5) Pana, hook, binding wire
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environment Caring Technology : Cutting sections of steel bars are again used in slab or beam casting work. To avoid wastage of steel reinforcement
Details of the Construction / Engineering Drawings observed today Details of Engg. Drawing : Today we are observe beam & slab detail drawing sheet 1) To observe various number of beams whether they are continous beam, hide beam, cantilever beam 2) Four different type of slabs are provided in drawing, S1 - Cantilever S2 - TwoWay S3 - One way S4 - One way 3) To observe bending movement of distribution bars etc.
Details of the Bye Laws referred today Today we are study Bye Laws for : 1) To study the diameter of stirrups 2) Distance between two stirrups
Details of any Managerial Skill learned today Managerial skill : Steel Reinforcement bars are placed in a large space near the compound i.e do not placed in a moveable way of workers
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS OF EXTERNAL PLASTER : 12MM THICK PLASTER (1:3) ASSUME 1M2 SURFACE AREA VOLUME OF MORTER FOR 12MM PLASTER = (0.012* 30)+0.012 = 0.0156 M3 ADD 20% FOR DRY VOLUME = 0.0156+ (0.0156*25)/100 = 0.0195 M3 CEMENT = 0.0195 /(1+5) = 0.00487M3 = 0.005 M3 NUMBER OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAG COST = 0.15 * 260 = 39 RS SAND = 0.005 * 3 = 0.015 M3 COST = 0.015 *1125 = 16.87 RS MATERIAL COST = 39 + 16.87 = 55.87 RS LABOUR = 390 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 475.87 RS WATER 1 1/2% = (1.5* 475.87)/100 = 7.13 RS CONTRACTOR PROFIT = (10*475.87) = 47.85 RS TOTAL COST = 530 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530 RS
Todays BUZZ Word The Buzz Word of the day is \"Billing Department\" When brick comes the it is reported to the person go has delivered to it by sending a delivery cheat & the payment is done accordingly & the various care of bill taken by the person appointed. He take care of all bills coming at the site & keeps the of it near him & another of the person delivered the material.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Abhijit Bhosale Mob No. 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521-07

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Builders and Developers, Near Jay-prabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) bagmare dinesh shriram
Exam No. 13521
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge To visit and study the construction work going on of Farm house at Panhala as recommended by Paras Oswal sir.
Details of how you Planned & Executed the allotted work We went to Panhala in group. Their we met the site incharge he showed us the plans of farm house and gave us. Then we studied the plans and saw the site and checked that all the construction process going on as per plan.
Details of the Construction Procedure / Activity / Technology learned today We saw the process of concreting of roofing slab, filling work, the foundation work,plinth work going on.We saw the masonry work construction.Spring bar in roofing slab,Footing work,steel grid used for footing,
Details of the Construction Materials learned today 1. Use of waterproofing chemical while concreteing algae proof 200 ml. 2. Different types of bricks. 1. Hollow Bricks for temporary structure. 2. Wire cut Bricks for attractive elevation and good strength. 3. Cement 43 grade Bagalkot supreme.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited
Details of the Construction / Engineering Drawings observed today 1. Plan of farm-house of 900 sq.ft 1000sq.ft and 1200 sq.ft. 2. Contour plan.
Details of the Bye Laws referred today 1.Maximum cantilever porch length 4.00m according to bye laws has been followed. 2.Stair case is designed as per bye laws.
Details of any Managerial Skill learned today 1. The site incharge inspected saw the concreteing process going on. 2. The site incharge checked the propotions of different materials used. 3. The site incharge kept a proper record of total quantity
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for EXTERNAL PLASTER. Considering 25 mm thick plaster in two coats. Mortar = 1:4. Cement=0.22 Cost of Cement= 0.22*265= Rs.58.30. Sand=0.025. Cost of sand= 0.025*2120= Rs.53. Labour= Rs.65. Total Cost= 58.30+53+65= Rs.176.30. For each sq.m add Rs.15 extra for water proofing. Total cost= 176.30+15= Rs.191.30. Considering 10% profit= 19.13. Total cost of external plaster= 191.13+19.13= Rs.210.43. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.210.43. per sq.m
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SALIM MOMIN PH NO.9225816079.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: shindeamol5255@yahoo.in
Subject: 13546-07

Company Name Deshmukh Developers
Project Name & Site Address Goldenshelter
Students Name (Surname_First Name_Middle Name) Shinde Amol Jagannath
Exam No. 13546
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1) Finding out the requirement of M-15 grade concrete for slab of proposed building. 2) Calculate the steel reinforce required for slab. .
Details of how you Planned & Executed the allotted work First we divide our group in to two sub groups out of it one group worked on , 1)Calculating quantity of concrete required a)first find the all inner dimensions of slab from detailed structural drawing. b)Multiply with thickness of slab & find gross quantity. c)Add all gross quantity of slab calculated above. d) Separately calculate quantity of concrete laying above beam excluding depth of beam. e)Add all above quantity of slab & beam. Second group worked on 1)calculation of steel reinforcement:- a)Prepare bar bending schedule table b)Find length of bar on both way for two way slab & one length for one way slab. c)Find length of curtail bar whichever provided . d)Add total length as per diameter of bar . e)note down all values in table systematically. .
Details of the Construction Procedure / Activity / Technology learned today 1) Reading of reinforce drawing on site. 2) Placing of steel for slab & for beam. 3)Removal of form work. 4)Precautions taken during removal of form work. 5)Arrangement for height of supports of form work. .
Details of the Construction Materials learned today Quality of wood used for form work. M-15 grade of concrete. Admixtures used in concrete making. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel supports used for form work are more eco friendly compare to wood works. .
Details of the Construction / Engineering Drawings observed today 1)reinforce detailed drawing for slab & beam. 2)Municiple drawing .
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment. .
Details of any Managerial Skill learned today How to manage the labour force & time ,quality of concreting work ,steel distribution economy. .
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012=0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012=0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 . cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=890Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs ( Rs per Unit ): 980.58Rs Result of RATE ANALYSIS ( Rs per Unit ): Rs.980.58
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word Todays BUZZ Word: Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Bhosle
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-07

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) JAGADALE ASHVANI RAMRAO
Exam No. 13530
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the reinforcement done with help of steel drawings.
Details of how you Planned & Executed the allotted work we directly go to the fifth floor where the steel work is almost completed.as per the location of the slabs in the drawings, we check that weather bars of given sizes and number of bars are placed in their exact location or not.
Details of the Construction Procedure / Activity / Technology learned today we learned about how the bars are provided in beams means top,bottom, extra top, extra bottom and why they are provided. when the joining of column is done one above the other then how much the lap length is provided.stirrups are provided to join the bars of the beams and spacing is closer near the support and wider at the central portion. extra bars are provided where the shear force is more. in case of slabs bars are bent at the length L/4 to transfer the load on the beams then from beams to column.
Details of the Construction Materials learned today NONE
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR EXTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 50 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 135.78 RS WATER= 1.5 % = 2.03 RS CONTRACTOR PROFIT = 10% = 13.57 RS TOTAL COST = 151.38 RS
Result of RATE ANALYSIS ( Rs per Unit ) 151.38 RS
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGULE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-07

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) PATIL ADITYA PANDURANG
Exam No. 13538
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the reinforcement done with help of steel drawings.
Details of how you Planned & Executed the allotted work we directly go to the fifth floor where the steel work is almost completed.as per the location of the slabs in the drawings, we check that weather bars of given sizes and number of bars are placed in their exact location or not.
Details of the Construction Procedure / Activity / Technology learned today we learned about how the bars are provided in beams means top,bottom, extra top, extra bottom and why they are provided. when the joining of column is done one above the other then how much the lap length is provided.stirrups are provided to join the bars of the beams and spacing is closer near the support and wider at the central portion. extra bars are provided where the shear force is more. in case of slabs bars are bent at the length L/4 to transfer the load on the beams then from beams to column.
Details of the Construction Materials learned today tor and mild steel bars ,cover blocks of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR EXTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 50 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 135.78 RS WATER= 1.5 % = 2.03 RS CONTRACTOR PROFIT = 10% = 13.57 RS TOTAL COST = 151.38 RS
Result of RATE ANALYSIS ( Rs per Unit ) 151.38 RS
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGULE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-07

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) MANGAONKAR MANOJ DATTATRAY
Exam No. 13536
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the reinforcement done with help of steel drawings.
Details of how you Planned & Executed the allotted work we directly go to the fifth floor where the steel work is almost completed.as per the location of the slabs in the drawings, we check that weather bars of given sizes and number of bars are placed in their exact location or not.
Details of the Construction Procedure / Activity / Technology learned today we learned about how the bars are provided in beams means top,bottom, extra top, extra bottom and why they are provided. when the joining of column is done one above the other then how much the lap length is provided.stirrups are provided to join the bars of the beams and spacing is closer near the support and wider at the central portion. extra bars are provided where the shear force is more. in case of slabs bars are bent at the length L/4 to transfer the load on the beams then from beams to column.
Details of the Construction Materials learned today tor and mild steel bars ,cover blocks of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR EXTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 50 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 135.78 RS WATER= 1.5 % = 2.03 RS CONTRACTOR PROFIT = 10% = 13.57 RS TOTAL COST = 151.38 RS
Result of RATE ANALYSIS ( Rs per Unit ) 151.38 RS
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGULE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-07

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the reinforcement done with help of steel drawings.
Details of how you Planned & Executed the allotted work we directly go to the fifth floor where the steel work is almost completed.as per the location of the slabs in the drawings, we check that weather bars of given sizes and number of bars are placed in their exact location or not.
Details of the Construction Procedure / Activity / Technology learned today we learned about how the bars are provided in beams means top,bottom, extra top, extra bottom and why they are provided. when the joining of column is done one above the other then how much the lap length is provided.stirrups are provided to join the bars of the beams and spacing is closer near the support and wider at the central portion. extra bars are provided where the shear force is more. in case of slabs bars are bent at the length L/4 to transfer the load on the beams then from beams to column.
Details of the Construction Materials learned today tor and mild steel bars ,cover blocks of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR EXTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 50 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 135.78 RS WATER= 1.5 % = 2.03 RS CONTRACTOR PROFIT = 10% = 13.57 RS TOTAL COST = 151.38 RS
Result of RATE ANALYSIS ( Rs per Unit ) 151.38 RS
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. CHOUGULE 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-07

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bhoite Vishal Rajaram
Exam No. 13555
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) To check the work of plumbing. 2) The materials that came on the site are to be checked as per the check list. 3) The work of water-proofing to be done by the labours.
Details of how you Planned & Executed the allotted work Planning was done in foll. manner:- 1) We were divided in three groups. 2) We planned to do the work each part. - First group for an hour had gone to check the plumbing work. - Second had gone for water-proofing work - Than third group checked the materials that was unloaded during site. 3) We all than changed the duty so that indivisual so that one can experience all the duties.
Details of the Construction Procedure / Activity / Technology learned today - To get work done by the labours. - To do the plumbing work as per design drawing given to the site. - To prepare the work before plumbing.
Details of the Construction Materials learned today - PVC pipes of various diameters. - Bends of pipes. - Elbows of pipes. - For Water-proofing we used \"DR.FIXIT\".
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plumbing drawing. - Floor plans . - Parking plan.
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment.
Details of any Managerial Skill learned today - Handling the labours - Checking materials as per the check-list.
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012= 0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012= 0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)= 0.0195 cement=0.0195/1+3= 0.00487m3 no of bag=0.005/0.035=0.142= 0.15bag cost=0.015*260= Rs39 Sand=0.005*3= 0.015m3. cost=0.015*1125=16.87 material cost=39.0+16.875= Rs55.87 labour=mason1= Rs250 labour= Rs140 total= Rs890 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13 ( Rs per Unit ): Rs980.58
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-07

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bauchakar Deepak Yuvraj
Exam No. 13554
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) To check the work of plumbing. 2) The materials that came on the site are to be checked as per the check list. 3) The work of water-proofing to be done by the labours.
Details of how you Planned & Executed the allotted work Planning was done in foll. manner:- 1) We were divided in three groups. 2) We planned to do the work each part. - First group for an hour had gone to check the plumbing work. - Second had gone for water-proofing work - Than third group checked the materials that was unloaded during site. 3) We all than changed the duty so that indivisual so that one can experience all the duties.
Details of the Construction Procedure / Activity / Technology learned today - To get work done by the labours. - To do the plumbing work as per design drawing given to the site. - To prepare the work before plumbing.
Details of the Construction Materials learned today - PVC pipes of various diameters. - Bends of pipes. - Elbows of pipes. - For Water-proofing we used \"DR.FIXIT\".
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plumbing drawing. - Floor plans . - Parking plan.
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment.
Details of any Managerial Skill learned today - Handling the labours - Checking materials as per the check-list.
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012= 0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012= 0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)= 0.0195 cement=0.0195/1+3= 0.00487m3 no of bag=0.005/0.035=0.142= 0.15bag cost=0.015*260= Rs39 Sand=0.005*3= 0.015m3. cost=0.015*1125=16.87 material cost=39.0+16.875= Rs55.87 labour=mason1= Rs250 labour= Rs140 total= Rs890 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13 ( Rs per Unit ): Rs980.58
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-07

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Suyvanshi patil Pratiksinh Vilas
Exam No. 13549
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) To check the work of plumbing. 2) The materials that came on the site are to be checked as per the check list. 3) The work of water-proofing to be done by the labours.
Details of how you Planned & Executed the allotted work Planning was done in foll. manner:- 1) We were divided in three groups. 2) We planned to do the work each part. - First group for an hour had gone to check the plumbing work. - Second had gone for water-proofing work - Than third group checked the materials that was unloaded during site. 3) We all than changed the duty so that indivisual so that one can experience all the duties.
Details of the Construction Procedure / Activity / Technology learned today - To get work done by the labours. - To do the plumbing work as per design drawing given to the site. - To prepare the work before plumbing.
Details of the Construction Materials learned today - PVC pipes of various diameters. - Bends of pipes. - Elbows of pipes. - For Water-proofing we used \"DR.FIXIT\".
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plumbing drawing. - Floor plans . - Parking plan.
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment.
Details of any Managerial Skill learned today - Handling the labours - Checking materials as per the check-list.
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012= 0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012= 0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)= 0.0195 cement=0.0195/1+3= 0.00487m3 no of bag=0.005/0.035=0.142= 0.15bag cost=0.015*260= Rs39 Sand=0.005*3= 0.015m3. cost=0.015*1125=16.87 material cost=39.0+16.875= Rs55.87 labour=mason1= Rs250 labour= Rs140 total= Rs890 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13 ( Rs per Unit ): Rs980.58
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-07

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Sharad Shankarrao
Exam No. 10897
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To fill the cracks in the slab with the bonding agent . .
Details of how you Planned & Executed the allotted work first we took all the material which is required for it such as bonding agent,cement,pan,brush etc.on the spot where cracks were to be filled & we filled all cracks in the slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of preparing mix of bonding agent & cement then to apply over the cracks.firstly 1&1/2 kg cement is taken & then 1 liter of bonding agent is mixed in it & paste is prepared from it& then it is applied over the cracks. .
Details of the Construction Materials learned today today we learned about bonding agent details-acrylic polymer based bonding & water proof agent.it was of condura-conchem company.its volume was of 5 liter.for 5 liter cost was 1500/- .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today all the steel material ,nails props etc.should be placed properly to avoid injury. .
Details of the Construction / Engineering Drawings observed today today we observed drawing of column reinforcement & its position. .
Details of the Bye Laws referred today today we referred all the temporary construction which can be done from bye-laws. .
Details of any Managerial Skill learned today costumer which came to see the site should be given clear cut details of any item by manager or site incharge .
RATE ANALYSIS (Detailed Stepwise Calculations required) ITEM QTY. UNIT RATE AMOUNT Cement 0.25 Bags 260 65 Sand 0.04 M3 1150 46 Waterproofing Compound per M2 10 Plastermesh per M2 10 Total 126 Wastage 5% 6 Total 132 Scaffolding 15 Labour 78 Curing 5 Total 230 23% Tax Overhead and Profit 53 Total 288 Say 288/- per M2
Result of RATE ANALYSIS ( Rs per Unit ) 288/- per M2
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-07

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Abhishek Dadasaheb
Exam No. 10895
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To fill the cracks in the slab with the bonding agent . .
Details of how you Planned & Executed the allotted work first we took all the material which is required for it such as bonding agent,cement,pan,brush etc.on the spot where cracks were to be filled & we filled all cracks in the slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of preparing mix of bonding agent & cement then to apply over the cracks.firstly 1&1/2 kg cement is taken & then 1 liter of bonding agent is mixed in it & paste is prepared from it& then it is applied over the cracks. .
Details of the Construction Materials learned today today we learned about bonding agent details-acrylic polymer based bonding & water proof agent.it was of condura-conchem company.its volume was of 5 liter.for 5 liter cost was 1500/- .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today all the steel material ,nails props etc.should be placed properly to avoid injury. .
Details of the Construction / Engineering Drawings observed today today we observed drawing of column reinforcement & its position. .
Details of the Bye Laws referred today today we referred all the temporary construction which can be done from bye-laws. .
Details of any Managerial Skill learned today costumer which came to see the site should be given clear cut details of any item by manager or site incharge .
RATE ANALYSIS (Detailed Stepwise Calculations required) ITEM QTY. UNIT RATE AMOUNT Cement 0.25 Bags 260 65 Sand 0.04 M3 1150 46 Waterproofing Compound per M2 10 Plastermesh per M2 10 Total 126 Wastage 5% 6 Total 132 Scaffolding 15 Labour 78 Curing 5 Total 230 23% Tax Overhead and Profit 53 Total 288 Say 288/- per M2
Result of RATE ANALYSIS ( Rs per Unit ) 288/- per M2
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: ayyar.vignesh@gmail.com
Subject: 13553-07

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Ayyar Vignesh Gopal
Exam No. 13553
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) To check the work of plumbing. 2) The materials that came on the site are to be checked as per the check list. 3) The work of water-proofing to be done by the labours.
Details of how you Planned & Executed the allotted work Planning was done in foll. manner:- 1) We were divided in three groups. 2) We planned to do the work each part. - First group for an hour had gone to check the plumbing work. - Second had gone for water-proofing work - Than third group checked the materials that was unloaded during site. 3) We all than changed the duty so that indivisual so that one can experience all the duties.
Details of the Construction Procedure / Activity / Technology learned today - To get work done by the labours. - To do the plumbing work as per design drawing given to the site. - To prepare the work before plumbing.
Details of the Construction Materials learned today - PVC pipes of various diameters. - Bends of pipes. - Elbows of pipes. - For Water-proofing we used \"DR.FIXIT\".
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plumbing drawing. - Floor plans . - Parking plan.
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment.
Details of any Managerial Skill learned today - Handling the labours - Checking materials as per the check-list.
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012= 0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012= 0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)= 0.0195 cement=0.0195/1+3= 0.00487m3 no of bag=0.005/0.035=0.142= 0.15bag cost=0.015*260= Rs39 Sand=0.005*3= 0.015m3. cost=0.015*1125=16.87 material cost=39.0+16.875= Rs55.87 labour=mason1= Rs250 labour= Rs140 total= Rs890 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13 ( Rs per Unit ): Rs980.58
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Vivek randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: cool.sushant007@gmail.com
Subject: 10880-07

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil sushant digambar
Exam No. 10880
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the reinforcement done with help of steel drawings.
Details of how you Planned & Executed the allotted work we directly go to the fifth floor where the steel work is almost completed.as per the location of the slabs in the drawings, we check that weather bars of given sizes and number of bars are placed in their exact location or not.
Details of the Construction Procedure / Activity / Technology learned today we learned about how the bars are provided in beams means top,bottom, extra top, extra bottom and why they are provided. when the joining of column is done one above the other then how much the lap length is provided.stirrups are provided to join the bars of the beams and spacing is closer near the support and wider at the central portion. extra bars are provided where the shear force is more. in case of slabs bars are bent at the length L/4 to transfer the load on the beams then from beams to column.
Details of the Construction Materials learned today tor and mild steel bars ,cover blocks of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR EXTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 50 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 135.78 RS WATER= 1.5 % = 2.03 RS CONTRACTOR PROFIT = 10% = 13.57 RS TOTAL COST = 151.38 RS
Result of RATE ANALYSIS ( Rs per Unit ) 151.38 RS
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: shinde_shital7@yahoo.com
Subject: 10884-07

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL KARANDEMALA CIRCUITHOUSE KOLHAPUR
Students Name (Surname_First Name_Middle Name) SHINDE SHITAL VILASRAO
Exam No. 10884
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge TODAY WE ALLOTTED WORK BY SITE IN CHARGE IS OBSERVED THE BRICK WORK AND FORM WORK OF COLUMN.
Details of how you Planned & Executed the allotted work 1- FIRST WE GO AND OBSERVED THE BRICKWORK ALONG WITH SITE SUPERVISIOR.WE OBSERVED THAT FIRST THE BRICKWORK ARRANGE ACCORDING TO DIMENSION OF THE ROOM WHICH IS CALLED LINING. 2-WE OBSERVED FORMATION OF FORMWORK OF COLUMN. 3-FIRST THREE SIDE OF FORMWORK WAS MADE THEN IT WAS RAISED AROUND THE COLUMN. FORTH OF PART IS ATTACHED TO IT.PLUMBBOB WAS USED TO CHECK THE IRRECTNESS OF THE FORMWORK BY THE SUPERVISOR.
Details of the Construction Procedure / Activity / Technology learned today WE LEARNED THAT FOR LAYING THE BRICKWORK FIRST ALL THE LINING ARE DONE ACCORDING TO ROOM DIMENSION .CURING OF THE BRICK ARE DONE BEFORE PLACING THEM. FRAME OF THE DOOR IS RAISED IN THE BEGINNING TO ENSURE CORRECT BONDING.
Details of the Construction Materials learned today WE LEARNED THAT PASTE OF LATICRETE ARE USED TO STICK MARBLE, GRANITE TO THE WALL.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today USE OF STRAIGHT CUT BAR OVER U-CUT BAR .WHICH SAVE THE WASTAGE OF STEEL AND SAVING THE NATURAL MINERAL OF STEEL.
Details of the Construction / Engineering Drawings observed today WE OBSERVED DRAWING OF COLUMN FOR GROUND FLOOR. WE OBSERVED DRAWING OF WHOLE BUILDING.
Details of the Bye Laws referred today BYE LAWS FOR HEIGHT OF PARAPET=1.2m HEIGHT OF DOOR =2.1m
Details of any Managerial Skill learned today CONVEY WORK DONE TO SUPERVISOR INSTEAD OF TALKING TO LABOUR.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PLASTER FOR 1 BRASS 10\'*10\'=(3048*3048)sq.mm =929sq.m **CEMENT FOR 1 BAG- FOR 1 BRASS COST=260Rs **SAND =18*15=270Rs LABOUR COST FOR sq.FOOT=30Rs FOR 1 sq.foot=30*10=300Rs FOR 1 BRASS=830Rs 1sq.m=90Rs
Result of RATE ANALYSIS ( Rs per Unit ) 90Rs
Todays BUZZ Word FOR ANY MATERIAL WHEN COME IT IS REPORTED TO WHO HAD DELIVERED TO IT BY SENDING A DELIVERY CHEAT AND THE PAYMENT IS DONE ACCORDINALY .THE VARIOUS CARE OF BILLIS TAKEN BY THE PERSON APPOINTED. HE TAKE CARE OF ALL BILLS COMING AT THE SITE &KEEP THE COPY OF IT NEAR HIM AND ANOTHER COPY OF THE PERSIN WE DELIVERED THE MATERIAL.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. KETAN CHARAPALE Mo.No.9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-07

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) misal swapnil shivaji
Exam No. 10877
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the reinforcement done with help of steel drawings.
Details of how you Planned & Executed the allotted work we directly go to the fifth floor where the steel work is almost completed.as per the location of the slabs in the drawings, we check that weather bars of given sizes and number of bars are placed in their exact location or not.
Details of the Construction Procedure / Activity / Technology learned today we learned about how the bars are provided in beams means top,bottom, extra top, extra bottom and why they are provided. when the joining of column is done one above the other then how much the lap length is provided.stirrups are provided to join the bars of the beams and spacing is closer near the support and wider at the central portion. extra bars are provided where the shear force is more. in case of slabs bars are bent at the length L/4 to transfer the load on the beams then from beams to column.
Details of the Construction Materials learned today tor and mild steel bars ,cover blocks of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR EXTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 50 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 135.78 RS WATER= 1.5 % = 2.03 RS CONTRACTOR PROFIT = 10% = 13.57 RS TOTAL COST = 151.38 RS
Result of RATE ANALYSIS ( Rs per Unit ) 151.38 RS
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: buntyphonde@gmail.com
Subject: 10889-07

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Phonde Pravin Tukaram
Exam No. 10889
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To fill the cracks in the slab with the bonding agent . .
Details of how you Planned & Executed the allotted work first we took all the material which is required for it such as bonding agent,cement,pan,brush etc.on the spot where cracks were to be filled & we filled all cracks in the slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of preparing mix of bonding agent & cement then to apply over the cracks.firstly 1&1/2 kg cement is taken & then 1 liter of bonding agent is mixed in it & paste is prepared from it& then it is applied over the cracks. .
Details of the Construction Materials learned today today we learned about bonding agent details-acrylic polymer based bonding & water proof agent.it was of condura-conchem company.its volume was of 5 liter.for 5 liter cost was 1500/- .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today all the steel material ,nails props etc.should be placed properly to avoid injury. .
Details of the Construction / Engineering Drawings observed today today we observed drawing of column reinforcement & its position. .
Details of the Bye Laws referred today today we referred all the temporary construction which can be done from bye-laws. .
Details of any Managerial Skill learned today costumer which came to see the site should be given clear cut details of any item by manager or site incharge .
RATE ANALYSIS (Detailed Stepwise Calculations required) ITEM QTY. UNIT RATE AMOUNT Cement 0.25 Bags 260 65 Sand 0.04 M3 1150 46 Waterproofing Compound per M2 10 Plastermesh per M2 10 Total 126 Wastage 5% 6 Total 132 Scaffolding 15 Labour 78 Curing 5 Total 230 23% Tax Overhead and Profit 53 Total 288 Say 288/- per M2
Result of RATE ANALYSIS ( Rs per Unit ) 288/- per M2
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: cool.sushant007@gmail.com
Subject: 10880-07

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil sushant digambar
Exam No. 10880
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the reinforcement done with help of steel drawings.
Details of how you Planned & Executed the allotted work we directly go to the fifth floor where the steel work is almost completed.as per the location of the slabs in the drawings, we check that weather bars of given sizes and number of bars are placed in their exact location or not.
Details of the Construction Procedure / Activity / Technology learned today we learned about how the bars are provided in beams means top,bottom, extra top, extra bottom and why they are provided. when the joining of column is done one above the other then how much the lap length is provided.stirrups are provided to join the bars of the beams and spacing is closer near the support and wider at the central portion. extra bars are provided where the shear force is more. in case of slabs bars are bent at the length L/4 to transfer the load on the beams then from beams to column.
Details of the Construction Materials learned today tor and mild steel bars ,cover blocks of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR EXTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 50 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 135.78 RS WATER= 1.5 % = 2.03 RS CONTRACTOR PROFIT = 10% = 13.57 RS TOTAL COST = 151.38 RS
Result of RATE ANALYSIS ( Rs per Unit ) 151.38 RS
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-07

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Tambe Trusha Sitaram
Exam No. 10902
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To fill the cracks in the slab with the bonding agent . .
Details of how you Planned & Executed the allotted work first we took all the material which is required for it such as bonding agent,cement,pan,brush etc.on the spot where cracks were to be filled & we filled all cracks in the slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of preparing mix of bonding agent & cement then to apply over the cracks.firstly 1&1/2 kg cement is taken & then 1 liter of bonding agent is mixed in it & paste is prepared from it& then it is applied over the cracks. .
Details of the Construction Materials learned today today we learned about bonding agent details-acrylic polymer based bonding & water proof agent.it was of condura-conchem company.its volume was of 5 liter.for 5 liter cost was 1500/- .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today all the steel material ,nails props etc.should be placed properly to avoid injury. .
Details of the Construction / Engineering Drawings observed today today we observed drawing of column reinforcement & its position. .
Details of the Bye Laws referred today today we referred all the temporary construction which can be done from bye-laws. .
Details of any Managerial Skill learned today costumer which came to see the site should be given clear cut details of any item by manager or site incharge .
RATE ANALYSIS (Detailed Stepwise Calculations required) ITEM QTY. UNIT RATE AMOUNT Cement 0.25 Bags 260 65 Sand 0.04 M3 1150 46 Waterproofing Compound per M2 10 Plastermesh per M2 10 Total 126 Wastage 5% 6 Total 132 Scaffolding 15 Labour 78 Curing 5 Total 230 23% Tax Overhead and Profit 53 Total 288 Say 288/- per M2
Result of RATE ANALYSIS ( Rs per Unit ) 288/- per M2
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-07

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Sawant Amit Ganpat
Exam No. 10900
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To fill the cracks in the slab with the bonding agent . .
Details of how you Planned & Executed the allotted work first we took all the material which is required for it such as bonding agent,cement,pan,brush etc.on the spot where cracks were to be filled & we filled all cracks in the slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of preparing mix of bonding agent & cement then to apply over the cracks.firstly 1&1/2 kg cement is taken & then 1 liter of bonding agent is mixed in it & paste is prepared from it& then it is applied over the cracks. .
Details of the Construction Materials learned today today we learned about the bonding agent acrylic polymer base bonding & water proof agent .it was of condura-conchem company.its volume was 5 liter.& having cost 1500/- .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today all the steel material ,nails props etc.should be placed properly to avoid injury. .
Details of the Construction / Engineering Drawings observed today today we observed drawing of column reinforcement & its position. .
Details of the Bye Laws referred today today we referred all the temporary construction which can be done from bye-laws. .
Details of any Managerial Skill learned today costumer which came to see the site should be given clear cut details of any item by manager or site incharge .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for External Double Coat Plaster ITEM QTY. UNIT RATE AMOUNT Cement 0.25 Bags 260 65 Sand 0.04 M3 1150 46 Waterproofing Compound per M2 10 Plastermesh per M2 10 Total 126 Wastage 5% 6 Total 132 Scaffolding 15 Labour 78 Curing 5 Total 230 23% Tax Overhead and Profit 53 Total 288 Say 288/- per M2
Result of RATE ANALYSIS ( Rs per Unit ) 288/- per M2
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-07

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.13 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the replacing of W.C. pan in row bunglow A-4. To see the lambi work & painting work in flat no.503.
Details of how you Planned & Executed the allotted work First we visited row bunglow A-4 & see replacement of W.C. pan. Then we went to flat no.503 & see the lambi work and painting work.
Details of the Construction Procedure / Activity / Technology learned today Procedure: Replacement of W.C. Pan : 1) First faulty or broken W.C. pan is removed with the help of hammer and schizzle. 2) Then remaining cement below W.C. pan is taken out. 3) Then new cement paste is prepared & placed in the required position. 4) Then new W.C. pan is fitted in this position. 5) Then with the help of white cement finishing work is done. Procedure: For lambi & painting work: 1) First lambi paste is prepared. 2) Then with the help of piece of metal sheet lambi is applied over the wall surface. Painting work: 1) First with the help of sand paper wall surface is rubbed out for making plne surface. 2) Then paint is prepared in required shade. 3) Then with the help of brush paint is applied over the surface of the wall.
Details of the Construction Materials learned today Stinner: this is used for mixing of paint. Pigment : This is added to the colour in order to get the required colour.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today For stopping the excavation of natural ores of iron from the mines they have used the cut pieces of steel bars .
Details of the Construction / Engineering Drawings observed today Details of furniture layout of row bunglow A-4
Details of the Bye Laws referred today Internal Roads of 5m are provided. Main road of 8m is provided .
Details of any Managerial Skill learned today They cooperated with us very well. They manage the work properly by giving proper direction to the workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Thickness of plaster= 20mm Quantity of mortar = 20* 0.02 =0.4cub.m Add 60% qt. dry mortar = 0.64 cub.m Qt. of cement = 0.64/4 = 0.16 cub.m No. of bags of cement = 0.16/0.035 = 4.57 = say 5 no.of bags Qt. of sand = 3* 0.16 = 0.48 cub.m Particular Quantity/No. Rate Cost Material Cement 5 bags 255 1275Rs/- Sand 0.48 cub.m 1644 789.12Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Scaffolding 200 200 Rs/- Total = 3754 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 4505Rs/- Rate per sq.m= 225.24 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 225Rs/- per sq.m
Todays BUZZ Word Buzz word ‘Billing department’ Billing is the documentary aspect of the workdone , through which, payment can e made to the person involved in the contract & whose is responsible to complete work. - Imperfect billing can cause considerable losses to the contractor or client. - Bill should be perfect & self explanatory @ any stage of the work . - All information in these format should be correctly incorporated to avoid confusion while checking. Types of bills: 1) Advanced bill 2) Running account bill 3) Cash bills 4) Final bills -Advanced bill can be prepared for the following: - For material contract , the advanced bill can prepared against the material dumped on the site by the contractor. - Running account bill: - This are prepared at the site for the workdone. They are also called as interim bills. These bills should prepared every fortnight. Cash bills: Cash bills are required to be prepared for the payments for the following items: -weekly payments for the department labourers. -petty contractors for small works or job works. -for urgent work done, on a lumpsum basis. - - Final bills should be cleared after 100% completion of the work by the contractor. - Joint measurements should be taken by the engineer,along with the contractor or his representative.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-07

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.13 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the replacing of W.C. pan in row bunglow A-4. To see the lambi work & painting work in flat no.503.
Details of how you Planned & Executed the allotted work First we visited row bunglow A-4 & see replacement of W.C. pan. Then we went to flat no.503 & see the lambi work and painting work.
Details of the Construction Procedure / Activity / Technology learned today Procedure: Replacement of W.C. Pan : 1) First faulty or broken W.C. pan is removed with the help of hammer and schizzle. 2) Then remaining cement below W.C. pan is taken out. 3) Then new cement paste is prepared & placed in the required position. 4) Then new W.C. pan is fitted in this position. 5) Then with the help of white cement finishing work is done. Procedure: For lambi & painting work: 1) First lambi paste is prepared. 2) Then with the help of piece of metal sheet lambi is applied over the wall surface. Painting work: 1) First with the help of sand paper wall surface is rubbed out for making plne surface. 2) Then paint is prepared in required shade. 3) Then with the help of brush paint is applied over the surface of the wall.
Details of the Construction Materials learned today Stinner: this is used for mixing of paint. Pigment : This is added to the colour in order to get the required colour.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today For stopping the excavation of natural ores of iron from the mines they have used the cut pieces of steel bars .
Details of the Construction / Engineering Drawings observed today Details of furniture layout of row bunglow A-4
Details of the Bye Laws referred today Internal Roads of 5m are provided. Main road of 8m is provided .
Details of any Managerial Skill learned today They cooperated with us very well. They manage the work properly by giving proper direction to the workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Thickness of plaster= 20mm Quantity of mortar = 20* 0.02 =0.4cub.m Add 60% qt. dry mortar = 0.64 cub.m Qt. of cement = 0.64/4 = 0.16 cub.m No. of bags of cement = 0.16/0.035 = 4.57 = say 5 no.of bags Qt. of sand = 3* 0.16 = 0.48 cub.m Particular Quantity/No. Rate Cost Material Cement 5 bags 255 1275Rs/- Sand 0.48 cub.m 1644 789.12Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Scaffolding 200 200 Rs/- Total = 3754 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 4505Rs/- Rate per sq.m= 225.24 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 225Rs/- per sq.m
Todays BUZZ Word Buzz word ‘Billing department’ Billing is the documentary aspect of the workdone , through which, payment can e made to the person involved in the contract & whose is responsible to complete work. - Imperfect billing can cause considerable losses to the contractor or client. - Bill should be perfect & self explanatory @ any stage of the work . - All information in these format should be correctly incorporated to avoid confusion while checking. Types of bills: 1) Advanced bill 2) Running account bill 3) Cash bills 4) Final bills -Advanced bill can be prepared for the following: - For material contract , the advanced bill can prepared against the material dumped on the site by the contractor. - Running account bill: - This are prepared at the site for the workdone. They are also called as interim bills. These bills should prepared every fortnight. Cash bills: Cash bills are required to be prepared for the payments for the following items: -weekly payments for the department labourers. -petty contractors for small works or job works. -for urgent work done, on a lumpsum basis. - - Final bills should be cleared after 100% completion of the work by the contractor. - Joint measurements should be taken by the engineer,along with the contractor or his representative.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-07

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.13 p.m.
Details of the Work Allotted to you today by the Site In-Charge To see the replacing of W.C. pan in row bunglow A-4. To see the lambi work & painting work in flat no.503.
Details of how you Planned & Executed the allotted work First we visited row bunglow A-4 & see replacement of W.C. pan. Then we went to flat no.503 & see the lambi work and painting work.
Details of the Construction Procedure / Activity / Technology learned today Procedure: Replacement of W.C. Pan : 1) First faulty or broken W.C. pan is removed with the help of hammer and schizzle. 2) Then remaining cement below W.C. pan is taken out. 3) Then new cement paste is prepared & placed in the required position. 4) Then new W.C. pan is fitted in this position. 5) Then with the help of white cement finishing work is done. Procedure: For lambi & painting work: 1) First lambi paste is prepared. 2) Then with the help of piece of metal sheet lambi is applied over the wall surface. Painting work: 1) First with the help of sand paper wall surface is rubbed out for making plne surface. 2) Then paint is prepared in required shade. 3) Then with the help of brush paint is applied over the surface of the wall.
Details of the Construction Materials learned today Stinner: this is used for mixing of paint. Pigment : This is added to the colour in order to get the required colour.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today For stopping the excavation of natural ores of iron from the mines they have used the cut pieces of steel bars .
Details of the Construction / Engineering Drawings observed today Details of furniture layout of row bunglow A-4
Details of the Bye Laws referred today Internal Roads of 5m are provided. Main road of 8m is provided .
Details of any Managerial Skill learned today They cooperated with us very well. They manage the work properly by giving proper direction to the workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) EXTERNAL PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Thickness of plaster= 20mm Quantity of mortar = 20* 0.02 =0.4cub.m Add 60% qt. dry mortar = 0.64 cub.m Qt. of cement = 0.64/4 = 0.16 cub.m No. of bags of cement = 0.16/0.035 = 4.57 = say 5 no.of bags Qt. of sand = 3* 0.16 = 0.48 cub.m Particular Quantity/No. Rate Cost Material Cement 5 bags 255 1275Rs/- Sand 0.48 cub.m 1644 789.12Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Scaffolding 200 200 Rs/- Total = 3754 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 4505Rs/- Rate per sq.m= 225.24 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 225Rs/- per sq.m
Todays BUZZ Word Buzz word ‘Billing department’ Billing is the documentary aspect of the workdone , through which, payment can e made to the person involved in the contract & whose is responsible to complete work. - Imperfect billing can cause considerable losses to the contractor or client. - Bill should be perfect & self explanatory @ any stage of the work . - All information in these format should be correctly incorporated to avoid confusion while checking. Types of bills: 1) Advanced bill 2) Running account bill 3) Cash bills 4) Final bills -Advanced bill can be prepared for the following: - For material contract , the advanced bill can prepared against the material dumped on the site by the contractor. - Running account bill: - This are prepared at the site for the workdone. They are also called as interim bills. These bills should prepared every fortnight. Cash bills: Cash bills are required to be prepared for the payments for the following items: -weekly payments for the department labourers. -petty contractors for small works or job works. -for urgent work done, on a lumpsum basis. - - Final bills should be cleared after 100% completion of the work by the contractor. - Joint measurements should be taken by the engineer,along with the contractor or his representative.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-07

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Tekwani Sagar Bansilal
Exam No. 10903
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To visit and study the construction work going on of Farm house at Panhala as recommended by Paras Oswal sir.
Details of how you Planned & Executed the allotted work We went to Panhala in group. Their we met the site incharge he showed us the plans of farm house and gave us. Then we studied the plans and saw the site and checked that all the construction process going on as per plan.
Details of the Construction Procedure / Activity / Technology learned today We saw the process of concreting of roofing slab, filling work, the foundation work,plinth work going on.We saw the masonry work construction.Spring bar in roofing slab,Footing work,steel grid used for footing,
Details of the Construction Materials learned today 1. Use of waterproofing chemical while concreteing algae proof 200 ml. 2. Different types of bricks. 1. Hollow Bricks for temporary structure. 2. Wire cut Bricks for attractive elevation and good strength. 3. Cement 43 grade Bagalkot supreme.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited
Details of the Construction / Engineering Drawings observed today 1. Plan of farm-house of 900 sq.ft 1000sq.ft and 1200 sq.ft. 2. Contour plan.
Details of the Bye Laws referred today 1.Maximum cantilever porch length 4.00m according to bye laws has been followed. 2.Stair case is designed as per bye laws.
Details of any Managerial Skill learned today 1. The site incharge inspected saw the concreteing process going on. 2. The site incharge checked the propotions of different materials used. 3. The site incharge kept a proper record of total quantity
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for EXTERNAL PLASTER. Considering 25 mm thick plaster in two coats. Mortar = 1:4. Cement=0.22 Cost of Cement= 0.22*265= Rs.58.30. Sand=0.025. Cost of sand= 0.025*2120= Rs.53. Labour= Rs.65. Total Cost= 58.30+53+65= Rs.176.30. For each sq.m add Rs.15 extra for water proofing. Total cost= 176.30+15= Rs.191.30. Considering 10% profit= 19.13. Total cost of external plaster= 191.13+19.13= Rs.210.43. per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.210.43. per sq.m
Todays BUZZ Word \"BILLING DEPARTMENT\" 1. Calulation of total steel required and its cost. 1.Total quantity of steel required for columns and its cost. 2.Total quantity of steel required for beams and its cost. 3.Total quantity of steel required for slab and its cost. 4.Total quantity of steel required for cantilevers, balconies etc and its cost. 2.Calulation of total material required for electrification purpose and its cost. 1.Total quantity of casing pipes required for external pupose and its cost. 2.Total quantity of casing pipes required for internal pupose and its cost. 3.Total quantity of wiring,switch board,power plugs,electric bell,sockets,meter etc and its cost. 3.Calculation of sanitary fittings required and its cost. 1. Total quantity of pipes reuired for water supply purpose and its cost. 2. Total quantity of pipes required for drainage puppose and its cost. 3. Total number of cocks,elbows,traps,valves etc and their cost. 4.Calculation of painting work and its cost. 1. Internal painting work and its cost. 2. External painting work and its cost. 3. Type of paint,quantity,varnishes etc and its cost. 5.Type of cement and its cost. 1. 43 grade opc of bagalkot supreme cement and its cost. 2. 53 grade opc of bagalkot supreme cement and its cost. 3. White cement and its cost. 4. Any other admixtures required and its cost. 6.Total cost of titling work. 1. Total cost of vitrified tiles. 2. Total cost of roofing tiles. 7. Total cost of plastering work. 1.Total cost of internal plaster work depending upon thickness provided. 2.Total cost of external plaster work depending upon thickness provided. 8. Total cost of bricks. 1.Total cost of flyash bricks and any other bricks used. 9. Total cost of centering work. 10.Total cost of windows and doors fittings like material used such as glass etc. 11.Total cost & quantity of sand required. 12.Total labour cost for different works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SALIM MOMIN PH NO.9225816079.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-07

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHAIKH RIZWAN KHALIL
Exam No. 13544
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.30 pm
Details of the Work Allotted to you today by the Site In-Charge To check the reinforcement done with help of steel drawings.
Details of how you Planned & Executed the allotted work we directly go to the fifth floor where the steel work is almost completed.as per the location of the slabs in the drawings, we check that weather bars of given sizes and number of bars are placed in their exact location or not.
Details of the Construction Procedure / Activity / Technology learned today we learned about how the bars are provided in beams means top,bottom, extra top, extra bottom and why they are provided. when the joining of column is done one above the other then how much the lap length is provided.stirrups are provided to join the bars of the beams and spacing is closer near the support and wider at the central portion. extra bars are provided where the shear force is more. in case of slabs bars are bent at the length L/4 to transfer the load on the beams then from beams to column.
Details of the Construction Materials learned today tor and mild steel bars ,cover blocks of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR EXTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 50 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 135.78 RS WATER= 1.5 % = 2.03 RS CONTRACTOR PROFIT = 10% = 13.57 RS TOTAL COST = 151.38 RS
Result of RATE ANALYSIS ( Rs per Unit ) 151.38 RS
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-07

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SALOKHE SUDARSHAN ANIL
Exam No. 13544
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.30 pm
Details of the Work Allotted to you today by the Site In-Charge To check the reinforcement done with help of steel drawings.
Details of how you Planned & Executed the allotted work we directly go to the fifth floor where the steel work is almost completed.as per the location of the slabs in the drawings, we check that weather bars of given sizes and number of bars are placed in their exact location or not.
Details of the Construction Procedure / Activity / Technology learned today we learned about how the bars are provided in beams means top,bottom, extra top, extra bottom and why they are provided. when the joining of column is done one above the other then how much the lap length is provided.stirrups are provided to join the bars of the beams and spacing is closer near the support and wider at the central portion. extra bars are provided where the shear force is more. in case of slabs bars are bent at the length L/4 to transfer the load on the beams then from beams to column.
Details of the Construction Materials learned today tor and mild steel bars ,cover blocks of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR EXTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 50 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 135.78 RS WATER= 1.5 % = 2.03 RS CONTRACTOR PROFIT = 10% = 13.57 RS TOTAL COST = 151.38 RS
Result of RATE ANALYSIS ( Rs per Unit ) 151.38 RS
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-07

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SINGH RAJAN RAJENDRA BAHADUR
Exam No. 13548
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.30 pm
Details of the Work Allotted to you today by the Site In-Charge To check the reinforcement done with help of steel drawings.
Details of how you Planned & Executed the allotted work we directly go to the fifth floor where the steel work is almost completed.as per the location of the slabs in the drawings, we check that weather bars of given sizes and number of bars are placed in their exact location or not.
Details of the Construction Procedure / Activity / Technology learned today we learned about how the bars are provided in beams means top,bottom, extra top, extra bottom and why they are provided. when the joining of column is done one above the other then how much the lap length is provided.stirrups are provided to join the bars of the beams and spacing is closer near the support and wider at the central portion. extra bars are provided where the shear force is more. in case of slabs bars are bent at the length L/4 to transfer the load on the beams then from beams to column.
Details of the Construction Materials learned today tor and mild steel bars ,cover blocks of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today steel drawings.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR EXTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 50 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 135.78 RS WATER= 1.5 % = 2.03 RS CONTRACTOR PROFIT = 10% = 13.57 RS TOTAL COST = 151.38 RS
Result of RATE ANALYSIS ( Rs per Unit ) 151.38 RS
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. ABHIJIT BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Swapnil Ashok
Exam No. 13529
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Nilam Jaywant
Exam No. 13528
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Dsouza Agnel Santan
Exam No. 13524
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57 total cost=534+8.01+53.4 =Rs.595.41
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur,
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57 total cost=534+8.01+53.4 =Rs.595.41
Result of RATE ANALYSIS ( Rs per Unit ) 595.41
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Dsouza Agnel Santan
Exam No. 13524
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57 total cost=534+8.01+53.4 =Rs.595.41
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Dsouza Agnel Santan
Exam No. 13524
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57 total cost=534+8.01+53.4 =Rs.595.41
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-07

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe column concreting.
Details of how you Planned & Executed the allotted work First we saw r.c.c. drawings of columns Then we observed actual concreting work.
Details of the Construction Procedure / Activity / Technology learned today beams are prepared as per the design given by the structural designer.
Details of the Construction Materials learned today cement sand mixer.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today beam drawing for the terrace floor.
Details of the Bye Laws referred today none.
Details of any Managerial Skill learned today we should check properly whether the material supplied is proper or not.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 30 mm thick plaster(1:4) assume,1sq.m surface srea=1*(30/1000)m volume of mortar for 30 mm plaster=1*0.030=0.030 cu.m add 30% for filling up uneven surface=(0.030*30/100)+0.030=0.0221 cu.m add 25% for dry volume=0.021*1.25=0.0262 cu.m a) cement-(0.0262/(1+4))=0.0065 cu.m0.007 cu.m no. of bags-(0.007/0.035)=0.2bags=0.2*254=Rs.50.8 b) sand-0.007*3=0.028=5000*0.028=Rs.105 total cost of material=Rs.155.8. f) labour- mason-1 no.-Rs.30/cu.m Boy or woman-Rs.17/cu.m shuttering-Rs.30 Total-Rs.(155.8+47+30)= Rs.232.8 g) water-1.5%=232.8*(1.5/100)=Rs.3.49 contractor profit=total cost*profit(10% profit) =Rs.232.8*1.10 =Rs.259.57
Result of RATE ANALYSIS ( Rs per Unit ) 259.57
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13561-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) jadhav sardar sawroop j.
Exam No. 13561
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) jade madhavrao anil
Exam No. 13560
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-07

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) patil sachin dhanaji
Exam No. 13539
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:10pm
Details of the Work Allotted to you today by the Site In-Charge to observation of slab casting 1.prapotion of concrete ingredient (1:2:4) 2.lift and transportation of concrete 3.needle vibrater used for compaction of concrete
Details of how you Planned & Executed the allotted work observation of slab casting 1.prapotion of concrete ingredient (1:2:4) 2.lift and transportation of concrete 3.needle vibrater used for compaction of concrete
Details of the Construction Procedure / Activity / Technology learned today we learn 1.lifting and transporting of concrete 2.compaction of concrete by needle vibrater 3.finishing the slab surface 4.concealed wiring in slab
Details of the Construction Materials learned today 1.cement -portland pozzolona cement fly ash based 43Grade 2.sand -standard size low clay containt 3.aggregate -average size 20mm 4.waer proof chemical -100Ml per one bag of cement 5.water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today RCC design for 1.slab 2.stair case 3.beam
Details of the Bye Laws referred today no flight shall contain more than 12 risers
Details of any Managerial Skill learned today 1.good communication with customer and us 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster 1.sand- 15 x 17 RS =255RS 2.cement- 1.75 x 250 RS =438RS 3.labour =400Rs 4.curing =30Rs 5.scafolding =50Rs Total =1173RS with cp =1407.6RS Total =14.07RS per sq.ft. Total =152Rs per Sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 152 RS
Todays BUZZ Word Billing department *1.purchase billing -checking market rate for 1.sand ,aggregate ,cement stone ,brick ,steel 2.plumbing material 3.tiles 4.electric materials 5.painting materials *2. labour billing 1.for excavation 2.bar bending and centring 3.mesonary worker 4.carpenter 5.fabricater 6.tiles fitter 7.plumber 8 painter
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-07

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) patil sangram madhukar
Exam No. 13540
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:10pm
Details of the Work Allotted to you today by the Site In-Charge to observation of slab casting 1.prapotion of concrete ingredient (1:2:4) 2.lift and transportation of concrete 3.needle vibrater used for compaction of concrete
Details of how you Planned & Executed the allotted work observation of slab casting 1.prapotion of concrete ingredient (1:2:4) 2.lift and transportation of concrete 3.needle vibrater used for compaction of concrete
Details of the Construction Procedure / Activity / Technology learned today we learn 1.lifting and transporting of concrete 2.compaction of concrete by needle vibrater 3.finishing the slab surface 4.concealed wiring in slab
Details of the Construction Materials learned today 1.cement -portland pozzolona cement fly ash based 43Grade 2.sand -standard size low clay containt 3.aggregate -average size 20mm 4.waer proof chemical -100Ml per one bag of cement 5.water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today RCC design for 1.slab 2.stair case 3.beam
Details of the Bye Laws referred today no flight shall contain more than 12 risers
Details of any Managerial Skill learned today 1.good communication with customer and us 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster 1.sand- 15 x 17 RS =255RS 2.cement- 1.75 x 250 RS =438RS 3.labour =400Rs 4.curing =30Rs 5.scafolding =50Rs Total =1173RS with cp =1407.6RS Total =14.07RS per sq.ft. Total =152Rs per Sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 152 RS
Todays BUZZ Word Billing department *1.purchase billing -checking market rate for 1.sand ,aggregate ,cement stone ,brick ,steel 2.plumbing material 3.tiles 4.electric materials 5.painting materials *2. labour billing 1.for excavation 2.bar bending and centring 3.mesonary worker 4.carpenter 5.fabricater 6.tiles fitter 7.plumber 8 painter
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no-9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-07

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudev
Exam No. 10891
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe Painting work,w/c pan replacement. .
Details of how you Planned & Executed the allotted work First we go in a 8th bungalow whose w/c pan was damaged, the repair work was going on. we observed the same. .
Details of the Construction Procedure / Activity / Technology learned today Replacement of damage w/c- 1)Remove the damage w/c pan 2)Clean the outlet pipe 3)Apply glue to in side of outlet pipe & outside of w/c pan 4)Connect w/c pan to outlet pipe. 5)Next day test for any leakage. .
Details of the Construction Materials learned today w/c pan & its related connection material. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel supports used for form work are more eco friendly compare to wood works. ..
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing .
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment. .
Details of any Managerial Skill learned today How to manage the labour force & time ,quality of concreting work ,steel distribution economy .
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012=0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012=0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 . cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=890Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs ( Rs per Unit ): 980.58Rs .
Result of RATE ANALYSIS ( Rs per Unit ) Rs 980.58/-m2
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam patil (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-07

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To observe Painting work,w/c pan replacement. .
Details of how you Planned & Executed the allotted work First we go in a 8th bungalow whose w/c pan was damaged, the repair work was going on. we observed the same. .
Details of the Construction Procedure / Activity / Technology learned today Replacement of damage w/c- 1)Remove the damage w/c pan 2)Clean the outlet pipe 3)Apply glue to in side of outlet pipe & outside of w/c pan 4)Connect w/c pan to outlet pipe. 5)Next day test for any leakage. .
Details of the Construction Materials learned today w/c pan & its related connection material. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel supports used for form work are more eco friendly compare to wood works. ..
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing .
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment. .
Details of any Managerial Skill learned today How to manage the labour force & time ,quality of concreting work ,steel distribution economy .
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012=0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012=0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 . cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=890Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs ( Rs per Unit ): 980.58Rs .
Result of RATE ANALYSIS ( Rs per Unit ) Rs 980.58/-m2
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam patil (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya
Exam No. 13572
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya
Exam No. 13572
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya
Exam No. 13572
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya
Exam No. 13572
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya
Exam No. 13572
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya
Exam No. 13572
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya
Exam No. 13572
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya
Exam No. 13572
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya
Exam No. 13572
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya
Exam No. 13572
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558-07

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, new balinga.
Students Name (Surname_First Name_Middle Name) Chavan Shivprasad Prakash
Exam No. 13558
Working Day No. 07
Date (DD/MM/YYYY) 15.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To observe column concreting in apartment building. 2. To observe centering of lift shaft.
Details of how you Planned & Executed the allotted work 1. Column concreting ; First we had seen r.c.c. drwaings of columns and concreting spacifications. Then we observe actual concreting work on site. 2. Centering of lift shaft ; First we had seen R,C.C. drwaing and detailed drwaing of lift shaft. Then we observe actual centering work and we checked it with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Column concreting ; 1. Reinforcement is prepared as per r.c.c. design and placed in its position by mestry. 2. Then mould is casted as per size of column, 3. Reinforcement is checked by site in charge and corrected if there are any mistakes. 4. Concrete is prepared as per spacifications and placed in mould. 5. Compaction is done by vibrator.
Details of the Construction Materials learned today M.C. Dr. FIXIT ; It is chemical used at the joint of fresh concrete and old concrete. It is very important chemical as it acts as binding agent which binds the fresh and new concrete together
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of ground water ; 1. Water from two large wells is used for all watering purposes. 2. So use of river water is avoided which saves water demand. 3. Waste water is also treated again it is used and also ground water is recharged.
Details of the Construction / Engineering Drawings observed today R.C.C, drawings of apartment building, center line plan of apartment building and r.c.c. drwaing of lift shaft.
Details of the Bye Laws referred today Sizes of Septic Tank ; 1. Minimum internal width = 75 cm 2. Minimum depth = 1 m 3. Minimum liquid capacity = 1 cu.m 4. Lenth of tank = 2 to 4 times width of tank
Details of any Managerial Skill learned today How to plan and distribuute the work. So as to complete the work perfectly and speedily.
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering ; per sq.m Morter Proportion [1;6] Sand = 6.5 cu.ft = 350.00 Rs Cement = 15 kg. = 80.00 Rs Labour cost + 2.0% Wastage TOTAL = 500.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 500.00Rs. per sq.m
Todays BUZZ Word BILLING DEPARTMENT ; Types of bills: 1. Advance bill 2. Running Account bill (R. A. BILL) 3. Cash bill 4. Labour Departement bill 5. Final bill PROCEDURE FOR BILLING, CHECKING & PAYMENTS 1. Preparation of bills at site weekly. 2. Checking of bills by project engineer. 3. Submission of bill alongwith building division. 4. Bill entry in inward register at head office. 5. Bill received by billing engg.,with sign & date in register. 6. Checking by billing engg., certification for net payments. 7. Checking & approval by chief engg. 8. Bills to a/c dept.with proper entry in register. 9. Checking of bills by a/c dept. 10.Sign of director on cheque. 11.Entry of cheque details in a/c register/ computer. 12.Forwarding of cheques to billing engg. from a/c dept. 13.Counter sign of contractor in cheque issue register. 14.Entry of cheques in respective contractors file by billing engg.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-07

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Redekar Shantanu Ravindra
Exam No. 13566
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about the footing such as combined footing, trapezoidal footing etc.
Details of how you Planned & Executed the allotted work * First we observe the actual plan of footing * Then according to plan construct the formwork around the reinforcement.
Details of the Construction Procedure / Activity / Technology learned today * Murum filling by POCLAND(JCB) equipment. * Steel bar cutting by using steel cutter. * Steel formwork of staircase, footing, cantilever, etc. * Casting of beam and staircase etc.
Details of the Construction Materials learned today * Special steel cutting equipment for cutting steel bars. * Needle vibrator * Tamping rod * Roller * Cement 43 grade. * Admixture * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. * anchor bar 12mm stirrups 8mm & 6mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly-ash bricks used for brick work.
Details of the Construction / Engineering Drawings observed today * Footing layout plan. * Working drawing. * Electrification drawing
Details of the Bye Laws referred today PLINTH- * The height of plinth shall not be less than 0.45m above the ground level provided. * Shops plinth height may be 0.3m provided.
Details of any Managerial Skill learned today * Maintain the quaility of work. * Control on wastage material. * Maintain cleanliness of the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering (1:3) a) Material required for plastering for 100m2 unit per m2 b) Dry quantity of C.M. required for 100m2 for 12mm thik. plastering in C.M. 1:3 in 2m3 1) cement = 2/(1+3) = 0.5m3 no. bags= 0.5/0.034= 14.7= 15bags. 2) Sand = 0.5 x 3 = 1.5m3 SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 15 bags 250.00/- 3750.00/- b) sand 1.5 cum 850.00/- (per cum) 1275.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) mason 10 no. 200.00/- 2000.00/- c) male mazdur 15 no. 160.00/- 2400.00/- d) bhisti 1 no. 120.00/- 240.00/- 3 Others _ TOTAL 9965.00/- 4 Tools and plant @ 1.5% ----------------------- 150.00/- on total 5 Water charges @ 1.0% ----------------------- 100.00/- on total TOTAL(A) 10215.00/- 6 Overhead and profit @ 15% on tOtal A ----------------------- 1532.00/- -------------------------------------------------------------------------- TOTAL = 11750.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 11750/- per 100 m2
Todays BUZZ Word Advance bills- * For material contract the advance bill can be prepared against the material dumped on site by contractor. * Advance bill should be prepared on standard format that is payment challan. R.A. bills- * This bill are prepared at the site for workdone. * These bills should be prepared every for night * Normally payments to contractors are done on weekly basis. CASH bills- * This bill required to be prepared for the payments for the following items. * Weekly payments for the department labourers * Petty contractors for small work/job work FINAL bills- * This bills should be cleared after 100% completion of the work by the contractor. * Joints measurement should be taken by the engineer along with the contractor.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: Rohit_patil361@rediffmail.com
Subject: 13565-07

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Patil Rohit Ashok
Exam No. 13565
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about the footing such as combined footing, trapezoidal footing etc.
Details of how you Planned & Executed the allotted work * First we observe the actual plan of footing * Then according to plan construct the formwork around the reinforcement.
Details of the Construction Procedure / Activity / Technology learned today * Murum filling by POCLAND(JCB) equipment. * Steel bar cutting by using steel cutter. * Steel formwork of staircase, footing, cantilever, etc. * Casting of beam and staircase etc.
Details of the Construction Materials learned today * Special steel cutting equipment for cutting steel bars. * Needle vibrator * Tamping rod * Roller * Cement 43 grade. * Admixture * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. * anchor bar 12mm stirrups 8mm & 6mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly-ash bricks used for brick work.
Details of the Construction / Engineering Drawings observed today * Footing layout plan. * Working drawing. * Electrification drawing
Details of the Bye Laws referred today PLINTH- * The height of plinth shall not be less than 0.45m above the ground level provided. * Shops plinth height may be 0.3m provided.
Details of any Managerial Skill learned today * Maintain the quaility of work. * Control on wastage material. * Maintain cleanliness of the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering (1:3) a) Material required for plastering for 100m2 unit per m2 b) Dry quantity of C.M. required for 100m2 for 12mm thik. plastering in C.M. 1:3 in 2m3 1) cement = 2/(1+3) = 0.5m3 no. bags= 0.5/0.034= 14.7= 15bags. 2) Sand = 0.5 x 3 = 1.5m3 SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 15 bags 250.00/- 3750.00/- b) sand 1.5 cum 850.00/- (per cum) 1275.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) mason 10 no. 200.00/- 2000.00/- c) male mazdur 15 no. 160.00/- 2400.00/- d) bhisti 1 no. 120.00/- 240.00/- 3 Others _ TOTAL 9965.00/- 4 Tools and plant @ 1.5% ----------------------- 150.00/- on total 5 Water charges @ 1.0% ----------------------- 100.00/- on total TOTAL(A) 10215.00/- 6 Overhead and profit @ 15% on tOtal A ----------------------- 1532.00/- -------------------------------------------------------------------------- TOTAL = 11750.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 11750.00/- per 100m2
Todays BUZZ Word Advance bills- * For material contract the advance bill can be prepared against the material dumped on site by contractor. * Advance bill should be prepared on standard format that is payment challan. R.A. bills- * This bill are prepared at the site for workdone. * These bills should be prepared every for night * Normally payments to contractors are done on weekly basis. CASH bills- * This bill required to be prepared for the payments for the following items. * Weekly payments for the department labourers * Petty contractors for small work/job work FINAL bills- * This bills should be cleared after 100% completion of the work by the contractor. * Joints measurement should be taken by the engineer along with the contractor.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: pinkrosee4u@yahoo.com
Subject: 10878-07

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) narnaware shikha haridas
Exam No. 10878
Working Day No. 07
Date (DD/MM/YYYY) 15/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge We were told to view rebarring to view how POP is done cleaning of road before construction
Details of how you Planned & Executed the allotted work We observed carefully the working done for POP its working and finishing done electrification work in pop was also observed In rebarring hole was drilled along with chemical to bar to fix it by workers road was cleaned by simple means with broomers
Details of the Construction Procedure / Activity / Technology learned today POP tecgnology rebarring technology
Details of the Construction Materials learned today plywood,plaster,putty drill machine,strips of bar,chemicals
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today farming drawing
Details of the Bye Laws referred today for road dimensions 10 m width,setback line 10.5m
Details of any Managerial Skill learned today drilling hole for rebarring
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for external plastering for 20mm thick plastring sand=1*1*0.02=0.02m3 for getting 0.02m3 sand for plastering we require double sand=2*0.02=0.04m3 rate of sand=0.04*1411rs=57rs cement required=0.25bag*250rs=62.50rs material cost=57+62.50=120rs labour cost=5ft2*10.76=54rs total cost=120+54=174rs
Result of RATE ANALYSIS ( Rs per Unit ) 174rs/m2
Todays BUZZ Word billing department preperation of bills at sites weekly or fortnightly by jnior engg. with measurement sheets and sketches checking of bills by project engg. in detail submission of bills along with sketches and all required supported document to billing devision bill entry in inward registereed at office bills recieved by billing engg, with sign an date in register checking by billing engg,preparing payment challan and certification for net payments checking and approval by chief engg. bills to a/c ept with proper entry in register checing of bills by a/c dept. sign of irector on cheque entry f check details in account register/computer forwarding of checks to billing engg. from a/c dept. counter sign of contractor in cheque issue register entry of cheques in resective contractors file by billing engg
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, Bye Law Book, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge SATISH 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-07

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Mohare Vishal Bhalchandra
Exam No. 13564
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about the footing such as combined footing, trapezoidal footing etc.
Details of how you Planned & Executed the allotted work * First we observe the actual plan of footing * Then according to plan construct the formwork around the reinforcement.
Details of the Construction Procedure / Activity / Technology learned today * Murum filling by POCLAND(JCB) equipment. * Steel bar cutting by using steel cutter. * Steel formwork of staircase, footing, cantilever, etc. * Casting of beam and staircase etc.
Details of the Construction Materials learned today * Special steel cutting equipment for cutting steel bars. * Needle vibrator * Tamping rod * Roller * Cement 43 grade. * Admixture * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. * anchor bar 12mm stirrups 8mm & 6mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly-ash bricks used for brick work.
Details of the Construction / Engineering Drawings observed today * Footing layout plan. * Working drawing. * Electrification drawing
Details of the Bye Laws referred today PLINTH- * The height of plinth shall not be less than 0.45m above the ground level provided. * Shops plinth height may be 0.3m provided.
Details of any Managerial Skill learned today * Maintain the quaility of work. * Control on wastage material. * Maintain cleanliness of the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering (1:3) a) Material required for plastering for 100m2 unit per m2 b) Dry quantity of C.M. required for 100m2 for 12mm thik. plastering in C.M. 1:3 in 2m3 1) cement = 2/(1+3) = 0.5m3 no. bags= 0.5/0.034= 14.7= 15bags. 2) Sand = 0.5 x 3 = 1.5m3 SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 15 bags 250.00/- 3750.00/- b) sand 1.5 cum 850.00/- (per cum) 1275.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) mason 10 no. 200.00/- 2000.00/- c) male mazdur 15 no. 160.00/- 2400.00/- d) bhisti 1 no. 120.00/- 240.00/- 3 Others _ TOTAL 9965.00/- 4 Tools and plant @ 1.5% ----------------------- 150.00/- on total 5 Water charges @ 1.0% ----------------------- 100.00/- on total TOTAL(A) 10215.00/- 6 Overhead and profit @ 15% on tOtal A ----------------------- 1532.00/- -------------------------------------------------------------------------- TOTAL = 11750.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 11750.00/- per 100m2
Todays BUZZ Word Advance bills- * For material contract the advance bill can be prepared against the material dumped on site by contractor. * Advance bill should be prepared on standard format that is payment challan. R.A. bills- * This bill are prepared at the site for workdone. * These bills should be prepared every for night * Normally payments to contractors are done on weekly basis. CASH bills- * This bill required to be prepared for the payments for the following items. * Weekly payments for the department labourers * Petty contractors for small work/job work FINAL bills- * This bills should be cleared after 100% completion of the work by the contractor. * Joints measurement should be taken by the engineer along with the contractor.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-07

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 07
Date (DD/MM/YYYY) 15/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge We were told to view rebarring to view how POP is done cleaning of road before construction
Details of how you Planned & Executed the allotted work We observed carefully the working done for POP its working and finishing done electrification work in pop was also observed In rebarring hole was drilled along with chemical to bar to fix it by workers road was cleaned by simple means with broomers
Details of the Construction Procedure / Activity / Technology learned today POP tecgnology rebarring technology
Details of the Construction Materials learned today plywood,plaster,putty drill machine,strips of bar,chemicals
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today farming drawing
Details of the Bye Laws referred today for road dimensions 10 m width,setback line 10.5m
Details of any Managerial Skill learned today drilling hole for rebarring
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for external plastering for 20mm thick plastring sand=1*1*0.02=0.02m3 for getting 0.02m3 sand for plastering we require double sand=2*0.02=0.04m3 rate of sand=0.04*1411rs=57rs cement required=0.25bag*250rs=62.50rs material cost=57+62.50=120rs labour cost=5ft2*10.76=54rs total cost=120+54=174rs
Result of RATE ANALYSIS ( Rs per Unit ) 174rs/m2
Todays BUZZ Word billing department preperation of bills at sites weekly or fortnightly by jnior engg. with measurement sheets and sketches checking of bills by project engg. in detail submission of bills along with sketches and all required supported document to billing devision bill entry in inward registereed at office bills recieved by billing engg, with sign an date in register checking by billing engg,preparing payment challan and certification for net payments checking and approval by chief engg. bills to a/c ept with proper entry in register checing of bills by a/c dept. sign of irector on cheque entry f check details in account register/computer forwarding of checks to billing engg. from a/c dept. counter sign of contractor in cheque issue register entry of cheques in resective contractors file by billing engg
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-07

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about the footing such as combined footing, trapezoidal footing etc.
Details of how you Planned & Executed the allotted work * First we observe the actual plan of footing * Then according to plan construct the formwork around the reinforcement.
Details of the Construction Procedure / Activity / Technology learned today * Murum filling by POCLAND(JCB) equipment. * Steel bar cutting by using steel cutter. * Steel formwork of staircase, footing, cantilever, etc. * Casting of beam and staircase etc.
Details of the Construction Materials learned today * Special steel cutting equipment for cutting steel bars. * Needle vibrator * Tamping rod * Roller * Cement 43 grade. * Admixture * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. * anchor bar 12mm stirrups 8mm & 6mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly-ash bricks used for brick work.
Details of the Construction / Engineering Drawings observed today * Footing layout plan. * Working drawing. * Electrification drawing
Details of the Bye Laws referred today PLINTH- * The height of plinth shall not be less than 0.45m above the ground level provided. * Shops plinth height may be 0.3m provided.
Details of any Managerial Skill learned today * Maintain the quaility of work. * Control on wastage material. * Maintain cleanliness of the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering (1:3) a) Material required for plastering for 100m2 unit per m2 b) Dry quantity of C.M. required for 100m2 for 12mm thik. plastering in C.M. 1:3 in 2m3 1) cement = 2/(1+3) = 0.5m3 no. bags= 0.5/0.034= 14.7= 15bags. 2) Sand = 0.5 x 3 = 1.5m3 SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 15 bags 250.00/- 3750.00/- b) sand 1.5 cum 850.00/- (per cum) 1275.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) mason 10 no. 200.00/- 2000.00/- c) male mazdur 15 no. 160.00/- 2400.00/- d) bhisti 1 no. 120.00/- 240.00/- 3 Others _ TOTAL 9965.00/- 4 Tools and plant @ 1.5% ----------------------- 150.00/- on total 5 Water charges @ 1.0% ----------------------- 100.00/- on total TOTAL(A) 10215.00/- 6 Overhead and profit @ 15% on tOtal A ----------------------- 1532.00/- -------------------------------------------------------------------------- TOTAL = 11750.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 11750.00 per 100m2
Todays BUZZ Word Advance bills- * For material contract the advance bill can be prepared against the material dumped on site by contractor. * Advance bill should be prepared on standard format that is payment challan. R.A. bills- * This bill are prepared at the site for workdone. * These bills should be prepared every for night * Normally payments to contractors are done on weekly basis. CASH bills- * This bill required to be prepared for the payments for the following items. * Weekly payments for the department labourers * Petty contractors for small work/job work FINAL bills- * This bills should be cleared after 100% completion of the work by the contractor. * Joints measurement should be taken by the engineer along with the contractor.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: viju128@gmail.com
Subject: 3638-07

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.rajnra nagar kolhapur
Students Name (Surname_First Name_Middle Name) shinde vijay namdeo
Exam No. 3638
Working Day No. 07
Date (DD/MM/YYYY) 15/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge We were told to view rebarring to view how POP is done cleaning of road before construction
Details of how you Planned & Executed the allotted work We observed carefully the working done for POP its working and finishing done electrification work in pop was also observed In rebarring hole was drilled along with chemical to bar to fix it by workers road was cleaned by simple means with broomers
Details of the Construction Procedure / Activity / Technology learned today POP tecgnology rebarring technology
Details of the Construction Materials learned today plywood,plaster,putty drill machine,strips of bar,chemicals
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today farming drawing
Details of the Bye Laws referred today for road dimensions 10 m width,setback line 10.5m
Details of any Managerial Skill learned today drilling hole for rebarring
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for external plastering for 20mm thick plastring sand=1*1*0.02=0.02m3 for getting 0.02m3 sand for plastering we require double sand=2*0.02=0.04m3 rate of sand=0.04*1411rs=57rs cement required=0.25bag*250rs=62.50rs material cost=57+62.50=120rs labour cost=5ft2*10.76=54rs total cost=120+54=174rs
Result of RATE ANALYSIS ( Rs per Unit ) 174rs/m2
Todays BUZZ Word billing department preperation of bills at sites weekly or fortnightly by jnior engg. with measurement sheets and sketches checking of bills by project engg. in detail submission of bills along with sketches and all required supported document to billing devision bill entry in inward registereed at office bills recieved by billing engg, with sign an date in register checking by billing engg,preparing payment challan and certification for net payments checking and approval by chief engg. bills to a/c ept with proper entry in register checing of bills by a/c dept. sign of irector on cheque entry f check details in account register/computer forwarding of checks to billing engg. from a/c dept. counter sign of contractor in cheque issue register entry of cheques in resective contractors file by billing engg
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Camera, Bye Law Book, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SATISH 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-07

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Ramchandra
Exam No. 13557
Working Day No. 07
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about the footing such as combined footing, trapezoidal footing etc.
Details of how you Planned & Executed the allotted work * First we observe the actual plan of footing * Then according to plan construct the formwork around the reinforcement.
Details of the Construction Procedure / Activity / Technology learned today * Murum filling by POCLAND(JCB) equipment. * Steel bar cutting by using steel cutter. * Steel formwork of staircase, footing, cantilever, etc. * Casting of beam and staircase etc.
Details of the Construction Materials learned today * Special steel cutting equipment for cutting steel bars. * Needle vibrator * Tamping rod * Roller * Cement 43 grade. * Admixture * Aggregate 20-25 mm * Sand- river sand * Steel- main bars 20,18 mm etc. * anchor bar 12mm stirrups 8mm & 6mm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly-ash bricks used for brick work.
Details of the Construction / Engineering Drawings observed today * Footing layout plan. * Working drawing. * Electrification drawing
Details of the Bye Laws referred today PLINTH- * The height of plinth shall not be less than 0.45m above the ground level provided. * Shops plinth height may be 0.3m provided.
Details of any Managerial Skill learned today * Maintain the quaility of work. * Control on wastage material. * Maintain cleanliness of the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) External Plastering (1:3) a) Material required for plastering for 100m2 unit per m2 b) Dry quantity of C.M. required for 100m2 for 12mm thik. plastering in C.M. 1:3 in 2m3 1) cement = 2/(1+3) = 0.5m3 no. bags= 0.5/0.034= 14.7= 15bags. 2) Sand = 0.5 x 3 = 1.5m3 SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 15 bags 250.00/- 3750.00/- b) sand 1.5 cum 850.00/- (per cum) 1275.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) mason 10 no. 200.00/- 2000.00/- c) male mazdur 15 no. 160.00/- 2400.00/- d) bhisti 1 no. 120.00/- 240.00/- 3 Others _ TOTAL 9965.00/- 4 Tools and plant @ 1.5% ----------------------- 150.00/- on total 5 Water charges @ 1.0% ----------------------- 100.00/- on total TOTAL(A) 10215.00/- 6 Overhead and profit @ 15% on tOtal A ----------------------- 1532.00/- -------------------------------------------------------------------------- TOTAL = 11750.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 11750/- per 100m2
Todays BUZZ Word Advance bills- * For material contract the advance bill can be prepared against the material dumped on site by contractor. * Advance bill should be prepared on standard format that is payment challan. R.A. bills- * This bill are prepared at the site for workdone. * These bills should be prepared every for night * Normally payments to contractors are done on weekly basis. CASH bills- * This bill required to be prepared for the payments for the following items. * Weekly payments for the department labourers * Petty contractors for small work/job work FINAL bills- * This bills should be cleared after 100% completion of the work by the contractor. * Joints measurement should be taken by the engineer along with the contractor.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr .Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-07

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Students Name (Surname_First Name_Middle Name) Sutar Namdev Rangnath
Exam No. 13571
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge 1) Finding out the requirement of M-15 grade concrete for slab of proposed building. 2) Calculate the steel reinforce required for slab.
Details of how you Planned & Executed the allotted work First we divide our group in to two sub groups out of it one group worked on , 1)Calculating quantity of concrete required a)first find the all inner dimensions of slab from detailed structural drawing. b)Multiply with thickness of slab & find gross quantity. c)Add all gross quantity of slab calculated above. d) Separately calculate quantity of concrete laying above beam excluding depth of beam. e)Add all above quantity of slab & beam. Second group worked on 1)calculation of steel reinforcement:- a)Prepare bar bending schedule table b)Find length of bar on both way for two way slab & one length for one way slab. c)Find length of curtail bar whichever provided . d)Add total length as per diameter of bar . e)note down all values in table systematically.
Details of the Construction Procedure / Activity / Technology learned today 1) Reading of reinforce drawing on site. 2) Placing of steel for slab & for beam. 3)Removal of form work. 4)Precautions taken during removal of form work. 5)Arrangement for height of supports of form work.
Details of the Construction Materials learned today Quality of wood used for form work. M-15 grade of concrete. Admixtures used in concrete making.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel supports used for form work are more eco friendly compare to wood works.
Details of the Construction / Engineering Drawings observed today 1)reinforce detailed drawing for slab & beam. 2)Municiple drawing
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment.
Details of any Managerial Skill learned today How to manage the labour force & time ,quality of concreting work ,steel distribution economy during casting of slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012=0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012=0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 . cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=890Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs ( Rs per Unit ): 980.58Rs
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal MN. 943281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: mayur.sonawane61@gmail.com
Subject: 13570-07

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Students Name (Surname_First Name_Middle Name) Sonawane Mayur Madhukar
Exam No. 13570
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge 1) Finding out the requirement of M-15 grade concrete for slab of proposed building. 2) Calculate the steel reinforce required for slab. .
Details of how you Planned & Executed the allotted work First we divide our group in to two sub groups out of it one group worked on , 1)Calculating quantity of concrete required a)first find the all inner dimensions of slab from detailed structural drawing. b)Multiply with thickness of slab & find gross quantity. c)Add all gross quantity of slab calculated above. d) Separately calculate quantity of concrete laying above beam excluding depth of beam. e)Add all above quantity of slab & beam. Second group worked on 1)calculation of steel reinforcement:- a)Prepare bar bending schedule table b)Find lengthttp://www.profiip.blogspot.com/h of bar on both way for two way slab & one length for one way slab. c)Find length of curtail bar whichever provided . d)Add total length as per diameter of bar . e)note down all values in table systematically. .
Details of the Construction Procedure / Activity / Technology learned today 1) Reading of reinforce drawing on site. 2) Placing of steel for slab & for beam. 3)Removal of form work. 4)Precautions taken during removal of form work. 5)Arrangement for height of supports of form work. . .
Details of the Construction Materials learned today Quality of wood used for form work. M-15 grade of concrete. Admixtures used in concrete making. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel supports used for form work are more eco friendly compare to wood works. .
Details of the Construction / Engineering Drawings observed today 1)reinforce detailed drawing for slab & beam. 2)Municiple drawing .
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment. .
Details of any Managerial Skill learned today How to manage the labour force & time ,quality of concreting work ,steel distribution economy during casting of slab. .
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012=0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012=0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 . cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=890Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs ( Rs per Unit ): 980.58Rs
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal MN. 943281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883-07

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) saurabh arora
Exam No. 10883
Working Day No. 06
Date (DD/MM/YYYY) 15/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge We were told to view rebarring to view how POP is done cleaning of road before construction
Details of how you Planned & Executed the allotted work We observed carefully the working done for POP its working and finishing done electrification work in pop was also observed In rebarring hole was drilled along with chemical to bar to fix it by workers road was cleaned by simple means with broomers
Details of the Construction Procedure / Activity / Technology learned today POP tecgnology rebarring technology
Details of the Construction Materials learned today plywood,plaster,putty drill machine,strips of bar,chemicals
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today farming drawing
Details of the Bye Laws referred today for road dimensions 10 m width,setback line 10.5m
Details of any Managerial Skill learned today drilling hole for rebarring
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for external plastering for 20mm thick plastring sand=1*1*0.02=0.02m3 for getting 0.02m3 sand for plastering we require double sand=2*0.02=0.04m3 rate of sand=0.04*1411rs=57rs cement required=0.25bag*250rs=62.50rs material cost=57+62.50=120rs labour cost=5ft2*10.76=54rs total cost=120+54=174rs
Result of RATE ANALYSIS ( Rs per Unit ) 174rs/m2
Todays BUZZ Word billing department preperation of bills at sites weekly or fortnightly by jnior engg. with measurement sheets and sketches checking of bills by project engg. in detail submission of bills along with sketches and all required supported document to billing devision bill entry in inward registereed at office bills recieved by billing engg, with sign an date in register checking by billing engg,preparing payment challan and certification for net payments checking and approval by chief engg. bills to a/c ept with proper entry in register checing of bills by a/c dept. sign of irector on cheque entry f check details in account register/computer forwarding of checks to billing engg. from a/c dept. counter sign of contractor in cheque issue register entry of cheques in resective contractors file by billing engg
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 9
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-07

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Students Name (Surname_First Name_Middle Name) Shivtare Prabhakar Chandrakant
Exam No. 1369
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge 1) Finding out the requirement of M-15 grade concrete for slab of proposed building. 2) Calculate the steel reinforce required for slab. .
Details of how you Planned & Executed the allotted work First we divide our group in to two sub groups out of it one group worked on , 1)Calculating quantity of concrete required a)first find the all inner dimensions of slab from detailed structural drawing. b)Multiply with thickness of slab & find gross quantity. c)Add all gross quantity of slab calculated above. d) Separately calculate quantity of concrete laying above beam excluding depth of beam. e)Add all above quantity of slab & beam. Second group worked on 1)calculation of steel reinforcement:- a)Prepare bar bending schedule table b)Find length of bar on both way for two way slab & one length for one way slab. c)Find length of curtail bar whichever provided . d)Add total length as per diameter of bar . e)note down all values in table systematically. .
Details of the Construction Procedure / Activity / Technology learned today 1) Reading of reinforce drawing on site. 2) Placing of steel for slab & for beam. 3)Removal of form work. 4)Precautions taken during removal of form work. 5)Arrangement for height of supports of form work. .
Details of the Construction Materials learned today Quality of wood used for form work. M-15 grade of concrete. Admixtures used in concrete making. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel supports used for form work are more eco friendly compare to wood works. .
Details of the Construction / Engineering Drawings observed today 1)reinforce detailed drawing for slab & beam. 2)Municiple drawing .
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment. .
Details of any Managerial Skill learned today How to manage the labour force & time ,quality of concreting work ,steel distribution economy during casting of slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012=0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012=0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 . cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=890Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs ( Rs per Unit ): 980.58Rs
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pradip Bharamal MN. 943281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-07

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Students Name (Surname_First Name_Middle Name) Shinde Sagar Arvind
Exam No. 13568
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge 1) Finding out the requirement of M-15 grade concrete for slab of proposed building. 2) Calculate the steel reinforce required for slab. .
Details of how you Planned & Executed the allotted work First we divide our group in to two sub groups out of it one group worked on , 1)Calculating quantity of concrete required a)first find the all inner dimensions of slab from detailed structural drawing. b)Multiply with thickness of slab & find gross quantity. c)Add all gross quantity of slab calculated above. d) Separately calculate quantity of concrete laying above beam excluding depth of beam. e)Add all above quantity of slab & beam. Second group worked on 1)calculation of steel reinforcement:- a)Prepare bar bending schedule table b)Find length of bar on both way for two way slab & one length for one way slab. c)Find length of curtail bar whichever provided . d)Add total length as per diameter of bar . e)note down all values in table systematically. .
Details of the Construction Procedure / Activity / Technology learned today 1) Reading of reinforce drawing on site. 2) Placing of steel for slab & for beam. 3)Removal of form work. 4)Precautions taken during removal of form work. 5)Arrangement for height of supports of form work. .
Details of the Construction Materials learned today Quality of wood used for form work. M-15 grade of concrete. Admixtures used in concrete making. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel supports used for form work are more eco friendly compare to wood works. .
Details of the Construction / Engineering Drawings observed today 1)reinforce detailed drawing for slab & beam. 2)Municiple drawing .
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment. .
Details of any Managerial Skill learned today How to manage the labour force & time ,quality of concreting work ,steel distribution economy during casting of slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012=0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012=0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 . cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=890Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs ( Rs per Unit ): 980.58Rs
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal MN. 943281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/15/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 13567-07

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 07
Date (DD/MM/YYYY) 15-12-2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge 1) Finding out the requirement of M-15 grade concrete for slab of proposed building. 2) Calculate the steel reinforce required for slab. .
Details of how you Planned & Executed the allotted work First we divide our group in to two sub groups out of it one group worked on , 1)Calculating quantity of concrete required a)first find the all inner dimensions of slab from detailed structural drawing. b)Multiply with thickness of slab & find gross quantity. c)Add all gross quantity of slab calculated above. d) Separately calculate quantity of concrete laying above beam excluding depth of beam. e)Add all above quantity of slab & beam. Second group worked on 1)calculation of steel reinforcement:- a)Prepare bar bending schedule table b)Find length of bar on both way for two way slab & one length for one way slab. c)Find length of curtail bar whichever provided . d)Add total length as per diameter of bar . e)note down all values in table systematically. .
Details of the Construction Procedure / Activity / Technology learned today 1) Reading of reinforce drawing on site. 2) Placing of steel for slab & for beam. 3)Removal of form work. 4)Precautions taken during removal of form work. 5)Arrangement for height of supports of form work. .
Details of the Construction Materials learned today Quality of wood used for form work. M-15 grade of concrete. Admixtures used in concrete making. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Steel supports used for form work are more eco friendly compare to wood works. .
Details of the Construction / Engineering Drawings observed today 1)reinforce detailed drawing for slab & beam. 2)Municiple drawing .
Details of the Bye Laws referred today 1)Height to side margin ratio for apartment. 2)Overlapping of road in residential & commercial area. 3)Minimum side margin for apartment. .
Details of any Managerial Skill learned today How to manage the labour force & time ,quality of concreting work ,steel distribution economy during casting of slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) External plaster:- 25 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 25 mm plaster= 1*0.012=0.012m3 add 30% for filling up uneven surface= (0.012*30/100)+0.012=0.0156 Add 25% of dry volume = 0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 . cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=890Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs ( Rs per Unit ): 980.58Rs
Result of RATE ANALYSIS ( Rs per Unit ) Rs.980.58
Todays BUZZ Word Billing department includes following stepwise procedure 1. Prepare site wise file for each counter 2. Study the contractor agreement. 3. Record day to day departmental labour engaged on each site. 4. Visit site on weekly basis. 5. Cross check departmental labour bills,contractor bills submitted by site for presentation,detailing,accuracy and work out net payable amount to contractor considering retention,advance payment & previous paid amount. 6. maintain record for every contractors advance,up to date payments etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.Pradip Bharamal MN. 943281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10893-06

Company Name V. S. Joshi & Associates
Project Name & Site Address VVishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) kamble ankit
Exam No. 10893
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.30AM
Site Leaving Time (HH:MM am/pm) 5.30PM
Details of the Work Allotted to you today by the Site In-Charge 1. To Study various Tiling Floor with their Specifications. 2. To Study \"Preparation of Base for Flooring\". 3. To Study \"Laying of Tiles\".
Details of how you Planned & Executed the allotted work 1. We all together (5 members) in our group went to Flat No. 408, to study the various aspects required before & after Flooring work. 2. We observed various aspects such as \"Preparation of Base for Flooring in Kitchen Balcony\" & \"Laying of tiles in Master Bed Terrace\".
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR VITRIFIED TILE FLOORING WORK\" # - Prepare Cement slurry in Ratio of 1.5 Bag : 100 Litre of water approximately. - Start Fixing Tiles from reference line & reference tiles diagonally. - Spread the Cement Slurry on Mortar Bed. - Match all the four corners of Tiles properly with the help of \'Wooden Mallet\'. - Fix the \'Mosic Tiles\' in particular sequence. - After completing the tiling work check the overall level - Clean the floor & do not allow anybody to enter the flat for minimum 24 hours. - Next day fill the \"Gap joints\" between tiles with cement slurry. - Cure it for 14 days minimum ---------------------------------------------------------------------------------- # \"Vitrified Tile Skirting\" # - With the help of \"Wooden Farma\", Skirting Tile was fixed, projecting only 8 mm from Wall Plaster. - Keep the skirting in one line. - Fix skirting at two corners & fix the line dori as a guide line for line of the in between skirting. - At columns positions Skirting should be sliced in vertical direction. - Ensure that skirting lines are perpendicular to the vitrified tile line. Details of the Construction Materials learned today: 1. PCC - Ratio of 1:4:8 ( M-10 Grade Concrete ). 2. Anti Skid Tiles. - 16\" x 16\" ( Regency Brand ). 3. Vitrified Tiles. - 2\' x 2\' ( Commet Brand ). 4. White Cement Putty - Wall Shine ( Creamcem Brand).
Details of the Construction Materials learned today 1. PCC - Ratio of 1:4:8 ( M-10 Grade Concrete ). 2. Anti Skid Tiles. - 16\" x 16\" ( Regency Brand ). 3. Vitrified Tiles. - 2\' x 2\' ( Commet Brand ). 4. White Cement Putty - Wall Shine ( Creamcem Brand).
Details of Environment Caring Technology / Methodology / Procedure / Product learned today For ordinary construction works \"crushed sand\" was used instead of natural sand.
Details of the Construction / Engineering Drawings observed today Details of Upflow Filter & Baffle wall of septic tank. - Septic Tank Details. - Service Layout for \"C-Wing\" - Details of perforated RCC Slab. - Details of anerobic filter.
Details of the Bye Laws referred today Details of the Bye Laws referred today: FSI related Details - pg 80 - Septic Tank Details - pg 104
Details of any Managerial Skill learned today - Punctuality. - Keeping mind cool even in stressed situations.
RATE ANALYSIS (Detailed Stepwise Calculations required) # INTERNAL PLASTER # 12 mm thick plaster in single coat for : 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bed Room = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bath Room = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m Deductions for : 1. D1 = 2.6 sq.m 2. D2 = 13.2 sq.m 3. D3 = 3.3 sq.m 4. W1 = 11.2 sq.m 5. W2 = 2.8 sq.m 6. W3 = 0.9 sq.m 7. Grill = 3 sq.m TOTAL = 37 sq.m Deduct 50% = 218.21 - (37/2) = 199.71 sq.m Therefore Area of Plaster 199.71 sq.m Volume of plaster = 2.4 cu.m Add 50% for voids & 10% for uneveness : Dry Vol of mortar = 3.84 cu.m Cement = 28 bags Sand = 2.88 cu.m B) Cost of Materials : 1. Cement = 28 x 230 = 6440/- 2. Sand = 2.9 x 850 = 8905/- C) Cost of Labours : 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 1 x 110 = 110/- 5. Scaffolding = 300/- 6. T&P = 300/- TOTAL = 4760 x 2 = 9520/- D) TOTAL = B + C = 18425/- E) Add 2% for water charges = 368.5/- F) Add 15% for contractors profit = 2763.75/- G) Grand Total = 21557.25/- H) Rate per sq.m = Rs. 107.94/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 107.94/-
Todays BUZZ Word The following shall not be counted under F.S.I. calculations: 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge amol mule
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-2

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bauchakar deepak yuvaraj
Exam No. 13554
Working Day No. 2
Date (DD/MM/YYYY) 10/12/10
Site Reporting Time (HH:MM am/pm) 10am
Site Leaving Time (HH:MM am/pm) 4:45pm
Details of the Work Allotted to you today by the Site In-Charge Told us to find the no. of bricks required quantity of sand , Cement etc and thus find the amount required for contruction of wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose
Details of the Construction Procedure / Activity / Technology learned today - We learnt about the Rebaring of beams. 1)First holes of 7\" are drilled by using drilling machine. 2)Than a solution of Adhesoin known as \"GERMAN FISHER CHEMICALS\" was appilied in the hole. 3)Than steel bars of 12mm were hammered and thus rebarring was done.
Details of the Construction Materials learned today - Adhesion material known as \"GERMAN FISHER CHEMICAL\" - Quantity of tube avaliable is 345ml of cost 1150/- per tube
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today For the purpose of Rebaring we observed the structural design(SLAB) of that particular floor.
Details of the Bye Laws referred today About loft - lintel.
Details of any Managerial Skill learned today 1) Brickwork 2) Lintels 3) Lofts
RATE ANALYSIS (Detailed Stepwise Calculations required) Size of Beam = 11\'*9\"*6\" Total volume of the Beam = 5.94 cu.ft Matreial Required. 1. Cement = 2 Bags 2. Sand = 4.1 cu.ft 3. Aggregate = 4.25 cu.ft 4. Steel= 20kg 5. Labour charge = 500/- Total= 2406/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 406
Todays BUZZ Word \"CONTRACTORS\" 1.Centering contractor 2. Labour contractor 3. Material supply contractor. 4.Plumbing contractor 5. Water-proofing contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-2

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bhoite vishal rajaram
Exam No. 13555
Working Day No. 2
Date (DD/MM/YYYY) 10/12/10
Site Reporting Time (HH:MM am/pm) 10am
Site Leaving Time (HH:MM am/pm) 4:45pm
Details of the Work Allotted to you today by the Site In-Charge Told us to find the no. of bricks required quantity of sand , Cement etc and thus find the amount required for contruction of wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose
Details of the Construction Procedure / Activity / Technology learned today - We learnt about the Rebaring of beams. 1)First holes of 7\" are drilled by using drilling machine. 2)Than a solution of Adhesoin known as \"GERMAN FISHER CHEMICALS\" was appilied in the hole. 3)Than steel bars of 12mm were hammered and thus rebarring was done.
Details of the Construction Materials learned today - Adhesion material known as \"GERMAN FISHER CHEMICAL\" - Quantity of tube avaliable is 345ml of cost 1150/- per tube
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today For the purpose of Rebaring we observed the structural design(SLAB) of that particular floor.
Details of the Bye Laws referred today About loft - lintel.
Details of any Managerial Skill learned today 1) Brickwork 2) Lintels 3) Lofts
RATE ANALYSIS (Detailed Stepwise Calculations required) Size of Beam = 11\'*9\"*6\" Total volume of the Beam = 5.94 cu.ft Matreial Required. 1. Cement = 2 Bags 2. Sand = 4.1 cu.ft 3. Aggregate = 4.25 cu.ft 4. Steel= 20kg 5. Labour charge = 500/- Total= 2406/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 406
Todays BUZZ Word \"CONTRACTORS\" 1.Centering contractor 2. Labour contractor 3. Material supply contractor. 4.Plumbing contractor 5. Water-proofing contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-06

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell,karande mala
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To Study various Tiling Floor with their Specifications. 2. To Study \"Preparation of Base for Flooring\". 3. To Study \"Laying of Tiles\".
Details of how you Planned & Executed the allotted work 1. We all together (5 members) in our group went to Flat No. 408, to study the various aspects required before & after Flooring work. 2. We observed various aspects such as \"Preparation of Base for Flooring in Kitchen Balcony\" & \"Laying of tiles in Master Bed Terrace\".
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR VITRIFIED TILE FLOORING WORK\" # - Prepare Cement slurry in Ratio of 1.5 Bag : 100 Litre of water approximately. - Start Fixing Tiles from reference line & reference tiles diagonally. - Spread the Cement Slurry on Mortar Bed. - Match all the four corners of Tiles properly with the help of \'Wooden Mallet\'. - Fix the \'Mosic Tiles\' in particular sequence. - After completing the tiling work check the overall level - Clean the floor & do not allow anybody to enter the flat for minimum 24 hours. - Next day fill the \"Gap joints\" between tiles with cement slurry. - Cure it for 14 days minimum ---------------------------------------------------------------------------------- # \"Vitrified Tile Skirting\" # - With the help of \"Wooden Farma\", Skirting Tile was fixed, projecting only 8 mm from Wall Plaster. - Keep the skirting in one line. - Fix skirting at two corners & fix the line dori as a guide line for line of the in between skirting. - At columns positions Skirting should be sliced in vertical direction. - Ensure that skirting lines are perpendicular to the vitrified tile line.
Details of the Construction Materials learned today 1. PCC - Ratio of 1:4:8 ( M-10 Grade Concrete ). 2. Anti Skid Tiles. - 16\" x 16\" ( Regency Brand ). 3. Vitrified Tiles. - 2\' x 2\' ( Commet Brand ). 4. White Cement Putty - Wall Shine ( Creamcem Brand).
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today 1. Steel Scaffolding Drawings for Lift & Duct for Plastering purpose. 2. Floor Plans.
Details of the Bye Laws referred today # Parking Bye-Laws # 1. Motar Vehicle - 2.5 m x 5.5 m. 2. Motor Cycle - 3 sq.m.
Details of any Managerial Skill learned today How to convience a customer. How to Bargain with the dealer.
RATE ANALYSIS (Detailed Stepwise Calculations required) # INTERNAL PLASTER # 12 mm thick plaster in single coat for : 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bed Room = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bath Room = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m Deductions for : 1. D1 = 2.6 sq.m 2. D2 = 13.2 sq.m 3. D3 = 3.3 sq.m 4. W1 = 11.2 sq.m 5. W2 = 2.8 sq.m 6. W3 = 0.9 sq.m 7. Grill = 3 sq.m TOTAL = 37 sq.m Deduct 50% = 218.21 - (37/2) = 199.71 sq.m Therefore Area of Plaster 199.71 sq.m Volume of plaster = 2.4 cu.m Add 50% for voids & 10% for uneveness : Dry Vol of mortar = 3.84 cu.m Cement = 28 bags Sand = 2.88 cu.m B) Cost of Materials : 1. Cement = 28 x 230 = 6440/- 2. Sand = 2.9 x 850 = 8905/- C) Cost of Labours : 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 1 x 110 = 110/- 5. Scaffolding = 300/- 6. T&P = 300/- TOTAL = 4760 x 2 = 9520/- D) TOTAL = B + C = 18425/- E) Add 2% for water charges = 368.5/- F) Add 15% for contractors profit = 2763.75/- G) Grand Total = 21557.25/- H) Rate per sq.m = Rs. 107.94/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 107.94/-
Todays BUZZ Word The following shall not be counted under F.S.I. calculations: 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-5

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bauchakar deepak yuvaraj
Exam No. 13554
Working Day No. 5
Date (DD/MM/YYYY) 14/12/10
Site Reporting Time (HH:MM am/pm) 9:50 am
Site Leaving Time (HH:MM am/pm) 5 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To see the work going on of plumbing 2. To see the work of plastering. 3. To estimate the plastering cost.
Details of how you Planned & Executed the allotted work - We group of five were divided in two groups - First group for half time we saw the plumbing - Second we saw the plastering, and vice-versa. - Then we measured the room and calculated the plastering.
Details of the Construction Procedure / Activity / Technology learned today - About plumbing - Plastering - Dealing with labours
Details of the Construction Materials learned today - About the water proofing material \"DR. FIXIT\".
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - none
Details of the Construction / Engineering Drawings observed today - Plumbing Drawing - Floor plans.
Details of the Bye Laws referred today - For plumbing - For plastering.
Details of any Managerial Skill learned today - Punctuality is the key to success
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost= 39.0+16.875= Rs55.87 labor = mason1= Rs250 labor= Rs140 total= Rs390 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13
Result of RATE ANALYSIS ( Rs per Unit ) Rs530.58
Todays BUZZ Word The following shall not be counted during F.S.I. 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: prasadkharat@ymail.com
Subject: 13531-06

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Prasad Ramachandra
Exam No. 13531
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the electrical plans
Details of how you Planned & Executed the allotted work we get electical plan from site engineer.we went on the second floor slab and observe electrical points.consiled wiring is provided.20mm.dia.pipe is used for wiring
Details of the Construction Procedure / Activity / Technology learned today conciled wiring- P.V.C.material pipes are used for consiled wiring.consiled wiring electical plans are used provided by ARCHITECTURE.it is very economical wiring method than other type of wiring method
Details of the Construction Materials learned today scafolding- scafolding is used for various perposes.it is used for brick work,plaster and penting
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of alluminium and iron frames for door and window dicreases plant cutting
Details of the Construction / Engineering Drawings observed today electrical drawing-conceled wiring fan points,lamp points,powerplug points
Details of the Bye Laws referred today min.area of kitchen=5.75 sq.m. living room=9 sq.m.
Details of any Managerial Skill learned today polliteness and co-operative
RATE ANALYSIS (Detailed Stepwise Calculations required) assume 10 sq.m.area for plastering thickness of plaster=12mm. =0.012m. total volume =10*0.012 =0.12 cu.m. add 50% for dry volume=0.18 cu.m. no of bags=0.18/(1+4)=0.036 cu.m.=1.27 cu.m.----say 10 bags sand=0.036*4 =0.144 cu.m=5 cu ft.=0.144*1060=152.65 Rs. say 160Rs. Labour =350Rs. per brass 400 Rs. increase 1.5% water cost =883.05Rs. contractor profit =15% =1015Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1015Rs. for 10 sq.m. wall
Todays BUZZ Word Balcony =10% of total built up area Terrace- 12% of total built up area stare case - Landing width > 2m. cupboard projected to margin
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-06

Company Name V. S. Joshi & Associates
Project Name & Site Address vishwa enclave
Students Name (Surname_First Name_Middle Name) janbandhu rakshit d.
Exam No. 10875
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 5.30 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To Study various Tiling Floor with their Specifications. 2. To Study \"Preparation of Base for Flooring\". 3. To Study \"Laying of Tiles\".
Details of how you Planned & Executed the allotted work 1. We all together (5 members) in our group went to Flat No. 408, to study the various aspects required before & after Flooring work. 2. We observed various aspects such as \"Preparation of Base for Flooring in Kitchen Balcony\" & \"Laying of tiles in Master Bed Terrace\".
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR VITRIFIED TILE FLOORING WORK\" # - Prepare Cement slurry in Ratio of 1.5 Bag : 100 Litre of water approximately. - Start Fixing Tiles from reference line & reference tiles diagonally. - Spread the Cement Slurry on Mortar Bed. - Match all the four corners of Tiles properly with the help of \'Wooden Mallet\'. - Fix the \'Mosic Tiles\' in particular sequence. - After completing the tiling work check the overall level - Clean the floor & do not allow anybody to enter the flat for minimum 24 hours. - Next day fill the \"Gap joints\" between tiles with cement slurry. - Cure it for 14 days minimum ---------------------------------------------------------------------------------- # \"Vitrified Tile Skirting\" # - With the help of \"Wooden Farma\", Skirting Tile was fixed, projecting only 8 mm from Wall Plaster. - Keep the skirting in one line. - Fix skirting at two corners & fix the line dori as a guide line for line of the in between skirting. - At columns positions Skirting should be sliced in vertical direction. - Ensure that skirting lines are perpendicular to the vitrified tile line.
Details of the Construction Materials learned today 1. PCC - Ratio of 1:4:8 ( M-10 Grade Concrete ). 2. Anti Skid Tiles. - 16\" x 16\" ( Regency Brand ). 3. Vitrified Tiles. - 2\' x 2\' ( Commet Brand ). 4. White Cement Putty - Wall Shine ( Creamcem Brand).
Details of Environment Caring Technology / Methodology / Procedure / Product learned today For ordinary construction works \"crushed sand\" was used instead of natural sand.
Details of the Construction / Engineering Drawings observed today Details of Upflow Filter & Baffle wall of septic tank. - Septic Tank Details. - Service Layout for \"C-Wing\" - Details of perforated RCC Slab. - Details of anerobic filter.
Details of the Bye Laws referred today FSI related Details - pg 80 - Septic Tank Details - pg 104
Details of any Managerial Skill learned today - Punctuality. - Keeping mind cool even in stressed situations.
RATE ANALYSIS (Detailed Stepwise Calculations required) # INTERNAL PLASTER # 12 mm thick plaster in single coat for : 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bed Room = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bath Room = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m Deductions for : 1. D1 = 2.6 sq.m 2. D2 = 13.2 sq.m 3. D3 = 3.3 sq.m 4. W1 = 11.2 sq.m 5. W2 = 2.8 sq.m 6. W3 = 0.9 sq.m 7. Grill = 3 sq.m TOTAL = 37 sq.m Deduct 50% = 218.21 - (37/2) = 199.71 sq.m Therefore Area of Plaster 199.71 sq.m Volume of plaster = 2.4 cu.m Add 50% for voids & 10% for uneveness : Dry Vol of mortar = 3.84 cu.m Cement = 28 bags Sand = 2.88 cu.m B) Cost of Materials : 1. Cement = 28 x 230 = 6440/- 2. Sand = 2.9 x 850 = 8905/- C) Cost of Labours : 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 1 x 110 = 110/- 5. Scaffolding = 300/- 6. T&P = 300/- TOTAL = 4760 x 2 = 9520/- D) TOTAL = B + C = 18425/- E) Add 2% for water charges = 368.5/- F) Add 15% for contractors profit = 2763.75/- G) Grand Total = 21557.25/- H) Rate per sq.m = Rs. 107.94/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 107.94/-
Todays BUZZ Word The following shall not be counted under F.S.I. calculations: 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge amol mule
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-06

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Patil Vrishali Vitthal
Exam No. 13541
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the electrical plans
Details of how you Planned & Executed the allotted work we get electical plan from site engineer.we went on the second floor slab and observe electrical points.consiled wiring is provided.20mm.dia.pipe is used for wiring
Details of the Construction Procedure / Activity / Technology learned today conciled wiring- P.V.C.material pipes are used for consiled wiring.consiled wiring electical plans are used provided by ARCHITECTURE.it is very economical wiring method than other type of wiring method
Details of the Construction Materials learned today scafolding- scafolding is used for various perposes.it is used for brick work,plaster and penting
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of alluminium and iron frames for door and window dicreases plant cutting
Details of the Construction / Engineering Drawings observed today electrical drawing-conceled wiring fan points,lamp points,powerplug points
Details of the Bye Laws referred today min.area of kitchen=5.75 sq.m. living room=9 sq.m.
Details of any Managerial Skill learned today polliteness and co-operative
RATE ANALYSIS (Detailed Stepwise Calculations required) assume 10 sq.m.area for plastering thickness of plaster=12mm. =0.012m. total volume =10*0.012 =0.12 cu.m. add 50% for dry volume=0.18 cu.m. no of bags=0.18/(1+4)=0.036 cu.m.=1.27 cu.m.----say 10 bags sand=0.036*4 =0.144 cu.m=5 cu ft.=0.144*1060=152.65 Rs. say 160Rs. Labour =350Rs. per brass 400 Rs. increase 1.5% water cost =883.05Rs. contractor profit =15% =1015Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1015Rs. for 10 sq.m. wall
Todays BUZZ Word Balcony =10% of total built up area Terrace- 12% of total built up area stare case - Landing width > 2m. cupboard projected to margin
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: vishlr2844@gmail.com
Subject: 13555-5

Company Name Shendre Associates
Project Name & Site Address : Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) bhoite vishal rajaram
Exam No. 13555
Working Day No. 5
Date (DD/MM/YYYY) 14/12/10
Site Reporting Time (HH:MM am/pm) 9:50 am
Site Leaving Time (HH:MM am/pm) 5 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To see the work going on of plumbing 2. To see the work of plastering. 3. To estimate the plastering cost.
Details of how you Planned & Executed the allotted work - We group of five were divided in two groups - First group for half time we saw the plumbing - Second we saw the plastering, and vice-versa. - Then we measured the room and calculated the plastering.
Details of the Construction Procedure / Activity / Technology learned today - About plumbing - Plastering - Dealing with labours
Details of the Construction Materials learned today - About the water proofing material \"DR. FIXIT\".
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - none
Details of the Construction / Engineering Drawings observed today - Plumbing Drawing - Floor plans.
Details of the Bye Laws referred today - For plumbing - For plastering.
Details of any Managerial Skill learned today - Punctuality is the key to success
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost= 39.0+16.875= Rs55.87 labor = mason1= Rs250 labor= Rs140 total= Rs390 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13
Result of RATE ANALYSIS ( Rs per Unit ) Rs530.58
Todays BUZZ Word The following shall not be counted during F.S.I. 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-06

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.09 p.m.
Details of the Work Allotted to you today by the Site In-Charge Work allotted today: -To see the pile formation in the strata -To see the casting of plinth beam -to see the erection of the formwork for slab.
Details of how you Planned & Executed the allotted work Ist we observed & see the pile formation and take all details We see the casting of plinth beam Then we see & taking notes about erection of form work for slab
Details of the Construction Procedure / Activity / Technology learned today Procedure : Pile formation: 1) First dia. Is decided for formation of pile . 2) Pile core are placed on ground. 3) The pile formation which we saw was manual one. Casting of the plinth beam: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. Erection of forwork: 1) First level is taken with the help of level tube. 2) Then with the help of bamboo , wooden planks & marine ply & nails form work is prepared for slab.
Details of the Construction Materials learned today Steel : 6mm,12mm,16mm,20mm Concrete : M-20 Bamboo : For formwork Marine ply wood CPVC pipe APVC Pipe
Details of Environment Caring Technology / Methodology / Procedure / Product learned today CFL bulbs are used for saving electrical energy.
Details of the Construction / Engineering Drawings observed today Detail drawing of slab & beam for formation of formwork
Details of the Bye Laws referred today L/B Ratio for every room is 1.2 to 1.5 which is according to the byelaws.
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor.
RATE ANALYSIS (Detailed Stepwise Calculations required) PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Quantity of mortar = 0.4cub.m (0.2 cub.m for 10sq.m) Qt. of cement = 0.4/4 = 0.1 cub.m No. of bags of cement = 0.1/0.035 = 2.85 = say 3no.of bags Qt. of sand = 3* 0.1 = 0.3 cub.m Particular Quantity/No. Rate Cost Material Cement 3 bags 255 765Rs/- Sand 0.3 cub.m 1644 493.2Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Total = 2748 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 3298Rs/- Rate per sq.m= 165 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 165 Rs/- per unit
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.per Unit ): 300.00 Rs per sq.m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-06

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.09 p.m.
Details of the Work Allotted to you today by the Site In-Charge Work allotted today: -To see the pile formation in the strata -To see the casting of plinth beam -to see the erection of the formwork for slab.
Details of how you Planned & Executed the allotted work Ist we observed & see the pile formation and take all details We see the casting of plinth beam Then we see & taking notes about erection of form work for slab
Details of the Construction Procedure / Activity / Technology learned today Procedure : Pile formation: 1) First dia. Is decided for formation of pile . 2) Pile core are placed on ground. 3) The pile formation which we saw was manual one. Casting of the plinth beam: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. Erection of forwork: 1) First level is taken with the help of level tube. 2) Then with the help of bamboo , wooden planks & marine ply & nails form work is prepared for slab.
Details of the Construction Materials learned today Steel : 6mm,12mm,16mm,20mm Concrete : M-20 Bamboo : For formwork Marine ply wood CPVC pipe APVC Pipe
Details of Environment Caring Technology / Methodology / Procedure / Product learned today CFL bulbs are used for saving electrical energy.
Details of the Construction / Engineering Drawings observed today Detail drawing of slab & beam for formation of formwork
Details of the Bye Laws referred today L/B Ratio for every room is 1.2 to 1.5 which is according to the byelaws.
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor.
RATE ANALYSIS (Detailed Stepwise Calculations required) PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Quantity of mortar = 0.4cub.m (0.2 cub.m for 10sq.m) Qt. of cement = 0.4/4 = 0.1 cub.m No. of bags of cement = 0.1/0.035 = 2.85 = say 3no.of bags Qt. of sand = 3* 0.1 = 0.3 cub.m Particular Quantity/No. Rate Cost Material Cement 3 bags 255 765Rs/- Sand 0.3 cub.m 1644 493.2Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Total = 2748 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 3298Rs/- Rate per sq.m= 165 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 165 Rs/- per unit
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.per Unit ): 300.00 Rs per sq.m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-06

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Lad Manoj Sadashiv
Exam No. 13534
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the electrical plans
Details of how you Planned & Executed the allotted work we get electical plan from site engineer.we went on the second floor slab and observe electrical points.consiled wiring is provided.20mm.dia.pipe is used for wiring
Details of the Construction Procedure / Activity / Technology learned today conciled wiring- P.V.C.material pipes are used for consiled wiring.consiled wiring electical plans are used provided by ARCHITECTURE.it is very economical wiring method than other type of wiring method
Details of the Construction Materials learned today scafolding- scafolding is used for various perposes.it is used for brick work,plaster and penting
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of alluminium and iron frames for door and window dicreases plant cutting
Details of the Construction / Engineering Drawings observed today electrical drawing-conceled wiring fan points,lamp points,powerplug points
Details of the Bye Laws referred today min.area of kitchen=5.75 sq.m. living room=9 sq.m.
Details of any Managerial Skill learned today polliteness and co-operative
RATE ANALYSIS (Detailed Stepwise Calculations required) assume 10 sq.m.area for plastering thickness of plaster=12mm. =0.012m. total volume =10*0.012 =0.12 cu.m. add 50% for dry volume=0.18 cu.m. no of bags=0.18/(1+4)=0.036 cu.m.=1.27 cu.m.----say 10 bags sand=0.036*4 =0.144 cu.m=5 cu ft.=0.144*1060=152.65 Rs. say 160Rs. Labour =350Rs. per brass 400 Rs. increase 1.5% water cost =883.05Rs. contractor profit =15% =1015Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1015Rs. for 10 sq.m. wall
Todays BUZZ Word Balcony =10% of total built up area Terrace- 12% of total built up area stare case - Landing width > 2m. cupboard projected to margin
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523

Company Name Pooja Developers & Builders
Project Name & Site Address poja bavda
Students Name (Surname_First Name_Middle Name) devkar vikram dilip
Exam No. 13523
Working Day No. 6
Date (DD/MM/YYYY) 14-12-10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge 1) To check electrification points according to electrification plan
Details of how you Planned & Executed the allotted work One of us holded electrificatrion plan,other student was finding location according to plan and remaining students were checking points according to instruction\'s.
Details of the Construction Procedure / Activity / Technology learned today 1) Pile foundation at nearby site of Chetan Oswal Sir. 2) Placing of concrete of slab which was transported with pumps & pipes. 3) Casting of remaining slab for second floor with the help of R.M.C. 4) Casting of stair-case. 5) Curing of slab.
Details of the Construction Materials learned today - Pipes and wirings used for concealed electrification purpose
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such technology was adopted today.
Details of the Construction / Engineering Drawings observed today 1) Electrification plan. 2) Centre line plan.
Details of the Bye Laws referred today 1) Door size provided was 1.18m*2.1m, according to Bye- Laws it should be minimum 0.9m*2.0m.
Details of any Managerial Skill learned today - We saw how to solve the problem arrived during constuction activites. - Wes aw how the manager has a control over the entire work going on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) Providing internal cement plaster 12mm thick in a single coat in cement mortar (1:4) without neeru finish to concrete or brick surface including scaffolding and curing complete. Materials and labour required: Cement= 0.1 bag /sq.m. Sand= 0.012 /cu.m. Rates. Cement= Rs.265/bag.= 265*0.1= Rs. 26.50. Sand= Rs.2100/cu.m= 2100*0.012= Rs. 25.20. Labour rate including scaffolding etc.= Rs. 55/ sq.m Total= 55+26.50+25.20= Rs. 106.70. Including 10% profit.= 106.70+10.67= Rs. 117.37. Total Cost of Internal Plaster =Rs. 117.37 / sq.m Result of RATE ANALYSIS ( Rs per Unit ): Rs. 117.37 /sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 117.37 /sq.m
Todays BUZZ Word \"BUILDING COMPONENENTS THAT GET EXCLUDED IN F.S.I CALCULATIONS\" 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Bye Law Book, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: rameshkharat1987@gmail.com
Subject: 13532-06

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Ramesh Laxman
Exam No. 13532
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the electrical plans
Details of how you Planned & Executed the allotted work we get electical plan from site engineer.we went on the second floor slab and observe electrical points.consiled wiring is provided.20mm.dia.pipe is used for wiring
Details of the Construction Procedure / Activity / Technology learned today conciled wiring- P.V.C.material pipes are used for consiled wiring.consiled wiring electical plans are used provided by ARCHITECTURE.it is very economical wiring method than other type of wiring method
Details of the Construction Materials learned today scafolding- scafolding is used for various perposes.it is used for brick work,plaster and penting
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of alluminium and iron frames for door and window dicreases plant cutting
Details of the Construction / Engineering Drawings observed today electrical drawing-conceled wiring fan points,lamp points,powerplug points
Details of the Bye Laws referred today min.area of kitchen=5.75 sq.m. living room=9 sq.m.
Details of any Managerial Skill learned today polliteness and co-operative
RATE ANALYSIS (Detailed Stepwise Calculations required) assume 10 sq.m.area for plastering thickness of plaster=12mm. =0.012m. total volume =10*0.012 =0.12 cu.m. add 50% for dry volume=0.18 cu.m. no of bags=0.18/(1+4)=0.036 cu.m.=1.27 cu.m.----say 10 bags sand=0.036*4 =0.144 cu.m=5 cu ft.=0.144*1060=152.65 Rs. say 160Rs. Labour =350Rs. per brass 400 Rs. increase 1.5% water cost =883.05Rs. contractor profit =15% =1015Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1015Rs. for 10 sq.m. wall
Todays BUZZ Word Balcony =10% of total built up area Terrace- 12% of total built up area stare case - Landing width > 2m. cupboard projected to margin
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: vishalsapakal@gmail.com
Subject: 10882-06

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) sapakal vishal manohar
Exam No. 10882
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for beams and fixing of beam bottoms, checking their levels, heights, manufacturing of concrete of m20 as per proportions and placing of concrete on stair case reinforcement and checking thickness of concrete for rise.
Details of how you Planned & Executed the allotted work We checked the width and depth of beam and height of beam bottom from floor level. Then we inspected the manufacturing of concrete, counted the pans of sand and aggregate, and liters of water used in its manufacturing. We saw the placing and compaction of concrete on the reinforcement of stair case.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the side of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing concrete in stair case section and its compaction with needle vibrator .
Details of the Construction Materials learned today No new material has been used today on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method or material is used on the site.
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today : Compound wall provide on the site is 1.50m in height. As per bye law height is 1.50m minimum.
Details of any Managerial Skill learned today Self involvement in selection of material required considering quantity of material and rate to achieve economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS (Detailed Stepwise Calculations required): “Quantity calculation for compound wall using cement blocks“ Dimensions of typical part of wall-2.9*1.5*0.15m Size of block-0.75*0.40*0.15m 1. Volume of wall =0.6525 cu.m. 2.Quantity of cement mortar (1:6)=45% of total volume =0.29cu.m. 3. Quantity of cement =0.29/1+6 =0.041 =0.041/0.035=1.18=2 bags 4. Quantity of sand=0.041*6=0.246 cu.m. 5. number of blocks=55nos “Rate Analysis for compound wall using cement blocks” (Considering local rates of material) (wall size=2.9*1.5*0.15m) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.246*1600=394/-…………(1600/- per cu.m.) 3. Cost of block=55*10=550/-…………(10/- per block ) 4.Labour charges=1130/- 7. Total cost= 2574/- 8.10% profit of total cost for the contractor=257.4/- 9. Total cost=2831/-
Result of RATE ANALYSIS ( Rs per Unit ) 4338/-
Todays BUZZ Word “Building components excluded in F.S.I calculations” In calculation of FSI following components are excluded- 1.Passage upto 1.20m 2.Lift well having dimensions of1.20*1.20m 3.Stair case upto 1.20m in width. 4.Balcony having area less than 1/3rd of the total area of the flat
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-06

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Hasabnis Ketaki Bhagwan
Exam No. 13527
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge > To check electrification points according to electrification plan.
Details of how you Planned & Executed the allotted work We were given the electrification plan. One of us held the plan. Another student found the location of points according to the plan. Other group members checked the points acccording to the instruction.
Details of the Construction Procedure / Activity / Technology learned today > Pile foundation at landscape (ketan oswal\'s site) > Placing of concrete with the help of pumps and pipes for casting of slab.
Details of the Construction Materials learned today > Pipes used for concealed electrification purpose
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today > Electrification plan & > Centre line plan
Details of the Bye Laws referred today > Door size provided was 1.18m*2.1m, according to Bye-Laws it should be minimum 0.9m*2.0m. > Window size provided was 1.2m*1.2m, according to Bye-Laws it should be minimum 0.6m*1.2m.
Details of any Managerial Skill learned today > How to solve 11th hour problems arising on site due to miscommunication, misinterpretation etc.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER.(per sq.m) Providing internal cement plaster 12mm thick in a single coat in cement mortar (1:4) without neeru finish to concrete or brick surface including scaffolding and curing complete. Materials and labour required: Cement= 0.1 bag /sq.m. Sand= 0.012 /cu.m. Rates. Cement= Rs.265/bag.= 265*0.1= Rs. 26.50. Sand= Rs.2100/cu.m= 2100*0.012= Rs. 25.20. Labour rate including scaffolding etc.= Rs. 55/ sq.m Total= 55+26.50+25.20= Rs. 106.70. Including 10% profit.= 106.70+10.67= Rs. 117.37. Total Cost of Internal Plaster =Rs. 117.37 / sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 117.37 /sq.m
Todays BUZZ Word The following shall not be counted during F.S.I. 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m 14) Areas covered by service duct, pump room, corridor passages etc. with the permission of commssioner.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar cell No: 09922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-06

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kolekar Shyam Suryakant
Exam No. 13533
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe the electrical plans
Details of how you Planned & Executed the allotted work we get electical plan from site engineer.we went on the second floor slab and observe electrical points.consiled wiring is provided.20mm.dia.pipe is used for wiring
Details of the Construction Procedure / Activity / Technology learned today conciled wiring- P.V.C.material pipes are used for consiled wiring.consiled wiring electical plans are used provided by ARCHITECTURE.it is very economical wiring method than other type of wiring method
Details of the Construction Materials learned today scafolding- scafolding is used for various perposes.it is used for brick work,plaster and penting
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of alluminium and iron frames for door and window dicreases plant cutting
Details of the Construction / Engineering Drawings observed today electrical drawing-conceled wiring fan points,lamp points,powerplug points
Details of the Bye Laws referred today min.area of kitchen=5.75 sq.m. living room=9 sq.m.
Details of any Managerial Skill learned today polliteness and co-operative
RATE ANALYSIS (Detailed Stepwise Calculations required) assume 10 sq.m.area for plastering thickness of plaster=12mm. =0.012m. total volume =10*0.012 =0.12 cu.m. add 50% for dry volume=0.18 cu.m. no of bags=0.18/(1+4)=0.036 cu.m.=1.27 cu.m.----say 10 bags sand=0.036*4 =0.144 cu.m=5 cu ft.=0.144*1060=152.65 Rs. say 160Rs. Labour =350Rs. per brass 400 Rs. increase 1.5% water cost =883.05Rs. contractor profit =15% =1015Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1015Rs. for 10 sq.m. wall
Todays BUZZ Word Balcony =10% of total built up area Terrace- 12% of total built up area stare case - Landing width > 2m. cupboard projected to margin
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521

Company Name Pooja Developers & Builders
Project Name & Site Address pooja builders bawada
Students Name (Surname_First Name_Middle Name) bagmare dinesh shriram
Exam No. 13521
Working Day No. 6
Date (DD/MM/YYYY) 14-12-10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge 1) To check electrification points according to electrification plan
Details of how you Planned & Executed the allotted work One of us holded electrificatrion plan,other student was finding location according to plan and remaining students were checking points according to instruction\'s.
Details of the Construction Procedure / Activity / Technology learned today 1) Pile foundation at nearby site of Chetan Oswal Sir. 2) Placing of concrete of slab which was transported with pumps & pipes. 3) Casting of remaining slab for second floor with the help of R.M.C. 4) Casting of stair-case. 5) Curing of slab.
Details of the Construction Materials learned today - Pipes and wirings used for concealed electrification purpose
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such technology was adopted today.
Details of the Construction / Engineering Drawings observed today 1) Electrification plan. 2) Centre line plan.
Details of the Bye Laws referred today 1) Door size provided was 1.18m*2.1m, according to Bye- Laws it should be minimum 0.9m*2.0m.
Details of any Managerial Skill learned today - We saw how to solve the problem arrived during constuction activites. - Wes aw how the manager has a control over the entire work going on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) Providing internal cement plaster 12mm thick in a single coat in cement mortar (1:4) without neeru finish to concrete or brick surface including scaffolding and curing complete. Materials and labour required: Cement= 0.1 bag /sq.m. Sand= 0.012 /cu.m. Rates. Cement= Rs.265/bag.= 265*0.1= Rs. 26.50. Sand= Rs.2100/cu.m= 2100*0.012= Rs. 25.20. Labour rate including scaffolding etc.= Rs. 55/ sq.m Total= 55+26.50+25.20= Rs. 106.70. Including 10% profit.= 106.70+10.67= Rs. 117.37. Total Cost of Internal Plaster =Rs. 117.37 / sq.m Result of RATE ANALYSIS ( Rs per Unit ): Rs. 117.37 /sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 117.37 /sq.m
Todays BUZZ Word \"BUILDING COMPONENENTS THAT GET EXCLUDED IN F.S.I CALCULATIONS\" 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-06

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) yadav hrisheekesh deepak
Exam No. 10885
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for beams and fixing of beam bottoms, checking their levels, heights, manufacturing of concrete of m20 as per proportions and placing of concrete on stair case reinforcement and checking thickness of concrete for rise.
Details of how you Planned & Executed the allotted work We checked the width and depth of beam and height of beam bottom from floor level. Then we inspected the manufacturing of concrete, counted the pans of sand and aggregate, and liters of water used in its manufacturing. We saw the placing and compaction of concrete on the reinforcement of stair case.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the side of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing concrete in stair case section and its compaction with needle vibrator .
Details of the Construction Materials learned today No new material has been used today on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method or material is used on the site.
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Compound wall provide on the site is 1.50m in height. As per bye law height is 1.50m minimum.
Details of any Managerial Skill learned today Self involvement in selection of material required considering quantity of material and rate to achieve economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for compound wall using cement blocks“ Dimensions of typical part of wall-2.9*1.5*0.15m Size of block-0.75*0.40*0.15m 1. Volume of wall =0.6525 cu.m. 2.Quantity of cement mortar (1:6)=45% of total volume =0.29cu.m. 3. Quantity of cement =0.29/1+6 =0.041 =0.041/0.035=1.18=2 bags 4. Quantity of sand=0.041*6=0.246 cu.m. 5. number of blocks=55nos “Rate Analysis for compound wall using cement blocks” (Considering local rates of material) (wall size=2.9*1.5*0.15m) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.246*1600=394/-…………(1600/- per cu.m.) 3. Cost of block=55*10=550/-…………(10/- per block ) 4.Labour charges=1130/- 7. Total cost= 2574/- 8.10% profit of total cost for the contractor=257.4/- 9. Total cost=2831/-
Result of RATE ANALYSIS ( Rs per Unit ) 4338/-
Todays BUZZ Word “Building components excluded in F.S.I calculations” In calculation of FSI following components are excluded- 1.Passage upto 1.20m 2.Lift well having dimensions of1.20*1.20m 3.Stair case upto 1.20m in width. 4.Balcony having area less than 1/3rd of the total area of the flat
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: vishalsapakal@gmail.com
Subject: 10882-06

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) sapakal vishal manohar
Exam No. 10882
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for beams and fixing of beam bottoms, checking their levels, heights, manufacturing of concrete of m20 as per proportions and placing of concrete on stair case reinforcement and checking thickness of concrete for rise.
Details of how you Planned & Executed the allotted work We checked the width and depth of beam and height of beam bottom from floor level. Then we inspected the manufacturing of concrete, counted the pans of sand and aggregate, and liters of water used in its manufacturing. We saw the placing and compaction of concrete on the reinforcement of stair case.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the side of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing concrete in stair case section and its compaction with needle vibrator .
Details of the Construction Materials learned today No new material has been used today on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method or material is used on the site.
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Compound wall provide on the site is 1.50m in height. As per bye law height is 1.50m minimum.
Details of any Managerial Skill learned today Self involvement in selection of material required considering quantity of material and rate to achieve economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for compound wall using cement blocks“ Dimensions of typical part of wall-2.9*1.5*0.15m Size of block-0.75*0.40*0.15m 1. Volume of wall =0.6525 cu.m. 2.Quantity of cement mortar (1:6)=45% of total volume =0.29cu.m. 3. Quantity of cement =0.29/1+6 =0.041 =0.041/0.035=1.18=2 bags 4. Quantity of sand=0.041*6=0.246 cu.m. 5. number of blocks=55nos “Rate Analysis for compound wall using cement blocks” (Considering local rates of material) (wall size=2.9*1.5*0.15m) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.246*1600=394/-…………(1600/- per cu.m.) 3. Cost of block=55*10=550/-…………(10/- per block ) 4.Labour charges=1130/- 7. Total cost= 2574/- 8.10% profit of total cost for the contractor=257.4/- 9. Total cost=2831/-
Result of RATE ANALYSIS ( Rs per Unit ) 4338/-
Todays BUZZ Word 1.Passage upto 1.20m 2.Lift well having dimensions of1.20*1.20m 3.Stair case upto 1.20m in width. 4.Balcony having area less than 1/3rd of the total area of the flat
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-06

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Jape Vishwajeet Ramesh
Exam No. 10892
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - To Estimate the quantity of Concrete, Steel, Cement, Aggregate Etc. for a septic tank - To Study the Brickwork. ------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work # For Brickwork: - We all together went to the site & studied the brickwork. - We also asked the queries to the mistri who was incharge of it. ----------------------------------------------------------------------- # For Estimation of Quantity: - To study the plans of Septic tank - Then we determined the area & volume of the septic Tank. - The we compared with actual ones. --------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today # BRICK LAYING PROCEDURE: - All bricks were soked in water before using. - Bricks were laid with their frogs facing upwards. - Mortar was spread over the area to be covered. - First corner of the wall was constructed. - Check the level & alignment. - Then lay down few headers & strechers in first course. - Again lay the mortor & spread over the first course - Similarly lay down the corner at the other end of the wall. - Stretch a Line dori alon the top of the first course, laid at each corner of wall. - The course is then raised. - The procedure is repeted to second, third, & other courses until the wall is constructed to the required height. ----------------------------------------------------------------------------------
Details of the Construction Materials learned today - Standard Brick (6\" thick). - Cement Mortor ---------------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - For ordinary construction works \"crushed sand\" was used instead of natural sand. ------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today - Details of Upflow Filter & Baffle wall of septic tank. - Septic Tank Details. - Service Layout for \"C-Wing\" - Details of perforated RCC Slab. - Details of anerobic filter. ------------------------------------------------------------------------------------
Details of the Bye Laws referred today - FSI related Details - pg 80 - Septic Tank Details - pg 104
Details of any Managerial Skill learned today - Punctuality. - Keeping mind cool even in stressed situations. --------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # INTERNAL PLASTER # 12 mm thick plaster in single coat for : 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bed Room = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bath Room = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m Deductions for : 1. D1 = 2.6 sq.m 2. D2 = 13.2 sq.m 3. D3 = 3.3 sq.m 4. W1 = 11.2 sq.m 5. W2 = 2.8 sq.m 6. W3 = 0.9 sq.m 7. Grill = 3 sq.m TOTAL = 37 sq.m Deduct 50% = 218.21 - (37/2) = 199.71 sq.m Therefore Area of Plaster 199.71 sq.m Volume of plaster = 2.4 cu.m Add 50% for voids & 10% for uneveness : Dry Vol of mortar = 3.84 cu.m Cement = 28 bags Sand = 2.88 cu.m B) Cost of Materials : 1. Cement = 28 x 230 = 6440/- 2. Sand = 2.9 x 850 = 8905/- C) Cost of Labours : 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 1 x 110 = 110/- 5. Scaffolding = 300/- 6. T&P = 300/- TOTAL = 4760 x 2 = 9520/- D) TOTAL = B + C = 18425/- E) Add 2% for water charges = 368.5/- F) Add 15% for contractors profit = 2763.75/- G) Grand Total = 21557.25/- H) Rate per sq.m = Rs. 107.94/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 107.94/-
Todays BUZZ Word The following shall not be counted under F.S.I. calculations: 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m. -------------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay ( 9922507376 )
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-06

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Nagvekar Yogesh Deepak
Exam No. 10894
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - To Estimate the quantity of Concrete, Steel, Cement, Aggregate Etc. for a septic tank - To Study the Brickwork. ------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work # For Brickwork: - We all together went to the site & studied the brickwork. - We also asked the queries to the mistri who was incharge of it. ----------------------------------------------------------------------- # For Estimation of Quantity: - To study the plans of Septic tank - Then we determined the area & volume of the septic Tank. - The we compared with actual ones. --------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today # BRICK LAYING PROCEDURE: - All bricks were soked in water before using. - Bricks were laid with their frogs facing upwards. - Mortar was spread over the area to be covered. - First corner of the wall was constructed. - Check the level & alignment. - Then lay down few headers & strechers in first course. - Again lay the mortor & spread over the first course - Similarly lay down the corner at the other end of the wall. - Stretch a Line dori alon the top of the first course, laid at each corner of wall. - The course is then raised. - The procedure is repeted to second, third, & other courses until the wall is constructed to the required height. ----------------------------------------------------------------------------------
Details of the Construction Materials learned today - Standard Brick (6\" thick). - Cement Mortor ---------------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - For ordinary construction works \"crushed sand\" was used instead of natural sand. ------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today - Details of Upflow Filter & Baffle wall of septic tank. - Septic Tank Details. - Service Layout for \"C-Wing\" - Details of perforated RCC Slab. - Details of anerobic filter. ------------------------------------------------------------------------------------
Details of the Bye Laws referred today - FSI related Details - pg 80 - Septic Tank Details - pg 104
Details of any Managerial Skill learned today - Punctuality. - Keeping mind cool even in stressed situations. --------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # INTERNAL PLASTER # 12 mm thick plaster in single coat for : 1. Kitchen & Dining = 50.25 sq.m 2. Living Room = 56.95 sq.m 3. Bed Room = 56.95 sq.m 4. Verandah = 33.66 sq.m 5. Bath Room = 11.90 sq.m 6. WC = 8.50 sq.m TOTAL = 218.21 sq.m Deductions for : 1. D1 = 2.6 sq.m 2. D2 = 13.2 sq.m 3. D3 = 3.3 sq.m 4. W1 = 11.2 sq.m 5. W2 = 2.8 sq.m 6. W3 = 0.9 sq.m 7. Grill = 3 sq.m TOTAL = 37 sq.m Deduct 50% = 218.21 - (37/2) = 199.71 sq.m Therefore Area of Plaster 199.71 sq.m Volume of plaster = 2.4 cu.m Add 50% for voids & 10% for uneveness : Dry Vol of mortar = 3.84 cu.m Cement = 28 bags Sand = 2.88 cu.m B) Cost of Materials : 1. Cement = 28 x 230 = 6440/- 2. Sand = 2.9 x 850 = 8905/- C) Cost of Labours : 1. Mistri = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 15 x 140 = 2100/- 4. Bhisti = 1 x 110 = 110/- 5. Scaffolding = 300/- 6. T&P = 300/- TOTAL = 4760 x 2 = 9520/- D) TOTAL = B + C = 18425/- E) Add 2% for water charges = 368.5/- F) Add 15% for contractors profit = 2763.75/- G) Grand Total = 21557.25/- H) Rate per sq.m = Rs. 107.94/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 107.94/-
Todays BUZZ Word The following shall not be counted under F.S.I. calculations: 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m. -------------------------------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay ( 9922507376 )
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: gauravdesai75@gmail.com
Subject: 13522-06

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Builders and Developers,near Jayprabha studio,Kolhapur,
Students Name (Surname_First Name_Middle Name) DESAI GAURAV RAVINDRA
Exam No. 13522
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge To check electrification points according to electrification plan.
Details of how you Planned & Executed the allotted work One of us holded electrificatrion plan,other student was finding location according to plan and remaining students were checking points according to instruction\'s.
Details of the Construction Procedure / Activity / Technology learned today 1) Pile foundation at nearby site of Chetan Oswal Sir. 2) Placing of concrete of slab which was transported with pumps & pipes. 3) Casting of remaining slab for second floor with the help of R.M.C. 4) Casting of stair-case. 5) Curing of slab.
Details of the Construction Materials learned today - Pipes and wirings used for concealed electrification purpose.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such technology was adopted today.
Details of the Construction / Engineering Drawings observed today 1) Electrification plan. 2) Centre line plan.
Details of the Bye Laws referred today 1) Door size provided was 1.18m*2.1m, according to Bye-Laws it should be minimum 0.9m*2.0m. 2) Window size provided was 1.2m*1.2m, according to Bye-Laws it should be minimum 0.6m*1.2m.
Details of any Managerial Skill learned today - We saw how to solve the problem arrived during constuction activites. - Wes aw how the manager has a control over the entire work going on site.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER.(per sq.m) Providing internal cement plaster 12mm thick in a single coat in cement mortar (1:4) without neeru finish to concrete or brick surface including scaffolding and curing complete. Materials and labour required: Cement= 0.1 bag /sq.m. Sand= 0.012 /cu.m. Rates. Cement= Rs.265/bag.= 265*0.1= Rs. 26.50. Sand= Rs.2100/cu.m= 2100*0.012= Rs. 25.20. Labour rate including scaffolding etc.= Rs. 55/ sq.m Total= 55+26.50+25.20= Rs. 106.70. Including 10% profit.= 106.70+10.67= Rs. 117.37. Total Cost of Internal Plaster =Rs. 117.37 / sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 117.37 /sq.m
Todays BUZZ Word \"BUILDING COMPONENENTS THAT GET EXCLUDED IN F.S.I CALCULATIONS\" 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-06

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) JAGADALE ASHVANI RAMRAO
Exam No. 13530
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge Line out of first floor brick work
Details of how you Planned & Executed the allotted work *First we check outer boundary by plumb bob *Then we mark internal brick work by dimension
Details of the Construction Procedure / Activity / Technology learned today *How to mark centre of column on p.c.c *Match the centre of jali with centre of column
Details of the Construction Materials learned today various types of fittings in toilet, bath ,utility
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use steel formwork instead of using wood.
Details of the Construction / Engineering Drawings observed today Detailed plumbing drawings of each flats.
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 390 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 475.87 RS WATER= 1.5 % = 7.13 RS CONTRACTOR PROFIT = 10% = 47.58 RS TOTAL COST = 530.58 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530.58 RS
Todays BUZZ Word 1. if balcony width is less 1.2 m then it is excluded in F.S.I. 2. If stair width is less or equal than 1 m then it is excluded in F.S.I. 3. porch area is not considered in F.S.I. 4. Open to sky portion is not considered in F.S.I. 5. lobby area is not considered in F.S.I. 6. terrace area is not considered in F.S.I.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J J Chougule mob no - 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-06

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) PATIL ADITYA PANDURANG
Exam No. 13538
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge Line out of first floor brick work
Details of how you Planned & Executed the allotted work *First we check outer boundary by plumb bob *Then we mark internal brick work by dimension
Details of the Construction Procedure / Activity / Technology learned today *How to mark centre of column on p.c.c *Match the centre of jali with centre of column
Details of the Construction Materials learned today various types of fittings in toilet, bath ,utility
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use steel formwork instead of using wood.
Details of the Construction / Engineering Drawings observed today Detailed plumbing drawings of each flats.
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 390 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 475.87 RS WATER= 1.5 % = 7.13 RS CONTRACTOR PROFIT = 10% = 47.58 RS TOTAL COST = 530.58 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530.58 RS
Todays BUZZ Word 1. if balcony width is less 1.2 m then it is excluded in F.S.I. 2. If stair width is less or equal than 1 m then it is excluded in F.S.I. 3. porch area is not considered in F.S.I. 4. Open to sky portion is not considered in F.S.I. 5. lobby area is not considered in F.S.I. 6. terrace area is not considered in F.S.I.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J J Chougule mob no - 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-06

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) MANGAONKAR MANOJ DATTATRAY
Exam No. 13536
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge Line out of first floor brick work
Details of how you Planned & Executed the allotted work *First we check outer boundary by plumb bob *Then we mark internal brick work by dimension
Details of the Construction Procedure / Activity / Technology learned today *How to mark centre of column on p.c.c *Match the centre of jali with centre of column
Details of the Construction Materials learned today various types of fittings in toilet, bath ,utility
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use steel formwork instead of using wood.
Details of the Construction / Engineering Drawings observed today Detailed plumbing drawings of each flats.
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 390 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 475.87 RS WATER= 1.5 % = 7.13 RS CONTRACTOR PROFIT = 10% = 47.58 RS TOTAL COST = 530.58 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530.58 RS
Todays BUZZ Word 1. if balcony width is less 1.2 m then it is excluded in F.S.I. 2. If stair width is less or equal than 1 m then it is excluded in F.S.I. 3. porch area is not considered in F.S.I. 4. Open to sky portion is not considered in F.S.I. 5. lobby area is not considered in F.S.I. 6. terrace area is not considered in F.S.I.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J J Chougule mob no - 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-06

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge Line out of first floor brick work
Details of how you Planned & Executed the allotted work *First we check outer boundary by plumb bob *Then we mark internal brick work by dimension
Details of the Construction Procedure / Activity / Technology learned today *How to mark centre of column on p.c.c *Match the centre of jali with centre of column
Details of the Construction Materials learned today various types of fittings in toilet, bath ,utility
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use steel formwork instead of using wood.
Details of the Construction / Engineering Drawings observed today Detailed plumbing drawings of each flats.
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 390 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 475.87 RS WATER= 1.5 % = 7.13 RS CONTRACTOR PROFIT = 10% = 47.58 RS TOTAL COST = 530.58 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530.58 RS
Todays BUZZ Word 1. if balcony width is less 1.2 m then it is excluded in F.S.I. 2. If stair width is less or equal than 1 m then it is excluded in F.S.I. 3. porch area is not considered in F.S.I. 4. Open to sky portion is not considered in F.S.I. 5. lobby area is not considered in F.S.I. 6. terrace area is not considered in F.S.I.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J J Chougule mob no - 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: buntyphonde@gmail.com
Subject: 10899-06

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Phonde Pravin Tukaram
Exam No. 10899
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise concreting operation. .
Details of how you Planned & Executed the allotted work we had given the proportion of concrete & according to it we were inspecting whether the labors are taking correct proportion or not.afterwards we gone to the spot where slab was going on.& there we supervised the concreting operation of slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of making cubes of concrete which are used for testing of its strength.firstly oiling is done from the inside of the mould in which concrete is to be filled.then the concrete which is to be tested is filled properly.&then it is taken to the laboratory for testing. .
Details of the Construction Materials learned today today we learned the p.v.c material of which the pipes are used on the site .the pipes are used to fix it in the slab for electric purpose. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today today we discussed the cutting of trees which is done at time of developing new site.& it should be planted afterward at the time of completion of work. .
Details of the Construction / Engineering Drawings observed today today we observed plinth beam drawing. .
Details of the Bye Laws referred today today we referred the open spaces,area,f.s.i & height limitation for the ares in bye-laws. .
Details of any Managerial Skill learned today proper communication between the supervisor & the labors is required for the sake of completing the work in given time &also for the purpose of doing quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Internal Neru Finishing Plaster ITEM QTY. UNIT RATE AMOUNT Cement 0.2 Bags 260 52 Sand 0.04 M3 1150 46 Plastermesh per M2 10 Neru M2 10 Total 114 Wastage 5% 6 Total 120 Scaffolding 15 Labour 70 Curing 5 Total 210 23% Tax Overhead and Profit 48 Total 262 Say 262/- per M2
Result of RATE ANALYSIS ( Rs per Unit ) 262/- per M2
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M S 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-06

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Tambe Trusha Sitaram
Exam No. 10902
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise concreting operation. .
Details of how you Planned & Executed the allotted work we had given the proportion of concrete & according to it we were inspecting whether the labors are taking correct proportion or not.afterwards we gone to the spot where slab was going on.& there we supervised the concreting operation of slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of making cubes of concrete which are used for testing of its strength.firstly oiling is done from the inside of the mould in which concrete is to be filled.then the concrete which is to be tested is filled properly.&then it is taken to the laboratory for testing. .
Details of the Construction Materials learned today today we learned the p.v.c material of which the pipes are used on the site .the pipes are used to fix it in the slab for electric purpose. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today today we discussed the cutting of trees which is done at time of developing new site.& it should be planted afterward at the time of completion of work. .
Details of the Construction / Engineering Drawings observed today today we observed plinth beam drawing. .
Details of the Bye Laws referred today today we referred the open spaces,area,f.s.i & height limitation for the ares in bye-laws. .
Details of any Managerial Skill learned today proper communication between the supervisor & the labors is required for the sake of completing the work in given time &also for the purpose of doing quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Internal Neru Finishing Plaster ITEM QTY. UNIT RATE AMOUNT Cement 0.2 Bags 260 52 Sand 0.04 M3 1150 46 Plastermesh per M2 10 Neru M2 10 Total 114 Wastage 5% 6 Total 120 Scaffolding 15 Labour 70 Curing 5 Total 210 23% Tax Overhead and Profit 48 Total 262 Say 258/- per M2
Result of RATE ANALYSIS ( Rs per Unit ) 258/- per M2
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M S 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-06

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Abhishek Dadasaheb
Exam No. 10895
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise concreting operation. .
Details of how you Planned & Executed the allotted work we had given the proportion of concrete & according to it we were inspecting whether the labors are taking correct proportion or not.afterwards we gone to the spot where slab was going on.& there we supervised the concreting operation of slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of making cubes of concrete which are used for testing of its strength.firstly oiling is done from the inside of the mould in which concrete is to be filled.then the concrete which is to be tested is filled properly.&then it is taken to the laboratory for testing. .
Details of the Construction Materials learned today today we learned the p.v.c material of which the pipes are used on the site .the pipes are used to fix it in the slab for electric purpose. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today today we discussed the cutting of trees which is done at time of developing new site.& it should be planted afterward at the time of completion of work. .
Details of the Construction / Engineering Drawings observed today today we observed plinth beam drawing. .
Details of the Bye Laws referred today today we referred the open spaces,area,f.s.i & height limitation for the ares in bye-laws. .
Details of any Managerial Skill learned today proper communication between the supervisor & the labors is required for the sake of completing the work in given time &also for the purpose of doing quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Internal Neru Finishing Plaster ITEM QTY. UNIT RATE AMOUNT Cement 0.2 Bags 260 52 Sand 0.04 M3 1150 46 Plastermesh per M2 10 Neru M2 10 Total 114 Wastage 5% 6 Total 120 Scaffolding 15 Labour 70 Curing 5 Total 210 23% Tax Overhead and Profit 48 Total 262 Say 262/- per M2
Result of RATE ANALYSIS ( Rs per Unit ) 262/- per M2
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M S 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-06

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Sawant Amit Ganpat
Exam No. 10900
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise concreting operation. .
Details of how you Planned & Executed the allotted work we had given the proportion of concrete & according to it we were inspecting whether the labors are taking correct proportion or not.afterwards we gone to the spot where slab was going on.& there we supervised the concreting operation of slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of making cubes of concrete which are used for testing of its strength.firstly oiling is done from the inside of the mould in which concrete is to be filled.then the concrete which is to be tested is filled properly.&then it is taken to the laboratory for testing. .
Details of the Construction Materials learned today today we learned the p.v.c material of which the pipes are used on the site .the pipes are used to fix it in the slab for electric purpose. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today today we discussed the cutting of trees which is done at time of developing new site.& it should be planted afterward at the time of completion of work. .
Details of the Construction / Engineering Drawings observed today today we observed plinth beam drawing. .
Details of the Bye Laws referred today today we referred the open spaces,area,f.s.i & height limitation for the ares in bye-laws. .
Details of any Managerial Skill learned today proper communication between the supervisor & the labors is required for the sake of completing the work in given time &also for the purpose of doing quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Internal Neru Finishing Plaster ITEM QTY. UNIT RATE AMOUNT Cement 0.2 Bags 260 52 Sand 0.04 M3 1150 46 Plastermesh per M2 10 Neru M2 10 Total 114 Wastage 5% 6 Total 120 Scaffolding 15 Labour 70 Curing 5 Total 210 23% Tax Overhead and Profit 48 Total 262 Say 262/- per M2
Result of RATE ANALYSIS ( Rs per Unit ) 262/m2
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M S 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-06

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Sharad Shankarrao
Exam No. 10897
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge to supervise concreting operation. .
Details of how you Planned & Executed the allotted work we had given the proportion of concrete & according to it we were inspecting whether the labors are taking correct proportion or not.afterwards we gone to the spot where slab was going on.& there we supervised the concreting operation of slab. .
Details of the Construction Procedure / Activity / Technology learned today today we learned the procedure of making cubes of concrete which are used for testing of its strength.firstly oiling is done from the inside of the mould in which concrete is to be filled.then the concrete which is to be tested is filled properly.&then it is taken to the laboratory for testing. .
Details of the Construction Materials learned today today we learned the p.v.c material of which the pipes are used on the site .the pipes are used to fix it in the slab for electric purpose. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today today we discussed the cutting of trees which is done at time of developing new site.& it should be planted afterward at the time of completion of work. .
Details of the Construction / Engineering Drawings observed today today we observed plinth beam drawing. .
Details of the Bye Laws referred today today we referred the open spaces,area,f.s.i & height limitation for the ares in bye-laws. .
Details of any Managerial Skill learned today proper communication between the supervisor & the labors is required for the sake of completing the work in given time &also for the purpose of doing quality work. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Internal Neru Finishing Plaster ITEM QTY. UNIT RATE AMOUNT Cement 0.2 Bags 260 52 Sand 0.04 M3 1150 46 Plastermesh per M2 10 Neru M2 10 Total 114 Wastage 5% 6 Total 120 Scaffolding 15 Labour 70 Curing 5 Total 210 23% Tax Overhead and Profit 48 Total 262 Say 262/- per M2
Result of RATE ANALYSIS ( Rs per Unit ) 262/- per M2
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M S 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-06

Company Name Deshmukh Developers
Project Name & Site Address Deshmukh Developments,Pratibha Nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Birajdar Minaxi Renuk
Exam No. 13556
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today we observe further Plumbing : 1) We are all groupmates study carefully about fittings, pipes, different shapes of sections 2) Rain Harvesting pipes 3) PVC pipes, CPVC pipes, Insulation pipes, Diameter of pipes etc 4) And we are observe connection s of Plumbing pipes for different purposes drinking, bathing, washing etc
Details of how you Planned & Executed the allotted work Firstly we are go to that floor : 1) To study the pipes connections point in bathroom, attached toilets,sink, 2) Pipes for cold water, hot water and also soil pipe, rain harvesting pipes 3) point for shower, flushing,cocks etc we are observe
Details of the Construction Procedure / Activity / Technology learned today Construction Procedure : 1) We are observe in attached toilets there are various pipes connections for flushing, shower, wash basin 2) Measure height of shower-2.1m, wash basin-0.8m,cocks-1m 3) All above connections are get connect to drainage pits which are provided ground level at every toilets blocks 4) In elevation these toilet pipes are not seen due to extra block is provided for it
Details of the Construction Materials learned today Construction Material we are learned today : 1) PVC pipes, CPVC pipes, Insulation pipes, L-shape, Y-shape,Four Side Opening Section of pipe 2) PVC cover pipe, Flow Guard, Rubber 3) Pana, Cutter etc
Details of Environment Caring Technology / Methodology / Procedure / Product learned today We are learned today Environment Technology as follows : Use fly ash material which are produced by natural coals since to reduce the pollution of air
Details of the Construction / Engineering Drawings observed today Today we are observe above floor plan carefully : 1) Position of bathroom, sink, wash basin, attached toilets are studied 2) And with help of number of pipes connection we are calculated 3) Inspection Chamber 1m*1m are provided below each toilets and also at change in direction
Details of the Bye Laws referred today We are referred Bye Laws today for : 1) Size of Inspection Chamber 2) Distance between two inspection chamber 3) Above dimensions reffered in actual drawing
Details of any Managerial Skill learned today All stock materials are placed in a dry place . Materials such as cement bags, city tiles, plaster of paris bags are placed easily accessible to construction.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER : 12mm thick plaster (1:3) Assume 1m2 surface area Volume of mortor for 12mm plaster = 1 * 0.012 = 0.012m3 Add 30% for filling up uneven surface , =(0.015*30)/100 + 0.012 =0.0156m3 Add 20% for dry Volume = 0.0156 + (0.0156*0.25) = 0.0195 m3 CEMENT = 0.0195/(1+3) = 0.00487 M3 = 0.005 M3 NUMBER OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAG COST =( 0.15 * 3) = 39 RS SAND = 0.005 * 3 = 0.015 M3 COST = 0.015 * 1125 = 16.875 MATERIAL COST = 39 + 16.875 = 55.87 RS LABOUR : 1) MASON = 1 NUMBER =250 RS 2) UNSKIILED LABOUR = 1 NUMBER =140 TOTAL = 390 RS SCAFFOLDING : 30 RS TOTAL COST : 55.875 + 390 + 30 = 475.87 RS WATER 1 1/2% = (1.5 * 475.87) = 7.13 RS CONTRACTOR PROFIT = (10 * 475.87) = 475.87 RS TOTAL COST = 530 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530 RS
Todays BUZZ Word 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Abhijit Bhosale Mob No.9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-06

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave,Mukt sainik vasahat,kolhapur
Students Name (Surname_First Name_Middle Name) Shinde Shraddha Tukaram
Exam No. 10901
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 5.30pm
Details of the Work Allotted to you today by the Site In-Charge The work allotted to us today by the site in charge are as follows: 1) To visit whole site and investigate work going on the site. 2) To fill up the daily report form. 3) To work out the quantity of concrete for septic tank as per given drawing.
Details of how you Planned & Executed the allotted work -First of all,we started proceeding towards our site by observing work going on in the site. -One by one, we investigated all the flats and noted down details of the work going on. -Accordingly we observed all the seven floors. -For working out on quantity of concrete, we first studied the drawing of septic tank carefully. -Then we noted down the dimensions and calculated area,volume &then finally the quantity of the concrete required for the construction of septic tank.
Details of the Construction Procedure / Activity / Technology learned today Today we learned about construction of brickwork: -First, the bricks were soaked in water for one hour before they used for work. -New work should be kept wet during construction. -Some part of masonry work such as top of walls were kept covered with wet gunny bags as the work was not in progress. -No mortar joint should exceed 1/4\" for first class brickwork in cement & 3/8\" for second class brickwork in lime & no joint should be less than 3/16\" in thickness. -Mortar of proper consistency was applied on work. -Mortar that was too thick or too thin was sent back to mixing floor. -Surface of each course was thoroughly cleaned before another course was laid on top of it. -Straight lines were marked with a string which were pressed in the mortar.
Details of the Construction Materials learned today Today, we learned about paving blocks. There are various types of paving blocks like: -T-shape(Thickness=60mm) -Diamond shape(Thickness=60to80mm) -Cosmic(195nos.per 100sq.ft) -Roman-I(345nos.per100sq.ft) -Plus shape(140nos.per100sq.ft) -Flab(200nos.per100sq.ft) -Milan(224nos.per100sq.ft) -Irish(100+100nos.per100sq.ft) -Apple(250nos.per100sq.ft)
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Perforated sheets of 2\"x2\" are used in mild steed door in front of main door (teak wood) which will provide ventilation when required and also safety to use.
Details of the Construction / Engineering Drawings observed today Today, we observed: -drawing of electrification sheet of the flats. -Service layout for C wing which included the arrangement of laying of underground pipes. -Drawing of septic tank.
Details of the Bye Laws referred today Today the bye laws referred were: Residential zones with shop lines.R-2 non flashing business signs placed parallel to wall and not exceeding 1 meter height per establishment.
Details of any Managerial Skill learned today Today, sir had inspected the construction site to see whether the labors were doing their work properly or not,whether they were present on site or not and gave instructions about work carried on site. this will help him for giving payment of labors according to their work done.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER: A) 12mm thick in single coat for- a.Kitchen & dining=(2x(3.5+4))x3.35=50.25sq.m. b.Living room=(2x(3.5+5))x3.35=56.95sq.m. c.Bedroom=56.95sq.m. d.Veranda=33.66sq.m. e.Bathroom=11.90sq.m. f.W.C.=8.50sq.m. TOTAL=218.21sq.m. Deduction for- a.D1=2.6sq.m b.D2=13.2sq.m. c.D3=3.3sq.m. d.W1=11.2sq.m. e.W2=2.8sq.m. f.W3=0.9sq.m. g.Grill=3sq.m. TOTAL=37sq.m. Deduct 50%=218.21-(37/2) =199.71sq.m. Area of plaster=199.71sq.m. Volume of plaster=2.4cu.m. Add 50% for voids & 10% for unevenness Therefore, dry volume of mortar=2.4+2.4x(60/100) =3.84cu.m. Cement=3.84/(1+3)=0.96 =28bags. Sand=0.96x3=2.88cu.m. B)Cost of materials: a.Cement=28x230=Rs.6440 b.Sand=2.9x850=Rs.2465 TOTAL=Rs.8905 C)Cost of labors: a.Mistry=1x250=Rs.250 b.Mason=10x170=Rs.1700 c.Male mazdoor=15x140=Rs.2100 d.Bhisti=1x110=Rs.110 e.Scaffolding=Rs.300 f.T & P=Rs.300 TOTAL=Rs.9520 D)Total=B+C=Rs.18425 E)Add 2 % for water charges=Rs.368.5 F)Add 15% for contractor\'s profit=Rs.2763.75 G)Grand total=Rs.21557.25 H)Rate per sq.m.=Rs.107.94
Result of RATE ANALYSIS ( Rs per Unit ) Rs.107.94 per sq.m.
Todays BUZZ Word Today\'s buzz word: Building components which should be excluded from FSI computations- -Area covered by lofts,meter rooms,porches -Watchman\'s cabin -Area of balconies -Areas covered by service ducts,pump rooms,corridor passages. -Areas covered by additional lift -Area of separate letter box on ground floor of residential building.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol Mulay 9922507376
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-d6

Company Name Shendre Associates
Project Name & Site Address \'mallhar hights\',c.s no367\\9ward ambai defence,kolhapur
Students Name (Surname_First Name_Middle Name) Fulari sujata shankar
Exam No. 13559
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.45am
Site Leaving Time (HH:MM am/pm) 5.00pm
Details of the Work Allotted to you today by the Site In-Charge today site in-charge gave work for determine the quantity of paint required for one 2-bhk flat and its rate.
Details of how you Planned & Executed the allotted work - firstly we measure the room sizes of all room and calculate area with deducting door and window area and going for rate analysis for paint - these all work done with dividing two group of 2-3 student. .
Details of the Construction Procedure / Activity / Technology learned today -today we learn how to cast beam and placement of concrete for casting beam and mixing of ingredients for concrete. -plumbing fitting for bath & w.c
Details of the Construction Materials learned today on site we learn water proofing material in mixing of concrete for grater strength of concrete. - this water proofing chemical is about rate 1500per 5litre and mix in concrete with per bag of cement 100ml - About the water proofing material \"DR. FIXIT\".
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environment Caring Technology : To use crushing sand in place of natural sand.Therefore to minimize environment pollution
Details of the Construction / Engineering Drawings observed today - Plumbing Drawing - Floor plans.
Details of the Bye Laws referred today - For plumbing - For plastering. - Height of ventilator
Details of any Managerial Skill learned today - Punctuality is the key to success
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:2) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+2=0.0065cu.m no.of bag=0.0065/0.0035=0.019 cost of cement=(0.19*270)=50.14say51rs. sand=0.0065*2=0.013cu.m cost of sand=(0.013*1125)=14.62rs material cost=(51+14.62)=65.62say66rs. labour mason 250rs unskilled labour 140rs scaffolding 50rs cost=440rs. total cost of =(66+440)=50rs. water=1.5%=1.5/100*506=7.59rs. contractor profit=10/100*506=50.6rs. TOTAL COST OF PLASTERING FOR 0.012cu.m =(506+7.59+50.6)=564.19rs
Result of RATE ANALYSIS ( Rs per Unit ) 564.19rs
Todays BUZZ Word 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: bsalman75@yahoo.com
Subject: 10888-06

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) baig salman samad
Exam No. 10888
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for beams and fixing of beam bottoms, checking their levels, heights, manufacturing of concrete of m20 as per proportions and placing of concrete on stair case reinforcement and checking thickness of concrete for rise
Details of how you Planned & Executed the allotted work We checked the width and depth of beam and height of beam bottom from floor level. Then we inspected the manufacturing of concrete, counted the pans of sand and aggregate, and liters of water used in its manufacturing. We saw the placing and compaction of concrete on the reinforcement of stair case.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the side of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing concrete in stair case section and its compaction with needle vibrator
Details of the Construction Materials learned today No new material has been used today on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method or material is used on the site
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Compound wall provide on the site is 1.50m in height. As per bye law height is 1.50m minimum.
Details of any Managerial Skill learned today Self involvement in selection of material required considering quantity of material and rate to achieve economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for compound wall using cement blocks“ Dimensions of typical part of wall-2.9*1.5*0.15m Size of block-0.75*0.40*0.15m 1. Volume of wall =0.6525 cu.m. 2.Quantity of cement mortar (1:6)=45% of total volume =0.29cu.m. 3. Quantity of cement =0.29/1+6 =0.041 =0.041/0.035=1.18=2 bags 4. Quantity of sand=0.041*6=0.246 cu.m. 5. number of blocks=55nos “Rate Analysis for compound wall using cement blocks” (Considering local rates of material) (wall size=2.9*1.5*0.15m) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.246*1600=394/-…………(1600/- per cu.m.) 3. Cost of block=55*10=550/-…………(10/- per block ) 4.Labour charges=1130/- 7. Total cost= 2574/- 8.10% profit of total cost for the contractor=257.4/- 9. Total cost=2831/-
Result of RATE ANALYSIS ( Rs per Unit ) 4338/-
Todays BUZZ Word 1.Passage upto 1.20m 2.Lift well having dimensions of1.20*1.20m 3.Stair case upto 1.20m in width. 4.Balcony having area less than 1/3rd of the total area of the flat
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: vishalsapakal@gmail.com
Subject: 10882-06

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) sapakal vishal manohar
Exam No. 10882
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for beams and fixing of beam bottoms, checking their levels, heights, manufacturing of concrete of m20 as per proportions and placing of concrete on stair case reinforcement and checking thickness of concrete for rise
Details of how you Planned & Executed the allotted work We checked the width and depth of beam and height of beam bottom from floor level. Then we inspected the manufacturing of concrete, counted the pans of sand and aggregate, and liters of water used in its manufacturing. We saw the placing and compaction of concrete on the reinforcement of stair case.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the side of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing concrete in stair case section and its compaction with needle vibrator
Details of the Construction Materials learned today No new material has been used today on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method or material is used on the site
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Compound wall provide on the site is 1.50m in height. As per bye law height is 1.50m minimum.
Details of any Managerial Skill learned today Self involvement in selection of material required considering quantity of material and rate to achieve economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for compound wall using cement blocks“ Dimensions of typical part of wall-2.9*1.5*0.15m Size of block-0.75*0.40*0.15m 1. Volume of wall =0.6525 cu.m. 2.Quantity of cement mortar (1:6)=45% of total volume =0.29cu.m. 3. Quantity of cement =0.29/1+6 =0.041 =0.041/0.035=1.18=2 bags 4. Quantity of sand=0.041*6=0.246 cu.m. 5. number of blocks=55nos “Rate Analysis for compound wall using cement blocks” (Considering local rates of material) (wall size=2.9*1.5*0.15m) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.246*1600=394/-…………(1600/- per cu.m.) 3. Cost of block=55*10=550/-…………(10/- per block ) 4.Labour charges=1130/- 7. Total cost= 2574/- 8.10% profit of total cost for the contractor=257.4/- 9. Total cost=2831/-
Result of RATE ANALYSIS ( Rs per Unit ) 4338/-
Todays BUZZ Word 1.Passage upto 1.20m 2.Lift well having dimensions of1.20*1.20m 3.Stair case upto 1.20m in width. 4.Balcony having area less than 1/3rd of the total area of the flat
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-06

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) babar moreshwar mahipati
Exam No. 10873
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for beams and fixing of beam bottoms, checking their levels, heights, manufacturing of concrete of m20 as per proportions and placing of concrete on stair case reinforcement and checking thickness of concrete for rise
Details of how you Planned & Executed the allotted work We checked the width and depth of beam and height of beam bottom from floor level. Then we inspected the manufacturing of concrete, counted the pans of sand and aggregate, and liters of water used in its manufacturing. We saw the placing and compaction of concrete on the reinforcement of stair case.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the side of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing concrete in stair case section and its compaction with needle vibrator
Details of the Construction Materials learned today No new material has been used today on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method or material is used on the site
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Compound wall provide on the site is 1.50m in height. As per bye law height is 1.50m minimum.
Details of any Managerial Skill learned today Self involvement in selection of material required considering quantity of material and rate to achieve economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for compound wall using cement blocks“ Dimensions of typical part of wall-2.9*1.5*0.15m Size of block-0.75*0.40*0.15m 1. Volume of wall =0.6525 cu.m. 2.Quantity of cement mortar (1:6)=45% of total volume =0.29cu.m. 3. Quantity of cement =0.29/1+6 =0.041 =0.041/0.035=1.18=2 bags 4. Quantity of sand=0.041*6=0.246 cu.m. 5. number of blocks=55nos “Rate Analysis for compound wall using cement blocks” (Considering local rates of material) (wall size=2.9*1.5*0.15m) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.246*1600=394/-…………(1600/- per cu.m.) 3. Cost of block=55*10=550/-…………(10/- per block ) 4.Labour charges=1130/- 7. Total cost= 2574/- 8.10% profit of total cost for the contractor=257.4/- 9. Total cost=2831/-
Result of RATE ANALYSIS ( Rs per Unit ) 4338/-
Todays BUZZ Word 1.Passage upto 1.20m 2.Lift well having dimensions of1.20*1.20m 3.Stair case upto 1.20m in width. 4.Balcony having area less than 1/3rd of the total area of the flat
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-06

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Suyvanshi patil Pratiksinh Vilas
Exam No. 13549
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 5:00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To see the work going on of plumbing 2. To see the work of plastering. 3. To estimate the plastering cost.
Details of how you Planned & Executed the allotted work - We group of five were divided in two groups - First group for half time we saw the plumbing - Second we saw the plastering, and vice-versa. - Then we measured the room and calculated the plastering.
Details of the Construction Procedure / Activity / Technology learned today - About plumbing - Plastering - Dealing with labours
Details of the Construction Materials learned today - About the water proofing material \"DR. FIXIT\".
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - none
Details of the Construction / Engineering Drawings observed today - Plumbing Drawing - Floor plans.
Details of the Bye Laws referred today - For plumbing - For plastering.
Details of any Managerial Skill learned today - Punctuality is the key to success
RATE ANALYSIS (Detailed Stepwise Calculations required) 2 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost= 39.0+16.875= Rs55.87 labor = mason1= Rs250 labor= Rs140 total= Rs390 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13
Result of RATE ANALYSIS ( Rs per Unit ) Rs 530.58
Todays BUZZ Word The following shall not be counted during F.S.I. 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: patilpratibha7070@yahoo.in
Subject: 10896-06

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) patil pratibha dilip
Exam No. 10896
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for beams and fixing of beam bottoms, checking their levels, heights, manufacturing of concrete of m20 as per proportions and placing of concrete on stair case reinforcement and checking thickness of concrete for rise
Details of how you Planned & Executed the allotted work We checked the width and depth of beam and height of beam bottom from floor level. Then we inspected the manufacturing of concrete, counted the pans of sand and aggregate, and liters of water used in its manufacturing. We saw the placing and compaction of concrete on the reinforcement of stair case.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the side of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing concrete in stair case section and its compaction with needle vibrator
Details of the Construction Materials learned today No new material has been used today on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method or material is used on the site
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Compound wall provide on the site is 1.50m in height. As per bye law height is 1.50m minimum.
Details of any Managerial Skill learned today Self involvement in selection of material required considering quantity of material and rate to achieve economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for compound wall using cement blocks“ Dimensions of typical part of wall-2.9*1.5*0.15m Size of block-0.75*0.40*0.15m 1. Volume of wall =0.6525 cu.m. 2.Quantity of cement mortar (1:6)=45% of total volume =0.29cu.m. 3. Quantity of cement =0.29/1+6 =0.041 =0.041/0.035=1.18=2 bags 4. Quantity of sand=0.041*6=0.246 cu.m. 5. number of blocks=55nos “Rate Analysis for compound wall using cement blocks” (Considering local rates of material) (wall size=2.9*1.5*0.15m) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.246*1600=394/-…………(1600/- per cu.m.) 3. Cost of block=55*10=550/-…………(10/- per block ) 4.Labour charges=1130/- 7. Total cost= 2574/- 8.10% profit of total cost for the contractor=257.4/- 9. Total cost=2831/-
Result of RATE ANALYSIS ( Rs per Unit ) 4338/-
Todays BUZZ Word 1.Passage upto 1.20m 2.Lift well having dimensions of1.20*1.20m 3.Stair case upto 1.20m in width. 4.Balcony having area less than 1/3rd of the total area of the flat
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-06

Company Name P. B. Builders & Developers
Project Name & Site Address P. B. Builders & Developers
Students Name (Surname_First Name_Middle Name) Shivtare Prabhakar Chandrakant
Exam No. 13569
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To take the levels of existing road and plotting them on the building.
Details of how you Planned & Executed the allotted work We transfer the road level on the existing permanent structure and then on the columns of the building. We execute the work with the help of water level tube.
Details of the Construction Procedure / Activity / Technology learned today Taking levels with the help of the help of water level.
Details of the Construction Materials learned today Types of PVC pies:- A-PVC C-PVC
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use Eco-friendly plywood which is made up of waste material from Sugar factory.
Details of the Construction / Engineering Drawings observed today Sections of the building
Details of the Bye Laws referred today Bye-laws for the FSI calculations.
Details of any Managerial Skill learned today Punctuality is the key to success.
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs
Result of RATE ANALYSIS ( Rs per Unit ) 530.58Rs
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr.Bharamal
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-06

Company Name P. B. Builders & Developers
Project Name & Site Address P. B. Builders & Developers
Students Name (Surname_First Name_Middle Name) Sutar Namdev Rangnath
Exam No. 13571
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To take the levels of existing road and plotting them on the building.
Details of how you Planned & Executed the allotted work We transfer the road level on the existing permanent structure and then on the columns of the building. We execute the work with the help of water level tube.
Details of the Construction Procedure / Activity / Technology learned today Taking levels with the help of the help of water level.
Details of the Construction Materials learned today Types of PVC pies:- A-PVC C-PVC
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use Eco-friendly plywood which is made up of waste material from Sugar factory.
Details of the Construction / Engineering Drawings observed today Sections of the building
Details of the Bye Laws referred today Bye-laws for the FSI calculations.
Details of any Managerial Skill learned today Punctuality is the key to success.
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs
Result of RATE ANALYSIS ( Rs per Unit ) 530.58Rs
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Bharamal
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: mayur.sonawane61@gmail.com
Subject: 13570-06

Company Name P. B. Builders & Developers
Project Name & Site Address P. B. Builders & Developers
Students Name (Surname_First Name_Middle Name) Sonavane Mayur Madhukar
Exam No. 13570
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To take the levels of existing road and plotting them on the building.
Details of how you Planned & Executed the allotted work We transfer the road level on the existing permanent structure and then on the columns of the building. We execute the work with the help of water level tube.
Details of the Construction Procedure / Activity / Technology learned today Taking levels with the help of the help of water level.
Details of the Construction Materials learned today Types of PVC pies:- A-PVC C-PVC
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use Eco-friendly plywood which is made up of waste material from Sugar factory.
Details of the Construction / Engineering Drawings observed today Sections of the building
Details of the Bye Laws referred today Bye-laws for the FSI calculations.
Details of any Managerial Skill learned today Punctuality is the key to success.
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs
Result of RATE ANALYSIS ( Rs per Unit ) 530.58Rs
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Bharamal
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-06

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) yadavhrisheekesh deepak
Exam No. 10885
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for beams and fixing of beam bottoms, checking their levels, heights, manufacturing of concrete of m20 as per proportions and placing of concrete on stair case reinforcement and checking thickness of concrete for rise
Details of how you Planned & Executed the allotted work We checked the width and depth of beam and height of beam bottom from floor level. Then we inspected the manufacturing of concrete, counted the pans of sand and aggregate, and liters of water used in its manufacturing. We saw the placing and compaction of concrete on the reinforcement of stair case.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the side of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing concrete in stair case section and its compaction with needle vibrator
Details of the Construction Materials learned today No new material has been used today on the site.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such method or material is used on the site
Details of the Construction / Engineering Drawings observed today Detail plan of first floor.
Details of the Bye Laws referred today Compound wall provide on the site is 1.50m in height. As per bye law height is 1.50m minimum.
Details of any Managerial Skill learned today Self involvement in selection of material required considering quantity of material and rate to achieve economy.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for compound wall using cement blocks“ Dimensions of typical part of wall-2.9*1.5*0.15m Size of block-0.75*0.40*0.15m 1. Volume of wall =0.6525 cu.m. 2.Quantity of cement mortar (1:6)=45% of total volume =0.29cu.m. 3. Quantity of cement =0.29/1+6 =0.041 =0.041/0.035=1.18=2 bags 4. Quantity of sand=0.041*6=0.246 cu.m. 5. number of blocks=55nos “Rate Analysis for compound wall using cement blocks” (Considering local rates of material) (wall size=2.9*1.5*0.15m) 1. Cost of cement=2*250=500/-………..(250/- per bag) 2. Cost of sand=0.246*1600=394/-…………(1600/- per cu.m.) 3. Cost of block=55*10=550/-…………(10/- per block ) 4.Labour charges=1130/- 7. Total cost= 2574/- 8.10% profit of total cost for the contractor=257.4/- 9. Total cost=2831/-
Result of RATE ANALYSIS ( Rs per Unit ) 4338/-
Todays BUZZ Word “Building components excluded in F.S.I calculations” In calculation of FSI following components are excluded- 1.Passage upto 1.20m 2.Lift well having dimensions of1.20*1.20m 3.Stair case upto 1.20m in width. 4.Balcony having area less than 1/3rd of the total area of the flat
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: shinde_shital7@yahoo.com
Subject: 10884-06

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL KARANDEMALA CIRCUITHOUSE KOLHAPUR
Students Name (Surname_First Name_Middle Name) SHINDE SHITAL VILASRAO
Exam No. 10884
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge TO OBSERVED HOW TO DO PLASTER WORK.
Details of how you Planned & Executed the allotted work WE DIVIDED IN TWO GROUPS. FIRST GROUP SAW THICKNESS OF PLASTER IN HALL. SECOND GROUP SAW THICKNESS OF PLASTER IN KITCHEN. BOTH GROUP OBSERVED THAT THICKNESS OF PLASTER SHOULD BE SAME.
Details of the Construction Procedure / Activity / Technology learned today WE LEARNED THAT HOW TO WORKER CHECK THE THICKNESS OF PLASTER BY PLUMBING BOB.WHEN THICKNESS OF PLASTER NOT SAME USE MORE MORTAR TO BECOME LEVEL AND FOR GOOD APPEARANCE.
Details of the Construction Materials learned today We learned Construction Materials sand ,cement, trowel, measuring scale.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today TO USE CRUSHING SAND IN PLACE NATURAL SAND.
Details of the Construction / Engineering Drawings observed today WE OBSERVED ENGINEERING DRAWING PARKING AREA.
Details of the Bye Laws referred today WE OBSERVED BYE LAWS FOR RISE, TRADE , WIDTH OF STAIR. RISE=150mm TRADE=250mm WIDTH OF STAIR=1.56m
Details of any Managerial Skill learned today THE AGGERGATE,SAND, BRICK ,ARE PLACED IN A SUITABLE PLACE TO CONVEY EASY LIFTING OF MATERIAL.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR PLASTER FOR 1 BRASS 10\'*10\'=(3048*3048)mm=929sq.m PROPORTION 1:18 FOR 1 BRASS CEMENT =1 BAG COST FOR 1 BAG=260Rs **SAND:- SAND=18*15=270Rs 22 PER sq. feet=22*10 =220Rs **LABOUR COST=270Rs TOTAL COST=750Rs FOR 1 BRASS =750Rs 1 sq. m=? 1 sq.m=80.7281Rs
Result of RATE ANALYSIS ( Rs per Unit ) 81Rs
Todays BUZZ Word OPEN TO SKY=(16\'*14\'6\") DUCT =(11\'10\"*5\'8\") BALCONY =(10\'10\"*6\') LOBBY =(12\'3\"*14\'6\") STAIRCASE =(68.04)sq.foot LIFT =(5\'6\"*5\'6\") TERRACE =(10\'4\"*5\'2\")
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge KETAN CHARAPALE Mo.No.6552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 13567-06

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To take the levels of existing road and plotting them on the building.
Details of how you Planned & Executed the allotted work We transfer the road level on the existing permanent structure and then on the columns of the building. We execute the work with the help of water level tube.
Details of the Construction Procedure / Activity / Technology learned today Taking levels with the help of the help of water level.
Details of the Construction Materials learned today Types of PVC pies:- A-PVC C-PVC
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use Eco-friendly plywood which is made up of waste material from Sugar factory.
Details of the Construction / Engineering Drawings observed today Sections of the building
Details of the Bye Laws referred today Bye-laws for the FSI calculations.
Details of any Managerial Skill learned today Punctuality is the key to success.
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs
Result of RATE ANALYSIS ( Rs per Unit ) 530.58Rs
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Bharamal
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: v.g.ayyar@gmail.com
Subject: 13553-06

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Ayyar Vignesh Gopal
Exam No. 13553
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:50pm
Details of the Work Allotted to you today by the Site In-Charge 1. To see the work going on of plumbing 2. To see the work of plastering. 3. To estimate the plastering cost.
Details of how you Planned & Executed the allotted work - We group of five were divided in two groups - First group for half time we saw the plumbing - Second we saw the plastering, and vice-versa. - Then we measured the room and calculated the plastering.
Details of the Construction Procedure / Activity / Technology learned today - About plumbing - Plastering - Dealing with labours
Details of the Construction Materials learned today - About the water proofing material \"DR. FIXIT\".
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - none
Details of the Construction / Engineering Drawings observed today - Plumbing Drawing - Floor plans.
Details of the Bye Laws referred today - For plumbing - For plastering.
Details of any Managerial Skill learned today - Punctuality is the key to success
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost= 39.0+16.875= Rs55.87 labor = mason1= Rs250 labor= Rs140 total= Rs390 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13
Result of RATE ANALYSIS ( Rs per Unit ) Rs530.58
Todays BUZZ Word The following shall not be counted during F.S.I. 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-06

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Tekwani Sagar Bansilal
Exam No. 10903
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) To check electrification points according to electrification plan
Details of how you Planned & Executed the allotted work - One of us holded electrificatrion plan,other student was finding location according to plan and remaining students were checking ponts according to instruction\'s.
Details of the Construction Procedure / Activity / Technology learned today 1) Pile foundation at nearby site of Chetan Oswal. 2) Placing of concrete of slab which was transported with pumps & pipes.
Details of the Construction Materials learned today - Pipes used for concealed electrification purpose
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today 1) Electrification plan & 2) Centre line plan
Details of the Bye Laws referred today 1) Door size provided was 1.18m*2.1m, according to Bye-Laws it should be minimum 0.9m*2.0m. 2) Window size provided was 1.2m*1.2m, according to Bye-Laws it should be minimum 0.6m*1.2m.
Details of any Managerial Skill learned today -We saw how to solve the problem arrived during constuction activites.
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost= 39.0+16.875= Rs55.87 labor = mason1= Rs250 labor= Rs140 total= Rs390 Scaffolding= Rs30 water1.5%=1.5/100*475.87= Rs7.13
Result of RATE ANALYSIS ( Rs per Unit ) Rs530.58
Todays BUZZ Word The following shall not be counted during F.S.I. 1) Stuctures permitted in recreational open spaces. 2) All the features permitted in open spaces. 3) Area covered by stair-case of width of 1.2m or more,lift room above above the top most storey,lift wells, stair wells etc. 4) Area of basement used only for storage, A.C. plant, meter room, Electric sub-station or parking. 5) Area of fire escape stairways and fire escape passages. 6) Refuge area. 7) Area of balconies. 8) Area of unenclosed but covered parking spaces. 9) Lofts. 10) Meter rooms. 11) Porches. 12) Canopies. 13) Watchman cabin of size 5 sq.m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 09922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: cool.sushant007@gmail.com
Subject: 10880-06

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil sushant digambar
Exam No. 10880
Working Day No. 04
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge check out the plumbing work done in the flats and use of various type of equipments.
Details of how you Planned & Executed the allotted work we first collected the plumbing drawings from the site supervisor , after stuyding those drawings we go to the room with the drawings and we check that whether those dimensions actually followed in the place or not by checking the dimensions.
Details of the Construction Procedure / Activity / Technology learned today they are provided foam material for insulation of hot water pipes. for flushing purpose pipes of larger diameter is used.most of the plumbing work is done is concealed.hot and cold water mixers are provided for showers. nahani traps are provided for bathrooms , kitchen sink. bore water is used for flushing and municipal water is utilised for drinking and washing purpose.
Details of the Construction Materials learned today various types of fittings in toilet, bath ,utility.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use steel formwork instead of using wood.
Details of the Construction / Engineering Drawings observed today Detailed plumbing drawings of each flats.
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 390 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 475.87 RS WATER= 1.5 % = 7.13 RS CONTRACTOR PROFIT = 10% = 47.58 RS TOTAL COST = 530.58 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530.58 RS
Todays BUZZ Word 1. if balcony width is less 1.2 m then it is excluded in F.S.I. 2. If stair width is less or equal than 1 m then it is excluded in F.S.I. 3. porch area is not considered in F.S.I. 4. Open to sky portion is not considered in F.S.I. 5. lobby area is not considered in F.S.I. 6. terrace area is not considered in F.S.I.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-06

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) misal swapnil shivaji
Exam No. 10877
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge check out the plumbing work done in the flats and use of various type of equipments.
Details of how you Planned & Executed the allotted work we first collected the plumbing drawings from the site supervisor , after stuyding those drawings we go to the room with the drawings and we check that whether those dimensions actually followed in the place or not by checking the dimensions.
Details of the Construction Procedure / Activity / Technology learned today they are provided foam material for insulation of hot water pipes. for flushing purpose pipes of larger diameter is used.most of the plumbing work is done is concealed.hot and cold water mixers are provided for showers. nahani traps are provided for bathrooms , kitchen sink. bore water is used for flushing and municipal water is utilised for drinking and washing purpose.
Details of the Construction Materials learned today various types of fittings in toilet, bath ,utility.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use steel formwork instead of using wood.
Details of the Construction / Engineering Drawings observed today Detailed plumbing drawings of each flats.
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 390 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 475.87 RS WATER= 1.5 % = 7.13 RS CONTRACTOR PROFIT = 10% = 47.58 RS TOTAL COST = 530.58 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530.58 RS
Todays BUZZ Word 1. if balcony width is less 1.2 m then it is excluded in F.S.I. 2. If stair width is less or equal than 1 m then it is excluded in F.S.I. 3. porch area is not considered in F.S.I. 4. Open to sky portion is not considered in F.S.I. 5. lobby area is not considered in F.S.I. 6. terrace area is not considered in F.S.I.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. KETAN CHARAPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-06

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SALOKHE SUDARSHAN ANIL
Exam No. 13544
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.30 pm
Details of the Work Allotted to you today by the Site In-Charge check out the plumbing work done in the flats and use of various type of equipments.
Details of how you Planned & Executed the allotted work we first collected the plumbing drawings from the site supervisor , after stuyding those drawings we go to the room with the drawings and we check that whether those dimensions actually followed in the place or not by checking the dimensions.
Details of the Construction Procedure / Activity / Technology learned today they are provided foam material for insulation of hot water pipes. for flushing purpose pipes of larger diameter is used.most of the plumbing work is done is concealed.hot and cold water mixers are provided for showers. nahani traps are provided for bathrooms , kitchen sink. bore water is used for flushing and municipal water is utilised for drinking and washing purpose.
Details of the Construction Materials learned today various types of fittings in toilet, bath ,utility.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use steel formwork instead of using wood.
Details of the Construction / Engineering Drawings observed today Detailed plumbing drawings of each flats.
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 390 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 475.87 RS WATER= 1.5 % = 7.13 RS CONTRACTOR PROFIT = 10% = 47.58 RS TOTAL COST = 530.58 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530.58 RS
Todays BUZZ Word 1. if balcony width is less 1.2 m then it is excluded in F.S.I. 2. If stair width is less or equal than 1 m then it is excluded in F.S.I. 3. porch area is not considered in F.S.I. 4. Open to sky portion is not considered in F.S.I. 5. lobby area is not considered in F.S.I. 6. terrace area is not considered in F.S.I.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Abhijit bhosale 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-06

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHAIKH RIZWAN KHALIL
Exam No. 13545
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.30 pm
Details of the Work Allotted to you today by the Site In-Charge check out the plumbing work done in the flats and use of various type of equipments.
Details of how you Planned & Executed the allotted work we first collected the plumbing drawings from the site supervisor , after stuyding those drawings we go to the room with the drawings and we check that whether those dimensions actually followed in the place or not by checking the dimensions.
Details of the Construction Procedure / Activity / Technology learned today they are provided foam material for insulation of hot water pipes. for flushing purpose pipes of larger diameter is used.most of the plumbing work is done is concealed.hot and cold water mixers are provided for showers. nahani traps are provided for bathrooms , kitchen sink. bore water is used for flushing and municipal water is utilised for drinking and washing purpose.
Details of the Construction Materials learned today various types of fittings in toilet, bath ,utility.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use steel formwork instead of using wood.
Details of the Construction / Engineering Drawings observed today Detailed plumbing drawings of each flats.
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 390 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 475.87 RS WATER= 1.5 % = 7.13 RS CONTRACTOR PROFIT = 10% = 47.58 RS TOTAL COST = 530.58 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530.58 RS
Todays BUZZ Word 1. if balcony width is less 1.2 m then it is excluded in F.S.I. 2. If stair width is less or equal than 1 m then it is excluded in F.S.I. 3. porch area is not considered in F.S.I. 4. Open to sky portion is not considered in F.S.I. 5. lobby area is not considered in F.S.I. 6. terrace area is not considered in F.S.I.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Abhijit bhosale 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-06

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SINGH RAJAN RAJENDRA BAHADUR
Exam No. 13548
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.30 pm
Details of the Work Allotted to you today by the Site In-Charge check out the plumbing work done in the flats and use of various type of equipments
Details of how you Planned & Executed the allotted work we first collected the plumbing drawings from the site supervisor , after stuyding those drawings we go to the room with the drawings and we check that whether those dimensions actually followed in the place or not by checking the dimensions.
Details of the Construction Procedure / Activity / Technology learned today they are provided foam material for insulation of hot water pipes. for flushing purpose pipes of larger diameter is used.most of the plumbing work is done is concealed.hot and cold water mixers are provided for showers. nahani traps are provided for bathrooms , kitchen sink. bore water is used for flushing and municipal water is utilised for drinking and washing purpose.
Details of the Construction Materials learned today various types of fittings in toilet, bath ,utility.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use steel formwork instead of using wood.
Details of the Construction / Engineering Drawings observed today Detailed plumbing drawings of each flats.
Details of the Bye Laws referred today We saw the details of the marginal spaces which is 2m front , 1.5m rear and 2m side margine which is according to the bye-laws of the Kolhapur.
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR INTERNAL PLASTER: 12 MM THICK PLASTER , PROPORTION USED 1:3 PLASTER FOR 1 SQ.M SURFACE AREA VOLUME OF MORTAR FOR 12 MM PLASTER = 1 X 0.012 = 0.012 CU.M ADD 30% FOR FILLING UP UNEVEN SURFACE = 1.30 X 0.012 = 0.0156 CU.M ADD 25 % FOR DRY VOLUME = 1.25 X 0.0156 = 0.0195 CU.M CEMENT = 0.0195/(1+3)= 0.00487 CU.M = 0.005 CU.M NO. OF BAGS = 0.005/0.035 = 0.142 = 0.15 BAGS COST= (260 X 0.15)=39 RS SAND = 0.005 X 3 = 0.015 CU.M COST= (1125 X 0.015)= 16.87 RS TOTAL COST OF MATERIAL= 39 + 16.87 = 55.87 RS LABOUR = 390 RS SCAFFOLDING = 30 RS TOTAL COST = 55.87 + 390 + 30 = 475.87 RS WATER= 1.5 % = 7.13 RS CONTRACTOR PROFIT = 10% = 47.58 RS TOTAL COST = 530.58 RS
Result of RATE ANALYSIS ( Rs per Unit ) 530.58 RS
Todays BUZZ Word 1. if balcony width is less 1.2 m then it is excluded in F.S.I. 2. If stair width is less or equal than 1 m then it is excluded in F.S.I. 3. porch area is not considered in F.S.I. 4. Open to sky portion is not considered in F.S.I. 5. lobby area is not considered in F.S.I. 6. terrace area is not considered in F.S.I.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Abhijit bhosale 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-06

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sutar Namdev Rangnath
Exam No. 13571
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To take the levels of existing road and plotting them on the building. .
Details of how you Planned & Executed the allotted work We transfer the road level on the existing permanent structure and then on the columns of the building. We execute the work with the help of water level tube. .
Details of the Construction Procedure / Activity / Technology learned today Taking levels with the help of the help of water level. .
Details of the Construction Materials learned today Types of PVC pies:- A-PVC C-PVC .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use Eco-friendly plywood which is made up of waste material from Sugar factory. .
Details of the Construction / Engineering Drawings observed today Sections of the building. .
Details of the Bye Laws referred today Bye-laws for the FSI calculations. .
Details of any Managerial Skill learned today Punctuality is the key to success. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs TOTAL COST=530.58Rs .
Result of RATE ANALYSIS ( Rs per Unit ) 530.5/cu.m
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. P.Bharamal. .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-06

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 80 , near new palace, nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Redekar Shantanu Ravindra
Exam No. 13566
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge Pile foundation - * to understand about pile foundation construction. * to understand about pile foundation layout as per drawing. * R.C.C. slab to floor on other side
Details of how you Planned & Executed the allotted work * first we observe the center of pile. * we saw how to construct pile. * requirement depth for pile.
Details of the Construction Procedure / Activity / Technology learned today * first we observe the position of pile from given plan. * workers set up the assembly of pile foundation. * four workers are required for this job. * after the pile then concreting has placed properly in to that pile.
Details of the Construction Materials learned today Steel rod rope tripod bulb cutter aggregate 20-25 mm sand- river sand cement- opc 43 grade water- bore water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today best high technique used for excavating of pile surface area.
Details of the Construction / Engineering Drawings observed today * pile foundation layout * reinforcement details for pile * slab drawing
Details of the Bye Laws referred today parking area/space- the maximum size of parking to be provided with respect to bylaws. motor vehicales- 2.5 x 5.5 m (min) scooter - 3.89 m (min) bicycle - 1.4 m2 (min)
Details of any Managerial Skill learned today * work out the quantities * prepare requirement of material * check the daily progress report * maintain the clean liness of the site
RATE ANALYSIS (Detailed Stepwise Calculations required) plastering (1:6) for 100 m2 area, thik-12mm volume of morter= 100x0.012 = 1.2 m3 add 30% for filling joints= 1.56m3 add 25% for morter in dry weight= 1.95m3 cement = (1.95/7)x1 = 7.7= 8 nos. sand = (1.95/7)x6 = 1.67 m3 SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 8 bags 250.00/- 2000.00/- b) sand 1.67 cum 850.00/- (per cum) 1420.00/- 2 Labourers a) head mason 2 no. 300.00/- 600.00/- b) male mazdur 4 no. 200.00/- 800.00/- c) female mazdur 2 no. 120.00/- 240.00/- d) bhisti 1 no. 120.00/- 240.00/- 3 Others _ TOTAL 5210.00/- 4 Tools and plant @ 1.5% ----------------------- 78.50/- on total 5 Water charges @ 1.0% ----------------------- 52.00/- on total TOTAL(A) 5340.50/- 6 Overhead and profit @ 15% on tOtal A ----------------------- 800.00/- -------------------------------------------------------------------------- TOTAL = 6140.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 6140.00/-
Todays BUZZ Word * structure permitted in recreational open spaces. * all the features permitted in open spaces. * area of fire escape stairways and fire excape passages. * area of the basement , used only for storage, a.c. plant, meter room, electric sub-station or parking. * watchman cabin of size 5.00 m2.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: shindeamol5255@yahoo.in
Subject: 13546-06

Company Name Deshmukh Developers
Project Name & Site Address Goldenshelter
Students Name (Surname_First Name_Middle Name) Shinde Amol Jagannath
Exam No. 13546
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To take the levels of existing road and plotting them on the building. .
Details of how you Planned & Executed the allotted work We transfer the road level on the existing permanent structure and then on the columns of the building. We execute the work with the help of water level tube. .
Details of the Construction Procedure / Activity / Technology learned today Taking levels with the help of the help of water level. .
Details of the Construction Materials learned today Types of PVC pies:- A-PVC C-PVC .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use Eco-friendly plywood which is made up of waste material from Sugar factory. .
Details of the Construction / Engineering Drawings observed today Sections of the building. .
Details of the Bye Laws referred today Bye-laws for the FSI calculations. .
Details of any Managerial Skill learned today Punctuality is the key to success. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs TOTAL COST=530.58Rs .
Result of RATE ANALYSIS ( Rs per Unit ) 530.5/cu.m
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Bhosle. .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: abkhade@yahoo.com
Subject: 13563-06

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 80 , near new palace, nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge Pile foundation - * to understand about pile foundation construction. * to understand about pile foundation layout as per drawing. * R.C.C. slab to floor on other side
Details of how you Planned & Executed the allotted work * first we observe the center of pile. * we saw how to construct pile. * requirement depth for pile.
Details of the Construction Procedure / Activity / Technology learned today * first we observe the position of pile from given plan. * workers set up the assembly of pile foundation. * four workers are required for this job. * after the pile then concreting has placed properly in to that pile.
Details of the Construction Materials learned today Steel rod rope tripod bulb cutter aggregate 20-25 mm sand- river sand cement- opc 43 grade water- bore water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today best high technique used for excavating of pile surface area.
Details of the Construction / Engineering Drawings observed today * pile foundation layout * reinforcement details for pile * slab drawing
Details of the Bye Laws referred today parking area/space- the maximum size of parking to be provided with respect to bylaws. motor vehicales- 2.5 x 5.5 m (min) scooter - 3.89 m (min) bicycle - 1.4 m2 (min)
Details of any Managerial Skill learned today * work out the quantities * prepare requirement of material * check the daily progress report * maintain the clean liness of the site
RATE ANALYSIS (Detailed Stepwise Calculations required) plastering (1:6) for 100 m2 area, thik-12mm volume of morter= 100x0.012 = 1.2 m3 add 30% for filling joints= 1.56m3 add 25% for morter in dry weight= 1.95m3 cement = (1.95/7)x1 = 7.7= 8 nos. sand = (1.95/7)x6 = 1.67 m3 SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 8 bags 250.00/- 2000.00/- b) sand 1.67 cum 850.00/- (per cum) 1420.00/- 2 Labourers a) head mason 2 no. 300.00/- 600.00/- b) male mazdur 4 no. 200.00/- 800.00/- c) female mazdur 2 no. 120.00/- 240.00/- d) bhisti 1 no. 120.00/- 240.00/- 3 Others _ TOTAL 5210.00/- 4 Tools and plant @ 1.5% ----------------------- 78.50/- on total 5 Water charges @ 1.0% ----------------------- 52.00/- on total TOTAL(A) 5340.50/- 6 Overhead and profit @ 15% on tOtal A ----------------------- 800.00/- -------------------------------------------------------------------------- TOTAL = 6140.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 6140.00/-
Todays BUZZ Word * structure permitted in recreational open spaces. * all the features permitted in open spaces. * area of fire escape stairways and fire excape passages. * area of the basement , used only for storage, a.c. plant, meter room, electric sub-station or parking. * watchman cabin of size 5.00 m2.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-06

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Shivtare Prabharkar Chandrakant
Exam No. 13569
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To take the levels of existing road and plotting them on the building. .
Details of how you Planned & Executed the allotted work We transfer the road level on the existing permanent structure and then on the columns of the building. We execute the work with the help of water level tube. .
Details of the Construction Procedure / Activity / Technology learned today Taking levels with the help of the help of water level. .
Details of the Construction Materials learned today Types of PVC pies:- A-PVC C-PVC .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use Eco-friendly plywood which is made up of waste material from Sugar factory. .
Details of the Construction / Engineering Drawings observed today Sections of the building. .
Details of the Bye Laws referred today Bye-laws for the FSI calculations. .
Details of any Managerial Skill learned today Punctuality is the key to success. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs TOTAL COST=530.58Rs .
Result of RATE ANALYSIS ( Rs per Unit ) 530.5/cu.m
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.P.Bharamal. .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: Rohit_patil361@rediffmail.com
Subject: 13565-06

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 80 , near new palace, nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Patil Rohit Ashok
Exam No. 13565
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge Pile foundation - * to understand about pile foundation construction. * to understand about pile foundation layout as per drawing. * R.C.C. slab to floor on other side
Details of how you Planned & Executed the allotted work * first we observe the center of pile. * we saw how to construct pile. * requirement depth for pile.
Details of the Construction Procedure / Activity / Technology learned today * first we observe the position of pile from given plan. * workers set up the assembly of pile foundation. * four workers are required for this job. * after the pile then concreting has placed properly in to that pile.
Details of the Construction Materials learned today Steel rod rope tripod bulb cutter aggregate 20-25 mm sand- river sand cement- opc 43 grade water- bore water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today best high technique used for excavating of pile surface area.
Details of the Construction / Engineering Drawings observed today * pile foundation layout * reinforcement details for pile * slab drawing
Details of the Bye Laws referred today parking area/space- the maximum size of parking to be provided with respect to bylaws. motor vehicales- 2.5 x 5.5 m (min) scooter - 3.89 m (min) bicycle - 1.4 m2 (min)
Details of any Managerial Skill learned today * work out the quantities * prepare requirement of material * check the daily progress report * maintain the clean liness of the site
RATE ANALYSIS (Detailed Stepwise Calculations required) plastering (1:6) for 100 m2 area, thik-12mm volume of morter= 100x0.012 = 1.2 m3 add 30% for filling joints= 1.56m3 add 25% for morter in dry weight= 1.95m3 cement = (1.95/7)x1 = 7.7= 8 nos. sand = (1.95/7)x6 = 1.67 m3 SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 8 bags 250.00/- 2000.00/- b) sand 1.67 cum 850.00/- (per cum) 1420.00/- 2 Labourers a) head mason 2 no. 300.00/- 600.00/- b) male mazdur 4 no. 200.00/- 800.00/- c) female mazdur 2 no. 120.00/- 240.00/- d) bhisti 1 no. 120.00/- 240.00/- 3 Others _ TOTAL 5210.00/- 4 Tools and plant @ 1.5% ----------------------- 78.50/- on total 5 Water charges @ 1.0% ----------------------- 52.00/- on total TOTAL(A) 5340.50/- 6 Overhead and profit @ 15% on tOtal A ----------------------- 800.00/- -------------------------------------------------------------------------- TOTAL = 6140.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 6140.00/-
Todays BUZZ Word * structure permitted in recreational open spaces. * all the features permitted in open spaces. * area of fire escape stairways and fire excape passages. * area of the basement , used only for storage, a.c. plant, meter room, electric sub-station or parking. * watchman cabin of size 5.00 m2.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: mayur.sonavne61@gmail.com
Subject: 13570-06

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sonavne Mayur Madhukar
Exam No. 13570
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To take the levels of existing road and plotting them on the building. .
Details of how you Planned & Executed the allotted work We transfer the road level on the existing permanent structure and then on the columns of the building. We execute the work with the help of water level tube. .
Details of the Construction Procedure / Activity / Technology learned today Taking levels with the help of the help of water level. .
Details of the Construction Materials learned today Types of PVC pies:- A-PVC C-PVC .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use Eco-friendly plywood which is made up of waste material from Sugar factory. .
Details of the Construction / Engineering Drawings observed today Sections of the building. .
Details of the Bye Laws referred today Bye-laws for the FSI calculations. .
Details of any Managerial Skill learned today Punctuality is the key to success. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs TOTAL COST=530.58Rs .
Result of RATE ANALYSIS ( Rs per Unit ) 530.5/cu.m
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. P. Bharamal. .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: nitinpatil22.2010@rediffmail.com
Subject: 10879-06

Company Name S. S. Developers & Builders
Project Name & Site Address winter training,s,s.developers,tarabai park ,karandi mala
Students Name (Surname_First Name_Middle Name) Patil Nitin Dilip
Exam No. 10879
Working Day No. 06
Date (DD/MM/YYYY) 15/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1)observing the plaster work 2)observing the compound wall construction
Details of how you Planned & Executed the allotted work 1)at 9am we decided to go 4th floor ,& we saw the plastering process. 2)then we observed the construction of compound wall 3)after 2pm ,we calculated rate analysis of plaster
Details of the Construction Procedure / Activity / Technology learned today 1)we understood the technic of plaster 2)we understood the technics of septik tank construction
Details of the Construction Materials learned today 1)putte 2)cement block 3)types of tiles
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1)podiam garden 2)4000 sq.ft garden area 3)solar panel
Details of the Construction / Engineering Drawings observed today 1)working drawing 2)parking drwaing
Details of the Bye Laws referred today 1)puja room-1.5 sq,m 2kitchen-9.5sq.m
Details of any Managerial Skill learned today 1)we learnd how the behaviour with the labour 2)we learned talking manners with client
RATE ANALYSIS (Detailed Stepwise Calculations required) for 1 brass-(1:18) cement-1bag-260 Rs 18 x 15=270 Rs 22per sq.ft 22 x 10=220 Rs 1 brass=750 Rs per sqare in charge=80.72 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 80.72 Rs
Todays BUZZ Word 1)open to sky-(16\'x14.6\') 2)duct-(110\'x5\'8\") 3)balcony-(10\'10\"x6\') 4)lobby-(12\'x14\'6\") 5)lift-(5\'6\"x6\'6\") 6)terrase-(10\'4\"x 5\'2\")
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan chareple-9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-06

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 80 , near new palace, nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Mohare Vishal Bhalchandra
Exam No. 13564
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge Pile foundation - * to understand about pile foundation construction. * to understand about pile foundation layout as per drawing. * R.C.C. slab to floor on other side
Details of how you Planned & Executed the allotted work * first we observe the center of pile. * we saw how to construct pile. * requirement depth for pile.
Details of the Construction Procedure / Activity / Technology learned today * first we observe the position of pile from given plan. * workers set up the assembly of pile foundation. * four workers are required for this job. * after the pile then concreting has placed properly in to that pile.
Details of the Construction Materials learned today Steel rod rope tripod bulb cutter aggregate 20-25 mm sand- river sand cement- opc 43 grade water- bore water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today best high technique used for excavating of pile surface area.
Details of the Construction / Engineering Drawings observed today * pile foundation layout * reinforcement details for pile * slab drawing
Details of the Bye Laws referred today parking area/space- the maximum size of parking to be provided with respect to bylaws. motor vehicales- 2.5 x 5.5 m (min) scooter - 3.89 m (min) bicycle - 1.4 m2 (min)
Details of any Managerial Skill learned today * work out the quantities * prepare requirement of material * check the daily progress report * maintain the clean liness of the site
RATE ANALYSIS (Detailed Stepwise Calculations required) plastering (1:6) for 100 m2 area, thik-12mm volume of morter= 100x0.012 = 1.2 m3 add 30% for filling joints= 1.56m3 add 25% for morter in dry weight= 1.95m3 cement = (1.95/7)x1 = 7.7= 8 nos. sand = (1.95/7)x6 = 1.67 m3 SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 8 bags 250.00/- 2000.00/- b) sand 1.67 cum 850.00/- (per cum) 1420.00/- 2 Labourers a) head mason 2 no. 300.00/- 600.00/- b) male mazdur 4 no. 200.00/- 800.00/- c) female mazdur 2 no. 120.00/- 240.00/- d) bhisti 1 no. 120.00/- 240.00/- 3 Others _ TOTAL 5210.00/- 4 Tools and plant @ 1.5% ----------------------- 78.50/- on total 5 Water charges @ 1.0% ----------------------- 52.00/- on total TOTAL(A) 5340.50/- 6 Overhead and profit @ 15% on tOtal A ----------------------- 800.00/- -------------------------------------------------------------------------- TOTAL = 6140.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 6140.00/-
Todays BUZZ Word * structure permitted in recreational open spaces. * all the features permitted in open spaces. * area of fire escape stairways and fire excape passages. * area of the basement , used only for storage, a.c. plant, meter room, electric sub-station or parking. * watchman cabin of size 5.00 m2.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-06

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Swapnil Ashok
Exam No. 13529
Working Day No. 06
Date (DD/MM/YYYY) 14.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe casting of staircase.
Details of how you Planned & Executed the allotted work we were just told to observe the casting.so there was no planning required.
Details of the Construction Procedure / Activity / Technology learned today use of needle vibrator for columns and beams.
Details of the Construction Materials learned today needle vibrator.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today 1.floor drawings. 2.beam drawings.
Details of the Bye Laws referred today bye laws referred: 1.porch-if it is more than 1.2 m, it should be considered. 2.balcony-if it is more than 1.5 m,then it should be considered.
Details of any Managerial Skill learned today none.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 12 mm thick plaster(1:3) assume,1sq.m surface srea=1*(12/1000)m volume of mortar for 12 mm plaster=1*0.012=0.012 cu.m add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 cu.m add 25% for dry volume=0.0156*1.25=0.0195 cu.m a) cement-(0.0195/(1+3))=0.00487 cu.m0.005 cu.m no. of bags-(0.005/0.035)=0.142 0.15 bags=0.15*260=Rs.39 b) sand-0.005*3=0.015=5000*0.015=Rs.75 total cost of material=Rs.114. f) labour- mason-1 no.-Rs.250 Boy or woman-Rs.140 shuttering-Rs.30 Total-Rs.(114+390+30)= Rs.534 g) water-1.5%=534*(1.5/100)=Rs.8.01 contractor profit=total cost*profit(10% profit) =Rs.534*1.10 =Rs.53.4 total cost=534+8.01+53.4 =Rs.595.41
Result of RATE ANALYSIS ( Rs per Unit ) 595.41
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: suchitapatil5@yahoo.in
Subject: 10898-06

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.09 p.m.
Details of the Work Allotted to you today by the Site In-Charge Work allotted today: -To see the pile formation in the strata -To see the casting of plinth beam -to see the erection of the formwork for slab.
Details of how you Planned & Executed the allotted work Ist we observed & see the pile formation and take all details We see the casting of plinth beam Then we see & taking notes about erection of form work for slab
Details of the Construction Procedure / Activity / Technology learned today Procedure : Pile formation: 1) First dia. Is decided for formation of pile . 2) Pile core are placed on ground. 3) The pile formation which we saw was manual one. Casting of the plinth beam: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. Erection of forwork: 1) First level is taken with the help of level tube. 2) Then with the help of bamboo , wooden planks & marine ply & nails form work is prepared for slab.
Details of the Construction Materials learned today Steel : 6mm,12mm,16mm,20mm Concrete : M-20 Bamboo : For formwork Marine ply wood CPVC pipe APVC Pipe
Details of Environment Caring Technology / Methodology / Procedure / Product learned today CFL bulbs are used for saving electrical energy
Details of the Construction / Engineering Drawings observed today Detail drawing of slab & beam for formation of formwork
Details of the Bye Laws referred today L/B Ratio for every room is 1.2 to 1.5 which is according to the byelaws.
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor.
RATE ANALYSIS (Detailed Stepwise Calculations required) PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Quantity of mortar = 0.4cub.m (0.2 cub.m for 10sq.m) Qt. of cement = 0.4/4 = 0.1 cub.m No. of bags of cement = 0.1/0.035 = 2.85 = say 3no.of bags Qt. of sand = 3* 0.1 = 0.3 cub.m Particular Quantity/No. Rate Cost Material Cement 3 bags 255 765Rs/- Sand 0.3 cub.m 1644 493.2Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Total = 2748 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 3298Rs/- Rate per sq.m= 165 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 165 Rs/- per unit
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.per Unit ): 300.00 Rs per sq.m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-06

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.09 p.m.
Details of the Work Allotted to you today by the Site In-Charge Work allotted today: -To see the pile formation in the strata -To see the casting of plinth beam -to see the erection of the formwork for slab.
Details of how you Planned & Executed the allotted work Ist we observed & see the pile formation and take all details We see the casting of plinth beam Then we see & taking notes about erection of form work for slab
Details of the Construction Procedure / Activity / Technology learned today Procedure : Pile formation: 1) First dia. Is decided for formation of pile . 2) Pile core are placed on ground. 3) The pile formation which we saw was manual one. Casting of the plinth beam: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. Erection of forwork: 1) First level is taken with the help of level tube. 2) Then with the help of bamboo , wooden planks & marine ply & nails form work is prepared for slab.
Details of the Construction Materials learned today Steel : 6mm,12mm,16mm,20mm Concrete : M-20 Bamboo : For formwork Marine ply wood CPVC pipe APVC Pipe
Details of Environment Caring Technology / Methodology / Procedure / Product learned today CFL bulbs are used for saving electrical energy
Details of the Construction / Engineering Drawings observed today Detail drawing of slab & beam for formation of formwork
Details of the Bye Laws referred today L/B Ratio for every room is 1.2 to 1.5 which is according to the byelaws.
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor.
RATE ANALYSIS (Detailed Stepwise Calculations required) PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Quantity of mortar = 0.4cub.m (0.2 cub.m for 10sq.m) Qt. of cement = 0.4/4 = 0.1 cub.m No. of bags of cement = 0.1/0.035 = 2.85 = say 3no.of bags Qt. of sand = 3* 0.1 = 0.3 cub.m Particular Quantity/No. Rate Cost Material Cement 3 bags 255 765Rs/- Sand 0.3 cub.m 1644 493.2Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Total = 2748 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 3298Rs/- Rate per sq.m= 165 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 165 Rs/- per unit
Todays BUZZ Word
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? Yes
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: suchitapatil5@yahoo.in
Subject: 10898-06

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.09 p.m.
Details of the Work Allotted to you today by the Site In-Charge Work allotted today: -To see the pile formation in the strata -To see the casting of plinth beam -to see the erection of the formwork for slab.
Details of how you Planned & Executed the allotted work Ist we observed & see the pile formation and take all details We see the casting of plinth beam Then we see & taking notes about erection of form work for slab
Details of the Construction Procedure / Activity / Technology learned today Procedure : Pile formation: 1) First dia. Is decided for formation of pile . 2) Pile core are placed on ground. 3) The pile formation which we saw was manual one. Casting of the plinth beam: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. Erection of forwork: 1) First level is taken with the help of level tube. 2) Then with the help of bamboo , wooden planks & marine ply & nails form work is prepared for slab.
Details of the Construction Materials learned today Steel : 6mm,12mm,16mm,20mm Concrete : M-20 Bamboo : For formwork Marine ply wood CPVC pipe APVC Pipe
Details of Environment Caring Technology / Methodology / Procedure / Product learned today CFL bulbs are used for saving electrical energy
Details of the Construction / Engineering Drawings observed today Detail drawing of slab & beam for formation of formwork
Details of the Bye Laws referred today L/B Ratio for every room is 1.2 to 1.5 which is according to the byelaws.
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor.
RATE ANALYSIS (Detailed Stepwise Calculations required) PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Quantity of mortar = 0.4cub.m (0.2 cub.m for 10sq.m) Qt. of cement = 0.4/4 = 0.1 cub.m No. of bags of cement = 0.1/0.035 = 2.85 = say 3no.of bags Qt. of sand = 3* 0.1 = 0.3 cub.m Particular Quantity/No. Rate Cost Material Cement 3 bags 255 765Rs/- Sand 0.3 cub.m 1644 493.2Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Total = 2748 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 3298Rs/- Rate per sq.m= 165 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 165 Rs/- per unit
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.per Unit ): 300.00 Rs per sq.m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: sawantganesh52@gmail.com
Subject: 13567-06

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To take the levels of existing road and plotting them on the building. .
Details of how you Planned & Executed the allotted work We transfer the road level on the existing permanent structure and then on the columns of the building. We execute the work with the help of water level tube. .
Details of the Construction Procedure / Activity / Technology learned today Taking levels with the help of the help of water level. .
Details of the Construction Materials learned today Types of PVC pies:- A-PVC C-PVC .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use Eco-friendly plywood which is made up of waste material from Sugar factory. .
Details of the Construction / Engineering Drawings observed today Sections of the building. .
Details of the Bye Laws referred today Bye-laws for the FSI calculations. .
Details of any Managerial Skill learned today Punctuality is the key to success. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs TOTAL COST=530.58Rs .
Result of RATE ANALYSIS ( Rs per Unit ) 530.5/cu.m
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. P. Bharamal. .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-06

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Nilam Jaywant
Exam No. 13528
Working Day No. 06
Date (DD/MM/YYYY) 14.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe casting of staircase.
Details of how you Planned & Executed the allotted work we were just told to observe the casting.so there was no planning required.
Details of the Construction Procedure / Activity / Technology learned today use of needle vibrator for columns and beams.
Details of the Construction Materials learned today needle vibrator.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today 1.floor drawings. 2.beam drawings.
Details of the Bye Laws referred today bye laws referred: 1.porch-if it is more than 1.2 m, it should be considered. 2.balcony-if it is more than 1.5 m,then it should be considered.
Details of any Managerial Skill learned today none.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 12 mm thick plaster(1:3) assume,1sq.m surface srea=1*(12/1000)m volume of mortar for 12 mm plaster=1*0.012=0.012 cu.m add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 cu.m add 25% for dry volume=0.0156*1.25=0.0195 cu.m a) cement-(0.0195/(1+3))=0.00487 cu.m0.005 cu.m no. of bags-(0.005/0.035)=0.142 0.15 bags=0.15*260=Rs.39 b) sand-0.005*3=0.015=5000*0.015=Rs.75 total cost of material=Rs.114. f) labour- mason-1 no.-Rs.250 Boy or woman-Rs.140 shuttering-Rs.30 Total-Rs.(114+390+30)= Rs.534 g) water-1.5%=534*(1.5/100)=Rs.8.01 contractor profit=total cost*profit(10% profit) =Rs.534*1.10 =Rs.53.4 total cost=534+8.01+53.4 =Rs.595.41
Result of RATE ANALYSIS ( Rs per Unit ) 595.41
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-06

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.09 p.m.
Details of the Work Allotted to you today by the Site In-Charge Work allotted today: -To see the pile formation in the strata -To see the casting of plinth beam -to see the erection of the formwork for slab.
Details of how you Planned & Executed the allotted work Ist we observed & see the pile formation and take all details We see the casting of plinth beam Then we see & taking notes about erection of form work for slab
Details of the Construction Procedure / Activity / Technology learned today Procedure : Pile formation: 1) First dia. Is decided for formation of pile . 2) Pile core are placed on ground. 3) The pile formation which we saw was manual one. Casting of the plinth beam: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. Erection of forwork: 1) First level is taken with the help of level tube. 2) Then with the help of bamboo , wooden planks & marine ply & nails form work is prepared for slab.
Details of the Construction Materials learned today Steel : 6mm,12mm,16mm,20mm Concrete : M-20 Bamboo : For formwork Marine ply wood CPVC pipe APVC Pipe
Details of Environment Caring Technology / Methodology / Procedure / Product learned today CFL bulbs are used for saving electrical energy
Details of the Construction / Engineering Drawings observed today Detail drawing of slab & beam for formation of formwork
Details of the Bye Laws referred today L/B Ratio for every room is 1.2 to 1.5 which is according to the byelaws.
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor.
RATE ANALYSIS (Detailed Stepwise Calculations required) PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Quantity of mortar = 0.4cub.m (0.2 cub.m for 10sq.m) Qt. of cement = 0.4/4 = 0.1 cub.m No. of bags of cement = 0.1/0.035 = 2.85 = say 3no.of bags Qt. of sand = 3* 0.1 = 0.3 cub.m Particular Quantity/No. Rate Cost Material Cement 3 bags 255 765Rs/- Sand 0.3 cub.m 1644 493.2Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Total = 2748 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 3298Rs/- Rate per sq.m= 165 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 165 Rs/- per unit
Todays BUZZ Word
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? Yes
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-06

Company Name P. B. Builders & Developers
Project Name & Site Address Pritam Residancy,Samrat nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Shinde Sagar Arvind
Exam No. 13568
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To take the levels of existing road and plotting them on the building. .
Details of how you Planned & Executed the allotted work We transfer the road level on the existing permanent structure and then on the columns of the building. We execute the work with the help of water level tube. .
Details of the Construction Procedure / Activity / Technology learned today Taking levels with the help of the help of water level. .
Details of the Construction Materials learned today Types of PVC pies:- A-PVC C-PVC .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use Eco-friendly plywood which is made up of waste material from Sugar factory. .
Details of the Construction / Engineering Drawings observed today Sections of the building. .
Details of the Bye Laws referred today Bye-laws for the FSI calculations. .
Details of any Managerial Skill learned today Punctuality is the key to success. .
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs TOTAL COST=530.58Rs .
Result of RATE ANALYSIS ( Rs per Unit ) 530.5/cu.m
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Bharamal
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-06

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 06
Date (DD/MM/YYYY) 14.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe casting of staircase.
Details of how you Planned & Executed the allotted work we were just told to observe the casting.so there was no planning required.
Details of the Construction Procedure / Activity / Technology learned today use of needle vibrator for columns and beams.
Details of the Construction Materials learned today needle vibrator.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today 1.floor drawings. 2.beam drawings.
Details of the Bye Laws referred today bye laws referred: 1.porch-if it is more than 1.2 m, it should be considered. 2.balcony-if it is more than 1.5 m,then it should be considered.
Details of any Managerial Skill learned today none.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 12 mm thick plaster(1:3) assume,1sq.m surface srea=1*(12/1000)m volume of mortar for 12 mm plaster=1*0.012=0.012 cu.m add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 cu.m add 25% for dry volume=0.0156*1.25=0.0195 cu.m a) cement-(0.0195/(1+3))=0.00487 cu.m0.005 cu.m no. of bags-(0.005/0.035)=0.142 0.15 bags=0.15*260=Rs.39 b) sand-0.005*3=0.015=5000*0.015=Rs.75 total cost of material=Rs.114. f) labour- mason-1 no.-Rs.250 Boy or woman-Rs.140 shuttering-Rs.30 Total-Rs.(114+390+30)= Rs.534 g) water-1.5%=534*(1.5/100)=Rs.8.01 contractor profit=total cost*profit(10% profit) =Rs.534*1.10 =Rs.53.4 total cost=534+8.01+53.4 =Rs.595.41
Result of RATE ANALYSIS ( Rs per Unit ) 595.41
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-06

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Dsouza Agnel Santan
Exam No. 13524
Working Day No. 06
Date (DD/MM/YYYY) 14.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe casting of staircase.
Details of how you Planned & Executed the allotted work we were just told to observe the casting.so there was no planning required.
Details of the Construction Procedure / Activity / Technology learned today use of needle vibrator for columns and beams.
Details of the Construction Materials learned today needle vibrator.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today 1.floor drawings. 2.beam drawings.
Details of the Bye Laws referred today bye laws referred: 1.porch-if it is more than 1.2 m, it should be considered. 2.balcony-if it is more than 1.5 m,then it should be considered.
Details of any Managerial Skill learned today none.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 12 mm thick plaster(1:3) assume,1sq.m surface srea=1*(12/1000)m volume of mortar for 12 mm plaster=1*0.012=0.012 cu.m add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 cu.m add 25% for dry volume=0.0156*1.25=0.0195 cu.m a) cement-(0.0195/(1+3))=0.00487 cu.m0.005 cu.m no. of bags-(0.005/0.035)=0.142 0.15 bags=0.15*260=Rs.39 b) sand-0.005*3=0.015=5000*0.015=Rs.75 total cost of material=Rs.114. f) labour- mason-1 no.-Rs.250 Boy or woman-Rs.140 shuttering-Rs.30 Total-Rs.(114+390+30)= Rs.534 g) water-1.5%=534*(1.5/100)=Rs.8.01 contractor profit=total cost*profit(10% profit) =Rs.534*1.10 =Rs.53.4 total cost=534+8.01+53.4 =Rs.595.41
Result of RATE ANALYSIS ( Rs per Unit ) 595.41
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-06

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.09 p.m.
Details of the Work Allotted to you today by the Site In-Charge Work allotted today: -To see the pile formation in the strata -To see the casting of plinth beam -to see the erection of the formwork for slab.
Details of how you Planned & Executed the allotted work Ist we observed & see the pile formation and take all details We see the casting of plinth beam Then we see & taking notes about erection of form work for slab
Details of the Construction Procedure / Activity / Technology learned today Procedure : Pile formation: 1) First dia. Is decided for formation of pile . 2) Pile core are placed on ground. 3) The pile formation which we saw was manual one. Casting of the plinth beam: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. Erection of forwork: 1) First level is taken with the help of level tube. 2) Then with the help of bamboo , wooden planks & marine ply & nails form work is prepared for slab.
Details of the Construction Materials learned today Steel : 6mm,12mm,16mm,20mm Concrete : M-20 Bamboo : For formwork Marine ply wood CPVC pipe APVC Pipe
Details of Environment Caring Technology / Methodology / Procedure / Product learned today CFL bulbs are used for saving electrical energy
Details of the Construction / Engineering Drawings observed today Detail drawing of slab & beam for formation of formwork
Details of the Bye Laws referred today L/B Ratio for every room is 1.2 to 1.5 which is according to the byelaws.
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor.
RATE ANALYSIS (Detailed Stepwise Calculations required) PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Quantity of mortar = 0.4cub.m (0.2 cub.m for 10sq.m) Qt. of cement = 0.4/4 = 0.1 cub.m No. of bags of cement = 0.1/0.035 = 2.85 = say 3no.of bags Qt. of sand = 3* 0.1 = 0.3 cub.m Particular Quantity/No. Rate Cost Material Cement 3 bags 255 765Rs/- Sand 0.3 cub.m 1644 493.2Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Total = 2748 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 3298Rs/- Rate per sq.m= 165 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 165 Rs/- per unit
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.per Unit ): 300.00 Rs per sq.m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-06

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 06
Date (DD/MM/YYYY) 14.12.2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe casting of staircase.
Details of how you Planned & Executed the allotted work we were just told to observe the casting.so there was no planning required.
Details of the Construction Procedure / Activity / Technology learned today use of needle vibrator for columns and beams.
Details of the Construction Materials learned today needle vibrator.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today 1.floor drawings. 2.beam drawings.
Details of the Bye Laws referred today bye laws referred: 1.porch-if it is more than 1.2 m, it should be considered. 2.balcony-if it is more than 1.5 m,then it should be considered.
Details of any Managerial Skill learned today none.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for plaster 12 mm thick plaster(1:3) assume,1sq.m surface srea=1*(12/1000)m volume of mortar for 12 mm plaster=1*0.012=0.012 cu.m add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 cu.m add 25% for dry volume=0.0156*1.25=0.0195 cu.m a) cement-(0.0195/(1+3))=0.00487 cu.m0.005 cu.m no. of bags-(0.005/0.035)=0.142 0.15 bags=0.15*260=Rs.39 b) sand-0.005*3=0.015=5000*0.015=Rs.75 total cost of material=Rs.114. f) labour- mason-1 no.-Rs.250 Boy or woman-Rs.140 shuttering-Rs.30 Total-Rs.(114+390+30)= Rs.534 g) water-1.5%=534*(1.5/100)=Rs.8.01 contractor profit=total cost*profit(10% profit) =Rs.534*1.10 =Rs.53.4 total cost=534+8.01+53.4 =Rs.595.41
Result of RATE ANALYSIS ( Rs per Unit ) 595.41
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob:9422046580
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-06

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.09 p.m.
Details of the Work Allotted to you today by the Site In-Charge Work allotted today: -To see the pile formation in the strata -To see the casting of plinth beam -to see the erection of the formwork for slab.
Details of how you Planned & Executed the allotted work Ist we observed & see the pile formation and take all details We see the casting of plinth beam Then we see & taking notes about erection of form work for slab
Details of the Construction Procedure / Activity / Technology learned today Procedure : Pile formation: 1) First dia. Is decided for formation of pile . 2) Pile core are placed on ground. 3) The pile formation which we saw was manual one. Casting of the plinth beam: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. Erection of forwork: 1) First level is taken with the help of level tube. 2) Then with the help of bamboo , wooden planks & marine ply & nails form work is prepared for slab.
Details of the Construction Materials learned today Steel : 6mm,12mm,16mm,20mm Concrete : M-20 Bamboo : For formwork Marine ply wood CPVC pipe APVC Pipe
Details of Environment Caring Technology / Methodology / Procedure / Product learned today CFL bulbs are used for saving electrical energy
Details of the Construction / Engineering Drawings observed today Detail drawing of slab & beam for formation of formwork
Details of the Bye Laws referred today L/B Ratio for every room is 1.2 to 1.5 which is according to the byelaws.
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor.
RATE ANALYSIS (Detailed Stepwise Calculations required) PLASTERING: Assume Quantity for plastering = 20sq.m Proportion 1:3 Quantity of mortar = 0.4cub.m (0.2 cub.m for 10sq.m) Qt. of cement = 0.4/4 = 0.1 cub.m No. of bags of cement = 0.1/0.035 = 2.85 = say 3no.of bags Qt. of sand = 3* 0.1 = 0.3 cub.m Particular Quantity/No. Rate Cost Material Cement 3 bags 255 765Rs/- Sand 0.3 cub.m 1644 493.2Rs/- Labour Mason 2 210 420 Rs/- mazdoor Male 3 160 480Rs/- Female 3 130 390Rs/- Bhisti 1 100 100Rs/- Lumpsump 100Rs/- Total = 2748 Rs/- Add 20% buildersprofit including sales tax, service tax, VAT ,all charges etc. 3298Rs/- Rate per sq.m= 165 Rs/-
Result of RATE ANALYSIS ( Rs per Unit ) 165 Rs/- per unit
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.per Unit ): 300.00 Rs per sq.m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-06

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudev
Exam No. 10891
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Pile foundation excavation plinth beam casting Erection of framework of slab .
Details of how you Planned & Executed the allotted work First we see pile foundation drawing & go on side also follow all instruction gave by site in-charge. also we see plinth beam drawing plan & planed conduct procedure of casting beam. .
Details of the Construction Procedure / Activity / Technology learned today IN pile foundation -: Hand pile driven for this foundation . first diameter of pile is selected (16\") for driving tool is circular in shape called CORE is put on earth surface & drvive in circular in direction by handle with the help of man. some rotetation is done core is filled with soil which is taken out on earth surface & taken out all soil filled in it then it agan placed in bore & same proceture is taken out until hard rock is obtained.also provide a bulb by desining condition.then concrete mix is put in this mold. IN PLINTH BEAM-: first steel are cutting in beam size & prepared a net of beam also framework is done in proper size & steel are placed in mold & m20 concrete are filled in this mold also vibrator are put in mold for compaction .
Details of the Construction Materials learned today concrete(for pile ),bambu A PVC pipe material,C PVC pipe marine ply steel . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today C.F.L tubes re provided in all room to save electrical energy by 30/. .
Details of the Construction / Engineering Drawings observed today slab steel drawing,plinth beam drawing. .
Details of the Bye Laws referred today length breadth ratio are maintain in each room according to by laws .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor.
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs TOTAL COST=530.58Rs
Result of RATE ANALYSIS ( Rs per Unit ) Rs 530.58
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil. 9890997979. . .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-06

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 06
Date (DD/MM/YYYY) 14-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4.15PM
Details of the Work Allotted to you today by the Site In-Charge Pile foundation excavation plinth beam casting Erection of framework of slab .
Details of how you Planned & Executed the allotted work First we see pile foundation drawing & go on side also fqllow all instruction gave by site incharge. also we see plint beam drawing plan & planed conduct procedure of casting beam. .
Details of the Construction Procedure / Activity / Technology learned today IN pile foundation -: Hand pile driven for this foundation . first diameter of pile is selected (16\") for driving tool is circular in shape called CORE is put on earth surface & drvive in circular in direction by handle with the help of man. some rotetation is done core is filled with soil which is taken out on earth surface & taken out all soil filled in it then it agan placed in bore & same proceture is taken out until hard rock is obtained.also provide a bulb by desining condition.then concret mix is put in this mould. IN PLINTH BEAM-: first steel are cutting in beam size & prepared a net of beam also framework is done in proper size & steel are placed in mould & m20 concret are filled in this mould also vibretor are put in mould for compaction .
Details of the Construction Materials learned today concrete(for pile ),bambu A PVC pipe material,C PVC pipe marine ply steel . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today C.F.L tubes re provided in all room to save electrical energy by 30/. .
Details of the Construction / Engineering Drawings observed today slab steel drawing,plinth beam drawing. .
Details of the Bye Laws referred today length breadth ratio are maintain in each room according to by laws .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor.
RATE ANALYSIS (Detailed Stepwise Calculations required) 12 mm thick plaster (1:3) proportion Assume 1*12/1000(m) volume of mortar for 12 mm plaster=1*0.012=0.012m3 add 30% for filling up uneven surface=(0.012*30/100)+0.012=0.0156 Add 25% of dry volume =0.156+(0.1556*25/100)=0.0195 cement=0.0195/1+3=0.00487m3 no of bag=0.005/0.035=0.142=0.15bag cost=0.015*260=39Rs Sand=0.005*3=0.015m3 cost=0.015*1125=16.87 material cost=39.0+16.875=55.87Rs labor=mason1=250Rs labor=140Rs total=390Rs Scaffolding=30Rs water1.5%=1.5/100*475.87=7.13Rs TOTAL COST=530.58Rs
Result of RATE ANALYSIS ( Rs per Unit ) Rs 530.58
Todays BUZZ Word 1)Area covered by stair-case of width 1.2 m lift room above the the top most story lift well stair well & stair case chimney ,elevated tank of permissible dimension in in bldg .permissible only resid.& commercial zone. 2)Area of unclosed but covered paring place. 3)Area of sanitary block consisting of bathroom and water closet at each floor level of prescribed dimensions for the use of domestic servents on the premises. 4)Refuge area 5)Area covered by:- Loft Meter room Air-conditioning plant room Porches Canopies Service floor of height not exceeding 1.5m with the special permission Video room of size 5sq.m. Watchmen room of size 5sq.m 6)Area of balconies as per regulation 7)Entrance foyer:- The area between ext. face up to staircase/lift The width of fire shall not be more than lift and stair width
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil. 9890997979. . .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: nikitashinde15@gmail.com
Subject: 13547-06

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) shinde nikita eknath
Exam No. 13547
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:10pm
Details of the Work Allotted to you today by the Site In-Charge 1.observation of construction of PCC 2.reinforcement in footing and column
Details of how you Planned & Executed the allotted work oservation of field work
Details of the Construction Procedure / Activity / Technology learned today 1.line out of column 2.centring opf column
Details of the Construction Materials learned today 1.portland pozzolona cement fly ash based
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today 1.foundation plans for bunglow no.9
Details of the Bye Laws referred today roof tanks and their supports , ventilating lift room and similar service equipment , roof structures other thn. barsatis, stair cover and parapet wall not exeeding 1m in height
Details of any Managerial Skill learned today 1.good cummunication with us and customer 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Internal plaster 1.sand -15 x 17 Rs =255Rs 2.cement -175 x 250 RS =438Rs 3. labour =400Rs 4.scafolding -1 x 50 Rs =50Rs total = 1143Rs with cp 20% =1371.6RS per sq.ft. total =15240Rs per sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 15240Rs
Todays BUZZ Word Floor area to be excluded 1.area coverd by stair case of width 1.2m or more ,lift rooms above the top most storay 2.area of fire escape stir ways and passage 3.area of basement 4.area covered by lofts,meter rooms,porches 5.service floor of height not exeeding 1.5m 6.video room of size 5 sq.mt. 7.watch mans cabin of size 5 sq.mt 8.area of balcony 9.cupboards of tothe extend of 0.6x2.4 meters shall be permited in required open space
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph- 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: rajendrapawar54@gmail.com
Subject: 13542-06

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) pawar rajendra eknath
Exam No. 13542
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:10pm
Details of the Work Allotted to you today by the Site In-Charge 1.observation of construction of PCC 2.reinforcement in footing and column
Details of how you Planned & Executed the allotted work oservation of field work
Details of the Construction Procedure / Activity / Technology learned today 1.line out of column 2.centring opf column
Details of the Construction Materials learned today 1.portland pozzolona cement fly ash based
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today 1.foundation plans for bunglow no.9
Details of the Bye Laws referred today roof tanks and their supports , ventilating lift room and similar service equipment , roof structures other thn. barsatis, stair cover and parapet wall not exeeding 1m in height
Details of any Managerial Skill learned today 1.good cummunication with us and customer 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Internal plaster 1.sand -15 x 17 Rs =255Rs 2.cement -175 x 250 RS =438Rs 3. labour =400Rs 4.scafolding -1 x 50 Rs =50Rs total = 1143Rs with cp 20% =1371.6RS per sq.ft. total =15240Rs per sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 15240Rs
Todays BUZZ Word Floor area to be excluded 1.area coverd by stair case of width 1.2m or more ,lift rooms above the top most storay 2.area of fire escape stir ways and passage 3.area of basement 4.area covered by lofts,meter rooms,porches 5.service floor of height not exeeding 1.5m 6.video room of size 5 sq.mt. 7.watch mans cabin of size 5 sq.mt 8.area of balcony 9.cupboards of tothe extend of 0.6x2.4 meters shall be permited in required open space
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph- 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-06

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) patil sangram madhukar
Exam No. 13540
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:10pm
Details of the Work Allotted to you today by the Site In-Charge 1.observation of construction of PCC 2.reinforcement in footing and column
Details of how you Planned & Executed the allotted work oservation of field work
Details of the Construction Procedure / Activity / Technology learned today 1.line out of column 2.centring opf column
Details of the Construction Materials learned today 1.portland pozzolona cement fly ash based
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today 1.foundation plans for bunglow no.9
Details of the Bye Laws referred today roof tanks and their supports , ventilating lift room and similar service equipment , roof structures other thn. barsatis, stair cover and parapet wall not exeeding 1m in height
Details of any Managerial Skill learned today 1.good cummunication with us and customer 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Internal plaster 1.sand -15 x 17 Rs =255Rs 2.cement -175 x 250 RS =438Rs 3. labour =400Rs 4.scafolding -1 x 50 Rs =50Rs total = 1143Rs with cp 20% =1371.6RS per sq.ft. total =15240Rs per sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 15240Rs
Todays BUZZ Word Floor area to be excluded 1.area coverd by stair case of width 1.2m or more ,lift rooms above the top most storay 2.area of fire escape stir ways and passage 3.area of basement 4.area covered by lofts,meter rooms,porches 5.service floor of height not exeeding 1.5m 6.video room of size 5 sq.mt. 7.watch mans cabin of size 5 sq.mt 8.area of balcony 9.cupboards of tothe extend of 0.6x2.4 meters shall be permited in required open space
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph- 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-06

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) patil sachin dhanaji
Exam No. 13539
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:10pm
Details of the Work Allotted to you today by the Site In-Charge 1.observation of construction of PCC 2.reinforcement in footing and column
Details of how you Planned & Executed the allotted work oservation of field work
Details of the Construction Procedure / Activity / Technology learned today 1.line out of column 2.centring opf column
Details of the Construction Materials learned today 1.portland pozzolona cement fly ash based
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today 1.foundation plans for bunglow no.9
Details of the Bye Laws referred today roof tanks and their supports , ventilating lift room and similar service equipment , roof structures other thn. barsatis, stair cover and parapet wall not exeeding 1m in height
Details of any Managerial Skill learned today 1.good cummunication with us and customer 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Internal plaster 1.sand -15 x 17 Rs =255Rs 2.cement -175 x 250 RS =438Rs 3. labour =400Rs 4.scafolding -1 x 50 Rs =50Rs total = 1143Rs with cp 20% =1371.6RS per sq.ft. total =15240Rs per sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 15240Rs
Todays BUZZ Word Floor area to be excluded 1.area coverd by stair case of width 1.2m or more ,lift rooms above the top most storay 2.area of fire escape stir ways and passage 3.area of basement 4.area covered by lofts,meter rooms,porches 5.service floor of height not exeeding 1.5m 6.video room of size 5 sq.mt. 7.watch mans cabin of size 5 sq.mt 8.area of balcony 9.cupboards of tothe extend of 0.6x2.4 meters shall be permited in required open space
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph- 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: vishwajit.p09@gmail.com
Subject: 13543-06

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) paymal vishwajit shamarao
Exam No. 13543
Working Day No. 06
Date (DD/MM/YYYY) 14/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:10pm
Details of the Work Allotted to you today by the Site In-Charge 1.observation of construction of PCC 2.reinforcement in footing and column
Details of how you Planned & Executed the allotted work oservation of field work
Details of the Construction Procedure / Activity / Technology learned today 1.line out of column 2.centring opf column
Details of the Construction Materials learned today 1.portland pozzolona cement fly ash based
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today 1.foundation plans for bunglow no.9
Details of the Bye Laws referred today roof tanks and their supports , ventilating lift room and similar service equipment , roof structures other thn. barsatis, stair cover and parapet wall not exeeding 1m in height
Details of any Managerial Skill learned today 1.good cummunication with us and customer 2.command on labour
RATE ANALYSIS (Detailed Stepwise Calculations required) Internal plaster 1.sand -15 x 17 Rs =255Rs 2.cement -175 x 250 RS =438Rs 3. labour =400Rs 4.scafolding -1 x 50 Rs =50Rs total = 1143Rs with cp 20% =1371.6RS per sq.ft. total =15240Rs per sq.mt.
Result of RATE ANALYSIS ( Rs per Unit ) 15240Rs
Todays BUZZ Word Floor area to be excluded 1.area coverd by stair case of width 1.2m or more ,lift rooms above the top most storay 2.area of fire escape stir ways and passage 3.area of basement 4.area covered by lofts,meter rooms,porches 5.service floor of height not exeeding 1.5m 6.video room of size 5 sq.mt. 7.watch mans cabin of size 5 sq.mt 8.area of balcony 9.cupboards of tothe extend of 0.6x2.4 meters shall be permited in required open space
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph- 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: pinkrosee4u@yahoo.com
Subject: 10878-06

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) narnaware shikha haridas
Exam No. 10878
Working Day No. 06
Date (DD/MM/YYYY) 14/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge Plastring shuttering for architctural view external colouring for bunglows leakage of water tanks
Details of how you Planned & Executed the allotted work we planned how to see leakage and methods to control it we planned to make 4 inch hole sch that pipe is fitted to pour concrete an minimize the leakage by using chemical mixed with cement paste
Details of the Construction Procedure / Activity / Technology learned today Chemicals used for constructionpai pump usage in construction to get hardened quickly
Details of the Construction Materials learned today chemicals,paint colour
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today plumbing design
Details of the Bye Laws referred today floor area excludedd from fsi
Details of any Managerial Skill learned today how to check the leakage from watr tanks
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS for 20 mm thick plastering using sand=1*1*0.020=0.02m3 for getting 0.02 m3 sand we require double sand=0.04m3 rate of sand =0.04*1411=57rs cement =0.22bag=0.22*250=55rs material costs =55+57=112rs labour cost =5ft2*10.56=54rs total cost=112+54=165rs/1m2
Result of RATE ANALYSIS ( Rs per Unit ) 165rs/1m2
Todays BUZZ Word open spac stair casee stairways and fire escape packages paring areas area of sanatory blocks refuge areas lofts meter room air conditioning plant room porches canopyies watchman cabin area covered by service ducts pums electric substations area of sepraate letter blocks on ground floor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: prasadkolekkar83@rediffmail.com
Subject: 10876-06

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr. rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 06
Date (DD/MM/YYYY) 14/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge Plastring shuttering for architctural view external colouring for bunglows leakage of water tanks
Details of how you Planned & Executed the allotted work we planned how to see leakage and methods to control it we planned to make 4 inch hole sch that pipe is fitted to pour concrete an minimize the leakage by using chemical mixed with cement paste
Details of the Construction Procedure / Activity / Technology learned today Chemicals used for constructionpai pump usage in construction to get hardened quickly
Details of the Construction Materials learned today chemicals,paint colour
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today plumbing design
Details of the Bye Laws referred today floor area excludedd from fsi
Details of any Managerial Skill learned today how to check the leakage from watr tanks
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS for 20 mm thick plastering using sand=1*1*0.020=0.02m3 for getting 0.02 m3 sand we require double sand=0.04m3 rate of sand =0.04*1411=57rs cement =0.22bag=0.22*250=55rs material costs =55+57=112rs labour cost =5ft2*10.56=54rs total cost=112+54=165rs/1m2
Result of RATE ANALYSIS ( Rs per Unit ) 165rs/1m2
Todays BUZZ Word open spac stair casee stairways and fire escape packages paring areas area of sanatory blocks refuge areas lofts meter room air conditioning plant room porches canopyies watchman cabin area covered by service ducts pums electric substations area of sepraate letter blocks on ground floor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: viju128@gmail.com
Subject: 3638-06

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr. rajendra nagar kolhapr
Students Name (Surname_First Name_Middle Name) shinde vijay namdeo
Exam No. 3638
Working Day No. 06
Date (DD/MM/YYYY) 14/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge Plastring shuttering for architctural view external colouring for bunglows leakage of water tanks
Details of how you Planned & Executed the allotted work we planned how to see leakage and methods to control it we planned to make 4 inch hole sch that pipe is fitted to pour concrete an minimize the leakage by using chemical mixed with cement paste
Details of the Construction Procedure / Activity / Technology learned today Chemicals used for constructionpai pump usage in construction to get hardened quickly
Details of the Construction Materials learned today chemicals,paint colour
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today plumbing design
Details of the Bye Laws referred today floor area excludedd from fsi
Details of any Managerial Skill learned today how to check the leakage from watr tanks
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS for 20 mm thick plastering using sand=1*1*0.020=0.02m3 for getting 0.02 m3 sand we require double sand=0.04m3 rate of sand =0.04*1411=57rs cement =0.22bag=0.22*250=55rs material costs =55+57=112rs labour cost =5ft2*10.56=54rs total cost=112+54=165rs/1m2
Result of RATE ANALYSIS ( Rs per Unit ) 165rs/1m2
Todays BUZZ Word open spac stair casee stairways and fire escape packages paring areas area of sanatory blocks refuge areas lofts meter room air conditioning plant room porches canopyies watchman cabin area covered by service ducts pums electric substations area of sepraate letter blocks on ground floor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Camera, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883-06

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.rajenra nagar kolhapur
Students Name (Surname_First Name_Middle Name) saurabh arora
Exam No. 10883
Working Day No. 05
Date (DD/MM/YYYY) 14/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4PM
Details of the Work Allotted to you today by the Site In-Charge Plastring shuttering for architctural view external colouring for bunglows leakage of water tanks
Details of how you Planned & Executed the allotted work we planned how to see leakage and methods to control it we planned to make 4 inch hole sch that pipe is fitted to pour concrete an minimize the leakage by using chemical mixed with cement paste
Details of the Construction Procedure / Activity / Technology learned today Chemicals used for constructionpai pump usage in construction to get hardened quickly
Details of the Construction Materials learned today chemicals,paint colour
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today plumbing design
Details of the Bye Laws referred today floor area excludedd from fsi
Details of any Managerial Skill learned today how to check the leakage from watr tanks
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS for 20 mm thick plastering using sand=1*1*0.020=0.02m3 for getting 0.02 m3 sand we require double sand=0.04m3 rate of sand =0.04*1411=57rs cement =0.22bag=0.22*250=55rs material costs =55+57=112rs labour cost =5ft2*10.56=54rs total cost=112+54=165rs/1m2
Result of RATE ANALYSIS ( Rs per Unit ) 165rs/1m2
Todays BUZZ Word open spac stair casee stairways and fire escape packages paring areas area of sanatory blocks refuge areas lofts meter room air conditioning plant room porches canopyies watchman cabin area covered by service ducts pums electric substations area of sepraate letter blocks on ground floor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Bye Law Book, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13561-06

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Jadhav Sardar Swaroop J.
Exam No. 13561
Working Day No. 06
Date (DD/MM/YYYY) 14.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. LEVELLING ; To calculate reduced levels of footings as area is very large hence to check level of footings is same or not. 2. To observe casting of staircase.
Details of how you Planned & Executed the allotted work Levelling ; 1. First we had set instrument by levelling and centering it. 2. Then we measured height of instrument. 3. Then we had taken back sight and fore sight readings. 4. Then we had calculated reduced levels of points by H.I. method.
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today Crushed sand ; 1. This is important ingredient of concrete. 2. It acts as binding agent in concrete, it forms bulk of concrete with aggregate. 3. It also is used in mortar for fly ash brick masonry. 4. Crush sand is made by fine grounding of stones. 5. Rate of crushed sand is 2200.00Rs per brass. 6. Test results has prooved that crush sand gives more strength than normal sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment
Details of the Construction / Engineering Drawings observed today Center line plan, staircase drwaings,working drawings of plinth beam.
Details of the Bye Laws referred today Height of parapet wall 1.00m Max cantilever porch length 4.00m
Details of any Managerial Skill learned today To check the material supplied by supplyer to clarrify the mistakes if any. So as to keep supply continuosly and efficiently.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PLASTERING ; per sq.m Sand = 0.3 sq.m = 196.00 Rs. Cement = 11 KG = 60.75 Rs Labour cost = 35.00 Rs per sq.m TOTAL = 291.00 Rs + 2% WASTAGE = 300.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 300.00 Rs per sq.m
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-06

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Jade Madhavrao Anil
Exam No. 13560
Working Day No. 06
Date (DD/MM/YYYY) 14.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. LEVELLING ; To calculate reduced levels of footings as area is very large hence to check level of footings is same or not. 2. To observe casting of staircase.
Details of how you Planned & Executed the allotted work Levelling ; 1. First we had set instrument by levelling and centering it. 2. Then we measured height of instrument. 3. Then we had taken back sight and fore sight readings. 4. Then we had calculated reduced levels of points by H.I. method.
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today Crushed sand ; 1. This is important ingredient of concrete. 2. It acts as binding agent in concrete, it forms bulk of concrete with aggregate. 3. It also is used in mortar for fly ash brick masonry. 4. Crush sand is made by fine grounding of stones. 5. Rate of crushed sand is 2200.00Rs per brass. 6. Test results has prooved that crush sand gives more strength than normal sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment
Details of the Construction / Engineering Drawings observed today Center line plan, staircase drwaings,working drawings of plinth beam.
Details of the Bye Laws referred today Height of parapet wall 1.00m Max cantilever porch length 4.00m
Details of any Managerial Skill learned today To check the material supplied by supplyer to clarrify the mistakes if any. So as to keep supply continuosly and efficiently.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PLASTERING ; per sq.m Sand = 0.3 sq.m = 196.00 Rs. Cement = 11 KG = 60.75 Rs Labour cost = 35.00 Rs per sq.m TOTAL = 291.00 Rs + 2% WASTAGE = 300.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 300.00 Rs per sq.m
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-06

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) katral raju maruti
Exam No. 13562
Working Day No. 06
Date (DD/MM/YYYY) 14.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. LEVELLING ; To calculate reduced levels of footings as area is very large hence to check level of footings is same or not. 2. To observe casting of staircase.
Details of how you Planned & Executed the allotted work Levelling ; 1. First we had set instrument by levelling and centering it. 2. Then we measured height of instrument. 3. Then we had taken back sight and fore sight readings. 4. Then we had calculated reduced levels of points by H.I. method.
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today Crushed sand ; 1. This is important ingredient of concrete. 2. It acts as binding agent in concrete, it forms bulk of concrete with aggregate. 3. It also is used in mortar for fly ash brick masonry. 4. Crush sand is made by fine grounding of stones. 5. Rate of crushed sand is 2200.00Rs per brass. 6. Test results has prooved that crush sand gives more strength than normal sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment
Details of the Construction / Engineering Drawings observed today Center line plan, staircase drwaings,working drawings of plinth beam.
Details of the Bye Laws referred today Height of parapet wall 1.00m Max cantilever porch length 4.00m
Details of any Managerial Skill learned today To check the material supplied by supplyer to clarrify the mistakes if any. So as to keep supply continuosly and efficiently.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PLASTERING ; per sq.m Sand = 0.3 sq.m = 196.00 Rs. Cement = 11 KG = 60.75 Rs Labour cost = 35.00 Rs per sq.m TOTAL = 291.00 Rs + 2% WASTAGE = 300.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 300.00 Rs per sq.m
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-06

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) tirmare pradnya ashok
Exam No. 13572
Working Day No. 06
Date (DD/MM/YYYY) 14.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. LEVELLING ; To calculate reduced levels of footings as area is very large hence to check level of footings is same or not. 2. To observe casting of staircase.
Details of how you Planned & Executed the allotted work Levelling ; 1. First we had set instrument by levelling and centering it. 2. Then we measured height of instrument. 3. Then we had taken back sight and fore sight readings. 4. Then we had calculated reduced levels of points by H.I. method.
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today Crushed sand ; 1. This is important ingredient of concrete. 2. It acts as binding agent in concrete, it forms bulk of concrete with aggregate. 3. It also is used in mortar for fly ash brick masonry. 4. Crush sand is made by fine grounding of stones. 5. Rate of crushed sand is 2200.00Rs per brass. 6. Test results has prooved that crush sand gives more strength than normal sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment
Details of the Construction / Engineering Drawings observed today Center line plan, staircase drwaings,working drawings of plinth beam.
Details of the Bye Laws referred today Height of parapet wall 1.00m Max cantilever porch length 4.00m
Details of any Managerial Skill learned today To check the material supplied by supplyer to clarrify the mistakes if any. So as to keep supply continuosly and efficiently.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PLASTERING ; per sq.m Sand = 0.3 sq.m = 196.00 Rs. Cement = 11 KG = 60.75 Rs Labour cost = 35.00 Rs per sq.m TOTAL = 291.00 Rs + 2% WASTAGE = 300.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 300.00 Rs per sq.m
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/14/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558-06

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Chavan Shivprasad Prakash
Exam No. 13558
Working Day No. 06
Date (DD/MM/YYYY) 14.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. LEVELLING ; To calculate reduced levels of footings as area is very large hence to check level of footings is same or not. 2. To observe casting of staircase.
Details of how you Planned & Executed the allotted work Levelling ; 1. First we had set instrument by levelling and centering it. 2. Then we measured height of instrument. 3. Then we had taken back sight and fore sight readings. 4. Then we had calculated reduced levels of points by H.I. method.
Details of the Construction Procedure / Activity / Technology learned today Casting of steel staircase ; 1. First steel frame of staircase is made and checked. 2. Then placed and welded in its position as per plan. 3. Then it is checked by site in charge. 4. Then supporting beam and column is casted and concrete work is finished. 5. Then wooden planks are placed in frame of staircase and then it is finished,
Details of the Construction Materials learned today Crushed sand ; 1. This is important ingredient of concrete. 2. It acts as binding agent in concrete, it forms bulk of concrete with aggregate. 3. It also is used in mortar for fly ash brick masonry. 4. Crush sand is made by fine grounding of stones. 5. Rate of crushed sand is 2200.00Rs per brass. 6. Test results has prooved that crush sand gives more strength than normal sand.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of crushed sand is environmental freindly. As use of river sand is prohibited. Use of river sand gives bad impact on flow of river .sometimes flow of river also may changed. Use of crushed sand avoids abve harmfull effect on environment.
Details of the Construction / Engineering Drawings observed today Center line plan, staircase drwaings,working drawings of plinth beam.
Details of the Bye Laws referred today Height of parapet wall 1.00m Max cantilever porch length 4.00m
Details of any Managerial Skill learned today To check the material supplied by supplyer to clarrify the mistakes if any. So as to keep supply contineous and efficient.
RATE ANALYSIS (Detailed Stepwise Calculations required) INTERNAL PLASTERING ; per sq.m Sand = 0.3 sq.m = 196.00 Rs. Cement = 11 KG = 60.75 Rs Labour cost = 35.00 Rs per sq.m TOTAL = 291.00 Rs + 2% WASTAGE = 300.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 300.00 Rs per sq.m
Todays BUZZ Word Buildinng components that gets EXCLUDED in F.S.I. calculations ; 1. Structures permitted in recreational open spaces. 2. All the features permitted in open spaces. 3. Area covered by staircase of width of 1.2 m,or more. 4. Area of fire escape & fire escape passages. 5. Area of basement. 6. Area of enclosede but covered parking. 7. Area covered by lofts. 8. Area covered by poarches. 9. Area covered by meter rooms. 10. Area covered by canopies. 11. Watchmen`s cabin of size 5.0 sq.m. 12. Video room of size 5.0 sq.m. 13. Cupboards to the extent of 1.44 sq.m. 14. Area of covered passage of clear width noy more than 1.52 m. 15. Balconies may be permitted free of F.S.I. at each floor, excluding the ground & terrace floors, or an area not more than 10% of area of the floor from which such balconies projects.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Swapnil Raut. mob. no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-01

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates,mukta sainik vasahat, kolhapur.
Students Name (Surname_First Name_Middle Name) SHINDE SHRADDHA TUKARAM
Exam No. 10901
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time (HH:MM am/pm) 09;00
Site Leaving Time (HH:MM am/pm) 05:00
Details of the Work Allotted to you today by the Site In-Charge Marking positions for swimming pool. - Study of duplex ready flat.
Details of how you Planned & Executed the allotted work For making position for a swimming pool: We first bifercated our self into two groups One group took measurements and the others executed the marking points. For study duplex ready flat: We indivisually bifercated ourselves to study various components of flats like plumbing, electrification, furnitur
Details of the Construction Procedure / Activity / Technology learned today How to construct a brick bat coba? Materials used : 1:4, waterproofing materials-SBR The brick bat coba was done on concrete flooring for amphitheatre.
Details of the Construction Materials learned today Cement: 1.PPC 53grade (Fly Ash based \'Birla Shakti\') 2.Conventional Brick 3.Water Proofing Material-SBR Chemical 4.Concrete Blocks
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly Ash based Cement in PPC : This is an environmental caring as it helps in reduction of emmission of CO2 than traditional OPC.
Details of the Construction / Engineering Drawings observed today Swimming Floor Layout, Floor Plan Layout.
Details of the Bye Laws referred today Provision of FSI = 1. Parking Spaces: Two Wheeler/Four Wheeler - The space provided for parking was more than specified in Bye Laws Book.
Details of any Managerial Skill learned today Dividing & Alloting the work in groups of labours.
RATE ANALYSIS (Detailed Stepwise Calculations required) Quantity of concrete-30 cu.m cement Quantity -48.60 cu.m (163 bags) sand Quantity -194.4 cu.m Aggregate Quantity -388.8 cu.m Rate calculations cement- 275*148=40700/- sand- 50*194.4=9720/- Aggregate- 48*388.8=18662.4/- Labour= 40*28=1120/- total amount-70282.4/- rate for 1cu.m=2342.74/-
Result of RATE ANALYSIS ( Rs per Unit ) 2342.74/-
Todays BUZZ Word -Weigh batching must be done instead of volume batching -The mixing of Concrete & Mortor must be done on a water tight surface to reduce the wastage of materials.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR. MULE (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-05

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Hasabnis Ketaki Bhagwan
Exam No. 13527
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge 1. To see the curing of slab. 2. To see the column reinforcement for second floor. 3. To see the slab centering work for third floor.
Details of how you Planned & Executed the allotted work We saw the curing of slab that was casted two days back. The slab had attained sufficient firmness. For curing, ponds were made, and water was continously sprinkled on slab for 3-4 times a day.
Details of the Construction Procedure / Activity / Technology learned today We saw the laying of column reinforcement for second floor. The bars were reduced in size from 1200 mm to 80 mm. We saw the slab centering work going on for third floor. We also saw the construction of formwork for the next flight from second floor to third floor. We saw how the labourers check the level by water pipes by holding them at two points and see their levels, this is the new technique we learnt.
Details of the Construction Materials learned today Column reinforcement- Tor steel bars 20mm, stirrups. Formwork and other materials for staircase.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such Technology was adopted today.
Details of the Construction / Engineering Drawings observed today 1. Plan for centering work for third floor. 2. Plan for third floor.
Details of the Bye Laws referred today 1. According to bye-laws cantilever beams should be placed at L/2 distance. 2. According to bye-laws maximum length of cantilever beam is 4m. On site it is provided 2m. 3.According to bye laws, minimum head requirement for garage is 2.4m. On site it is provided 3.8m. 4.According to bye laws, maximum height of riser is 190 mm. On site it is provided 160 mm. 5.According to bye laws,minimum width of treads is 250 mm. On site it is provided 300 mm.
Details of any Managerial Skill learned today 1. The site incharge saw whether curing was done properly or not. 2. He saw the Slab centering work. 3. He suggested the labour to make changes wherever needed.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for \"Brick work\" Rate analysis for 6\" bricks. No. of bricks required for per sq.m- 50 Cost per brick= Rs.4. For 50 bricks cost= Rs.200. Proportion = 1:4 For 1 sq.m = 0.22 cement required. Cost of cement= Rs. 265. Total cement cost=265*0.22= Rs.58.30. Cost of sand= Rs.1060. Total cost of sand per sq.m= 1060*0.15= Rs.159. Total cost=200+58.30+159=Rs. 417. Labour cost= 20%= Rs.83.4. Total cost=417+83.4=Rs.500.4. With 10% profit=Rs.550.4 Total cost of brick work for 6\" bricks = Rs.550.4 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.550.4 per sq.m for 6\" bricks.
Todays BUZZ Word 1.Slab centering checked with architectural drawing. 1. For elevation. 2. For room dimension. 3. For electric points. 2. Slab centering checked completely. 1. For required beam depth/ slab thickness. 2. For required head rooms. 3. For other points. 3.Slab centering checked completely. 1. Level checked/ Line checked. 2. Column centering checked / modified. 3. Oiling to beams/ slab shuttering. 4. Centering for stair-case checked. 5. Changes for amenities if any checked. 6. Reinforcement checked for beams and slabs as per R.C.C drawings. 7. Proper cover for bottom /side checked for beams. 8. Proper number of chairs provided for slab. 9. Proper cover bottom/top checked for slab/fan hook checked. 10.Reduction of columns as per drawing done for above slab. 11.Hidden beams/Cantilever beams/inverted beams checked if any. 12.Pardi bars left for balconies etc. 13.Proper cover bottom side/checked for all. 14.Dowels (any required ) are left. 15.R.C.C work centering checked for with architectural drawings. 1. For elevation. 2. For cenetring plan. 3. For electrical points. 4. For required size of beam /footings/slabs etc. 5. For other points. 16.Reinforcement checked as per R.C.C drwaings. 1. For beams. 2. For columns. 3. For pardhi. 4. For waist slab. 5. For other items. 17.B.B masonry work checked with architectural drawing. 1. For elevation. 2. For room dimension. 3. For openings. 18.B.B. masonry checked. 1. For beam size. 2. For column size. 3. For door and window openings. 19.Is the floor clen before starting line out of masonry. 20.First layer checked with beam top/beam edge,offset,plumb and line. 21.Erection of door and window frame with necessary no. of holdfast. 22.Painting door and window frame with one coat of primer (Anti-Termite paint) 23.Alignment of door and window frames for plumb/bend/level. 24.Verticalitiy of walls and corners. 25.Thickness of joints.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO. 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-05

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) SHINDE SHRADDHA TUKARAM
Exam No. 10901
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00
Site Leaving Time (HH:MM am/pm) 05:30
Details of the Work Allotted to you today by the Site In-Charge 1. To Study various Tiling Floor with their Specifications. 2. To Study \"Preparation of Base for Flooring\". 3. To Study \"Laying of Tiles\".
Details of how you Planned & Executed the allotted work 1. We all together (5 members) in our group went to Flat No. 408, to study the various aspects required before & after Flooring work. 2. We observed various aspects such as \"Preparation of Base for Flooring in Kitchen Balcony\" & \"Laying of tiles in Master Bed Terrace\". ------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR VITRIFIED TILE FLOORING WORK\" # - Prepare Cement slurry in Ratio of 1.5 Bag : 100 Litre of water approximately. - Start Fixing Tiles from reference line & reference tiles diagonally. - Spread the Cement Slurry on Mortar Bed. - Match all the four corners of Tiles properly with the help of \'Wooden Mallet\'. - Fix the \'Mosic Tiles\' in particular sequence. - After completing the tiling work check the overall level - Clean the floor & do not allow anybody to enter the flat for minimum 24 hours. - Next day fill the \"Gap joints\" between tiles with cement slurry. - Cure it for 14 days minimum ---------------------------------------------------------------------------------- # \"Vitrified Tile Skirting\" # - With the help of \"Wooden Farma\", Skirting Tile was fixed, projecting only 8 mm from Wall Plaster. - Keep the skirting in one line. - Fix skirting at two corners & fix the line dori as a guide line for line of the in between skirting. - At columns positions Skirting should be sliced in vertical direction. - Ensure that skirting lines are perpendicular to the vitrified tile line
Details of the Construction Materials learned today 1. PCC - Ratio of 1:4:8 ( M-10 Grade Concrete ). 2. Anti Skid Tiles. - 16\" x 16\" ( Regency Brand ). 3. Vitrified Tiles. - 2\' x 2\' ( Commet Brand ). 4. White Cement Putty - Wall Shine ( Creamcem Brand).
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Product learned today: Not observed such Methodology today.
Details of the Construction / Engineering Drawings observed today 1. Steel Scaffolding Drawings for Lift & Duct for Plastering purpose. 2. Floor Plans.
Details of the Bye Laws referred today # Parking Bye-Laws # 1. Motar Vehicle - 2.5 m x 5.5 m. 2. Motor Cycle - 3 sq.m.
Details of any Managerial Skill learned today - How to convience a customer. - How to Bargain with the dealer.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR BRICKWORK\" # --------------------------------------------------- - Brick Size = 20 cm x 10 cm x 10 cm. - Cement Mortor = 1:6. - Volume of Brickwork = 10 cu.m. --------------------------------------------------- A) Materials: 1. Brick required for 10 cu.m = 5000 nos. 2. Mortor = 30% = 3 cu.m 3. Cement = 0.428 cu.m 4. No of Bags Of Cement = 12.23 = 13 bags (approximate) 5. Sand = 0.428 x 6 = 2.568 cu.m -------------------------------------------------------- B) Cost of Material: 1. Brick = 5000 x 4 = 20000/-. 2. Cement = 13 x 230 = 2990/-. 3. Sand = 2.568 x 850 = 2182.8/-. * TOTAL = 25172.8/- --------------------------------------------------------- C) Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 8 x 140 = 1120/- 4. Female Mazdoor = 10 x 1100 = 1100/- 5. Bhisti = 2 x 120 = 240/- 6. Scaffolding = 500/-(Lumpsum) 7. Tools & Plants = 300/-(Lumpsum) * TOTAL = 5210/- -------------------------------------------------------- D) TOTAL = B+C = 30382.8/- -------------------------------------------------------- E) Add 2% water charges = 607.656/- -------------------------------------------------------- F) Add 15% for contractors Profit = 4557.42/- -------------------------------------------------------- G) GRAND TOTAL = 35547.876/- -------------------------------------------------------- H) Rate Per cu.m = 3554.7876/- -------------------------------------------------------- Result of RATE ANALYSIS ( Rs per Unit ): Rs 3554.7876/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 3554.7876/-
Todays BUZZ Word \"Checklist For Tiling Work\" Description Of Work ---- (Yes/No) 1. Is all the materials checked? 2. Is there any defect in tiles / stones received? 3. Are the rooms cleaned before tiling? 4. Is the skirting gap sufficient? 5. Is the lime mortar fresh & properly mixxed in mixtures? 6. Are Thiyyas Taken before Machan work? 7. Is right angle set before starting tiling? 8. Are level lines are marked on the walls of flat? 9. Are tile joints filled with matching colour cement slurry? 10. Is the skirting Farma used before fixing skirting? 11. Are all the cut-pieces made with help of cutting machine? 12. Is there sufficient stock of 12 mm thick skirting for fixing near RCC column? 13. Are new polishing stones used for polishing? 14. Is proper Curing for three days done to the grouting coat? 15. Are all polishing coats properly executed? 16. Is oxalic acid in powder form used for acid form? 17. Is the balcony flooring given sufficient slope towards spout? 18. Is all G.I., P.V.C. conduiting completed before glazed tile fixing? 19. Is the tile taken on the opening side of the door fro WC floor? 20. Are the edges of kitchen otta & sill rounded? 21. Are the slopes of kitchen platform top & sink proper? 22. Is the WC / Bath floor slope in proper direction? 23. Is the oil paint applied to kitchen platform & sill? 24. Are umbra pattis fixed wherever required? 25. Is the cleaning properly done?
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay. (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-05

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) SHINDE SHRADDHA TUKARAM
Exam No. 10901
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00
Site Leaving Time (HH:MM am/pm) 05:30
Details of the Work Allotted to you today by the Site In-Charge 1. To Study various Tiling Floor with their Specifications. 2. To Study \"Preparation of Base for Flooring\". 3. To Study \"Laying of Tiles\".
Details of how you Planned & Executed the allotted work 1. We all together (5 members) in our group went to Flat No. 408, to study the various aspects required before & after Flooring work. 2. We observed various aspects such as \"Preparation of Base for Flooring in Kitchen Balcony\" & \"Laying of tiles in Master Bed Terrace\". ------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR VITRIFIED TILE FLOORING WORK\" # - Prepare Cement slurry in Ratio of 1.5 Bag : 100 Litre of water approximately. - Start Fixing Tiles from reference line & reference tiles diagonally. - Spread the Cement Slurry on Mortar Bed. - Match all the four corners of Tiles properly with the help of \'Wooden Mallet\'. - Fix the \'Mosic Tiles\' in particular sequence. - After completing the tiling work check the overall level - Clean the floor & do not allow anybody to enter the flat for minimum 24 hours. - Next day fill the \"Gap joints\" between tiles with cement slurry. - Cure it for 14 days minimum ---------------------------------------------------------------------------------- # \"Vitrified Tile Skirting\" # - With the help of \"Wooden Farma\", Skirting Tile was fixed, projecting only 8 mm from Wall Plaster. - Keep the skirting in one line. - Fix skirting at two corners & fix the line dori as a guide line for line of the in between skirting. - At columns positions Skirting should be sliced in vertical direction. - Ensure that skirting lines are perpendicular to the vitrified tile line
Details of the Construction Materials learned today 1. PCC - Ratio of 1:4:8 ( M-10 Grade Concrete ). 2. Anti Skid Tiles. - 16\" x 16\" ( Regency Brand ). 3. Vitrified Tiles. - 2\' x 2\' ( Commet Brand ). 4. White Cement Putty - Wall Shine ( Creamcem Brand).
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Product learned today: Not observed such Methodology today.
Details of the Construction / Engineering Drawings observed today 1. Steel Scaffolding Drawings for Lift & Duct for Plastering purpose. 2. Floor Plans.
Details of the Bye Laws referred today # Parking Bye-Laws # 1. Motar Vehicle - 2.5 m x 5.5 m. 2. Motor Cycle - 3 sq.m.
Details of any Managerial Skill learned today - How to convience a customer. - How to Bargain with the dealer.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR BRICKWORK\" # --------------------------------------------------- - Brick Size = 20 cm x 10 cm x 10 cm. - Cement Mortor = 1:6. - Volume of Brickwork = 10 cu.m. --------------------------------------------------- A) Materials: 1. Brick required for 10 cu.m = 5000 nos. 2. Mortor = 30% = 3 cu.m 3. Cement = 0.428 cu.m 4. No of Bags Of Cement = 12.23 = 13 bags (approximate) 5. Sand = 0.428 x 6 = 2.568 cu.m -------------------------------------------------------- B) Cost of Material: 1. Brick = 5000 x 4 = 20000/-. 2. Cement = 13 x 230 = 2990/-. 3. Sand = 2.568 x 850 = 2182.8/-. * TOTAL = 25172.8/- --------------------------------------------------------- C) Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 8 x 140 = 1120/- 4. Female Mazdoor = 10 x 1100 = 1100/- 5. Bhisti = 2 x 120 = 240/- 6. Scaffolding = 500/-(Lumpsum) 7. Tools & Plants = 300/-(Lumpsum) * TOTAL = 5210/- -------------------------------------------------------- D) TOTAL = B+C = 30382.8/- -------------------------------------------------------- E) Add 2% water charges = 607.656/- -------------------------------------------------------- F) Add 15% for contractors Profit = 4557.42/- -------------------------------------------------------- G) GRAND TOTAL = 35547.876/- -------------------------------------------------------- H) Rate Per cu.m = 3554.7876/- -------------------------------------------------------- Result of RATE ANALYSIS ( Rs per Unit ): Rs 3554.7876/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 3554.7876/-
Todays BUZZ Word \"Checklist For Tiling Work\" Description Of Work ---- (Yes/No) 1. Is all the materials checked? 2. Is there any defect in tiles / stones received? 3. Are the rooms cleaned before tiling? 4. Is the skirting gap sufficient? 5. Is the lime mortar fresh & properly mixxed in mixtures? 6. Are Thiyyas Taken before Machan work? 7. Is right angle set before starting tiling? 8. Are level lines are marked on the walls of flat? 9. Are tile joints filled with matching colour cement slurry? 10. Is the skirting Farma used before fixing skirting? 11. Are all the cut-pieces made with help of cutting machine? 12. Is there sufficient stock of 12 mm thick skirting for fixing near RCC column? 13. Are new polishing stones used for polishing? 14. Is proper Curing for three days done to the grouting coat? 15. Are all polishing coats properly executed? 16. Is oxalic acid in powder form used for acid form? 17. Is the balcony flooring given sufficient slope towards spout? 18. Is all G.I., P.V.C. conduiting completed before glazed tile fixing? 19. Is the tile taken on the opening side of the door fro WC floor? 20. Are the edges of kitchen otta & sill rounded? 21. Are the slopes of kitchen platform top & sink proper? 22. Is the WC / Bath floor slope in proper direction? 23. Is the oil paint applied to kitchen platform & sill? 24. Are umbra pattis fixed wherever required? 25. Is the cleaning properly done?
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay. (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-05

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) JAGADALE ASHVANI RAMRAO
Exam No. 13530
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today none
Details of the Construction Materials learned today PLUMBING DRAWINGS.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS/CU.M
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.J.J.Chougule Mo.9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-05

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) PATIL ADITYA PANDURANG
Exam No. 13538
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today none
Details of the Construction Materials learned today none
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS/CU.M
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.J.J.Chougule Mo.9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-05

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today none
Details of the Construction Materials learned today Various types of the pipe material and pipe fittings.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS/CU.M
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.J.J.Chougule Mo.9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-05

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today none
Details of the Construction Materials learned today Various types of the pipe material and pipe fittings.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS/CU.M
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.J.J.Chougule Mo.9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-05

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) MANGAONKAR MANOJ DATTATRAY
Exam No. 13536
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today none
Details of the Construction Materials learned today Various types of the pipe material and pipe fittings.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today PLUMBING DRAWINGS.
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS/CU.M
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.J.J.Chougule Mo.9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: pinkrosee4U@yahoo.com
Subject: 10878-03

Company Name Star Tech Infra
Project Name & Site Address Star Tech Infra.,Rajendra nagar.Kolhapur
Students Name (Surname_First Name_Middle Name) Narnavre Shikha Haridas
Exam No. 10878
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1)Quantity analysis of Beam. 2)Preparing check list for column casting. .
Details of how you Planned & Executed the allotted work We prepare the check list (as per IS 456:2000) of allotted work and execute the work as per check list and drawings. Check list:- Precautions before Concreting:- Size & diagonals to ensure right angles of column. (ii) Plumb (Olamba) of column. (iii) Covering to reinforcement. (iv) Concreting (Bharai) should be up to plinth beam bottom. Carry out concreting of column with specified mix. During concreting don\'t allow labours to pull or push the reinforcements. Check List for Column shuttering:- a. Proper covering must be provided for column reinforcement preferably on the ring. b. The casting level must be marked on the column before casting. c. Before casting cement slurry must be poured on the joint. d. The casted top must be maintained rough so as to have good joint with beam. e. There should be a master ring at the top of filling level. f. Before fixing the formwork, the material used for shuttering should have a coat of an oil so as to have good finishing. g. The care should be taken that the reinforcement should free from oil. h. Channel should be always of 3\"x 3\" or of standard size available and should be fixed at 1\'3\"C/C. i. First Channel & last channel should be fixed 6\" C/C at top and bottom respectively. j. Shikanjas should be fixed on upper side, on both side of Channel. k. Modia should not be greater than 9\" size. l. Starter should be cast before starting the column so as to prevent segregation at the joint between slab & column. m. Centre to centre distance to be checked at starter point and at the top of column. n. Column alignment should be at right angle at top of column. o. Before & after casting the verticality of column must be checked. p. Column face and side should be parallel in line dori. q. Plank supports should not be normally allowed for columns. Props with choti at top should be fixed Channel. r. Top of column should be always be maintained rough or chipped off after casting of columns to remove laitance. s. Starter shuttering is done in channels preferably. t. Minimum Cover:- u. Minimum cover for different structural element: v. (i) Footing - 75 mm (iii) Beam - 20mm w. (ii) Column - 45mm (IV) Slab - 15mm .
Details of the Construction Procedure / Activity / Technology learned today Casting of column:- STARTERS 1) After casting plinth slab, column is casted up to 4” height as a starter for column. By checking its size, position and center line distances for more accuracy of column position & location before casting full column. Proper cover for steel reinforcement is maintained. Right angle (katkona) of starter & line should be checked.Remove the laitance at plinth top in column area. 2) Erect column shuttering of specified size. Support it & do it tight by channels, nut-bolts or scanteling (chavi) & shikanja at 6\" from bottom & top intermediates should be at 1\' 3\" center to center. 3) Mark the filling level on the Column steel or formwork. 4) Pour the cement slurry on the starter, so as to have sufficient cement paste at joint. 5) Place the concrete and do the vibration with the help of needle vibrator. 6) When column is filled to required depth stop pouring concrete, vibrate the last layer and make the top surface rough. .
Details of the Construction Materials learned today Vibrator:- It is used to compact the concrete up to maximum possible density. Types:- 1)Needle Vibrator 2)Surface Vibrator 3)Screed Vibrator 4)Platform Vibrator 5)Table Vibrator We use Needle vibrator on site. We have both electric and diesel vibrator as stand-by. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today On our site special efforts are taken regarding use of water. Water becomes scare in summer. Therefore we use water very carefully. .
Details of the Construction / Engineering Drawings observed today 1)R.C.C. drawing of beam and slab. 2)Working drawing of respective drawing. .
Details of the Bye Laws referred today Minimum dimensions of doors and windows, and slab height. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Beam size:-300x450 R.C.C Design of beam:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Span of beam: - Assume 3m . Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /- .
Result of RATE ANALYSIS ( Rs per Unit ) 9923.72/-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Satish Mistry .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: pinkrosee40@yahoo.com
Subject: 10878-05

Company Name Star Tech Infra
Project Name & Site Address Star Tech Infra.,Rajendra nagar.Kolhapur
Students Name (Surname_First Name_Middle Name) Narnavre Shikha Haridas
Exam No. 10878
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Prepare the detailed estimate of given project. .
Details of how you Planned & Executed the allotted work We work individually for different items and then combine all values and find the estimate of project with the help of current D.S.R. .
Details of the Construction Procedure / Activity / Technology learned today Construction activity:- Tiling:- (Mosaic tiles) 1) Prepare the cement slurry in the ratio of 1.5 bags to 100 Lit of water approximately. start fixing tiles from the reference line and reference tiles diagonally. 2)Spread the cement slurry of a honey like consistency, on the mortar bed, over area as much as could be covered with half an hour. 3)Match all the four corner of the tiles properly with the help of wooden mallet. 4)Fix the mosaic tiles in the particular sequence for better results and fine joints. 5)Except for balconies, bath and toilet complete the flooring of one unit per day, for better bonding and uniform and quick work. 6)If there are are two types of tiling( i.e. living room with white and other room in gray) break the joint at the shutter groove line/ on the inside edge of the masonry in other room, if door is not provided. 7)After completing the tiling work of the floor, check the overall level. Any unevenness can be rectified with wooden mallet. 8)The gap between walls and floor are fixed with cut pieces of the mosaic tile. 9)Clean the floor and don\'t allow anybody to enter the flat for at least 24hrs. 10)Next day fill the gaps/joints between the tiles with cement slurry. 11) Then cure the flooring and skirting for at least 14days. .
Details of the Construction Materials learned today Tiles:- Types:- 1)Mosaic 2)Cuddappa 3)Marble 4)Glazed Size:- As per the requirement of unit and market availability. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Mortar falling down during plaster work if reused again within 30min, it will save the materials and thereby it will save the natural resources of those material. .
Details of the Construction / Engineering Drawings observed today Details of the Construction / Engineering Drawings observed today: Interior Decorator Drawing. -For the details of flooring and other furniture and electrification requirement. .
Details of the Bye Laws referred today Minimum length and width of rooms for residential building. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/- .
Result of RATE ANALYSIS ( Rs per Unit ) 2270.1/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Satish Mistry. .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10983-05

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates,mukta sainik vasahat, kolhapur.
Students Name (Surname_First Name_Middle Name) KAMBLE ANKIT VIJAYANAND
Exam No. 10983
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00
Site Leaving Time (HH:MM am/pm) 05:30
Details of the Work Allotted to you today by the Site In-Charge 1. To Study various Tiling Floor with their Specifications. 2. To Study \"Preparation of Base for Flooring\". 3. To Study \"Laying of Tiles\".
Details of how you Planned & Executed the allotted work 1. We all together (5 members) in our group went to Flat No. 408, to study the various aspects required before & after Flooring work. 2. We observed various aspects such as \"Preparation of Base for Flooring in Kitchen Balcony\" & \"Laying of tiles in Master Bed Terrace\".
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR VITRIFIED TILE FLOORING WORK\" # - Prepare Cement slurry in Ratio of 1.5 Bag : 100 Litre of water approximately. - Start Fixing Tiles from reference line & reference tiles diagonally. - Spread the Cement Slurry on Mortar Bed. - Match all the four corners of Tiles properly with the help of \'Wooden Mallet\'. - Fix the \'Mosic Tiles\' in particular sequence. - After completing the tiling work check the overall level - Clean the floor & do not allow anybody to enter the flat for minimum 24 hours. - Next day fill the \"Gap joints\" between tiles with cement slurry. - Cure it for 14 days minimum ---------------------------------------------------------------------------------- # \"Vitrified Tile Skirting\" # - With the help of \"Wooden Farma\", Skirting Tile was fixed, projecting only 8 mm from Wall Plaster. - Keep the skirting in one line. - Fix skirting at two corners & fix the line dori as a guide line for line of the in between skirting. - At columns positions Skirting should be sliced in vertical direction. - Ensure that skirting lines are perpendicular to the vitrified tile line.
Details of the Construction Materials learned today 1. PCC - Ratio of 1:4:8 ( M-10 Grade Concrete ). 2. Anti Skid Tiles. - 16\" x 16\" ( Regency Brand ). 3. Vitrified Tiles. - 2\' x 2\' ( Commet Brand ). 4. White Cement Putty - Wall Shine ( Creamcem Brand).
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Product learned today: Not observed such Methodology today.
Details of the Construction / Engineering Drawings observed today 1. Steel Scaffolding Drawings for Lift & Duct for Plastering purpose. 2. Floor Plans
Details of the Bye Laws referred today # Parking Bye-Laws # 1. Motar Vehicle - 2.5 m x 5.5 m. 2. Motor Cycle - 3 sq.m.
Details of any Managerial Skill learned today - How to convience a customer. - How to Bargain with the dealer.
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR BRICKWORK\" # --------------------------------------------------- - Brick Size = 20 cm x 10 cm x 10 cm. - Cement Mortor = 1:6. - Volume of Brickwork = 10 cu.m. --------------------------------------------------- A) Materials: 1. Brick required for 10 cu.m = 5000 nos. 2. Mortor = 30% = 3 cu.m 3. Cement = 0.428 cu.m 4. No of Bags Of Cement = 12.23 = 13 bags (approximate) 5. Sand = 0.428 x 6 = 2.568 cu.m -------------------------------------------------------- B) Cost of Material: 1. Brick = 5000 x 4 = 20000/-. 2. Cement = 13 x 230 = 2990/-. 3. Sand = 2.568 x 850 = 2182.8/-. * TOTAL = 25172.8/- --------------------------------------------------------- C) Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 8 x 140 = 1120/- 4. Female Mazdoor = 10 x 1100 = 1100/- 5. Bhisti = 2 x 120 = 240/- 6. Scaffolding = 500/-(Lumpsum) 7. Tools & Plants = 300/-(Lumpsum) * TOTAL = 5210/- -------------------------------------------------------- D) TOTAL = B+C = 30382.8/- -------------------------------------------------------- E) Add 2% water charges = 607.656/- -------------------------------------------------------- F) Add 15% for contractors Profit = 4557.42/- -------------------------------------------------------- G) GRAND TOTAL = 35547.876/- -------------------------------------------------------- H) Rate Per cu.m = 3554.7876/- -------------------------------------------------------- Result of RATE ANALYSIS ( Rs per Unit ): Rs 3554.7876/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 3554.7876/-per meter cube
Todays BUZZ Word \"Checklist For Tiling Work\" Description Of Work ---- (Yes/No) 1. Is all the materials checked? 2. Is there any defect in tiles / stones received? 3. Are the rooms cleaned before tiling? 4. Is the skirting gap sufficient? 5. Is the lime mortar fresh & properly mixxed in mixtures? 6. Are Thiyyas Taken before Machan work? 7. Is right angle set before starting tiling? 8. Are level lines are marked on the walls of flat? 9. Are tile joints filled with matching colour cement slurry? 10. Is the skirting Farma used before fixing skirting? 11. Are all the cut-pieces made with help of cutting machine? 12. Is there sufficient stock of 12 mm thick skirting for fixing near RCC column? 13. Are new polishing stones used for polishing? 14. Is proper Curing for three days done to the grouting coat? 15. Are all polishing coats properly executed? 16. Is oxalic acid in powder form used for acid form? 17. Is the balcony flooring given sufficient slope towards spout? 18. Is all G.I., P.V.C. conduiting completed before glazed tile fixing? 19. Is the tile taken on the opening side of the door fro WC floor? 20. Are the edges of kitchen otta & sill rounded? 21. Are the slopes of kitchen platform top & sink proper? 22. Is the WC / Bath floor slope in proper direction? 23. Is the oil paint applied to kitchen platform & sill? 24. Are umbra pattis fixed wherever required? 25. Is the cleaning properly done?
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay. (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: cool.sushantoo7@gmail.com
Subject: 10880-05

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil sushant digambar
Exam No. 10880
Working Day No. 03
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:AM
Site Leaving Time (HH:MM am/pm) 04:PM
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today different diameter pipes are used according to the usage. 1. flushing pipe diameter = 35 mm 2. normal diameter pipe = 20 mm 3. soil and rainwater downtake pipes = 110 mm pipes used for hot water supply pipes are provided with foam material. none
Details of the Construction Materials learned today Various types of the pipe material and pipe fittings.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge mr. ketan charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: Pinkrosee40@yahoo.com
Subject: 10878-05

Company Name Star Tech Infra
Project Name & Site Address Star Tech Infra.,Rajendra nagar.Kolhapur
Students Name (Surname_First Name_Middle Name) Narnavre Shikha Haridas
Exam No. 10878
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Prepare the detailed estimate of given project. .
Details of how you Planned & Executed the allotted work We work individually for different items and then combine all values and find the estimate of project with the help of current D.S.R. .
Details of the Construction Procedure / Activity / Technology learned today Construction activity:- Tiling:- (Mosaic tiles) 1) Prepare the cement slurry in the ratio of 1.5 bags to 100 Lit of water approximately. start fixing tiles from the reference line and reference tiles diagonally. 2)Spread the cement slurry of a honey like consistency, on the mortar bed, over area as much as could be covered with half an hour. 3)Match all the four corner of the tiles properly with the help of wooden mallet. 4)Fix the mosaic tiles in the particular sequence for better results and fine joints. 5)Except for balconies, bath and toilet complete the flooring of one unit per day, for better bonding and uniform and quick work. 6)If there are are two types of tiling( i.e. living room with white and other room in gray) break the joint at the shutter groove line/ on the inside edge of the masonry in other room, if door is not provided. 7)After completing the tiling work of the floor, check the overall level. Any unevenness can be rectified with wooden mallet. 8)The gap between walls and floor are fixed with cut pieces of the mosaic tile. 9)Clean the floor and don\'t allow anybody to enter the flat for at least 24hrs. 10)Next day fill the gaps/joints between the tiles with cement slurry. 11) Then cure the flooring and skirting for at least 14days. .
Details of the Construction Materials learned today Tiles:- Types:- 1)Mosaic 2)Cuddappa 3)Marble 4)Glazed Size:- As per the requirement of unit and market availability. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Mortar falling down during plaster work if reused again within 30min, it will save the materials and thereby it will save the natural resources of those material. .
Details of the Construction / Engineering Drawings observed today Interior Decorator Drawing. -For the details of flooring and other furniture and electrification requirement. .
Details of the Bye Laws referred today Minimum length and width of rooms for residential building. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Satish Mistry.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-05

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Jape Vishwajeet Ramesh
Exam No. 10892
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 5:30pm
Details of the Work Allotted to you today by the Site In-Charge 1. To Study various Tiling Floor with their Specifications. 2. To Study \"Preparation of Base for Flooring\". 3. To Study \"Laying of Tiles\". -------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work 1. We all together (5 members) in our group went to Flat No. 408, to study the various aspects required before & after Flooring work. 2. We observed various aspects such as \"Preparation of Base for Flooring in Kitchen Balcony\" & \"Laying of tiles in Master Bed Terrace\". ------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR VITRIFIED TILE FLOORING WORK\" # - Prepare Cement slurry in Ratio of 1.5 Bag : 100 Litre of water approximately. - Start Fixing Tiles from reference line & reference tiles diagonally. - Spread the Cement Slurry on Mortar Bed. - Match all the four corners of Tiles properly with the help of \'Wooden Mallet\'. - Fix the \'Mosic Tiles\' in particular sequence. - After completing the tiling work check the overall level - Clean the floor & do not allow anybody to enter the flat for minimum 24 hours. - Next day fill the \"Gap joints\" between tiles with cement slurry. - Cure it for 14 days minimum ---------------------------------------------------------------------------------- # \"Vitrified Tile Skirting\" # - With the help of \"Wooden Farma\", Skirting Tile was fixed, projecting only 8 mm from Wall Plaster. - Keep the skirting in one line. - Fix skirting at two corners & fix the line dori as a guide line for line of the in between skirting. - At columns positions Skirting should be sliced in vertical direction. - Ensure that skirting lines are perpendicular to the vitrified tile line. -------------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. PCC - Ratio of 1:4:8 ( M-10 Grade Concrete ). 2. Anti Skid Tiles. - 16\" x 16\" ( Regency Brand ). 3. Vitrified Tiles. - 2\' x 2\' ( Commet Brand ). 4. White Cement Putty - Wall Shine ( Creamcem Brand). -----------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not observed such Methodology today. --------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1. Steel Scaffolding Drawings for Lift & Duct for Plastering purpose. 2. Floor Plans. --------------------------------------------------------------------------------------
Details of the Bye Laws referred today # Parking Bye-Laws # 1. Motar Vehicle - 2.5 m x 5.5 m. 2. Motor Cycle - 3 sq.m. -----------------------------------------------------------------------------------
Details of any Managerial Skill learned today - How to convience a customer. - How to Bargain with the dealer. ---------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR BRICKWORK\" # --------------------------------------------------- - Brick Size = 20 cm x 10 cm x 10 cm. - Cement Mortor = 1:6. - Volume of Brickwork = 10 cu.m. --------------------------------------------------- A) Materials: 1. Brick required for 10 cu.m = 5000 nos. 2. Mortor = 30% = 3 cu.m 3. Cement = 0.428 cu.m 4. No of Bags Of Cement = 12.23 = 13 bags (approximate) 5. Sand = 0.428 x 6 = 2.568 cu.m -------------------------------------------------------- B) Cost of Material: 1. Brick = 5000 x 4 = 20000/-. 2. Cement = 13 x 230 = 2990/-. 3. Sand = 2.568 x 850 = 2182.8/-. * TOTAL = 25172.8/- --------------------------------------------------------- C) Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 8 x 140 = 1120/- 4. Female Mazdoor = 10 x 1100 = 1100/- 5. Bhisti = 2 x 120 = 240/- 6. Scaffolding = 500/-(Lumpsum) 7. Tools & Plants = 300/-(Lumpsum) * TOTAL = 5210/- -------------------------------------------------------- D) TOTAL = B+C = 30382.8/- -------------------------------------------------------- E) Add 2% water charges = 607.656/- -------------------------------------------------------- F) Add 15% for contractors Profit = 4557.42/- -------------------------------------------------------- G) GRAND TOTAL = 35547.876/- -------------------------------------------------------- H) Rate Per cu.m = 3554.7876/- --------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs 3554.7876/-
Todays BUZZ Word \"Checklist For Tiling Work\" Description Of Work ---- (Yes/No) 1. Is all the materials checked? 2. Is there any defect in tiles / stones received? 3. Are the rooms cleaned before tiling? 4. Is the skirting gap sufficient? 5. Is the lime mortar fresh & properly mixxed in mixtures? 6. Are Thiyyas Taken before Machan work? 7. Is right angle set before starting tiling? 8. Are level lines are marked on the walls of flat? 9. Are tile joints filled with matching colour cement slurry? 10. Is the skirting Farma used before fixing skirting? 11. Are all the cut-pieces made with help of cutting machine? 12. Is there sufficient stock of 12 mm thick skirting for fixing near RCC column? 13. Are new polishing stones used for polishing? 14. Is proper Curing for three days done to the grouting coat? 15. Are all polishing coats properly executed? 16. Is oxalic acid in powder form used for acid form? 17. Is the balcony flooring given sufficient slope towards spout? 18. Is all G.I., P.V.C. conduiting completed before glazed tile fixing? 19. Is the tile taken on the opening side of the door fro WC floor? 20. Are the edges of kitchen otta & sill rounded? 21. Are the slopes of kitchen platform top & sink proper? 22. Is the WC / Bath floor slope in proper direction? 23. Is the oil paint applied to kitchen platform & sill? 24. Are umbra pattis fixed wherever required? 25. Is the cleaning properly done? ---------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay. (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-05

Company Name V. S. Joshi & Associates
Project Name & Site Address vishava enclave
Students Name (Surname_First Name_Middle Name) janbandhu rakshit d
Exam No. 10875
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 am
Site Leaving Time (HH:MM am/pm) 5.30pm
Details of the Work Allotted to you today by the Site In-Charge Details of the Work Allotted to you today by the Site In-Charge: to check the dimension of rooms as per drawing. windows size,door height,sunk slab etc. for row bunglows
Details of how you Planned & Executed the allotted work 1)we go through by drawing 2)1st one was note down the dimension. 3)another were just measuring the dimension 4)the door height is 2.1m 5)window size is 1.5*1.5 6)sill level is 0.62m
Details of the Construction Procedure / Activity / Technology learned today 1)we learn hows the transportation done 2)by hand vehicle, gadda 3)brick supply at top of building by crane 4)tiles cutting device
Details of the Construction Materials learned today 1)window grill 2)tiles 3)door frame of m.s. 4)scarting tiles
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today 1)we observed parking drawind. 2)overall parking arrangment is nice. 3)around the building of both side the parking provided 4)two wheelers and 4 wheeler both are seperated
Details of the Bye Laws referred today 1)store room size is(3 m2)
Details of any Managerial Skill learned today 1)we learn how careful about material 2)minimum wastage of material
RATE ANALYSIS (Detailed Stepwise Calculations required) 1)brick work 2)propertion (1:22) 3)cement 1.52/1+22 =0.067 4)no.of bags= 0.067/0.035 =2 nos. 5)cost of cement=520 rs. 6)sand 0.152*725 =3.344 =3.344*725=2424.4 rs. 7)brick 8)size(9\"*6\"*4\") 10)for 1m3 no.of bricks =295 11)cost per brick=6 rs. 12)totl brick cost =295*6=1770 rs. 13)labour =125+200+80=405 rs. 14)total cost for 1m3 =405+2425+520+1770 =5120 rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1m3 cost=5120 rs.
Todays BUZZ Word 1)beam 2)top bars 20mm dia. 3)2 nos. 4)extra top=20mm dia 2 nos. 5)bottom bar=16mm 6)covering=30mm 7)stirrups=8mm dia. 8)spacing betn.stirrups=6\" 9)no. of stirrups=26 nos. 10)lengh of beam=4.20m 11)height=0.153m 13)width=0.230m 14)proportion=(1:1.5:3) 15)cement used=53 grade 16)admixture protect used(50 ml for 1bag) 17)form work pwriod=15 days 18)curing=14 days 19)plaster 20)1st coat of morter=12mm 21)final coat=3mm 22)material proportion=1:4.5 23)final coat=1:2.5 24)curing 7 days for plaster 25)concrete=M20
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge amol maulay
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-05

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Nagvekar Yogesh Deepak
Exam No. 10894
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To Study various Tiling Floor with their Specifications. 2. To Study \"Preparation of Base for Flooring\". 3. To Study \"Laying of Tiles\". -------------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work 1. We all together (5 members) in our group went to Flat No. 408, to study the various aspects required before & after Flooring work. 2. We observed various aspects such as \"Preparation of Base for Flooring in Kitchen Balcony\" & \"Laying of tiles in Master Bed Terrace\". ------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today # \"PROCEDURE FOR VITRIFIED TILE FLOORING WORK\" # - Prepare Cement slurry in Ratio of 1.5 Bag : 100 Litre of water approximately. - Start Fixing Tiles from reference line & reference tiles diagonally. - Spread the Cement Slurry on Mortar Bed. - Match all the four corners of Tiles properly with the help of \'Wooden Mallet\'. - Fix the \'Mosic Tiles\' in particular sequence. - After completing the tiling work check the overall level - Clean the floor & do not allow anybody to enter the flat for minimum 24 hours. - Next day fill the \"Gap joints\" between tiles with cement slurry. - Cure it for 14 days minimum ---------------------------------------------------------------------------------- # \"Vitrified Tile Skirting\" # - With the help of \"Wooden Farma\", Skirting Tile was fixed, projecting only 8 mm from Wall Plaster. - Keep the skirting in one line. - Fix skirting at two corners & fix the line dori as a guide line for line of the in between skirting. - At columns positions Skirting should be sliced in vertical direction. - Ensure that skirting lines are perpendicular to the vitrified tile line. -------------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. PCC - Ratio of 1:4:8 ( M-10 Grade Concrete ). 2. Anti Skid Tiles. - 16\" x 16\" ( Regency Brand ). 3. Vitrified Tiles. - 2\' x 2\' ( Commet Brand ). 4. White Cement Putty - Wall Shine ( Creamcem Brand). -----------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not observed such Methodology today. --------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today 1. Steel Scaffolding Drawings for Lift & Duct for Plastering purpose. 2. Floor Plans. --------------------------------------------------------------------------------------
Details of the Bye Laws referred today # Parking Bye-Laws # 1. Motar Vehicle - 2.5 m x 5.5 m. 2. Motor Cycle - 3 sq.m. -----------------------------------------------------------------------------------
Details of any Managerial Skill learned today - How to convience a customer. - How to Bargain with the dealer. ---------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) # \"RATE ANALYSIS FOR BRICKWORK\" # --------------------------------------------------- - Brick Size = 20 cm x 10 cm x 10 cm. - Cement Mortor = 1:6. - Volume of Brickwork = 10 cu.m. --------------------------------------------------- A) Materials: 1. Brick required for 10 cu.m = 5000 nos. 2. Mortor = 30% = 3 cu.m 3. Cement = 0.428 cu.m 4. No of Bags Of Cement = 12.23 = 13 bags (approximate) 5. Sand = 0.428 x 6 = 2.568 cu.m -------------------------------------------------------- B) Cost of Material: 1. Brick = 5000 x 4 = 20000/-. 2. Cement = 13 x 230 = 2990/-. 3. Sand = 2.568 x 850 = 2182.8/-. * TOTAL = 25172.8/- --------------------------------------------------------- C) Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 10 x 170 = 1700/- 3. Male Mazdoor = 8 x 140 = 1120/- 4. Female Mazdoor = 10 x 1100 = 1100/- 5. Bhisti = 2 x 120 = 240/- 6. Scaffolding = 500/-(Lumpsum) 7. Tools & Plants = 300/-(Lumpsum) * TOTAL = 5210/- -------------------------------------------------------- D) TOTAL = B+C = 30382.8/- -------------------------------------------------------- E) Add 2% water charges = 607.656/- -------------------------------------------------------- F) Add 15% for contractors Profit = 4557.42/- -------------------------------------------------------- G) GRAND TOTAL = 35547.876/- -------------------------------------------------------- H) Rate Per cu.m = 3554.7876/- --------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs 3554.7876/-
Todays BUZZ Word \"Checklist For Tiling Work\" Description Of Work ---- (Yes/No) 1. Is all the materials checked? 2. Is there any defect in tiles / stones received? 3. Are the rooms cleaned before tiling? 4. Is the skirting gap sufficient? 5. Is the lime mortar fresh & properly mixxed in mixtures? 6. Are Thiyyas Taken before Machan work? 7. Is right angle set before starting tiling? 8. Are level lines are marked on the walls of flat? 9. Are tile joints filled with matching colour cement slurry? 10. Is the skirting Farma used before fixing skirting? 11. Are all the cut-pieces made with help of cutting machine? 12. Is there sufficient stock of 12 mm thick skirting for fixing near RCC column? 13. Are new polishing stones used for polishing? 14. Is proper Curing for three days done to the grouting coat? 15. Are all polishing coats properly executed? 16. Is oxalic acid in powder form used for acid form? 17. Is the balcony flooring given sufficient slope towards spout? 18. Is all G.I., P.V.C. conduiting completed before glazed tile fixing? 19. Is the tile taken on the opening side of the door fro WC floor? 20. Are the edges of kitchen otta & sill rounded? 21. Are the slopes of kitchen platform top & sink proper? 22. Is the WC / Bath floor slope in proper direction? 23. Is the oil paint applied to kitchen platform & sill? 24. Are umbra pattis fixed wherever required? 25. Is the cleaning properly done? ---------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay. (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-05

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) fulari sujata shankar
Exam No. 13559
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 10.00am
Site Leaving Time (HH:MM am/pm) 04.50pm
Details of the Work Allotted to you today by the Site In-Charge Today we have seen construction procedure of Brick-Masonry and calculate the number of bricks required in wall. .
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurement of the wall and second for calculation purpose .
Details of the Construction Procedure / Activity / Technology learned today We have learn various Bonds of bricks .
Details of the Construction Materials learned today - About brick masonry and preparing cement mortar as per proportion. - By using Plumb bob we check the line the of the wall. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None .
Details of the Construction / Engineering Drawings observed today - Plans of the floor. .
Details of the Bye Laws referred today -None .
Details of any Managerial Skill learned today - To convince the dealers regarding rates .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for 6\" bricks. No. of bricks required for per sq.m- 50 Cost per brick= Rs.4. For 50 bricks cost= Rs.200. Proportion = 1:4 For 1 sq.m = 0.22 cement required. Cost of cement= Rs. 265. Total cement cost=265*0.22= Rs.58.30. Cost of sand= Rs.1060. Total cost of sand per sq.m= 1060*0.15= Rs.159. Total cost=200+58.30+159=Rs. 417. Labour cost= 20%= Rs.83.4. Total cost=417+83.4=Rs.500.4. With 10% profit=Rs.550.4 Total cost of brick work for 6\" bricks = Rs.550.4 per sq.m . .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.550.4 per sq.m for 6\" bricks.
Todays BUZZ Word \"Checklist For Tiling Work\" Description Of Work----(Yes/No) 1. Is all the materials checked? 2. Is there any defect in tiles / stones received? 3. Are the rooms cleaned before tiling? 4. Is the skirting gap sufficient? 5. Is the lime mortar fresh & properly mixxed in mixtures? 6. Are Thiyyas Taken before Machan work? 7. Is right angle set before starting tiling? 8. Are level lines are marked on the walls of flat? 9. Are tile joints filled with matching colour cement slurry? 10. Is the skirting Farma used before fixing skirting? 11. Are all the cut-pieces made with help of cutting machine? 12. Is there sufficient stock of 12 mm thick skirting for fixing near RCC column? 13. Are new polishing stones used for polishing? 14. Is proper Curing for three days done to the grouting coat? 15. Are all polishing coats properly executed? 16. Is oxalic acid in powder form used for acid form? 17. Is the balcony flooring given sufficient slope towards spout? 18. Is all G.I., P.V.C. conduiting completed before glazed tile fixing? 19. Is the tile taken on the opening side of the door fro WC floor? 20. Are the edges of kitchen otta & sill rounded? 21. Are the slopes of kitchen platform top & sink proper? 22. Is the WC / Bath floor slope in proper direction? 23. Is the oil paint applied to kitchen platform & sill? 24. Are umbra patties fixed wherever required? 25. Is the cleaning properly done? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: shinde_shital7@yahoo.com
Subject: 10884-05

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) shinde shital vilasrao
Exam No. 10884
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today different diameter pipes are used according to the usage. 1. flushing pipe diameter = 35 mm 2. normal diameter pipe = 20 mm 3. soil and rainwater downtake pipes = 110 mm pipes used for hot water supply pipes are provided with foam material.
Details of the Construction Materials learned today Various types of the pipe material and pipe fittings.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge mr. ketan charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: cool.sushantoo7@gmail.com
Subject: 10880-05

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) patil sushant digambar
Exam No. 10880
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today different diameter pipes are used according to the usage. 1. flushing pipe diameter = 35 mm 2. normal diameter pipe = 20 mm 3. soil and rainwater downtake pipes = 110 mm pipes used for hot water supply pipes are provided with foam material.
Details of the Construction Materials learned today Various types of the pipe material and pipe fittings.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS/CU.M
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge mr. ketan charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-05

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) misal swapnil shivaji
Exam No. 10877
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today different diameter pipes are used according to the usage. 1. flushing pipe diameter = 35 mm 2. normal diameter pipe = 20 mm 3. soil and rainwater downtake pipes = 110 mm pipes used for hot water supply pipes are provided with foam material.
Details of the Construction Materials learned today Various types of the pipe material and pipe fittings.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge mr. ketan charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-05

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell,karande mala,new tarabai park
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge to check the dimension of rooms as per drawing. windows size,door height,sunk slab etc. for row bunglows
Details of how you Planned & Executed the allotted work 1)we go through by drawing 2)1st one was note down the dimension. 3)another were just measuring the dimension 4)the door height is 2.1m 5)window size is 1.5*1.5 6)sill level is 0.62m
Details of the Construction Procedure / Activity / Technology learned today 1)we learn hows the transportation done 2)by hand vehicle, gadda 3)brick supply at top of building by crane 4)tiles cutting device
Details of the Construction Materials learned today 1)window grill 2)tiles 3)door frame of m.s. 4)scarting tiles
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today 1)we observed parking drawind. 2)overall parking arrangment is nice. 3)around the building of both side the parking provided 4)two wheelers and 4 wheeler both are seperated
Details of the Bye Laws referred today 1)store room size is(3 m2)
Details of any Managerial Skill learned today 1)we learn how careful about material 2)minimum wastage of material
RATE ANALYSIS (Detailed Stepwise Calculations required) 1)brick work 2)propertion (1:22) 3)cement 1.52/1+22 =0.067 4)no.of bags= 0.067/0.035 =2 nos. 5)cost of cement=520 rs. 6)sand 0.152*725 =3.344 =3.344*725=2424.4 rs. 7)brick 8)size(9\"*6\"*4\") 10)for 1m3 no.of bricks =295 11)cost per brick=6 rs. 12)totl brick cost =295*6=1770 rs. 13)labour =125+200+80=405 rs. 14)total cost for 1m3 =405+2425+520+1770 =5120 rs.
Result of RATE ANALYSIS ( Rs per Unit ) for 1m3 cost=5120 rs.
Todays BUZZ Word 1)beam 2)top bars 20mm dia. 3)2 nos. 4)extra top=20mm dia 2 nos. 5)bottom bar=16mm 6)covering=30mm 7)stirrups=8mm dia. 8)spacing betn.stirrups=6\" 9)no. of stirrups=26 nos. 10)lengh of beam=4.20m 11)height=0.153m 13)width=0.230m 14)proportion=(1:1.5:3) 15)cement used=53 grade 16)admixture protect used(50 ml for 1bag) 17)form work pwriod=15 days 18)curing=14 days 19)plaster 20)1st coat of morter=12mm 21)final coat=3mm 22)material proportion=1:4.5 23)final coat=1:2.5 24)curing 7 days for plaster 25)concrete=M20
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge KETAN CHARPALE 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-05

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHAIKH RIZWAN KHALIL
Exam No. 13545
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today different diameter pipes are used according to the usage. 1. flushing pipe diameter = 35 mm 2. normal diameter pipe = 20 mm 3. soil and rainwater downtake pipes = 110 mm pipes used for hot water supply pipes are provided with foam material.
Details of the Construction Materials learned today Various types of the pipe material and pipe fittings.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS/CU.M
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr ABHIJEET BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-05

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SALOKHE SUDARSHAN ANIL
Exam No. 13544
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today different diameter pipes are used according to the usage. 1. flushing pipe diameter = 35 mm 2. normal diameter pipe = 20 mm 3. soil and rainwater downtake pipes = 110 mm pipes used for hot water supply pipes are provided with foam material.
Details of the Construction Materials learned today Various types of the pipe material and pipe fittings.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS/CU.M
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr ABHIJEET BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-05

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SINGH RAJAN RAJENDRA BAHADUR
Exam No. 13548
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.25 PM
Details of the Work Allotted to you today by the Site In-Charge check the plumbing activities going on.
Details of how you Planned & Executed the allotted work we go to the store room where the various equipments related to the plumbing arrangements.
Details of the Construction Procedure / Activity / Technology learned today different diameter pipes are used according to the usage. 1. flushing pipe diameter = 35 mm 2. normal diameter pipe = 20 mm 3. soil and rainwater downtake pipes = 110 mm pipes used for hot water supply pipes are provided with foam material.
Details of the Construction Materials learned today Various types of the pipe material and pipe fittings.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NONE
Details of the Construction / Engineering Drawings observed today PLUMBING DRAWINGS.
Details of the Bye Laws referred today NONE
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICK WORK PROPORTION USED :(1:6) VOLUME OF THE BRICK WALL : 1 CU.M BRICK IN 1 CU,M= 500 NO. COST= (500 X 4.50)=2250 RS 30% MORTAR IS REQUIRED FOR 1 CU.M OF BRICK MASONRY = 0.3 CU.M CEMENT = 0.3/(1+6)=0.0428 CU.M NO. OF BAGS = 0.0428/0.035= 1.22 = 1.5 BAGS COST= 1.5 X 260 =390 RS SAND = 0.0428 X 6 =0.2568 CU.M COST= 0.2568 X 1125 = 288.90 RS TOTAL MATERIAL COST = 2928.90 RS LABOUR = 540 RS SCAFFOLDING = 60 RS TOTAL COST = 3528.90 RS WATER 1.5% = (1.5/100) X 3528.90 =52.93 RS CONTRACTOR PROFIT = 15% = (15/100) X 3528.90 =529.33 RS TOTAL COST = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS/CU.M
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr ABHIJEET BHOSALE 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-05

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.08 p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see brickwork going in row bunglow D-8. -To see sewere line work in D-8 row bunglow.
Details of how you Planned & Executed the allotted work -First we go in D-8 row bunglow & see all the details of brickwork. -Then we see the laying of sewre pipeline behind the D-8 wing.
Details of the Construction Procedure / Activity / Technology learned today Procedure of masonary work: -First mortor is prepared for brickwork in proportion of 1:6. -All the bricks are soaked in water so that they do not absorb water. -First mortor is spread over the surface of 10mm thick then corner brick is placed & fixed in the motor. -header bond is used for masonry. -Strech a string (line dori)along the top of the first coarse laid at each corner of the wall. -Then coarse is raised. -Then procedure is repeated for 2nd , 3rd & other coarses until wall is constructed to the requireb height. Sewere line.- -first excavation is done for placing the septic tank. -then excavation is done for pipe line. -one end of the pipe is attached to the septic tank & other is taken to the waste water treatment plant. -Then water is treated 7 reused for gardening purpose only.
Details of the Construction Materials learned today -R.C.C. pipes for sewere line of 150mm dia. -bricks 22.5x15x10 cm -Aggregate brick 40x18.8x15 cm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today septic tanks are used for sewage disposal.
Details of the Construction / Engineering Drawings observed today -Plumbing layout -Drainage layout
Details of the Bye Laws referred today -Parking height is 2.5m provided.
Details of any Managerial Skill learned today -when we observe all the bunglow we found the toilet cock is not on the proper height we told the site incharge then he gave instruction to the plumber strictly.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis of brick work: assume quantity of brickwork=10sq.m. -quantity of morter=35% of quantity - =10x0.35 =3.5cub. m. -quantity of cement =3.5/1+6 =0.5cub.m. -no.of bags of cement=0.5/0.035 =14.28 say 15 bags -quantity of sand = 6x0.5 =3 cub.m. -bricks = 1 sq.m.=450 then 10sq.m.=4500no. particular Qt. or NO. rate RS Cement 15 bags 255/- 3225/- Sand 3 cub.m. 1827/- 5481/- Bricks 4500 5600/- 22500/- -Labour mason 2 210/- 420/- Mazdoor mail 3 160/- 480/- femail 3 130/- 390/- Bhisti 1 100/- 100/- Lumpsum 100/- 100/- TOTAL = 32746/- Add 20% buildres profit including sales tax ,service tax,vat, all charges =39295.2/- Rate per sq. m. = 3930/-
Result of RATE ANALYSIS ( Rs per Unit ) 3930/-Per sq.m.
Todays BUZZ Word CHECKLIST -incomplete tiles are provided for the kitchen otta. -sink pipe are of not good quality -Exhaust fans are not provided at sufficient height. -replacement of w.c.pan. -inappropriate door & window fastenings. -height of w.c. cock are wrong. -placement of the switchboard are not hidden from the people. -Height of the switch board is wrong. -Height of the kitchen otta is less as compare to bylaws. -Dining table 1400x750mm. -ceiling height of the window 850mm -Privacy is not maintained in master bed of A-3 bunglow. -Position of bath in master bed is not sufficent. -Master bed door width 1390mm. -master bed size 6.25mx3.40m -sizes of bath are wrong. -Dressing table height is not proper. -No provision of space for gas cylinder. -Size of the window in kitchen is so large. -Proper maintanance is not done. -Wastage of tiles, bricks ,plywood considerably. -No of switchboard are more than sufficient. -Position of the all room in the A-3 are not proper. -Main entrance door is not sufficient according to Byelaws.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523-05

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders, Near Jayprabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) devkar vikram dilip
Exam No. 13523
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To see the curing of slab. 2. To see the column reinforcement for second floor. 3. To see the slab centering work for third floor.
Details of how you Planned & Executed the allotted work We saw the curing of slab that was casted two days before. The slab had attained sufficient firmness. For curing, ponds were made, and water was continously sprinkled on slab for 3-4 times a day.
Details of the Construction Procedure / Activity / Technology learned today We saw the laying of column reinforcement for second floor. The bars were reduced in size from 1200 mm to 80 mm. We saw the slab centering work going on for third floor. We also saw the construction of formwork for the next flight from second floor to third floor. We saw how the labourers check the level by water pipes by holding them at two points and see their levels, this is the new technique we learnt. Details of the Construction Materials learned today: Column reinforcement- Tor steel bars 20mm, stirrups. Formwork and other materials for staircase.
Details of the Construction Materials learned today 1. Plan for centering work for third floor. 2. Plan for third floor.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such Technology was adopted today.
Details of the Construction / Engineering Drawings observed today 1. Plan for centering work for third floor. 2. Plan for third floor.
Details of the Bye Laws referred today 1. According to bye-laws cantilever beams should be placed at L/2 distance. 2. According to bye-laws maximum length of cantilever beam is 4m. On site it is provided 2m. 3.According to bye laws, minimum head requirement for garage is 2.4m. On site it is provided 3.8m. 5.According to bye laws, maximum height of riser is 190 mm. On site it is provided 160 mm. 7.According to bye laws,minimum width of treads is 250 mm. On site it is provided 300 mm.
Details of any Managerial Skill learned today Details of any Managerial Skill learned today: 1. The site incharge saw whether curing was done properly or not. 2. He saw the Slab centering work. 3. He suggested the labour to make changes wherever needed
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for \"Brick work\" Rate analysis for 6\" bricks. No. of bricks required for per sq.m- 50 Cost per brick= Rs.4. For 50 bricks cost= Rs.200. Proportion = 1:4 For 1 sq.m = 0.22 cement required. Cost of cement= Rs. 265. Total cement cost=265*0.22= Rs.58.30. Cost of sand= Rs.1060. Total cost of sand per sq.m= 1060*0.15= Rs.159. Total cost=200+58.30+159=Rs. 417. Labour cost= 20%= Rs.83.4. Total cost=417+83.4=Rs.500.4. With 10% profit=Rs.550.4 Total cost of brick work for 6\" bricks = Rs.550.4 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.550.4 per sq.m for 6\" bricks.
Todays BUZZ Word \"CHECK-LIST\" 1.Slab centering checked with architectural drawing. 1. For elevation. 2. For room dimension. 3. For electric points. 2. Slab centering checked completely. 1. For required beam depth/ slab thickness. 2. For required head rooms. 3. For other points. 3.Slab centering checked completely. 1. Level checked/ Line checked. 2. Column centering checked / modified. 3. Oiling to beams/ slab shuttering. 4. Centering for stair-case checked. 5. Changes for amenities if any checked. 6. Reinforcement checked for beams and slabs as per R.C.C drawings. 7. Proper cover for bottom /side checked for beams. 8. Proper number of chairs provided for slab. 9. Proper cover bottom/top checked for slab/fan hook checked. 10.Reduction of columns as per drawing done for above slab. 11.Hidden beams/Cantilever beams/inverted beams checked if any. 12.Pardi bars left for balconies etc. 13.Proper cover bottom side/checked for all. 14.Dowels (any required ) are left. 15.R.C.C work centering checked for with architectural drawings. 1. For elevation. 2. For cenetring plan. 3. For electrical points. 4. For required size of beam /footings/slabs etc. 5. For other points. 16.Reinforcement checked as per R.C.C drwaings. 1. For beams. 2. For columns. 3. For pardhi. 4. For waist slab. 5. For other items. 17.B.B masonry work checked with architectural drawing. 1. For elevation. 2. For room dimension. 3. For openings. 18.B.B. masonry checked. 1. For beam size. 2. For column size. 3. For door and window openings. 19.Is the floor clen before starting line out of masonry. 20.First layer checked with beam top/beam edge,offset,plumb and line. 21.Erection of door and window frame with necessary no. of holdfast. 22.Painting to door and window frame with one coat of primer (Anti-Termite paint) 23.Alignment of door and window frames for plumb/bend/level. 24.Verticalitiy of walls and corners. 25.Thickness of joints.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO. 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: nitinpatil22.2010@rediffmail.com
Subject: 10879-05

Company Name S. S. Developers & Builders
Project Name & Site Address winter training,s,s.developers,tarabai park ,karandi mala
Students Name (Surname_First Name_Middle Name) Patil Nitin Dilip
Exam No. 10879
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1)Observing the Brick Construction 2)Observing the Row House Construction 3)Observing the Construction Material 4)noting the requirements of Beam Construction
Details of how you Planned & Executed the allotted work First we decided to go last floor to see the brick work. Then we Observe the brick sizes.We saw types of brick & brick quality
Details of the Construction Procedure / Activity / Technology learned today 1.How the construction of wall 2.method of checking the material which comes on the site
Details of the Construction Materials learned today 1.Gokak Sand 2.Bricks type-1.6\" 2.4\" 3.Putte
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1.Solar Panel 2.Garden 3.Rain Water,harvesting
Details of the Construction / Engineering Drawings observed today 1.we observed the Working Drawings 2.we observed the Parking drawings
Details of the Bye Laws referred today 1.Row houses-Bathroom size-1.5M x 3M Door size-2.1m x 0.78m
Details of any Managerial Skill learned today 1.how the checking the material on site 2.how to know solving the problem on site,workers
RATE ANALYSIS (Detailed Stepwise Calculations required) 1brick area = 9\" x 4\" = 23294.34mm2 Total no. brick for 1brass=399no+5%wastage Proportion=1:22 1cu.m=1.52 cement=1.52/1+22=0.067 no.of bags=0.067/0.035=2no 2x260=520 Sand=0.152x22=3.34 3.34x725=2424.4Rs Labour=125+200+80=405Rs total cost=3350Rs for 1cu.m=295no x 6=1770Rs Total cost=1770+3350=5125Rs
Result of RATE ANALYSIS ( Rs per Unit ) 5125Rs
Todays BUZZ Word Bum works 1.Extratop=20mm-2no 2.Top Bar=20mm-2no 3.Bottom=16mm-dia-2no 4.Covering=30mm 5.Strirrups=8mm 6.Spacing bet stirrups=6\",5\",4\",3\" 7.Length of beam=4.20m 8.Width of beam=0.23m 9.ht of beam=0.153m 10.Material for beam 11.Proportion 1:1.5:3 12.Cement=53grade 13.Admix-50ml-1bag 14.Stirrup no =36 15.Removal of formwork=15days 16.Curing-14days 17.Plaster of beam 18.1st coat material=6mm thick 19.Final cot-3mm 20.First coat-1:4.5 21.Final coat-1:2.5 22.Curing-7 days 23.Binding-1kg 24.kartal 25.bar cost
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Ketan Charaple 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-05

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Tambe Trusha Sitaram
Exam No. 10902
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge supervision of prepairing concrete. .
Details of how you Planned & Executed the allotted work first we checked all the material i.e sand,aggregate,cement,water is available of exact size & quality.then we observed that how much quantity they are to be added for making the concrete. .
Details of the Construction Procedure / Activity / Technology learned today today we observed the procedure of making concrete which is used here for the slab.concrete here is prepared by mixing cement,sand,aggregate & water in suitable proportion & also small amount of plasticizer is added to get the proper workability of concrete.aggregate & sand are first added in the weigh batcher & then it is added in mixer in which 1 bag of cement & small amount of plasticizer is added.& it is properly mixed & the concrete is prepared. .
Details of the Construction Materials learned today concrete- 1 bag cement ,measured quantity of sand ,aggregate & water. mixed until they give uniform colour. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today minimum use of water to prevent the wastage. .
Details of the Construction / Engineering Drawings observed today footing drawing of temple which is constructed on front of building with details . .
Details of the Bye Laws referred today the planning design &construction of any building shall be such as to ensure safty from fire.for that width of approch building is provided such that weight of up to 18 tonnes can take.also the open space shall be free of any construction .suitable exit are provided horizontally & vertically. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for 0.230 thk Brick Masonary 1:6 - 1 m3 ITEM QTY. UNIT RATE AMOUNT Brick 500 No\'s 3.6 1,800 Cement 1.5 Bags 260 390 Sand 0.35 M3 1150 403 Total 2,593 8% wastage 207.44 Total 2,800.40 Labour for masonary 370 Scaffolding charge 50 Curing 20 Total 3,220.4 23% Tax Overhead and Profit 740.692 Total 3,961.092 Say - 3,961/- M3 .
Result of RATE ANALYSIS ( Rs per Unit ) 3,961/- M3
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: suchitapatil5@gmail.com
Subject: 10898-05

Company Name Sanghavi Sons & Constructions
Project Name & Site Address suncity,near new palace,kolhapur
Students Name (Surname_First Name_Middle Name) Patil Suchita Tukaram
Exam No. 10898
Working Day No. 05
Date (DD/MM/YYYY) 13.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.30pm
Details of the Work Allotted to you today by the Site In-Charge 1. To see brickwork which is carried on D ROW BUNGLLOWS 2. Sewer line work in D wings. 3. Observe all the bunglows plumbing work.
Details of how you Planned & Executed the allotted work 1. To see the details of the brickwork, we saw the site together. 2. Laying of sewer pipe line behind bunglows.
Details of the Construction Procedure / Activity / Technology learned today A. BRICKWORK ; 1. Preparation of mortar [1;6] 2. Bricks soaked in water before use because it do not absorb water from mortar. 3. Spread mortar of depth 10mm firstly on a surface then construct corners of the wall fixed in mortar. 4. check the level and alingment. 5. All the work is carried out by line dori method and no skilled labours are required also joints should be cleaned and finished after work every day. B. SEWER LINE ; 1. Excavation is done for placing of septic tank also for laying of pipe line with propetr fixity [ r.c.c. cement 6\"] to the septic tank. 2. From septic tank connection is connected to waste water treatment plant. 3. Water is treated and reused for gardening purpose only.
Details of the Construction Materials learned today Granite, conventional bricks. r.c.c cement pipes,cement blocks.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Waste water treatment plant ; Here all the waste water is treated and reused.
Details of the Construction / Engineering Drawings observed today Plumbing drawings,drainage drawings.
Details of the Bye Laws referred today Parking height 2.4m.
Details of any Managerial Skill learned today To check the work done by labour and corrected if there are any mistakes.
RATE ANALYSIS (Detailed Stepwise Calculations required) BRICKWORK [1;6] ; PER SQ.M Sand = 475.2 Rs Cement = 367.20 Rs Brick = 2520.00 Rs total = 3363.00 Rs + labour cost = 3631.00 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 3631.00 Rs per sq.m
Todays BUZZ Word CHECKLIST for furniture work ; 1. tiles provided not cmpletely to kitchen otta. 2. sink ipe. 3. chimney 4. ht. of the exhaust. 5. replacement of w.c. pan. 6. door bathroom fastenings. 7. ht.of the bath cock. 8. placement of all switch board. 9. ht.of switch board. 10. ht.of the kitchen otta. 11. sizes of dining table. 12. ceiling ht. of the window. 13. clear openings of the main door. 14. privacy maintained. 15. position of baths. 16. M.B.width. 17. master bed room sizes. 18. sizes of the bath. 19. dressing table sizes. 20. space for cylinder. 21. maintainance of work. 22. wastage of material. 23. no. of switch boards are more than sufficient. 24. position of rooms in A3 bunglows. 25. width of all furniture. 9. 5.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pritam Patil, Mo.no.9890997979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: buntyphonde@gmail.com
Subject: 10899-05

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Phonde Pravin Tukaram
Exam No. 10899
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge supervision of prepairing concrete. .
Details of how you Planned & Executed the allotted work first we checked all the material i.e sand,aggregate,cement,water is available of exact size & quality.then we observed that how much quantity they are to be added for making the concrete. .
Details of the Construction Procedure / Activity / Technology learned today today we observed the procedure of making concrete which is used here for the slab.concrete here is prepared by mixing cement,sand,aggregate & water in suitable proportion & also small amount of plasticizer is added to get the proper workability of concrete.aggregate & sand are first added in the weigh batcher & then it is added in mixer in which 1 bag of cement & small amount of plasticizer is added.& it is properly mixed & the concrete is prepared. .
Details of the Construction Materials learned today concrete- 1 bag cement ,measured quantity of sand ,aggregate & water. mixed until they give uniform colour. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today minimum use of water to prevent the wastage. .
Details of the Construction / Engineering Drawings observed today footing drawing of temple which is constructed on front of building with details . .
Details of the Bye Laws referred today the planning design &construction of any building shall be such as to ensure safty from fire.for that width of approch building is provided such that weight of up to 18 tonnes can take.also the open space shall be free of any construction .suitable exit are provided horizontally & vertically. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for 0.230 thk Brick Masonary 1:6 - 1 m3 ITEM QTY. UNIT RATE AMOUNT Brick 500 No\'s 3.6 1,800 Cement 1.5 Bags 260 390 Sand 0.35 M3 1150 403 Total 2,593 8% wastage 207.44 Total 2,800.40 Labour for masonary 370 Scaffolding charge 50 Curing 20 Total 3,220.4 23% Tax Overhead and Profit 740.692 Total 3,961.092 Say - 3,961/- M3 .
Result of RATE ANALYSIS ( Rs per Unit ) 3,961/- M3
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-05

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Abhishek Dadasaheb
Exam No. 10895
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge supervision of prepairing concrete. .
Details of how you Planned & Executed the allotted work first we checked all the material i.e sand,aggregate,cement,water is available of exact size & quality.then we observed that how much quantity they are to be added for making the concrete. .
Details of the Construction Procedure / Activity / Technology learned today today we observed the procedure of making concrete which is used here for the slab.concrete here is prepared by mixing cement,sand,aggregate & water in suitable proportion & also small amount of plasticizer is added to get the proper workability of concrete.aggregate & sand are first added in the weigh batcher & then it is added in mixer in which 1 bag of cement & small amount of plasticizer is added.& it is properly mixed & the concrete is prepared. .
Details of the Construction Materials learned today concrete- 1 bag cement ,measured quantity of sand ,aggregate & water. mixed until they give uniform colour. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today minimum use of water to prevent the wastage. .
Details of the Construction / Engineering Drawings observed today footing drawing of temple which is constructed on front of building with details . .
Details of the Bye Laws referred today the planning design &construction of any building shall be such as to ensure safty from fire.for that width of approch building is provided such that weight of up to 18 tonnes can take.also the open space shall be free of any construction .suitable exit are provided horizontally & vertically. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for 0.230 thk Brick Masonary 1:6 - 1 m3 ITEM QTY. UNIT RATE AMOUNT Brick 500 No\'s 3.6 1,800 Cement 1.5 Bags 260 390 Sand 0.35 M3 1150 403 Total 2,593 8% wastage 207.44 Total 2,800.40 Labour for masonary 370 Scaffolding charge 50 Curing 20 Total 3,220.4 23% Tax Overhead and Profit 740.692 Total 3,961.092 Say - 3,961/- M3 .
Result of RATE ANALYSIS ( Rs per Unit ) 3,961/- M3
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-03

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.water tank rajendra nagar
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 03
Date (DD/MM/YYYY) 10/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge Painting
Details of how you Planned & Executed the allotted work We observed > that painting work done by the workers.They use the rollers so that it will > get smooth finish is less time and use rollers is less lavorious. > *Details of the Construction Procedure / Activity / Technology learned > today:* Tube levelling & shuttering have to pack & open the shuttering > work.
Details of the Construction Procedure / Activity / Technology learned today Tube levelling & shuttering have to pack & open the shuttering > work.
Details of the Construction Materials learned today Oil paint,oil bond,putty(They have used the company sunlight)
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no
Details of the Construction / Engineering Drawings observed today Rcc beams & columns
Details of the Bye Laws referred today Internal room stress. Bathroom,toiletsliving room,bedroom,kitchen
Details of any Managerial Skill learned today no
RATE ANALYSIS (Detailed Stepwise Calculations required) for Rcc beam for 1m3 > For 1m3 Rcc cost =3300rs/1m3 > Labour cost for 1ft3 of Rcc beam=35rs > For 1m3=35*35.28=1235rs/1m3 > Total cost=3300+1235=4535 > Add 5% wastage = 227rs > =4762 rs > Using 75 kg steel bar =2775 > =7537 rs > Add 20% contractor’s profit =1507 > =9044 rs/1m3 beam
Result of RATE ANALYSIS ( Rs per Unit ) 9044 rs/1m3 beam
Todays BUZZ Word Different type of Contractors in detail required their > scope > small scale and large scale > -small scale works and handle by an individual contractor > -but for the large scale work are no of people working on it and it for the > team & it’s team. > Distribute the day to day work and give the direction to the work on site > as well asthey maintain the office works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish mestri 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-05

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Sawant Amit Ganpat
Exam No. 10900
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge supervision of prepairing concrete. .
Details of how you Planned & Executed the allotted work first we checked all the material i.e sand,aggregate,cement,water is available of exact size & quality.then we observed that how much quantity they are to be added for making the concrete. .
Details of the Construction Procedure / Activity / Technology learned today today we observed the procedure of making concrete which is used here for the slab.concrete here is prepared by mixing cement,sand,aggregate & water in suitable proportion & also small amount of plasticizer is added to get the proper workability of concrete.aggregate & sand are first added in the weigh batcher & then it is added in mixer in which 1 bag of cement & small amount of plasticizer is added.& it is properly mixed & the concrete is prepared. .
Details of the Construction Materials learned today concrete- 1 bag cement ,measured quantity of sand ,aggregate & water. mixed until they give uniform colour. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today minimum use of water to prevent the wastage. .
Details of the Construction / Engineering Drawings observed today footing drawing of temple which is constructed on front of building with details . .
Details of the Bye Laws referred today the planning design &construction of any building shall be such as to ensure safty from fire.for that width of approch building is provided such that weight of up to 18 tonnes can take.also the open space shall be free of any construction .suitable exit are provided horizontally & vertically. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for 0.230 thk Brick Masonary 1:6 - 1 m3 ITEM QTY. UNIT RATE AMOUNT Brick 500 No\'s 3.6 1,800 Cement 1.5 Bags 260 390 Sand 0.35 M3 1150 403 Total 2,593 8% wastage 207.44 Total 2,800.40 Labour for masonary 370 Scaffolding charge 50 Curing 20 Total 3,220.4 23% Tax Overhead and Profit 740.692 Total 3,961.092 Say - 3,961/- M3 .
Result of RATE ANALYSIS ( Rs per Unit ) 3,961/- M3 .
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521-05

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders, Near Jayprabha studio,Kolhapur
Students Name (Surname_First Name_Middle Name) bagmare dinesh shriram
Exam No. 13521
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To see the curing of slab. 2. To see the column reinforcement for second floor. 3. To see the slab centering work for third floor.
Details of how you Planned & Executed the allotted work We saw the curing of slab that was casted two days before. The slab had attained sufficient firmness. For curing, ponds were made, and water was continously sprinkled on slab for 3-4 times a day.
Details of the Construction Procedure / Activity / Technology learned today We saw the laying of column reinforcement for second floor. The bars were reduced in size from 1200 mm to 80 mm. We saw the slab centering work going on for third floor. We also saw the construction of formwork for the next flight from second floor to third floor. We saw how the labourers check the level by water pipes by holding them at two points and see their levels, this is the new technique we learnt. Details of the Construction Materials learned today: Column reinforcement- Tor steel bars 20mm, stirrups. Formwork and other materials for staircase.
Details of the Construction Materials learned today No such Technology was adopted today.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such Technology was adopted today.
Details of the Construction / Engineering Drawings observed today 1. Plan for centering work for third floor. 2. Plan for third floor.
Details of the Bye Laws referred today 1. According to bye-laws cantilever beams should be placed at L/2 distance. 2. According to bye-laws maximum length of cantilever beam is 4m. On site it is provided 2m. 3.According to bye laws, minimum head requirement for garage is 2.4m. On site it is provided 3.8m. 5.According to bye laws, maximum height of riser is 190 mm. On site it is provided 160 mm. 7.According to bye laws,minimum width of treads is 250 mm. On site it is provided 300 mm.
Details of any Managerial Skill learned today 1. The site incharge saw whether curing was done properly or not. 2. He saw the Slab centering work. 3. He suggested the labour to make changes wherever needed
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for \"Brick work\" Rate analysis for 6\" bricks. No. of bricks required for per sq.m- 50 Cost per brick= Rs.4. For 50 bricks cost= Rs.200. Proportion = 1:4 For 1 sq.m = 0.22 cement required. Cost of cement= Rs. 265. Total cement cost=265*0.22= Rs.58.30. Cost of sand= Rs.1060. Total cost of sand per sq.m= 1060*0.15= Rs.159. Total cost=200+58.30+159=Rs. 417. Labour cost= 20%= Rs.83.4. Total cost=417+83.4=Rs.500.4. With 10% profit=Rs.550.4 Total cost of brick work for 6\" bricks = Rs.550.4 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.550.4 per sq.m for 6\" bricks.
Todays BUZZ Word \"CHECK-LIST\" 1.Slab centering checked with architectural drawing. 1. For elevation. 2. For room dimension. 3. For electric points. 2. Slab centering checked completely. 1. For required beam depth/ slab thickness. 2. For required head rooms. 3. For other points. 3.Slab centering checked completely. 1. Level checked/ Line checked. 2. Column centering checked / modified. 3. Oiling to beams/ slab shuttering. 4. Centering for stair-case checked. 5. Changes for amenities if any checked. 6. Reinforcement checked for beams and slabs as per R.C.C drawings. 7. Proper cover for bottom /side checked for beams. 8. Proper number of chairs provided for slab. 9. Proper cover bottom/top checked for slab/fan hook checked. 10.Reduction of columns as per drawing done for above slab. 11.Hidden beams/Cantilever beams/inverted beams checked if any. 12.Pardi bars left for balconies etc. 13.Proper cover bottom side/checked for all. 14.Dowels (any required ) are left. 15.R.C.C work centering checked for with architectural drawings. 1. For elevation. 2. For cenetring plan. 3. For electrical points. 4. For required size of beam /footings/slabs etc. 5. For other points. 16.Reinforcement checked as per R.C.C drwaings. 1. For beams. 2. For columns. 3. For pardhi. 4. For waist slab. 5. For other items. 17.B.B masonry work checked with architectural drawing. 1. For elevation. 2. For room dimension. 3. For openings. 18.B.B. masonry checked. 1. For beam size. 2. For column size. 3. For door and window openings. 19.Is the floor clen before starting line out of masonry. 20.First layer checked with beam top/beam edge,offset,plumb and line. 21.Erection of door and window frame with necessary no. of holdfast. 22.Painting to door and window frame with one coat of primer (Anti-Termite paint) 23.Alignment of door and window frames for plumb/bend/level. 24.Verticalitiy of walls and corners. 25.Thickness of joints.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO. 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: shindeamol5255@yahoo.in
Subject: 13546-05

Company Name Deshmukh Developers
Project Name & Site Address Goldenshelter
Students Name (Surname_First Name_Middle Name) Shinde Amol Jagannath
Exam No. 13546
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To see a brick work which is going on d8 bungalo alo sewer line laying observed. .
Details of how you Planned & Executed the allotted work First we go on side & planed to placing brick according to building line plan which is give us the site incharge.then started the work step by step,alo planed about sewer pipe line in d wing.
Details of the Construction Procedure / Activity / Technology learned today First morter is prepared for brickwork in proportion 1:6 All the brick are soaked in water so they not absorbed morter water Then marked line which on brick on laying Then morter are spred on this surface in 1 cm layer. Then side corner brick are fixed & line strip are stretched with two corner brickthen middle brick are placed along the line Also check by plumbob *for sewer lin First escavation is done on earth surface with maintain the slop of line & laid concret pipe in it with proper fixing is kept One end of sewer are conectcd to septic tank another is connected to wast water treatment plant & this water reused for gardening puporse. .
Details of the Construction Materials learned today *R C C pipe (dia 150mm) *brick(19*9*9cm) *cement concret block-(16\"*7.5\"*6\")
Details of Environment Caring Technology / Methodology / Procedure / Product learned today mortar fallen during plastering work if collected on plastic sheet then reused within 30 minitus , it will save the material & there by saving natural materiel. .
Details of the Construction / Engineering Drawings observed today Plumbing layout drawing(drainage line) .
Details of the Bye Laws referred today Parking height2.4m provided according to bylaws. .
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge bhosale .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: shindeamol5255@yahoo.in
Subject: 13546-05

Company Name Deshmukh Developers
Project Name & Site Address Goldenshelter
Students Name (Surname_First Name_Middle Name) Shinde Amol Jagannath
Exam No. 13546
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To see a brick work which is going on d8 bungalo alo sewer line laying observed. .
Details of how you Planned & Executed the allotted work First we go on side & planed to placing brick according to building line plan which is give us the site incharge.then started the work step by step,alo planed about sewer pipe line in d wing.
Details of the Construction Procedure / Activity / Technology learned today First morter is prepared for brickwork in proportion 1:6 All the brick are soaked in water so they not absorbed morter water Then marked line which on brick on laying Then morter are spred on this surface in 1 cm layer. Then side corner brick are fixed & line strip are stretched with two corner brickthen middle brick are placed along the line Also check by plumbob *for sewer lin First escavation is done on earth surface with maintain the slop of line & laid concret pipe in it with proper fixing is kept One end of sewer are conectcd to septic tank another is connected to wast water treatment plant & this water reused for gardening puporse. .
Details of the Construction Materials learned today *R C C pipe (dia 150mm) *brick(19*9*9cm) *cement concret block-(16\"*7.5\"*6\")
Details of Environment Caring Technology / Methodology / Procedure / Product learned today mortar fallen during plastering work if collected on plastic sheet then reused within 30 minitus , it will save the material & there by saving natural materiel. .
Details of the Construction / Engineering Drawings observed today Plumbing layout drawing(drainage line) .
Details of the Bye Laws referred today Parking height2.4m provided according to bylaws. .
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge bhosale .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-05

Company Name Star Tech Infra
Project Name & Site Address star aashiyana, rajendranagar.
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 8.50am
Site Leaving Time (HH:MM am/pm) 4.15
Details of the Work Allotted to you today by the Site In-Charge To see plasterig, & count bricks in 1 cu.m., see near by construction of bunglow
Details of how you Planned & Executed the allotted work we observe process of plastering count bricks in 1 cu. m. {40 bricks} see near by construction.
Details of the Construction Procedure / Activity / Technology learned today plastering, brickwork, pop.
Details of the Construction Materials learned today mortor for plastering & brickwork. lambi for pop.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no.
Details of the Construction / Engineering Drawings observed today municipal drawing.
Details of the Bye Laws referred today bye for building specification.
Details of any Managerial Skill learned today handeling workers.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE FOR 1sq.m. BRICK MASONRY BRICK SIZE; L=.230m, W=.150m, H=.075m for 1cu.m. quantity; 1.25 bag cement*250 Rs=312.5Rs 0.35cu.m.sand*1411Rs.=493.85Rs 550 bricks*3.5Rs=1925Rs Material cost=2731.35Rs. 3%wastege=81.93Rs Total cost=2813.28Rs But 1cu.m.=1/.230=4.34sq.m.*10.76=46.78s.q.ft. labour cost=47*5=235Rs total=3048.28 so; 1sq.m. brick work=3048.28/47=64.85*10.76=697.86=700Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 700/sq.m.
Todays BUZZ Word CHECK LIST 1.line out 2.foundation 3.plinth 4.plinth beam 5.column 6.slab 7.beam 8.UCR masonry 9.brick masonry 10.plaster 11.plumbing 12.electrification 13.colouring 14.flooring 15.door 16.window 17.stair 18.steel in column 19.steel in beam 20.steel in slab 21.earthing.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? Yes
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish mestri. 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-05

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Sharad Shankarrao
Exam No. 10897
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge supervision of prepairing concrete. .
Details of how you Planned & Executed the allotted work first we checked all the material i.e sand,aggregate,cement,water is available of exact size & quality.then we observed that how much quantity they are to be added for making the concrete. .
Details of the Construction Procedure / Activity / Technology learned today today we observed the procedure of making concrete which is used here for the slab.concrete here is prepared by mixing cement,sand,aggregate & water in suitable proportion & also small amount of plasticizer is added to get the proper workability of concrete.aggregate & sand are first added in the weigh batcher & then it is added in mixer in which 1 bag of cement & small amount of plasticizer is added.& it is properly mixed & the concrete is prepared. .
Details of the Construction Materials learned today concrete- 1 bag cement ,measured quantity of sand ,aggregate & water. mixed until they give uniform colour. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today minimum use of water to prevent the wastage. .
Details of the Construction / Engineering Drawings observed today footing drawing of temple which is constructed on front of building with details . .
Details of the Bye Laws referred today the planning design &construction of any building shall be such as to ensure safty from fire.for that width of approch building is provided such that weight of up to 18 tonnes can take.also the open space shall be free of any construction .suitable exit are provided horizontally & vertically.
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for 0.230 thk Brick Masonary 1:6 - 1 m3 ITEM QTY. UNIT RATE AMOUNT Brick 500 No\'s 3.6 1,800 Cement 1.5 Bags 260 390 Sand 0.35 M3 1150 403 Total 2,593 8% wastage 207.44 Total 2,800.40 Labour for masonary 370 Scaffolding charge 50 Curing 20 Total 3,220.4 23% Tax Overhead and Profit 740.692 Total 3,961.092 Say - 3,961/- M3 .
Result of RATE ANALYSIS ( Rs per Unit ) 3,961/- M3
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-05

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage sardar park kolhapur
Students Name (Surname_First Name_Middle Name) babar moreshwar mahipati
Exam No. 10873
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the placing of reinforcement for staircase, marking of rise and tread as per drawings and details on the side shuttering with the help of level tube.
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions of rise tread and level of the rise and tread with reference to details given to us and then we marked the rise and tread
Details of the Construction Procedure / Activity / Technology learned today Fixing bottom of the beams supported with timber supports, placing reinforcement bars for staircase and marking of rise and tread on the side shuttering.
Details of the Construction Materials learned today Non-teak wood battens of 3”size and 12mm plywood of unix company having rate of 55/- per sq ft
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material is used on the site till now.
Details of the Construction / Engineering Drawings observed today Detail drawing of beams, staircase
Details of the Bye Laws referred today Ceiling height from floor level is 3.0m. As per bye law it is minimum 2.75m.
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS (Detailed Stepwise Calculations required): “Quantity calculation for B.B.M wall 1.53*1.83*0.23 with cement mortar of 1:6“ 1. volume of BBM wall of concrete=0.64cu.m. 2. Quantity of cement mortar= take 35% of volume of BBM. =0.224cu.m. 3. Quantity of cement (volume of 1part of cement)=0.224/1+6 =0.032 cu.m. =1 bag 4. Quantity of sand for 6 parts =0.224*6 cu.m. =1.344cu.m. 5. Number of bricks =500*0.64 =320nos…….(500 nos for10 cu.m) “Rate Analysis for BBM wall with cement mortar1:6” (Considering local rates of material) 1. Cost of cement=1*250=250/-………..(250/- per bag) 2. Cost of sand=1.344*1600=2134/-…………(1600/- per cu.m.) 3. Cost of bricks=320*4=1280/-…………(4/- per brick.) 4. Labour charges=1130/- 7. Total cost= 4794/- 8.10% profit of total cost for the contractor=479.4/- 9. Total cost=5273/- 10. Rate per cu.m.= 8240/-
Result of RATE ANALYSIS ( Rs per Unit ) : 8240/-
Todays BUZZ Word Todays BUZZ Word: “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-05

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Tekwani Sagar Bansilal
Exam No. 10903
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To see the curing of slab. 2. To see the column reinforcement for second floor. 3. To see the slab centering work for third floor.
Details of how you Planned & Executed the allotted work We saw the curing of slab that was casted two days before. The slab had attained sufficient firmness. For curing, ponds were made, and water was continously sprinkled on slab for 3-4 times a day.
Details of the Construction Procedure / Activity / Technology learned today We saw the laying of column reinforcement for second floor. The bars were reduced in size from 1200 mm to 80 mm. We saw the slab centering work going on for third floor. We also saw the construction of formwork for the next flight from second floor to third floor. We saw how the labourers check the level by water pipes by holding them at two points and see their levels, this is the new technique we learnt.
Details of the Construction Materials learned today Column reinforcement- Tor steel bars 20mm, stirrups. Formwork and other materials for staircase.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today 1. Plan for centering work for third floor. 2. Plan for third floor.
Details of the Bye Laws referred today 1. According to bye-laws cantilever beams should be placed at L/2 distance. 2. According to bye-laws maximum length of cantilever beam is 4m. On site it is provided 2m. 3.According to bye laws, minimum head requirement for garage is 2.4m. On site it is provided 3.8m. 5.According to bye laws, maximum height of riser is 190 mm. On site it is provided 160 mm. 7.According to bye laws,minimum width of treads is 250 mm. On site it is provided 300 mm.
Details of any Managerial Skill learned today 1. The site incharge saw whether curing was done properly or not. 2. He saw the Slab centering work. 3. He suggested the labour to make changes wherever needed
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for \"Brick work\" Rate analysis for 6\" bricks. No. of bricks required for per sq.m- 50 Cost per brick= Rs.4. For 50 bricks cost= Rs.200. Proportion = 1:4 For 1 sq.m = 0.22 cement required. Cost of cement= Rs. 265. Total cement cost=265*0.22= Rs.58.30. Cost of sand= Rs.1060. Total cost of sand per sq.m= 1060*0.15= Rs.159. Total cost=200+58.30+159=Rs. 417. Labour cost= 20%= Rs.83.4. Total cost=417+83.4=Rs.500.4. With 10% profit=Rs.550.4 Total cost of brick work for 6\" bricks = Rs.550.4 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.550.4 per sq.m for 6\" bricks.
Todays BUZZ Word \"CHECK-LIST\" 1.Slab centering checked with architectural drawing. 1. For elevation. 2. For room dimension. 3. For electric points. 2. Slab centering checked completely. 1. For required beam depth/ slab thickness. 2. For required head rooms. 3. For other points. 3.Slab centering checked completely. 1. Level checked/ Line checked. 2. Column centering checked / modified. 3. Oiling to beams/ slab shuttering. 4. Centering for stair-case checked. 5. Changes for amenities if any checked. 6. Reinforcement checked for beams and slabs as per R.C.C drawings. 7. Proper cover for bottom /side checked for beams. 8. Proper number of chairs provided for slab. 9. Proper cover bottom/top checked for slab/fan hook checked. 10.Reduction of columns as per drawing done for above slab. 11.Hidden beams/Cantilever beams/inverted beams checked if any. 12.Pardi bars left for balconies etc. 13.Proper cover bottom side/checked for all. 14.Dowels (any required ) are left. 15.R.C.C work centering checked for with architectural drawings. 1. For elevation. 2. For cenetring plan. 3. For electrical points. 4. For required size of beam /footings/slabs etc. 5. For other points. 16.Reinforcement checked as per R.C.C drwaings. 1. For beams. 2. For columns. 3. For pardhi. 4. For waist slab. 5. For other items. 17.B.B masonry work checked with architectural drawing. 1. For elevation. 2. For room dimension. 3. For openings. 18.B.B. masonry checked. 1. For beam size. 2. For column size. 3. For door and window openings. 19.Is the floor clen before starting line out of masonry. 20.First layer checked with beam top/beam edge,offset,plumb and line. 21.Erection of door and window frame with necessary no. of holdfast. 22.Painting to door and window frame with one coat of primer (Anti-Termite paint) 23.Alignment of door and window frames for plumb/bend/level. 24.Verticalitiy of walls and corners. 25.Thickness of joints.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO. 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-05

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bhoite Vishal Rajaram
Exam No. 13555
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:50pm
Details of the Work Allotted to you today by the Site In-Charge Today we have seen construction procedure of Brick-Masonary and calculate the number of bricks required in wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today We have learnt various Bonds of bricks.
Details of the Construction Materials learned today - About brick masonary and preparing cement mortar as per proportion. - By using Plumb bob we check the line the of the wall.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plans of the floor.
Details of the Bye Laws referred today - None
Details of any Managerial Skill learned today - To convince the dealers regarding rates.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for 6\" bricks. No. of bricks required for per sq.m- 50 Cost per brick= Rs.4. For 50 bricks cost= Rs.200. Proportion = 1:4 For 1 sq.m = 0.22 cement required. Cost of cement= Rs. 265. Total cement cost=265*0.22= Rs.58.30. Cost of sand= Rs.1060. Total cost of sand per sq.m= 1060*0.15= Rs.159. Total cost=200+58.30+159=Rs. 417. Labour cost= 20%= Rs.83.4. Total cost=417+83.4=Rs.500.4. With 10% profit=Rs.550.4 Total cost of brick work for 6\" bricks = Rs.550.4 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.550.4 per sq.m for 6\" bricks.
Todays BUZZ Word Description Of Work----(Yes/No) 1. Is all the materials checked? 2. Is there any defect in tiles / stones received? 3. Are the rooms cleaned before tiling? 4. Is the skirting gap sufficient? 5. Is the lime mortar fresh & properly mixxed in mixtures? 6. Are Thiyyas Taken before Machan work? 7. Is right angle set before starting tiling? 8. Are level lines are marked on the walls of flat? 9. Are tile joints filled with matching colour cement slurry? 10. Is the skirting Farma used before fixing skirting? 11. Are all the cut-pieces made with help of cutting machine? 12. Is there sufficient stock of 12 mm thick skirting for fixing near RCC column? 13. Are new polishing stones used for polishing? 14. Is proper Curing for three days done to the grouting coat? 15. Are all polishing coats properly executed? 16. Is oxalic acid in powder form used for acid form? 17. Is the balcony flooring given sufficient slope towards spout? 18. Is all G.I., P.V.C. conduiting completed before glazed tile fixing? 19. Is the tile taken on the opening side of the door fro WC floor? 20. Are the edges of kitchen otta & sill rounded? 21. Are the slopes of kitchen platform top & sink proper? 22. Is the WC / Bath floor slope in proper direction? 23. Is the oil paint applied to kitchen platform & sill? 24. Are umbra pattis fixed wherever required? 25. Is the cleaning properly done?
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-05

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bauchakar Deepak Yuvraj
Exam No. 13553
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:50pm
Details of the Work Allotted to you today by the Site In-Charge Today we have seen construction procedure of Brick-Masonary and calculate the number of bricks required in wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today We have learnt various Bonds of bricks.
Details of the Construction Materials learned today - About brick masonary and preparing cement mortar as per proportion. - By using Plumb bob we check the line the of the wall.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plans of the floor.
Details of the Bye Laws referred today - None
Details of any Managerial Skill learned today - To convince the dealers regarding rates.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for 6\" bricks. No. of bricks required for per sq.m- 50 Cost per brick= Rs.4. For 50 bricks cost= Rs.200. Proportion = 1:4 For 1 sq.m = 0.22 cement required. Cost of cement= Rs. 265. Total cement cost=265*0.22= Rs.58.30. Cost of sand= Rs.1060. Total cost of sand per sq.m= 1060*0.15= Rs.159. Total cost=200+58.30+159=Rs. 417. Labour cost= 20%= Rs.83.4. Total cost=417+83.4=Rs.500.4. With 10% profit=Rs.550.4 Total cost of brick work for 6\" bricks = Rs.550.4 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.550.4 per sq.m for 6\" bricks.
Todays BUZZ Word Description Of Work----(Yes/No) 1. Is all the materials checked? 2. Is there any defect in tiles / stones received? 3. Are the rooms cleaned before tiling? 4. Is the skirting gap sufficient? 5. Is the lime mortar fresh & properly mixxed in mixtures? 6. Are Thiyyas Taken before Machan work? 7. Is right angle set before starting tiling? 8. Are level lines are marked on the walls of flat? 9. Are tile joints filled with matching colour cement slurry? 10. Is the skirting Farma used before fixing skirting? 11. Are all the cut-pieces made with help of cutting machine? 12. Is there sufficient stock of 12 mm thick skirting for fixing near RCC column? 13. Are new polishing stones used for polishing? 14. Is proper Curing for three days done to the grouting coat? 15. Are all polishing coats properly executed? 16. Is oxalic acid in powder form used for acid form? 17. Is the balcony flooring given sufficient slope towards spout? 18. Is all G.I., P.V.C. conduiting completed before glazed tile fixing? 19. Is the tile taken on the opening side of the door fro WC floor? 20. Are the edges of kitchen otta & sill rounded? 21. Are the slopes of kitchen platform top & sink proper? 22. Is the WC / Bath floor slope in proper direction? 23. Is the oil paint applied to kitchen platform & sill? 24. Are umbra pattis fixed wherever required? 25. Is the cleaning properly done?
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-05

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Jadhav Swapnil Ashok
Exam No. 13529
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To check reinforcement of beam.
Details of how you Planned & Executed the allotted work 1. We had seen all r.c.c. drawings of beam. we check whether reinforcment is as per proportion or not.with checking of bars,curtailed bars,extra top, extra bottom with site incharge.
Details of the Construction Procedure / Activity / Technology learned today application of white plaster.
Details of the Construction Materials learned today none.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel plates instead of plywood in formwork. this is environment friendly.
Details of the Construction / Engineering Drawings observed today beam drawings.
Details of the Bye Laws referred today minimum stairs in a staircase-18
Details of any Managerial Skill learned today every work should be checked after it is completed and also during its work.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for brickwork: we used the proportion:1:6 assume 1 cu.m of wall construction. brick=1*500=500 no.=500*6.50=Rs.3250 30% mortar is required for cu.m of masonry. i.e.mortar volume for 1 cu.m=0.3 cu.m a) cement-(0.3/(1+6)=0.0428 cu.m no. of bags-(0.0428/0.035)=1.22 1.5 bags=1.5*260=Rs.390 b) sand-0.0428*6=0.2568=5000*0.0428=Rs.1284 total cost of material=Rs.4924 f) labour-mestri-Rs.250 mason-1 no.-Rs.190 Boy or woman-Rs.110*2no.=Rs.220 g) water-1.5%=(4924+660)*(1.5/100)=Rs.5584 contractor profit=total cost*profit(15% profit) =Rs.(5584+83.76)*1.15 =Rs.850.164 total amount=Rs.6517.92
Result of RATE ANALYSIS ( Rs per Unit ) Rs.6517.92
Todays BUZZ Word checklist for building exterior: 1. Is the approach road properly laid with proper tarring. 2. is the compound wall & gate work properly. 3. is the building painted from outside properly. 4. is the septic tank work complete. 5. is the flooring work in stilts complete. 6. are the letter boxes fixed with names of clients on it. 7. is the work of staircase completed in all respects. 8. is the pump room work completed in all respect. 9. the parking allotment done as per the approved plan. 10. are all common electrical switches & fittings working properly 11. is common TV antenna working properly. 12. is the garden work complete in all respect. 13. common toilet or washing place is provided or not. 14. society office or watchmens cabin is provided or not. 15. is the finishing in duct complete. 16. shoe to rainwater pipe is provided or not. 17. proper outlet to rainwater in duct is given or not. 18. transformer room or L.T.room etc. has been provided or not. 19. building no.& name has been painted or not. 20. are all lifts working properly. 21. are door closers for all lifts doors freely working. 22. is the collapsible type door provided for lift. 23. is the capicity board fixed in lift cabin. 24. are meters no.& flat owners names painted in meter cabinet. 25. is water meter fixed on municiple water line? initial reading.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-05

Company Name Deshmukh Developers
Project Name & Site Address Deshmukh Developments,Pratibha Nagar ,Kolhapur
Students Name (Surname_First Name_Middle Name) Birajdar Minaxi Renuk
Exam No. 13556
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today we are observe Storage Of Plumbing Materials : 1) Plumbing Materials are stored in a seperate store room 2) PVC pipes, CPVC pipes, are stored in it 3) Rain Water Harvesting pipes of diameter 150mm are also stored in it
Details of how you Planned & Executed the allotted work Firstly we are all groupmates go to that store room : 1) To observe the different sections of pipes 2) Different shape Y-shaped,L-shaped pipe fittings are stored in it 3) And also Insulation pipes for solar,Aluminium plates for windows are stored in it
Details of the Construction Procedure / Activity / Technology learned today Construction Procedure : 1) All materials are stored in a systematic manner 2) PVC pipes are stored in a one corner 3) In another corner Insulation pipes are stored 4) Small shaped Y-section, L-section pipe fittings are stored in a cement size bags 5) Aluminium Plates are placed horizontally on floor to avoid vertical slidung
Details of the Construction Materials learned today The Construction materials learned toady are as follows : 1) PVC pipes of diameter-4\", fittings size-1.5\" 2) Flow Guard 3) Rubber lubricant 4) Shower arm, Pillar cock, Angle Cock, Bottle trap
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environment Caring Technology : To use Admixtures in cement concrete to maintain water cement ratio. Since the wastage of water is minimised.And to increase strength of concrete.
Details of the Construction / Engineering Drawings observed today Today we observe Plumbing Drawing : 1) The section is goes through bate room 2) So we are get all information about height of door-2.1, height of wash basin-0.8, position of W.C provided 0.25*0.25 side sizes, position of door, ventilater 3) All above things we are observe in Plumbing Drawing
Details of the Bye Laws referred today We are referred Bye Laws today for : 1) Height of ventilation in toilets 2) Height of door 3) Height of wash basin 4) Minimum size required for attached toilets
Details of any Managerial Skill learned today Managerial Skill Learned today is : Plumbing Materials i.e pipes, plates, fittings,rubber lubricants are placed in a systematic manner which are found to the workers very easily.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BRICKWORK : Proportion 1:6- 9\" mm thick wall Assume 1m3 of wall construction BRICK = 1* 500 = 500 NUMBER = 4.5* 500= 2250 Rs 30% mortor is requied for m3 of brick masonry i.e mortor volume for 1 m3 =0.3 m3 CEMENT = 0.3/ (1+6) = 0.0428 M3 NUMBER OF BAGS = 0.0428/0.035 = 1.22= 1.5 bags =1.58*260 = 390 Rs SAND = 0.0428*6 = 0.2568 M3 = 0.2568*1125 = 288.90 Rs LABOUR NUMBER RATE/UNIT HEAD MASAN = 1/2 =250= 125 Rs MASON = 1 =175= 175 Rs UNSKILLED LABOUR =2=120= 240 Rs TOTAL = 540 Rs SCAFFOLDING : LUMP SUMP= 60 Rs TOTAL COST = 2928.90+540+60= 3528.60 Rs WATER1 1 1/2 % = (1.5*3528.90)/100= 52.93 Rs CONTRACTOR PROFIT 15% = (15* 3528.90) /100= 529.33 Rs TOTAL AMOUNT = 4111.16 RS
Result of RATE ANALYSIS ( Rs per Unit ) 4111.16 RS
Todays BUZZ Word BUZZ WORD IS ABOUT \"CHECK LIST\" 1) Is the floor in proper level ? 2) Is the floor and skirting properly polished and cleaned ? 3) Is the skirting in one line and at right angles ? 4) Are the flooring tiles of one type ? 5) Is the mosaic tile in the room continued up to outer edge of main door frame ? 6) Is the butt properly finished ? 7) Is the skirting & butt properly in line level ? 8) Are cracked tiles in flooring removed & replaced ? 9) Are all glazed tile dado in right angle & level ? 10) Are all glazed tiles fixed of uniform coiour & design ? 11) Are jams of windows prperly finished with glazed tile ? 12) Are you sure that there is not a single cracked tile in dado ? 13) Are the glazed tiles around W.C pan properly fixed ? 14) Are sure that no water accumulates on flooring of W.C ? 15) Is proper slope given to bathroom ? 16) Is the balcony floor level half tile down than room floor ? 17) Is the length of pipe floor wise correct ? 18) Is the kitchen pllatform leakage proof ? 19) Is the proper slope given to kitchen platform top ? 20) Is the kitchen platform finished prperly ? 21) Is the any threshold fixed to bath & w.c ? 22) Is edge polishing & rounding done ? 23) Is the tilling below kitchen otta raised by half tile thickness than floor level? 24) Is the door sill fixed for w.c /bath & main door ? 25) Is the space for gas cylinder ok to put cylinder freely ? 24)
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Abhijit Bhosale Mob No.9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-05

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Jadhav Nilam Jaywant
Exam No. 13528
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To check reinforcement of beam.
Details of how you Planned & Executed the allotted work 1. We had seen all r.c.c. drawings of beam. we check whether reinforcment is as per proportion or not.with checking of bars,curtailed bars,extra top, extra bottom with site incharge.
Details of the Construction Procedure / Activity / Technology learned today application of white plaster.
Details of the Construction Materials learned today none.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel plates instead of plywood in formwork. this is environment friendly.
Details of the Construction / Engineering Drawings observed today beam drawings.
Details of the Bye Laws referred today minimum stairs in a staircase-18
Details of any Managerial Skill learned today every work should be checked after it is completed and also during its work.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for brickwork: we used the proportion:1:6 assume 1 cu.m of wall construction. brick=1*500=500 no.=500*6.50=Rs.3250 30% mortar is required for cu.m of masonry. i.e.mortar volume for 1 cu.m=0.3 cu.m a) cement-(0.3/(1+6)=0.0428 cu.m no. of bags-(0.0428/0.035)=1.22 1.5 bags=1.5*260=Rs.390 b) sand-0.0428*6=0.2568=5000*0.0428=Rs.1284 total cost of material=Rs.4924 f) labour-mestri-Rs.250 mason-1 no.-Rs.190 Boy or woman-Rs.110*2no.=Rs.220 g) water-1.5%=(4924+660)*(1.5/100)=Rs.5584 contractor profit=total cost*profit(15% profit) =Rs.(5584+83.76)*1.15 =Rs.850.164 total amount=Rs.6517.92
Result of RATE ANALYSIS ( Rs per Unit ) Rs.6517.92
Todays BUZZ Word checklist for building exterior: 1. Is the approach road properly laid with proper tarring. 2. is the compound wall & gate work properly. 3. is the building painted from outside properly. 4. is the septic tank work complete. 5. is the flooring work in stilts complete. 6. are the letter boxes fixed with names of clients on it. 7. is the work of staircase completed in all respects. 8. is the pump room work completed in all respect. 9. the parking allotment done as per the approved plan. 10. are all common electrical switches & fittings working properly 11. is common TV antenna working properly. 12. is the garden work complete in all respect. 13. common toilet or washing place is provided or not. 14. society office or watchmens cabin is provided or not. 15. is the finishing in duct complete. 16. shoe to rainwater pipe is provided or not. 17. proper outlet to rainwater in duct is given or not. 18. transformer room or L.T.room etc. has been provided or not. 19. building no.& name has been painted or not. 20. are all lifts working properly. 21. are door closers for all lifts doors freely working. 22. is the collapsible type door provided for lift. 23. is the capicity board fixed in lift cabin. 24. are meters no.& flat owners names painted in meter cabinet. 25. is water meter fixed on municiple water line? initial reading.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-05

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Dsouza Agnel Santan
Exam No. 13524
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To check reinforcement of beam.
Details of how you Planned & Executed the allotted work 1. We had seen all r.c.c. drawings of beam. we check whether reinforcment is as per proportion or not.with checking of bars,curtailed bars,extra top, extra bottom with site incharge.
Details of the Construction Procedure / Activity / Technology learned today application of white plaster.
Details of the Construction Materials learned today none.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel plates instead of plywood in formwork. this is environment friendly.
Details of the Construction / Engineering Drawings observed today beam drawings.
Details of the Bye Laws referred today minimum stairs in a staircase-18
Details of any Managerial Skill learned today every work should be checked after it is completed and also during its work.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for brickwork: we used the proportion:1:6 assume 1 cu.m of wall construction. brick=1*500=500 no.=500*6.50=Rs.3250 30% mortar is required for cu.m of masonry. i.e.mortar volume for 1 cu.m=0.3 cu.m a) cement-(0.3/(1+6)=0.0428 cu.m no. of bags-(0.0428/0.035)=1.22 1.5 bags=1.5*260=Rs.390 b) sand-0.0428*6=0.2568=5000*0.0428=Rs.1284 total cost of material=Rs.4924 f) labour-mestri-Rs.250 mason-1 no.-Rs.190 Boy or woman-Rs.110*2no.=Rs.220 g) water-1.5%=(4924+660)*(1.5/100)=Rs.5584 contractor profit=total cost*profit(15% profit) =Rs.(5584+83.76)*1.15 =Rs.850.164 total amount=Rs.6517.92
Result of RATE ANALYSIS ( Rs per Unit ) Rs.6517.92
Todays BUZZ Word checklist for building exterior: 1. Is the approach road properly laid with proper tarring. 2. is the compound wall & gate work properly. 3. is the building painted from outside properly. 4. is the septic tank work complete. 5. is the flooring work in stilts complete. 6. are the letter boxes fixed with names of clients on it. 7. is the work of staircase completed in all respects. 8. is the pump room work completed in all respect. 9. the parking allotment done as per the approved plan. 10. are all common electrical switches & fittings working properly 11. is common TV antenna working properly. 12. is the garden work complete in all respect. 13. common toilet or washing place is provided or not. 14. society office or watchmens cabin is provided or not. 15. is the finishing in duct complete. 16. shoe to rainwater pipe is provided or not. 17. proper outlet to rainwater in duct is given or not. 18. transformer room or L.T.room etc. has been provided or not. 19. building no.& name has been painted or not. 20. are all lifts working properly. 21. are door closers for all lifts doors freely working. 22. is the collapsible type door provided for lift. 23. is the capicity board fixed in lift cabin. 24. are meters no.& flat owners names painted in meter cabinet. 25. is water meter fixed on municiple water line? initial reading.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-05

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Suyvanshi patil Pratiksinh Vilas
Exam No. 13549
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:50pm
Details of the Work Allotted to you today by the Site In-Charge Today we have seen construction procedure of Brick-Masonary and calculate the number of bricks required in wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today We have learnt various Bonds of bricks.
Details of the Construction Materials learned today - About brick masonary and preparing cement mortar as per proportion. - By using Plumb bob we check the line the of the wall.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plans of the floor.
Details of the Bye Laws referred today - None
Details of any Managerial Skill learned today - To convince the dealers regarding rates.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for 6\" bricks. No. of bricks required for per sq.m- 50 Cost per brick= Rs.4. For 50 bricks cost= Rs.200. Proportion = 1:4 For 1 sq.m = 0.22 cement required. Cost of cement= Rs. 265. Total cement cost=265*0.22= Rs.58.30. Cost of sand= Rs.1060. Total cost of sand per sq.m= 1060*0.15= Rs.159. Total cost=200+58.30+159=Rs. 417. Labour cost= 20%= Rs.83.4. Total cost=417+83.4=Rs.500.4. With 10% profit=Rs.550.4 Total cost of brick work for 6\" bricks = Rs.550.4 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.550.4 per sq.m for 6\" bricks.
Todays BUZZ Word Description Of Work----(Yes/No) 1. Is all the materials checked? 2. Is there any defect in tiles / stones received? 3. Are the rooms cleaned before tiling? 4. Is the skirting gap sufficient? 5. Is the lime mortar fresh & properly mixxed in mixtures? 6. Are Thiyyas Taken before Machan work? 7. Is right angle set before starting tiling? 8. Are level lines are marked on the walls of flat? 9. Are tile joints filled with matching colour cement slurry? 10. Is the skirting Farma used before fixing skirting? 11. Are all the cut-pieces made with help of cutting machine? 12. Is there sufficient stock of 12 mm thick skirting for fixing near RCC column? 13. Are new polishing stones used for polishing? 14. Is proper Curing for three days done to the grouting coat? 15. Are all polishing coats properly executed? 16. Is oxalic acid in powder form used for acid form? 17. Is the balcony flooring given sufficient slope towards spout? 18. Is all G.I., P.V.C. conduiting completed before glazed tile fixing? 19. Is the tile taken on the opening side of the door fro WC floor? 20. Are the edges of kitchen otta & sill rounded? 21. Are the slopes of kitchen platform top & sink proper? 22. Is the WC / Bath floor slope in proper direction? 23. Is the oil paint applied to kitchen platform & sill? 24. Are umbra pattis fixed wherever required? 25. Is the cleaning properly done?
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-05

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To check reinforcement of beam.
Details of how you Planned & Executed the allotted work 1. We had seen all r.c.c. drawings of beam. we check whether reinforcment is as per proportion or not.with checking of bars,curtailed bars,extra top, extra bottom with site incharge.
Details of the Construction Procedure / Activity / Technology learned today application of white plaster.
Details of the Construction Materials learned today none.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel plates instead of plywood in formwork. this is environment friendly.
Details of the Construction / Engineering Drawings observed today beam drawings.
Details of the Bye Laws referred today minimum stairs in a staircase-18
Details of any Managerial Skill learned today every work should be checked after it is completed and also during its work.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for brickwork: we used the proportion:1:6 assume 1 cu.m of wall construction. brick=1*500=500 no.=500*6.50=Rs.3250 30% mortar is required for cu.m of masonry. i.e.mortar volume for 1 cu.m=0.3 cu.m a) cement-(0.3/(1+6)=0.0428 cu.m no. of bags-(0.0428/0.035)=1.22 1.5 bags=1.5*260=Rs.390 b) sand-0.0428*6=0.2568=5000*0.0428=Rs.1284 total cost of material=Rs.4924 f) labour-mestri-Rs.250 mason-1 no.-Rs.190 Boy or woman-Rs.110*2no.=Rs.220 g) water-1.5%=(4924+660)*(1.5/100)=Rs.5584 contractor profit=total cost*profit(15% profit) =Rs.(5584+83.76)*1.15 =Rs.850.164 total amount=Rs.6517.92
Result of RATE ANALYSIS ( Rs per Unit ) Rs.6517.92
Todays BUZZ Word checklist for building exterior: 1. Is the approach road properly laid with proper tarring. 2. is the compound wall & gate work properly. 3. is the building painted from outside properly. 4. is the septic tank work complete. 5. is the flooring work in stilts complete. 6. are the letter boxes fixed with names of clients on it. 7. is the work of staircase completed in all respects. 8. is the pump room work completed in all respect. 9. the parking allotment done as per the approved plan. 10. are all common electrical switches & fittings working properly 11. is common TV antenna working properly. 12. is the garden work complete in all respect. 13. common toilet or washing place is provided or not. 14. society office or watchmens cabin is provided or not. 15. is the finishing in duct complete. 16. shoe to rainwater pipe is provided or not. 17. proper outlet to rainwater in duct is given or not. 18. transformer room or L.T.room etc. has been provided or not. 19. building no.& name has been painted or not. 20. are all lifts working properly. 21. are door closers for all lifts doors freely working. 22. is the collapsible type door provided for lift. 23. is the capicity board fixed in lift cabin. 24. are meters no.& flat owners names painted in meter cabinet. 25. is water meter fixed on municiple water line? initial reading.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-05

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To check reinforcement of beam.
Details of how you Planned & Executed the allotted work 1. We had seen all r.c.c. drawings of beam. we check whether reinforcment is as per proportion or not.with checking of bars,curtailed bars,extra top, extra bottom with site incharge.
Details of the Construction Procedure / Activity / Technology learned today application of white plaster.
Details of the Construction Materials learned today none.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel plates instead of plywood in formwork. this is environment friendly.
Details of the Construction / Engineering Drawings observed today beam drawings.
Details of the Bye Laws referred today minimum stairs in a staircase-18
Details of any Managerial Skill learned today every work should be checked after it is completed and also during its work.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for brickwork: we used the proportion:1:6 assume 1 cu.m of wall construction. brick=1*500=500 no.=500*6.50=Rs.3250 30% mortar is required for cu.m of masonry. i.e.mortar volume for 1 cu.m=0.3 cu.m a) cement-(0.3/(1+6)=0.0428 cu.m no. of bags-(0.0428/0.035)=1.22 1.5 bags=1.5*260=Rs.390 b) sand-0.0428*6=0.2568=5000*0.0428=Rs.1284 total cost of material=Rs.4924 f) labour-mestri-Rs.250 mason-1 no.-Rs.190 Boy or woman-Rs.110*2no.=Rs.220 g) water-1.5%=(4924+660)*(1.5/100)=Rs.5584 contractor profit=total cost*profit(15% profit) =Rs.(5584+83.76)*1.15 =Rs.850.164 total amount=Rs.6517.92
Result of RATE ANALYSIS ( Rs per Unit ) Rs.6517.92
Todays BUZZ Word checklist for building exterior: 1. Is the approach road properly laid with proper tarring. 2. is the compound wall & gate work properly. 3. is the building painted from outside properly. 4. is the septic tank work complete. 5. is the flooring work in stilts complete. 6. are the letter boxes fixed with names of clients on it. 7. is the work of staircase completed in all respects. 8. is the pump room work completed in all respect. 9. the parking allotment done as per the approved plan. 10. are all common electrical switches & fittings working properly 11. is common TV antenna working properly. 12. is the garden work complete in all respect. 13. common toilet or washing place is provided or not. 14. society office or watchmens cabin is provided or not. 15. is the finishing in duct complete. 16. shoe to rainwater pipe is provided or not. 17. proper outlet to rainwater in duct is given or not. 18. transformer room or L.T.room etc. has been provided or not. 19. building no.& name has been painted or not. 20. are all lifts working properly. 21. are door closers for all lifts doors freely working. 22. is the collapsible type door provided for lift. 23. is the capicity board fixed in lift cabin. 24. are meters no.& flat owners names painted in meter cabinet. 25. is water meter fixed on municiple water line? initial reading.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: v.g.ayyar@gmail.com
Subject: 13553-05

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Ayyar Vignesh Gopal
Exam No. 13553
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:50pm
Details of the Work Allotted to you today by the Site In-Charge Today we have seen construction procedure of Brick-Masonary and calculate the number of bricks required in wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today We have learnt various Bonds of bricks.
Details of the Construction Materials learned today - About brick masonary and preparing cement mortar as per proportion. - By using Plumb bob we check the line the of the wall.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - None
Details of the Construction / Engineering Drawings observed today - Plans of the floor.
Details of the Bye Laws referred today - None
Details of any Managerial Skill learned today - To convince the dealers regarding rates.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for 6\" bricks. No. of bricks required for per sq.m- 50 Cost per brick= Rs.4. For 50 bricks cost= Rs.200. Proportion = 1:4 For 1 sq.m = 0.22 cement required. Cost of cement= Rs. 265. Total cement cost=265*0.22= Rs.58.30. Cost of sand= Rs.1060. Total cost of sand per sq.m= 1060*0.15= Rs.159. Total cost=200+58.30+159=Rs. 417. Labour cost= 20%= Rs.83.4. Total cost=417+83.4=Rs.500.4. With 10% profit=Rs.550.4 Total cost of brick work for 6\" bricks = Rs.550.4 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.550.4 per sq.m for 6\" bricks.
Todays BUZZ Word \"Checklist For Tiling Work\" Description Of Work----(Yes/No) 1. Is all the materials checked? 2. Is there any defect in tiles / stones received? 3. Are the rooms cleaned before tiling? 4. Is the skirting gap sufficient? 5. Is the lime mortar fresh & properly mixxed in mixtures? 6. Are Thiyyas Taken before Machan work? 7. Is right angle set before starting tiling? 8. Are level lines are marked on the walls of flat? 9. Are tile joints filled with matching colour cement slurry? 10. Is the skirting Farma used before fixing skirting? 11. Are all the cut-pieces made with help of cutting machine? 12. Is there sufficient stock of 12 mm thick skirting for fixing near RCC column? 13. Are new polishing stones used for polishing? 14. Is proper Curing for three days done to the grouting coat? 15. Are all polishing coats properly executed? 16. Is oxalic acid in powder form used for acid form? 17. Is the balcony flooring given sufficient slope towards spout? 18. Is all G.I., P.V.C. conduiting completed before glazed tile fixing? 19. Is the tile taken on the opening side of the door fro WC floor? 20. Are the edges of kitchen otta & sill rounded? 21. Are the slopes of kitchen platform top & sink proper? 22. Is the WC / Bath floor slope in proper direction? 23. Is the oil paint applied to kitchen platform & sill? 24. Are umbra pattis fixed wherever required? 25. Is the cleaning properly done?
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-05

Company Name Sanghavi Sons & Constructions
Project Name & Site Address suncity Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur
Students Name (Surname_First Name_Middle Name) desai Akshay prakash
Exam No. 10890
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00a.m.
Site Leaving Time (HH:MM am/pm) 4.09p.m.
Details of the Work Allotted to you today by the Site In-Charge -To see brickwork going in row bunglow D-8. -To see sewre line work in D-8 row bunglow.
Details of how you Planned & Executed the allotted work -First we go in D-8 row bunglow & see all the details of brickwork. -Then we see the laying of sewre pipeline behind the D-8 wing.
Details of the Construction Procedure / Activity / Technology learned today -First mortor is prepared for brickwork in proportion of 1:6. -All the bricks are soaked in water so that they do not absorb water. -First mortor is spread over the surface of 10mm thick then corner brick is placed & fixed in the motor. -header bond is used for masonry. -Strech a string (line dori)along the top of the first coarse laid at each corner of the wall. -Then coarse is raised. -Then procedure is repeated for 2nd , 3rd & other coarses until wall is constructed to the requireb height. Sewere line.- -first excavation is done for placing the septic tank. -then excavation is done for pipe line. -one end of the pipe is attached to the septic tank & other is taken to the waste water treatment plant. -Then water is treated 7 reused for gardening purpose only.
Details of the Construction Materials learned today -R.C.C. pipe for sewre line. -bricks 22.5x15x10 cm -Aggregate brick 40x18.8x15
Details of Environment Caring Technology / Methodology / Procedure / Product learned today septic tanks are used for sewage disposal.
Details of the Construction / Engineering Drawings observed today -Plumbing layout -Drainage layout
Details of the Bye Laws referred today -Parking height is 2.5m provided.
Details of any Managerial Skill learned today -when we observe all the bunglow we found the toilet cock is not on the proper height we told the site incharge then he gave instruction to the plumber strictly.
RATE ANALYSIS (Detailed Stepwise Calculations required) assume quantity of brickwork=10sq.m. -quantity of morter=35% of quantity - =10x0.35 =3.5cub. m. -quantity of cement =3.5/1+6 =0.5cub.m. -no.of bags of cement=0.5/0.035 =14.28 say 15 bags -quantity of sand = 6x0.5 =3 cub.m. -bricks = 1 sq.m.=450 then 10sq.m.=4500no. particular Qt. or NO. rate RS Cement 15 bags 255/- 3225/- Sand 3 cub.m. 1827/- 5481/- Bricks 4500 5600/- 22500/- -Labour mason 2 210/- 420/- Mazdoor mail 3 160/- 480/- femail 3 130/- 390/- Bhisti 1 100/- 100/- Lumpsum 100/- 100/- TOTAL = 32746/- Add 20% buildres profit including sales tax ,service tax,vat, all charges =39295.2/- Rate per sq. m. = 3930/-
Result of RATE ANALYSIS ( Rs per Unit ) 3930/-Per sq.m.
Todays BUZZ Word CHECKLIST -incomplete tiles are provided for the kitchen otta. -sink pipe are no good quality -Exhaust fans are not provided. -replacement of w.c.pan. -inappropriate door & window fastenings. -height of w.c. cock are wrong. -placement of the switchboard are not hidden from the people. -Height of the switch board is wrong. -Height of the kitchen otta is less as compair to bylaws. -Dining table 1400x750mm. -ceiling height of the window 850mm -Privacy is not maintained in master bed of A-3 bunglow. -Position of bath in master bed is not sufficent. -Master bed door width 1390mm. -master bed size 6.25mx3.40m -sizes of bath are wrong. -Dressing table height is not proper. -No provision of space for gas cylinder. -Size of the window in kitchen is so large. -Proper maintanance is not done. -Wastage of tiles, bricks ,plywood considerably. -No of switchboard are more than sufficient. -Position of the all room in the A-3 are not proper. -Main entrance door is not sufficient according to Bylaws. -
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: shindeamol5255@yahoo.co.in
Subject: 13546-05

Company Name Deshmukh Developers
Project Name & Site Address Goldenshelter
Students Name (Surname_First Name_Middle Name) Shinde Amol Jagannath
Exam No. 13546
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe the plumbing work. .
Details of how you Planned & Executed the allotted work We observe the work weather it has been done as per drawing or not and note the important things. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing work of bathroom:- 1)Mark the level of pipes on wall. 2)Make a groove in the wall with the grooving tool. 3)Lay the pipe and apply the fittings. 4)After completing all fittings apply plaster to conceal the place. .
Details of the Construction Materials learned today Plumbing pipes:- Dia.= 110mm downtake pipe 35mm For flushing 20mm Water carrying pipe. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use water carefully by preventing wastage. .
Details of the Construction / Engineering Drawings observed today Plumbing drawing:- Plumbing drawing for bath, toilet and rainwater pipes. .
Details of the Bye Laws referred today Minimum floor to floor height criteria for the residential buildings. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Abhijeet Bhosale. 9921515194 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-05

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Lad Manoj Sadashiv
Exam No. 13534
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.10.pm
Details of the Work Allotted to you today by the Site In-Charge marketing of construction in CREDAI exhibition
Details of how you Planned & Executed the allotted work we approached to the Rajesh construction stall in CREDAI exhibition we understand all detail of salable area, carpet area,floor plans ,elavation,flood red zone,pent house.
Details of the Construction Procedure / Activity / Technology learned today marketing of construction is important process in building development.in this process healthy communication in between customer and builder customer reaction about the project is observed.
Details of the Construction Materials learned today coarse agg.- it gives builky nature to concrete. agg.cement ratio is very imp. in mix design. rounded agg.increases worcability of concrete. angular agg.help for proper locking
Details of Environment Caring Technology / Methodology / Procedure / Product learned today cement bags not thrown in any drainage system or NALA it is stored in particular place to avoid water logging.
Details of the Construction / Engineering Drawings observed today representation plan for marketing process
Details of the Bye Laws referred today F.S.I. consumed= 0.87
Details of any Managerial Skill learned today good marketing skills
RATE ANALYSIS (Detailed Stepwise Calculations required) Brickwork for wall- height = 10 feet length = 20 feet total area =200 ft.sq. =18.58 sq.m. for 1sq.m. 45 bricks are required total bricks =836 ammount for bricks =836*6.50=5434 Rs. mason + mistri =600 Rs. (1 brass) morter required =30cu ft. ammount of morter =730 Rs.(40 pan F.A. +1 bag cement) total ammount =5434+1200+730 =7364 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 7364 Rs.per wall
Todays BUZZ Word CHECK LIST- 1.distance between column -3m. 2.distance of overlap =900mm. 3.stair case height=3m. 4.width of landing=1.2m. 5.maximum column size=0.9m.*0.15m 6.min,column size=0.6m*0.15m 7.slab tk.=150mm. 8.size of stirrups=48cm. 9.size of steel bar for heavy beam=25mm. 10.size of steel bar of curt=12mm. 11.size of anchor(spring)=2ft. 12.projection of cantiliver slab=1.2m. 13.floor ht.=3m. 14.distance bet.main bar=150mm. 15.distance bet.distribution bar=175mm. 16.no.of bars at top=2/3 17.no of bars at bottom=2/3 18.extra top=1/2 19.extra bottom=1/2 20.extra centre=1/2 21.no. of stirrups in each l/4 distance=10 22.depth of sunk slab=0.5m. 23.depth of hidden beam=0.15m. 24.depth of inverted slab=130mm. 25.tk. of column cover=10mm.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum (9850508669)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: nikitashinde15@gmail.com
Subject: 13547-05

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) shinde nikita eknath
Exam No. 13547
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge calculation of concrete required for salb * we calculated 1.concrete required for slab -198.75 cu.ft. 2. concrete required for beam -103.85 cu.ft. 3. concrete required for staircase-9.1 cu.ft. total-312 cu.ft.
Details of how you Planned & Executed the allotted work 1.mesurement size of beam and slab according to desing 2.calculate volume of concrete required
Details of the Construction Procedure / Activity / Technology learned today 1.fitting of concealed wiring in wall and slab 2.plastering of external wall
Details of the Construction Materials learned today 1.door frame , window frame 2. types of brick
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today drawing for doors and window schedules
Details of the Bye Laws referred today permmisible FSI- 1. 1.5 for pure residential. 2. 0.5 for mixed residential & commerical.
Details of any Managerial Skill learned today good communication with us & customer.
RATE ANALYSIS (Detailed Stepwise Calculations required) 6\" thk brick 1.brick -350 x 6.5Rs =2177.5Rs 2.sand -40 x 17Rs =680Rs 3.cement 2.5 x 250Rs =625Rs 4. labour =300Rs 5.water curring =40Rs total =3822.5Rs with c.p. =4587Rs total =45.87Rs per squre foot total =510Rs per sq mt
Result of RATE ANALYSIS ( Rs per Unit ) 510 Rs
Todays BUZZ Word check the 1.north direction of plane 2.plancs in level 3.two sides in diagonal 4.center point of column 5.column footing net and center of column 6.cover to that net 7.size of footing 8.level of column by plum bob 9.PCC level 10.line out for super structure 11.window marking 12.west concrete 13.level of steps 14.level of landining 15.level of slab 16.steel bars and rings 17.types of wiring 18.prapotion of concrete 19.lapping column if neccesary 20.formwork of beam 21.stone mesonary for plinth with refer to road 22.size of column 23.distance of transporting material 24.height of concrete placed 25.thickness of west concrete
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no - 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: rajendrapawar54@gmail.com
Subject: 13542-05

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) pawar rajendra eknath
Exam No. 13542
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge calculation of concrete required for salb * we calculated 1.concrete required for slab -198.75 cu.ft. 2. concrete required for beam -103.85 cu.ft. 3. concrete required for staircase-9.1 cu.ft. total-312 cu.ft.
Details of how you Planned & Executed the allotted work 1.mesurement size of beam and slab according to desing 2.calculate volume of concrete required
Details of the Construction Procedure / Activity / Technology learned today 1.fitting of concealed wiring in wall and slab 2.plastering of external wall
Details of the Construction Materials learned today 1.door frame , window frame 2. types of brick
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today drawing for doors and window schedules
Details of the Bye Laws referred today permmisible FSI- 1. 1.5 for pure residential. 2. 0.5 for mixed residential & commerical.
Details of any Managerial Skill learned today good communication with us & customer.
RATE ANALYSIS (Detailed Stepwise Calculations required) 6\" thk brick 1.brick -350 x 6.5Rs =2177.5Rs 2.sand -40 x 17Rs =680Rs 3.cement 2.5 x 250Rs =625Rs 4. labour =300Rs 5.water curring =40Rs total =3822.5Rs with c.p. =4587Rs total =45.87Rs per squre foot total =510Rs per sq mt
Result of RATE ANALYSIS ( Rs per Unit ) 510 Rs
Todays BUZZ Word check the 1.north direction of plane 2.plancs in level 3.two sides in diagonal 4.center point of column 5.column footing net and center of column 6.cover to that net 7.size of footing 8.level of column by plum bob 9.PCC level 10.line out for super structure 11.window marking 12.west concrete 13.level of steps 14.level of landining 15.level of slab 16.steel bars and rings 17.types of wiring 18.prapotion of concrete 19.lapping column if neccesary 20.formwork of beam 21.stone mesonary for plinth with refer to road 22.size of column 23.distance of transporting material 24.height of concrete placed 25.thickness of west concrete
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no - 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: gauravdesai75@gmail.com
Subject: 13522-05

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers and Builders, Near Jayprabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DESAI GAURAV RAVINDRA
Exam No. 13522
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge 1. To see the curing of slab. 2. To see the column reinforcement for second floor. 3. To see the slab centering work for third floor.
Details of how you Planned & Executed the allotted work We saw the curing of slab that was casted two days before. The slab had attained sufficient firmness. For curing, ponds were made, and water was continously sprinkled on slab for 3-4 times a day.
Details of the Construction Procedure / Activity / Technology learned today We saw the laying of column reinforcement for second floor. The bars were reduced in size from 1200 mm to 80 mm. We saw the slab centering work going on for third floor. We also saw the construction of formwork for the next flight from second floor to third floor. We saw how the labourers check the level by water pipes by holding them at two points and see their levels, this is the new technique we learnt.
Details of the Construction Materials learned today Column reinforcement- Tor steel bars 20mm, stirrups. Formwork and other materials for staircase.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such Technology was adopted today.
Details of the Construction / Engineering Drawings observed today 1. Plan for centering work for third floor. 2. Plan for third floor.
Details of the Bye Laws referred today 1. According to bye-laws cantilever beams should be placed at L/2 distance. 2. According to bye-laws maximum length of cantilever beam is 4m. On site it is provided 2m. 3.According to bye laws, minimum head requirement for garage is 2.4m. On site it is provided 3.8m. 5.According to bye laws, maximum height of riser is 190 mm. On site it is provided 160 mm. 7.According to bye laws,minimum width of treads is 250 mm. On site it is provided 300 mm.
Details of any Managerial Skill learned today 1. The site incharge saw whether curing was done properly or not. 2. He saw the Slab centering work. 3. He suggested the labour to make changes wherever needed
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for \"Brick work\" Rate analysis for 6\" bricks. No. of bricks required for per sq.m- 50 Cost per brick= Rs.4. For 50 bricks cost= Rs.200. Proportion = 1:4 For 1 sq.m = 0.22 cement required. Cost of cement= Rs. 265. Total cement cost=265*0.22= Rs.58.30. Cost of sand= Rs.1060. Total cost of sand per sq.m= 1060*0.15= Rs.159. Total cost=200+58.30+159=Rs. 417. Labour cost= 20%= Rs.83.4. Total cost=417+83.4=Rs.500.4. With 10% profit=Rs.550.4 Total cost of brick work for 6\" bricks = Rs.550.4 per sq.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.550.4 per sq.m for 6\" bricks.
Todays BUZZ Word \"CHECK-LIST\" 1.Slab centering checked with architectural drawing. 1. For elevation. 2. For room dimension. 3. For electric points. 2. Slab centering checked completely. 1. For required beam depth/ slab thickness. 2. For required head rooms. 3. For other points. 3.Slab centering checked completely. 1. Level checked/ Line checked. 2. Column centering checked / modified. 3. Oiling to beams/ slab shuttering. 4. Centering for stair-case checked. 5. Changes for amenities if any checked. 6. Reinforcement checked for beams and slabs as per R.C.C drawings. 7. Proper cover for bottom /side checked for beams. 8. Proper number of chairs provided for slab. 9. Proper cover bottom/top checked for slab/fan hook checked. 10.Reduction of columns as per drawing done for above slab. 11.Hidden beams/Cantilever beams/inverted beams checked if any. 12.Pardi bars left for balconies etc. 13.Proper cover bottom side/checked for all. 14.Dowels (any required ) are left. 15.R.C.C work centering checked for with architectural drawings. 1. For elevation. 2. For cenetring plan. 3. For electrical points. 4. For required size of beam /footings/slabs etc. 5. For other points. 16.Reinforcement checked as per R.C.C drwaings. 1. For beams. 2. For columns. 3. For pardhi. 4. For waist slab. 5. For other items. 17.B.B masonry work checked with architectural drawing. 1. For elevation. 2. For room dimension. 3. For openings. 18.B.B. masonry checked. 1. For beam size. 2. For column size. 3. For door and window openings. 19.Is the floor clen before starting line out of masonry. 20.First layer checked with beam top/beam edge,offset,plumb and line. 21.Erection of door and window frame with necessary no. of holdfast. 22.Painting to door and window frame with one coat of primer (Anti-Termite paint) 23.Alignment of door and window frames for plumb/bend/level. 24.Verticalitiy of walls and corners. 25.Thickness of joints.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO. 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-05

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Patil Vrishali Vitthal
Exam No. 13541
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.10.pm
Details of the Work Allotted to you today by the Site In-Charge marketing of construction in CREDAI exhibition
Details of how you Planned & Executed the allotted work we approached to the Rajesh construction stall in CREDAI exhibition we understand all detail of salable area, carpet area,floor plans ,elavation,flood red zone,pent house.
Details of the Construction Procedure / Activity / Technology learned today marketing of construction is important process in building development.in this process healthy communication in between customer and builder customer reaction about the project is observed.
Details of the Construction Materials learned today coarse agg.- it gives builky nature to concrete. agg.cement ratio is very imp. in mix design. rounded agg.increases worcability of concrete. angular agg.help for proper locking
Details of Environment Caring Technology / Methodology / Procedure / Product learned today cement bags not thrown in any drainage system or NALA it is stored in particular place to avoid water logging.
Details of the Construction / Engineering Drawings observed today representation plan for marketing process
Details of the Bye Laws referred today F.S.I. consumed= 0.87
Details of any Managerial Skill learned today good marketing skills
RATE ANALYSIS (Detailed Stepwise Calculations required) Brickwork for wall- height = 10 feet length = 20 feet total area =200 ft.sq. =18.58 sq.m. for 1sq.m. 45 bricks are required total bricks =836 ammount for bricks =836*6.50=5434 Rs. mason + mistri =600 Rs. (1 brass) morter required =30cu ft. ammount of morter =730 Rs.(40 pan F.A. +1 bag cement) total ammount =5434+1200+730 =7364 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 7364 Rs.per wall
Todays BUZZ Word CHECK LIST- 1.distance between column -3m. 2.distance of overlap =900mm. 3.stair case height=3m. 4.width of landing=1.2m. 5.maximum column size=0.9m.*0.15m 6.min,column size=0.6m*0.15m 7.slab tk.=150mm. 8.size of stirrups=48cm. 9.size of steel bar for heavy beam=25mm. 10.size of steel bar of curt=12mm. 11.size of anchor(spring)=2ft. 12.projection of cantiliver slab=1.2m. 13.floor ht.=3m. 14.distance bet.main bar=150mm. 15.distance bet.distribution bar=175mm. 16.no.of bars at top=2/3 17.no of bars at bottom=2/3 18.extra top=1/2 19.extra bottom=1/2 20.extra centre=1/2 21.no. of stirrups in each l/4 distance=10 22.depth of sunk slab=0.5m. 23.depth of hidden beam=0.15m. 24.depth of inverted slab=130mm. 25.tk. of column cover=10mm.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum (9850508669)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: prasadkharat@ymail.com
Subject: 13531-05

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Prasad Ramchandra
Exam No. 13531
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.10pm
Details of the Work Allotted to you today by the Site In-Charge marketing of construction in CREDAI exhibition
Details of how you Planned & Executed the allotted work we approached to the Rajesh construction stall in CREDAI exhibition we understand all detail of salable area, carpet area,floor plans ,elavation,flood red zone,pent house.
Details of the Construction Procedure / Activity / Technology learned today marketing of construction is important process in building development.in this process healthy communication in between customer and builder customer reaction about the project is observed.
Details of the Construction Materials learned today coarse agg.- it gives builky nature to concrete. agg.cement ratio is very imp. in mix design. rounded agg.increases worcability of concrete. angular agg.help for proper locking
Details of Environment Caring Technology / Methodology / Procedure / Product learned today cement bags not thrown in any drainage system or NALA it is stored in particular place to avoid water logging.
Details of the Construction / Engineering Drawings observed today representation plan for marketing process
Details of the Bye Laws referred today F.S.I. consumed= 0.87
Details of any Managerial Skill learned today good marketing skills
RATE ANALYSIS (Detailed Stepwise Calculations required) Brickwork for wall- height = 10 feet length = 20 feet total area =200 ft.sq. =18.58 sq.m. for 1sq.m. 45 bricks are required total bricks =836 ammount for bricks =836*6.50=5434 Rs. mason + mistri =600 Rs. (1 brass) morter required =30cu ft. ammount of morter =730 Rs.(40 pan F.A. +1 bag cement) total ammount =5434+1200+730 =7364 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 7364 Rs.per wall
Todays BUZZ Word CHECK LIST- 1.distance between column -3m. 2.distance of overlap =900mm. 3.stair case height=3m. 4.width of landing=1.2m. 5.maximum column size=0.9m.*0.15m 6.min,column size=0.6m*0.15m 7.slab tk.=150mm. 8.size of stirrups=48cm. 9.size of steel bar for heavy beam=25mm. 10.size of steel bar of curt=12mm. 11.size of anchor(spring)=2ft. 12.projection of cantiliver slab=1.2m. 13.floor ht.=3m. 14.distance bet.main bar=150mm. 15.distance bet.distribution bar=175mm. 16.no.of bars at top=2/3 17.no of bars at bottom=2/3 18.extra top=1/2 19.extra bottom=1/2 20.extra centre=1/2 21.no. of stirrups in each l/4 distance=10 22.depth of sunk slab=0.5m. 23.depth of hidden beam=0.15m. 24.depth of inverted slab=130mm. 25.tk. of column cover=10mm.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum (9850508669)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-05

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) patil sachin dhanaji
Exam No. 13539
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge calculation of concrete required for salb * we calculated 1.concrete required for slab -198.75 cu.ft. 2. concrete required for beam -103.85 cu.ft. 3. concrete required for staircase-9.1 cu.ft. total-312 cu.ft.
Details of how you Planned & Executed the allotted work 1.mesurement size of beam and slab according to desing 2.calculate volume of concrete required
Details of the Construction Procedure / Activity / Technology learned today 1.fitting of concealed wiring in wall and slab 2.plastering of external wall
Details of the Construction Materials learned today 1.door frame , window frame 2. types of brick
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today drawing for doors and window schedules
Details of the Bye Laws referred today permmisible FSI- 1. 1.5 for pure residential. 2. 0.5 for mixed residential & commerical.
Details of any Managerial Skill learned today good communication with us & customer.
RATE ANALYSIS (Detailed Stepwise Calculations required) 6\" thk brick 1.brick -350 x 6.5Rs =2177.5Rs 2.sand -40 x 17Rs =680Rs 3.cement 2.5 x 250Rs =625Rs 4. labour =300Rs 5.water curring =40Rs total =3822.5Rs with c.p. =4587Rs total =45.87Rs per squre foot total =510Rs per sq mt
Result of RATE ANALYSIS ( Rs per Unit ) 510 Rs
Todays BUZZ Word check the 1.north direction of plane 2.plancs in level 3.two sides in diagonal 4.center point of column 5.column footing net and center of column 6.cover to that net 7.size of footing 8.level of column by plum bob 9.PCC level 10.line out for super structure 11.window marking 12.west concrete 13.level of steps 14.level of landining 15.level of slab 16.steel bars and rings 17.types of wiring 18.prapotion of concrete 19.lapping column if neccesary 20.formwork of beam 21.stone mesonary for plinth with refer to road 22.size of column 23.distance of transporting material 24.height of concrete placed 25.thickness of west concrete
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no - 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: rameshkharat1987@gmail.com
Subject: 13532-05

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) Kharat Ramesh Laxman
Exam No. 13532
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am.
Site Leaving Time (HH:MM am/pm) 4.10pm
Details of the Work Allotted to you today by the Site In-Charge marketing of construction in CREDAI exhibition
Details of how you Planned & Executed the allotted work we approached to the Rajesh construction stall in CREDAI exhibition we understand all detail of salable area, carpet area,floor plans ,elavation,flood red zone,pent house.
Details of the Construction Procedure / Activity / Technology learned today marketing of construction is important process in building development.in this process healthy communication in between customer and builder customer reaction about the project is observed.
Details of the Construction Materials learned today coarse agg.- it gives builky nature to concrete. agg.cement ratio is very imp. in mix design. rounded agg.increases worcability of concrete. angular agg.help for proper locking
Details of Environment Caring Technology / Methodology / Procedure / Product learned today cement bags not thrown in any drainage system or NALA it is stored in particular place to avoid water logging.
Details of the Construction / Engineering Drawings observed today representation plan for marketing process
Details of the Bye Laws referred today F.S.I. consumed= 0.87
Details of any Managerial Skill learned today good marketing skills
RATE ANALYSIS (Detailed Stepwise Calculations required) Brickwork for wall- height = 10 feet length = 20 feet total area =200 ft.sq. =18.58 sq.m. for 1sq.m. 45 bricks are required total bricks =836 ammount for bricks =836*6.50=5434 Rs. mason + mistri =600 Rs. (1 brass) morter required =30cu ft. ammount of morter =730 Rs.(40 pan F.A. +1 bag cement) total ammount =5434+1200+730 =7364 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 7364 Rs.per wall
Todays BUZZ Word CHECK LIST- 1.distance between column -3m. 2.distance of overlap =900mm. 3.stair case height=3m. 4.width of landing=1.2m. 5.maximum column size=0.9m.*0.15m 6.min,column size=0.6m*0.15m 7.slab tk.=150mm. 8.size of stirrups=48cm. 9.size of steel bar for heavy beam=25mm. 10.size of steel bar of curt=12mm. 11.size of anchor(spring)=2ft. 12.projection of cantiliver slab=1.2m. 13.floor ht.=3m. 14.distance bet.main bar=150mm. 15.distance bet.distribution bar=175mm. 16.no.of bars at top=2/3 17.no of bars at bottom=2/3 18.extra top=1/2 19.extra bottom=1/2 20.extra centre=1/2 21.no. of stirrups in each l/4 distance=10 22.depth of sunk slab=0.5m. 23.depth of hidden beam=0.15m. 24.depth of inverted slab=130mm. 25.tk. of column cover=10mm.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum (9850508669)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-05

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) patil sangram madhukar
Exam No. 13540
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge calculation of concrete required for salb * we calculated 1.concrete required for slab -198.75 cu.ft. 2. concrete required for beam -103.85 cu.ft. 3. concrete required for staircase-9.1 cu.ft. total-312 cu.ft.
Details of how you Planned & Executed the allotted work 1.mesurement size of beam and slab according to desing 2.calculate volume of concrete required
Details of the Construction Procedure / Activity / Technology learned today 1.fitting of concealed wiring in wall and slab 2.plastering of external wall
Details of the Construction Materials learned today 1.door frame , window frame 2. types of brick
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today drawing for doors and window schedules
Details of the Bye Laws referred today permmisible FSI- 1. 1.5 for pure residential. 2. 0.5 for mixed residential & commerical.
Details of any Managerial Skill learned today good communication with us & customer.
RATE ANALYSIS (Detailed Stepwise Calculations required) 6\" thk brick 1.brick -350 x 6.5Rs =2177.5Rs 2.sand -40 x 17Rs =680Rs 3.cement 2.5 x 250Rs =625Rs 4. labour =300Rs 5.water curring =40Rs total =3822.5Rs with c.p. =4587Rs total =45.87Rs per squre foot total =510Rs per sq mt
Result of RATE ANALYSIS ( Rs per Unit ) 510 Rs
Todays BUZZ Word check the 1.north direction of plane 2.plancs in level 3.two sides in diagonal 4.center point of column 5.column footing net and center of column 6.cover to that net 7.size of footing 8.level of column by plum bob 9.PCC level 10.line out for super structure 11.window marking 12.west concrete 13.level of steps 14.level of landining 15.level of slab 16.steel bars and rings 17.types of wiring 18.prapotion of concrete 19.lapping column if neccesary 20.formwork of beam 21.stone mesonary for plinth with refer to road 22.size of column 23.distance of transporting material 24.height of concrete placed 25.thickness of west concrete
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no - 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: vishwajit.p09@gmail.com
Subject: 13543-05

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) paymal vishwajit shamarao
Exam No. 13543
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge calculation of concrete required for salb * we calculated 1.concrete required for slab -198.75 cu.ft. 2. concrete required for beam -103.85 cu.ft. 3. concrete required for staircase-9.1 cu.ft. total-312 cu.ft.
Details of how you Planned & Executed the allotted work 1.mesurement size of beam and slab according to desing 2.calculate volume of concrete required
Details of the Construction Procedure / Activity / Technology learned today 1.fitting of concealed wiring in wall and slab 2.plastering of external wall
Details of the Construction Materials learned today 1.door frame , window frame 2. types of brick
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today drawing for doors and window schedules
Details of the Bye Laws referred today permmisible FSI- 1. 1.5 for pure residential. 2. 0.5 for mixed residential & commerical.
Details of any Managerial Skill learned today good communication with us & customer.
RATE ANALYSIS (Detailed Stepwise Calculations required) 6\" thk brick 1.brick -350 x 6.5Rs =2177.5Rs 2.sand -40 x 17Rs =680Rs 3.cement 2.5 x 250Rs =625Rs 4. labour =300Rs 5.water curring =40Rs total =3822.5Rs with c.p. =4587Rs total =45.87Rs per squre foot total =510Rs per sq mt
Result of RATE ANALYSIS ( Rs per Unit ) 510 Rs
Todays BUZZ Word check the 1.north direction of plane 2.plancs in level 3.two sides in diagonal 4.center point of column 5.column footing net and center of column 6.cover to that net 7.size of footing 8.level of column by plum bob 9.PCC level 10.line out for super structure 11.window marking 12.west concrete 13.level of steps 14.level of landining 15.level of slab 16.steel bars and rings 17.types of wiring 18.prapotion of concrete 19.lapping column if neccesary 20.formwork of beam 21.stone mesonary for plinth with refer to road 22.size of column 23.distance of transporting material 24.height of concrete placed 25.thickness of west concrete
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh bhapat Ph no - 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-05

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) kolekar shyam suryakant
Exam No. 13533
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.10pm
Details of the Work Allotted to you today by the Site In-Charge marketing of construction in CREDAI exhibition
Details of how you Planned & Executed the allotted work we approached to the Rajesh construction stall in CREDAI exhibition we understand all detail of salable area, carpet area,floor plans ,elavation,flood red zone,pent house.
Details of the Construction Procedure / Activity / Technology learned today marketing of construction is important process in building development.in this process healthy communication in between customer and builder customer reaction about the project is observed.
Details of the Construction Materials learned today coarse agg.- it gives builky nature to concrete. agg.cement ratio is very imp. in mix design. rounded agg.increases worcability of concrete. angular agg.help for proper locking
Details of Environment Caring Technology / Methodology / Procedure / Product learned today cement bags not thrown in any drainage system or NALA it is stored in particular place to avoid water logging.
Details of the Construction / Engineering Drawings observed today representation plan for marketing process
Details of the Bye Laws referred today F.S.I. consumed= 0.87
Details of any Managerial Skill learned today good marketing skills
RATE ANALYSIS (Detailed Stepwise Calculations required) Brickwork for wall- height = 10 feet length = 20 feet total area =200 ft.sq. =18.58 sq.m. for 1sq.m. 45 bricks are required total bricks =836 ammount for bricks =836*6.50=5434 Rs. mason + mistri =600 Rs. (1 brass) morter required =30cu ft. ammount of morter =730 Rs.(40 pan F.A. +1 bag cement) total ammount =5434+1200+730 =7364 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 7364 Rs.per wall
Todays BUZZ Word CHECK LIST- 1.distance between column -3m. 2.distance of overlap =900mm. 3.stair case height=3m. 4.width of landing=1.2m. 5.maximum column size=0.9m.*0.15m 6.min,column size=0.6m*0.15m 7.slab tk.=150mm. 8.size of stirrups=48cm. 9.size of steel bar for heavy beam=25mm. 10.size of steel bar of curt=12mm. 11.size of anchor(spring)=2ft. 12.projection of cantiliver slab=1.2m. 13.floor ht.=3m. 14.distance bet.main bar=150mm. 15.distance bet.distribution bar=175mm. 16.no.of bars at top=2/3 17.no of bars at bottom=2/3 18.extra top=1/2 19.extra bottom=1/2 20.extra centre=1/2 21.no. of stirrups in each l/4 distance=10 22.depth of sunk slab=0.5m. 23.depth of hidden beam=0.15m. 24.depth of inverted slab=130mm. 25.tk. of column cover=10mm.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum (9850508669)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: viju128@gmail.com
Subject: 3638-05

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.water tank rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) shinde vijay namdeo
Exam No. 3638
Working Day No. 05
Date (DD/MM/YYYY) 13/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge Details of works Plastering working Observered framedoor
Details of how you Planned & Executed the allotted work Plastering is done in tow layer firstly it levelled and finished
Details of the Construction Procedure / Activity / Technology learned today We observed the tiling work if their difference in size in the tiles on error is come.how to compensate with that error . we obervered they adjust with the line . the tiling working is started with start of room and error is compensate at end corners of the room so that it should look good
Details of the Construction Materials learned today Difference between the mortar concentration required for brick wall & plastering For brick work cement 1 bag & sand 30 ghamela ratio 4:30 for outer coting plaster cement 1 bag& sand 10 gamella for inner cotting plastering cement 1 bag sand 20 gamella
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no methodology
Details of the Construction / Engineering Drawings observed today plumbing drawing
Details of the Bye Laws referred today fsi=built up area /total area < or=1
Details of any Managerial Skill learned today how to handle workers arranging the tile checking the construction materials
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis brick dimensions l=230mm w=150mm h=100mm vol=.03m3 for 1m3 brick masonary 1.25 bags of cement=250*1.25 = 312.5 rs 0.35m3 sand=0.35 *1411=493.85rs 550 bricks used =550*3.5=1925rs Total material cost =2731.35rs 3% wastage added =81.93rs Total=2813.28rs Now,1m3 =1/0.23=4.34m2=4.34*10.76=46.78ft2 Assume 47 Labour cost=47*5=235rs Total=2813.28+235=3048.28rs Fore 1m2 brick work 3048.28/47=64.85*10.76 =697.86 or 700 for 9inch thickness
Result of RATE ANALYSIS ( Rs per Unit ) 697.86 or 700 for 9inch thickness
Todays BUZZ Word 1 line out of building 2 foundation plan 3 Center line 4 Excavation 5 Steel binding as per design 6 Plinth beam 7 Column shuttering 8 Shuttering with plumb and lining 9 Starter(due to accuracy of beam) 10 Levelling tube 11 Slab and beam shuttering 12 Sun flor level portion 13 w/c ratio 14 sand aggregate conc. With respect to cementr and water 15 UCR masonary 16 Trough stone must be taken after 2-3 meter 17 Brick masonary with checking line out 18 Curing of brick(wet) 19 Brick worker daily allow about max. 1m ht 20 Plastering with plumb bob 21 Hacking of concrete surface 22 Checking Plumbing joints 23 Give slope to horizontal line for water 24 flooring level 25 earthing of electrification
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-05

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To see a brick work which is going on d8 bungalo alo sewer line laying observed. .
Details of how you Planned & Executed the allotted work First we go on side & planed to placing brick according to building line plan which is give us the site incharge.then started the work step by step,alo planed about sewer pipe line in d wing.
Details of the Construction Procedure / Activity / Technology learned today First morter is prepared for brickwork in proportion 1:6 All the brick are soaked in water so they not absorbed morter water Then marked line which on brick on laying Then morter are spred on this surface in 1 cm layer. Then side corner brick are fixed & line strip are stretched with two corner brickthen middle brick are placed along the line Also check by plumbob *for sewer lin First escavation is done on earth surface with maintain the slop of line & laid concret pipe in it with proper fixing is kept One end of sewer are conectcd to septic tank another is connected to wast water treatment plant & this water reused for gardening puporse. .
Details of the Construction Materials learned today *R C C pipe (dia 150mm) *brick(19*9*9cm) *cement concret block-(16\"*7.5\"*6\")
Details of Environment Caring Technology / Methodology / Procedure / Product learned today mortar fallen during plastering work if collected on plastic sheet then reused within 30 minitus , it will save the material & there by saving natural materiel. .
Details of the Construction / Engineering Drawings observed today Plumbing layout drawing(drainage line) .
Details of the Bye Laws referred today Parking height2.4m provided according to bylaws. .
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Pritam Patil (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-05

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudev
Exam No. 10891
Working Day No. 05
Date (DD/MM/YYYY) 13-12-2010
Site Reporting Time (HH:MM am/pm) 9:00 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To see a brick work which is going on d8 bungalo alo sewer line laying observed. .
Details of how you Planned & Executed the allotted work First we go on side & planed to placing brick according to building line plan which is give us the site incharge.then started the work step by step,alo planed about sewer pipe line in d wing.
Details of the Construction Procedure / Activity / Technology learned today First morter is prepared for brickwork in proportion 1:6 All the brick are soaked in water so they not absorbed morter water Then marked line which on brick on laying Then morter are spred on this surface in 1 cm layer. Then side corner brick are fixed & line strip are stretched with two corner brickthen middle brick are placed along the line Also check by plumbob *for sewer lin First escavation is done on earth surface with maintain the slop of line & laid concret pipe in it with proper fixing is kept One end of sewer are conectcd to septic tank another is connected to wast water treatment plant & this water reused for gardening puporse. .
Details of the Construction Materials learned today *R C C pipe (dia 150mm) *brick(19*9*9cm) *cement concret block-(16\"*7.5\"*6\")
Details of Environment Caring Technology / Methodology / Procedure / Product learned today mortar fallen during plastering work if collected on plastic sheet then reused within 30 minitus , it will save the material & there by saving natural materiel. .
Details of the Construction / Engineering Drawings observed today Plumbing layout drawing(drainage line) .
Details of the Bye Laws referred today Parking height2.4m provided according to bylaws. .
Details of any Managerial Skill learned today When we observed all bungalow we found bath cock is not in proper height we told the site incharge then he gave instruction to plumber very strikly. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: bsalman75@yahoo.com
Subject: 10888-05

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage, sardar park ,devkar panand, kolhapur
Students Name (Surname_First Name_Middle Name) baig salman samad
Exam No. 10888
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the placing of reinforcement for staircase, marking of rise and tread as per drawings and details on the side shuttering with the help of level tube.
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions of rise tread and level of the rise and tread with reference to details given to us and then we marked the rise and tread.
Details of the Construction Procedure / Activity / Technology learned today Fixing bottom of the beams supported with timber supports, placing reinforcement bars for staircase and marking of rise and tread on the side shuttering.
Details of the Construction Materials learned today Non-teak wood battens of 3”size and 12mm plywood of unix company having rate of 55/- per sq ft.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material is used on the site till now.
Details of the Construction / Engineering Drawings observed today Detail drawing of beams, staircase
Details of the Bye Laws referred today Ceiling height from floor level is 3.0m. As per bye law it is minimum 2.75m.
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for B.B.M wall 1.53*1.83*0.23 with cement mortar of 1:6“ 1. volume of BBM wall of concrete=0.64cu.m. 2. Quantity of cement mortar= take 35% of volume of BBM. =0.224cu.m. 3. Quantity of cement (volume of 1part of cement)=0.224/1+6 =0.032 cu.m. =1 bag 4. Quantity of sand for 6 parts =0.224*6 cu.m. =1.344cu.m. 5. Number of bricks =500*0.64 =320nos…….(500 nos for10 cu.m) “Rate Analysis for BBM wall with cement mortar1:6” (Considering local rates of material) 1. Cost of cement=1*250=250/-………..(250/- per bag) 2. Cost of sand=1.344*1600=2134/-…………(1600/- per cu.m.) 3. Cost of bricks=320*4=1280/-…………(4/- per brick.) 4. Labour charges=1130/- 7. Total cost= 4794/- 8.10% profit of total cost for the contractor=479.4/- 9. Total cost=5273/- 10. Rate per cu.m.= 8240/-
Result of RATE ANALYSIS ( Rs per Unit ) 8240/-
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: patilpratibha707@yahoo.in
Subject: 10896-05

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage, sardar park ,devkar panand, kolhapur
Students Name (Surname_First Name_Middle Name) Patil Pratibha Dilip
Exam No. 10896
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the placing of reinforcement for staircase, marking of rise and tread as per drawings and details on the side shuttering with the help of level tube.
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions of rise tread and level of the rise and tread with reference to details given to us and then we marked the rise and tread.
Details of the Construction Procedure / Activity / Technology learned today Fixing bottom of the beams supported with timber supports, placing reinforcement bars for staircase and marking of rise and tread on the side shuttering.
Details of the Construction Materials learned today Non-teak wood battens of 3”size and 12mm plywood of unix company having rate of 55/- per sq ft.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material is used on the site till now.
Details of the Construction / Engineering Drawings observed today Detail drawing of beams, staircase
Details of the Bye Laws referred today Ceiling height from floor level is 3.0m. As per bye law it is minimum 2.75m.
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for B.B.M wall 1.53*1.83*0.23 with cement mortar of 1:6“ 1. volume of BBM wall of concrete=0.64cu.m. 2. Quantity of cement mortar= take 35% of volume of BBM. =0.224cu.m. 3. Quantity of cement (volume of 1part of cement)=0.224/1+6 =0.032 cu.m. =1 bag 4. Quantity of sand for 6 parts =0.224*6 cu.m. =1.344cu.m. 5. Number of bricks =500*0.64 =320nos…….(500 nos for10 cu.m) “Rate Analysis for BBM wall with cement mortar1:6” (Considering local rates of material) 1. Cost of cement=1*250=250/-………..(250/- per bag) 2. Cost of sand=1.344*1600=2134/-…………(1600/- per cu.m.) 3. Cost of bricks=320*4=1280/-…………(4/- per brick.) 4. Labour charges=1130/- 7. Total cost= 4794/- 8.10% profit of total cost for the contractor=479.4/- 9. Total cost=5273/- 10. Rate per cu.m.= 8240/-
Result of RATE ANALYSIS ( Rs per Unit ) 8240/-
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-05

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage, sardar park ,devkar panand, kolhapur
Students Name (Surname_First Name_Middle Name) yadav Hrishikesh Depak
Exam No. 10885
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the placing of reinforcement for staircase, marking of rise and tread as per drawings and details on the side shuttering with the help of level tube.
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions of rise tread and level of the rise and tread with reference to details given to us and then we marked the rise and tread.
Details of the Construction Procedure / Activity / Technology learned today Fixing bottom of the beams supported with timber supports, placing reinforcement bars for staircase and marking of rise and tread on the side shuttering.
Details of the Construction Materials learned today Non-teak wood battens of 3”size and 12mm plywood of unix company having rate of 55/- per sq ft
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material is used on the site till now.
Details of the Construction / Engineering Drawings observed today Detail drawing of beams, staircase
Details of the Bye Laws referred today Ceiling height from floor level is 3.0m. As per bye law it is minimum 2.75m.
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work and self checking of measurements and markings of various sections and members.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for B.B.M wall 1.53*1.83*0.23 with cement mortar of 1:6“ 1. volume of BBM wall of concrete=0.64cu.m. 2. Quantity of cement mortar= take 35% of volume of BBM. =0.224cu.m. 3. Quantity of cement (volume of 1part of cement)=0.224/1+6 =0.032 cu.m. =1 bag 4. Quantity of sand for 6 parts =0.224*6 cu.m. =1.344cu.m. 5. Number of bricks =500*0.64 =320nos…….(500 nos for10 cu.m) “Rate Analysis for BBM wall with cement mortar1:6” (Considering local rates of material) 1. Cost of cement=1*250=250/-………..(250/- per bag) 2. Cost of sand=1.344*1600=2134/-…………(1600/- per cu.m.) 3. Cost of bricks=320*4=1280/-…………(4/- per brick.) 4. Labour charges=1130/- 7. Total cost= 4794/- 8.10% profit of total cost for the contractor=479.4/- 9. Total cost=5273/- 10. Rate per cu.m.= 8240/-
Result of RATE ANALYSIS ( Rs per Unit ) 8240/-
Todays BUZZ Word “Checklist for beam” 1. Check width of beam 2. Depth of beam 3. Diameter of top and bottom bars. 4. Diameter of stirrups bar. 5. Clear span of the beam 6. Top cover 7. Bottom cover 8. Side cover 9. Curtailment bar 10. Spacing of stirrups 11. Distance between faces of two parallel beams 12. Centre to centre distance between two supports of beam. 13 line dori of beam is in right angle from the face of column. 14. Side shuttering is in line dori or no. 15. Beam bottom is in level or no from both supports. 16. Height of beam bottom from the floor level. 17. Height of beam from floor level to the top of beam 18. Level of top of beam from both the supports. 19. Size of stirrups. 20. Length of main bars 21. Number of bars provided as per design. 22. Number of stirrups as per spacing provided. 23. Spacing of stirrups by distance of L/4 from the side supports. 24. If bent up bars are provide within the beam then the distance from the supports at which bars are to be bent. 25. If cantilever beam is provided the anchored length of bars behind the supports is sufficient or no.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13561-05

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Jadhav Sardar Swaroop J.
Exam No. 13561
Working Day No. 05
Date (DD/MM/YYYY) 13.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To check reinforcement of plinth beam. 2. To observe beam concreting.
Details of how you Planned & Executed the allotted work 1. We had seen all r.c.c. drawings of plinth beam. Then we check that reinforcment is asper proportion or not.with checking of bars,curtailed bars,extra top, extra bottom with site incharge and centering contractor. 2. We had seen concreting specifications. then we had seen actual concreting on site with site incharge.
Details of the Construction Procedure / Activity / Technology learned today 1. Reinforcment is prepared as per r.c.c. design placed and checked. 2. Formwork is casted asper size of member and placed. 3. Concrete is prepared asper specifications. 4. Concrete is placed and compacted and finished.
Details of the Construction Materials learned today Concrete ; concrete is prepared by mixing of sand ,cement,aggregate,water as per specified propotions. Then it is tested in lab to chek compressive strength of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel plates instead of plywood in formwork. this is environment friendly
Details of the Construction / Engineering Drawings observed today r.c.c. drwaings of plinth beam, center line plan of 3 bhk building.
Details of the Bye Laws referred today Minimum steps in each flight of staircase 18.
Details of any Managerial Skill learned today Checking the work strictly and correct the mistakes of labouurs to complete the work with perfection.
RATE ANALYSIS (Detailed Stepwise Calculations required) BRICKWORK ; PER SQ.M size of brick = 225*100*75 mm wall thk. = 0.23 m NO. of bricks = 33 nos. = 264.00 Rs cement = 5 kg = 1050.00 Rs sand = 0.06 cu.m = 50.00 Rs TOTAL = 1364.00 + labour cost + 2% wastage = 1600.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1600.00 Rs per sq.m
Todays BUZZ Word CHECKLIST : FOR BUILDING EXTERIOR 1. Is the approach road properly laid with proper tarring. 2. is the compound wall & gate work properly. 3. is the building painted from outside properly. 4. is the septic tank work complete. 5. is the flooring work in stilts complete. 6. are the letter boxes fixed with names of clients on it. 7. is the work of staircase completed in all respects. 8. is the pump room work completed in all respect. 9. the parking allotment done as per the approved plan. 10. are all common electrical switches & fittings working properly 11. is common TV antenna working properly. 12. is the garden work complete in all respect. 13. common toilet or washing place is provided or not. 14. society office or watchmens cabin is provided or not. 15. is the finishing in duct complete. 16. shoe to rainwater pipe is provided or not. 17. proper outlet to rainwater in duct is given or not. 18. transformer room or L.T.room etc. has been provided or not. 19. building no.& name has been painted or not. 20. are all lifts working properly. 21. are door closers for all lifts doors freely working. 22. is the collapsible type door provided for lift. 23. is the capicity board fixed in lift cabin. 24. are meters no.& flat owners names painted in meter cabinet. 25. is water meter fixed on municiple water line? initial reading.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut , mo no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-05

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Jade Madhavrao Anil
Exam No. 13560
Working Day No. 05
Date (DD/MM/YYYY) 13.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To check reinforcement of plinth beam. 2. To observe beam concreting.
Details of how you Planned & Executed the allotted work 1. We had seen all r.c.c. drawings of plinth beam. Then we check that reinforcment is asper proportion or not.with checking of bars,curtailed bars,extra top, extra bottom with site incharge and centering contractor. 2. We had seen concreting specifications. then we had seen actual concreting on site with site incharge.
Details of the Construction Procedure / Activity / Technology learned today 1. Reinforcment is prepared as per r.c.c. design placed and checked. 2. Formwork is casted asper size of member and placed. 3. Concrete is prepared asper specifications. 4. Concrete is placed and compacted and finished.
Details of the Construction Materials learned today Concrete ; concrete is prepared by mixing of sand ,cement,aggregate,water as per specified propotions. Then it is tested in lab to chek compressive strength of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel plates instead of plywood in formwork. this is environment friendly
Details of the Construction / Engineering Drawings observed today r.c.c. drwaings of plinth beam, center line plan of 3 bhk building.
Details of the Bye Laws referred today Minimum steps in each flight of staircase 18.
Details of any Managerial Skill learned today Checking the work strictly and correct the mistakes of labouurs to complete the work with perfection.
RATE ANALYSIS (Detailed Stepwise Calculations required) BRICKWORK ; PER SQ.M size of brick = 225*100*75 mm wall thk. = 0.23 m NO. of bricks = 33 nos. = 264.00 Rs cement = 5 kg = 1050.00 Rs sand = 0.06 cu.m = 50.00 Rs TOTAL = 1364.00 + labour cost + 2% wastage = 1600.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1600.00 Rs per sq.m
Todays BUZZ Word CHECKLIST : FOR BUILDING EXTERIOR 1. Is the approach road properly laid with proper tarring. 2. is the compound wall & gate work properly. 3. is the building painted from outside properly. 4. is the septic tank work complete. 5. is the flooring work in stilts complete. 6. are the letter boxes fixed with names of clients on it. 7. is the work of staircase completed in all respects. 8. is the pump room work completed in all respect. 9. the parking allotment done as per the approved plan. 10. are all common electrical switches & fittings working properly 11. is common TV antenna working properly. 12. is the garden work complete in all respect. 13. common toilet or washing place is provided or not. 14. society office or watchmens cabin is provided or not. 15. is the finishing in duct complete. 16. shoe to rainwater pipe is provided or not. 17. proper outlet to rainwater in duct is given or not. 18. transformer room or L.T.room etc. has been provided or not. 19. building no.& name has been painted or not. 20. are all lifts working properly. 21. are door closers for all lifts doors freely working. 22. is the collapsible type door provided for lift. 23. is the capicity board fixed in lift cabin. 24. are meters no.& flat owners names painted in meter cabinet. 25. is water meter fixed on municiple water line? initial reading.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut , mo no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-05

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) katral raju maruti
Exam No. 13562
Working Day No. 05
Date (DD/MM/YYYY) 13.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To check reinforcement of plinth beam. 2. To observe beam concreting.
Details of how you Planned & Executed the allotted work 1. We had seen all r.c.c. drawings of plinth beam. Then we check that reinforcment is asper proportion or not.with checking of bars,curtailed bars,extra top, extra bottom with site incharge and centering contractor. 2. We had seen concreting specifications. then we had seen actual concreting on site with site incharge.
Details of the Construction Procedure / Activity / Technology learned today 1. Reinforcment is prepared as per r.c.c. design placed and checked. 2. Formwork is casted asper size of member and placed. 3. Concrete is prepared asper specifications. 4. Concrete is placed and compacted and finished.
Details of the Construction Materials learned today Concrete ; concrete is prepared by mixing of sand ,cement,aggregate,water as per specified propotions. Then it is tested in lab to chek compressive strength of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel plates instead of plywood in formwork. this is environment friendly
Details of the Construction / Engineering Drawings observed today r.c.c. drwaings of plinth beam, center line plan of 3 bhk building.
Details of the Bye Laws referred today Minimum steps in each flight of staircase 18.
Details of any Managerial Skill learned today Checking the work strictly and correct the mistakes of labouurs to complete the work with perfection.
RATE ANALYSIS (Detailed Stepwise Calculations required) BRICKWORK ; PER SQ.M size of brick = 225*100*75 mm wall thk. = 0.23 m NO. of bricks = 33 nos. = 264.00 Rs cement = 5 kg = 1050.00 Rs sand = 0.06 cu.m = 50.00 Rs TOTAL = 1364.00 + labour cost + 2% wastage = 1600.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1600.00 Rs per sq.m
Todays BUZZ Word CHECKLIST : FOR BUILDING EXTERIOR 1. Is the approach road properly laid with proper tarring. 2. is the compound wall & gate work properly. 3. is the building painted from outside properly. 4. is the septic tank work complete. 5. is the flooring work in stilts complete. 6. are the letter boxes fixed with names of clients on it. 7. is the work of staircase completed in all respects. 8. is the pump room work completed in all respect. 9. the parking allotment done as per the approved plan. 10. are all common electrical switches & fittings working properly 11. is common TV antenna working properly. 12. is the garden work complete in all respect. 13. common toilet or washing place is provided or not. 14. society office or watchmens cabin is provided or not. 15. is the finishing in duct complete. 16. shoe to rainwater pipe is provided or not. 17. proper outlet to rainwater in duct is given or not. 18. transformer room or L.T.room etc. has been provided or not. 19. building no.& name has been painted or not. 20. are all lifts working properly. 21. are door closers for all lifts doors freely working. 22. is the collapsible type door provided for lift. 23. is the capicity board fixed in lift cabin. 24. are meters no.& flat owners names painted in meter cabinet. 25. is water meter fixed on municiple water line? initial reading.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut , mo no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-05

Company Name Chougule Sawant Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) tirmare pradnya ashok
Exam No. 13572
Working Day No. 05
Date (DD/MM/YYYY) 13.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To check reinforcement of plinth beam. 2. To observe beam concreting.
Details of how you Planned & Executed the allotted work 1. We had seen all r.c.c. drawings of plinth beam. Then we check that reinforcment is asper proportion or not.with checking of bars,curtailed bars,extra top, extra bottom with site incharge and centering contractor. 2. We had seen concreting specifications. then we had seen actual concreting on site with site incharge.
Details of the Construction Procedure / Activity / Technology learned today 1. Reinforcment is prepared as per r.c.c. design placed and checked. 2. Formwork is casted asper size of member and placed. 3. Concrete is prepared asper specifications. 4. Concrete is placed and compacted and finished.
Details of the Construction Materials learned today Concrete ; concrete is prepared by mixing of sand ,cement,aggregate,water as per specified propotions. Then it is tested in lab to chek compressive strength of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel plates instead of plywood in formwork. this is environment friendly
Details of the Construction / Engineering Drawings observed today r.c.c. drwaings of plinth beam, center line plan of 3 bhk building.
Details of the Bye Laws referred today Minimum steps in each flight of staircase 18.
Details of any Managerial Skill learned today Checking the work strictly and correct the mistakes of labouurs to complete the work with perfection.
RATE ANALYSIS (Detailed Stepwise Calculations required) BRICKWORK ; PER SQ.M size of brick = 225*100*75 mm wall thk. = 0.23 m NO. of bricks = 33 nos. = 264.00 Rs cement = 5 kg = 1050.00 Rs sand = 0.06 cu.m = 50.00 Rs TOTAL = 1364.00 + labour cost + 2% wastage = 1600.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1600.00 Rs per sq.m
Todays BUZZ Word CHECKLIST : FOR BUILDING EXTERIOR 1. Is the approach road properly laid with proper tarring. 2. is the compound wall & gate work properly. 3. is the building painted from outside properly. 4. is the septic tank work complete. 5. is the flooring work in stilts complete. 6. are the letter boxes fixed with names of clients on it. 7. is the work of staircase completed in all respects. 8. is the pump room work completed in all respect. 9. the parking allotment done as per the approved plan. 10. are all common electrical switches & fittings working properly 11. is common TV antenna working properly. 12. is the garden work complete in all respect. 13. common toilet or washing place is provided or not. 14. society office or watchmens cabin is provided or not. 15. is the finishing in duct complete. 16. shoe to rainwater pipe is provided or not. 17. proper outlet to rainwater in duct is given or not. 18. transformer room or L.T.room etc. has been provided or not. 19. building no.& name has been painted or not. 20. are all lifts working properly. 21. are door closers for all lifts doors freely working. 22. is the collapsible type door provided for lift. 23. is the capicity board fixed in lift cabin. 24. are meters no.& flat owners names painted in meter cabinet. 25. is water meter fixed on municiple water line? initial reading.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge 8Swapnil Raut , mo no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558-05

Company Name Bhima Builders & Developers
Project Name & Site Address Shree samarth nagar, nave balinga.
Students Name (Surname_First Name_Middle Name) Chavan Shivprasad Prakash
Exam No. 13558
Working Day No. 05
Date (DD/MM/YYYY) 13.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To check reinforcement of plinth beam. 2. To observe beam concreting.
Details of how you Planned & Executed the allotted work 1. We had seen all r.c.c. drawings of plinth beam. Then we check that reinforcment is asper proportion or not.with checking of bars,curtailed bars,extra top, extra bottom with site incharge and centering contractor. 2. We had seen concreting specifications. then we had seen actual concreting on site with site incharge.
Details of the Construction Procedure / Activity / Technology learned today BEAM CONCRETING ; 1. Reinforcment is prepared as per r.c.c. design placed and checked. 2. Formwork is casted asper size of member and placed. 3. Concrete is prepared asper specifications. 4. Concrete is placed and compacted and finished.
Details of the Construction Materials learned today Concrete ; concrete is prepared by mixing of sand ,cement,aggregate,water as per specified propotions. Then it is tested in lab to chek compressive strength of concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of steel plates instead of plywood in formwork. this is environment friendly.
Details of the Construction / Engineering Drawings observed today r.c.c. drwaings of plinth beam, center line plan of 3 bhk building.
Details of the Bye Laws referred today Minimum steps in each flight of staircase 18.
Details of any Managerial Skill learned today Checking the work strictly and correct the mistakes of labouurs to complete the work with perfection.
RATE ANALYSIS (Detailed Stepwise Calculations required) BRICKWORK ; PER SQ.M size of brick = 225*100*75 mm wall thk. = 0.23 m NO. of bricks = 33 nos. = 264.00 Rs cement = 5 kg = 1050.00 Rs sand = 0.06 cu.m = 50.00 Rs TOTAL = 1364.00 + labour cost + 2% wastage = 1600.00 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1600.00 Rs per sq.m
Todays BUZZ Word CHECKLIST : FOR BUILDING EXTERIOR 1. Is the approach road properly laid with proper tarring. 2. is the compound wall & gate work properly. 3. is the building painted from outside properly. 4. is the septic tank work complete. 5. is the flooring work in stilts complete. 6. are the letter boxes fixed with names of clients on it. 7. is the work of staircase completed in all respects. 8. is the pump room work completed in all respect. 9. the parking allotment done as per the approved plan. 10. are all common electrical switches & fittings working properly 11. is common TV antenna working properly. 12. is the garden work complete in all respect. 13. common toilet or washing place is provided or not. 14. society office or watchmens cabin is provided or not. 15. is the finishing in duct complete. 16. shoe to rainwater pipe is provided or not. 17. proper outlet to rainwater in duct is given or not. 18. transformer room or L.T.room etc. has been provided or not. 19. building no.& name has been painted or not. 20. are all lifts working properly. 21. are door closers for all lifts doors freely working. 22. is the collapsible type door provided for lift. 23. is the capicity board fixed in lift cabin. 24. are meters no.& flat owners names painted in meter cabinet. 25. is water meter fixed on municiple water line? initial reading.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut , mo no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-05

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Redekar Shantanu Ravindra
Exam No. 13566
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the construction of stair case.
Details of how you Planned & Executed the allotted work We take the plan of stair case and along the plan we observe the dimension of stair case and requirement of reinforcement as well as size of steel bars and their spacing.
Details of the Construction Procedure / Activity / Technology learned today Open well stair case provided. First place the plywood for the size of stair case and apply oil to these. Top of plywood steel bars are provided at same spacing as in drawing. Form landing another steel is provided at top at some distance of early provided bars . Bottom provided steel bars bent at top where the junction of beam and continue for slab. Another steel bars provided from slab above the early provided steel bars. For main bar distribution steel is provided at spacing. Steel work is done then formwork is provided as size of trade and rise is given in plan. After the formwork is done then concreting process is start. Stair Case is constructed the formwork is removed After 15 Days because it gives strength.
Details of the Construction Materials learned today Marine Plywood Wood Steel bars - main bars, distributory bars. Cement 20M grade Aggregate 20 & 25 mm Sand Admixture - Super plasticizers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today To avoid minimum cutting of steel bars.
Details of the Construction / Engineering Drawings observed today Stair Case Drawing Plan of stair case Reinforcement details Size of steel bar which are provided Spacing For stair case
Details of the Bye Laws referred today Stair Case Details Minimum width - 2.0 m Riser - 150 mm Trade - 300 mm Landing - 2.0 m Minimum Head-room - 2.2 m
Details of any Managerial Skill learned today To check bars are properly bent at junction of slab. Rise and trade are in proportion. Any small gap between the formwork.
RATE ANALYSIS (Detailed Stepwise Calculations required) For room size - 2m X 2m Height - 1 m. 0.23 m Brick Masonry Cement masonry 1 : 4 Length of one side - 2.46 m Size of Brick - 19 X 9 X 9 cum Size of brick with mortar - 20 X 10 X 10 cum. Therefore, 2.46 X 0.23 X 1.00 X 2.00 = 1.13 2.00 X 0.23 X 1.00 X 2.00 = 0.92 Total = 2.05 cum. Nos. of brick = 2.05 / 0.2 X 0.1 X 0.1 = 1026 nos. Actual volume of brick = 1026 X 0.19 X 0.09 X 0.09 = 1.58 cum. Quantity of mortar = 2.05 – 1.58 = 0.47 cum. Add 10 % Of Wastage = 0.517 cum weight in condition. Add 25% of Dry weight = 0.646 cum in condition. For 1 : 4 proportion. ( 1 + 4 = 5 ) 0.646/5 X 1 = 0.12 cement / cum. - 4 bags. 0.646/5 X 4 = 0.516 sand / cum. SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 4 bags 250.00/- 1000.00/- b) sand 0.516 cum 850.00/- (per cum) 440.00/- c) Brick 1026 no. 7.00/- (per brick) 7182.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) male mazdur 2 no. 200.00/- 400.00/- d) bhisti 1 no. 120.00/- 120.00/- 3 Centering and lum sum 250/- shuttering 4 Others _ TOTAL 9692.00/- 5 Tools and plant @ 1.5% ----------------------- 145.50/- on total 6 Water charges @ 1.0% ----------------------- 97.00/- on total TOTAL(A) 9935.00/- 7 Overhead and profit @ 15% on tOtal A ----------------------- 1490.00/- -------------------------------------------------------------------------- TOTAL = 11425.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 3111.00/- per cu.m.
Todays BUZZ Word CHECKLIST- A) Wall and ceilling – 1) Are all crack in wall properly filled? 2) Are all signs of dampness/ leakage on walls removed? 3) Are all patches or black strips observed in painting attended? 4) Are loose patches in ceiling and walls ractified ? 5) Are all the corneres sharp and finished ? B) Doors and windows- 1) Are all doors/ windows, opening and closing smoothly? 2) Are all glass pannels fitted properly? 3) Is an eyepiece provided ? 4) Are all the gaps between door / window frame and walls properly filled ? 5) Are screws to all the fittings are provided ? C) Tiling – 1) Is the floor in proper level ? 2) Are the flooring tiles of one type ? 3) Are glazed tiles cleaned and finished properly ? 4) Is proper slope given to bathroom ? 5) Is proper slope given to kitchen platform ? D) Plumbing and sanitation – 1) Are all fixturs like bib taps , mixer are fixed properly and at proper height ? 2) Is proper cleaning done for all sanitary fixtures ? 3) Is there any leakage from taps ? 4) Is there proper pressure to all taps ? 5) Is the P-trap of W.C. properly cleaned ? E) Electification- 1) Is individual meter allotted to the flat ? 2) Is the earthing connection tested for working condition ? 3) Is the main switch fixed in meter cabinet ? 4) All the fittings fixed on board are in line and level or not ? 5) Is the position and quantity of electrical points as per working drawing.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-05

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Mohare Vishal Bhalchandra
Exam No. 13564
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the construction of stair case.
Details of how you Planned & Executed the allotted work We take the plan of stair case and along the plan we observe the dimension of stair case and requirement of reinforcement as well as size of steel bars and their spacing.
Details of the Construction Procedure / Activity / Technology learned today Open well stair case provided. First place the plywood for the size of stair case and apply oil to these. Top of plywood steel bars are provided at same spacing as in drawing. Form landing another steel is provided at top at some distance of early provided bars . Bottom provided steel bars bent at top where the junction of beam and continue for slab. Another steel bars provided from slab above the early provided steel bars. For main bar distribution steel is provided at spacing. Steel work is done then formwork is provided as size of trade and rise is given in plan. After the formwork is done then concreting process is start. Stair Case is constructed the formwork is removed After 15 Days because it gives strength.
Details of the Construction Materials learned today Marine Plywood Wood Steel bars - main bars, distributory bars. Cement 20M grade Aggregate 20 & 25 mm Sand Admixture - Super plasticizers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today To avoid minimum cutting of steel bars.
Details of the Construction / Engineering Drawings observed today Stair Case Drawing Plan of stair case Reinforcement details Size of steel bar which are provided Spacing For stair case
Details of the Bye Laws referred today Stair Case Details Minimum width - 2.0 m Riser - 150 mm Trade - 300 mm Landing - 2.0 m Minimum Head-room - 2.2 m
Details of any Managerial Skill learned today To check bars are properly bent at junction of slab. Rise and trade are in proportion. Any small gap between the formwork.
RATE ANALYSIS (Detailed Stepwise Calculations required) For room size - 2m X 2m Height - 1 m. 0.23 m Brick Masonry Cement masonry 1 : 4 Length of one side - 2.46 m Size of Brick - 19 X 9 X 9 cum Size of brick with mortar - 20 X 10 X 10 cum. Therefore, 2.46 X 0.23 X 1.00 X 2.00 = 1.13 2.00 X 0.23 X 1.00 X 2.00 = 0.92 Total = 2.05 cum. Nos. of brick = 2.05 / 0.2 X 0.1 X 0.1 = 1026 nos. Actual volume of brick = 1026 X 0.19 X 0.09 X 0.09 = 1.58 cum. Quantity of mortar = 2.05 – 1.58 = 0.47 cum. Add 10 % Of Wastage = 0.517 cum weight in condition. Add 25% of Dry weight = 0.646 cum in condition. For 1 : 4 proportion. ( 1 + 4 = 5 ) 0.646/5 X 1 = 0.12 cement / cum. - 4 bags. 0.646/5 X 4 = 0.516 sand / cum. SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 4 bags 250.00/- 1000.00/- b) sand 0.516 cum 850.00/- (per cum) 440.00/- c) Brick 1026 no. 7.00/- (per brick) 7182.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) male mazdur 2 no. 200.00/- 400.00/- d) bhisti 1 no. 120.00/- 120.00/- 3 Centering and lum sum 250/- shuttering 4 Others _ TOTAL 9692.00/- 5 Tools and plant @ 1.5% ----------------------- 145.50/- on total 6 Water charges @ 1.0% ----------------------- 97.00/- on total TOTAL(A) 9935.00/- 7 Overhead and profit @ 15% on tOtal A ----------------------- 1490.00/- -------------------------------------------------------------------------- TOTAL = 11425.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 3111.00/- per cu.m.
Todays BUZZ Word CHECKLIST- A) Wall and ceilling – 1) Are all crack in wall properly filled? 2) Are all signs of dampness/ leakage on walls removed? 3) Are all patches or black strips observed in painting attended? 4) Are loose patches in ceiling and walls ractified ? 5) Are all the corneres sharp and finished ? B) Doors and windows- 1) Are all doors/ windows, opening and closing smoothly? 2) Are all glass pannels fitted properly? 3) Is an eyepiece provided ? 4) Are all the gaps between door / window frame and walls properly filled ? 5) Are screws to all the fittings are provided ? C) Tiling – 1) Is the floor in proper level ? 2) Are the flooring tiles of one type ? 3) Are glazed tiles cleaned and finished properly ? 4) Is proper slope given to bathroom ? 5) Is proper slope given to kitchen platform ? D) Plumbing and sanitation – 1) Are all fixturs like bib taps , mixer are fixed properly and at proper height ? 2) Is proper cleaning done for all sanitary fixtures ? 3) Is there any leakage from taps ? 4) Is there proper pressure to all taps ? 5) Is the P-trap of W.C. properly cleaned ? E) Electification- 1) Is individual meter allotted to the flat ? 2) Is the earthing connection tested for working condition ? 3) Is the main switch fixed in meter cabinet ? 4) All the fittings fixed on board are in line and level or not ? 5) Is the position and quantity of electrical points as per working drawing.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-05

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the construction of stair case.
Details of how you Planned & Executed the allotted work We take the plan of stair case and along the plan we observe the dimension of stair case and requirement of reinforcement as well as size of steel bars and their spacing.
Details of the Construction Procedure / Activity / Technology learned today Open well stair case provided. First place the plywood for the size of stair case and apply oil to these. Top of plywood steel bars are provided at same spacing as in drawing. Form landing another steel is provided at top at some distance of early provided bars . Bottom provided steel bars bent at top where the junction of beam and continue for slab. Another steel bars provided from slab above the early provided steel bars. For main bar distribution steel is provided at spacing. Steel work is done then formwork is provided as size of trade and rise is given in plan. After the formwork is done then concreting process is start. Stair Case is constructed the formwork is removed After 15 Days because it gives strength.
Details of the Construction Materials learned today Marine Plywood Wood Steel bars - main bars, distributory bars. Cement 20M grade Aggregate 20 & 25 mm Sand Admixture - Super plasticizers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today To avoid minimum cutting of steel bars.
Details of the Construction / Engineering Drawings observed today Stair Case Drawing Plan of stair case Reinforcement details Size of steel bar which are provided Spacing For stair case
Details of the Bye Laws referred today Stair Case Details Minimum width - 2.0 m Riser - 150 mm Trade - 300 mm Landing - 2.0 m Minimum Head-room - 2.2 m
Details of any Managerial Skill learned today To check bars are properly bent at junction of slab. Rise and trade are in proportion. Any small gap between the formwork.
RATE ANALYSIS (Detailed Stepwise Calculations required) For room size - 2m X 2m Height - 1 m. 0.23 m Brick Masonry Cement masonry 1 : 4 Length of one side - 2.46 m Size of Brick - 19 X 9 X 9 cum Size of brick with mortar - 20 X 10 X 10 cum. Therefore, 2.46 X 0.23 X 1.00 X 2.00 = 1.13 2.00 X 0.23 X 1.00 X 2.00 = 0.92 Total = 2.05 cum. Nos. of brick = 2.05 / 0.2 X 0.1 X 0.1 = 1026 nos. Actual volume of brick = 1026 X 0.19 X 0.09 X 0.09 = 1.58 cum. Quantity of mortar = 2.05 – 1.58 = 0.47 cum. Add 10 % Of Wastage = 0.517 cum weight in condition. Add 25% of Dry weight = 0.646 cum in condition. For 1 : 4 proportion. ( 1 + 4 = 5 ) 0.646/5 X 1 = 0.12 cement / cum. - 4 bags. 0.646/5 X 4 = 0.516 sand / cum. SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 4 bags 250.00/- 1000.00/- b) sand 0.516 cum 850.00/- (per cum) 440.00/- c) Brick 1026 no. 7.00/- (per brick) 7182.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) male mazdur 2 no. 200.00/- 400.00/- d) bhisti 1 no. 120.00/- 120.00/- 3 Centering and lum sum 250/- shuttering 4 Others _ TOTAL 9692.00/- 5 Tools and plant @ 1.5% ----------------------- 145.50/- on total 6 Water charges @ 1.0% ----------------------- 97.00/- on total TOTAL(A) 9935.00/- 7 Overhead and profit @ 15% on tOtal A ----------------------- 1490.00/- -------------------------------------------------------------------------- TOTAL = 11425.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 3111.00/- per cu.m.
Todays BUZZ Word CHECKLIST- A) Wall and ceilling – 1) Are all crack in wall properly filled? 2) Are all signs of dampness/ leakage on walls removed? 3) Are all patches or black strips observed in painting attended? 4) Are loose patches in ceiling and walls ractified ? 5) Are all the corneres sharp and finished ? B) Doors and windows- 1) Are all doors/ windows, opening and closing smoothly? 2) Are all glass pannels fitted properly? 3) Is an eyepiece provided ? 4) Are all the gaps between door / window frame and walls properly filled ? 5) Are screws to all the fittings are provided ? C) Tiling – 1) Is the floor in proper level ? 2) Are the flooring tiles of one type ? 3) Are glazed tiles cleaned and finished properly ? 4) Is proper slope given to bathroom ? 5) Is proper slope given to kitchen platform ? D) Plumbing and sanitation – 1) Are all fixturs like bib taps , mixer are fixed properly and at proper height ? 2) Is proper cleaning done for all sanitary fixtures ? 3) Is there any leakage from taps ? 4) Is there proper pressure to all taps ? 5) Is the P-trap of W.C. properly cleaned ? E) Electification- 1) Is individual meter allotted to the flat ? 2) Is the earthing connection tested for working condition ? 3) Is the main switch fixed in meter cabinet ? 4) All the fittings fixed on board are in line and level or not ? 5) Is the position and quantity of electrical points as per working drawin
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-05

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.DEVELOPERS , PREETAM RESIDENCY , SAMRAT-NAGAR
Students Name (Surname_First Name_Middle Name) Shinde Sagar Arvind
Exam No. 13568
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Prepare the detailed estimate of given project. .
Details of how you Planned & Executed the allotted work We work individually for different items and then combine all values and find the estimate of project with the help of current D.S.R. .
Details of the Construction Procedure / Activity / Technology learned today Construction activity:- Tiling:- (Mosaic tiles) 1) Prepare the cement slurry in the ratio of 1.5 bags to 100 Lit of water approximately. start fixing tiles from the reference line and reference tiles diagonally. 2)Spread the cement slurry of a honey like consistency, on the mortar bed, over area as much as could be covered with half an hour. 3)Match all the four corner of the tiles properly with the help of wooden mallet. 4)Fix the mosaic tiles in the particular sequence for better results and fine joints. 5)Except for balconies, bath and toilet complete the flooring of one unit per day, for better bonding and uniform and quick work. 6)If there are are two types of tiling( i.e. living room with white and other room in gray) break the joint at the shutter groove line/ on the inside edge of the masonry in other room, if door is not provided. 7)After completing the tiling work of the floor, check the overall level. Any unevenness can be rectified with wooden mallet. 8)The gap between walls and floor are fixed with cut pieces of the mosaic tile. 9)Clean the floor and don\'t allow anybody to enter the flat for at least 24hrs. 10)Next day fill the gaps/joints between the tiles with cement slurry. 11) Then cure the flooring and skirting for at least 14days. .
Details of the Construction Materials learned today Tiles:- Types:- 1)Mosaic 2)Cuddappa 3)Marble 4)Glazed Size:- As per the requirement of unit and market availability. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Mortar falling down during plaster work if reused again within 30min, it will save the materials and thereby it will save the natural resources of those material. .
Details of the Construction / Engineering Drawings observed today Interior Decorator Drawing. -For the details of flooring and other furniture and electrification requirement. .
Details of the Bye Laws referred today Minimum length and width of rooms for residential building. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.P.Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: Rohit_patil361@rediffmail.com
Subject: 13565-05

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Patil Rohit Ashok
Exam No. 13565
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the construction of stair case.
Details of how you Planned & Executed the allotted work We take the plan of stair case and along the plan we observe the dimension of stair case and requirement of reinforcement as well as size of steel bars and their spacing.
Details of the Construction Procedure / Activity / Technology learned today Open well stair case provided. First place the plywood for the size of stair case and apply oil to these. Top of plywood steel bars are provided at same spacing as in drawing. Form landing another steel is provided at top at some distance of early provided bars . Bottom provided steel bars bent at top where the junction of beam and continue for slab. Another steel bars provided from slab above the early provided steel bars. For main bar distribution steel is provided at spacing. Steel work is done then formwork is provided as size of trade and rise is given in plan. After the formwork is done then concreting process is start. Stair Case is constructed the formwork is removed After 15 Days because it gives strength.
Details of the Construction Materials learned today Marine Plywood Wood Steel bars - main bars, distributory bars. Cement 20M grade Aggregate 20 & 25 mm Sand Admixture - Super plasticizers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today To avoid minimum cutting of steel bars.
Details of the Construction / Engineering Drawings observed today Stair Case Drawing Plan of stair case Reinforcement details Size of steel bar which are provided Spacing For stair case
Details of the Bye Laws referred today Stair Case Details Minimum width - 2.0 m Riser - 150 mm Trade - 300 mm Landing - 2.0 m Minimum Head-room - 2.2 m
Details of any Managerial Skill learned today To check bars are properly bent at junction of slab. Rise and trade are in proportion. Any small gap between the formwork.
RATE ANALYSIS (Detailed Stepwise Calculations required) For room size - 2m X 2m Height - 1 m. 0.23 m Brick Masonry Cement masonry 1 : 4 Length of one side - 2.46 m Size of Brick - 19 X 9 X 9 cum Size of brick with mortar - 20 X 10 X 10 cum. Therefore, 2.46 X 0.23 X 1.00 X 2.00 = 1.13 2.00 X 0.23 X 1.00 X 2.00 = 0.92 Total = 2.05 cum. Nos. of brick = 2.05 / 0.2 X 0.1 X 0.1 = 1026 nos. Actual volume of brick = 1026 X 0.19 X 0.09 X 0.09 = 1.58 cum. Quantity of mortar = 2.05 – 1.58 = 0.47 cum. Add 10 % Of Wastage = 0.517 cum weight in condition. Add 25% of Dry weight = 0.646 cum in condition. For 1 : 4 proportion. ( 1 + 4 = 5 ) 0.646/5 X 1 = 0.12 cement / cum. - 4 bags. 0.646/5 X 4 = 0.516 sand / cum. SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 4 bags 250.00/- 1000.00/- b) sand 0.516 cum 850.00/- (per cum) 440.00/- c) Brick 1026 no. 7.00/- (per brick) 7182.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) male mazdur 2 no. 200.00/- 400.00/- d) bhisti 1 no. 120.00/- 120.00/- 3 Centering and lum sum 250/- shuttering 4 Others _ TOTAL 9692.00/- 5 Tools and plant @ 1.5% ----------------------- 145.50/- on total 6 Water charges @ 1.0% ----------------------- 97.00/- on total TOTAL(A) 9935.00/- 7 Overhead and profit @ 15% on tOtal A ----------------------- 1490.00/- -------------------------------------------------------------------------- TOTAL = 11425.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 3111.00/- per cu.m.
Todays BUZZ Word CHECKLIST- A) Wall and ceilling – 1) Are all crack in wall properly filled? 2) Are all signs of dampness/ leakage on walls removed? 3) Are all patches or black strips observed in painting attended? 4) Are loose patches in ceiling and walls ractified ? 5) Are all the corneres sharp and finished ? B) Doors and windows- 1) Are all doors/ windows, opening and closing smoothly? 2) Are all glass pannels fitted properly? 3) Is an eyepiece provided ? 4) Are all the gaps between door / window frame and walls properly filled ? 5) Are screws to all the fittings are provided ? C) Tiling – 1) Is the floor in proper level ? 2) Are the flooring tiles of one type ? 3) Are glazed tiles cleaned and finished properly ? 4) Is proper slope given to bathroom ? 5) Is proper slope given to kitchen platform ? D) Plumbing and sanitation – 1) Are all fixturs like bib taps , mixer are fixed properly and at proper height ? 2) Is proper cleaning done for all sanitary fixtures ? 3) Is there any leakage from taps ? 4) Is there proper pressure to all taps ? 5) Is the P-trap of W.C. properly cleaned ? E) Electification- 1) Is individual meter allotted to the flat ? 2) Is the earthing connection tested for working condition ? 3) Is the main switch fixed in meter cabinet ? 4) All the fittings fixed on board are in line and level or not ? 5) Is the position and quantity of electrical points as per working drawing.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-05

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.DEVELOPERS , PREETAM RESIDENCY , SAMRAT-NAGAR
Students Name (Surname_First Name_Middle Name) Shivtare Prabhakar Chandrakant
Exam No. 13569
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Prepare the detailed estimate of given project. .
Details of how you Planned & Executed the allotted work We work individually for different items and then combine all values and find the estimate of project with the help of current D.S.R. .
Details of the Construction Procedure / Activity / Technology learned today Construction activity:- Tiling:- (Mosaic tiles) 1) Prepare the cement slurry in the ratio of 1.5 bags to 100 Lit of water approximately. start fixing tiles from the reference line and reference tiles diagonally. 2)Spread the cement slurry of a honey like consistency, on the mortar bed, over area as much as could be covered with half an hour. 3)Match all the four corner of the tiles properly with the help of wooden mallet. 4)Fix the mosaic tiles in the particular sequence for better results and fine joints. 5)Except for balconies, bath and toilet complete the flooring of one unit per day, for better bonding and uniform and quick work. 6)If there are are two types of tiling( i.e. living room with white and other room in gray) break the joint at the shutter groove line/ on the inside edge of the masonry in other room, if door is not provided. 7)After completing the tiling work of the floor, check the overall level. Any unevenness can be rectified with wooden mallet. 8)The gap between walls and floor are fixed with cut pieces of the mosaic tile. 9)Clean the floor and don\'t allow anybody to enter the flat for at least 24hrs. 10)Next day fill the gaps/joints between the tiles with cement slurry. 11) Then cure the flooring and skirting for at least 14days. .
Details of the Construction Materials learned today Tiles:- Types:- 1)Mosaic 2)Cuddappa 3)Marble 4)Glazed Size:- As per the requirement of unit and market availability. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Mortar falling down during plaster work if reused again within 30min, it will save the materials and thereby it will save the natural resources of those material. .
Details of the Construction / Engineering Drawings observed today Interior Decorator Drawing. -For the details of flooring and other furniture and electrification requirement. .
Details of the Bye Laws referred today Minimum length and width of rooms for residential building. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.P.Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 13567-05

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.DEVELOPERS , PREETAM RESIDENCY , SAMRAT-NAGAR
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Prepare the detailed estimate of given project. .
Details of how you Planned & Executed the allotted work We work individually for different items and then combine all values and find the estimate of project with the help of current D.S.R. .
Details of the Construction Procedure / Activity / Technology learned today Construction activity:- Tiling:- (Mosaic tiles) 1) Prepare the cement slurry in the ratio of 1.5 bags to 100 Lit of water approximately. start fixing tiles from the reference line and reference tiles diagonally. 2)Spread the cement slurry of a honey like consistency, on the mortar bed, over area as much as could be covered with half an hour. 3)Match all the four corner of the tiles properly with the help of wooden mallet. 4)Fix the mosaic tiles in the particular sequence for better results and fine joints. 5)Except for balconies, bath and toilet complete the flooring of one unit per day, for better bonding and uniform and quick work. 6)If there are are two types of tiling( i.e. living room with white and other room in gray) break the joint at the shutter groove line/ on the inside edge of the masonry in other room, if door is not provided. 7)After completing the tiling work of the floor, check the overall level. Any unevenness can be rectified with wooden mallet. 8)The gap between walls and floor are fixed with cut pieces of the mosaic tile. 9)Clean the floor and don\'t allow anybody to enter the flat for at least 24hrs. 10)Next day fill the gaps/joints between the tiles with cement slurry. 11) Then cure the flooring and skirting for at least 14days. .
Details of the Construction Materials learned today Tiles:- Types:- 1)Mosaic 2)Cuddappa 3)Marble 4)Glazed Size:- As per the requirement of unit and market availability. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Mortar falling down during plaster work if reused again within 30min, it will save the materials and thereby it will save the natural resources of those material. .
Details of the Construction / Engineering Drawings observed today Interior Decorator Drawing. -For the details of flooring and other furniture and electrification requirement. .
Details of the Bye Laws referred today Minimum length and width of rooms for residential building. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.P.Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-05

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.DEVELOPERS , PREETAM RESIDENCY , SAMRAT-NAGAR
Students Name (Surname_First Name_Middle Name) Sutar Namdev Rangnath
Exam No. 13571
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Prepare the detailed estimate of given project. .
Details of how you Planned & Executed the allotted work We work individually for different items and then combine all values and find the estimate of project with the help of current D.S.R. .
Details of the Construction Procedure / Activity / Technology learned today Construction activity:- Tiling:- (Mosaic tiles) 1) Prepare the cement slurry in the ratio of 1.5 bags to 100 Lit of water approximately. start fixing tiles from the reference line and reference tiles diagonally. 2)Spread the cement slurry of a honey like consistency, on the mortar bed, over area as much as could be covered with half an hour. 3)Match all the four corner of the tiles properly with the help of wooden mallet. 4)Fix the mosaic tiles in the particular sequence for better results and fine joints. 5)Except for balconies, bath and toilet complete the flooring of one unit per day, for better bonding and uniform and quick work. 6)If there are are two types of tiling( i.e. living room with white and other room in gray) break the joint at the shutter groove line/ on the inside edge of the masonry in other room, if door is not provided. 7)After completing the tiling work of the floor, check the overall level. Any unevenness can be rectified with wooden mallet. 8)The gap between walls and floor are fixed with cut pieces of the mosaic tile. 9)Clean the floor and don\'t allow anybody to enter the flat for at least 24hrs. 10)Next day fill the gaps/joints between the tiles with cement slurry. 11) Then cure the flooring and skirting for at least 14days. .
Details of the Construction Materials learned today Tiles:- Types:- 1)Mosaic 2)Cuddappa 3)Marble 4)Glazed Size:- As per the requirement of unit and market availability. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Mortar falling down during plaster work if reused again within 30min, it will save the materials and thereby it will save the natural resources of those material. .
Details of the Construction / Engineering Drawings observed today Interior Decorator Drawing. -For the details of flooring and other furniture and electrification requirement. .
Details of the Bye Laws referred today Minimum length and width of rooms for residential building. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.P.Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-05

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Ramchandra
Exam No. 13557
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the construction of stair case.
Details of how you Planned & Executed the allotted work We take the plan of stair case and along the plan we observe the dimension of stair case and requirement of reinforcement as well as size of steel bars and their spacing.
Details of the Construction Procedure / Activity / Technology learned today Open well stair case provided. First place the plywood for the size of stair case and apply oil to these. Top of plywood steel bars are provided at same spacing as in drawing. Form landing another steel is provided at top at some distance of early provided bars . Bottom provided steel bars bent at top where the junction of beam and continue for slab. Another steel bars provided from slab above the early provided steel bars. For main bar distribution steel is provided at spacing. Steel work is done then formwork is provided as size of trade and rise is given in plan. After the formwork is done then concreting process is start. Stair Case is constructed the formwork is removed After 15 Days because it gives strength.
Details of the Construction Materials learned today Marine Plywood Wood Steel bars - main bars, distributory bars. Cement 20M grade Aggregate 20 & 25 mm Sand Admixture - Super plasticizers.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today To avoid minimum cutting of steel bars.
Details of the Construction / Engineering Drawings observed today Stair Case Drawing Plan of stair case Reinforcement details Size of steel bar which are provided Spacing For stair case
Details of the Bye Laws referred today Stair Case Details Minimum width - 2.0 m Riser - 150 mm Trade - 300 mm Landing - 2.0 m Minimum Head-room - 2.2 m
Details of any Managerial Skill learned today To check bars are properly bent at junction of slab. Rise and trade are in proportion. Any small gap between the formwork.
RATE ANALYSIS (Detailed Stepwise Calculations required) For room size - 2m X 2m Height - 1 m. 0.23 m Brick Masonry Cement masonry 1 : 4 Length of one side - 2.46 m Size of Brick - 19 X 9 X 9 cum Size of brick with mortar - 20 X 10 X 10 cum. Therefore, 2.46 X 0.23 X 1.00 X 2.00 = 1.13 2.00 X 0.23 X 1.00 X 2.00 = 0.92 Total = 2.05 cum. Nos. of brick = 2.05 / 0.2 X 0.1 X 0.1 = 1026 nos. Actual volume of brick = 1026 X 0.19 X 0.09 X 0.09 = 1.58 cum. Quantity of mortar = 2.05 – 1.58 = 0.47 cum. Add 10 % Of Wastage = 0.517 cum weight in condition. Add 25% of Dry weight = 0.646 cum in condition. For 1 : 4 proportion. ( 1 + 4 = 5 ) 0.646/5 X 1 = 0.12 cement / cum. - 4 bags. 0.646/5 X 4 = 0.516 sand / cum. SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 4 bags 250.00/- 1000.00/- b) sand 0.516 cum 850.00/- (per cum) 440.00/- c) Brick 1026 no. 7.00/- (per brick) 7182.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) male mazdur 2 no. 200.00/- 400.00/- d) bhisti 1 no. 120.00/- 120.00/- 3 Centering and lum sum 250/- shuttering 4 Others _ TOTAL 9692.00/- 5 Tools and plant @ 1.5% ----------------------- 145.50/- on total 6 Water charges @ 1.0% ----------------------- 97.00/- on total TOTAL(A) 9935.00/- 7 Overhead and profit @ 15% on tOtal A ----------------------- 1490.00/- -------------------------------------------------------------------------- TOTAL = 11425.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 3111.00/- per cu.m.
Todays BUZZ Word CHECKLIST- A) Wall and ceilling – 1) Are all crack in wall properly filled? 2) Are all signs of dampness/ leakage on walls removed? 3) Are all patches or black strips observed in painting attended? 4) Are loose patches in ceiling and walls ractified ? 5) Are all the corneres sharp and finished ? B) Doors and windows- 1) Are all doors/ windows, opening and closing smoothly? 2) Are all glass pannels fitted properly? 3) Is an eyepiece provided ? 4) Are all the gaps between door / window frame and walls properly filled ? 5) Are screws to all the fittings are provided ? C) Tiling – 1) Is the floor in proper level ? 2) Are the flooring tiles of one type ? 3) Are glazed tiles cleaned and finished properly ? 4) Is proper slope given to bathroom ? 5) Is proper slope given to kitchen platform ? D) Plumbing and sanitation – 1) Are all fixturs like bib taps , mixer are fixed properly and at proper height ? 2) Is proper cleaning done for all sanitary fixtures ? 3) Is there any leakage from taps ? 4) Is there proper pressure to all taps ? 5) Is the P-trap of W.C. properly cleaned ? E) Electification- 1) Is individual meter allotted to the flat ? 2) Is the earthing connection tested for working condition ? 3) Is the main switch fixed in meter cabinet ? 4) All the fittings fixed on board are in line and level or not ? 5) Is the position and quantity of electrical points as per working drawing.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/13/2010
E-mail Address: mayur.sonawane61@gmail.com
Subject: 13570-05

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.DEVELOPERS , PREETAM RESIDENCY , SAMRAT-NAGAR
Students Name (Surname_First Name_Middle Name) Sonawane Mayur Madhukar
Exam No. 13570
Working Day No. 05
Date (DD/MM/YYYY) 13/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Prepare the detailed estimate of given project. .
Details of how you Planned & Executed the allotted work We work individually for different items and then combine all values and find the estimate of project with the help of current D.S.R. .
Details of the Construction Procedure / Activity / Technology learned today Construction activity:- Tiling:- (Mosaic tiles) 1) Prepare the cement slurry in the ratio of 1.5 bags to 100 Lit of water approximately. start fixing tiles from the reference line and reference tiles diagonally. 2)Spread the cement slurry of a honey like consistency, on the mortar bed, over area as much as could be covered with half an hour. 3)Match all the four corner of the tiles properly with the help of wooden mallet. 4)Fix the mosaic tiles in the particular sequence for better results and fine joints. 5)Except for balconies, bath and toilet complete the flooring of one unit per day, for better bonding and uniform and quick work. 6)If there are are two types of tiling( i.e. living room with white and other room in gray) break the joint at the shutter groove line/ on the inside edge of the masonry in other room, if door is not provided. 7)After completing the tiling work of the floor, check the overall level. Any unevenness can be rectified with wooden mallet. 8)The gap between walls and floor are fixed with cut pieces of the mosaic tile. 9)Clean the floor and don\'t allow anybody to enter the flat for at least 24hrs. 10)Next day fill the gaps/joints between the tiles with cement slurry. 11) Then cure the flooring and skirting for at least 14days. .
Details of the Construction Materials learned today Tiles:- Types:- 1)Mosaic 2)Cuddappa 3)Marble 4)Glazed Size:- As per the requirement of unit and market availability. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Mortar falling down during plaster work if reused again within 30min, it will save the materials and thereby it will save the natural resources of those material. .
Details of the Construction / Engineering Drawings observed today Interior Decorator Drawing. -For the details of flooring and other furniture and electrification requirement. .
Details of the Bye Laws referred today Minimum length and width of rooms for residential building. .
Details of any Managerial Skill learned today Gesture and posture of a person has a impact on others and it can help to get things in your favor. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For Brick Work Room Size = 3m x 4m Wall thickness = 0.230m Mix Proportion = 1:4 Total Quantity = 3 x 4 x 0.230 =2.760 cu.m Quantity of Mortar = 40% of Total Quantity = (40/100)*2.76 = 1.104 cu.m Quantity of Brick = 2.760 - 1.104 = 1.656 cu.m Quantity of cement = 1.104/(1+4) = 0.220 cu.m no. of cement bags required = 0.220/0.033 = 7 bags Quantity of Sand = 4 x 0.220 = 0.880 cu.m COST OF MATERIAL Material Quantity Rate/cu.m Cost Cement 0.220 7575.75/- 1666.67/- Sand 0.880 2400/- 2112/- TOTAL = 3778.65/- Add 1.5% water charges = 56.67/- Add 10% contractor profit = 377.865/- GRAND TOTAL = 4213.185/- For 2.76 cu.m = 4213.185 /- For 1 cu.m = 1526.510/- COST OF LABOUR Labour Quantity/10cu.m Rate/day cost Mistri 01 250/- 250/- Masson 10 250/- 4000/- M.Mazdoor 10 150/- 1500/- F.Mazdoor 10 120/- 1200/- Bhisty 02 120/- 240/- T&P Lump-sump 250/- 250/- Total = 7440/- For 10cu.m = 7440/- For 1cu.m = 744/- Total cost for 01 cu.m = 1526.510+744 = Rs.2270.510/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.2270.510/-
Todays BUZZ Word Check List for Tiling work:- 1) Is the floor in proper level? 2) Is the floor and skirting properly polished and cleaned? 3) Is the skirting in one line and at right angle? 4) Are the flooring tile of one type? 5) Is the mosaic tile in room continued upto outer edge of the main door frame? 6) Is the butt/jud properly finished? 7) Is the skirting and butt properly in a line level and right angle around the column? 8) Are cracked tiles in flooring( if any) removed and replaced? 9) Are glased tiles cleaned and finished properly? 10)Are all glazed tiles fixed of uniform colour and design? 11)Is the glazed tiles dado in a right angle and level? 12)Are the gaps between glazed tiles dado and the bathroom ceiling/flooring filled properly? 13)Are jams of window properly finished with glazed tiles? 14)Are you sure that there are no cracked tiles in dado? 15)Are the glazed tiles around the WC pan properly fixed? 16)Are you sure that no water accumulates on flooring of WC? 17)Have you confirmed by knowing each tiles that there are no loose patches left in dado? 18)Is proper slope given to bathroom? 19)Is slope proper towards nahani trap and no water accumulated in between? 20)Is the bath and WC floor half tile down than room floor? Is boundary edge finished properly? 21)Is the slope properly given to balcony towards water spout? 22)Is the balcony floor level half tile down than room floor? 23)Is the length of pipe floor wise correct? 24)Are water spout in balcony fitted properly and cleaned? 25)Is there any threshold fixed to the bath and WC? 26)Is the kitchen platform finished properly? 27)Is the kitchen platform is leakage proof? 28)Is proper slope given to the kitchen platform top? 29)Are the glazed tiles near water taps are properly cut and fixed? 30)Is the hole for gas provided with PVC bend above kitchen otta? 31)Is the polishing of kitchen otta kaddapa vertical? 32)Is edge polishing and rubbing done? 33)Is the tiling below kitchen otta raised by half tie thk. than floor level? 34)Is the door sill fixed for WC/Bath and main door? 35)Is the space for gas cylinder OK to put cylinder freely? 36)Are you sure that hole for gas pipe is not chocked with cement/debris? 37)Is the finishing and painting of wall below kitchen platform done properly? .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.P.Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/12/2010
E-mail Address: shinde_shital7@yahoo.com
Subject: 10884-04

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell karendemala circuithouse kolhapur
Students Name (Surname_First Name_Middle Name) SHINDE SHITAL VILASRAO
Exam No. 10884
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9am .
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge Observe the watertank on terrace and groundfloor.
Details of how you Planned & Executed the allotted work We formed two group frist group measured the capacity of groundfloor, which is 13000lit.and second group measured of the terrace which is 25000lit.
Details of the Construction Procedure / Activity / Technology learned today We learn that how Gypsum plaster is used for water proofing when there either less availability of time or worker.
Details of the Construction Materials learned today Today\'s construction material is KHANAPURI BRICK(local name).It having perfect size i.e. width, depth and length which is (9*4*3)inch.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Walls not affecting any sideeffect of bacteria,season\'s condition by using Gypsum plaster.
Details of the Construction / Engineering Drawings observed today We observed the electrification drawing. Mainly for C.F.L.bulbs, fans they used two point switch.And for T.V. switch board, freeze, gyser,washing machine etc they used three point switch.
Details of the Bye Laws referred today They used Bye laws for staircase and width is 0.75m.
Details of any Managerial Skill learned today How to interact with labour,giving payment time to time of labour.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C.Slab Slab size 3657.6*3048mm Main bar -29 no.Sub bar- 20 no. MAIN BAR CALCULATION- Main bar length-3.6576m, 1bar weight for 1m -400gm, 3.6576=1.464kg, 29*1.464=24.456kg=1273.68Rs. SUB BAR CALCULATION- Sub bar length-3.048m, 1bar weight for 1m-200gm, For 3.048m length - 609.9 gm weight, 20*609.9=12.192Kg=365.76Rs. Total steel cost= 1273.68+365+76=1639.44Rs Concrete cost for 1cubic m=2855Rs. Volume= 1.41cubic m=4025Rs. Cost for slab=3657.6+3048+127=5664.44Rs. Labour cost=2400 Total cost= 8065Rs So for 1 cu.m=5720Rs
Result of RATE ANALYSIS ( Rs per Unit ) 5720Rs
Todays BUZZ Word firsly they invities quotation then according there need they gives the order and there advanced payment upto 30%.when they receive order or material they first checke material by supervisor.Then supervisor sumites the report to respective person.When supervisor say OK then notes on register name of material,date,time, quantity and truck no.and collect the material on perticular site.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge KETAN CHARAPALE(9552597474)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-04

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Janbandhu Rakshit Dulichand
Exam No. 10875
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9:30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. To study the External Plastering Work. 2. To study Electrification. 3. To prepare the daily report work analysis.
Details of how you Planned & Executed the allotted work 1. We divided ourself into two groups. 2. The first group studied the plastering work. 3. The second group studied the electrification work. 4. Then again the first group changed their work & studied the electrification work & vice versa.
Details of the Construction Procedure / Activity / Technology learned today 1. First of all the rendering of external wall surface was done for south wall . this work was carried out yesterday. 2. Then the second coat was applied today. 3. This work included applying the mortar with force on the surface, with a trowel. 4. Then using floats the mortered surface was levelled.
Details of the Construction Materials learned today 1. Mortar to be used for plastering in ratio of 1:3. 2. Anchor Wires (copper) 1sq.mm (1100V capacity)
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No,
Details of the Construction / Engineering Drawings observed today Electrification Working Drawings.
Details of the Bye Laws referred today Bye-Law Book Page No 35 Additional Restriction on construction.
Details of any Managerial Skill learned today 1. Bargaining with external agencies. 2. Study of daily report analysis.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For RCC Slab\" -------------------------------------------------------------------------- * Volume Of Concrete Slab = 10 cu.m * Concrete Mix = 1:2:4 * Volume of Concrete Mix = 15.2 cu.m -------------------------------------------------------------------------- A) Materials: 1. Steel: * Volume Of steel reqd. = 785 kg 2. Cement: (2.17 cu.m) * No Of bags = 64 3. Sand: (4.34 cu.m) 4. Coarse Aggregate: (8.68 cu.m) 5. Binding Wire: (20 kg) --------------------------------------------------------------------------- B) Cost Of Material: 1. Cement = 64 x 230 = 14720/- 2. Sand = 4.34 x 850 = 3689/- 3. Aggregate = 8.68 x 530 = 4600.4/- 4. Steel = 785 x 35 = 27475/- 5. Binding Wire = 20 x 55 = 1100/- * TOTAL = 51584.4/- --------------------------------------------------------------------------- C) Cost Of Labour: 1. Head Mason = 2 x 250 = 500/- 2. Mason = 4 x 170 = 680/- 3. Mazdoor = 15 x 110 = 1650/- 4. Centering & Shutttering including removing = 5% Cost Of material = 2579.22/- 5. Carpenter = 10 x 250 = 2500/- Nails = 1000/- 6. Blacksmith = 15 x 200 = 3000/- * TOTAL = 11909.2/- ----------------------------------------------------------------------------- D) TOTAL COST = B+C = 63493.62/- ---------------------------------------------------------------------------- E) Add 2% Water Charges = 1269.8724/- ----------------------------------------------------------------------------- F) 15% Contractors Profit = 9524.043/- ------------------------------------------------------------------------------- G) GRAND TOTAL = D+E+F = 74287.54/- ------------------------------------------------------------------------------ H) Rate for 1 cu.m = 7428.754/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 7428.754/-
Todays BUZZ Word Purchase Dept: The Purchase dept Contributes towards companys profit,. ------------------------------ Activities Of Purchase Dept: 1. Market Survey for new materials. 2. Vendor Development. 3. Follow Up To Ensure proper delivery. 4. Contribute towards the company\'s profit. ----------------------------------------------------------- Procedure Followed By Dept: - Before starting a new project specifications of all materials should be finalised & the requsitions accepted accordingly. - If the specifications are altered by Management the same should be intimated to the Purchase Dept ------------------------------------------------------------ Documents: 1. Acceptance of requisitions. 2. Issuing Of Purchase Order. 3. Pending Requsitations. 4. Site Visits. 5. Reporting.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-04

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Jape Vishwajeet Ramesh
Exam No. 10892
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 5:30pm
Details of the Work Allotted to you today by the Site In-Charge 1. To study the External Plastering Work. 2. To study Electrification. 3. To prepare the daily report work analysis.
Details of how you Planned & Executed the allotted work 1. We divided ourself into two groups. 2. The first group studied the plastering work. 3. The second group studied the electrification work. 4. Then again the first group changed their work & studied the electrification work & vice versa.
Details of the Construction Procedure / Activity / Technology learned today 1. First of all the rendering of external wall surface was done for south wall . this work was carried out yesterday. 2. Then the second coat was applied today. 3. This work included applying the mortar with force on the surface, with a trowel. 4. Then using floats the mortered surface was levelled.
Details of the Construction Materials learned today 1. Mortar to be used for plastering in ratio of 1:3. 2. Anchor Wires (copper) 1sq.mm (1100V capacity)
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No, not observed such technology today.
Details of the Construction / Engineering Drawings observed today Electrification Working Drawings.
Details of the Bye Laws referred today Bye-Law Book Page No 35 Additional Restriction on construction.
Details of any Managerial Skill learned today 1. Bargaining with external agencies. 2. Study of daily report analysis.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For RCC Slab\" -------------------------------------------------------------------------- * Volume Of Concrete Slab = 10 cu.m * Concrete Mix = 1:2:4 * Volume of Concrete Mix = 15.2 cu.m -------------------------------------------------------------------------- A) Materials: 1. Steel: * Volume Of steel reqd. = 785 kg 2. Cement: (2.17 cu.m) * No Of bags = 64 3. Sand: (4.34 cu.m) 4. Coarse Aggregate: (8.68 cu.m) 5. Binding Wire: (20 kg) --------------------------------------------------------------------------- B) Cost Of Material: 1. Cement = 64 x 230 = 14720/- 2. Sand = 4.34 x 850 = 3689/- 3. Aggregate = 8.68 x 530 = 4600.4/- 4. Steel = 785 x 35 = 27475/- 5. Binding Wire = 20 x 55 = 1100/- * TOTAL = 51584.4/- --------------------------------------------------------------------------- C) Cost Of Labour: 1. Head Mason = 2 x 250 = 500/- 2. Mason = 4 x 170 = 680/- 3. Mazdoor = 15 x 110 = 1650/- 4. Centering & Shutttering including removing = 5% Cost Of material = 2579.22/- 5. Carpenter = 10 x 250 = 2500/- Nails = 1000/- 6. Blacksmith = 15 x 200 = 3000/- * TOTAL = 11909.2/- ----------------------------------------------------------------------------- D) TOTAL COST = B+C = 63493.62/- ---------------------------------------------------------------------------- E) Add 2% Water Charges = 1269.8724/- ----------------------------------------------------------------------------- F) 15% Contractors Profit = 9524.043/- ------------------------------------------------------------------------------- G) GRAND TOTAL = D+E+F = 74287.54/- ------------------------------------------------------------------------------ H) Rate for 1 cu.m = 7428.754/- -------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 7428.754/-
Todays BUZZ Word Purchase Dept: The Purchase dept Contributes towards companys profit,. ------------------------------ Activities Of Purchase Dept: 1. Market Survey for new materials. 2. Vendor Development. 3. Follow Up To Ensure proper delivery. 4. Contribute towards the company\'s profit. ----------------------------------------------------------- Procedure Followed By Dept: - Before starting a new project specifications of all materials should be finalised & the requsitions accepted accordingly. - If the specifications are altered by Management the same should be intimated to the Purchase Dept ------------------------------------------------------------ Documents: 1. Acceptance of requisitions. 2. Issuing Of Purchase Order. 3. Pending Requsitations. 4. Site Visits. 5. Reporting. ---------------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-04

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Nagvekar Yogesh Deepak
Exam No. 10894
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 5:30pm
Details of the Work Allotted to you today by the Site In-Charge 1. To study the External Plastering Work. 2. To study Electrification. 3. To prepare the daily report work analysis. -------------------------------------------------------------------------------
Details of how you Planned & Executed the allotted work 1. We divided ourself into two groups. 2. The first group studied the plastering work. 3. The second group studied the electrification work. 4. Then again the first group changed their work & studied the electrification work & vice versa. -------------------------------------------------------------------------------------
Details of the Construction Procedure / Activity / Technology learned today 1. First of all the rendering of external wall surface was done for south wall . this work was carried out yesterday. 2. Then the second coat was applied today. 3. This work included applying the mortar with force on the surface, with a trowel. 4. Then using floats the mortered surface was levelled. ---------------------------------------------------------------------------------------
Details of the Construction Materials learned today 1. Mortar to be used for plastering in ratio of 1:3. 2. Anchor Wires (copper) 1sq.mm (1100V capacity) --------------------------------------------------------------------------------------
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No, not observed such technology today. ----------------------------------------------------------------------------------------
Details of the Construction / Engineering Drawings observed today Electrification Working Drawings.
Details of the Bye Laws referred today Bye-Law Book Page No 35 Additional Restriction on construction. --------------------------------------------------------------------------------------
Details of any Managerial Skill learned today 1. Bargaining with external agencies. 2. Study of daily report analysis. -------------------------------------------------------------------------------------
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For RCC Slab\" -------------------------------------------------------------------------- * Volume Of Concrete Slab = 10 cu.m * Concrete Mix = 1:2:4 * Volume of Concrete Mix = 15.2 cu.m -------------------------------------------------------------------------- A) Materials: 1. Steel: * Volume Of steel reqd. = 785 kg 2. Cement: (2.17 cu.m) * No Of bags = 64 3. Sand: (4.34 cu.m) 4. Coarse Aggregate: (8.68 cu.m) 5. Binding Wire: (20 kg) --------------------------------------------------------------------------- B) Cost Of Material: 1. Cement = 64 x 230 = 14720/- 2. Sand = 4.34 x 850 = 3689/- 3. Aggregate = 8.68 x 530 = 4600.4/- 4. Steel = 785 x 35 = 27475/- 5. Binding Wire = 20 x 55 = 1100/- * TOTAL = 51584.4/- --------------------------------------------------------------------------- C) Cost Of Labour: 1. Head Mason = 2 x 250 = 500/- 2. Mason = 4 x 170 = 680/- 3. Mazdoor = 15 x 110 = 1650/- 4. Centering & Shutttering including removing = 5% Cost Of material = 2579.22/- 5. Carpenter = 10 x 250 = 2500/- Nails = 1000/- 6. Blacksmith = 15 x 200 = 3000/- * TOTAL = 11909.2/- ----------------------------------------------------------------------------- D) TOTAL COST = B+C = 63493.62/- ---------------------------------------------------------------------------- E) Add 2% Water Charges = 1269.8724/- ----------------------------------------------------------------------------- F) 15% Contractors Profit = 9524.043/- ------------------------------------------------------------------------------- G) GRAND TOTAL = D+E+F = 74287.54/- ------------------------------------------------------------------------------ H) Rate for 1 cu.m = 7428.754/- -------------------------------------------------------------------------------
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 7428.754/-
Todays BUZZ Word Purchase Dept: The Purchase dept Contributes towards companys profit,. ------------------------------ Activities Of Purchase Dept: 1. Market Survey for new materials. 2. Vendor Development. 3. Follow Up To Ensure proper delivery. 4. Contribute towards the company\'s profit. ----------------------------------------------------------- Procedure Followed By Dept: - Before starting a new project specifications of all materials should be finalised & the requsitions accepted accordingly. - If the specifications are altered by Management the same should be intimated to the Purchase Dept ------------------------------------------------------------ Documents: 1. Acceptance of requisitions. 2. Issuing Of Purchase Order. 3. Pending Requsitations. 4. Site Visits. 5. Reporting. --------------------------------------------------------
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-04

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Hasabnis Ketaki Bhagwan
Exam No. 13527
Working Day No. 4
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge > To check the cover of reinforcement, beams, columns, spacing between stirrups etc. prior to the casting of slab, with the help of plans.
Details of how you Planned & Executed the allotted work > We first took the plan showing deatils of beams and columns from site incharge and then went on site checked whether covers were provided or not, spacing between stirrups are proper or not etc.
Details of the Construction Procedure / Activity / Technology learned today > We found that at some places covers were not provided. we informed the site incharge about it. He assigned two labourers for this work .We asked the labours to provide covers for beams and observed it. > We found the shuttering was open at some places and their were chances that the R.M.C would leak through it.We asked the labourer to put adhesive tapes. > The structural consulatant had come from pune to check whether the beams and colums arrangements were feasible for casting the slabs. He conveyed the faults at various places to the site incharge and accordingly the site incharge conveyed it to the labourers. > we helped the structural consultant in his job. He told us the name of column or beam he was checking and we told him the no. of steel (bars) provided for that particular column or beam referring the plan.
Details of the Construction Materials learned today Ready Mix Concrete(R.M.C)- Ultratech Company. > Materials used for covers- R.C.C, Granite. > Conduit pipes for electrical wiring. > Other necessary things to be done prior to casting of slab.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today > For the conservation of water, waste water will be treated and used for gardening and cleaning. > Rain water harvesting will be provided after the completion of the project for recharging the ground water.
Details of the Construction / Engineering Drawings observed today > Plan showing schedule of beams and columns and their details. > Plan showing electrical fittings.
Details of the Bye Laws referred today > According to bye-laws cantilever beams should be placed at L/2 distance. > According to bye-laws maximum length of cantilever beam is 4m. On site it is provided 2m. > According to bye-laws the covering should be slab- 15mm, beams- 25mm and column -40mm.
Details of any Managerial Skill learned today > We observed how the structural engineer checked the quality of work. > How he communicated with site incharge about the faults and corrections and instructions given to him
RATE ANALYSIS (Detailed Stepwise Calculations required) For R.C.C Slab. Material: Ultratech Ready Mix Concrete (R.M.C) is used Cost of concrete is - Rs. 3500 /per cu.m. Steel Centering work with adjustable props . Centering for Beams. Providing Fan hook. - Rs. 1500 / per cu.m. Slab and beam covers. Labour __________________ Total cost per cu.m - Rs.5000 /per cu.m Add profit 10% -Rs.500. Total cost of R.C.C SLAB per cu.m -Rs. 5500 /- per cu.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.5500/- per cu.m
Todays BUZZ Word 1.Cement:Bagalkot Supreme 43 grade, 53 grade, white cement as per requirement. 2.Steel:M.S. Steel of mahalaxmi TMT. As per requirements for building. 3.Fresh river sand. 4.Well graded metal. 5.Trap stone metal. 6.Electrical fittings- wires,switches,board,casing pipes etc. as per requirement of each floor. 7.Sanitary fittings- pipes,cocks,valves,meters etc. according to requirements of each floor. 8.Tiles- vitrifried, kitchen otta,for bathrooms etc as per requirement. 9.Doors & Windows- aluminium windows,M.S.grill, different sizes as per requirement. Doors teakwood,panelled,flushed,pvc coated etc as per the requirement. 10.Drainage pipes and inspection Chamber covers,nahni trap etc. as per requirement
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR Cell No..9922313712.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523-04

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Devkar Vikram Dilip
Exam No. 13523
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To check the cover of reinforcement, beams, columns, spacing between stirrups etc. prior to the casting of slab, with the help of plans.
Details of how you Planned & Executed the allotted work We first took the plan showing deatils of beams and columns from site incharge and then went on site checked whether covers were provided or not, spacing between stirrups was proper or not etc.
Details of the Construction Procedure / Activity / Technology learned today 1.While checking the site we found that at some places covers were not provided we informed the site incharge about this then he assigned two ;abours with us and we then told the labours to provide covers for beams, at some palces the shuttering was open and their were chances that the R.M.C would have leaked through it.so we told the labourer to put adhesive tapes their. The structural consulatant came from pune today and he checked whether the beams and colums arrangements were feasible for casting the slabs. He conveyed the faults at various places to the site incharge and accordingly the site incharge conveyed it to the labourers. we helped the structural consultant. he told us the name of column or beam he was checking and we use to tell him the no. of steel (bars) provided for that particular column or beam. Product learned today: 2. Concreting of slab by Ready Mix Concrete (R.M.C) 3. Vibration by needle vibrator. 4. Compaction by rodding.
Details of the Construction Materials learned today Ready Mix Concrete(R.M.C)- Ultratech Company. Materials used for covers- R.C.C, Granite. Conduit pipes for electrical wiring. and all other necessary things to be done prior to casting of slab.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Plan showing schedule of beams and columns and their details. Plan showing electrical fittings.
Details of the Bye Laws referred today According to bye-laws cantilever beams should be placed at L/2 distance. According to bye-laws maximum length of cantilever beam is 4m. On site it is provided 2m.
Details of any Managerial Skill learned today 1. The site supervisor checked the spacing between stirrups, covers provided etc. 2. The site supervisor and the structural consultant found out the faults and they told it to the workers properly. 3. The site supervisor was present on site throughout the casting of slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) For R.C.C Slab. Material: Ultratech Ready Mix Concrete (R.M.C) is used Cost of concrete is - Rs. 3500 /per cu.m. Steel Centering work with adjustable props . Centering for Beams. Providing Fan hook. - Rs. 1500 / per cu.m. Slab and beam covers. Labour __________________ Total cost per cu.m - Rs.5000 /per cu.m Add profit 10% -Rs.500. Total cost of R.C.C SLAB per cu.m -Rs. 5500 /- per cu.m
Result of RATE ANALYSIS ( Rs per Unit ) -Rs. 5500 /- per cu.m
Todays BUZZ Word 1.Cement. Bagalkot Supreme 43 grade, 53 grade, white cement as per requirement. 2. Steel . M.S. Steel of mahalaxmi TMT. As per requirements for building. 3. Fresh river sand. 4. Well graded metal. 5. Trap stone metal. 6. Electrical fittings- wires,switches,board,casing pipes etc. as per requirement of each floor. 7. Sanitary fittings- pipes,cocks,valves,meters etc. according to requirements of each floor. 8. Tiles- vitrifried, kitchen otta,for bathrooms etc as per requirement. 9.Doors & Windows- aluminium windows,M.S.grill, different sizes as per required. Doors teakwood,panelled,flushed,pvc coated etc as per requirement. 10. Drainage pipes and inspection Chamber covers,nahni trap etc. as per requirement
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521-04

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Bagmare Dinesh Shriram
Exam No. 13521
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To check the cover of reinforcement, beams, columns, spacing between stirrups etc. prior to the casting of slab, with the help of plans.
Details of how you Planned & Executed the allotted work We first took the plan showing deatils of beams and columns from site incharge and then went on site checked whether covers were provided or not, spacing between stirrups was proper or not etc.
Details of the Construction Procedure / Activity / Technology learned today 1.While checking the site we found that at some places covers were not provided we informed the site incharge about this then he assigned two ;abours with us and we then told the labours to provide covers for beams, at some palces the shuttering was open and their were chances that the R.M.C would have leaked through it.so we told the labourer to put adhesive tapes their. The structural consulatant came from pune today and he checked whether the beams and colums arrangements were feasible for casting the slabs. He conveyed the faults at various places to the site incharge and accordingly the site incharge conveyed it to the labourers. we helped the structural consultant. he told us the name of column or beam he was checking and we use to tell him the no. of steel (bars) provided for that particular column or beam. Product learned today: 2. Concreting of slab by Ready Mix Concrete (R.M.C) 3. Vibration by needle vibrator. 4. Compaction by rodding.
Details of the Construction Materials learned today Ready Mix Concrete(R.M.C)- Ultratech Company. Materials used for covers- R.C.C, Granite. Conduit pipes for electrical wiring. and all other necessary things to be done prior to casting of slab.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Plan showing schedule of beams and columns and their details. Plan showing electrical fittings.
Details of the Bye Laws referred today According to bye-laws cantilever beams should be placed at L/2 distance. According to bye-laws maximum length of cantilever beam is 4m. On site it is provided 2m.
Details of any Managerial Skill learned today 1. The site supervisor checked the spacing between stirrups, covers provided etc. 2. The site supervisor and the structural consultant found out the faults and they told it to the workers properly. 3. The site supervisor was present on site throughout the casting of slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) For R.C.C Slab. Material: Ultratech Ready Mix Concrete (R.M.C) is used Cost of concrete is - Rs. 3500 /per cu.m. Steel Centering work with adjustable props . Centering for Beams. Providing Fan hook. - Rs. 1500 / per cu.m. Slab and beam covers. Labour __________________ Total cost per cu.m - Rs.5000 /per cu.m Add profit 10% -Rs.500. Total cost of R.C.C SLAB per cu.m -Rs. 5500 /- per cu.m
Result of RATE ANALYSIS ( Rs per Unit ) -Rs. 5500 /- per cu.m
Todays BUZZ Word 1.Cement. Bagalkot Supreme 43 grade, 53 grade, white cement as per requirement. 2. Steel . M.S. Steel of mahalaxmi TMT. As per requirements for building. 3. Fresh river sand. 4. Well graded metal. 5. Trap stone metal. 6. Electrical fittings- wires,switches,board,casing pipes etc. as per requirement of each floor. 7. Sanitary fittings- pipes,cocks,valves,meters etc. according to requirements of each floor. 8. Tiles- vitrifried, kitchen otta,for bathrooms etc as per requirement. 9.Doors & Windows- aluminium windows,M.S.grill, different sizes as per required. Doors teakwood,panelled,flushed,pvc coated etc as per requirement. 10. Drainage pipes and inspection Chamber covers,nahni trap etc. as per requirement
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? Yes
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-04

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Tekwani Sagar Bansilal
Exam No. 10903
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To check the cover of reinforcement, beams, columns, spacing between stirrups etc. prior to the casting of slab, with the help of plans.
Details of how you Planned & Executed the allotted work We first took the plan showing deatils of beams and columns from site incharge and then went on site checked whether covers were provided or not, spacing between stirrups was proper or not etc.
Details of the Construction Procedure / Activity / Technology learned today 1_)While checking the site we found that at some places covers were not provided we informed the site incharge about this then he assigned two ;abours with us and we then told the labours to provide covers for beams, at some palces the shuttering was open and their were chances that the R.M.C would have leaked through it.so we told the labourer to put adhesive tapes their. The structural consulatant came from pune today and he checked whether the beams and colums arrangements were feasible for casting the slabs. He conveyed the faults at various places to the site incharge and accordingly the site incharge conveyed it to the labourers. we helped the structural consultant. he told us the name of column or beam he was checking and we use to tell him the no. of steel (bars) provided for that particular column or beam. Product learned today: 2. Concreting of slab by Ready Mix Concrete (R.M.C) 3. Vibration by needle vibrator. 4. Compaction by rodding.
Details of the Construction Materials learned today Ready Mix Concrete(R.M.C)- Ultratech Company. Materials used for covers- R.C.C, Granite. Conduit pipes for electrical wiring. and all other necessary things to be done prior to casting of slab.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Plan showing schedule of beams and columns and their details. Plan showing electrical fittings.
Details of the Bye Laws referred today According to bye-laws cantilever beams should be placed at L/2 distance. According to bye-laws maximum length of cantilever beam is 4m. On site it is provided 2m.
Details of any Managerial Skill learned today 1. The site supervisor checked the spacing between stirrups, covers provided etc. 2. The site supervisor and the structural consultant found out the faults and they told it to the workers properly. 3. The site supervisor was present on site throughout the casting of slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) For R.C.C Slab. Material: Ultratech Ready Mix Concrete (R.M.C) is used Cost of concrete is - Rs. 3500 /per cu.m. Steel Centering work with adjustable props . Centering for Beams. Providing Fan hook. - Rs. 1500 / per cu.m. Slab and beam covers. Labour __________________ Total cost per cu.m - Rs.5000 /per cu.m Add profit 10% -Rs.500. Total cost of R.C.C SLAB per cu.m -Rs. 5500 /- per cu.m
Result of RATE ANALYSIS ( Rs per Unit ) -Rs. 5500 /- per cu.m
Todays BUZZ Word 1.Cement. Bagalkot Supreme 43 grade, 53 grade, white cement as per requirement. 2. Steel . M.S. Steel of mahalaxmi TMT. As per requirements for building. 3. Fresh river sand. 4. Well graded metal. 5. Trap stone metal. 6. Electrical fittings- wires,switches,board,casing pipes etc. as per requirement of each floor. 7. Sanitary fittings- pipes,cocks,valves,meters etc. according to requirements of each floor. 8. Tiles- vitrifried, kitchen otta,for bathrooms etc as per requirement. 9.Doors & Windows- aluminium windows,M.S.grill, different sizes as per required. Doors teakwood,panelled,flushed,pvc coated etc as per requirement. 10. Drainage pipes and inspection Chamber covers,nahni trap etc. as per requirement
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-04

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) janbandhu rakshit d
Exam No. 10875
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 5.30pm
Details of the Work Allotted to you today by the Site In-Charge 1)observation the water tank slab steel 2)checking the dimension of water tank
Details of how you Planned & Executed the allotted work 1) we seen the water tank whose located on terrace. 2) we seen hows steel placed in beam 3) observ shuttring 4) steel arrangement and taken dimension 5) size (5.5*2.2*2.8) 6) capacity (25000 liters)
Details of the Construction Procedure / Activity / Technology learned today used gypsum plaster technique now a days used. for less time and less availability of worker
Details of the Construction Materials learned today brick moulding by khanapuri sand (local name) size(9\"*4\"*3\") size should be perfect than soil bricks
Details of Environment Caring Technology / Methodology / Procedure / Product learned today used solar planner for parking
Details of the Construction / Engineering Drawings observed today we seen electric layout 1) gysor 2) washing maching switch 3) exhaust fan 4) lamp 5) fridge switch
Details of the Bye Laws referred today 1) stair case width 0.75m 2) security cabin size(1m*2m)
Details of any Managerial Skill learned today we learn how to planning the whole day
RATE ANALYSIS (Detailed Stepwise Calculations required) 1) main bar=6mm spacing 6\" 2) sub bar =8mm spacing 5\" 3)size of slab (3.657*3.048) 4)main bar= 29 nos. 5)sub bar=20 nos. 6)main= 42.456 kg =1273.68 rs. 7)sub bar= 12.192 kg =365 rs. 8)total steel cost =1639.44 rs. 9)concrete cost(1m3) =2855 rs. 10)volm=1.41m3 11) cost- 4025 rs. 12)total cost for slab =(3657.6+3048+127) = 5664.44 rs. 13)labour =2400 14)for 1.41 m3=5664+2400 =8065 15)for 1m3= 5720 rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1m3=5720 rs.
Todays BUZZ Word 1)1st requird materil choosen from delers 2)then order by owner requirment 3)then received materiak checked by site superwiser 4)documents a)quatqtion receipt b)delivary receipt c)received receipt Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog): Yes Faced any Accident / Injury today?: No I carried & used following accessories on the site today: Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction Daily Site Work Form filled, stamped & signed by the Site In-Charge?: Yes Name & Mobile No. of the Site In-charge: ketan charpale 9552597474 Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done: Yes, I am aware of it
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. Amol A. Mule. (9922507376
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-04

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Shivtare Prabhakar Chandrakant
Exam No. 13569
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) Casting of slab 2) Rate analysis for slab .
Details of how you Planned & Executed the allotted work 1) First we divide our group in two sub-group 2) First group find the procedure for casting of slab & steel distribution. 3) second group analysed the slab quantity .
Details of the Construction Procedure / Activity / Technology learned today A) Centering work for slab 1) First engineer gives detailed drawing for slab i.e. steel details , concrete details , beam detils , column details. B) Form work were arranged by using drawings. C) Surface level cheked by LINE-DORI OR WATER TUBE. D) then steel arranged as per drawings. E) skill supervision should be maintained throught the work. F) the form work should be removed after 28 days to achieved the adequate strength. .
Details of the Construction Materials learned today 1) Steel - 450 & 500 grade 2) M-20 grade concrete .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The vertical supports use for form work should be of steel.Because saving of wood. .
Details of the Construction / Engineering Drawings observed today 1) Reinforcement detail drawing for slab. 2) Centering detail drawing. 3) Beam details drawing. 4) column detail drawing. .
Details of the Bye Laws referred today None. .
Details of any Managerial Skill learned today Details of any Managerial Skill learned today: How to manage labour force & quality of work during casting of slab. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For R.C.C slab by using M-20 (1:1.5:3) Take 3m x 4m span of slab & 150mm thick slab Total quantity of slab : 3m x 4m x 0.150m = 1.8cu.m Total quantity of material required for casting of slab 1) Quantity of Cement : 1.8 /(1+1.5+3) = 0.32cu.m No. of bags required : 0.32 / 0.033 = 9.69 nos. say 10 bags 2)Quantity of Sand : 0.32 x 1.5 = 0.48 cu.m 3)Quantity of aggregate : 0.32 x 3 = 0.96 cu.m Total Quantity of steel required for casting of slab Assume 2% steel of total quantity of slab = 0.036 cu.m Total weight of steel required in KG = 0.036 x 7850 = 282.6 kg Rate analysis for material Material Quantity in cu.m Rate per cu.m Cost Cement 0.32 7575.75/- 2424.2 /- Sand 0.48 2400 /- 1152/- Aggregate 0.96 535 /- 513.6/- Steel 282.6 kg 45/kg 12717/- TOTAL = 16806.84/- Add 1.5% water charges = 252.102/- Add 10 % contractors profit = 1680.684/- Grand Total = 18739.626/- Total cost of concrete required for slab = 4089.85/- Rate analysis for labour Labour Quantity in nos. Rate / day Cost Mason 03 250 750/- M.mazdoor 10 150 1500/- F.mazdoor 10 120 1200/- Bhisty 05 120 600/- Fitter 04 250 1000/- T&P Lump-sum 100 100/- Grand Total = 5150/- For 1 cu.m = 5150/- For 1.8 cu.m = 9270/- Total cost for 1.8 cu.m slab = 18800+9270 = 28070 /- Total cost for 1 cu.m slab = 15600/-
Result of RATE ANALYSIS ( Rs per Unit ) 15600/-
Todays BUZZ Word Construction material contribute the 70% cost of project.So purchasing & quality of material plays an important role in every construction activity to achieve economy. For purchasing any material e.g. Steel following documents are required. a) Steel details like various diameters of bar required their weight in tuns. b) Company of steel & their reputation. c) Quality of steel. d) Minimum rate of material, company which offers for purchasing steel. . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: mayur.sonawane61@gmail.com
Subject: 13570-04

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) SONAWANE MAYUR MADHUKAR
Exam No. 13570
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) Casting of slab 2) Rate analysis for slab .
Details of how you Planned & Executed the allotted work 1) First we divide our group in two sub-group 2) First group find the procedure for casting of slab & steel distribution. 3) second group analysed the slab quantity .
Details of the Construction Procedure / Activity / Technology learned today A) Centering work for slab 1) First engineer gives detailed drawing for slab i.e. steel details , concrete details , beam detils , column details. B) Form work were arranged by using drawings. C) Surface level cheked by LINE-DORI OR WATER TUBE. D) then steel arranged as per drawings. E) skill supervision should be maintained throught the work. F) the form work should be removed after 28 days to achieved the adequate strength. .
Details of the Construction Materials learned today 1) Steel - 450 & 500 grade 2) M-20 grade concrete .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The vertical supports use for form work should be of steel.Because saving of wood. .
Details of the Construction / Engineering Drawings observed today 1) Reinforcement detail drawing for slab. 2) Centering detail drawing. 3) Beam details drawing. 4) column detail drawing. .
Details of the Bye Laws referred today None. .
Details of any Managerial Skill learned today Details of any Managerial Skill learned today: How to manage labour force & quality of work during casting of slab. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For R.C.C slab by using M-20 (1:1.5:3) Take 3m x 4m span of slab & 150mm thick slab Total quantity of slab : 3m x 4m x 0.150m = 1.8cu.m Total quantity of material required for casting of slab 1) Quantity of Cement : 1.8 /(1+1.5+3) = 0.32cu.m No. of bags required : 0.32 / 0.033 = 9.69 nos. say 10 bags 2)Quantity of Sand : 0.32 x 1.5 = 0.48 cu.m 3)Quantity of aggregate : 0.32 x 3 = 0.96 cu.m Total Quantity of steel required for casting of slab Assume 2% steel of total quantity of slab = 0.036 cu.m Total weight of steel required in KG = 0.036 x 7850 = 282.6 kg Rate analysis for material Material Quantity in cu.m Rate per cu.m Cost Cement 0.32 7575.75/- 2424.2 /- Sand 0.48 2400 /- 1152/- Aggregate 0.96 535 /- 513.6/- Steel 282.6 kg 45/kg 12717/- TOTAL = 16806.84/- Add 1.5% water charges = 252.102/- Add 10 % contractors profit = 1680.684/- Grand Total = 18739.626/- Total cost of concrete required for slab = 4089.85/- Rate analysis for labour Labour Quantity in nos. Rate / day Cost Mason 03 250 750/- M.mazdoor 10 150 1500/- F.mazdoor 10 120 1200/- Bhisty 05 120 600/- Fitter 04 250 1000/- T&P Lump-sum 100 100/- Grand Total = 5150/- For 1 cu.m = 5150/- For 1.8 cu.m = 9270/- Total cost for 1.8 cu.m slab = 18800+9270 = 28070 /- Total cost for 1 cu.m slab = 15600/-
Result of RATE ANALYSIS ( Rs per Unit ) 15600/-
Todays BUZZ Word Construction material contribute the 70% cost of project.So purchasing & quality of material plays an important role in every construction activity to achieve economy. For purchasing any material e.g. Steel following documents are required. a) Steel details like various diameters of bar required their weight in tuns. b) Company of steel & their reputation. c) Quality of steel. d) Minimum rate of material, company which offers for purchasing steel. . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-04

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) PATIL ADITYA PANDURANG
Exam No. 13538
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge Checking strength of brick.
Details of how you Planned & Executed the allotted work First we drop brick from 1m height & observe whether it breack or not. We also check water absorption by brick
Details of the Construction Procedure / Activity / Technology learned today how to cut steel rod & observe diametre steel
Details of the Construction Materials learned today STEEL We observe machine cutter for steel cutting . We also cut some specimen.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today We observe working drawing of 2BHk plan
Details of the Bye Laws referred today We observwd set back distance as per BYE-LAWS
Details of any Managerial Skill learned today Give instruction to the site supervisor to unload the materials at proper places so that loss of the material is reduced due to the external agencies.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 CU.M ADDITION FOR DRY VOLUME: 52 % TOTAL VOLUME TO BE MADE: 1.52 CU.M CEMENT: 1.52/1+1.5+3=0.2763 CU.M NUMBER OF BAGS: 0.2763/0.035=7.89=8 CU.M COST= (260X 8)=2080 RS SAND: 0.2763 X 1.5 =0.4144 CU.M COST = (0.4144 X 742.04)=307.50 RS AGGREGATE: 0.2763 X 3=0.8289 CU.M COST= (0.8289 X 636.04)=527.21 RS TOTAL COST OF MATERIAL: 2080+307.50+527.21= 2914.71 RS REINFORCEMENT: 52 KG/CU.M X 32 = 1664 RS LABOURS: 985 RS WATER: 1.5% X (2914.71)=43.72 RS CENTERING AND SHUTTERING : 445 RS TOTAL COST: 6052 RS CONTRACTORS PROFIT: 15% TOTAL COST=6960.29 RS Result of RATE ANALYSIS ( Rs per Unit ): 6960.29 RS/CU.M
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 RS/CU.
Todays BUZZ Word 1. Find the specification required by the building. 2. contact all the suppliers in the market. 3. Give him a letter and quotation required for us. 4. tell them the time limit in which you required those material. 5. take the quotation from suppliers. 6. if you feel that it is ok then visit and select the material required. 7. check the quality of the material and compare the cost of material with others in the market. 8. finalise the cost of material. 9. give him the supply order. 10.after the delivery record taken in the inward register by refering the delivery chalan. 11. check the materials given by the suppliers an accordingly bills payments are done store into the rooms.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J.J Chougule mob no- 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-04

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge Checking strength of brick.
Details of how you Planned & Executed the allotted work First we drop brick from 1m height & observe whether it breack or not. We also check water absorption by brick
Details of the Construction Procedure / Activity / Technology learned today how to cut steel rod & observe diametre steel
Details of the Construction Materials learned today STEEL We observe machine cutter for steel cutting . We also cut some specimen.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today We observe working drawing of 2BHk plan
Details of the Bye Laws referred today We observwd set back distance as per BYE-LAWS
Details of any Managerial Skill learned today Give instruction to the site supervisor to unload the materials at proper places so that loss of the material is reduced due to the external agencies.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 CU.M ADDITION FOR DRY VOLUME: 52 % TOTAL VOLUME TO BE MADE: 1.52 CU.M CEMENT: 1.52/1+1.5+3=0.2763 CU.M NUMBER OF BAGS: 0.2763/0.035=7.89=8 CU.M COST= (260X 8)=2080 RS SAND: 0.2763 X 1.5 =0.4144 CU.M COST = (0.4144 X 742.04)=307.50 RS AGGREGATE: 0.2763 X 3=0.8289 CU.M COST= (0.8289 X 636.04)=527.21 RS TOTAL COST OF MATERIAL: 2080+307.50+527.21= 2914.71 RS REINFORCEMENT: 52 KG/CU.M X 32 = 1664 RS LABOURS: 985 RS WATER: 1.5% X (2914.71)=43.72 RS CENTERING AND SHUTTERING : 445 RS TOTAL COST: 6052 RS CONTRACTORS PROFIT: 15% TOTAL COST=6960.29 RS Result of RATE ANALYSIS ( Rs per Unit ): 6960.29 RS/CU.M
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 RS/CU.
Todays BUZZ Word 1. Find the specification required by the building. 2. contact all the suppliers in the market. 3. Give him a letter and quotation required for us. 4. tell them the time limit in which you required those material. 5. take the quotation from suppliers. 6. if you feel that it is ok then visit and select the material required. 7. check the quality of the material and compare the cost of material with others in the market. 8. finalise the cost of material. 9. give him the supply order. 10.after the delivery record taken in the inward register by refering the delivery chalan. 11. check the materials given by the suppliers an accordingly bills payments are done store into the rooms.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J.J Chougule mob no- 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-04

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) MANGAOKAR MANOJ DATTATRAY
Exam No. 13536
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge Checking strength of brick.
Details of how you Planned & Executed the allotted work First we drop brick from 1m height & observe whether it breack or not. We also check water absorption by brick
Details of the Construction Procedure / Activity / Technology learned today how to cut steel rod & observe diametre steel
Details of the Construction Materials learned today STEEL We observe machine cutter for steel cutting . We also cut some specimen.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today We observe working drawing of 2BHk plan
Details of the Bye Laws referred today We observwd set back distance as per BYE-LAWS
Details of any Managerial Skill learned today Give instruction to the site supervisor to unload the materials at proper places so that loss of the material is reduced due to the external agencies.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 CU.M ADDITION FOR DRY VOLUME: 52 % TOTAL VOLUME TO BE MADE: 1.52 CU.M CEMENT: 1.52/1+1.5+3=0.2763 CU.M NUMBER OF BAGS: 0.2763/0.035=7.89=8 CU.M COST= (260X 8)=2080 RS SAND: 0.2763 X 1.5 =0.4144 CU.M COST = (0.4144 X 742.04)=307.50 RS AGGREGATE: 0.2763 X 3=0.8289 CU.M COST= (0.8289 X 636.04)=527.21 RS TOTAL COST OF MATERIAL: 2080+307.50+527.21= 2914.71 RS REINFORCEMENT: 52 KG/CU.M X 32 = 1664 RS LABOURS: 985 RS WATER: 1.5% X (2914.71)=43.72 RS CENTERING AND SHUTTERING : 445 RS TOTAL COST: 6052 RS CONTRACTORS PROFIT: 15% TOTAL COST=6960.29 RS Result of RATE ANALYSIS ( Rs per Unit ): 6960.29 RS/CU.M
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 RS/CU.
Todays BUZZ Word 1. Find the specification required by the building. 2. contact all the suppliers in the market. 3. Give him a letter and quotation required for us. 4. tell them the time limit in which you required those material. 5. take the quotation from suppliers. 6. if you feel that it is ok then visit and select the material required. 7. check the quality of the material and compare the cost of material with others in the market. 8. finalise the cost of material. 9. give him the supply order. 10.after the delivery record taken in the inward register by refering the delivery chalan. 11. check the materials given by the suppliers an accordingly bills payments are done store into the rooms.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J.J Chougule mob no- 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: www.shital_shinde@yahoo.com
Subject: 10884-04

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) SHINDE SHITAL VILAS
Exam No. 10884
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge To observe construction work regarding beams of compound wall.
Details of how you Planned & Executed the allotted work we saw steel reinforcement in compound wall,shuttering is placed exactly parallel to columns with the help of plumb bob.
Details of the Construction Procedure / Activity / Technology learned today Gypsum plaster= used when shortage of soil
Details of the Construction Materials learned today concrete mixing
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Electrification drawings.
Details of the Bye Laws referred today regarding security ROOM size-2m*3m
Details of any Managerial Skill learned today Give instruction to the site supervisor to unload the materials at proper places so that loss of the material is reduced due to the external agencies.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 CU.M ADDITION FOR DRY VOLUME: 52 % TOTAL VOLUME TO BE MADE: 1.52 CU.M CEMENT: 1.52/1+1.5+3=0.2763 CU.M NUMBER OF BAGS: 0.2763/0.035=7.89=8 CU.M COST= (260X 8)=2080 RS SAND: 0.2763 X 1.5 =0.4144 CU.M COST = (0.4144 X 742.04)=307.50 RS AGGREGATE: 0.2763 X 3=0.8289 CU.M COST= (0.8289 X 636.04)=527.21 RS TOTAL COST OF MATERIAL: 2080+307.50+527.21= 2914.71 RS REINFORCEMENT: 52 KG/CU.M X 32 = 1664 RS LABOURS: 985 RS WATER: 1.5% X (2914.71)=43.72 RS CENTERING AND SHUTTERING : 445 RS TOTAL COST: 6052 RS CONTRACTORS PROFIT: 15% TOTAL COST=6960.29 RS Result of RATE ANALYSIS ( Rs per Unit ): 6960.29 RS/CU.M
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 RS/CU.
Todays BUZZ Word 1. Find the specification required by the building. 2. contact all the suppliers in the market. 3. Give him a letter and quotation required for us. 4. tell them the time limit in which you required those material. 5. take the quotation from suppliers. 6. if you feel that it is ok then visit and select the material required. 7. check the quality of the material and compare the cost of material with others in the market. 8. finalise the cost of material. 9. give him the supply order. 10.after the delivery record taken in the inward register by refering the delivery chalan. 11. check the materials given by the suppliers an accordingly bills payments are done store into the rooms.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.ketan charapale Mo.9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-04

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) Jagadale Ashvani Ramrao
Exam No. 13530
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge Checking strength of brick.
Details of how you Planned & Executed the allotted work First we drop brick from 1m height & observe whether it breack or not. We also check water absorption by brick
Details of the Construction Procedure / Activity / Technology learned today how to cut steel rod & observe diametre steel
Details of the Construction Materials learned today STEEL We observe machine cutter for steel cutting . We also cut some specimen.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today We observe working drawing of 2BHk plan
Details of the Bye Laws referred today We observwd set back distance as per BYE-LAWS
Details of any Managerial Skill learned today Give instruction to the site supervisor to unload the materials at proper places so that loss of the material is reduced due to the external agencies.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 CU.M ADDITION FOR DRY VOLUME: 52 % TOTAL VOLUME TO BE MADE: 1.52 CU.M CEMENT: 1.52/1+1.5+3=0.2763 CU.M NUMBER OF BAGS: 0.2763/0.035=7.89=8 CU.M COST= (260X 8)=2080 RS SAND: 0.2763 X 1.5 =0.4144 CU.M COST = (0.4144 X 742.04)=307.50 RS AGGREGATE: 0.2763 X 3=0.8289 CU.M COST= (0.8289 X 636.04)=527.21 RS TOTAL COST OF MATERIAL: 2080+307.50+527.21= 2914.71 RS REINFORCEMENT: 52 KG/CU.M X 32 = 1664 RS LABOURS: 985 RS WATER: 1.5% X (2914.71)=43.72 RS CENTERING AND SHUTTERING : 445 RS TOTAL COST: 6052 RS CONTRACTORS PROFIT: 15% TOTAL COST=6960.29 RS Result of RATE ANALYSIS ( Rs per Unit ): 6960.29 RS/CU.M
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 RS/CU.
Todays BUZZ Word 1. Find the specification required by the building. 2. contact all the suppliers in the market. 3. Give him a letter and quotation required for us. 4. tell them the time limit in which you required those material. 5. take the quotation from suppliers. 6. if you feel that it is ok then visit and select the material required. 7. check the quality of the material and compare the cost of material with others in the market. 8. finalise the cost of material. 9. give him the supply order. 10.after the delivery record taken in the inward register by refering the delivery chalan. 11. check the materials given by the suppliers an accordingly bills payments are done store into the rooms.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr J.J Chougule mob no- 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-04

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Sutar namdev R.
Exam No. 13571
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1) Casting of slab 2) Rate analysis for slab .
Details of how you Planned & Executed the allotted work 1) First we divide our group in two sub-group 2) First group find the procedure for casting of slab & steel distribution. 3) second group analysed the slab quantity .
Details of the Construction Procedure / Activity / Technology learned today A) Centering work for slab 1) First engineer gives detailed drawing for slab i.e. steel details , concrete details , beam detils , column details. B) Form work were arranged by using drawings. C) Surface level cheked by LINE-DORI OR WATER TUBE. D) then steel arranged as per drawings. E) skill supervision should be maintained throught the work. F) the form work should be removed after 28 days to achieved the adequate strength. .
Details of the Construction Materials learned today 1) Steel - 450 & 500 grade 2) M-20 grade concrete .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The vertical supports use for form work should be of steel.Because saving of wood. .
Details of the Construction / Engineering Drawings observed today 1) Reinforcement detail drawing for slab. 2) Centering detail drawing. 3) Beam details drawing. 4) column detail drawing. .
Details of the Bye Laws referred today None. .
Details of any Managerial Skill learned today Details of any Managerial Skill learned today: How to manage labour force & quality of work during casting of slab. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For R.C.C slab by using M-20 (1:1.5:3) Take 3m x 4m span of slab & 150mm thick slab Total quantity of slab : 3m x 4m x 0.150m = 1.8cu.m Total quantity of material required for casting of slab 1) Quantity of Cement : 1.8 /(1+1.5+3) = 0.32cu.m No. of bags required : 0.32 / 0.033 = 9.69 nos. say 10 bags 2)Quantity of Sand : 0.32 x 1.5 = 0.48 cu.m 3)Quantity of aggregate : 0.32 x 3 = 0.96 cu.m Total Quantity of steel required for casting of slab Assume 2% steel of total quantity of slab = 0.036 cu.m Total weight of steel required in KG = 0.036 x 7850 = 282.6 kg Rate analysis for material Material Quantity in cu.m Rate per cu.m Cost Cement 0.32 7575.75/- 2424.2 /- Sand 0.48 2400 /- 1152/- Aggregate 0.96 535 /- 513.6/- Steel 282.6 kg 45/kg 12717/- TOTAL = 16806.84/- Add 1.5% water charges = 252.102/- Add 10 % contractors profit = 1680.684/- Grand Total = 18739.626/- Total cost of concrete required for slab = 4089.85/- Rate analysis for labour Labour Quantity in nos. Rate / day Cost Mason 03 250 750/- M.mazdoor 10 150 1500/- F.mazdoor 10 120 1200/- Bhisty 05 120 600/- Fitter 04 250 1000/- T&P Lump-sum 100 100/- Grand Total = 5150/- For 1 cu.m = 5150/- For 1.8 cu.m = 9270/- Total cost for 1.8 cu.m slab = 18800+9270 = 28070 /- Total cost for 1 cu.m slab = 15600/-
Result of RATE ANALYSIS ( Rs per Unit ) 15600/-
Todays BUZZ Word Construction material contribute the 70% cost of project.So purchasing & quality of material plays an important role in every construction activity to achieve economy. For purchasing any material e.g. Steel following documents are required. a) Steel details like various diameters of bar required their weight in tuns. b) Company of steel & their reputation. c) Quality of steel. d) Minimum rate of material, company which offers for purchasing steel. . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-04

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00a.m.
Site Leaving Time (HH:MM am/pm) 4.15p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge Milind Patil – Site incharge engineer To see the casting of plinth beam.
Details of how you Planned & Executed the allotted work First we observed the beam layout plan & we see actual casting of the beam on site means placing the concrete and compaction.
Details of the Construction Procedure / Activity / Technology learned today Procedure: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. New technology: Needle Vibrator is used for compaction of concrete. Fixing chemical is used for bonding between old & new surfaces of concrete.
Details of the Construction Materials learned today Material learnt today: Steel: Tor steel 8mm ,12mm,16mm,20mm. Mild steel 6mm, Concrete: M-20
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environmental care: To save electrical energy, proper ventilation is provided in the entire project .Up coming proposed buildings are also provided with proper ventilation.
Details of the Construction / Engineering Drawings observed today Drawing: Plinth beam layout plan
Details of the Bye Laws referred today Byelaws: Balcony 1.2m wide according to byelaws.
Details of any Managerial Skill learned today Managerial skill: We met the owner of the project Mr. Lalit Shanghavi .He gave us construction tips and cooperated with us very well. - He gave instructions to site engineer to give us the detail information about the entire project.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. Slab For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Assumed 4m *3m Room and calculated steel requirement in kg/m Steel - 8mm dia. 3*20* .3 9 = 23.4kg/m 12mm dia. 4* 15 * .89 = 53.4 kg/m Total steel required = 76.8kg/m = 76.8 *43 =3302 Rs/- Add 5% wastage = 3468 Rs/- Labour 1cub.m *1260 =1260Rs/- 7510 Rs/- Builders profit including Service tax , VAT etc 7510* 1.20 = 9012 Rs./-sq.m. 20 % This is according to the current rate of material and labour charge
Result of RATE ANALYSIS ( Rs per Unit ) 9012Rs/- per sq.m
Todays BUZZ Word Buzz word : “Purchase/Procurement Department” Purchase department is provided for this project . - Work of this department is to purchase material required for the entire project. - One purchase officer is appointed for this purpose. Here Mr. Preetam Patil is the incharge of this department . - According to site requirement ,purchase officer gives order to the material supplier for various materials. - And then supplier sends material according to demand list . - Then this material is stored in the store room of the project. - One store keeper is provided for checking the material and taking records of all materials. Documents required : 1) Material demand list from purchase officer. 2) Bill & receipt from the material supplier. 3)Record receipt from the store keeper to the main office.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-04

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) shinde sagar
Exam No. 13568
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) Casting of slab 2) Rate analysis for slab .
Details of how you Planned & Executed the allotted work 1) First we divide our group in two sub-group 2) First group find the procedure for casting of slab & steel distribution. 3) second group analysed the slab quantity .
Details of the Construction Procedure / Activity / Technology learned today A) Centering work for slab 1) First engineer gives detailed drawing for slab i.e. steel details , concrete details , beam detils , column details. B) Form work were arranged by using drawings. C) Surface level cheked by LINE-DORI OR WATER TUBE. D) then steel arranged as per drawings. E) skill supervision should be maintained throught the work. F) the form work should be removed after 28 days to achieved the adequate strength. .
Details of the Construction Materials learned today 1) Steel - 450 & 500 grade 2) M-20 grade concrete .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The vertical supports use for form work should be of steel.Because saving of wood. .
Details of the Construction / Engineering Drawings observed today 1) Reinforcement detail drawing for slab. 2) Centering detail drawing. 3) Beam details drawing. 4) column detail drawing. .
Details of the Bye Laws referred today None. .
Details of any Managerial Skill learned today Details of any Managerial Skill learned today: How to manage labour force & quality of work during casting of slab. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For R.C.C slab by using M-20 (1:1.5:3) Take 3m x 4m span of slab & 150mm thick slab Total quantity of slab : 3m x 4m x 0.150m = 1.8cu.m Total quantity of material required for casting of slab 1) Quantity of Cement : 1.8 /(1+1.5+3) = 0.32cu.m No. of bags required : 0.32 / 0.033 = 9.69 nos. say 10 bags 2)Quantity of Sand : 0.32 x 1.5 = 0.48 cu.m 3)Quantity of aggregate : 0.32 x 3 = 0.96 cu.m Total Quantity of steel required for casting of slab Assume 2% steel of total quantity of slab = 0.036 cu.m Total weight of steel required in KG = 0.036 x 7850 = 282.6 kg Rate analysis for material Material Quantity in cu.m Rate per cu.m Cost Cement 0.32 7575.75/- 2424.2 /- Sand 0.48 2400 /- 1152/- Aggregate 0.96 535 /- 513.6/- Steel 282.6 kg 45/kg 12717/- TOTAL = 16806.84/- Add 1.5% water charges = 252.102/- Add 10 % contractors profit = 1680.684/- Grand Total = 18739.626/- Total cost of concrete required for slab = 4089.85/- Rate analysis for labour Labour Quantity in nos. Rate / day Cost Mason 03 250 750/- M.mazdoor 10 150 1500/- F.mazdoor 10 120 1200/- Bhisty 05 120 600/- Fitter 04 250 1000/- T&P Lump-sum 100 100/- Grand Total = 5150/- For 1 cu.m = 5150/- For 1.8 cu.m = 9270/- Total cost for 1.8 cu.m slab = 18800+9270 = 28070 /- Total cost for 1 cu.m slab = 15600/-
Result of RATE ANALYSIS ( Rs per Unit ) 15600/-
Todays BUZZ Word Construction material contribute the 70% cost of project.So purchasing & quality of material plays an important role in every construction activity to achieve economy. For purchasing any material e.g. Steel following documents are required. a) Steel details like various diameters of bar required their weight in tuns. b) Company of steel & their reputation. c) Quality of steel. d) Minimum rate of material, company which offers for purchasing steel. . .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-04

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00a.m.
Site Leaving Time (HH:MM am/pm) 4.15p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge Milind Patil – Site incharge engineer To see the casting of plinth beam.
Details of how you Planned & Executed the allotted work First we observed the beam layout plan & we see actual casting of the beam on site means placing the concrete and compaction.
Details of the Construction Procedure / Activity / Technology learned today Procedure: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. New technology: Needle Vibrator is used for compaction of concrete. Fixing chemical is used for bonding between old & new surfaces of concrete.
Details of the Construction Materials learned today Material learnt today: Steel: Tor steel 8mm ,12mm,16mm,20mm. Mild steel 6mm, Concrete: M-20
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environmental care: To save electrical energy, proper ventilation is provided in the entire project .Up coming proposed buildings are also provided with proper ventilation.
Details of the Construction / Engineering Drawings observed today Drawing: Plinth beam layout plan
Details of the Bye Laws referred today Byelaws: Balcony 1.2m wide according to byelaws.
Details of any Managerial Skill learned today Managerial skill: We met the owner of the project Mr. Lalit Shanghavi .He gave us construction tips and cooperated with us very well. - He gave instructions to site engineer to give us the detail information about the entire project.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. Slab For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Assumed 4m *3m Room and calculated steel requirement in kg/m Steel - 8mm dia. 3*20* .3 9 = 23.4kg/m 12mm dia. 4* 15 * .89 = 53.4 kg/m Total steel required = 76.8kg/m = 76.8 *43 =3302 Rs/- Add 5% wastage = 3468 Rs/- Labour 1cub.m *1260 =1260Rs/- 7510 Rs/- Builders profit including Service tax , VAT etc 7510* 1.20 = 9012 Rs./-sq.m. 20 % This is according to the current rate of material and labour charge
Result of RATE ANALYSIS ( Rs per Unit ) 9012Rs/- per sq.m
Todays BUZZ Word Buzz word : “Purchase/Procurement Department” Purchase department is provided for this project . - Work of this department is to purchase material required for the entire project. - One purchase officer is appointed for this purpose. Here Mr. Preetam Patil is the incharge of this department . - According to site requirement ,purchase officer gives order to the material supplier for various materials. - And then supplier sends material according to demand list . - Then this material is stored in the store room of the project. - One store keeper is provided for checking the material and taking records of all materials. Documents required : 1) Material demand list from purchase officer. 2) Bill & receipt from the material supplier. 3)Record receipt from the store keeper to the main office.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-04

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00a.m.
Site Leaving Time (HH:MM am/pm) 4.15p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge Milind Patil – Site incharge engineer To see the casting of plinth beam.
Details of how you Planned & Executed the allotted work First we observed the beam layout plan & we see actual casting of the beam on site means placing the concrete and compaction.
Details of the Construction Procedure / Activity / Technology learned today Procedure: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. New technology: Needle Vibrator is used for compaction of concrete. Fixing chemical is used for bonding between old & new surfaces of concrete.
Details of the Construction Materials learned today Material learnt today: Steel: Tor steel 8mm ,12mm,16mm,20mm. Mild steel 6mm, Concrete: M-20
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environmental care: To save electrical energy, proper ventilation is provided in the entire project .Up coming proposed buildings are also provided with proper ventilation.
Details of the Construction / Engineering Drawings observed today Drawing: Plinth beam layout plan
Details of the Bye Laws referred today Byelaws: Balcony 1.2m wide according to byelaws.
Details of any Managerial Skill learned today Managerial skill: We met the owner of the project Mr. Lalit Shanghavi .He gave us construction tips and cooperated with us very well. - He gave instructions to site engineer to give us the detail information about the entire project.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. Slab For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Assumed 4m *3m Room and calculated steel requirement in kg/m Steel - 8mm dia. 3*20* .3 9 = 23.4kg/m 12mm dia. 4* 15 * .89 = 53.4 kg/m Total steel required = 76.8kg/m = 76.8 *43 =3302 Rs/- Add 5% wastage = 3468 Rs/- Labour 1cub.m *1260 =1260Rs/- 7510 Rs/- Builders profit including Service tax , VAT etc 7510* 1.20 = 9012 Rs./-sq.m. 20 % This is according to the current rate of material and labour charge
Result of RATE ANALYSIS ( Rs per Unit ) 9012Rs/- per sq.m
Todays BUZZ Word Buzz word : “Purchase/Procurement Department” Purchase department is provided for this project . - Work of this department is to purchase material required for the entire project. - One purchase officer is appointed for this purpose. Here Mr. Preetam Patil is the incharge of this department . - According to site requirement ,purchase officer gives order to the material supplier for various materials. - And then supplier sends material according to demand list . - Then this material is stored in the store room of the project. - One store keeper is provided for checking the material and taking records of all materials. Documents required : 1) Material demand list from purchase officer. 2) Bill & receipt from the material supplier. 3)Record receipt from the store keeper to the main office.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-04

Company Name Sanghavi Sons & Constructions
Project Name & Site Address Sun City,sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00a.m.
Site Leaving Time (HH:MM am/pm) 4.15p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge Milind Patil – Site incharge engineer To see the casting of plinth beam.
Details of how you Planned & Executed the allotted work First we observed the beam layout plan & we see actual casting of the beam on site means placing the concrete and compaction.
Details of the Construction Procedure / Activity / Technology learned today Procedure: - First according to design reinforcement is done . - Then reinforcement is placed in required position. - Then formwork is done for casting. - Then concrete is prepared & placed in this mould. - Compaction is done with the help of needle vibrator. New technology: Needle Vibrator is used for compaction of concrete. Fixing chemical is used for bonding between old & new surfaces of concrete.
Details of the Construction Materials learned today Material learnt today: Steel: Tor steel 8mm ,12mm,16mm,20mm. Mild steel 6mm, Concrete: M-20
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environmental care: To save electrical energy, proper ventilation is provided in the entire project .Up coming proposed buildings are also provided with proper ventilation.
Details of the Construction / Engineering Drawings observed today Drawing: Plinth beam layout plan
Details of the Bye Laws referred today Byelaws: Balcony 1.2m wide according to byelaws.
Details of any Managerial Skill learned today Managerial skill: We met the owner of the project Mr. Lalit Shanghavi .He gave us construction tips and cooperated with us very well. - He gave instructions to site engineer to give us the detail information about the entire project.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. Slab For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Assumed 4m *3m Room and calculated steel requirement in kg/m Steel - 8mm dia. 3*20* .3 9 = 23.4kg/m 12mm dia. 4* 15 * .89 = 53.4 kg/m Total steel required = 76.8kg/m = 76.8 *43 =3302 Rs/- Add 5% wastage = 3468 Rs/- Labour 1cub.m *1260 =1260Rs/- 7510 Rs/- Builders profit including Service tax , VAT etc 7510* 1.20 = 9012 Rs./-sq.m. 20 % This is according to the current rate of material and labour charge
Result of RATE ANALYSIS ( Rs per Unit ) 9012Rs/- per sq.m
Todays BUZZ Word Buzz word : “Purchase/Procurement Department” Purchase department is provided for this project . - Work of this department is to purchase material required for the entire project. - One purchase officer is appointed for this purpose. Here Mr. Preetam Patil is the incharge of this department . - According to site requirement ,purchase officer gives order to the material supplier for various materials. - And then supplier sends material according to demand list . - Then this material is stored in the store room of the project. - One store keeper is provided for checking the material and taking records of all materials. Documents required : 1) Material demand list from purchase officer. 2) Bill & receipt from the material supplier. 3)Record receipt from the store keeper to the main office.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10893-04

Company Name V. S. Joshi & Associates
Project Name & Site Address vishwa enclave,mukta sainik vasahat, kolhapur.
Students Name (Surname_First Name_Middle Name) Kamble Ankit Vijayanand
Exam No. 10893
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30pm
Details of the Work Allotted to you today by the Site In-Charge The work alloted by the site in-charge to we was to -(1)To visit all the flats of each floor . (2)and to record the work in progress by each agencies (3)to measure the no. of workers doing the work of each agencies . (4)and asking the mistri for tommorows work. (5)to know the wages of each labour .(6)to fill the daily report form of site .
Details of how you Planned & Executed the allotted work (1)First we taken the daily report form. (2)we went to each floors and then in each flats. (3)we observed the work going on, agencies like-electrical,flooring,plastering,etc. (4)we observed the no.of labours,type of labours as like-skilled,unskilled,etc. (5)we asked them , upto which the work they are completing today, and what they will do tommorow . (6)we also asked the wages of each labour and recorded it. (7)all this data written in rough book, at last we written it in \'daily report\' form.
Details of the Construction Procedure / Activity / Technology learned today (1)For preparation of water proofing surface, first some quantity of paste is placed on each interval with different thicknesses. (2)for water proofing using the brick bats.
Details of the Construction Materials learned today NO ONE
Details of Environment Caring Technology / Methodology / Procedure / Product learned today FLY ASH CEMENT- USE OF FLY ASH CEMENT IN THE FLOORING WORK
Details of the Construction / Engineering Drawings observed today WE OBSERVED THE DRG. OF FLATS (PLAN) OF EACH FLOOR TODAY.
Details of the Bye Laws referred today NO
Details of any Managerial Skill learned today (1)APPOINT THE LABOUR AS PER WORK DONE REQUIRED. (2)OBSERVE THE LABOURS CAREFULLY. (3)MEASURE THE QUANTITY OF WORK DONE BY THE LABOUR AND GIVE THE WAGES AS PER THE WORK DONE.
RATE ANALYSIS (Detailed Stepwise Calculations required) *RATE ANALYSIS FOR R.C.C. SLAB- -VOLUME OF CONCRETE SLAB= 10 METER CUBE -CONC. MIX=1:2:4 -VOLUME OF CONC. MIX=10.2 METER CUBE A)MATERIALS- 1)STEEL- VOLUME OF STEEL REQD. =1% OF VOLUME OF CONC. =1/100 * 10 =0.1 METER CUBE =0.1*7850=785 kg 2)CEMENT- 15.2/ (1+2+4) =2.17 METER CUBE NO. OF BAGS=(2.17/0.034) * 63.81= 64 BAGS. 3)SAND- 2.17*2=4.34 METER CUBE 4)C.A.- 2.17*4=8.68 METER CUBE 5)BINDING WIRE- 20kg B)COST OF MATERIALS - 1)CEMENT- 64*RS.230= RS.14720 2)SAND- 4.34*850= RS.3639 3)AGGREGATE- 8.08*590= RS.4600 .4 4)STEEL-735*55= 27475 5)BINDING WIRES- 20*55= RS.1100 TOTAL=RS.51584.4 C)COST OF LABOUR- 1)HEAD MASON- 2*250=RS.500 2)MASON- 4*170=RS.680 3)MAJDOOR- 15*110=RS.1650 4)CENTERING AND SHUTTERING- 5% COST OF MATERIAL =5/100 * 51584.4 =RS.2579.22 5)CARPENTER- 10*250=RS.2500 6)NAILS- 1000RS. 7)BLACKSMITH- 15*200=RS.3000 D)TOTAL COST- MATERIAL+LABOUR =51584.4+11908.2 = RS.63493.62 E)ADD 2%FOR WATER CHARGES - 0.02*63493.62 =1269.8724 F)15% CONTRACTORS PROFIT - 0.15*63493.62 =9624.043 G)GRAND TOTAL - D+E+F =RS.74287.54 H)RATE FOR 1 METER CUBE - RS.7428.754
Result of RATE ANALYSIS ( Rs per Unit ) RS.7428.754/ METER CUBE
Todays BUZZ Word *OBJECTIVES AND SCOPE- THE PRINCIPAL OBJECTIVE OF THE PURCHASE DEPT. CAN BE SUMMARIZED AS THE PROCUREMENT OF MATERIALS OF THE BEST QUALITY , IN ACCURATE QUANTITIESAND AT THE RIGHT TIME FROM THE RIGHT SUPPLIER FOR THE CORRECT PRICE. *PROCEDURE DETAILS IN PURCHASE DEPT. - (1)BEFORE STARTING A NEW PROJECT, SPECIFICATIONS OF ALL MATERIALS SHOULD FINALIZED AND REQUISITIONACCEPTED ACCORDINGLY. (2)IF THE SPECIFICATIONS ARE ALTERED BY THE MANAGEMENTOR DUE TO TWO AVAILABILITY OF THE MATERIALS, THE SAME SHOULD BE INTIMATED TO THE PURCHASE DEPT. , ENGG.DEPT. AND THE RESPECTIVE SITE. *FUNCTIONAL PROCEDURE- 1)ACCEPTANCE OF REQUISITIONS 2)ISSUING OF PURCHASE ORDER 3)PENDING REQUISITIONS 4)SITE VISITS 5)REPORTING *DOCUMENTS - 1)REQUISITION 2)PURCHASE ORDER
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Amol Mulay 9922507376
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: gauravdesai75@gmail.com
Subject: 13522-04

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Builders and Developers, Near jayprabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DESAI GAURAV RAVINDRA
Exam No. 13522
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge To check the cover of reinforcement, beams, columns, spacing between stirrups etc. prior to the casting of slab, with the help of plans.
Details of how you Planned & Executed the allotted work We first took the plan showing deatils of beams and columns from site incharge and then went on site checked whether covers were provided or not, spacing between stirrups was proper or not etc.
Details of the Construction Procedure / Activity / Technology learned today While checking the site we found that at some places covers were not provided we informed the site incharge about this then he assigned two ;abours with us and we then told the labours to provide covers for beams, at some palces the shuttering was open and their were chances that the R.M.C would have leaked through it.so we told the labourer to put adhesive tapes their. The structural consulatant came from pune today and he checked whether the beams and colums arrangements were feasible for casting the slabs. He conveyed the faults at various places to the site incharge and accordingly the site incharge conveyed it to the labourers. we helped the structural consultant. he told us the name of column or beam he was checking and we use to tell him the no. of steel (bars) provided for that particular column or beam.
Details of the Construction Materials learned today Ready Mix Concrete(R.M.C)- Ultratech Company. Materials used for covers- R.C.C, Granite. Conduit pipes for electrical wiring. and all other necessary things to be done prior to casting of slab.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. Concreting of slab by Ready Mix Concrete (R.M.C) 2. Vibration by needle vibrator. 3. Compaction by rodding.
Details of the Construction / Engineering Drawings observed today Plan showing schedule of beams and columns and their details. Plan showing electrical fittings.
Details of the Bye Laws referred today According to bye-laws cantilever beams should be placed at L/2 distance. According to bye-laws maximum length of cantilever beam is 4m. On site it is provided 2m.
Details of any Managerial Skill learned today 1. The site supervisor checked the spacing between stirrups, covers provided etc. 2. The site supervisor and the structural consultant found out the faults and they told it to the workers properly. 3. The site supervisor was present on site throughout the casting of slab.
RATE ANALYSIS (Detailed Stepwise Calculations required) For R.C.C Slab. Material: Ultratech Ready Mix Concrete (R.M.C) is used Cost of concrete is - Rs. 3500 /per cu.m. Steel Centering work with adjustable props . Centering for Beams. Providing Fan hook. - Rs. 1500 / per cu.m. Slab and beam covers. Labour __________________ Total cost per cu.m - Rs.5000 /per cu.m Add profit 10% -Rs.500. Total cost of R.C.C SLAB per cu.m -Rs. 5500 /- per cu.m
Result of RATE ANALYSIS ( Rs per Unit ) Rs.5500/- per cu.m
Todays BUZZ Word \"PROCUREMENT/ PURCHASE MATERIALS\" 1.Cement. Bagalkot Supreme 43 grade, 53 grade, white cement as per requirement. 2. Steel . M.S. Steel of mahalaxmi TMT. As per requirements for building. 3. Fresh river sand. 4. Well graded metal. 5. Trap stone metal. 6. Electrical fittings- wires,switches,board,casing pipes etc. as per requirement of each floor. 7. Sanitary fittings- pipes,cocks,valves,meters etc. according to requirements of each floor. 8. Tiles- vitrifried, kitchen otta,for bathrooms etc as per requirement. 9.Doors & Windows- aluminium windows,M.S.grill, different sizes as per required. Doors teakwood,panelled,flushed,pvc coated etc as per requirement. 10. Drainage pipes and inspection Chamber covers,nahni trap etc. as per requirement
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 13567-04

Company Name P. B. Builders & Developers
Project Name & Site Address Preetam Residency , samrat nagar
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) Casting of slab 2) Rate analysis for slab .
Details of how you Planned & Executed the allotted work 1) First we divide our group in two sub-group 2) First group find the procedure for casting of slab & steel distribution. 3) second group analysed the slab quantity. .
Details of the Construction Procedure / Activity / Technology learned today A) Centering work for slab 1) First engineer gives detailed drawing for slab i.e. steel details , concrete details , beam detils , column details. B) Form work were arranged by using drawings. C) Surface level cheked by LINE-DORI OR WATER TUBE. D) then steel arranged as per drawings. E) skill supervision should be maintained throught the work. F) the form work should be removed after 28 days to achieved the adequate strength. .
Details of the Construction Materials learned today 1) Steel - 450 & 500 grade 2) M-20 grade concrete .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The vertical supports use for form work should be of steel.Because saving of wood. .
Details of the Construction / Engineering Drawings observed today 1) Reinforcement detail drawing for slab. 2) Centering detail drawing. 3) Beam details drawing. 4) column detail drawing.
Details of the Bye Laws referred today NONE .
Details of any Managerial Skill learned today How to manage labour force & quality of work during casting of slab. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For R.C.C slab by using M-20 (1:1.5:3) Take 3m x 4m span of slab & 150mm thick slab Total quantity of slab : 3m x 4m x 0.150m = 1.8cu.m Total quantity of material required for casting of slab 1) Quantity of Cement : 1.8 /(1+1.5+3) = 0.32cu.m No. of bags required : 0.32 / 0.033 = 9.69 nos. say 10 bags 2)Quantity of Sand : 0.32 x 1.5 = 0.48 cu.m 3)Quantity of aggregate : 0.32 x 3 = 0.96 cu.m Total Quantity of steel required for casting of slab Assume 2% steel of total quantity of slab = 0.036 cu.m Total weight of steel required in KG = 0.036 x 7850 = 282.6 kg Rate analysis for material Material Quantity in cu.m Rate per cu.m Cost Cement 0.32 7575.75/- 2424.2 /- Sand 0.48 2400 /- 1152/- Aggregate 0.96 535 /- 513.6/- Steel 282.6 kg 45/kg 12717/- TOTAL = 16806.84/- Add 1.5% water charges = 252.102/- Add 10 % contractors profit = 1680.684/- Grand Total = 18739.626/- Total cost of concrete required for slab = 4089.85/- Rate analysis for labour Labour Quantity in nos. Rate / day Cost Mason 03 250 750/- M.mazdoor 10 150 1500/- F.mazdoor 10 120 1200/- Bhisty 05 120 600/- Fitter 04 250 1000/- T&P Lump-sum 100 100/- Grand Total = 5150/- For 1 cu.m = 5150/- For 1.8 cu.m = 9270/- Total cost for 1.8 cu.m slab = 18800+9270 = 28070 /- Total cost for 1 cu.m slab = 15600/- .
Result of RATE ANALYSIS ( Rs per Unit ) 15600/-
Todays BUZZ Word Construction material contribute the 70% cost of project.So purchasing & quality of material plays an important role in every construction activity to achieve economy. For purchasing any material e.g. Steel following documents are required. a) Steel details like various diameters of bar required their weight in tuns. b) Company of steel & their reputation. c) Quality of steel. d) Minimum rate of material, company which offers for purchasing steel. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Pradip Bharamal 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-04

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell,at karande mala, tarabai park
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9:00 am
Site Leaving Time (HH:MM am/pm) 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1)observation the water tank slab steel 2)checking the dimension of water tank
Details of how you Planned & Executed the allotted work 1) we seen the water tank whose located on terrace. 2) we seen hows steel placed in beam 3) observ shuttring 4) steel arrangement and taken dimension 5) size (5.5*2.2*2.8) 6) capacity (25000 liters)
Details of the Construction Procedure / Activity / Technology learned today used gypsum plaster technique now a days used. for less time and less availability of worker
Details of the Construction Materials learned today brick moulding by khanapuri sand (local name) size(9\"*4\"*3\") size should be perfect than soil bricks
Details of Environment Caring Technology / Methodology / Procedure / Product learned today used solar planner for parking
Details of the Construction / Engineering Drawings observed today we seen electric layout 1) gysor 2) washing maching switch 3) exhaust fan 4) lamp 5) fridge switch
Details of the Bye Laws referred today 1) stair case width 0.75m 2) security cabin size(1m*2m)
Details of any Managerial Skill learned today we learn how to planning the whole day
RATE ANALYSIS (Detailed Stepwise Calculations required) RCC SLAB: 1) main bar=6mm spacing 6\" 2) sub bar =8mm spacing 5\" 3)size of slab (3.657*3.048) 4)main bar= 29 nos. 5)sub bar=20 nos. 6)main= 42.456 kg =1273.68 rs. 7)sub bar= 12.192 kg =365 rs. 8)total steel cost =1639.44 rs. 9)concrete cost(1m3) =2855 rs. 10)volm=1.41m3 11) cost- 4025 rs. 12)total cost for slab =(3657.6+3048+127) = 5664.44 rs. 13)labour =2400 14)for 1.41 m3=5664+2400 =8065 15)for 1m3= 5720 rs.
Result of RATE ANALYSIS ( Rs per Unit ) 1m3=5720 rs.
Todays BUZZ Word 1)1st requird materil choosen from delers 2)then order by owner requirment 3)then received materiak checked by site superwiser 4)documents a)quatqtion receipt b)delivary receipt c)received receipt
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-04

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudev
Exam No. 10891
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To casting a Beam. .
Details of how you Planned & Executed the allotted work 1)First we observed beam layout plan of plinth beam 2)according to plan all position of beam is fixed betn. Coloumn 3)Check all material are present in sutable quantity 4)Then starting the work.
Details of the Construction Procedure / Activity / Technology learned today 1)First framework are prepared according to size of beam,by using the plywood.(540*230mm) 2)then steel bar cutting(12mm dia.) length also sitrupes are cutting, 3)then prepared a net of steel & place in mould.oil is apply to mould. 4)then concret prepared in M20 mix by mixer. 5)concret mix place in mould then needle vibretor are place in it for a compaction. *needle vibretor are advance tech. are used on side. *Fixity chemical are used for bonding)
Details of the Construction Materials learned today 1)Steel(12mm, 8mm,6mm dia bar) 2)Binding wire 3)concret mix(1:2:4) .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today To save electrical energy proper ventilation is provided.
Details of the Construction / Engineering Drawings observed today Plinth beam layout plan
Details of the Bye Laws referred today Balcony are provided 1.2M wide. According to bylaws .
Details of any Managerial Skill learned today We meet owner of the project he gave us brif information of handaling the project.(worker handaling, pazetation) he co-oprete very well. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For R.C.C slab by using M-20 (1:1.5:3) Take 3m x 4m span of slab & 150mm thick slab Total quantity of slab : 3m x 4m x 0.150m = 1.8cu.m Total quantity of material required for casting of slab 1) Quantity of Cement : 1.8 /(1+1.5+3) = 0.32cu.m No. of bags required : 0.32 / 0.033 = 9.69 nos. say 10 bags 2)Quantity of Sand : 0.32 x 1.5 = 0.48 cu.m 3)Quantity of aggregate : 0.32 x 3 = 0.96 cu.m Total Quantity of steel required for casting of slab Assume 2% steel of total quantity of slab = 0.036 cu.m Total weight of steel required in KG = 0.036 x 7850 = 282.6 kg Rate analysis for material Material Quantity in cu.m Rate per cu.m Cost Cement 0.32 7575.75/- 2424.2 /- Sand 0.48 2400 /- 1152/- Aggregate 0.96 535 /- 513.6/- Steel 282.6 kg 45/kg 12717/- TOTAL = 16806.84/- Add 1.5% water charges = 252.102/- Add 10 % contractors profit = 1680.684/- Grand Total = 18739.626/- Total cost of concrete required for slab = 4089.85/- Rate analysis for labour Labour Quantity in nos. Rate / day Cost Mason 03 250 750/- M.mazdoor 10 150 1500/- F.mazdoor 10 120 1200/- Bhisty 05 120 600/- Fitter 04 250 1000/- T&P Lump-sum 100 100/- Grand Total = 5150/- For 1 cu.m = 5150/- For 1.8 cu.m = 9270/- Total cost for 1.8 cu.m slab = 18800+9270 = 28070 /- Total cost for 1 cu.m slab = 15600/-
Result of RATE ANALYSIS ( Rs per Unit ) 15600/- m3
Todays BUZZ Word Purchase department contributes towards the companies profit.it is responsible for the procurement of materials required for construction as well as office work. 1.the requisitions should be accepted once a week by the purchace department & material be supplied as per the delivery date mentioned on the requisitions.purchace manager can reject it.mentioning the reason. 2.purchase order- Purchase order is printed format in triplicate copies of different colour .separate order should be issued for each requisition 7 material. 3.receipt of material at site- Store keeper will inspect material received at site for quality as per the specification .if he is satisfied material will be unloaded 4.pending requisitions- If material are not received as per requisitionthen senior engineer must prepare the requisition giving full details of the material required. 5.site visit- Purchase manager should visit the site every week to check the quality of material required ,unutilized excess material in site & to control the inventory & stacking of materils. 6.report- Purchase manager should submit a monthly report with full details.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil. (9890997979) .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-04

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) MISAL SWAPNIL SHIVAJI
Exam No. 10877
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 p.m.
Details of the Work Allotted to you today by the Site In-Charge To observe construction work regarding beams of compound wall.
Details of how you Planned & Executed the allotted work we saw steel reinforcement in compound wall,shuttering is placed exactly parallel to columns with the help of plumb bob.
Details of the Construction Procedure / Activity / Technology learned today Gypsum plaster= used when shortage of soil.
Details of the Construction Materials learned today concrete mixing.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Electrification drawings.
Details of the Bye Laws referred today regarding security cabin size-2m*3m
Details of any Managerial Skill learned today Give instruction to the site supervisor to unload the materials at proper places so that loss of the material is reduced due to the external agencies.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 CU.M ADDITION FOR DRY VOLUME: 52 % TOTAL VOLUME TO BE MADE: 1.52 CU.M CEMENT: 1.52/1+1.5+3=0.2763 CU.M NUMBER OF BAGS: 0.2763/0.035=7.89=8 CU.M COST= (260X 8)=2080 RS SAND: 0.2763 X 1.5 =0.4144 CU.M COST = (0.4144 X 742.04)=307.50 RS AGGREGATE: 0.2763 X 3=0.8289 CU.M COST= (0.8289 X 636.04)=527.21 RS TOTAL COST OF MATERIAL: 2080+307.50+527.21= 2914.71 RS REINFORCEMENT: 52 KG/CU.M X 32 = 1664 RS LABOURS: 985 RS WATER: 1.5% X (2914.71)=43.72 RS CENTERING AND SHUTTERING : 445 RS TOTAL COST: 6052 RS CONTRACTORS PROFIT: 15% TOTAL COST=6960.29 RS
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 RS/CU.M
Todays BUZZ Word PROCEDURE REQUIRED FOR PURCHASING THE MATERIALS: 1. Find the specification required by the building. 2. contact all the suppliers in the market. 3. Give him a letter and quotation required for us. 4. tell them the time limit in which you required those material. 5. take the quotation from suppliers. 6. if you feel that it is ok then visit and select the material required. 7. check the quality of the material and compare the cost of material with others in the market. 8. finalise the cost of material. 9. give him the supply order. 10.after the delivery record taken in the inward register by refering the delivery chalan. 11. check the materials given by the suppliers an accordingly bills payments are done store into the rooms.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.ketan charapale Mo.9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-04

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge To casting a Beam. .
Details of how you Planned & Executed the allotted work 1)First we observed beam layout plan of plinth beam 2)according to plan all position of beam is fixed betn. Coloumn 3)Check all material are present in sutable quantity 4)Then starting the work. .
Details of the Construction Procedure / Activity / Technology learned today 1)First framework are prepared according to size of beam,by using the plywood.(540*230mm) 2)then steel bar cutting(12mm dia.) length also sitrupes are cutting, 3)then prepared a net of steel & place in mould.oil is apply to mould. 4)then concret prepared in M20 mix by mixer. 5)concret mix place in mould then needle vibretor are place in it for a compaction. *needle vibretor are advance tech. are used on side. *Fixity chemical are used for bonding)
Details of the Construction Materials learned today 1)Steel(12mm, 8mm,6mm dia bar) 2)Binding wire 3)concret mix(1:2:4)
Details of Environment Caring Technology / Methodology / Procedure / Product learned today To save electrical energy proper ventilation is provided. .
Details of the Construction / Engineering Drawings observed today Plinth beam layout plan .
Details of the Bye Laws referred today Balcony are provided 1.2M wide. According to bylaws
Details of any Managerial Skill learned today We meet owner of the project he gave us brif information of handaling the project.(worker handaling, pazetation) he co-oprete very well. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis For R.C.C slab by using M-20 (1:1.5:3) Take 3m x 4m span of slab & 150mm thick slab Total quantity of slab : 3m x 4m x 0.150m = 1.8cu.m Total quantity of material required for casting of slab 1) Quantity of Cement : 1.8 /(1+1.5+3) = 0.32cu.m No. of bags required : 0.32 / 0.033 = 9.69 nos. say 10 bags 2)Quantity of Sand : 0.32 x 1.5 = 0.48 cu.m 3)Quantity of aggregate : 0.32 x 3 = 0.96 cu.m Total Quantity of steel required for casting of slab Assume 2% steel of total quantity of slab = 0.036 cu.m Total weight of steel required in KG = 0.036 x 7850 = 282.6 kg Rate analysis for material Material Quantity in cu.m Rate per cu.m Cost Cement 0.32 7575.75/- 2424.2 /- Sand 0.48 2400 /- 1152/- Aggregate 0.96 535 /- 513.6/- Steel 282.6 kg 45/kg 12717/- TOTAL = 16806.84/- Add 1.5% water charges = 252.102/- Add 10 % contractors profit = 1680.684/- Grand Total = 18739.626/- Total cost of concrete required for slab = 4089.85/- Rate analysis for labour Labour Quantity in nos. Rate / day Cost Mason 03 250 750/- M.mazdoor 10 150 1500/- F.mazdoor 10 120 1200/- Bhisty 05 120 600/- Fitter 04 250 1000/- T&P Lump-sum 100 100/- Grand Total = 5150/- For 1 cu.m = 5150/- For 1.8 cu.m = 9270/- Total cost for 1.8 cu.m slab = 18800+9270 = 28070 /- Total cost for 1 cu.m slab = 15600/-
Result of RATE ANALYSIS ( Rs per Unit ) 15600/- m3
Todays BUZZ Word Purchase department contributes towards the companies profit.it is responsible for the procurement of materials required for construction as well as office work. 1.the requisitions should be accepted once a week by the purchace department & material be supplied as per the delivery date mentioned on the requisitions.purchace manager can reject it.mentioning the reason. 2.purchase order- Purchase order is printed format in triplicate copies of different colour .separate order should be issued for each requisition 7 material. 3.receipt of material at site- Store keeper will inspect material received at site for quality as per the specification .if he is satisfied material will be unloaded 4.pending requisitions- If material are not received as per requisitionthen senior engineer must prepare the requisition giving full details of the material required. 5.site visit- Purchase manager should visit the site every week to check the quality of material required ,unutilized excess material in site & to control the inventory & stacking of materils. 6.report- Purchase manager should submit a monthly report with full details. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil (9890997979)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: nitinpatil22.2010@rediffmail.com
Subject: 10879-04

Company Name S. S. Developers & Builders
Project Name & Site Address witer training,s.s developers & builders ,circuit house,karande mala
Students Name (Surname_First Name_Middle Name) patil nitin dilip
Exam No. 10879
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge 1)observing the casting of the beam of compound wall 2)observing the water tank slab 3)tank size(2.2m x 5.5m x 2.8m )capacity=25000lit
Details of how you Planned & Executed the allotted work first we desided to see casting of the beam & how the steel bar are placed,septik tank construction
Details of the Construction Procedure / Activity / Technology learned today 1)use of the gypsem plaster instead of the plastering method.this method used where the time is less /no sufficint worker available 2)how carrying the material from ground floor to last top floor
Details of the Construction Materials learned today 1)brick-local name- khanapuri brick 2)size=(9\"x4\"x3\") 3)gokak sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1)plant the tress around totl area 2)garden 3)solar panal for parking light
Details of the Construction / Engineering Drawings observed today 1)electrification- containt- 1.bell push 2.s.b 3.exaust fan 4.tv s.b 5.refrigarator
Details of the Bye Laws referred today 1)raw housing-stair case- size-0.75 2)security room-size-1mx2m
Details of any Managerial Skill learned today how to face the problem to ste like electricity,water supply.how to handle the labour prroblem
RATE ANALYSIS (Detailed Stepwise Calculations required) sub bar 6mm spacing 6\" main bar 8mm spaciong 5\" (3567.6mm x 3048mm) main bar=29no sub bar=20no main length bar=3.6576m wt of 1 for 1m=400gm 36576=1.46kg 29x1,464=42.456kg=1273.86 sub bar length=3.04m 1 bar wt for 1m=200gm for 3.048m length=wt=609.6gm 20x609.6=12092kg=365.76 Rs total steel=1639.44Rs concreete cast for 1 cu.m=2855 Rs vol=1.41 cu.m 1.41 cu.m=4025Rs totl=5664.44 Rs labour=2400+5664.44=8064.44Rs total cost 1.41-8064Rs 1 cu.m=5720 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 5720 Rs=1 cu.m
Todays BUZZ Word receiving the materil reqd for construction are checked by superviser & he gives the receipt.He gives the money or check
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge ketan charaple-9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-04

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Abhishek Dadasaheb
Exam No. 10895
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check cover of spacing of steel reinforcement in beams.
Details of how you Planned & Executed the allotted work First of all we took the drawing of steel reinforcement &observing it.we check all the spacing between the steel where the covers are used &of what diameters are used.also we checked whether the plates used for slab are in proper level or not. .
Details of the Construction Procedure / Activity / Technology learned today Today we learned how the quantity of material in dumper is measured.firstly we fixed a steel bar at center of it.&we marked the height of it.&then we measured the length &breadth of the material & then we calculate the volume of the material. .
Details of the Construction Materials learned today Today we learned plum concrete material which is used here on the site for the compound wall.in plumconcrete,boulders,sand,aggregate&lime are used. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such technology we learned today.
Details of the Construction / Engineering Drawings observed today Today also we observed structural drawing of slab &according to it we checked all spacing &cover used for it. .
Details of the Bye Laws referred today Today we referred the staircase details in bye-laws.width of staircase is according to the bye-laws i.e1.2m.tread should be minimum 300mm & rise should be 150mm.on our site tread is 280mm &rise 150mm. .
Details of any Managerial Skill learned today Today we referred the staircase details in bye-laws.width of staircase is according to the bye-laws i.e1.2m.tread should be minimum 300mm & rise should be 150mm.on our site tread is 280mm &rise 150mm.
RATE ANALYSIS (Detailed Stepwise Calculations required) M20 slab/m3 Cement 6.90bag @240/- 1656/- Sand 0.6m3@915/- 549/- Metal 0.9m3@415/- 374/- Steel 78kg@35/- 2730/- Steel shuttering material & labor 8.00m2@225/- 1840/- Concrete pouring labor @350/m3 350/- 2% electricity & curing 94/- 20% tax overhead & profit 964/- Total 8500/m3
Result of RATE ANALYSIS ( Rs per Unit ) 8500/m3
Todays BUZZ Word Purchase department contributes towards the companies profit.it is responsible for the procurement of materials required for construction as well as office work. 1.the requisitions should be accepted once a week by the purchace department & material be supplied as per the delivery date mentioned on the requisitions.purchace manager can reject it.mentioning the reason. 2.purchase order- Purchase order is printed format in triplicate copies of different colour .separate order should be issued for each requisition 7 material. 3.receipt of material at site- Store keeper will inspect material received at site for quality as per the specification .if he is satisfied material will be unloaded 4.pending requisitions- If material are not received as per requisitionthen senior engineer must prepare the requisition giving full details of the material required. 5.site visit- Purchase manager should visit the site every week to check the quality of material required ,unutilized excess material in site & to control the inventory & stacking of materils. 6.report- Purchase manager should submit a monthly report with full details.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-04

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Sawant Amit Ganpat
Exam No. 10900
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check cover of spacing of steel reinforcement in beams. .
Details of how you Planned & Executed the allotted work First of all we took the drawing of steel reinforcement &observing it.we check all the spacing between the steel where the covers are used &of what diameters are used.also we checked whether the plates used for slab are in proper level or not. . .
Details of the Construction Procedure / Activity / Technology learned today Today we learned how the quantity of material in dumper is measured.firstly we fixed a steel bar at center of it.&we marked the height of it.&then we measured the length &breadth of the material & then we calculate the volume of the material. .
Details of the Construction Materials learned today Today we learned plum concrete material which is used here on the site for the compound wall.in plumconcrete,boulders,sand,aggregate&lime are used. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such technology we learned today. .
Details of the Construction / Engineering Drawings observed today Today also we observed structural drawing of slab &according to it we checked all spacing &cover used for it. .
Details of the Bye Laws referred today Today we referred the staircase details in bye-laws.width of staircase is according to the bye-laws i.e1.2m.tread should be minimum 300mm & rise should be 150mm.on our site tread is 280mm &rise 150mm. .
Details of any Managerial Skill learned today Today we referred the staircase details in bye-laws.width of staircase is according to the bye-laws i.e1.2m.tread should be minimum 300mm & rise should be 150mm.on our site tread is 280mm &rise 150mm. .
RATE ANALYSIS (Detailed Stepwise Calculations required) M20 slab/m3 Cement 6.90bag @240/- 1656/- Sand 0.6m3@915/- 549/- Metal 0.9m3@415/- 374/- Steel 78kg@35/- 2730/- Steel shuttering material & labor 8.00m2@225/- 1840/- Concrete pouring labor @350/m3 350/- 2% electricity & curing 94/- 20% tax overhead & profit 964/- Total 8500/m3 .
Result of RATE ANALYSIS ( Rs per Unit ) 8500/m3
Todays BUZZ Word Purchase department contributes towards the companies profit.it is responsible for the procurement of materials required for construction as well as office work. 1.the requisitions should be accepted once a week by the purchace department & material be supplied as per the delivery date mentioned on the requisitions.purchace manager can reject it.mentioning the reason. 2.purchase order- Purchase order is printed format in triplicate copies of different colour .separate order should be issued for each requisition 7 material. 3.receipt of material at site- Store keeper will inspect material received at site for quality as per the specification .if he is satisfied material will be unloaded 4.pending requisitions- If material are not received as per requisitionthen senior engineer must prepare the requisition giving full details of the material required. 5.site visit- Purchase manager should visit the site every week to check the quality of material required ,unutilized excess material in site & to control the inventory & stacking of materils. 6.report- Purchase manager should submit a monthly report with full details. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-04

Company Name Star Tech Infra
Project Name & Site Address star aashiyana, rajendra nagar
Students Name (Surname_First Name_Middle Name) kolekar prasad bhanudas
Exam No. 10876
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge Brick work, plastering.
Details of how you Planned & Executed the allotted work we observe process of plastering, How they level it, thickness is 0.5 inches. in brickwork of compound wall they maintain only strecher bond due to big size of brick.
Details of the Construction Procedure / Activity / Technology learned today Plastering, Brick bond etc.
Details of the Construction Materials learned today Mortor for plasterig & brickwork.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting.
Details of the Construction / Engineering Drawings observed today drawing for column & beam.
Details of the Bye Laws referred today bye laws for parking.
Details of any Managerial Skill learned today no.
RATE ANALYSIS (Detailed Stepwise Calculations required) RCC SLAB concrete=3300Rs labour cost is 23Rs 1sq.ft. slab of 6 inches for 1 cu.ft=2*23=46Rs for 1cu.m=35.28*46=1623Rs 5% wastage=246Rs 75kg steel*37Rs=2625Rs 20% contractor profit=1559Rs TOTAL=9353Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 9353 Rs per cu.m.
Todays BUZZ Word PURCHASE DEPARTMENT procedure detail in purchase department A. acceptance of requisition B. issuing of purchase order C. pending requisition D. site visits E. reporting
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish mestri 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-04

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Sharad Shankarrao
Exam No. 10897
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check cover of spacing of steel reinforcement in beams. .
Details of how you Planned & Executed the allotted work First of all we took the drawing of steel reinforcement &observing it.we check all the spacing between the steel where the covers are used &of what diameters are used.also we checked whether the plates used for slab are in proper level or not. .
Details of the Construction Procedure / Activity / Technology learned today Today we learned how the quantity of material in dumper is measured.firstly we fixed a steel bar at center of it.&we marked the height of it.&then we measured the length &breadth of the material & then we calculate the volume of the material. .
Details of the Construction Materials learned today Today we learned plum concrete material which is used here on the site for the compound wall.in plumconcrete,boulders,sand,aggregate&lime are used. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such technology we learned today. .
Details of the Construction / Engineering Drawings observed today Today also we observed structural drawing of slab &according to it we checked all spacing &cover used for it. .
Details of the Bye Laws referred today Today we referred the staircase details in bye-laws.width of staircase is according to the bye-laws i.e1.2m.tread should be minimum 300mm & rise should be 150mm.on our site tread is 280mm &rise 150mm.
Details of any Managerial Skill learned today Today we referred the staircase details in bye-laws.width of staircase is according to the bye-laws i.e1.2m.tread should be minimum 300mm & rise should be 150mm.on our site tread is 280mm &rise 150mm.
RATE ANALYSIS (Detailed Stepwise Calculations required) M20 slab/m3 Cement 6.90bag @240/- 1656/- Sand 0.6m3@915/- 549/- Metal 0.9m3@415/- 374/- Steel 78kg@35/- 2730/- Steel shuttering material & labor 8.00m2@225/- 1840/- Concrete pouring labor @350/m3 350/- 2% electricity & curing 94/- 20% tax overhead & profit 964/- Total 8500/m3
Result of RATE ANALYSIS ( Rs per Unit ) 8500/m3
Todays BUZZ Word Purchase department contributes towards the companies profit.it is responsible for the procurement of materials required for construction as well as office work. 1.the requisitions should be accepted once a week by the purchace department & material be supplied as per the delivery date mentioned on the requisitions.purchace manager can reject it.mentioning the reason. 2.purchase order- Purchase order is printed format in triplicate copies of different colour .separate order should be issued for each requisition 7 material. 3.receipt of material at site- Store keeper will inspect material received at site for quality as per the specification .if he is satisfied material will be unloaded 4.pending requisitions- If material are not received as per requisitionthen senior engineer must prepare the requisition giving full details of the material required. 5.site visit- Purchase manager should visit the site every week to check the quality of material required ,unutilized excess material in site & to control the inventory & stacking of materils. 6.report- Purchase manager should submit a monthly report with full details. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-04

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Tambe Trusha Sitaram
Exam No. 10902
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check cover of spacing of steel reinforcement in beams. .
Details of how you Planned & Executed the allotted work First of all we took the drawing of steel reinforcement &observing it.we check all the spacing between the steel where the covers are used &of what diameters are used.also we checked whether the plates used for slab are in proper level or not. .
Details of the Construction Procedure / Activity / Technology learned today Today we learned how the quantity of material in dumper is measured.firstly we fixed a steel bar at center of it.&we marked the height of it.&then we measured the length &breadth of the material & then we calculate the volume of the material. .
Details of the Construction Materials learned today Today we learned plum concrete material which is used here on the site for the compound wall.in plumconcrete,boulders,sand,aggregate&lime are used. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such technology we learned today. .
Details of the Construction / Engineering Drawings observed today Today also we observed structural drawing of slab &according to it we checked all spacing &cover used for it. .
Details of the Bye Laws referred today Today we referred the staircase details in bye-laws.width of staircase is according to the bye-laws i.e1.2m.tread should be minimum 300mm & rise should be 150mm.on our site tread is 280mm &rise 150mm.
Details of any Managerial Skill learned today Today we referred the staircase details in bye-laws.width of staircase is according to the bye-laws i.e1.2m.tread should be minimum 300mm & rise should be 150mm.on our site tread is 280mm &rise 150mm.
RATE ANALYSIS (Detailed Stepwise Calculations required) M20 slab/m3 Cement 6.90bag @240/- 1656/- Sand 0.6m3@915/- 549/- Metal 0.9m3@415/- 374/- Steel 78kg@35/- 2730/- Steel shuttering material & labor 8.00m2@225/- 1840/- Concrete pouring labor @350/m3 350/- 2% electricity & curing 94/- 20% tax overhead & profit 964/- Total 8500/m3
Result of RATE ANALYSIS ( Rs per Unit ) 8500/m3
Todays BUZZ Word Purchase department contributes towards the companies profit.it is responsible for the procurement of materials required for construction as well as office work. 1.the requisitions should be accepted once a week by the purchace department & material be supplied as per the delivery date mentioned on the requisitions.purchace manager can reject it.mentioning the reason. 2.purchase order- Purchase order is printed format in triplicate copies of different colour .separate order should be issued for each requisition 7 material. 3.receipt of material at site- Store keeper will inspect material received at site for quality as per the specification .if he is satisfied material will be unloaded 4.pending requisitions- If material are not received as per requisitionthen senior engineer must prepare the requisition giving full details of the material required. 5.site visit- Purchase manager should visit the site every week to check the quality of material required ,unutilized excess material in site & to control the inventory & stacking of materils. 6.report- Purchase manager should submit a monthly report with full details. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: buntyphonde@gmail.com
Subject: 10899-04

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Phonde Pravin Tukaram
Exam No. 10899
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check cover of spacing of steel reinforcement in beams. .
Details of how you Planned & Executed the allotted work First of all we took the drawing of steel reinforcement &observing it.we check all the spacing between the steel where the covers are used &of what diameters are used.also we checked whether the plates used for slab are in proper level or not. .
Details of the Construction Procedure / Activity / Technology learned today Today we learned how the quantity of material in dumper is measured.firstly we fixed a steel bar at center of it.&we marked the height of it.&then we measured the length &breadth of the material & then we calculate the volume of the material. .
Details of the Construction Materials learned today Today we learned plum concrete material which is used here on the site for the compound wall.in plumconcrete,boulders,sand,aggregate&lime are used. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such technology we learned today. .
Details of the Construction / Engineering Drawings observed today Today also we observed structural drawing of slab &according to it we checked all spacing &cover used for it. .
Details of the Bye Laws referred today Today we referred the staircase details in bye-laws.width of staircase is according to the bye-laws i.e1.2m.tread should be minimum 300mm & rise should be 150mm.on our site tread is 280mm &rise 150mm.
Details of any Managerial Skill learned today Today we referred the staircase details in bye-laws.width of staircase is according to the bye-laws i.e1.2m.tread should be minimum 300mm & rise should be 150mm.on our site tread is 280mm &rise 150mm.
RATE ANALYSIS (Detailed Stepwise Calculations required) M20 slab/m3 Cement 6.90bag @240/- 1656/- Sand 0.6m3@915/- 549/- Metal 0.9m3@415/- 374/- Steel 78kg@35/- 2730/- Steel shuttering material & labor 8.00m2@225/- 1840/- Concrete pouring labor @350/m3 350/- 2% electricity & curing 94/- 20% tax overhead & profit 964/- Total 8500/m3
Result of RATE ANALYSIS ( Rs per Unit ) 8500/m3
Todays BUZZ Word Purchase department contributes towards the companies profit.it is responsible for the procurement of materials required for construction as well as office work. 1.the requisitions should be accepted once a week by the purchace department & material be supplied as per the delivery date mentioned on the requisitions.purchace manager can reject it.mentioning the reason. 2.purchase order- Purchase order is printed format in triplicate copies of different colour .separate order should be issued for each requisition 7 material. 3.receipt of material at site- Store keeper will inspect material received at site for quality as per the specification .if he is satisfied material will be unloaded 4.pending requisitions- If material are not received as per requisitionthen senior engineer must prepare the requisition giving full details of the material required. 5.site visit- Purchase manager should visit the site every week to check the quality of material required ,unutilized excess material in site & to control the inventory & stacking of materils. 6.report- Purchase manager should submit a monthly report with full details. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge jagtap m.s 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: shindeamol5255@yahoo.in
Subject: 13546-04

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHINDE AMOL JAGANNATH
Exam No. 13546
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge check out the detail of wiring materials used.
Details of how you Planned & Executed the allotted work We studied about the electrification drawings and go to the flats , by consulting the wireman there we are try to find out the details about the work alloted to us today.
Details of the Construction Procedure / Activity / Technology learned today 1. provision of the telephones,and broadband in all the bedrooms , living rooms. 2. seperate circuit is for each room with concealed wiring. 3.for fans, tubes, low voltage operating units wire of 1 mm is used. 4. for board to board supply 1.5 mm is used. 4. for high voltage units wires 2.5 mm is used. 5. +, -, and earthing wire is used from transformer to main circuit board then from board to units +,- wires are used. 6. wires are available in 90 m length.
Details of the Construction Materials learned today main circuit boards, types of wires as per the capacity of current, P.V.C. pipes used in concealed wiring.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Electrification drawings.
Details of the Bye Laws referred today None
Details of any Managerial Skill learned today Give instruction to the site supervisor to unload the materials at proper places so that loss of the material is reduced due to the external agencies.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 CU.M ADDITION FOR DRY VOLUME: 52 % TOTAL VOLUME TO BE MADE: 1.52 CU.M CEMENT: 1.52/1+1.5+3=0.2763 CU.M NUMBER OF BAGS: 0.2763/0.035=7.89=8 CU.M COST= (260X 8)=2080 RS SAND: 0.2763 X 1.5 =0.4144 CU.M COST = (0.4144 X 742.04)=307.50 RS AGGREGATE: 0.2763 X 3=0.8289 CU.M COST= (0.8289 X 636.04)=527.21 RS TOTAL COST OF MATERIAL: 2080+307.50+527.21= 2914.71 RS REINFORCEMENT: 52 KG/CU.M X 32 = 1664 RS LABOURS: 985 RS WATER: 1.5% X (2914.71)=43.72 RS CENTERING AND SHUTTERING : 445 RS TOTAL COST: 6052 RS CONTRACTORS PROFIT: 15% TOTAL COST=6960.29 RS
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 RS/CU.M
Todays BUZZ Word PROCEDURE REQUIRED FOR PURCHASING THE MATERIALS: 1. Find the specification required by the building. 2. contact all the suppliers in the market. 3. Give him a letter and quotation required for us. 4. tell them the time limit in which you required those material. 5. take the quotation from suppliers. 6. if you feel that it is ok then visit and select the material required. 7. check the quality of the material and compare the cost of material with others in the market. 8. finalise the cost of material. 9. give him the supply order. 10.after the delivery record taken in the inward register by refering the delivery chalan. 11. check the materials given by the suppliers an accordingly bills payments are done store into the rooms.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. RAJESH CHOUGALE 9822502199
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-04

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHAIKH RIZWAN KHALIL
Exam No. 13545
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge check out the detail of wiring materials used.
Details of how you Planned & Executed the allotted work We studied about the electrification drawings and go to the flats , by consulting the wireman there we are try to find out the details about the work alloted to us today.
Details of the Construction Procedure / Activity / Technology learned today 1. provision of the telephones,and broadband in all the bedrooms , living rooms. 2. seperate circuit is for each room with concealed wiring. 3.for fans, tubes, low voltage operating units wire of 1 mm is used. 4. for board to board supply 1.5 mm is used. 4. for high voltage units wires 2.5 mm is used. 5. +, -, and earthing wire is used from transformer to main circuit board then from board to units +,- wires are used. 6. wires are available in 90 m length.
Details of the Construction Materials learned today main circuit boards, types of wires as per the capacity of current, P.V.C. pipes used in concealed wiring.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Electrification drawings.
Details of the Bye Laws referred today None
Details of any Managerial Skill learned today Give instruction to the site supervisor to unload the materials at proper places so that loss of the material is reduced due to the external agencies.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 CU.M ADDITION FOR DRY VOLUME: 52 % TOTAL VOLUME TO BE MADE: 1.52 CU.M CEMENT: 1.52/1+1.5+3=0.2763 CU.M NUMBER OF BAGS: 0.2763/0.035=7.89=8 CU.M COST= (260X 8)=2080 RS SAND: 0.2763 X 1.5 =0.4144 CU.M COST = (0.4144 X 742.04)=307.50 RS AGGREGATE: 0.2763 X 3=0.8289 CU.M COST= (0.8289 X 636.04)=527.21 RS TOTAL COST OF MATERIAL: 2080+307.50+527.21= 2914.71 RS REINFORCEMENT: 52 KG/CU.M X 32 = 1664 RS LABOURS: 985 RS WATER: 1.5% X (2914.71)=43.72 RS CENTERING AND SHUTTERING : 445 RS TOTAL COST: 6052 RS CONTRACTORS PROFIT: 15% TOTAL COST=6960.29 RS
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 RS/CU.M
Todays BUZZ Word PROCEDURE REQUIRED FOR PURCHASING THE MATERIALS: 1. Find the specification required by the building. 2. contact all the suppliers in the market. 3. Give him a letter and quotation required for us. 4. tell them the time limit in which you required those material. 5. take the quotation from suppliers. 6. if you feel that it is ok then visit and select the material required. 7. check the quality of the material and compare the cost of material with others in the market. 8. finalise the cost of material. 9. give him the supply order. 10.after the delivery record taken in the inward register by refering the delivery chalan. 11. check the materials given by the suppliers an accordingly bills payments are done store into the rooms.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. RAJESH CHOUGALE 9822502199
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-04

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SALOKHE SUDARSHAN ANIL
Exam No. 13544
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge check out the detail of wiring materials used.
Details of how you Planned & Executed the allotted work We studied about the electrification drawings and go to the flats , by consulting the wireman there we are try to find out the details about the work alloted to us today.
Details of the Construction Procedure / Activity / Technology learned today 1. provision of the telephones,and broadband in all the bedrooms , living rooms. 2. seperate circuit is for each room with concealed wiring. 3.for fans, tubes, low voltage operating units wire of 1 mm is used. 4. for board to board supply 1.5 mm is used. 4. for high voltage units wires 2.5 mm is used. 5. +, -, and earthing wire is used from transformer to main circuit board then from board to units +,- wires are used. 6. wires are available in 90 m length.
Details of the Construction Materials learned today main circuit boards, types of wires as per the capacity of current, P.V.C. pipes used in concealed wiring.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Electrification drawings.
Details of the Bye Laws referred today None
Details of any Managerial Skill learned today Give instruction to the site supervisor to unload the materials at proper places so that loss of the material is reduced due to the external agencies.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 CU.M ADDITION FOR DRY VOLUME: 52 % TOTAL VOLUME TO BE MADE: 1.52 CU.M CEMENT: 1.52/1+1.5+3=0.2763 CU.M NUMBER OF BAGS: 0.2763/0.035=7.89=8 CU.M COST= (260X 8)=2080 RS SAND: 0.2763 X 1.5 =0.4144 CU.M COST = (0.4144 X 742.04)=307.50 RS AGGREGATE: 0.2763 X 3=0.8289 CU.M COST= (0.8289 X 636.04)=527.21 RS TOTAL COST OF MATERIAL: 2080+307.50+527.21= 2914.71 RS REINFORCEMENT: 52 KG/CU.M X 32 = 1664 RS LABOURS: 985 RS WATER: 1.5% X (2914.71)=43.72 RS CENTERING AND SHUTTERING : 445 RS TOTAL COST: 6052 RS CONTRACTORS PROFIT: 15% TOTAL COST=6960.29 RS
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 RS/CU.M
Todays BUZZ Word PROCEDURE REQUIRED FOR PURCHASING THE MATERIALS: 1. Find the specification required by the building. 2. contact all the suppliers in the market. 3. Give him a letter and quotation required for us. 4. tell them the time limit in which you required those material. 5. take the quotation from suppliers. 6. if you feel that it is ok then visit and select the material required. 7. check the quality of the material and compare the cost of material with others in the market. 8. finalise the cost of material. 9. give him the supply order. 10.after the delivery record taken in the inward register by refering the delivery chalan. 11. check the materials given by the suppliers an accordingly bills payments are done store into the rooms.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. RAJESH CHOUGALE 9822502199
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-04

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SINGH RAJAN RAJENDRA BAHADUR
Exam No. 13548
Working Day No. 04
Date (DD/MM/YYYY) 11-12-2010
Site Reporting Time (HH:MM am/pm) 08.55 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge check out the detail of wiring materials used.
Details of how you Planned & Executed the allotted work We studied about the electrification drawings and go to the flats , by consulting the wireman there we are try to find out the details about the work alloted to us today.
Details of the Construction Procedure / Activity / Technology learned today 1. provision of the telephones,and broadband in all the bedrooms , living rooms. 2. seperate circuit is for each room with concealed wiring. 3.for fans, tubes, low voltage operating units wire of 1 mm is used. 4. for board to board supply 1.5 mm is used. 4. for high voltage units wires 2.5 mm is used. 5. +, -, and earthing wire is used from transformer to main circuit board then from board to units +,- wires are used. 6. wires are available in 90 m length.
Details of the Construction Materials learned today main circuit boards, types of wires as per the capacity of current, P.V.C. pipes used in concealed wiring.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today Electrification drawings.
Details of the Bye Laws referred today None
Details of any Managerial Skill learned today Give instruction to the site supervisor to unload the materials at proper places so that loss of the material is reduced due to the external agencies.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 CU.M ADDITION FOR DRY VOLUME: 52 % TOTAL VOLUME TO BE MADE: 1.52 CU.M CEMENT: 1.52/1+1.5+3=0.2763 CU.M NUMBER OF BAGS: 0.2763/0.035=7.89=8 CU.M COST= (260X 8)=2080 RS SAND: 0.2763 X 1.5 =0.4144 CU.M COST = (0.4144 X 742.04)=307.50 RS AGGREGATE: 0.2763 X 3=0.8289 CU.M COST= (0.8289 X 636.04)=527.21 RS TOTAL COST OF MATERIAL: 2080+307.50+527.21= 2914.71 RS REINFORCEMENT: 52 KG/CU.M X 32 = 1664 RS LABOURS: 985 RS WATER: 1.5% X (2914.71)=43.72 RS CENTERING AND SHUTTERING : 445 RS TOTAL COST: 6052 RS CONTRACTORS PROFIT: 15% TOTAL COST=6960.29 RS
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 RS/CU.M
Todays BUZZ Word PROCEDURE REQUIRED FOR PURCHASING THE MATERIALS: 1. Find the specification required by the building. 2. contact all the suppliers in the market. 3. Give him a letter and quotation required for us. 4. tell them the time limit in which you required those material. 5. take the quotation from suppliers. 6. if you feel that it is ok then visit and select the material required. 7. check the quality of the material and compare the cost of material with others in the market. 8. finalise the cost of material. 9. give him the supply order. 10.after the delivery record taken in the inward register by refering the delivery chalan. 11. check the materials given by the suppliers an accordingly bills payments are done store into the rooms.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. RAJESH CHOUGALE 9822502199
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-04

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave,Mukt sainik vasahat,kolhapur
Students Name (Surname_First Name_Middle Name) Shinde Shraddha Tukaram
Exam No. 10901
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.30AM
Site Leaving Time (HH:MM am/pm) 5.30PM
Details of the Work Allotted to you today by the Site In-Charge Sir,had allotted us to observe the duties allotted to different labours and fill up their \'DAILY REPORT\'.This report chart includes:A)Work done, B)Labour strength, C)Department labour.We also came to know about different agencies which are included in construction wok.
Details of how you Planned & Executed the allotted work We proceeded to our work by visiting every floor one by one. On every floor we noted down the construction going on in a particular flat. likewise by seeing,we filled up the daily report.
Details of the Construction Procedure / Activity / Technology learned today Today,we learnt about wiring work placed within walls, placing of flooring tiles, plastering(final coat), plumbing work,concrete bedding on brick bat.
Details of the Construction Materials learned today Today we observed the placing of flooring tiles & skirting work,fixing of down take pipes from the duct.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such methodology adopted.
Details of the Construction / Engineering Drawings observed today Today we studied how to fill the daily report which includes description of work done today,different agencies involved, name of the agencies, labour strength, no.of male and female coolies.
Details of the Bye Laws referred today today no such clause referred from bye laws.
Details of any Managerial Skill learned today Sir was co-operative and gave knowledge about how the competitive exams help us in future.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR R.C.C SLAB: * Volume of concrete slab=10cumec * Concrete mix=1:2:4 * Volume of concrete mix=15.2cumec A) Materials: 1. Steel: Volume of steel required=1% of volume of concrete. =1/100x10=0.1cumec =0.1x7850 =785kg. 2. Cement=15.2/(1+2+4)=2.17cumec No. of bags=(2.17/0.034)=64bags. 3. Sand=2.17x2 =4.34cumec 4. Coarse aggregate=2.17x4=8.68cumec 5. Binding wire=20kg B) Cost of materials: 1. Cement =64x230=14720Rs. 2. Sand =4.34x850=3689Rs. 3. Aggregate =8.68x530=4600.4Rs. 4. Steel =785x35=27475Rs. 5. Binding wire =20x55=1100Rs. TOTAL =51584.4Rs. C) Cost of labour: 1. Head mason=2x250=500Rs. 2. Mason =4x170=680Rs. 3. Mazdoor =15x110=1650Rs. 4. Centering&=5% of cost of materials shuttering=(5/100/0x51584.4=2579.22Rs. 5. Carpenter =10x250=2500Rs. Nails =1000/- 6. Blacksmith=15x200=3000Rs. D) Total cost =Material+Labour =51584.4+11909.2 =63493.62Rs. E) Add 2% for water charges =0.02x63493.62 =1269.8724Rs. F)15% contractors profit =0.15x63493.62 =9524.043Rs. G) Grand total=D+E+F =74287.54Rs. H) Rate of 1 cumec=7428.754Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 7428.754Rs per cumec
Todays BUZZ Word PURCHASE DEPARTMENT: The purchase department contributes towards the company\'s profit.It gives all the data of the materials required for construction. The procedures that it follows are market survey, ensure proper delivery. DOCUMENTS REQUIRED FOR PURCHASE DEPT.: 1.Acceptance of requisitions 2.Issuing of purchase order 3.Pending requisitions 4.Site visits 5.Reporting
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Amol Muley
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: prasadkharat@ymail.com
Subject: 13531-04

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) prasad ramchandra kharat
Exam No. 13531
Working Day No. 04
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge arkemting of construction in CREDAI exhibition
Details of how you Planned & Executed the allotted work we approach to Rajesh construction stall in CREDAI exhibition. we understand all the details of selable area,carpet area,floor plans and elevation
Details of the Construction Procedure / Activity / Technology learned today marketing of construction is important part of construction buisiness. in this activity how react the builder with costmour reaction about the project is observed
Details of the Construction Materials learned today crusher sand =5000/- per dumper it used instead of natural sand , but it gives lower strength sand it has less cost than natural sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today fly cement ash mix block are used for wall construction
Details of the Construction / Engineering Drawings observed today Representation plan - For marketing process
Details of the Bye Laws referred today Balcony width - 1.2 m wide(min.)
Details of any Managerial Skill learned today good marketing skill of site engg.
RATE ANALYSIS (Detailed Stepwise Calculations required) 1 bag of cement=1.24 cu.feet for concreat (1:3:6) 1+0.52=1.52 cu.m ..... volume of concreat cement content =1.52/(1+3+6)=0.152 no of bags =4.35=5 sand=0.152*3=0.456*1060=483 Rs. Agg.=0.152*6=0.912 cu m*600=547 Rs. steel slab area 12*10=120 ft. 3*4=12sq.m 4/0.15=26.66=26 steel bars 8mm. bars =0.395*4=1.6,1.6*26=41 kg. 3/0.1=30 steel bars 10mm. 10mm.=0.617*3=1.85 1.85*30=56kg. total steel =97kg.=97*34=3295Rs. labour cost =1500/- Total =5500+3295+1500=10295/-
Result of RATE ANALYSIS ( Rs per Unit ) 10292/- per cu m
Todays BUZZ Word purches department- construction material required for project,purchase by this dept. sand=13000 per truck C.A.=5000 per dumper steel=34 per kg. cement=250 per bag.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: rameshkharat1987@gmail.com
Subject: 13532-04

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) kharat ramesh laxman
Exam No. 13532
Working Day No. 04
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge arkemting of construction in CREDAI exhibition
Details of how you Planned & Executed the allotted work we approach to Rajesh construction stall in CREDAI exhibition. we understand all the details of selable area,carpet area,floor plans and elevation
Details of the Construction Procedure / Activity / Technology learned today marketing of construction is important part of construction buisiness. in this activity how react the builder with costmour reaction about the project is observed
Details of the Construction Materials learned today crusher sand =5000/- per dumper it used instead of natural sand , but it gives lower strength sand it has less cost than natural sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today fly cement ash mix block are used for wall construction
Details of the Construction / Engineering Drawings observed today Representation plan - For marketing process
Details of the Bye Laws referred today Balcony width - 1.2 m wide(min.)
Details of any Managerial Skill learned today good marketing skill of site engg.
RATE ANALYSIS (Detailed Stepwise Calculations required) 1 bag of cement=1.24 cu.feet for concreat (1:3:6) 1+0.52=1.52 cu.m ..... volume of concreat cement content =1.52/(1+3+6)=0.152 no of bags =4.35=5 sand=0.152*3=0.456*1060=483 Rs. Agg.=0.152*6=0.912 cu m*600=547 Rs. steel slab area 12*10=120 ft. 3*4=12sq.m 4/0.15=26.66=26 steel bars 8mm. bars =0.395*4=1.6,1.6*26=41 kg. 3/0.1=30 steel bars 10mm. 10mm.=0.617*3=1.85 1.85*30=56kg. total steel =97kg.=97*34=3295Rs. labour cost =1500/- Total =5500+3295+1500=10295/-
Result of RATE ANALYSIS ( Rs per Unit ) 10292/- per cu m
Todays BUZZ Word purches department- construction material required for project,purchase by this dept. sand=13000 per truck C.A.=5000 per dumper steel=34 per kg. cement=250 per bag.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-04

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) patil vrishali vithal
Exam No. 13541
Working Day No. 04
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00
Details of the Work Allotted to you today by the Site In-Charge arkemting of construction in CREDAI exhibition
Details of how you Planned & Executed the allotted work we approach to Rajesh construction stall in CREDAI exhibition. we understand all the details of selable area,carpet area,floor plans and elevation
Details of the Construction Procedure / Activity / Technology learned today marketing of construction is important part of construction buisiness. in this activity how react the builder with costmour reaction about the project is observed
Details of the Construction Materials learned today crusher sand =5000/- per dumper it used instead of natural sand , but it gives lower strength sand it has less cost than natural sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today fly cement ash mix block are used for wall construction
Details of the Construction / Engineering Drawings observed today Representation plan - For marketing process
Details of the Bye Laws referred today Balcony width - 1.2 m wide(min.)
Details of any Managerial Skill learned today good marketing skill of site engg.
RATE ANALYSIS (Detailed Stepwise Calculations required) 1 bag of cement=1.24 cu.feet for concreat (1:3:6) 1+0.52=1.52 cu.m ..... volume of concreat cement content =1.52/(1+3+6)=0.152 no of bags =4.35=5 sand=0.152*3=0.456*1060=483 Rs. Agg.=0.152*6=0.912 cu m*600=547 Rs. steel slab area 12*10=120 ft. 3*4=12sq.m 4/0.15=26.66=26 steel bars 8mm. bars =0.395*4=1.6,1.6*26=41 kg. 3/0.1=30 steel bars 10mm. 10mm.=0.617*3=1.85 1.85*30=56kg. total steel =97kg.=97*34=3295Rs. labour cost =1500/- Total =5500+3295+1500=10295/-
Result of RATE ANALYSIS ( Rs per Unit ) 10292/- per cu m
Todays BUZZ Word purches department- construction material required for project,purchase by this dept. sand=13000 per truck C.A.=5000 per dumper steel=34 per kg. cement=250 per bag.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-04

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Fulari Sujata Shankar
Exam No. 13559
Working Day No. 04
Date (DD/MM/YYYY) 11.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge - To find the number of tiles required for a flat.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the flat room dimensions and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today - Procedure for laying tiles - Brick masonary
Details of the Construction Materials learned today \"Chicken Mesh\" which is mainly used in masonary work so that the mortar must be in contact with wall
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -About Rain Water Harvesting
Details of the Construction / Engineering Drawings observed today - The floor plans
Details of the Bye Laws referred today 1)Bathroom 2)Water Closet
Details of any Managerial Skill learned today - We studied how the weekly \'Labour Payement\' is done.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For Flooring\" Rooms Sizes Area 1) Hall 13\'*10\' 130sq.ft 2)Kitchen 10\'*12\' 120Sq.ft 3)Passage 9.4\'*3.4\' 27.28Sq.ft 4)Bed-1 10\'*12\' 120 Sq.ft 5)Bed-2 10\'*12\' 120 Sq.ft Total carpet Area = 517.28Sq.ft Size of Vitrified = 2\'*2\' tile No.of tiles = 130 no. required Cost of Tile= 40/- Total Cost of Tiles= 5200/- Labour cost= 850/- per brass Total labour cost= 4394.50/- Total amount=9594.50/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 20 per Sq.ft
Todays BUZZ Word Various materials required over the site are Cement,Aggregate,Sand etc. Suppose if we take an example of Cement its procedure is as follows -: 1)Material required 2)Unit 3)Quantity per unit truck 4)Lead time etc The document required for the this material at the site a Indent is prepared and given to the company, thus as per the charges the Payment is done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-04

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Swapnil Ashok
Exam No. 13529
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.15 pm
Details of the Work Allotted to you today by the Site In-Charge to check the door designing.
Details of how you Planned & Executed the allotted work we saw the length and width of the door and the attachment of formica over the plywood.
Details of the Construction Procedure / Activity / Technology learned today we observed today the machine mixing method.
Details of the Construction Materials learned today checking of the formwork for columns.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today plinth beam drawings.
Details of the Bye Laws referred today bye laws for staircases: according to bye laws, tread-250mm rise-150mm on site-tread-265mm rise-150mm
Details of any Managerial Skill learned today The columns shouls be checked after erection of the formwork.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for slab: proportion used:1:1.5:3 a) cement-(1.52/(1+1.5+3))=0.2763 cu.m no.of bags=(0.2763/0.035)=7.898 bags=8*260=Rs.2080 b) sand-0.2763*1.5=0.4144=(5000/2083)*0.4144=Rs.1766 c) aggregate-0.2763*3=0.8289=(1800/2.83)*0.8289=Rs.527 total cost of material=Rs.3340. e) for beam reinforcement-52kg/cu.m*Rs.36=Rs.1872 f) labour-mestri- Rs.250 mason-4 no.-Rs.1000 Boy or woman-Rs.140*3no.=Rs.420 bishti-Rs.80 g) water-1.5%=total cost*(1.5/100)=Rs.41.445 centering and shuttering cost.-lump sump.-Rs.60 carpenter=2*150=Rs.300 mazdoor=Rs.80 unskilled=Rs.150 Total-Rs.(3340+1872+250+1000+420+60+300+80+150+41.44)= Rs.7675 contractor profit=total cost*profit(15% profit) =Rs.7675*1.15 =Rs.8827
Result of RATE ANALYSIS ( Rs per Unit ) Rs.8827
Todays BUZZ Word purchase/procurement department: 1. the total material required is worked out. 2. a list of all the material required is prepared. 3. then the material is checked in the market for good quality and cost. 4. a list is given to the shop from where the material is to be taken. 5. advance payment is done. 6. then the shop owner gives the material according to the requirement. 7. the shop owner gives us one copy of the bill and keeps another with him. 8. then when the material is recieved, it is checked whether it it is according to the requirement. 9. then the ownr is paid asper the bill given.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-04

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Jadhav Nilam Jaywant
Exam No. 13528
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.15 pm
Details of the Work Allotted to you today by the Site In-Charge to check the door designing.
Details of how you Planned & Executed the allotted work we saw the length and width of the door and the attachment of formica over the plywood.
Details of the Construction Procedure / Activity / Technology learned today we observed today the machine mixing method.
Details of the Construction Materials learned today checking of the formwork for columns.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today plinth beam drawings.
Details of the Bye Laws referred today bye laws for staircases: according to bye laws, tread-250mm rise-150mm on site-tread-265mm rise-150mm
Details of any Managerial Skill learned today The columns shouls be checked after erection of the formwork.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for slab: proportion used:1:1.5:3 a) cement-(1.52/(1+1.5+3))=0.2763 cu.m no.of bags=(0.2763/0.035)=7.898 bags=8*260=Rs.2080 b) sand-0.2763*1.5=0.4144=(5000/2083)*0.4144=Rs.1766 c) aggregate-0.2763*3=0.8289=(1800/2.83)*0.8289=Rs.527 total cost of material=Rs.3340. e) for beam reinforcement-52kg/cu.m*Rs.36=Rs.1872 f) labour-mestri- Rs.250 mason-4 no.-Rs.1000 Boy or woman-Rs.140*3no.=Rs.420 bishti-Rs.80 g) water-1.5%=total cost*(1.5/100)=Rs.41.445 centering and shuttering cost.-lump sump.-Rs.60 carpenter=2*150=Rs.300 mazdoor=Rs.80 unskilled=Rs.150 Total-Rs.(3340+1872+250+1000+420+60+300+80+150+41.44)= Rs.7675 contractor profit=total cost*profit(15% profit) =Rs.7675*1.15 =Rs.8827
Result of RATE ANALYSIS ( Rs per Unit ) Rs.8827
Todays BUZZ Word purchase/procurement department: 1. the total material required is worked out. 2. a list of all the material required is prepared. 3. then the material is checked in the market for good quality and cost. 4. a list is given to the shop from where the material is to be taken. 5. advance payment is done. 6. then the shop owner gives the material according to the requirement. 7. the shop owner gives us one copy of the bill and keeps another with him. 8. then when the material is recieved, it is checked whether it it is according to the requirement. 9. then the ownr is paid asper the bill given.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-04

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) lad manoj sadashiv
Exam No. 13534
Working Day No. 04
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge arkemting of construction in CREDAI exhibition
Details of how you Planned & Executed the allotted work we approach to Rajesh construction stall in CREDAI exhibition. we understand all the details of selable area,carpet area,floor plans and elevation
Details of the Construction Procedure / Activity / Technology learned today marketing of construction is important part of construction buisiness. in this activity how react the builder with costmour reaction about the project is observed
Details of the Construction Materials learned today crusher sand =5000/- per dumper it used instead of natural sand , but it gives lower strength sand it has less cost than natural sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today fly cement ash mix block are used for wall construction
Details of the Construction / Engineering Drawings observed today Representation plan - For marketing process
Details of the Bye Laws referred today Balcony width - 1.2 m wide(min.)
Details of any Managerial Skill learned today good marketing skill of site engg.
RATE ANALYSIS (Detailed Stepwise Calculations required) 1 bag of cement=1.24 cu.feet for concreat (1:3:6) 1+0.52=1.52 cu.m ..... volume of concreat cement content =1.52/(1+3+6)=0.152 no of bags =4.35=5 sand=0.152*3=0.456*1060=483 Rs. Agg.=0.152*6=0.912 cu m*600=547 Rs. steel slab area 12*10=120 ft. 3*4=12sq.m 4/0.15=26.66=26 steel bars 8mm. bars =0.395*4=1.6,1.6*26=41 kg. 3/0.1=30 steel bars 10mm. 10mm.=0.617*3=1.85 1.85*30=56kg. total steel =97kg.=97*34=3295Rs. labour cost =1500/- Total =5500+3295+1500=10295/-
Result of RATE ANALYSIS ( Rs per Unit ) 10295/- per cu.m
Todays BUZZ Word purches department- construction material required for project,purchase by this dept. sand=13000 per truck C.A.=5000 per dumper steel=34 per kg. cement=250 per bag.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-04

Company Name Deshmukh Developers
Project Name & Site Address Deshmukh Developments,Pratibha Nagar,Kolhapur
Students Name (Surname_First Name_Middle Name) Birajdar Minaxi Renuk
Exam No. 13556
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge Today we are observe further electrification, 1) Every room wire connection get connect to each main control board 2) And each main control board get connect to main meter which is placed at ground level 3) In each room space is provided at entrance ,to collect all the wire ,get connected to main meter board
Details of how you Planned & Executed the allotted work 1) Firstly we are goes to that floor 2) To study the electrification drawing 3) To observe all points are placed in a perticular point are not comparing with plans
Details of the Construction Procedure / Activity / Technology learned today Constrction Procedure : 1) We are all groupmates study the Electrical drawing 2) Our quarries are asked to wire fitter 3) To measure height of switch board, foot light from bottom 4) Seperate space is provided at entrance of size 0.75*0.60M conveying all electrical wire to the ground level 5) Which are connected to main meter at basement 6) The Main Meter is connected to MSEB
Details of the Construction Materials learned today Construction Material : 1) 8 Module,4 Module switch board 2) PVC pipe for concealed wiring ,positive, negative, earthing wiring 3) Pana 4) Iron net which is placed on a concealed wiring to avoid cracking
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Environment Caring Technology : To use crushing sand in place of natural sand.Therefore to minimise environment pollution
Details of the Construction / Engineering Drawings observed today Construction Drawings : Today we are observe Electrification Drawing- 1) Provision of switch board 2) Provision of fan point 3) Provision of tube,bulb point 4) All above connection are get connect to switch board as shown in drawing
Details of the Bye Laws referred today Today we are observe bye laws for, 1) Height of ventilator 2) Height of Door 3) Above values compare with actual site work
Details of any Managerial Skill learned today The aggregate,sand, brick are placed in a suitable place to convey easy lifting of material .
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR SLAB : Proportion used 1:1.5:3 For dry volume= 52% Volume=1.52 1)cement =1.52/(1+1.5+3) =0.2763m3 2)number of bags =0.2763/0.035 =8 bags 3)sand =0.2763*1.5 =0.4144m3 =0.4144*742.04 =307.50m3 4)Aggregate=0.2763*3 =0.8289*636.04 =527.21 Rs TOTAL COST OF MATERIAL=2080+307.50+527.21=2914.71 Rs 5) BEAM & REINFORCEMENT = 52KG/CUM * 32 =1664 Rs 6) LABOUR COST = 985 Rs 7) WATER 1 1/2% =43.72 8) CENTERING & SHUTTERING, carpenter=1=150,mazdoor=1=80,unskilled labour=1=150 9) TOTAL = 445 Rs 10) TOTAL NET COST = 6052.43 11) Contractor profit = 6052.43 * 1.15 =6960.29 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 6960.29 Rs
Todays BUZZ Word TODAYS BUZZ WORD IS \"PURCHASE DEPARTMENT\" 1) Material Specication 2) Contact Supplier 3) Call Quoatation 4) Quantity 5) Time limit 5) Visit 6) Selection 7) Final Rate Quality 8) Supply Order 9) Inward Register 10) Delivery Chalan 11) Payment Detail
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Abhijit Bhosale Mob No.9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-04

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Dsouza Agnel Santan
Exam No. 13524
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.15 pm
Details of the Work Allotted to you today by the Site In-Charge to check the door designing.
Details of how you Planned & Executed the allotted work we saw the length and width of the door and the attachment of formica over the plywood.
Details of the Construction Procedure / Activity / Technology learned today we observed today the machine mixing method.
Details of the Construction Materials learned today checking of the formwork for columns.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today plinth beam drawings.
Details of the Bye Laws referred today bye laws for staircases: according to bye laws, tread-250mm rise-150mm on site-tread-265mm rise-150mm
Details of any Managerial Skill learned today The columns shouls be checked after erection of the formwork.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for slab: proportion used:1:1.5:3 a) cement-(1.52/(1+1.5+3))=0.2763 cu.m no.of bags=(0.2763/0.035)=7.898 bags=8*260=Rs.2080 b) sand-0.2763*1.5=0.4144=(5000/2083)*0.4144=Rs.1766 c) aggregate-0.2763*3=0.8289=(1800/2.83)*0.8289=Rs.527 total cost of material=Rs.3340. e) for beam reinforcement-52kg/cu.m*Rs.36=Rs.1872 f) labour-mestri- Rs.250 mason-4 no.-Rs.1000 Boy or woman-Rs.140*3no.=Rs.420 bishti-Rs.80 g) water-1.5%=total cost*(1.5/100)=Rs.41.445 centering and shuttering cost.-lump sump.-Rs.60 carpenter=2*150=Rs.300 mazdoor=Rs.80 unskilled=Rs.150 Total-Rs.(3340+1872+250+1000+420+60+300+80+150+41.44)= Rs.7675 contractor profit=total cost*profit(15% profit) =Rs.7675*1.15 =Rs.8827
Result of RATE ANALYSIS ( Rs per Unit ) Rs.8827
Todays BUZZ Word purchase/procurement department: 1. the total material required is worked out. 2. a list of all the material required is prepared. 3. then the material is checked in the market for good quality and cost. 4. a list is given to the shop from where the material is to be taken. 5. advance payment is done. 6. then the shop owner gives the material according to the requirement. 7. the shop owner gives us one copy of the bill and keeps another with him. 8. then when the material is recieved, it is checked whether it it is according to the requirement. 9. then the ownr is paid asper the bill given.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-04

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.15 pm
Details of the Work Allotted to you today by the Site In-Charge to check the door designing.
Details of how you Planned & Executed the allotted work we saw the length and width of the door and the attachment of formica over the plywood.
Details of the Construction Procedure / Activity / Technology learned today we observed today the machine mixing method.
Details of the Construction Materials learned today checking of the formwork for columns.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today plinth beam drawings.
Details of the Bye Laws referred today bye laws for staircases: according to bye laws, tread-250mm rise-150mm on site-tread-265mm rise-150mm
Details of any Managerial Skill learned today The columns shouls be checked after erection of the formwork.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for slab: proportion used:1:1.5:3 a) cement-(1.52/(1+1.5+3))=0.2763 cu.m no.of bags=(0.2763/0.035)=7.898 bags=8*260=Rs.2080 b) sand-0.2763*1.5=0.4144=(5000/2083)*0.4144=Rs.1766 c) aggregate-0.2763*3=0.8289=(1800/2.83)*0.8289=Rs.527 total cost of material=Rs.3340. e) for beam reinforcement-52kg/cu.m*Rs.36=Rs.1872 f) labour-mestri- Rs.250 mason-4 no.-Rs.1000 Boy or woman-Rs.140*3no.=Rs.420 bishti-Rs.80 g) water-1.5%=total cost*(1.5/100)=Rs.41.445 centering and shuttering cost.-lump sump.-Rs.60 carpenter=2*150=Rs.300 mazdoor=Rs.80 unskilled=Rs.150 Total-Rs.(3340+1872+250+1000+420+60+300+80+150+41.44)= Rs.7675 contractor profit=total cost*profit(15% profit) =Rs.7675*1.15 =Rs.8827
Result of RATE ANALYSIS ( Rs per Unit ) Rs.8827
Todays BUZZ Word purchase/procurement department: 1. the total material required is worked out. 2. a list of all the material required is prepared. 3. then the material is checked in the market for good quality and cost. 4. a list is given to the shop from where the material is to be taken. 5. advance payment is done. 6. then the shop owner gives the material according to the requirement. 7. the shop owner gives us one copy of the bill and keeps another with him. 8. then when the material is recieved, it is checked whether it it is according to the requirement. 9. then the ownr is paid asper the bill given.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-04

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 09.00 am
Site Leaving Time (HH:MM am/pm) 04.15 pm
Details of the Work Allotted to you today by the Site In-Charge to check the door designing.
Details of how you Planned & Executed the allotted work we saw the length and width of the door and the attachment of formica over the plywood.
Details of the Construction Procedure / Activity / Technology learned today we observed today the machine mixing method.
Details of the Construction Materials learned today checking of the formwork for columns.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none.
Details of the Construction / Engineering Drawings observed today plinth beam drawings.
Details of the Bye Laws referred today bye laws for staircases: according to bye laws, tread-250mm rise-150mm on site-tread-265mm rise-150mm
Details of any Managerial Skill learned today The columns shouls be checked after erection of the formwork.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for slab: proportion used:1:1.5:3 a) cement-(1.52/(1+1.5+3))=0.2763 cu.m no.of bags=(0.2763/0.035)=7.898 bags=8*260=Rs.2080 b) sand-0.2763*1.5=0.4144=(5000/2083)*0.4144=Rs.1766 c) aggregate-0.2763*3=0.8289=(1800/2.83)*0.8289=Rs.527 total cost of material=Rs.3340. e) for beam reinforcement-52kg/cu.m*Rs.36=Rs.1872 f) labour-mestri- Rs.250 mason-4 no.-Rs.1000 Boy or woman-Rs.140*3no.=Rs.420 bishti-Rs.80 g) water-1.5%=total cost*(1.5/100)=Rs.41.445 centering and shuttering cost.-lump sump.-Rs.60 carpenter=2*150=Rs.300 mazdoor=Rs.80 unskilled=Rs.150 Total-Rs.(3340+1872+250+1000+420+60+300+80+150+41.44)= Rs.7675 contractor profit=total cost*profit(15% profit) =Rs.7675*1.15 =Rs.8827
Result of RATE ANALYSIS ( Rs per Unit ) Rs.8827
Todays BUZZ Word purchase/procurement department: 1. the total material required is worked out. 2. a list of all the material required is prepared. 3. then the material is checked in the market for good quality and cost. 4. a list is given to the shop from where the material is to be taken. 5. advance payment is done. 6. then the shop owner gives the material according to the requirement. 7. the shop owner gives us one copy of the bill and keeps another with him. 8. then when the material is recieved, it is checked whether it it is according to the requirement. 9. then the ownr is paid asper the bill given.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-04

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) kolekar shyam suryakant
Exam No. 13533
Working Day No. 04
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge arkemting of construction in CREDAI exhibition
Details of how you Planned & Executed the allotted work we approach to Rajesh construction stall in CREDAI exhibition. we understand all the details of selable area,carpet area,floor plans and elevation
Details of the Construction Procedure / Activity / Technology learned today marketing of construction is important part of construction buisiness. in this activity how react the builder with costmour reaction about the project is observed
Details of the Construction Materials learned today crusher sand =5000/- per dumper it used instead of natural sand , but it gives lower strength sand it has less cost than natural sand
Details of Environment Caring Technology / Methodology / Procedure / Product learned today fly cement ash mix block are used for wall construction
Details of the Construction / Engineering Drawings observed today Representation plan - For marketing process
Details of the Bye Laws referred today Balcony width - 1.2 m wide(min.)
Details of any Managerial Skill learned today good marketing skill of site engg.
RATE ANALYSIS (Detailed Stepwise Calculations required) 1 bag of cement=1.24 cu.feet for concreat (1:3:6) 1+0.52=1.52 cu.m ..... volume of concreat cement content =1.52/(1+3+6)=0.152 no of bags =4.35=5 sand=0.152*3=0.456*1060=483 Rs. Agg.=0.152*6=0.912 cu m*600=547 Rs. steel slab area 12*10=120 ft. 3*4=12sq.m 4/0.15=26.66=26 steel bars 8mm. bars =0.395*4=1.6,1.6*26=41 kg. 3/0.1=30 steel bars 10mm. 10mm.=0.617*3=1.85 1.85*30=56kg. total steel =97kg.=97*34=3295Rs. labour cost =1500/- Total =5500+3295+1500=10295/-
Result of RATE ANALYSIS ( Rs per Unit ) 10295/- per cu.m
Todays BUZZ Word purches department- construction material required for project,purchase by this dept. sand=13000 per truck C.A.=5000 per dumper steel=34 per kg. cement=250 per bag.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-04

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bhoite Vishal Rajaram
Exam No. 13555
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:45pm
Details of the Work Allotted to you today by the Site In-Charge - To find the number of tiles required for a flat.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the flat room dimensions and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today - Procedure for laying tiles - Brick masonary.
Details of the Construction Materials learned today - \"Chicken Mesh\" which is mainly used in masonary work so that the mortar must be in contact with wall
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - About Rain Water Harvesting
Details of the Construction / Engineering Drawings observed today - The floor plans
Details of the Bye Laws referred today 1)Bathroom 2)Water Closet
Details of any Managerial Skill learned today - We studied how the weekly \'Labour Payement\' is done.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For Flooring\" Rooms Sizes Area 1) Hall 13\'*10\' 130sq.ft 2)Kitchen 10\'*12\' 120Sq.ft 3)Passage 9.4\'*3.4\' 27.28Sq.ft 4)Bed-1 10\'*12\' 120 Sq.ft 5)Bed-2 10\'*12\' 120 Sq.ft Total carpet Area = 517.28Sq.ft Size of Vitrified = 2\'*2\' tile No.of tiles = 130 no. required Cost of Tile= 40/- Total Cost of Tiles= 5200/- Labour cost= 850/- per brass Total labour cost= 4394.50/- Total amount=9594.50/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 20 per Sq.ft
Todays BUZZ Word Various materials required over the site are Cement,Aggregate,Sand etc. Suppose if we take an example of Cement its procedure is as follows -: 1)Material required 2)Unit 3)Quantity per unit truck 4)Lead time etc The document required for the this material at the site a Indent is prepared and given to the company, thus as per the charges the Payment is done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-04

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bauchakar Deepak Yuvraj
Exam No. 13554
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:45pm
Details of the Work Allotted to you today by the Site In-Charge - To find the number of tiles required for a flat.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the flat room dimensions and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today - Procedure for laying tiles - Brick masonary.
Details of the Construction Materials learned today - \"Chicken Mesh\" which is mainly used in masonary work so that the mortar must be in contact with wall
Details of Environment Caring Technology / Methodology / Procedure / Product learned today - About Rain Water Harvesting
Details of the Construction / Engineering Drawings observed today - The floor plans
Details of the Bye Laws referred today 1)Bathroom 2)Water Closet
Details of any Managerial Skill learned today - We studied how the weekly \'Labour Payement\' is done.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For Flooring\" Rooms Sizes Area 1) Hall 13\'*10\' 130sq.ft 2)Kitchen 10\'*12\' 120Sq.ft 3)Passage 9.4\'*3.4\' 27.28Sq.ft 4)Bed-1 10\'*12\' 120 Sq.ft 5)Bed-2 10\'*12\' 120 Sq.ft Total carpet Area = 517.28Sq.ft Size of Vitrified = 2\'*2\' tile No.of tiles = 130 no. required Cost of Tile= 40/- Total Cost of Tiles= 5200/- Labour cost= 850/- per brass Total labour cost= 4394.50/- Total amount=9594.50/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 20 per Sq.ft
Todays BUZZ Word Various materials required over the site are Cement,Aggregate,Sand etc. Suppose if we take an example of Cement its procedure is as follows -: 1)Material required 2)Unit 3)Quantity per unit truck 4)Lead time etc The document required for the this material at the site a Indent is prepared and given to the company, thus as per the charges the Payment is done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-04

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) patil sangram madhukar
Exam No. 13540
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge estimation of labour charges tiles fitting
Details of how you Planned & Executed the allotted work 1.to calculate area in sq.ft 2.to calculate length of skirting in ft. 3.deduction of length for door and opening in skirting 4.deduction area of window and doors for dado
Details of the Construction Procedure / Activity / Technology learned today 1.procedure for slab steel work -one way slab -two way slab 2.inishing of work 3.attachment of cera cladding
Details of the Construction Materials learned today 1.differend types op tiles -antisliding -decorative -kota -marble -vectrified -marbonite
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today to refer the plans of bunglow and section drawings for detail information of bunglows
Details of the Bye Laws referred today area provided for balcony within 10% of flooring
Details of any Managerial Skill learned today labour management payment account is clear
RATE ANALYSIS (Detailed Stepwise Calculations required) 1.cement - 23 bags x 250 = 5750 Rs 2.,aggregate -90cuft x 15 = 1350 Rs 3.sand -50cuft x 37 = 1850Rs 4.labour =400Rs 5.water curing = 70Rs total =9420Rs with c.p. =11304Rs for one cu.ft =113.Rs RCC slab for 5\" thk slab =47.47Rs 1.basic rate =48Rs 2.steel 1.25Kg x 37 = 46.25Rs 3.labour =15Rs total = 109.25Rs with cp =120Rs for per sq.ft
Result of RATE ANALYSIS ( Rs per Unit ) 120 RS
Todays BUZZ Word procedure 1.steel purchase-check as per RCC design 2.cement -load purchases for large scale quantity 3.sand -store as per land available 4.brick-store as per land available 5.aggregate-as per concrete requirment documents 1.purchase book -site name -incoming /outgoing -material description -vehicle no -time -remark -driver sing -reciver sing
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh Bhapat ph.no- 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-04

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Suyvanshi patil Pratiksinh Vilas
Exam No. 13549
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:45pm
Details of the Work Allotted to you today by the Site In-Charge - To find the number of tiles required for a flat.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the flat room dimensions and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today - Procedure for laying tiles - Brick masonary.
Details of the Construction Materials learned today - \"Chicken Mesh\" which is mainly used in masonary work so that the mortar must be in contact with wall
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -About Rain Water Harvesting
Details of the Construction / Engineering Drawings observed today - The floor plans
Details of the Bye Laws referred today 1)Bathroom 2)Water Closet
Details of any Managerial Skill learned today - We studied how the weekly \'Labour Payement\' is done.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For Flooring\" Rooms Sizes Area 1) Hall 13\'*10\' 130sq.ft 2)Kitchen 10\'*12\' 120Sq.ft 3)Passage 9.4\'*3.4\' 27.28Sq.ft 4)Bed-1 10\'*12\' 120 Sq.ft 5)Bed-2 10\'*12\' 120 Sq.ft Total carpet Area = 517.28Sq.ft Size of Vitrified = 2\'*2\' tile No.of tiles = 130 no. required Cost of Tile= 40/- Total Cost of Tiles= 5200/- Labour cost= 850/- per brass Total labour cost= 4394.50/- Total amount=9594.50/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 20 per Sq.ft
Todays BUZZ Word Various materials required over the site are Cement,Aggregate,Sand etc. Suppose if we take an example of Cement its procedure is as follows -: 1)Material required 2)Unit 3)Quantity per unit truck 4)Lead time etc The document required for the this material at the site a Indent is prepared and given to the company, thus as per the charges the Payment is done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: rajendrapawar54@gmail.com
Subject: 13542-04

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) pawar rajendra eknath
Exam No. 13542
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge estimation of labour charges tiles fitting
Details of how you Planned & Executed the allotted work 1.to calculate area in sq.ft 2.to calculate length of skirting in ft. 3.deduction of length for door and opening in skirting 4.deduction area of window and doors for dado
Details of the Construction Procedure / Activity / Technology learned today 1.procedure for slab steel work -one way slab -two way slab 2.inishing of work 3.attachment of cera cladding
Details of the Construction Materials learned today 1.differend types op tiles -antisliding -decorative -kota -marble -vectrified -marbonite
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today to refer the plans of bunglow and section drawings for detail information of bunglows
Details of the Bye Laws referred today area provided for balcony within 10% of flooring
Details of any Managerial Skill learned today labour management payment account is clear
RATE ANALYSIS (Detailed Stepwise Calculations required) 1.cement - 23 bags x 250 = 5750 Rs 2.,aggregate -90cuft x 15 = 1350 Rs 3.sand -50cuft x 37 = 1850Rs 4.labour =400Rs 5.water curing = 70Rs total =9420Rs with c.p. =11304Rs for one cu.ft =113.Rs RCC slab for 5\" thk slab =47.47Rs 1.basic rate =48Rs 2.steel 1.25Kg x 37 = 46.25Rs 3.labour =15Rs total = 109.25Rs with cp =120Rs for per sq.ft
Result of RATE ANALYSIS ( Rs per Unit ) 120 RS
Todays BUZZ Word procedure 1.steel purchase-check as per RCC design 2.cement -load purchases for large scale quantity 3.sand -store as per land available 4.brick-store as per land available 5.aggregate-as per concrete requirment documents 1.purchase book -site name -incoming /outgoing -material description -vehicle no -time -remark -driver sing -reciver sing
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh Bhapat ph.no- 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-04

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) patil sachin dhanaji
Exam No. 13539
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 8:50am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge estimation of labour charges tiles fitting
Details of how you Planned & Executed the allotted work 1.to calculate area in sq.ft 2.to calculate length of skirting in ft. 3.deduction of length for door and opening in skirting 4.deduction area of window and doors for dado
Details of the Construction Procedure / Activity / Technology learned today 1.procedure for slab steel work -one way slab -two way slab 2.inishing of work 3.attachment of cera cladding
Details of the Construction Materials learned today 1.differend types op tiles -antisliding -decorative -kota -marble -vectrified -marbonite
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today to refer the plans of bunglow and section drawings for detail information of bunglows
Details of the Bye Laws referred today area provided for balcony within 10% of flooring
Details of any Managerial Skill learned today labour management payment account is clear
RATE ANALYSIS (Detailed Stepwise Calculations required) 1.cement - 23 bags x 250 = 5750 Rs 2.,aggregate -90cuft x 15 = 1350 Rs 3.sand -50cuft x 37 = 1850Rs 4.labour =400Rs 5.water curing = 70Rs total =9420Rs with c.p. =11304Rs for one cu.ft =113.Rs RCC slab for 5\" thk slab =47.47Rs 1.basic rate =48Rs 2.steel 1.25Kg x 37 = 46.25Rs 3.labour =15Rs total = 109.25Rs with cp =120Rs for per sq.ft
Result of RATE ANALYSIS ( Rs per Unit ) 120 RS
Todays BUZZ Word procedure 1.steel purchase-check as per RCC design 2.cement -load purchases for large scale quantity 3.sand -store as per land available 4.brick-store as per land available 5.aggregate-as per concrete requirment documents 1.purchase book -site name -incoming /outgoing -material description -vehicle no -time -remark -driver sing -reciver sing
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh Bhapat ph.no- 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: nikitashinde15@gmail.com
Subject: 13547-04

Company Name S. N. Builders
Project Name & Site Address animesh nagar dadu chougle nagar
Students Name (Surname_First Name_Middle Name) shinde nikita eknath
Exam No. 13547
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 8:55am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge estimation of labour charges tiles fitting
Details of how you Planned & Executed the allotted work 1.to calculate area in sq.ft 2.to calculate length of skirting in ft. 3.deduction of length for door and opening in skirting 4.deduction area of window and doors for dado
Details of the Construction Procedure / Activity / Technology learned today 1.procedure for slab steel work -one way slab -two way slab 2.inishing of work 3.attachment of cera cladding
Details of the Construction Materials learned today 1.differend types op tiles -antisliding -decorative -kota -marble -vectrified -marbonite
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today to refer the plans of bunglow and section drawings for detail information of bunglows
Details of the Bye Laws referred today area provided for balcony within 10% of flooring
Details of any Managerial Skill learned today labour management payment account is clear
RATE ANALYSIS (Detailed Stepwise Calculations required) 1.cement - 23 bags x 250 = 5750 Rs 2.,aggregate -90cuft x 15 = 1350 Rs 3.sand -50cuft x 37 = 1850Rs 4.labour =400Rs 5.water curing = 70Rs total =9420Rs with c.p. =11304Rs for one cu.ft =113.Rs RCC slab for 5\" thk slab =47.47Rs 1.basic rate =48Rs 2.steel 1.25Kg x 37 = 46.25Rs 3.labour =15Rs total = 109.25Rs with cp =120Rs for per sq.ft
Result of RATE ANALYSIS ( Rs per Unit ) 120 RS
Todays BUZZ Word procedure 1.steel purchase-check as per RCC design 2.cement -load purchases for large scale quantity 3.sand -store as per land available 4.brick-store as per land available 5.aggregate-as per concrete requirment documents 1.purchase book -site name -incoming /outgoing -material description -vehicle no -time -remark -driver sing -reciver sing
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh Bhapat ph.no- 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: bsalamn75@yahoo.com
Subject: 10888-04

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage,r.s.no.950/1b,plotno-44,sardar prk devkar panand kolhapur.
Students Name (Surname_First Name_Middle Name) Baig Salman samad
Exam No. 10888
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for staircase, beam bottoms, placing of centring plates for stairs and check their levels, heights and dimensions of rise and tread as per drawings and details
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions of supporting beams of stairs, rise, tread, level of the stair with reference to details given to us.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the bottom of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing centring plates for staircase supported on steel props. ponding is done on the first floor for curing the slab.
Details of the Construction Materials learned today Non-teak wood battens of 3”size.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material is used on the site till now.
Details of the Construction / Engineering Drawings observed today Detail drawing of slabs and schedule of slabs
Details of the Bye Laws referred today Rise provided at the site is 0.150m,and tread is 0.30m. As per bye law it is rise it is 0.15m and tread is 0.25m.
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for R.C.C. slab S1“ 1.Quantity of concrete=2.1875cu.m. 2.Quantity of cement=0.32 cu.m. =10 bags 3.Quantity of sand=0.95 cu.m. 4.Quantity of coarse aggregate=1.92 cu.m. 5.Quantity of steel considering 10%as wastage Tor steel Fe-415 =96.51kg =0.0965 tonne 6. Quantity of binding wire for 10 cu.m. =15.7 kg So for 2.1875cu.m.= 3.43kg “Rate Analysis for R.C.C. beam using M20 concrete” (Considering local rates of material) (slab size-7.0*2.5*0.125) 1. Cost of cement=10*250=2500/-………..(250/- per bag) 2. Cost of sand=0.96*1600=1520/-…………(1600/- per cu.m.) 3. Cost of coarse aggregate=1.92*625=1200/-…………(625/- per cu.m.) 4. Cost of tor steel= 0.965*32,000=3100/-…………(32000/- per tonne.) 5.Cost of binding wire=30*3.43=100/-………… (30/- per kg) 6.Labour charges=2700/- 7. Total cost= 11120/- 8.10% profit of total cost for the contractor=1112/- 9. Total cost=12232/- 10. Rate per cu.m.= 5590/-
Result of RATE ANALYSIS ( Rs per Unit ) 5590/-
Todays BUZZ Word “Purchase/procurement department” Detailed specification of material required with its size, quantity, quality and expected rate is given to 4-5 distributors and quotations are called upon from them. The distributor providing the material as per specifications with economy is selected and order letter is given to him. Then as he supplies the material to the site bill is taken and challan of respective bill amount is given to the distributors one receipt of payment received is kept for record purpose.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? Yes
I carried & used following accessories on the site today Safety Helmet, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: vishalsapakal124@gmail.com
Subject: 10882-04

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage,r.s.no.950/1b,plotno-44,sardar prk devkar panand kolhapur.
Students Name (Surname_First Name_Middle Name) Sapkal Vishal Manohar
Exam No. 10882
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for staircase, beam bottoms, placing of centring plates for stairs and check their levels, heights and dimensions of rise and tread as per drawings and details
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions of supporting beams of stairs, rise, tread, level of the stair with reference to details given to us.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the bottom of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing centring plates for staircase supported on steel props. ponding is done on the first floor for curing the slab.
Details of the Construction Materials learned today Non-teak wood battens of 3”size.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material is used on the site till now.
Details of the Construction / Engineering Drawings observed today Detail drawing of slabs and schedule of slabs
Details of the Bye Laws referred today Rise provided at the site is 0.150m,and tread is 0.30m. As per bye law it is rise it is 0.15m and tread is 0.25m.
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for R.C.C. slab S1“ 1.Quantity of concrete=2.1875cu.m. 2.Quantity of cement=0.32 cu.m. =10 bags 3.Quantity of sand=0.95 cu.m. 4.Quantity of coarse aggregate=1.92 cu.m. 5.Quantity of steel considering 10%as wastage Tor steel Fe-415 =96.51kg =0.0965 tonne 6. Quantity of binding wire for 10 cu.m. =15.7 kg So for 2.1875cu.m.= 3.43kg “Rate Analysis for R.C.C. beam using M20 concrete” (Considering local rates of material) (slab size-7.0*2.5*0.125) 1. Cost of cement=10*250=2500/-………..(250/- per bag) 2. Cost of sand=0.96*1600=1520/-…………(1600/- per cu.m.) 3. Cost of coarse aggregate=1.92*625=1200/-…………(625/- per cu.m.) 4. Cost of tor steel= 0.965*32,000=3100/-…………(32000/- per tonne.) 5.Cost of binding wire=30*3.43=100/-………… (30/- per kg) 6.Labour charges=2700/- 7. Total cost= 11120/- 8.10% profit of total cost for the contractor=1112/- 9. Total cost=12232/- 10. Rate per cu.m.= 5590/-
Result of RATE ANALYSIS ( Rs per Unit ) 5590/-
Todays BUZZ Word “Purchase/procurement department” Detailed specification of material required with its size, quantity, quality and expected rate is given to 4-5 distributors and quotations are called upon from them. The distributor providing the material as per specifications with economy is selected and order letter is given to him. Then as he supplies the material to the site bill is taken and challan of respective bill amount is given to the distributors one receipt of payment received is kept for record purpose.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-04

Company Name Shree Developers & Builders
Project Name & Site Address Karan Heritage,plot no.44,sardar park,devkar panand,kolhapur.
Students Name (Surname_First Name_Middle Name) Babar Moreshwar Mahipati
Exam No. 10873
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for staircase, beam bottoms, placing of centring plates for stairs and check their levels, heights and dimensions of rise and tread as per drawings and details
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions of supporting beams of stairs, rise, tread, level of the stair with reference to details given to us.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the bottom of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing centring plates for staircase supported on steel props. ponding is done on the first floor for curing the slab.
Details of the Construction Materials learned today Non-teak wood battens of 3”size.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material is used on the site till now.
Details of the Construction / Engineering Drawings observed today Detail drawing of slabs and schedule of slabs
Details of the Bye Laws referred today Rise provided at the site is 0.150m,and tread is 0.30m. As per bye law it is rise it is 0.15m and tread is 0.25m.
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for R.C.C. slab S1“ 1.Quantity of concrete=2.1875cu.m. 2.Quantity of cement=0.32 cu.m. =10 bags 3.Quantity of sand=0.95 cu.m. 4.Quantity of coarse aggregate=1.92 cu.m. 5.Quantity of steel considering 10%as wastage Tor steel Fe-415 =96.51kg =0.0965 tonne 6. Quantity of binding wire for 10 cu.m. =15.7 kg So for 2.1875cu.m.= 3.43kg “Rate Analysis for R.C.C. beam using M20 concrete” (Considering local rates of material) (slab size-7.0*2.5*0.125) 1. Cost of cement=10*250=2500/-………..(250/- per bag) 2. Cost of sand=0.96*1600=1520/-…………(1600/- per cu.m.) 3. Cost of coarse aggregate=1.92*625=1200/-…………(625/- per cu.m.) 4. Cost of tor steel= 0.965*32,000=3100/-…………(32000/- per tonne.) 5.Cost of binding wire=30*3.43=100/-………… (30/- per kg) 6.Labour charges=2700/- 7. Total cost= 11120/- 8.10% profit of total cost for the contractor=1112/- 9. Total cost=12232/- 10. Rate per cu.m.= 5590/-
Result of RATE ANALYSIS ( Rs per Unit ) 5590/-
Todays BUZZ Word “Purchase/procurement department” Detailed specification of material required with its size, quantity, quality and expected rate is given to 4-5 distributors and quotations are called upon from them. The distributor providing the material as per specifications with economy is selected and order letter is given to him. Then as he supplies the material to the site bill is taken and challan of respective bill amount is given to the distributors one receipt of payment received is kept for record purpose.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: vishwajit.p09@gmail.com
Subject: 13543-04

Company Name S. N. Builders
Project Name & Site Address animesh nagar,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) paymal vishwajit shamarao
Exam No. 13543
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 8:50am
Site Leaving Time (HH:MM am/pm) 4:30pm
Details of the Work Allotted to you today by the Site In-Charge estimation of labour charges tiles fitting
Details of how you Planned & Executed the allotted work 1.to calculate area in sq.ft 2.to calculate length of skirting in ft. 3.deduction of length for door and opening in skirting 4.deduction area of window and doors for dado
Details of the Construction Procedure / Activity / Technology learned today 1.procedure for slab steel work -one way slab -two way slab 2.inishing of work 3.attachment of cera cladding
Details of the Construction Materials learned today 1.differend types op tiles -antisliding -decorative -kota -marble -vectrified -marbonite
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting
Details of the Construction / Engineering Drawings observed today to refer the plans of bunglow and section drawings for detail information of bunglows
Details of the Bye Laws referred today area provided for balcony within 10% of flooring
Details of any Managerial Skill learned today labour management payment account is clear
RATE ANALYSIS (Detailed Stepwise Calculations required) 1.cement - 23 bags x 250 = 5750 Rs 2.,aggregate -90cuft x 15 = 1350 Rs 3.sand -50cuft x 37 = 1850Rs 4.labour =400Rs 5.water curing = 70Rs total =9420Rs with c.p. =11304Rs for one cu.ft =113.Rs RCC slab for 5\" thk slab =47.47Rs 1.basic rate =48Rs 2.steel 1.25Kg x 37 = 46.25Rs 3.labour =15Rs total = 109.25Rs with cp =120Rs for per sq.ft
Result of RATE ANALYSIS ( Rs per Unit ) 120 RS
Todays BUZZ Word procedure 1.steel purchase-check as per RCC design 2.cement -load purchases for large scale quantity 3.sand -store as per land available 4.brick-store as per land available 5.aggregate-as per concrete requirment documents 1.purchase book -site name -incoming /outgoing -material description -vehicle no -time -remark -driver sing -reciver sing
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh Bhapat ph.no- 9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: v.g.ayyar@gmail.com
Subject: 13553-04

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Ayyar Vignesh Gopal
Exam No. 13553
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:45pm
Details of the Work Allotted to you today by the Site In-Charge - To find the number of tiles required for a flat.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the flat room dimensions and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today - Procedure for laying tiles - Brick masonary.
Details of the Construction Materials learned today - \"Chicken Mesh\" which is mainly used in masonary work so that the mortar must be in contact with wall
Details of Environment Caring Technology / Methodology / Procedure / Product learned today -About Rain Water Harvesting
Details of the Construction / Engineering Drawings observed today - The floor plans
Details of the Bye Laws referred today 1)Bathroom 2)Water Closet
Details of any Managerial Skill learned today - We studied how the weekly \'Labour Payement\' is done.
RATE ANALYSIS (Detailed Stepwise Calculations required) \"Rate Analysis For Flooring\" Rooms Sizes Area 1) Hall 13\'*10\' 130sq.ft 2)Kitchen 10\'*12\' 120Sq.ft 3)Passage 9.4\'*3.4\' 27.28Sq.ft 4)Bed-1 10\'*12\' 120 Sq.ft 5)Bed-2 10\'*12\' 120 Sq.ft Total carpet Area = 517.28Sq.ft Size of Vitrified = 2\'*2\' tile No.of tiles = 130 no. required Cost of Tile= 40/- Total Cost of Tiles= 5200/- Labour cost= 850/- per brass Total labour cost= 4394.50/- Total amount=9594.50/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 20 per Sq.ft
Todays BUZZ Word Various materials required over the site are Cement,Aggregate,Sand etc. Suppose if we take an example of Cement its procedure is as follows -: 1)Material required 2)Unit 3)Quantity per unit truck 4)Lead time etc The document required for the this material at the site a Indent is prepared and given to the company, thus as per the charges the Payment is done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: patilpratibha7070@yahoo.in
Subject: 10896-04

Company Name Shree Developers & Builders
Project Name & Site Address Karan Heritage,plot no.44,sardar park,devkar panand,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Pratibha Dilip
Exam No. 10896
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for staircase, beam bottoms, placing of centring plates for stairs and check their levels, heights and dimensions of rise and tread as per drawings and details
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions of supporting beams of stairs, rise, tread, level of the stair with reference to details given to us.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the bottom of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing centring plates for staircase supported on steel props. ponding is done on the first floor for curing the slab.
Details of the Construction Materials learned today Non-teak wood battens of 3”size.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material is used on the site till now.
Details of the Construction / Engineering Drawings observed today Detail drawing of slabs and schedule of slabs
Details of the Bye Laws referred today Rise provided at the site is 0.150m,and tread is 0.30m. As per bye law it is rise it is 0.15m and tread is 0.25m
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for R.C.C. slab S1“ 1.Quantity of concrete=2.1875cu.m. 2.Quantity of cement=0.32 cu.m. =10 bags 3.Quantity of sand=0.95 cu.m. 4.Quantity of coarse aggregate=1.92 cu.m. 5.Quantity of steel considering 10%as wastage Tor steel Fe-415 =96.51kg =0.0965 tonne 6. Quantity of binding wire for 10 cu.m. =15.7 kg So for 2.1875cu.m.= 3.43kg “Rate Analysis for R.C.C. beam using M20 concrete” (Considering local rates of material) (slab size-7.0*2.5*0.125) 1. Cost of cement=10*250=2500/-………..(250/- per bag) 2. Cost of sand=0.96*1600=1520/-…………(1600/- per cu.m.) 3. Cost of coarse aggregate=1.92*625=1200/-…………(625/- per cu.m.) 4. Cost of tor steel= 0.965*32,000=3100/-…………(32000/- per tonne.) 5.Cost of binding wire=30*3.43=100/-………… (30/- per kg) 6.Labour charges=2700/- 7. Total cost= 11120/- 8.10% profit of total cost for the contractor=1112/- 9. Total cost=12232/- 10. Rate per cu.m.= 5590/-
Result of RATE ANALYSIS ( Rs per Unit ) 5590/-
Todays BUZZ Word “Purchase/procurement department” Detailed specification of material required with its size, quantity, quality and expected rate is given to 4-5 distributors and quotations are called upon from them. The distributor providing the material as per specifications with economy is selected and order letter is given to him. Then as he supplies the material to the site bill is taken and challan of respective bill amount is given to the distributors one receipt of payment received is kept for record purpose.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-04

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage,r.s.no.950/1b,plotno-44,sardar prk devkar panand kolhapur.
Students Name (Surname_First Name_Middle Name) Yadav Hrishikesh Deepak
Exam No. 10885
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for staircase, beam bottoms, placing of centring plates for stairs and check their levels, heights and dimensions of rise and tread as per drawings and details
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions of supporting beams of stairs, rise, tread, level of the stair with reference to details given to us.
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the bottom of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs, placing centring plates for staircase supported on steel props. ponding is done on the first floor for curing the slab.
Details of the Construction Materials learned today Non-teak wood battens of 3”size.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material is used on the site till now.
Details of the Construction / Engineering Drawings observed today Detail drawing of slabs and schedule of slabs
Details of the Bye Laws referred today Rise provided at the site is 0.150m,and tread is 0.30m. As per bye law it is rise it is 0.15m and tread is 0.25m.
Details of any Managerial Skill learned today Allotting work to the specific number of labours as per required to do the respective work.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for R.C.C. slab S1“ 1.Quantity of concrete=2.1875cu.m. 2.Quantity of cement=0.32 cu.m. =10 bags 3.Quantity of sand=0.95 cu.m. 4.Quantity of coarse aggregate=1.92 cu.m. 5.Quantity of steel considering 10%as wastage Tor steel Fe-415 =96.51kg =0.0965 tonne 6. Quantity of binding wire for 10 cu.m. =15.7 kg So for 2.1875cu.m.= 3.43kg “Rate Analysis for R.C.C. beam using M20 concrete” (Considering local rates of material) (slab size-7.0*2.5*0.125) 1. Cost of cement=10*250=2500/-………..(250/- per bag) 2. Cost of sand=0.96*1600=1520/-…………(1600/- per cu.m.) 3. Cost of coarse aggregate=1.92*625=1200/-…………(625/- per cu.m.) 4. Cost of tor steel= 0.965*32,000=3100/-…………(32000/- per tonne.) 5.Cost of binding wire=30*3.43=100/-………… (30/- per kg) 6.Labour charges=2700/- 7. Total cost= 11120/- 8.10% profit of total cost for the contractor=1112/- 9. Total cost=12232/- 10. Rate per cu.m.= 5590/-
Result of RATE ANALYSIS ( Rs per Unit ) 5590/-
Todays BUZZ Word “Purchase/procurement department” Detailed specification of material required with its size, quantity, quality and expected rate is given to 4-5 distributors and quotations are called upon from them. The distributor providing the material as per specifications with economy is selected and order letter is given to him. Then as he supplies the material to the site bill is taken and challan of respective bill amount is given to the distributors one receipt of payment received is kept for record purpose.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-04

Company Name Chougule Sawant Developers
Project Name & Site Address SHREE SAMARTH NAGAR,New balinga
Students Name (Surname_First Name_Middle Name) Tirmare Pradnya Ashok
Exam No. 13572
Working Day No. 04
Date (DD/MM/YYYY) 11.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1.To observe footing concreting. 2.To observe column concreting. 3.Slab formwork
Details of how you Planned & Executed the allotted work First we had seen detailed drwaings of footings,columns, concreting spacifications. Then we had seen actual site work with site incharge
Details of the Construction Procedure / Activity / Technology learned today Footing and Column concreting ; 1. First formwork is placed according to sizes of member and checked. 2. Then M20 concrete is prepared. 3. Then concrete is poured into formwork. 4. Compaction is done by needle vibrator
Details of the Construction Materials learned today STEEL; Mahalaxmi steel bars of diameter 10,12,16mm of grade fe 415 and 500. steel is tested in lab and then it is used.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Instead of bamboo props the steel props are used which are more stronger than bamboo props also saves cutting ofnatural material like bamboo.
Details of the Construction / Engineering Drawings observed today Detailed drawings of footings and R.C.C. drawings of columns. R.C.C. drawiongs of footings.
Details of the Bye Laws referred today WIDTH OF STAIRCASE = 1 M RISE = 175 MM TREAD = 250 MM
Details of any Managerial Skill learned today To speak strictly and making good co-ordination with contractors to complete the work quickly and with good quality
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. SLAB ; RATE PER CU.M STEEL = 36 kg = 1260 Rs CEMENT = 310 kg = 1280 Rs SAND = 120 kg = 380 Rs METAL = 180 kg = 680 Rs LABOUR = 1550 Rs TOTAL = 5150 + 2% WASTAGE + 10% Contractors PROFIT = 5850.00 RS
Result of RATE ANALYSIS ( Rs per Unit ) 5850.00 Rs per cu.m
Todays BUZZ Word Procedure: 1) purchase order is submitted to shop. 2) then material is transported to the site. 3) after obtaining the material & bill. 4) it is checked & signed by storage incharge. 5) same bill is signed by accountant & bill is paided. Documents : Sale quotation - in this process tenders are obtained.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut. mo no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-04

Company Name Chougule Sawant Developers
Project Name & Site Address SHREE SAMARTH NAGAR,New balinga
Students Name (Surname_First Name_Middle Name) Katral Raju Maruti
Exam No. 13562
Working Day No. 04
Date (DD/MM/YYYY) 11.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1.To observe footing concreting. 2.To observe column concreting. 3.Slab formwork
Details of how you Planned & Executed the allotted work First we had seen detailed drwaings of footings,columns, concreting spacifications. Then we had seen actual site work with site incharge
Details of the Construction Procedure / Activity / Technology learned today Footing and Column concreting ; 1. First formwork is placed according to sizes of member and checked. 2. Then M20 concrete is prepared. 3. Then concrete is poured into formwork. 4. Compaction is done by needle vibrator
Details of the Construction Materials learned today STEEL; Mahalaxmi steel bars of diameter 10,12,16mm of grade fe 415 and 500. steel is tested in lab and then it is used.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Instead of bamboo props the steel props are used which are more stronger than bamboo props also saves cutting ofnatural material like bamboo.
Details of the Construction / Engineering Drawings observed today Detailed drawings of footings and R.C.C. drawings of columns. R.C.C. drawiongs of footings.
Details of the Bye Laws referred today WIDTH OF STAIRCASE = 1 M RISE = 175 MM TREAD = 250 MM
Details of any Managerial Skill learned today To speak strictly and making good co-ordination with contractors to complete the work quickly and with good quality
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. SLAB ; RATE PER CU.M STEEL = 36 kg = 1260 Rs CEMENT = 310 kg = 1280 Rs SAND = 120 kg = 380 Rs METAL = 180 kg = 680 Rs LABOUR = 1550 Rs TOTAL = 5150 + 2% WASTAGE + 10% Contractors PROFIT = 5850.00 RS
Result of RATE ANALYSIS ( Rs per Unit ) 5850.00 Rs per cu.m
Todays BUZZ Word Procedure: 1) purchase order is submitted to shop. 2) then material is transported to the site. 3) after obtaining the material & bill. 4) it is checked & signed by storage incharge. 5) same bill is signed by accountant & bill is paided. Documents : Sale quotation - in this process tenders are obtained.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut. mo no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: viju128@gmail.com
Subject: 3638-04

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.water tank rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) shinde vijay namdeo
Exam No. 3638
Working Day No. 04
Date (DD/MM/YYYY) 11/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge -General construction like brick work of plastering
Details of how you Planned & Executed the allotted work We observed the brickwork first the vertically levelled and then plastered the brick wall with trowel and upto the 0.5 inch thickness Brick they used by big size width that why the use the stretcher bond
Details of the Construction Procedure / Activity / Technology learned today Surface of the plaster should be properly vertically held with help of steffni and plumb bob.also they used the string(line dori) for brick work of each layer
Details of the Construction Materials learned today Mortor used for brick work and plaster
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater harvesting
Details of the Construction / Engineering Drawings observed today Construction drawing of column which is shown actuall position to taken load
Details of the Bye Laws referred today Parking area of residential building as per bye laws
Details of any Managerial Skill learned today No managmnt skill
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis of slab Concrete rate=3300rs/1m3 Labour cost=23rs/ft2 with 6inches thickness 1ft3 =23*2=46rs 1m3 =35.28*46=1623rs Total =3300+1623=4923rs Add 5% wastage =246 =5169 Add 75kg steel used=37*75=2625 =7794 Add 20% profit of contractor +1559 9353 rs/1m3 of slab
Result of RATE ANALYSIS ( Rs per Unit ) 9353 rs/1m3 of slab
Todays BUZZ Word “purchase department details out the procedure it follows & documents used for purchasing material” 1)acceptance of requisitions 2)issuing of purchasing order 3)pending requisitions 4)site visit 5)reporting
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883-04

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.water tank rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) Saurabh Arora
Exam No. 10883
Working Day No. 03
Date (DD/MM/YYYY) 11/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge -General construction like brick work of plastering
Details of how you Planned & Executed the allotted work We observed the brickwork first the vertically levelled and then plastered the brick wall with trowel and upto the 0.5 inch thickness Brick they used by big size width that why the use the stretcher bond
Details of the Construction Procedure / Activity / Technology learned today Surface of the plaster should be properly vertically held with help of steffni and plumb bob.also they used the string(line dori) for brick work of each layer
Details of the Construction Materials learned today Mortor used for brick work and plaster
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater harvesting
Details of the Construction / Engineering Drawings observed today Construction drawing of column which is shown actuall position to taken load
Details of the Bye Laws referred today Parking area of residential building as per bye laws
Details of any Managerial Skill learned today No managmnt skill
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis of slab Concrete rate=3300rs/1m3 Labour cost=23rs/ft2 with 6inches thickness 1ft3 =23*2=46rs 1m3 =35.28*46=1623rs Total =3300+1623=4923rs Add 5% wastage =246 =5169 Add 75kg steel used=37*75=2625 =7794 Add 20% profit of contractor +1559 9353 rs/1m3 of slab
Result of RATE ANALYSIS ( Rs per Unit ) 9353 rs/1m3 of slab
Todays BUZZ Word “purchase department details out the procedure it follows & documents used for purchasing material” 1)acceptance of requisitions 2)issuing of purchasing order 3)pending requisitions 4)site visit 5)reporting
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883-04

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.water tank rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) Saurabh Arora
Exam No. 10883
Working Day No. 03
Date (DD/MM/YYYY) 11/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge -General construction like brick work of plastering
Details of how you Planned & Executed the allotted work We observed the brickwork first the vertically levelled and then plastered the brick wall with trowel and upto the 0.5 inch thickness Brick they used by big size width that why the use the stretcher bond
Details of the Construction Procedure / Activity / Technology learned today Surface of the plaster should be properly vertically held with help of steffni and plumb bob.also they used the string(line dori) for brick work of each layer
Details of the Construction Materials learned today Mortor used for brick work and plaster
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater harvesting
Details of the Construction / Engineering Drawings observed today Construction drawing of column which is shown actuall position to taken load
Details of the Bye Laws referred today Parking area of residential building as per bye laws
Details of any Managerial Skill learned today No managmnt skill
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis of slab Concrete rate=3300rs/1m3 Labour cost=23rs/ft2 with 6inches thickness 1ft3 =23*2=46rs 1m3 =35.28*46=1623rs Total =3300+1623=4923rs Add 5% wastage =246 =5169 Add 75kg steel used=37*75=2625 =7794 Add 20% profit of contractor +1559 9353 rs/1m3 of slab
Result of RATE ANALYSIS ( Rs per Unit ) 9353 rs/1m3 of slab
Todays BUZZ Word “purchase department details out the procedure it follows & documents used for purchasing material” 1)acceptance of requisitions 2)issuing of purchasing order 3)pending requisitions 4)site visit 5)reporting
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883-04

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.water tank rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) Saurabh Arora
Exam No. 10883
Working Day No. 03
Date (DD/MM/YYYY) 11/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge -General construction like brick work of plastering
Details of how you Planned & Executed the allotted work We observed the brickwork first the vertically levelled and then plastered the brick wall with trowel and upto the 0.5 inch thickness Brick they used by big size width that why the use the stretcher bond
Details of the Construction Procedure / Activity / Technology learned today Surface of the plaster should be properly vertically held with help of steffni and plumb bob.also they used the string(line dori) for brick work of each layer
Details of the Construction Materials learned today Mortor used for brick work and plaster
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater harvesting
Details of the Construction / Engineering Drawings observed today Construction drawing of column which is shown actuall position to taken load
Details of the Bye Laws referred today Parking area of residential building as per bye laws
Details of any Managerial Skill learned today No managmnt skill
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis of slab Concrete rate=3300rs/1m3 Labour cost=23rs/ft2 with 6inches thickness 1ft3 =23*2=46rs 1m3 =35.28*46=1623rs Total =3300+1623=4923rs Add 5% wastage =246 =5169 Add 75kg steel used=37*75=2625 =7794 Add 20% profit of contractor +1559 9353 rs/1m3 of slab
Result of RATE ANALYSIS ( Rs per Unit ) 9353 rs/1m3 of slab
Todays BUZZ Word “purchase department details out the procedure it follows & documents used for purchasing material” 1)acceptance of requisitions 2)issuing of purchasing order 3)pending requisitions 4)site visit 5)reporting
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13561-04

Company Name Chougule Sawant Developers
Project Name & Site Address SHREE SAMARTH NAGAR,New balinga
Students Name (Surname_First Name_Middle Name) Jadhav Sardar Swaroop J.
Exam No. 13561
Working Day No. 04
Date (DD/MM/YYYY) 11.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1.To observe footing concreting. 2.To observe column concreting. 3.Slab formwork
Details of how you Planned & Executed the allotted work First we had seen detailed drwaings of footings,columns, concreting spacifications. Then we had seen actual site work with site incharge
Details of the Construction Procedure / Activity / Technology learned today Footing and Column concreting ; 1. First formwork is placed according to sizes of member and checked. 2. Then M20 concrete is prepared. 3. Then concrete is poured into formwork. 4. Compaction is done by needle vibrator
Details of the Construction Materials learned today STEEL; Mahalaxmi steel bars of diameter 10,12,16mm of grade fe 415 and 500. steel is tested in lab and then it is used.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Instead of bamboo props the steel props are used which are more stronger than bamboo props also saves cutting ofnatural material like bamboo.
Details of the Construction / Engineering Drawings observed today Detailed drawings of footings and R.C.C. drawings of columns. R.C.C. drawiongs of footings.
Details of the Bye Laws referred today WIDTH OF STAIRCASE = 1 M RISE = 175 MM TREAD = 250 MM
Details of any Managerial Skill learned today To speak strictly and making good co-ordination with contractors to complete the work quickly and with good quality
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. SLAB ; RATE PER CU.M STEEL = 36 kg = 1260 Rs CEMENT = 310 kg = 1280 Rs SAND = 120 kg = 380 Rs METAL = 180 kg = 680 Rs LABOUR = 1550 Rs TOTAL = 5150 + 2% WASTAGE + 10% Contractors PROFIT = 5850.00 RS
Result of RATE ANALYSIS ( Rs per Unit ) 5850.00 Rs per cu.m
Todays BUZZ Word Procedure: 1) purchase order is submitted to shop. 2) then material is transported to the site. 3) after obtaining the material & bill. 4) it is checked & signed by storage incharge. 5) same bill is signed by accountant & bill is paided. Documents : Sale quotation - in this process tenders are obtained.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut. mo no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-04

Company Name Chougule Sawant Developers
Project Name & Site Address SHREE SAMARTH NAGAR,New balinga
Students Name (Surname_First Name_Middle Name) JADE MADHAVRAO ANIL
Exam No. 13560
Working Day No. 04
Date (DD/MM/YYYY) 11.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1.To observe footing concreting. 2.To observe column concreting. 3.Slab formwork.
Details of how you Planned & Executed the allotted work First we had seen detailed drwaings of footings,columns, concreting spacifications. Then we had seen actual site work with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Footing and Column concreting ; 1. First formwork is placed according to sizes of member and checked. 2. Then M20 concrete is prepared. 3. Then concrete is poured into formwork. 4. Compaction is done by needle vibrator
Details of the Construction Materials learned today STEEL; Mahalaxmi steel bars of diameter 10,12,16mm of grade fe 415 and 500. steel is tested in lab and then it is used.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Instead of bamboo props the steel props are used which are more stronger than bamboo props also saves cutting ofnatural material like bamboo.
Details of the Construction / Engineering Drawings observed today Detailed drawings of footings and R.C.C. drawings of columns. R.C.C. drawiongs of footings.
Details of the Bye Laws referred today WIDTH OF STAIRCASE = 1 M RISE = 175 MM TREAD = 250 MM
Details of any Managerial Skill learned today To speak strictly and making good co-ordination with contractors to complete the work quickly and with good quality
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. SLAB ; RATE PER CU.M STEEL = 36 kg = 1260 Rs CEMENT = 310 kg = 1280 Rs SAND = 120 kg = 380 Rs METAL = 180 kg = 680 Rs LABOUR = 1550 Rs TOTAL = 5150 + 2% WASTAGE + 10% Contractors PROFIT = 5850.00 RS
Result of RATE ANALYSIS ( Rs per Unit ) 5850.00 Rs per cu.m
Todays BUZZ Word Procedure: 1) purchase order is submitted to shop. 2) then material is transported to the site. 3) after obtaining the material & bill. 4) it is checked & signed by storage incharge. 5) same bill is signed by accountant & bill is paided. Documents : Sale quotation - in this process tenders are obtained.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut. mo no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-04

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Redekar Shantanu Ravindra
Exam No. 13566
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about R.C.C.Water tank. * Size of water tank. = 5.50m x 3.00m x 1.80m * Capacity of storage water tank. = 30580 liters.
Details of how you Planned & Executed the allotted work * First we observe the actual plan of R.C.C. Water tank. * According to plan formwork of water tank arround has been placed by using main, distribution, stirrups bars etc. * Then concreting has been done properly in to the formwork.
Details of the Construction Procedure / Activity / Technology learned today * Large murum filling by POKHALAND (JCB) equipment. * Road roller for levelling and compaction of murum filling. * To understand the machine mixing concrete by using HALF MINI MIXER.
Details of the Construction Materials learned today * Murum filling side of beam. * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Superplasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of HALF MINI MIXER of concreting for reducing the lifting of heavy concrete on 2nd , 3rd floor and so on.
Details of the Construction / Engineering Drawings observed today * Layout plan of R.C.C. Water tank. * Firest we observe the which types of bars using in construction of R.C.C. Water tank. * Then calculate total number of main bar and distribution bar required for water tank. * To observed the minimum clear cover provided between two bars.
Details of the Bye Laws referred today * Water tank shall have minimum intrnal width of 75 cm. minimum depth of 1.0 m below the water level and a minimum liquid capacity of one meter cube. * Length of water tank shall be 2 to 4 times the width. * Water tank may be constructed of brick work , stone, masonary, concrete as approved by the commissioner. * Water tank shall be provided Vent pipe minimum 50.00 mm dia.
Details of any Managerial Skill learned today * Co-ordination between different agencies to ensure smooth working of the project is good. * Maintain quality of work and control wastage of material at the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) FOR 1 cu.m proportion 1:1.5:3 - SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 7.4 bags 250.00/- 1850.00/- b) aggregate 27.75 kg 18.00/- 500.00/- c) sand 13.88 kg 35.00/- 485.80/- d) steel 56.30 kg 40.00/- 2251.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) male mazdur 2 no. 200.00/- 400.00/- c) female mazdur 2 no. 160.00/- 320.00/- d) bhisti 1 no. 120.00/- 120.00/- 3 Centering and 3 no. 250.00/- 750.00/- shuttering 4 Others _ TOTAL 6976.80/- 5 Tools and plant @ 1.5% ----------------------- 105.00/- on total 6 Water charges @ 1.0% ----------------------- 70.00/- on total TOTAL(A) 7152.80/- 7 Overhead and profit @ 15% on tOtal A ----------------------- 1073.00/- -------------------------------------------------------------------------- TOTAL = 8225.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 8225.00/-
Todays BUZZ Word PURCHASE DEPARTMENT- * Before starting a new project, specification of all materials should be finalized and requisition accepted accordingly. * If the specification are altered the management or due to non-availability of the materials, the same should be inimitted to the purches department. * The functional procedure followed by the purches departmaent are- a) Acceptance of requisitions b) Issuing of purches order. c) Pending requisition d) Site visits e) Reporting DOCUMENT- * Receving Recipt * Purches recipt * Rechording book. * Requisition slip
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-04

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Mohare Vishal Bhalchandra
Exam No. 13564
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about R.C.C.Water tank. * Size of water tank. = 5.50m x 3.00m x 1.80m * Capacity of storage water tank. = 30580 liters.
Details of how you Planned & Executed the allotted work * First we observe the actual plan of R.C.C. Water tank. * According to plan formwork of water tank arround has been placed by using main, distribution, stirrups bars etc. * Then concreting has been done properly in to the formwork.
Details of the Construction Procedure / Activity / Technology learned today * Large murum filling by POKHALAND (JCB) equipment. * Road roller for levelling and compaction of murum filling. * To understand the machine mixing concrete by using HALF MINI MIXER.
Details of the Construction Materials learned today * Murum filling side of beam. * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Superplasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of HALF MINI MIXER of concreting for reducing the lifting of heavy concrete on 2nd , 3rd floor and so on.
Details of the Construction / Engineering Drawings observed today * Layout plan of R.C.C. Water tank. * Firest we observe the which types of bars using in construction of R.C.C. Water tank. * Then calculate total number of main bar and distribution bar required for water tank. * To observed the minimum clear cover provided between two bars.
Details of the Bye Laws referred today * Water tank shall have minimum intrnal width of 75 cm. minimum depth of 1.0 m below the water level and a minimum liquid capacity of one meter cube. * Length of water tank shall be 2 to 4 times the width. * Water tank may be constructed of brick work , stone, masonary, concrete as approved by the commissioner. * Water tank shall be provided Vent pipe minimum 50.00 mm dia.
Details of any Managerial Skill learned today * Co-ordination between different agencies to ensure smooth working of the project is good. * Maintain quality of work and control wastage of material at the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) FOR 1 cu.m proportion 1:1.5:3 - SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 7.4 bags 250.00/- 1850.00/- b) aggregate 27.75 kg 18.00/- 500.00/- c) sand 13.88 kg 35.00/- 485.80/- d) steel 56.30 kg 40.00/- 2251.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) male mazdur 2 no. 200.00/- 400.00/- c) female mazdur 2 no. 160.00/- 320.00/- d) bhisti 1 no. 120.00/- 120.00/- 3 Centering and 3 no. 250.00/- 750.00/- shuttering 4 Others _ TOTAL 6976.80/- 5 Tools and plant @ 1.5% ----------------------- 105.00/- on total 6 Water charges @ 1.0% ----------------------- 70.00/- on total TOTAL(A) 7152.80/- 7 Overhead and profit @ 15% on tOtal A ----------------------- 1073.00/- -------------------------------------------------------------------------- TOTAL = 8225.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 8225.00/-
Todays BUZZ Word PURCHASE DEPARTMENT- * Before starting a new project, specification of all materials should be finalized and requisition accepted accordingly. * If the specification are altered the management or due to non-availability of the materials, the same should be inimitted to the purches department. * The functional procedure followed by the purches departmaent are- a) Acceptance of requisitions b) Issuing of purches order. c) Pending requisition d) Site visits e) Reporting DOCUMENT- * Receving Recipt * Purches recipt * Rechording book. * Requisition slip
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-04

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE, R.S. 83 near new palace , new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Khade Amardeep Bhagwan
Exam No. 13563
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about R.C.C.Water tank. * Size of water tank. = 5.50m x 3.00m x 1.80m * Capacity of storage water tank. = 30580 liters.
Details of how you Planned & Executed the allotted work * First we observe the actual plan of R.C.C. Water tank. * According to plan formwork of water tank arround has been placed by using main, distribution, stirrups bars etc. * Then concreting has been done properly in to the formwork.
Details of the Construction Procedure / Activity / Technology learned today * Large murum filling by POKHALAND (JCB) equipment. * Road roller for levelling and compaction of murum filling. * To understand the machine mixing concrete by using HALF MINI MIXER.
Details of the Construction Materials learned today * Murum filling side of beam. * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Superplasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of HALF MINI MIXER of concreting for reducing the lifting of heavy concrete on 2nd , 3rd floor and so on.
Details of the Construction / Engineering Drawings observed today * Layout plan of R.C.C. Water tank. * Firest we observe the which types of bars using in construction of R.C.C. Water tank. * Then calculate total number of main bar and distribution bar required for water tank. * To observed the minimum clear cover provided between two bars.
Details of the Bye Laws referred today * Water tank shall have minimum intrnal width of 75 cm. minimum depth of 1.0 m below the water level and a minimum liquid capacity of one meter cube. * Length of water tank shall be 2 to 4 times the width. * Water tank may be constructed of brick work , stone, masonary, concrete as approved by the commissioner. * Water tank shall be provided Vent pipe minimum 50.00 mm dia.
Details of any Managerial Skill learned today * Co-ordination between different agencies to ensure smooth working of the project is good. * Maintain quality of work and control wastage of material at the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) FOR 1 cu.m proportion 1:1.5:3 - SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 7.4 bags 250.00/- 1850.00/- b) aggregate 27.75 kg 18.00/- 500.00/- c) sand 13.88 kg 35.00/- 485.80/- d) steel 56.30 kg 40.00/- 2251.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) male mazdur 2 no. 200.00/- 400.00/- c) female mazdur 2 no. 160.00/- 320.00/- d) bhisti 1 no. 120.00/- 120.00/- 3 Centering and 3 no. 250.00/- 750.00/- shuttering 4 Others _ TOTAL 6976.80/- 5 Tools and plant @ 1.5% ----------------------- 105.00/- on total 6 Water charges @ 1.0% ----------------------- 70.00/- on total TOTAL(A) 7152.80/- 7 Overhead and profit @ 15% on tOtal A ----------------------- 1073.00/- -------------------------------------------------------------------------- TOTAL = 8225.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 8225.00/-
Todays BUZZ Word PURCHASE DEPARTMENT- * Before starting a new project, specification of all materials should be finalized and requisition accepted accordingly. * If the specification are altered the management or due to non-availability of the materials, the same should be inimitted to the purches department. * The functional procedure followed by the purches departmaent are- a) Acceptance of requisitions b) Issuing of purches order. c) Pending requisition d) Site visits e) Reporting DOCUMENT- * Receving Recipt * Purches recipt * Rechording book. * Requisition slip
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558-04

Company Name Chougule Sawant Developers
Project Name & Site Address SHREE SAMERTH NAGAR,New balinga
Students Name (Surname_First Name_Middle Name) Chavan Shivprasad Chavan
Exam No. 13558
Working Day No. 04
Date (DD/MM/YYYY) 11.12.2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1.To observe footing concreting. 2.To observe column concreting. 3.Slab formwork.
Details of how you Planned & Executed the allotted work First we had seen detailed drwaings of footings,columns, concreting spacifications. Then we had seen actual site work with site incharge.
Details of the Construction Procedure / Activity / Technology learned today Footing and Column concreting ; 1. First formwork is placed according to sizes of member and checked. 2. Then M20 concrete is prepared. 3. Then concrete is poured into formwork. 4. Compaction is done by needle vibrator.
Details of the Construction Materials learned today STEEL; Mahalaxmi steel bars of diameter 10,12,16mm of grade fe 415 and 500. steel is tested in lab and then it is used.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Instead of bamboo props the steel props are used which are more stronger than bamboo props also saves cutting ofnatural material like bamboo.
Details of the Construction / Engineering Drawings observed today Detailed drawings of footings and R.C.C. drawings of columns. R.C.C. drawiongs of footings.
Details of the Bye Laws referred today WIDTH OF STAIRCASE = 1 M RISE = 175 MM TREAD = 250 MM
Details of any Managerial Skill learned today To speak strictly and making good co-ordination with contractors to complete the work quickly and with good quality.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. SLAB ; RATE PER CU.M STEEL = 36 kg = 1260 Rs CEMENT = 310 kg = 1280 Rs SAND = 120 kg = 380 Rs METAL = 180 kg = 680 Rs LABOUR = 1550 Rs TOTAL = 5150 + 2% WASTAGE + 10% Contractors PROFIT = 5850.00 RS
Result of RATE ANALYSIS ( Rs per Unit ) 5850.00 Rs per cu.m
Todays BUZZ Word PURCHASE / PROCUREMENT department ; Procedure ; 1. Purchacse order is obtained. 2. Then it is submitted to shop. 3. Then material is submitted to site. 4. At that time bill is obtained. 5. Order is checked and bill is signed by store incharge. 6. Same bill is signed by accountant and bill is paid. Documents ; 1. TENDER ; In this process sale quotations are obtained from different supplyers. 2. Purchase order. 3. Bill 4. Receipt
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut. mo no. 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: Rohit_patil361@rediffmail.com
Subject: 13565-04

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE , R.S. NO.83 near new palace, new nagal park, kolhapur
Students Name (Surname_First Name_Middle Name) Patil Rohit Ashok
Exam No. 13565
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about R.C.C.Water tank. * Size of water tank. = 5.50m x 3.00m x 1.80m * Capacity of storage water tank. = 30580 liters.
Details of how you Planned & Executed the allotted work * First we observe the actual plan of R.C.C. Water tank. * According to plan formwork of water tank arround has been placed by using main, distribution, stirrups bars etc. * Then concreting has been done properly in to the formwork.
Details of the Construction Procedure / Activity / Technology learned today * Large murum filling by POKHALAND (JCB) equipment. * Road roller for levelling and compaction of murum filling. * To understand the machine mixing concrete by using HALF MINI MIXER.
Details of the Construction Materials learned today * Murum filling side of beam. * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Superplasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of HALF MINI MIXER of concreting for reducing the lifting of heavy concrete on 2nd , 3rd floor and so on.
Details of the Construction / Engineering Drawings observed today * Layout plan of R.C.C. Water tank. * Firest we observe the which types of bars using in construction of R.C.C. Water tank. * Then calculate total number of main bar and distribution bar required for water tank. * To observed the minimum clear cover provided between two bars.
Details of the Bye Laws referred today * Water tank shall have minimum intrnal width of 75 cm. minimum depth of 1.0 m below the water level and a minimum liquid capacity of one meter cube. * Length of water tank shall be 2 to 4 times the width. * Water tank may be constructed of brick work , stone, masonary, concrete as approved by the commissioner. * Water tank shall be provided Vent pipe minimum 50.00 mm dia.
Details of any Managerial Skill learned today * Co-ordination between different agencies to ensure smooth working of the project is good. * Maintain quality of work and control wastage of material at the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) FOR 1 cu.m proportion 1:1.5:3 - SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 7.4 bags 250.00/- 1850.00/- b) aggregate 27.75 kg 18.00/- 500.00/- c) sand 13.88 kg 35.00/- 485.80/- d) steel 56.30 kg 40.00/- 2251.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) male mazdur 2 no. 200.00/- 400.00/- c) female mazdur 2 no. 160.00/- 320.00/- d) bhisti 1 no. 120.00/- 120.00/- 3 Centering and 3 no. 250.00/- 750.00/- shuttering 4 Others _ TOTAL 6976.80/- 5 Tools and plant @ 1.5% ----------------------- 105.00/- on total 6 Water charges @ 1.0% ----------------------- 70.00/- on total TOTAL(A) 7152.80/- 7 Overhead and profit @ 15% on tOtal A ----------------------- 1073.00/- -------------------------------------------------------------------------- TOTAL = 8225.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 8225.00/-
Todays BUZZ Word PURCHASE DEPARTMENT- * Before starting a new project, specification of all materials should be finalized and requisition accepted accordingly. * If the specification are altered the management or due to non-availability of the materials, the same should be inimitted to the purches department. * The functional procedure followed by the purches departmaent are- a) Acceptance of requisitions b) Issuing of purches order. c) Pending requisition d) Site visits e) Reporting DOCUMENT- * Receving Recipt * Purches recipt * Rechording book. * Requisition slip
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise mo. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/11/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-04

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S.NO 83 near new palace, new nagala park, kolhapur
Students Name (Surname_First Name_Middle Name) Bulbule Khandoba Ramchandra
Exam No. 13557
Working Day No. 04
Date (DD/MM/YYYY) 11/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 am
Site Leaving Time (HH:MM am/pm) 4.00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about R.C.C.Water tank. * Size of water tank. = 5.50m x 3.00m x 1.80m * Capacity of storage water tank. = 30580 liters.
Details of how you Planned & Executed the allotted work * First we observe the actual plan of R.C.C. Water tank. * According to plan formwork of water tank arround has been placed by using main, distribution, stirrups bars etc. * Then concreting has been done properly in to the formwork.
Details of the Construction Procedure / Activity / Technology learned today * Large murum filling by POKHALAND (JCB) equipment. * Road roller for levelling and compaction of murum filling. * To understand the machine mixing concrete by using HALF MINI MIXER.
Details of the Construction Materials learned today * Murum filling side of beam. * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Superplasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of HALF MINI MIXER of concreting for reducing the lifting of heavy concrete on 2nd , 3rd floor and so on.
Details of the Construction / Engineering Drawings observed today * Layout plan of R.C.C. Water tank. * Firest we observe the which types of bars using in construction of R.C.C. Water tank. * Then calculate total number of main bar and distribution bar required for water tank. * To observed the minimum clear cover provided between two bars.
Details of the Bye Laws referred today bylaw- * Water tank shall have minimum intrnal width of 75 cm. minimum depth of 1.0 m below the water level and a minimum liquid capacity of one meter cube. * Length of water tank shall be 2 to 4 times the width. * Water tank may be constructed of brick work , stone, masonary, concrete as approved by the commissioner. * Water tank shall be provided Vent pipe minimum 50.00 mm dia.
Details of any Managerial Skill learned today * Co-ordination between different agencies to ensure smooth working of the project is good. * Maintain quality of work and control wastage of material at the site.
RATE ANALYSIS (Detailed Stepwise Calculations required) FOR 1 cu.m proportion 1:1.5:3 - SR.NO. ITEM QUANTITY RATE PER AMOUNT 1 Material a) cement 7.4 bags 250.00/- 1850.00/- b) aggregate 27.75 kg 18.00/- 500.00/- c) sand 13.88 kg 35.00/- 485.80/- d) steel 56.30 kg 40.00/- 2251.00/- 2 Labourers a) head mason 1 no. 300.00/- 300.00/- b) male mazdur 2 no. 200.00/- 400.00/- c) female mazdur 2 no. 160.00/- 320.00/- d) bhisti 1 no. 120.00/- 120.00/- 3 Centering and 3 no. 250.00/- 750.00/- shuttering 4 Others _ TOTAL 6976.80/- 5 Tools and plant @ 1.5% ----------------------- 105.00/- on total 6 Water charges @ 1.0% ----------------------- 70.00/- on total TOTAL(A) 7152.80/- 7 Overhead and profit @ 15% on tOtal A ----------------------- 1073.00/- -------------------------------------------------------------------------- TOTAL = 8225.00/- Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 8225.00/-
Todays BUZZ Word PURCHASE DEPARTMENT- * Before starting a new project, specification of all materials should be finalized and requisition accepted accordingly. * If the specification are altered the management or due to non-availability of the materials, the same should be inimitted to the purches department. * The functional procedure followed by the purches departmaent are- a) Acceptance of requisitions b) Issuing of purches order. c) Pending requisition d) Site visits e) Reporting DOCUMENT- * Receving Recipt * Purches recipt * Rechording book. * Requisition slip
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vikrant Pise Mob.no. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: rjmasterstroke@gmail.com
Subject: 10875-03

Company Name V. S. Joshi & Associates
Project Name & Site Address VVishwa Enclave - V.S,Joshi Associates,
Students Name (Surname_First Name_Middle Name) janbandhu rakshit janbandhu
Exam No. 10875
Working Day No. 03
Date (DD/MM/YYYY) 10/12/10
Site Reporting Time (HH:MM am/pm) 9.30AM
Site Leaving Time (HH:MM am/pm) 5.30PM
Details of the Work Allotted to you today by the Site In-Charge *Study Of Under Construction Flats 1. Electrification Work. 2. Plumbing Work. 3. Tilling Work. 4. Plastering Work *To Study Bore Well Excavation.
Details of how you Planned & Executed the allotted work *Study Of A Under Construction Flats* - We bifercated ourself into two groups - The first group observed the work being done on first floor. - The other group observed the second floor. - Accordingly Seven Floors were worked out. - The details of each work was then explained by Mr. Mulay. *To Study Excavation Of Bore Well* - We Studied various components of the truck mounted with hydraulic system of bore well. - Then accordingly Observed the excavation work. Details of the Construction Procedure / Activity / Technology learned today: *Excavation Of Bore Well: - First of all the site where the bore was to be dug was cleaned of. - Then the 6\" bore well mounted truck was brought near the site. - Then the installation of bore well was done. - The pipe rods were then attached to the metal drilling rod (with wedges) - Drilling was done - It was operated by a Hydraullic system fitted behind the truck. - Then accordingly excavation by drilling
Details of the Construction Procedure / Activity / Technology learned today *Excavation Of Bore Well: - First of all the site where the bore was to be dug was cleaned of. - Then the 6\" bore well mounted truck was brought near the site. - Then the installation of bore well was done. - The pipe rods were then attached to the metal drilling rod (with wedges) - Drilling was done - It was operated by a Hydraullic system fitted behind the truck. - Then accordingly excavation by drilling was carried out.
Details of the Construction Materials learned today - 3.5\' Metal drilling Rod - PVC Casing for bore well( 180mm dia, 6 kg/sq.cm )
Details of Environment Caring Technology / Methodology / Procedure / Product learned today NO
Details of the Construction / Engineering Drawings observed today Plans for each floor for \'C- Building\'
Details of the Bye Laws referred today NO
Details of any Managerial Skill learned today - Completing the work in time. - Way to execute the work.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for RCC Beam: 1. Volume Of Beam = 10 cu.m 2. Concrete Mix Proportion = 1:1.5:3 3. Volume of Dry Concrete Mix = 15.2 cu.m A. Materials: 1. Quantity Of cement = 2.763 cu.m 2. No Of bags Of cement = 81.28 3. Sand = 4.144 cu.m 4. C.A. = 8.289 cu.m 5. Steel = 1570 kg 6. Binding wire = 15.7 kg B. Cost of Material: 1. Cement = 81.28 x 230 = 18694.4/- 2. Sand = 4.144 x 850 = 3522.4/- 3. Aggregate = 8.289 x 530 = 4393.17/- 4. Steel = 1570 x 34 = 53380/- 5. Binding Wire = 15.7 x 55 = 863.5/- 6. Total = 80853.47/- C. Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 3 x 170 = 510/- 3. Mazdoor = 10 x 110 = 1100/- 4. Centering & Shuttering = 5% x 80853.57 = 4042.68/- 5. Carpenter = 10 x 250 = 2500/- Nails = 500/- 6. Blacksmith = 15 x 200 = 3000/- 7. Total Cost = 8902.68/- D. TOTAL COST = B+C = 89756.15/- E. Add 1.5% Water charges = 1346.34 F. Add 10% Contractors Profit = 8975.6 G. GRAND TOTAL =100078.09 H. RATE FOR 1 CUM = 10007.809
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 10007.809
Todays BUZZ Word CONTRACTORS: A general contractor is responsible for the day-to-day oversight of the construction site, and management of vendors and trades. In addition, keep communication between the general contractor and the involved parties open and clear through out the course of project. TYPES OF CONTRACTORS WITH THEIR SCOPE OF WORK: 1. Centering Contractor - Line out work as per RCC drg Building work. 2. Excavation Contractor - Excavation Footings Pits (Underground Safety Drainage). 3. Masonary Contractor - AS per Working Drg. & Internal & External Plaster. 4. Plumbing Contractor - Internal External Plumbing layout, Drainage. 5. Electrical Contractor - Internal External electrification. 6. Carpentry Contractor - Doors, Windows Etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. Amol A. Mule. (9922507376
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13561-03

Company Name Chougule Sawant Developers
Project Name & Site Address Shree Samarth Nagar, Balinge
Students Name (Surname_First Name_Middle Name) Jadhav Sardar Swaroop J.
Exam No. 13561
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1.Observation of cube test reports. 2.Observation of plinth beam shuttering. 3.Observation of bar bending & schedule. 4.Observation of centering of column & footing.
Details of how you Planned & Executed the allotted work 1.Before lunch we observe cube test report & centering of column & footing. 2.After lunch we observe bar bending & plinth beam shuttering.
Details of the Construction Procedure / Activity / Technology learned today They introuced Internet Wi-Fi system in the project.
Details of the Construction Materials learned today Alageproof liquid used for waterproofing.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today They introuced tree plantation in open space.
Details of the Construction / Engineering Drawings observed today Centerline drawing of column & plinth beam of apartment.
Details of the Bye Laws referred today Room sizes are so designed as per national building code as The minimum area required For- 1.Living room = 150.00sq.m. 2.Bed room = 9.50sq.m. 3.kitchen cum dining = 9.5sq.m. 4.Bathroom = 1.8sq.m. 5.Water closet = 1.1sq.m. 6.Toilet = 2.8sq.m.
Details of any Managerial Skill learned today We learned the whole work diveded in small parts & given to worker teams so work will be done fast.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for BEAM per cub.meter Material Quantity(kg) Rate(Rs) 1.Cement 310 1280 2.Sand 120 380 3.Aggregate 180 680 4.Steel 55 1925 Total = 5815.00 Add 2% wastage + Labour charges 1550.00 Grand Total = 6000.00Rs/cubic.meter
Result of RATE ANALYSIS ( Rs per Unit ) 6000.00Rs/cubic.meter
Todays BUZZ Word Todays buzz is about \"Contractors\" Different Types 1.R.C.C. contractor - For Reinforcement cement concrete work. 2.Labour contractor - a.R.C.C. b.Masonry c.Plastering d.Excavation 3.Tiling contractor - For do all tiling work of projest[like spartex tiling,paving blocks,dado,etc.] 4.Plumbing contractor - For all plumbing work of project[like water taps,sanitary work] 5.Electrical contractor - For all electrification work[like various electric points,transformer] 6.Carpenter contractor - For all wooden work[like doors,windows,frames,] 7.Water proofing contractor - For water proofing of baths ,toilets,watertanks,slabs,terrace & also waterproofing during plastering. 8.Painting contractor -For painting work. 9.Land scape - For secure basements, foundations against landscape. 10.Road contractor - For constructing road to site & internal roads of project.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Swapnil Raut. Mo.No.8805173173 Mr.Suhas Jadhav Mo.No.8007415015
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-03

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Tambe Trusha Sitaram
Exam No. 10902
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of steel reinforcement of beam. .
Details of how you Planned & Executed the allotted work First we took the structural drawing &checked all the spacing,cover,length,stirrups etc.as per the drawing. .
Details of the Construction Procedure / Activity / Technology learned today Today we learned the process of grouting.first drilling is done the affected area.then the pipe is fixed in it.and then pressure is applied through it which fills the voids from concrete and stops the leakage from it. .
Details of the Construction Materials learned today Crush sand is used instead of river sand. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Crush sand is used instead of river sand. .
Details of the Construction / Engineering Drawings observed today Today we observed the structural drawing that is of steel reinforcement.in it we observed the spacing,length,cover etc.and also how the notation or symbols of different types are given. .
Details of the Bye Laws referred today Balcony or balconies of max.width of 1.2m. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) cement= 6.90bags @Rs.260/bag Rs.1794/- sand = 0.6cu.m @Rs.1155/- Rs.693/- metal = 0.90cu.m @Rs.304/- Rs.273/- steel = 180kg @Rs.35/kg Rs.6300/- shuttering material@Rs.225/sq.m Rs.1800/- Conc. pouring @Rs.350/cu.m Rs.350/- Total= Rs.11210/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.11210/-
Todays BUZZ Word 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-03

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Shinde Shraddha Tukaram
Exam No. 10901
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge *Study Of Under Construction Flats 1. Electrification Work. 2. Plumbing Work. 3. Tilling Work. 4. Plastering Work *To Study Bore Well Excavation.
Details of how you Planned & Executed the allotted work *Study Of A Under Construction Flats* - We bifercated ourself into two groups - The first group observed the work being done on first floor. - The other group observed the second floor. - Accordingly Seven Floors were worked out. - The details of each work was then explained by Mr. Mulay. *To Study Excavation Of Bore Well* - We Studied various components of the truck mounted with hydraulic system of bore well. - Then accordingly Observed the excavation work.
Details of the Construction Procedure / Activity / Technology learned today *Excavation Of Bore Well: - First of all the site where the bore was to be dug was cleaned of. - Then the 6\" bore well mounted truck was brought near the site. - Then the installation of bore well was done. - The pipe rods were then attached to the metal drilling rod (with wedges) - Drilling was done - It was operated by a Hydraullic system fitted behind the truck. - Then accordingly excavation by drilling was carried out.
Details of the Construction Materials learned today - 3.5\' Metal drilling Rod - PVC Casing for bore well( 180mm dia, 6 kg/sq.cm )
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No
Details of the Construction / Engineering Drawings observed today Plans for each floor for \'C- Building\'
Details of the Bye Laws referred today No
Details of any Managerial Skill learned today - Completing the work in time. - Way to execute the work.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for RCC Beam: 1. Volume Of Beam = 10 cu.m 2. Concrete Mix Proportion = 1:1.5:3 3. Volume of Dry Concrete Mix = 15.2 cu.m A. Materials: 1. Quantity Of cement = 2.763 cu.m 2. No Of bags Of cement = 81.28 3. Sand = 4.144 cu.m 4. C.A. = 8.289 cu.m 5. Steel = 1570 kg 6. Binding wire = 15.7 kg B. Cost of Material: 1. Cement = 81.28 x 230 = 18694.4/- 2. Sand = 4.144 x 850 = 3522.4/- 3. Aggregate = 8.289 x 530 = 4393.17/- 4. Steel = 1570 x 34 = 53380/- 5. Binding Wire = 15.7 x 55 = 863.5/- 6. Total = 80853.47/- C. Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 3 x 170 = 510/- 3. Mazdoor = 10 x 110 = 1100/- 4. Centering & Shuttering = 5% x 80853.57 = 4042.68/- 5. Carpenter = 10 x 250 = 2500/- Nails = 500/- 6. Blacksmith = 15 x 200 = 3000/- 7. Total Cost = 8902.68/- D. TOTAL COST = B+C = 89756.15/- E. Add 1.5% Water charges = 1346.34 F. Add 10% Contractors Profit = 8975.6 G. GRAND TOTAL =100078.09 H. RATE FOR 1 CUM = 10007.809
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 10007.809
Todays BUZZ Word CONTRACTORS: A general contractor is responsible for the day-to-day oversight of the construction site, and management of vendors and trades. In addition, keep communication between the general contractor and the involved parties open and clear through out the course of project. TYPES OF CONTRACTORS WITH THEIR SCOPE OF WORK: 1. Centering Contractor - Line out work as per RCC drg Building work. 2. Excavation Contractor - Excavation Footings Pits (Underground Safety Drainage). 3. Masonary Contractor - AS per Working Drg. & Internal & External Plaster. 4. Plumbing Contractor - Internal External Plumbing layout, Drainage. 5. Electrical Contractor - Internal External electrification. 6. Carpentry Contractor - Doors, Windows Etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mule. (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10893-03

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Kamble Ankit V.
Exam No. 10893
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge *Study Of Under Construction Flats 1. Electrification Work. 2. Plumbing Work. 3. Tilling Work. 4. Plastering Work *To Study Bore Well Excavation.
Details of how you Planned & Executed the allotted work *Study Of A Under Construction Flats* - We bifercated ourself into two groups - The first group observed the work being done on first floor. - The other group observed the second floor. - Accordingly Seven Floors were worked out. - The details of each work was then explained by Mr. Mulay. *To Study Excavation Of Bore Well* - We Studied various components of the truck mounted with hydraulic system of bore well. - Then accordingly Observed the excavation work.
Details of the Construction Procedure / Activity / Technology learned today *Excavation Of Bore Well: - First of all the site where the bore was to be dug was cleaned of. - Then the 6\" bore well mounted truck was brought near the site. - Then the installation of bore well was done. - The pipe rods were then attached to the metal drilling rod (with wedges) - Drilling was done - It was operated by a Hydraullic system fitted behind the truck. - Then accordingly excavation by drilling was carried out.
Details of the Construction Materials learned today - 3.5\' Metal drilling Rod - PVC Casing for bore well( 180mm dia, 6 kg/sq.cm )
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No
Details of the Construction / Engineering Drawings observed today Plans for each floor for \'C- Building\'
Details of the Bye Laws referred today No
Details of any Managerial Skill learned today - Completing the work in time. - Way to execute the work.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for RCC Beam: 1. Volume Of Beam = 10 cu.m 2. Concrete Mix Proportion = 1:1.5:3 3. Volume of Dry Concrete Mix = 15.2 cu.m A. Materials: 1. Quantity Of cement = 2.763 cu.m 2. No Of bags Of cement = 81.28 3. Sand = 4.144 cu.m 4. C.A. = 8.289 cu.m 5. Steel = 1570 kg 6. Binding wire = 15.7 kg B. Cost of Material: 1. Cement = 81.28 x 230 = 18694.4/- 2. Sand = 4.144 x 850 = 3522.4/- 3. Aggregate = 8.289 x 530 = 4393.17/- 4. Steel = 1570 x 34 = 53380/- 5. Binding Wire = 15.7 x 55 = 863.5/- 6. Total = 80853.47/- C. Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 3 x 170 = 510/- 3. Mazdoor = 10 x 110 = 1100/- 4. Centering & Shuttering = 5% x 80853.57 = 4042.68/- 5. Carpenter = 10 x 250 = 2500/- Nails = 500/- 6. Blacksmith = 15 x 200 = 3000/- 7. Total Cost = 8902.68/- D. TOTAL COST = B+C = 89756.15/- E. Add 1.5% Water charges = 1346.34 F. Add 10% Contractors Profit = 8975.6 G. GRAND TOTAL =100078.09 H. RATE FOR 1 CUM = 10007.809
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 10007.809
Todays BUZZ Word CONTRACTORS: A general contractor is responsible for the day-to-day oversight of the construction site, and management of vendors and trades. In addition, keep communication between the general contractor and the involved parties open and clear through out the course of project. TYPES OF CONTRACTORS WITH THEIR SCOPE OF WORK: 1. Centering Contractor - Line out work as per RCC drg Building work. 2. Excavation Contractor - Excavation Footings Pits (Underground Safety Drainage). 3. Masonary Contractor - AS per Working Drg. & Internal & External Plaster. 4. Plumbing Contractor - Internal External Plumbing layout, Drainage. 5. Electrical Contractor - Internal External electrification. 6. Carpentry Contractor - Doors, Windows Etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mule. (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-03

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Jape Vishwajeet Ramesh
Exam No. 10892
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge *Study Of Under Construction Flats 1. Electrification Work. 2. Plumbing Work. 3. Tilling Work. 4. Plastering Work *To Study Bore Well Excavation.
Details of how you Planned & Executed the allotted work *Study Of A Under Construction Flats* - We bifercated ourself into two groups - The first group observed the work being done on first floor. - The other group observed the second floor. - Accordingly Seven Floors were worked out. - The details of each work was then explained by Mr. Mulay. *To Study Excavation Of Bore Well* - We Studied various components of the truck mounted with hydraulic system of bore well. - Then accordingly Observed the excavation work.
Details of the Construction Procedure / Activity / Technology learned today *Excavation Of Bore Well: - First of all the site where the bore was to be dug was cleaned of. - Then the 6\" bore well mounted truck was brought near the site. - Then the installation of bore well was done. - The pipe rods were then attached to the metal drilling rod (with wedges) - Drilling was done - It was operated by a Hydraullic system fitted behind the truck. - Then accordingly excavation by drilling was carried out.
Details of the Construction Materials learned today - 3.5\' Metal drilling Rod - PVC Casing for bore well( 180mm dia, 6 kg/sq.cm )
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No
Details of the Construction / Engineering Drawings observed today Plans for each floor for \'C- Building\'
Details of the Bye Laws referred today No
Details of any Managerial Skill learned today - Completing the work in time. - Way to execute the work.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for RCC Beam: 1. Volume Of Beam = 10 cu.m 2. Concrete Mix Proportion = 1:1.5:3 3. Volume of Dry Concrete Mix = 15.2 cu.m A. Materials: 1. Quantity Of cement = 2.763 cu.m 2. No Of bags Of cement = 81.28 3. Sand = 4.144 cu.m 4. C.A. = 8.289 cu.m 5. Steel = 1570 kg 6. Binding wire = 15.7 kg B. Cost of Material: 1. Cement = 81.28 x 230 = 18694.4/- 2. Sand = 4.144 x 850 = 3522.4/- 3. Aggregate = 8.289 x 530 = 4393.17/- 4. Steel = 1570 x 34 = 53380/- 5. Binding Wire = 15.7 x 55 = 863.5/- 6. Total = 80853.47/- C. Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 3 x 170 = 510/- 3. Mazdoor = 10 x 110 = 1100/- 4. Centering & Shuttering = 5% x 80853.57 = 4042.68/- 5. Carpenter = 10 x 250 = 2500/- Nails = 500/- 6. Blacksmith = 15 x 200 = 3000/- 7. Total Cost = 8902.68/- D. TOTAL COST = B+C = 89756.15/- E. Add 1.5% Water charges = 1346.34 F. Add 10% Contractors Profit = 8975.6 G. GRAND TOTAL =100078.09 H. RATE FOR 1 CUM = 10007.809
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 10007.809
Todays BUZZ Word CONTRACTORS: A general contractor is responsible for the day-to-day oversight of the construction site, and management of vendors and trades. In addition, keep communication between the general contractor and the involved parties open and clear through out the course of project. TYPES OF CONTRACTORS WITH THEIR SCOPE OF WORK: 1. Centering Contractor - Line out work as per RCC drg Building work. 2. Excavation Contractor - Excavation Footings Pits (Underground Safety Drainage). 3. Masonary Contractor - AS per Working Drg. & Internal & External Plaster. 4. Plumbing Contractor - Internal External Plumbing layout, Drainage. 5. Electrical Contractor - Internal External electrification. 6. Carpentry Contractor - Doors, Windows Etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mule. (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: prasadkharat@ymail.com
Subject: 13531-03

Company Name Rajesh Constructions
Project Name & Site Address cloud-9,bhind mahavir college
Students Name (Surname_First Name_Middle Name) KHARAT PRASAD RAMACHANDRA
Exam No. 13531
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge observe 1& 2 way slab, cant. slab, sunk slab, etc.
Details of how you Planned & Executed the allotted work by observing steel design dwg. provided by str. consultant. We check all casted slabs & beam
Details of the Construction Procedure / Activity / Technology learned today REMOVAL OF FORM WORK- F.W. is removed acoo. to curing period. slab-7 days beam-7 days verticle faces of beam- 21 days
Details of the Construction Materials learned today SHINKAJAA- used for binding F.W. of beam ,col. ,slab. made up of iron.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of gunny bags for curing instead of plastic sheets.
Details of the Construction / Engineering Drawings observed today Elevation Dwg. arch. provided good appearance, elegnance , balcony on front side.
Details of the Bye Laws referred today floor to floor ht. & sealing ht. for window-0.9m & for ventilators-1.2m
Details of any Managerial Skill learned today time management
RATE ANALYSIS (Detailed Stepwise Calculations required) cement- 0.152/0.035= 4.34 5bags sand- 0.152*3= 0.456*1060=483.36 Rs. agg.- 0.152*6= 0.912*600=547.2 Rs. amount- 1250 +483.60 +547.2 =2280 Rs. + 2448 Rs. 4728 Rs./m Add 15% proffit of contractor.
Result of RATE ANALYSIS ( Rs per Unit ) 4728 Rs./m
Todays BUZZ Word Contractors- 1) centring contractor- casts all type of steel works. 2) plumbing contractor- fits all plumbing material & sanitary work. 3) eiectrification contractor- provides all electrical work.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. MILIND MAGADUM
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-03

Company Name V. S. Joshi & Associates
Project Name & Site Address Vishwa Enclave - V.S,Joshi Associates, mukta sainik vasahat, kolhapu
Students Name (Surname_First Name_Middle Name) Nagvekar Yogesh Deepak
Exam No. 10894
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge *Study Of Under Construction Flats 1. Electrification Work. 2. Plumbing Work. 3. Tilling Work. 4. Plastering Work *To Study Bore Well Excavation.
Details of how you Planned & Executed the allotted work *Study Of A Under Construction Flats* - We bifercated ourself into two groups - The first group observed the work being done on first floor. - The other group observed the second floor. - Accordingly Seven Floors were worked out. - The details of each work was then explained by Mr. Mulay. *To Study Excavation Of Bore Well* - We Studied various components of the truck mounted with hydraulic system of bore well. - Then accordingly Observed the excavation work.
Details of the Construction Procedure / Activity / Technology learned today *Excavation Of Bore Well: - First of all the site where the bore was to be dug was cleaned of. - Then the 6\" bore well mounted truck was brought near the site. - Then the installation of bore well was done. - The pipe rods were then attached to the metal drilling rod (with wedges) - Drilling was done - It was operated by a Hydraullic system fitted behind the truck. - Then accordingly excavation by drilling was carried out.
Details of the Construction Materials learned today - 3.5\' Metal drilling Rod - PVC Casing for bore well( 180mm dia, 6 kg/sq.cm )
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No
Details of the Construction / Engineering Drawings observed today Plans for each floor for \'C- Building\'
Details of the Bye Laws referred today No
Details of any Managerial Skill learned today - Completing the work in time. - Way to execute the work.
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for RCC Beam: 1. Volume Of Beam = 10 cu.m 2. Concrete Mix Proportion = 1:1.5:3 3. Volume of Dry Concrete Mix = 15.2 cu.m A. Materials: 1. Quantity Of cement = 2.763 cu.m 2. No Of bags Of cement = 81.28 3. Sand = 4.144 cu.m 4. C.A. = 8.289 cu.m 5. Steel = 1570 kg 6. Binding wire = 15.7 kg B. Cost of Material: 1. Cement = 81.28 x 230 = 18694.4/- 2. Sand = 4.144 x 850 = 3522.4/- 3. Aggregate = 8.289 x 530 = 4393.17/- 4. Steel = 1570 x 34 = 53380/- 5. Binding Wire = 15.7 x 55 = 863.5/- 6. Total = 80853.47/- C. Cost of Labour: 1. Head Mason = 1 x 250 = 250/- 2. Mason = 3 x 170 = 510/- 3. Mazdoor = 10 x 110 = 1100/- 4. Centering & Shuttering = 5% x 80853.57 = 4042.68/- 5. Carpenter = 10 x 250 = 2500/- Nails = 500/- 6. Blacksmith = 15 x 200 = 3000/- 7. Total Cost = 8902.68/- D. TOTAL COST = B+C = 89756.15/- E. Add 1.5% Water charges = 1346.34 F. Add 10% Contractors Profit = 8975.6 G. GRAND TOTAL =100078.09 H. RATE FOR 1 CUM = 10007.809
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 10007.809
Todays BUZZ Word CONTRACTORS: A general contractor is responsible for the day-to-day oversight of the construction site, and management of vendors and trades. In addition, keep communication between the general contractor and the involved parties open and clear through out the course of project. TYPES OF CONTRACTORS WITH THEIR SCOPE OF WORK: 1. Centering Contractor - Line out work as per RCC drg Building work. 2. Excavation Contractor - Excavation Footings Pits (Underground Safety Drainage). 3. Masonary Contractor - AS per Working Drg. & Internal & External Plaster. 4. Plumbing Contractor - Internal External Plumbing layout, Drainage. 5. Electrical Contractor - Internal External electrification. 6. Carpentry Contractor - Doors, Windows Etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? Yes
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A. Mule. (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523-03

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Devkar Vikram Dilip
Exam No. 13523
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge 1)to check the electrification layout according to the plan > 2)land filling under the guidance of Paras Oswal sir
Details of how you Planned & Executed the allotted work > 1)we were given 2 plans > 2)we divided ourselves in 2 groups > 3)we checked the laying of electrification pipes of each room according to > the plan > 4)we communicated with the site incharge and understood the procedure of how > the concealed wiring is done
Details of the Construction Procedure / Activity / Technology learned today > 1)form work > >form work was done for the staircase > > 2)laying of reinforcement for slab > >tor steel bars of 12mm diameters were bein layed at distance of 6 inch > >bars were layed in such a way that they formed squares > > 3)construction of cantilever beam > > 4)we also studied two way slab and intermediate slab
Details of the Construction Materials learned today > 1)pipes used for concealed wiring > >we saw the details of the plan > >the centre of the room is found out by drawing diagonals > >the fan is placed at this point,and the other wires r taken out from the > same point and connected to the switch board > >lines r taken down to the switch board of the lower floor > > 2)curing of columns > >we were allowed to spray water on the pillars > >water is to be sprayed 4-5 times for good curing > >gunny bags were not used for keping the pillars wet as they were not > provided > to the workers
Details of Environment Caring Technology / Methodology / Procedure / Product learned today > *rain water harvesting will be provided after the completion of project. > *rain water will be used for rechargin of gronud water,gardening,cleaning
Details of the Construction / Engineering Drawings observed today > 1)plan for only R.C.C beam grid purpose > 2)electrical drawing
Details of the Bye Laws referred today >>according to bye laws cantilever beam should be L/2 distance.i.e. the >> length > which projects beyond the design should also be reinforced inside. >>usually a bit more length is reinforced for safety purpose >>the maximum length of cantilever slab is 4m according to the bye law. > here they have provided a length of 2m.
Details of any Managerial Skill learned today > site incharge checked every detail according to the plan. > the corrections(if any) were made then n there under his supervision
RATE ANALYSIS (Detailed Stepwise Calculations required) > RATE ANALYSIS FOR R.C.C BEAM. > > (EXCLUDING M.S.REINFORCEMENT) > > > > Item : Reinforced Concrete Works > > Rate Analysis for: 10.000 cu.mt of RCC-M20-1 > > ----------------------------------------------------------------------- > > Sr . Description Qty Unit Rate (Rs. /Unit) Amount (Rs.) > > ----------------------------------------------------------------------- > > ** Material ** Quantity Rate > Total > > 1. 53grade OPC cement 61.706 bags 265.00 = 16352.09 > > 2. River sand 5.060 cu.mt 1230.00 = > 6223.80 > > 3. Aggregate 10.12cu.mt 1200 = > 12144 > > 4. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 > > 5. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 > > > > Total of Material : Rs. > =41674.99 > > > > ** Labour ** > > 1. Foreman 1.50 days 170.00 = > 255/- > > 2. Mason concreting works 2.00 days 106.00 = 212.0/- > > 3. Male Mazdoor 9.000 days 140.00 = > 1260.00/- > > 4. Female Mazdoor 12.000 days 120.00 = > 1440.00/- > > 5. Waterman 1.500 days 110.00 = > 165.00/- > > 6. Labour.Add 1.750 days 150.00 = > 262.50/- > > Total of Labour : Rs. > = 3594.50/- > > > > Grand Total Cost for 10.00 cu.mt : Rs. > = 45269.49/-
Result of RATE ANALYSIS ( Rs per Unit ) > Result of RATE ANALYSIS ( Rs per Unit ): Rs.4526.94/-
Todays BUZZ Word > General contractor- >>he is responsible for>the day-to-day oversight of the construction site > >management of vendors and trades. >>He keeps the communication between the contractor and the other parties > involved,open and clear through out the project > >>A subcontractor is an individual or business that signs a contract to >> perform > part or all of the obligations of another\'s contract. > >>Types of subcontractor\'s > > Main 3 types- > > 1)Domestic type of subcontractor:he is a subcontractor who contracts with > the > main contractor to supply or fix any materials or goods or execute work > forming part of the main contract. > He is employed by the main contractor. > > 2)Nominated subcontractor > > 3)Named subcontractor > > Other type of contractor\'s are: > *Roofing contractor > *Electrical contractor > *Insulation contractor > *Architects > *Painting contractor > *Plumbing contractor > *Carpenter contractor > *Construction contractor > > >
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: shindeamol5255@yahoo.co.in
Subject: 13546-03

Company Name Deshmukh Developers
Project Name & Site Address Goldenshelter
Students Name (Surname_First Name_Middle Name) Shinde Amol Jagannath
Exam No. 13546
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To observe electrification work. .
Details of how you Planned & Executed the allotted work We observed the work carefully. Write down all steps. We asked them questions regarding our doubts and get then clear. .
Details of the Construction Procedure / Activity / Technology learned today 1)Study the drawing. 2)Mark the points of switch and board,bulbs tubes and fans. 3)Then cut the grooves in the wall. 4)Fix the fittings. 5)Then fit the wires. .
Details of the Construction Materials learned today Wire dia. 1mm 1.5mm 2.mm 4.0mm. 1mm for switch board to point. 1.5 for switch board to board. 2.5mm for switch board to power supply. 4.0mm for switch board to main supply. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of fly ash bricks over conventional bricks. .
Details of the Construction / Engineering Drawings observed today Electrification Drawing. Current flow direction. Detailed layout plan. .
Details of the Bye Laws referred today Length to width ratio related criteria. .
Details of any Managerial Skill learned today Site engineer planned regarding the storing of material. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Mix proportion:- 1:1.5:3 Dry volume=52% Wet volume=1.52% a)Cement=(1.52)/(1+1.5+3)=0.276 cu.m no of bags=(0.276/0.035)=8 @Rs.250/bag Rs.2000/- b)Sand=0.2763*1.5=0.4144 cu.m @Rs.742/bag Rs.308/- c)Aggregate=0.2763*3=0.8289 @Rs.600/cu.m Rs.497/- d) Labour+Reinforcement+Profit= Rs.5101/- Total= Rs.7985/- .
Result of RATE ANALYSIS ( Rs per Unit ) 7985/-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Abhijeet Bhosle 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-d3

Company Name Shendre Associates
Project Name & Site Address \'mallhar hights\',c.s no367\\9ward ambai defence,kolhapur
Students Name (Surname_First Name_Middle Name) Fulari sujata shanka
Exam No. 13559
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 10.am
Site Leaving Time (HH:MM am/pm) 4.45pm
Details of the Work Allotted to you today by the Site In-Charge today site in-charge gave us for determining the quantity and rate of cement,sand and bricks required for one wall with deduction of door,lintel and quantity for loft&lintel.
Details of how you Planned & Executed the allotted work they give us sizes,firstly we found out quantity of cement per bag with there rate after that bricks quantity per sq.m with no.of bricks and there rates and lastly sand required for one wall per sq.m&rate for per brass in that way we done the work gave to us.
Details of the Construction Procedure / Activity / Technology learned today -today we learned re-baring of beam,when all work is done and any extra beam is want to provide at external or internal side that time re-baring is done with help of chemical mortar -plastering of external wall.
Details of the Construction Materials learned today -chemical mortar for rebaring the beam with grater strength the rate of that chemical mortar is 1150 for 345ml
Details of Environment Caring Technology / Methodology / Procedure / Product learned today today we learned rainwater harvesting for environment caring methodology use rain water down take pipe of size 12mm diameter and filtration tank for purification of rain water.
Details of the Construction / Engineering Drawings observed today today we observed plan of 5th floor building and bar bending schedule for that building.
Details of the Bye Laws referred today today we referred bye laws for rise and tread rise-150mm tread-250mm as per bye laws
Details of any Managerial Skill learned today today we learned how to manage workers on site,and they cooperate us very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR R.C.C BEAM (1:1.5:3) VOLUME-1.5cu.m cement=1.5/1+1.5+3=.28 no of bag=.28/.035=8bags rate for cement=8*270=2160rs sand=.28*1.5=.42cu.m rate=.42*830=348.6rs aggregate=.28*3=.84cu.m rate=.84*650=546rs TOTAL COST OF MATERIAL=2160+348.6+546=3054.6rs rate for beam reinforcement=95*32=3040rs LABOUR COST- for mistri-1no=200rs for mason-2no=2*250=500rs women for water curing-1no=140rs water=3054.6*1.5/100=45.82rs CENTRING&SHUTTERING- lumsum=75rs carpenter=150rs mazdor=80rs TOTAL=1190rs TOTAL COST WITH CONTRACTOR PROFIT=7284.6*1.15=8377.29RS
Result of RATE ANALYSIS ( Rs per Unit ) 8377.29RS
Todays BUZZ Word \'The term of contractor means a person who undertake any type of contract\' contractor is usually divided in 7 class as per their work -class1 contractor can take tender of any limit -class2 is upto300lakhs -class3 is upto100lakhs -class4 is upto50lakhs -class5 is upto 15lakhs -class6 is upto5;lakhs contractor is of many type like plumber contractor electrification road only residenstial buil.contractor as per work and their qualification they work.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge MR.vivek Randive 8805494033
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-03

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL ,karande mala
Students Name (Surname_First Name_Middle Name) MISAL SWAPNIL SHIVAJI
Exam No. 10877
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge To painting & construction of septic tank.
Details of how you Planned & Executed the allotted work Clearly observe the painting work & see what exactly the rollers are used in painting work. In the septic tank the watertight admixtures are used .
Details of the Construction Procedure / Activity / Technology learned today Hand Rollers used in painting.
Details of the Construction Materials learned today Diff. types of painting materials are as aster, prymer,two coats of oil bond (internal wall) prymer,2 coats of cement paint
Details of Environment Caring Technology / Methodology / Procedure / Product learned today In parking solar panels are used
Details of the Construction / Engineering Drawings observed today R.C.C. BEAM & COLUMN PLANS
Details of the Bye Laws referred today REGARDING SEPTIC TANK
Details of any Managerial Skill learned today Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BEAM PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 Cu.m ADDITION FOR DRY VOLUME: 52% VOLUME BECOMES: 1.52 CU.M CEMENT 1.52/1+1.5+3=0.2763 CU.M NUMBER OF CEMENT BAGS REQUIRED: 0.2763/0.035=7.89=8 BAGS COST= (8X260)=2080 Rs SAND: 0.2763X1.5=0.4144 CU.M COST=(0.4144X742.04)=307.50 Rs AGGREGATE: 0.2763 X 3=0.8289 CU.M COST = (0.8289 X 636.04)=527.21 Rs TOTAL COST OF MATERIAL: 2080+307.50+527.21 =2914.71 Rs REINFORCEMENT/STEEL COST 92 Kg/cu.m x 32 = 2944 Rs LABOUR CHARGES: PERSON NO. RATE 1) MISTRI: 1/2 125 Rs 2) MASON : 2 2 X 250 =500 Rs 3) BOY/WOMAN COOLIE: 2 2 X 140 = 280 Rs TOTAL LABOUR COST: =905 RS WATER: 1.5 % 2914.71 X (1.5/100)=41.30 Rs CENTERING AND SHUTTERING: TIMBER PLANKS: LUMP-SUMP 65 RS CARPENTER: 1 150 RS MAZDOOR: 1 80 RS TOTAL COST = 300 RS TOTAL COST OF WORK : 7104.3 RS CONTRACTORS PROFIT: 15 % = 1.15 X 7104.3 = 8169.94 RS CONTRACTORS PROFIT: 15 %
Result of RATE ANALYSIS ( Rs per Unit ) 8169.94 Rs/cu.m
Todays BUZZ Word DIFFERENT TYPES OF CONTRACTOR REQUIRED ARE AS FOLLOWS: Contractor means the person who provide workers to do their particular work and take whole responsibility for that particular work until the completion. 1)R.C.C. -it is the actual construction work related to concrete ,steel and no. of persons required for that construction. 2)plumbing- To provide the various type of drainage facilities and water supply required to fulfill the requirement of the various units of the buildings such as for sink, toilet , bathrooms,utility. 3) electrification- to provide electric fittings required for the buildings. 4)carpenter- do the work related to the wood work such as doors, furnitures, windows frames. 5)tile fitter- to provide floorings and dado work in all the rooms , toilet,kitchen,balcony in the surrounding of buildings also. 6) centering- the work of the contractor is to provide the support/ formwork required before doing further work of steel and concreting. 7)mason- to provide the no. of masons required for doing the work. 8)mild steel contractor- provides only steel required for the windows grills ,safety doors,railings , gate. 9)painter- to give the final finishing to the building for decorative purposes and to apply the wall putty also. 10)aluminium works for windows- to provide the glass windows.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Ketan Charapale m.9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521-02

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) Bagmare Dinesh Shriram
Exam No. 13521
Working Day No. 02
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge > 1)to check the electrification layout according to the plan > 2)land filling under the guidance of Paras Oswal sir
Details of how you Planned & Executed the allotted work > 1)we were given 2 plans > 2)we divided ourselves in 2 groups > 3)we checked the laying of electrification pipes of each room according to > the plan > 4)we communicated with the site incharge and understood the procedure of how the concealed wiring is done
Details of the Construction Procedure / Activity / Technology learned today 1)form work form work was done for the staircase 2)laying of reinforcement for slab tor steel bars of 12mm diameters were bein layed at distance of 6 inch bars were layed in such a way that they formed squares 3)construction of cantilever beam 4)we also studied two way slab and intermediate slab
Details of the Construction Materials learned today 1)pipes used for concealed wiring > >we saw the details of the plan > >the centre of the room is found out by drawing diagonals > >the fan is placed at this point,and the other wires r taken out from the > same point and connected to the switch board > >lines r taken down to the switch board of the lower floor > > 2)curing of columns > >we were allowed to spray water on the pillars > >water is to be sprayed 4-5 times for good curing > >gunny bags were not used for keping the pillars wet as they were not > provided > to the workers
Details of Environment Caring Technology / Methodology / Procedure / Product learned today *rain water harvesting will be provided after the completion of project. > *rain water will be used for rechargin of gronud water,gardening,cleaning
Details of the Construction / Engineering Drawings observed today 1)plan for only R.C.C beam grid purpose > 2)electrical drawing
Details of the Bye Laws referred today >>according to bye laws cantilever beam should be L/2 distance.i.e. the >> length > which projects beyond the design should also be reinforced inside. >>usually a bit more length is reinforced for safety purpose >>the maximum length of cantilever slab is 4m according to the bye law. > here they have provided a length of 2m.
Details of any Managerial Skill learned today > site incharge checked every detail according to the plan. > the corrections(if any) were made then n there under his supervision
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR R.C.C BEAM. > (EXCLUDING M.S.REINFORCEMENT) > > > > Item : Reinforced Concrete Works > > Rate Analysis for: 10.000 cu.mt of RCC-M20-1 > > ----------------------------------------------------------------------- > > Sr . Description Qty Unit Rate (Rs. /Unit) Amount (Rs.) > > ----------------------------------------------------------------------- > > ** Material ** Quantity Rate > Total > > 1. 53grade OPC cement 61.706 bags 265.00 = 16352.09 > > 2. River sand 5.060 cu.mt 1230.00 = > 6223.80 > > 3. Aggregate 10.12cu.mt 1200 = > 12144 > > 4. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 > > 5. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 > > > > Total of Material : Rs. > =41674.99 > > > > ** Labour ** > > 1. Foreman 1.50 days 170.00 = > 255/- > > 2. Mason concreting works 2.00 days 106.00 = 212.0/- > > 3. Male Mazdoor 9.000 days 140.00 = > 1260.00/- > > 4. Female Mazdoor 12.000 days 120.00 = > 1440.00/- > > 5. Waterman 1.500 days 110.00 = > 165.00/- > > 6. Labour.Add 1.750 days 150.00 = > 262.50/- > > Total of Labour : Rs. > = 3594.50/- > > > > Grand Total Cost for 10.00 cu.mt : Rs. > = 45269.49/- > > > > Unit Cost per cu.mt is: Rs. > = 4526.94/- > >
Result of RATE ANALYSIS ( Rs per Unit ) > Result of RATE ANALYSIS ( Rs per Unit ): Rs.4526.94/-
Todays BUZZ Word General contractor- he is responsible for>the day-to-day oversight of the construction site management of vendors and trades. He keeps the communication between the contractor and the other parties involved,open and clear through out the project A subcontractor is an individual or business that signs a contract to perform part or all of the obligations of another\'s contract. >>Types of subcontractor\'s Main 3 types- 1)Domestic type of subcontractor:he is a subcontractor who contracts with the main contractor to supply or fix any materials or goods or execute work forming part of the main contract. He is employed by the main contractor. 2)Nominated subcontractor 3)Named subcontractor Other type of contractor\'s are: *Roofing contractor *Electrical contractor *Insulation contractor *Architects *Painting contractor *Plumbing contractor *Carpenter contractor *Construction contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-03

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Tambe Trusha
Exam No. 10902
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge Supervision of steel reinforcement of beam. .
Details of how you Planned & Executed the allotted work First we took the structural drawing &checked all the spacing,cover,length,stirrups etc.as per the drawing. .
Details of the Construction Procedure / Activity / Technology learned today Today we learned the process of grouting.first drilling is done the affected area.then the pipe is fixed in it.and then pressure is applied through it which fills the voids from concrete and stops the leakage from it. .
Details of the Construction Materials learned today Crush sand is used instead of river sand. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Crush sand is used instead of river sand. .
Details of the Construction / Engineering Drawings observed today Today we observed the structural drawing that is of steel reinforcement.in it we observed the spacing,length,cover etc.and also how the notation or symbols of different types are given. .
Details of the Bye Laws referred today Balcony or balconies of max.width of 1.2m. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) cement= 6.90bags @Rs.260/bag Rs.1794/- sand = 0.6cu.m @Rs.1155/- Rs.693/- metal = 0.90cu.m @Rs.304/- Rs.273/- steel = 180kg @Rs.35/kg Rs.6300/- shuttering material@Rs.225/sq.m Rs.1800/- Conc. pouring @Rs.350/cu.m Rs.350/- Total= Rs.11210/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.11210/-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-03

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dhapodkar Parag Vasudev
Exam No. 10891
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge Tilling Work/furniture…. .
Details of how you Planned & Executed the allotted work First we go on site & divided in two group first we see tiling work & take information from worker.then we see external plastering work.& take detal information also we see furniture work& get about detail information…. .
Details of the Construction Procedure / Activity / Technology learned today In tiling- first prepared base surface take sand & cement in proportion & laid on base in sutable layer ,on this surface Spread cement slurry & place vitrified tiles on this surface’ & applay blow on it by wooden rammer..
Details of the Construction Materials learned today Vertified tile,granite,kaddapa,alluminium window,bajari glass ,plain glass, .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Ecofriendly plywood are used for furniture work. .
Details of the Construction / Engineering Drawings observed today Furniture drawing Electrification drawing .
Details of the Bye Laws referred today Compound wall 2.4 M hight provide according to bylaws. .
Details of any Managerial Skill learned today We are meet different type of of contracter & they gave us brif information about his work projet & they co-oprete very well. .
RATE ANALYSIS (Detailed Stepwise Calculations required) M 20 concret 1 unit=1m3 Cement=6.90*255=1759.5 (rate per bag=255 & 6.90 no.of bag) Sand=0.035*1.5*6.90*44*35*28=562.327 Metal=0.035*3*6.90*18*35.28=460.08 Labour=40*35.48=1411 Steel=75*35=2625 Total=6817.00/m3 .
Result of RATE ANALYSIS ( Rs per Unit ) 6817.00/cu.m
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil 9890997979 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: gauravdesai75@gmail.com
Subject: 13522-03

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Builders and Developers, near jaybrabha studio,Kolhapur.
Students Name (Surname_First Name_Middle Name) DESAI GAURAV RAVINDRA
Exam No. 13522
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 AM
Site Leaving Time (HH:MM am/pm) 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge TO CHECK THE ELECTRICAL FIXTURES(PIPES) ETC. THAT ARE BEING PROVIDED ACCORDING TO PLANS. TO SEE THE LANDFILLING PROCESS IN THE ADJOINING AREA OF THE SITE AS RECOMMENDED BY PARAS OSWAL SIR.
Details of how you Planned & Executed the allotted work 1)We were given 2 plans. 2)We divided ourselves in 2 groups. 3)We checked the laying of electrification pipes of each room according to the plan. 4)We communicated with the site incharge and understood the procedure of how the concealed wiring is done.
Details of the Construction Procedure / Activity / Technology learned today 1.Process of Landfilling on adjoining site 2.Formwork and shuttering was been constructed for stair-case of next flight. 3.Concealed Electric wiring purpose conduit pipes were provided before casting of slab. 4.As per yesterdays markings for bathroom fittings, plumbing and pipe fitting work has been provided. 5.Laying of reinforcement for slab. Tor steel bars of 12mm diameters were bein layed at distance of 6 inch bars were layed in such a way that they formed squares. 6.Construction of cantilever beam. 7.We also studied two way slab and intermediate slab. 8.Pipes used for concealed wiring. >we saw the details of the plan. >the centre of the room is found out by drawing diagonals. >the fan is placed at this point,and the other wires r taken out from the same point and connected to the switch board. >lines r taken down to the switch board of the lower floor. 9.Curing of columns. >we were allowed to spray water on the pillars. >water is to be sprayed 4-5 times for good curing. >gunny bags were not used for keping the pillars wet as they were not provided. >to the workers.
Details of the Construction Materials learned today 1. Conduit pipes for electrical wiring. 2. Type of formwork for stair-case. 3. Types of bars used. 4. Type of material used for electrical fittings. 5. All the necessary things that are necessary to be done before casting of slab.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today *Rain water harvesting will be provided after the completion of project. *Rain water will be used for recharging of gronud water,gardening,cleaning.
Details of the Construction / Engineering Drawings observed today > 1)Plan for only R.C.C beam grid purpose. > 2)Electrical drawing plan.
Details of the Bye Laws referred today >According to bye laws cantilever beam should be L/2 distance.i.e. the length, which projects beyond the design should also be reinforced inside. Usually a bit more length is reinforced for safety purpose > The maximum length of cantilever slab is 4m according to the bye law. here they have provided a length of 2m.
Details of any Managerial Skill learned today > Site incharge checked every detail according to the plan. > The corrections(if any) were made then and there under his supervision. > The site incharge told the position of different electrical fittings to be provided according to the plans.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR R.C.C BEAM. (EXCLUDING M.S.REINFORCEMENT) Item : Reinforced Concrete Works Rate Analysis for: 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr . Description Qty Unit Rate (Rs. /Unit) Amount (Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade OPC cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 4. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 5. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs =41674.99 ** Labour ** 1. Foreman 1.50 days 170.00 = 255/- 2. Mason concreting works 2.00 days 106.00 = 212/- 3. Male Mazdoor 9.000 days 140.00 = 1260.00/- 4. Female Mazdoor 12.000 days 120.00 = 1440.00/- 5. Waterman 1.500 days 110.00 = 165.00/- 6. Labour.Add 1.750 days 150.00 = 262.50/- Total of Labour : Rs. = 3594.50/- Grand Total Cost for 10.00 cu.mt :Rs. =45269.49/- Unit Cost per cu.mt is: Rs. = 4526.94/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 4526.94/- per cu.mt
Todays BUZZ Word \"CONTRACTORS\" 1.Plumbing and sanitation. 2.Flooring and fixing of tiles with kitchen otta. 3.Anti-termite and pest control. 4.M.S. Window grill work and Aluminium Window fixing. 5.Furniture, wardrobes, door fitting etc. 6.Electrical wiring and fitting. 7.Painting internal and external. 8.Reticulated gas pipe system 9.Fire-fighting system. 10.Lift. 11.Cctv system. 12.Wi-fi system. 13.Security system. > General contractor- >he is responsible for>the day-to-day oversight of the construction site >management of vendors and trades. >>He keeps the communication between the contractor and the other parties involved,open and clear through out the project. >>A subcontractor is an individual or business that signs a contract to perform part or all of the obligations of another\'s contract. >>Types of subcontractor\'s Main 3 types- 1)Domestic type of subcontractor:he is a subcontractor who contracts with the main contractor to supply or fix any materials or goods or execute work forming part of the main contract. He is employed by the main contractor. 2)Nominated subcontractor.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR. PH NO.9922313712.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-03

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) LAVATE PRASHANT SURESH
Exam No. 13535
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9 a.m.
Site Leaving Time (HH:MM am/pm) 4 p.m.
Details of the Work Allotted to you today by the Site In-Charge *CHECKING THE MEASUREMENT OF TOWER \'A\' BY USING DIAGONAL METHOD
Details of how you Planned & Executed the allotted work * We decide 2 person will take distances & 2 persons will refer the plan.
Details of the Construction Procedure / Activity / Technology learned today * First we divided entire plan in 2 part. * Then we took measurement (side & diagonal) & referred with actual plan. * We found difference of about 1-2 cm after comparing with plan.
Details of the Construction Materials learned today * BRICK * They use block type brick of sizes 9\"*6\"*4\". * Cost of 1 brick is 6.30. * It is useful for rapid construction. * Trolley contain about 1000 no. & tampo cotain about 1500 no.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today * Instead of using normal wood they use marine formwork. * Advantage of using this formwork,it is long life.
Details of the Construction / Engineering Drawings observed today * Today we have seen working drawing, R.C.C. drawing of tower \'A\'.
Details of the Bye Laws referred today * They maintain distance between 2 column less than 6m ad per BYE-LAWS.
Details of any Managerial Skill learned today * There are 3 SITE-INCHARGE. They handle perticular tower \'A\',\'E\'& office work. * Good co-ordination between SITE-INCHAGE & ENGINEER.
RATE ANALYSIS (Detailed Stepwise Calculations required) *R.C.C. BEAM MATERIAL QUANTITY COST(Rs) CEMENT 6 bags 1560 SAND 0.2835 CuM 327.72 AGG. 0.567 CuM 766 MISTRI 6bags*70 420 WATER - 100 STEEL 118.47Kg 3554 TOTAL - 6728 PER CuM 6728/0.52 1293813000
Result of RATE ANALYSIS ( Rs per Unit ) 13000 RS/CuM
Todays BUZZ Word 1)R.C.C. -it is the actual construction work related to concrete ,steel and no. of persons required for that construction. 2)plumbing- To provide the various type of drainage facilities and water supply required to fulfill the requirement of the various units of the buildings such as for sink, toilet , bathrooms,utility. 3) electrification- to provide electric fittings required for the buildings. 4)carpenter- do the work related to the wood work such as doors, furnitures, windows frames. 5)tile fitter- to provide floorings and dado work in all the rooms , toilet,kitchen,balcony in the surrounding of buildings also. 6) centering- the work of the contractor is to provide the support/ formwork required before doing further work of steel and concreting. 7)mason- to provide the no. of masons required for doing the work. 8)mild steel contractor- provides only steel required for the windows grills ,safety doors,railings , gate. 9)painter- to give the final finishing to the building for decorative purposes and to apply the wall putty also. 10)aluminium works for windows- to provide the glass windows.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J.CHOUGALE MOB.NO.9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: buntyphonde@gmail.com
Subject: 10899-03

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Phonde Pravin Tukaram
Exam No. 10899
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of steel reinforcement of beam. .
Details of how you Planned & Executed the allotted work First we took the structural drawing &checked all the spacing,cover,length,stirrups etc.as per the drawing. .
Details of the Construction Procedure / Activity / Technology learned today Today we learned the process of grouting.first drilling is done the affected area.then the pipe is fixed in it.and then pressure is applied through it which fills the voids from concrete and stops the leakage from it. .
Details of the Construction Materials learned today Crush sand is used instead of river sand. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Crush sand is used instead of river sand. .
Details of the Construction / Engineering Drawings observed today Today we observed the structural drawing that is of steel reinforcement.in it we observed the spacing,length,cover etc.and also how the notation or symbols of different types are given. .
Details of the Bye Laws referred today Balcony or balconies of max.width of 1.2m. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) cement= 6.90bags @Rs.260/bag Rs.1794/- sand = 0.6cu.m @Rs.1155/- Rs.693/- metal = 0.90cu.m @Rs.304/- Rs.273/- steel = 180kg @Rs.35/kg Rs.6300/- shuttering material@Rs.225/sq.m Rs.1800/- Conc. pouring @Rs.350/cu.m Rs.350/- Total= Rs.11210/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.11210/-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-03

Company Name Deshmukh Developers
Project Name & Site Address Deshmukh Developments,Pratibha Nagar ,Kolhapur
Students Name (Surname_First Name_Middle Name) Birajdar Minaxi Renuk
Exam No. 13556
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today Site Incharge give us observation work of how the electrification is done in a residential building. - To study about how earthing is done - To study about how concealed wiring is done - T study about how the switch board, plug boards are attached
Details of how you Planned & Executed the allotted work We all groupmates are to measure distance of switch board, Main control board,Foot light from ground level. - To count how many ceiling fans are provided - To count how many flurocent tubes are provided - To count how many bulbs are provided
Details of the Construction Procedure / Activity / Technology learned today On site concealed wiring is done, - 1\" depth made into wall - 1mm wire is placed into in it - PVC pipe is covered - Distance from ground level, switch board-4\'8\" Foot light-10\" - Main control board-2.2m
Details of the Construction Materials learned today The material are used , - Three wires are used namely positive.negative,earthing - PVC pipes are used for concealing the wire - Metal switch boards are used of size-8 Module, 4 Module etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain water harvesting down take pipes are taken into ground, - PVC pipes are used of diameter 140mm
Details of the Construction / Engineering Drawings observed today Today we are observe Electrification Drawing. - Fan point,tube position, bulb point are shown - All above points are connected to switch board - Switch board are placed in every rooms - Every switch board connection connect to Main Control Board
Details of the Bye Laws referred today We are referred bye laws today for, - Plinth Height compared with actual given on site - Room Height Compared with actual given on site - Plinth Height-0.75 - Room Height- 3.1
Details of any Managerial Skill learned today Today we are learned, The Manager how they interact with customer, they put their ideas very intelligently and very confidently,make the customer to accept their ideas
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate Analysis for Beam: Proportion used 1:1/2:3 For dry volume=52% cement =1.52/(1+1.5+3) =0.2763m3 number of bags=0.2763/0.035 =8bags 8*260=2080 Rs sand =0.2763*1.5 =0.4144m3 =0.4144*742.05 =307.50 Aggregate =0.2763*3 =0.8289m3 =0.8289*600.71 =497.92 Rs Total Cost Of Material=2885.42 Rs For beam and reinforcement, 92kg/cum=2944 Rs Labour =mistri=1/2 number=125 Mason=2 number=2*250=500 Men/Woman 2 number=2*140=280 TOTAL = 905 Rs Water 1 1/2%=2753.47*(1.5/100) =41.30 Rs Centering & Shuttering= Timber plants=Lump Sump=65 Carpenter= 1 number = 150 Rs Mazdoor= 1 number =80 Rs TOTAL = 300 Contractor Profit=7075.72*1.15 =8137.08 Rs
Result of RATE ANALYSIS ( Rs per Unit ) 8137.08 Rs
Todays BUZZ Word Todays Buzz Word Is Contractors, The term contractors means a person or firm who undertakes any type of contract. Usually this term is confined to the contractors engaged for the construction or execution of works of repairs.For example-Contractors for centering, for R.C.C, for mason, for electrical,for tile fitter etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Abhijit Bhosale Mob.No 9921515194
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-03

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Abhishek Dadasaheb
Exam No. 10895
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of steel reinforcement of beam. .
Details of how you Planned & Executed the allotted work First we took the structural drawing &checked all the spacing,cover,length,stirrups etc.as per the drawing. .
Details of the Construction Procedure / Activity / Technology learned today Today we learned the process of grouting.first drilling is done the affected area.then the pipe is fixed in it.and then pressure is applied through it which fills the voids from concrete and stops the leakage from it. .
Details of the Construction Materials learned today Crush sand is used instead of river sand. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Crush sand is used instead of river sand. .
Details of the Construction / Engineering Drawings observed today Today we observed the structural drawing that is of steel reinforcement.in it we observed the spacing,length,cover etc.and also how the notation or symbols of different types are given. .
Details of the Bye Laws referred today Balcony or balconies of max.width of 1.2m. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) cement= 6.90bags @Rs.260/bag Rs.1794/- sand = 0.6cu.m @Rs.1155/- Rs.693/- metal = 0.90cu.m @Rs.304/- Rs.273/- steel = 180kg @Rs.35/kg Rs.6300/- shuttering material@Rs.225/sq.m Rs.1800/- Conc. pouring @Rs.350/cu.m Rs.350/- Total= Rs.11210/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.11210/-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-03

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Varun Vihar Township , Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) PATIL ADITYA PANDURANG
Exam No. 13538
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9 a.m.
Site Leaving Time (HH:MM am/pm) 4 p.m.
Details of the Work Allotted to you today by the Site In-Charge *CHECKING THE MEASUREMENT OF TOWER \'A\' BY USING DIAGONAL METHOD
Details of how you Planned & Executed the allotted work * We decide 2 person will take distances & 2 persons will refer the plan.
Details of the Construction Procedure / Activity / Technology learned today * First we divided entire plan in 2 part. * Then we took measurement (side & diagonal) & referred with actual plan. * We found difference of about 1-2 cm after comparing with plan.
Details of the Construction Materials learned today * BRICK * They use block type brick of sizes 9\"*6\"*4\". * Cost of 1 brick is 6.30. * It is useful for rapid construction. * Trolley contain about 1000 no. & tampo cotain about 1500 no.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today * Instead of using normal wood they use marine formwork. * Advantage of using this formwork,it is long life.
Details of the Construction / Engineering Drawings observed today * Today we have seen working drawing, R.C.C. drawing of tower \'A\'.
Details of the Bye Laws referred today * They maintain distance between 2 column less than 6m ad per BYE-LAWS.
Details of any Managerial Skill learned today * There are 3 SITE-INCHARGE. They handle perticular tower \'A\',\'E\'& office work. * Good co-ordination between SITE-INCHAGE & ENGINEER.
RATE ANALYSIS (Detailed Stepwise Calculations required) *R.C.C. BEAM MATERIAL QUANTITY COST(Rs) CEMENT 6 bags 1560 SAND 0.2835 CuM 327.72 AGG. 0.567 CuM 766 MISTRI 6bags*70 420 WATER - 100 STEEL 118.47Kg 3554 TOTAL - 6728 PER CuM 6728/0.52 1293813000
Result of RATE ANALYSIS ( Rs per Unit ) 13000 RS/CuM
Todays BUZZ Word 1)R.C.C. -it is the actual construction work related to concrete ,steel and no. of persons required for that construction. 2)plumbing- To provide the various type of drainage facilities and water supply required to fulfill the requirement of the various units of the buildings such as for sink, toilet , bathrooms,utility. 3) electrification- to provide electric fittings required for the buildings. 4)carpenter- do the work related to the wood work such as doors, furnitures, windows frames. 5)tile fitter- to provide floorings and dado work in all the rooms , toilet,kitchen,balcony in the surrounding of buildings also. 6) centering- the work of the contractor is to provide the support/ formwork required before doing further work of steel and concreting. 7)mason- to provide the no. of masons required for doing the work. 8)mild steel contractor- provides only steel required for the windows grills ,safety doors,railings , gate. 9)painter- to give the final finishing to the building for decorative purposes and to apply the wall putty also. 10)aluminium works for windows- to provide the glass windows.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J.CHOUGALE MOB.NO.9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-03

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) tekwani sagar bansilal
Exam No. 10903
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge 1)to check the electrification layout according to the plan 2)land filling under the guidance of Paras Oswal sir
Details of how you Planned & Executed the allotted work 1)we were given 2 plans 2)we divided ourselves in 2 groups 3)we checked the laying of electrification pipes of each room according to the plan 4)we communicated with the site incharge and understood the procedure of how the concealed wiring is done
Details of the Construction Procedure / Activity / Technology learned today 1)form work >form work was done for the staircase 2)laying of reinforcement for slab >tor steel bars of 12mm diameters were bein layed at distance of 6 inch >bars were layed in such a way that they formed squares 3)construction of cantilever beam 4)we also studied two way slab and intermediate slab
Details of the Construction Materials learned today 1)pipes used for concealed wiring >we saw the details of the plan >the centre of the room is found out by drawing diagonals >the fan is placed at this point,and the other wires r taken out from the same point and connected to the switch board >lines r taken down to the switch board of the lower floor 2)curing of columns >we were allowed to spray water on the pillars >water is to be sprayed 4-5 times for good curing >gunny bags were not used for keeping the pillars wet as they were not provided to the workers
Details of Environment Caring Technology / Methodology / Procedure / Product learned today *rain water harvesting will be provided after the completion of project. *rain water will be used for rechargin of gronud water,gardening,cleaning
Details of the Construction / Engineering Drawings observed today 1)plan for only R.C.C beam grid purpose 2)electrical drawing
Details of the Bye Laws referred today >according to bye laws cantilever beam should be L/2 distance.i.e.the length which projects beyond the design should also be reinforced inside. >usually a bit more length is reinforced for safety purpose >the maximum length of cantilever slab is 4m according to the bye law. here they have provided a length of 2m.
Details of any Managerial Skill learned today > site incharge checked every detail according to the plan. > the corrections(if any) were made then n there under his supervision
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR R.C.C BEAM. (EXCLUDING M.S.REINFORCEMENT) Item : Reinforced Concrete Works Rate Analysis for: 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr . Description Qty Unit Rate (Rs. /Unit) Amount (Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade OPC cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 4. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 5. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. =41674.99 ** Labour ** 1. Foreman 1.50 days 170.00 = 255/- 2. Mason concreting works 2.00 days 106.00 = 212.0/- 3. Male Mazdoor 9.000 days 140.00 = 1260.00/- 4. Female Mazdoor 12.000 days 120.00 = 1440.00/- 5. Waterman 1.500 days 110.00 = 165.00/- 6. Labour.Add 1.750 days 150.00 = 262.50/- Total of Labour : Rs. = 3594.50/- Grand Total Cost for 10.00 cu.mt : Rs. = 45269.49/- Unit Cost per cu.mt is: Rs. = 4526.94/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4526.94/-
Todays BUZZ Word General contractor- >he is responsible for>the day-to-day oversight of the construction site >management of vendors and trades. >He keeps the communication between the contractor and the other parties involved,open and clear through out the project >A subcontractor is an individual or business that signs a contract to perform part or all of the obligations of another\'s contract. >Types of subcontractor\'s Main 3 types- 1)Domestic type of subcontractor:he is a subcontractor who contracts with the main contractor to supply or fix any materials or goods or execute work forming part of the main contract. >He is employed by the main contractor. 2)Nominated subcontractor 3)Named subcontractor Other type of contractor\'s are: *Roofing contractor *Electrical contractor *Insulation contractor *Architects *Painting contractor *Plumbing contractor *Carpenter contractor *Construction contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-03

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Patil Sharad Shankarrao
Exam No. 10897
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 09.30am
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge Supervision of steel reinforcement of beam. .
Details of how you Planned & Executed the allotted work First we took the structural drawing &checked all the spacing,cover,length,stirrups etc.as per the drawing. .
Details of the Construction Procedure / Activity / Technology learned today Today we learned the process of grouting.first drilling is done the affected area.then the pipe is fixed in it.and then pressure is applied through it which fills the voids from concrete and stops the leakage from it. .
Details of the Construction Materials learned today Crush sand is used instead of river sand. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Crush sand is used instead of river sand. .
Details of the Construction / Engineering Drawings observed today Today we observed the structural drawing that is of steel reinforcement.in it we observed the spacing,length,cover etc.and also how the notation or symbols of different types are given. .
Details of the Bye Laws referred today Balcony or balconies of max.width of 1.2m. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) cement= 6.90bags @Rs.260/bag Rs.1794/- sand = 0.6cu.m @Rs.1155/- Rs.693/- metal = 0.90cu.m @Rs.304/- Rs.273/- steel = 180kg @Rs.35/kg Rs.6300/- shuttering material@Rs.225/sq.m Rs.1800/- Conc. pouring @Rs.350/cu.m Rs.350/- Total= Rs.11210/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.11210/-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-03

Company Name Shivshakti Constructions
Project Name & Site Address Chandra Milla, Shivshakti Developers
Students Name (Surname_First Name_Middle Name) Sawant Amit Ganpat
Exam No. 10900
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.30am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of steel reinforcement of beam. .
Details of how you Planned & Executed the allotted work First we took the structural drawing &checked all the spacing,cover,length,stirrups etc.as per the drawing. .
Details of the Construction Procedure / Activity / Technology learned today Today we learned the process of grouting.first drilling is done the affected area.then the pipe is fixed in it.and then pressure is applied through it which fills the voids from concrete and stops the leakage from it. .
Details of the Construction Materials learned today Crush sand is used instead of river sand. . .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Crush sand is used instead of river sand. .
Details of the Construction / Engineering Drawings observed today Today we observed the structural drawing that is of steel reinforcement.in it we observed the spacing,length,cover etc.and also how the notation or symbols of different types are given. .
Details of the Bye Laws referred today Balcony or balconies of max.width of 1.2m. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) cement= 6.90bags @Rs.260/bag Rs.1794/- sand = 0.6cu.m @Rs.1155/- Rs.693/- metal = 0.90cu.m @Rs.304/- Rs.273/- steel = 180kg @Rs.35/kg Rs.6300/- shuttering material@Rs.225/sq.m Rs.1800/- Conc. pouring @Rs.350/cu.m Rs.350/- Total= Rs.11210/- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs.11210/-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-03

Company Name Tirupati / Vertex Constructions
Project Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Students Name (Surname_First Name_Middle Name) MANGAOKAR MANOJ DATTATRAY
Exam No. 13536
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9 a.m.
Site Leaving Time (HH:MM am/pm) 4 p.m.
Details of the Work Allotted to you today by the Site In-Charge *CHECKING THE MEASUREMENT OF TOWER \'A\' BY USING DIAGONAL METHOD
Details of how you Planned & Executed the allotted work * We decide 2 person will take distances & 2 persons will refer the plan.
Details of the Construction Procedure / Activity / Technology learned today * First we divided entire plan in 2 part. * Then we took measurement (side & diagonal) & referred with actual plan. * We found difference of about 1-2 cm after comparing with plan.
Details of the Construction Materials learned today * BRICK * They use block type brick of sizes 9\"*6\"*4\". * Cost of 1 brick is 6.30. * It is useful for rapid construction. * Trolley contain about 1000 no. & tampo cotain about 1500 no.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today * Instead of using normal wood they use marine formwork. * Advantage of using this formwork,it is long life.
Details of the Construction / Engineering Drawings observed today * Today we have seen working drawing, R.C.C. drawing of tower \'A\'.
Details of the Bye Laws referred today * They maintain distance between 2 column less than 6m ad per BYE-LAWS.
Details of any Managerial Skill learned today * There are 3 SITE-INCHARGE. They handle perticular tower \'A\',\'E\'& office work. * Good co-ordination between SITE-INCHAGE & ENGINEER.
RATE ANALYSIS (Detailed Stepwise Calculations required) *R.C.C. BEAM MATERIAL QUANTITY COST(Rs) CEMENT 6 bags 1560 SAND 0.2835 CuM 327.72 AGG. 0.567 CuM 766 MISTRI 6bags*70 420 WATER - 100 STEEL 118.47Kg 3554 TOTAL - 6728 PER CuM 6728/0.52 1293813000
Result of RATE ANALYSIS ( Rs per Unit ) 13000 RS/CuM
Todays BUZZ Word DIFFERENT TYPES OF CONTRACTOR REQUIRED ARE AS FOLLOWS: Contractor means the person who provide workers to do their particular work and take whole responsibility for that particular work until the completion. 1)R.C.C. -it is the actual construction work related to concrete ,steel and no. of persons required for that construction. 2)plumbing- To provide the various type of drainage facilities and water supply required to fulfill the requirement of the various units of the buildings such as for sink, toilet , bathrooms,utility. 3) electrification- to provide electric fittings required for the buildings. 4)carpenter- do the work related to the wood work such as doors, furnitures, windows frames. 5)tile fitter- to provide floorings and dado work in all the rooms , toilet,kitchen,balcony in the surrounding of buildings also. 6) centering- the work of the contractor is to provide the support/ formwork required before doing further work of steel and concreting. 7)mason- to provide the no. of masons required for doing the work. 8)mild steel contractor- provides only steel required for the windows grills ,safety doors,railings , gate. 9)painter- to give the final finishing to the building for decorative purposes and to apply the wall putty also. 10)aluminium works for windows- to provide the glass windows.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J.CHOUGALE MOB.NO.9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-03

Company Name Pooja Developers & Builders
Project Name & Site Address Pooja Developers & Builders
Students Name (Surname_First Name_Middle Name) hasabnis ketaki bhagwan
Exam No. 13527
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge 1)to check the electrification layout according to the plan 2)land filling under the guidance of Paras Oswal sir
Details of how you Planned & Executed the allotted work 1)we were given 2 plans 2)we divided ourselves in 2 groups 3)we checked the laying of electrification pipes of each room according to the plan 4)we communicated with the site incharge and understood the procedure of how the concealed wiring is done
Details of the Construction Procedure / Activity / Technology learned today 1)form work >form work was done for the staircase 2)laying of reinforcement for slab >tor steel bars of 12mm diameters were bein layed at distance of 6 inch >bars were layed in such a way that they formed squares 3)construction of cantilever beam 4)we also studied two way slab and intermediate slab
Details of the Construction Materials learned today 1)pipes used for concealed wiring >we saw the details of the plan >the centre of the room is found out by drawing diagonals >the fan is placed at this point,and the other wires r taken out from the same point and connected to the switch board >lines r taken down to the switch board of the lower floor 2)curing of columns >we were allowed to spray water on the pillars >water is to be sprayed 4-5 times for good curing >gunny bags were not used for keping the pillars wet as they were not provided to the workers
Details of Environment Caring Technology / Methodology / Procedure / Product learned today *rain water harvesting will be provided after the completion of project. *rain water will be used for rechargin of gronud water,gardening,cleaning
Details of the Construction / Engineering Drawings observed today 1)plan for only R.C.C beam grid purpose 2)electrical drawing
Details of the Bye Laws referred today >according to bye laws cantilever beam should be L/2 distance.i.e. the length which projects beyond the design should also be reinforced inside. >usually a bit more length is reinforced for safety purpose >the maximum length of cantilever slab is 4m according to the bye law. here they have provided a length of 2m.
Details of any Managerial Skill learned today site incharge checked every detail according to the plan. the corrections(if any) were made then n there under his supervision
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR R.C.C BEAM. (EXCLUDING M.S.REINFORCEMENT) Item : Reinforced Concrete Works Rate Analysis for: 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr . Description Qty Unit Rate (Rs. /Unit) Amount (Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade OPC cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 4. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 5. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. =41674.99 ** Labour ** 1. Foreman 1.50 days 170.00 = 255/- 2. Mason concreting works 2.00 days 106.00 = 212.0/- 3. Male Mazdoor 9.000 days 140.00 = 1260.00/- 4. Female Mazdoor 12.000 days 120.00 = 1440.00/- 5. Waterman 1.500 days 110.00 = 165.00/- 6. Labour.Add 1.750 days 150.00 = 262.50/- Total of Labour : Rs. = 3594.50/- Grand Total Cost for 10.00 cu.mt : Rs. = 45269.49/- Unit Cost per cu.mt is: Rs. = 4526.94/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4526.94/-
Todays BUZZ Word General contractor- >he is responsible for>the day-to-day oversight of the construction site >management of vendors and trades. >He keeps the communication between the contractor and the other parties involved,open and clear through out the project >A subcontractor is an individual or business that signs a contract to perform part or all of the obligations of another\'s contract. >Types of subcontractor\'s Main 3 types- 1)Domestic type of subcontractor:he is a subcontractor who contracts with the main contractor to supply or fix any materials or goods or execute work forming part of the main contract. He is employed by the main contractor. 2)Nominated subcontractor 3)Named subcontractor Other type of contractor\'s are: *Roofing contractor *Electrical contractor *Insulation contractor *Architects *Painting contractor *Plumbing contractor *Carpenter contractor *Construction contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-03

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sangavi builder & devlopers
Students Name (Surname_First Name_Middle Name) Dalvi Yogesh Anant
Exam No. 10889
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9 AM
Site Leaving Time (HH:MM am/pm) 4 PM
Details of the Work Allotted to you today by the Site In-Charge Tilling Work/furniture…. .
Details of how you Planned & Executed the allotted work First we go on site & divided in two group first we see tiling work & take information from worker.then we see external plastering work.& take detal information also we see furniture work& get about detail information…. .
Details of the Construction Procedure / Activity / Technology learned today In tiling- first prepared base surface take sand & cement in proportion & laid on base in sutable layer ,on this surface Spread cement slurry & place vitrified tiles on this surface’ & applay blow on it by wooden rammer..
Details of the Construction Materials learned today Vertified tile,granite,kaddapa,alluminium window,bajari glass ,plain glass, .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Ecofriendly plywood are used for furniture work. .
Details of the Construction / Engineering Drawings observed today Furniture drawing Electrification drawing .
Details of the Bye Laws referred today Compound wall 2.4 M hight provide according to bylaws. .
Details of any Managerial Skill learned today We are meet different type of of contracter & they gave us brif information about his work projet & they co-oprete very well. .
RATE ANALYSIS (Detailed Stepwise Calculations required) M 20 concret 1 unit=1m3 Cement=6.90*255=1759.5 (rate per bag=255 & 6.90 no.of bag) Sand=0.035*1.5*6.90*44*35*28=562.327 Metal=0.035*3*6.90*18*35.28=460.08 Labour=40*35.48=1411 Steel=75*35=2625 Total=6817.00/m3
Result of RATE ANALYSIS ( Rs per Unit ) 6817Rs /m3
Todays BUZZ Word Buzz………… Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil 9890997979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558-03

Company Name Chougule Sawant Developers
Project Name & Site Address shree samarth nager, new balinga, kolhapur
Students Name (Surname_First Name_Middle Name) Chavan Shivprasad Prakash
Exam No. 13558
Working Day No. 03
Date (DD/MM/YYYY) 10.12.2010
Site Reporting Time (HH:MM am/pm) 9.10 am
Site Leaving Time (HH:MM am/pm) 4.15 pm
Details of the Work Allotted to you today by the Site In-Charge Todays alloted work was to observe casting of plinth beams, to see excavation procedure, to observe stripping of formwork,to observe batching,mixing,placing and compaction of concrete.
Details of how you Planned & Executed the allotted work First we saw detailed drawings of plinth beam,center line plans,test results of testing of concrete cubes. Then we had seen execution of work on site, site in charge had cleared out doubts.
Details of the Construction Procedure / Activity / Technology learned today A. Casting of plinth beam ; 1. All the reinforcement is placed in position and checked. 2. Formwork is placed as per dimensions of plinth beam and it is checked by site in charge. 3. Concreting is done. M 20 Grade is used.
Details of the Construction Materials learned today crushed sand ; this sand gives more stregnth than normal sand. it is made by crushing of stone n quarries. ply formwork ; plywood formwork is used . this gives perfect straight edges. we also learned about shinkanja,locking.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today SEWAGE TREATMENT PLANT ; There will be one treatment plant is installed. All the sewage is treated in this plant as reused for washing gardening.
Details of the Construction / Engineering Drawings observed today We had saw r.c.c. drawings of plinth beam, center line plans,detailed drwaings of 3 bhk row houses.
Details of the Bye Laws referred today Margines; side margine =2.25m front margine=4m rear margine =3m
Details of any Managerial Skill learned today We observe how site in charge was handeling labours and contractors to complete work speedily and with quality control.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. BEAM ; PER CU.M STEEL = 55 KG = 1925 RS CEMENT = 31 KG = 1280 RS METAL = 180 KG = 680 RS SAND = 120 KG = 380 RS LABOUR = 1550 RS TOTAL = 5815 + 2% WASTAGE = 6000.00 RS
Result of RATE ANALYSIS ( Rs per Unit ) 6000.00 RS PER CU.M
Todays BUZZ Word DIFFERENT TYPE OF CONTRACTORS AND THERE TYPES ; 1. Excavation contractor ; he carries out all the work related to excavation of project. 2. Centering contractor ; he execute works of shuttring,reinforcement,placing of formwork. 3.Concreting contractor ; he carries out all the work related to concreting as per specifications. 4. Electrification contractor who carries out electrical works. 5. Plumbing contractor ; he carries out all the plumbing works 6. Painting contractor who carries out all the painting works of project.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut. mo no.8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-03

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.03 p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge He allowed the work to see tileing work going in row bunglow C-8. -After visiting the row bunglow C-8 we seen all the tileing work with all details. - Milind Patil – Site incharge engineer He allowed the work to see external plastering work of D-8 row bunglow.
Details of how you Planned & Executed the allotted work First we divided into two groups. -alternately we visited both row bunglow no C-8 &D-8. We see all the tile work & external plastering work & internal POP finishing work & took all the details.
Details of the Construction Procedure / Activity / Technology learned today For Tiling- First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. For external plastering- -First mortar is prepared with proportion like 1-bag of cement & 12 pans of fine sand & water in proportion. -then mortar is taken into pans & applied to the surface. -then surface is planed with ‘reza’ -then if anywhere uniform level is not form then again mortar is apploed& finished.
Details of the Construction Materials learned today For tiling- Vetrified tile ,granite,kadappa. Vetrified tile 300Rs/- per box which contains 4 tiles. 1.46 sq.mtr. & nominal size of each tile is 605mm *605mm. Aluminium is used for sliding window. Sliding window fitting rate 120Rs/- per sq.ft. Powder coated window fitting rate 22Rs/- sq.ft. extra. - Plain and bazri glass is used for window. 18Rs/- bajri glass, 50Rs/- plane glass, one way glass 85 to 95 Rs/-, - Eco friendly plywood and sunmica
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Ecofriendly plywood is used for furniture work which reduces the deforestation
Details of the Construction / Engineering Drawings observed today Furniture and electrification plans. -Floor plans of proposed building (i.e. 2nd phase of sanghavi builders & developers)
Details of the Bye Laws referred today Compound wall 2.5m is provided which is according to the bye laws of Kolhapur.
Details of any Managerial Skill learned today We met various contractors . They gave us brief information about tender work & detail information of project site. They cooperated with us very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. Beam For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Steel 150 * 43 =6450 Rs./- Labour 40*35.28= 1411 Rs./- 10642.0 Rs./- per cub.m. Builders profit including Service tax,VAT etc VATetc 20% 10642* 1.20 = 12770 Rs./- This is according to the current rate of material and labour charges
Result of RATE ANALYSIS ( Rs per Unit ) 12770Rs./- per cub.m
Todays BUZZ Word Todays Buzz word “Contractors” Different types of Contractors are: Types of Contractors Name of contractor - plumbing contractor Dhavale - Painting Contractor - Plastering Contractor - POP finshing Contractor Nessar - Electrification Contractor Sachin More - Furniture Contractor - Fabrication Contractor Sawant - Glass work Contractor Subhash Mestri - Wi-fi Contractor Prashant More - Brick work Contractor - tilling Contractor - Gas Contractor Prasad Salvekar Scope of Contractors: Entire project work is divided into no. of departments like plumbing , Tiling,painting, electrificationetc. Therefore this dividation of work is done for better quality construction and fast rate of construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-03

Company Name Chougule Sawant Developers
Project Name & Site Address shree samarth nagar,fulewadi ringroad, near Balinga.
Students Name (Surname_First Name_Middle Name) Katral Raju Maruti.
Exam No. 13562
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) observation of cube test report. 2) observation of shuttering work for R.C.C. Beam, slab & plinth beam. 3) observation & checking of bar bending schedule. 4) observation of centering of column & footing.
Details of how you Planned & Executed the allotted work Before the lunch we observed cube test report as well as centering of column & footing. After the lunch we observed the bar bending scheduled & plinth beam.
Details of the Construction Procedure / Activity / Technology learned today They introduce the intrnet Wi-Fi system in their whole project.
Details of the Construction Materials learned today We learned that the algae proof liquid used for the joints of the beam & slab.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today For environmental caring they introduce the tree plantation in their whole project.
Details of the Construction / Engineering Drawings observed today we observed that the design drawing of plinth beam for apartment & footing drawing for 2.5 bhk bunglow.
Details of the Bye Laws referred today All the internal dimensions of the rooms of apartment are taking by reffering bye law, For e.g. Room minimum(sq.m.) maximum(sq.m) 1)living room 15 20 2) bed room 15 20 3) kitchen 12 16 4) toilet 2.1 2.5
Details of any Managerial Skill learned today we learn that how to divide the work in the systemetic pettern to do the work in the small time.
RATE ANALYSIS (Detailed Stepwise Calculations required) for R.C.C. Beam, material quantity(kg) Rate(Rs) 1) cement 310 1280 2) aggregate 180 680 3) sand 120 380 4) steel 55 1925 TOTAL = 4265 Rs. add a) 2% for wastage b) labor cost 1100 Rs. c) 10% for contractor\'s profit. Net TOTAL = 5895 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 5895 Rs./cu.m.
Todays BUZZ Word Types of contractor\'s 1) labor contractor - this contractor is done only following tasks a) R.C.C Work includes of beam, slab,column,footing etc. b) masonry & plastering work. 2) Tiling contractor- 3) Plastering contractor 4) Electrical contractor 5) Road contractor 6) Landscape contractor 7) Painting contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut Sir & Mob No.-8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-03

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) KOLEKAR SHYAM SURYAKANT
Exam No. 13533
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.00
Site Leaving Time (HH:MM am/pm) 4.00
Details of the Work Allotted to you today by the Site In-Charge To observe the details of one way slab, two way slab, cantilever, sunk slab, different sizes of beam. To inspect proportion of ingradients of concrete.
Details of how you Planned & Executed the allotted work By observing steel design drawing provided by structural engg. we checked all the details of various slab. Cantilever slab have alternate steel spring design. It does not have any supported columns. Then we distributed the work among ourself for checking mix proportion. one of us checked fine aggregete proportion, other one check coarse aggregate proportion & cement proportion.
Details of the Construction Procedure / Activity / Technology learned today Removal of form work according to curring of respective concrete structure; for slab = 7days (1 week) for plinth beam = 1day for bottom of beam= 21days (3 weeks)
Details of the Construction Materials learned today SHIKHANJA- It is used to fit form work. It is made up of cast iron. TRANSIT MIXER- It has speed of 16 r.p.m. It is used to mix concrete ingradients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of GUNNY BAGS instead of plastic bags for curring because plastic is not decomposed by invironment.
Details of the Construction / Engineering Drawings observed today ELEVATION DRAWING- Architect has provided good appearence to building, suitable balconies & windows. Attractive colour combination is done.
Details of the Bye Laws referred today Height of floor- min. 2.75m Cielling height for window- 0.9m Cielling height for ventiletor- 1.2m
Details of any Managerial Skill learned today Good time managment.
RATE ANALYSIS (Detailed Stepwise Calculations required) p.c.c (1:3:6) for 1cu.m volume, 1.52/(1+3+6)= 0.152 cu.m for cement = (0.152/0.035)*1= 4.34 say 5 bags 250*5= 1250Rs for sand = 0.152*3= 0.456 0.456*1060= 483.36Rs for aggregate = 0.152*6 = 0.912 0.912*600 = 547.2Rs for steel = 2448Rs Total amount = 1250+483.60+547.2+2448 = 4728Rs Add 15% contractors proffit total amount = 5437.2Rs say 5500Rs per cu.m
Result of RATE ANALYSIS ( Rs per Unit ) 5500Rs per cu.m
Todays BUZZ Word CONTRACTORS 1) Labour contractor- Provide all labours required for construction work. 2) Centring contractor- They construct all steel frameworks. 3) Plumbing contractors- Provide all types of plumbing & sanitory work. 4) Electrical contractors- Provide all electrification work. 5) Painting contractors- Provide painting of inner & outer surface of construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. MILIND MAGDUM mob.no.- 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-03

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.03 p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge He allowed the work to see tileing work going in row bunglow C-8. -After visiting the row bunglow C-8 we seen all the tileing work with all details. - Milind Patil – Site incharge engineer He allowed the work to see external plastering work of D-8 row bunglow.
Details of how you Planned & Executed the allotted work First we divided into two groups. -alternately we visited both row bunglow no C-8 &D-8. We see all the tile work & external plastering work & internal POP finishing work & took all the details.
Details of the Construction Procedure / Activity / Technology learned today For Tiling- First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. For external plastering- -First mortar is prepared with proportion like 1-bag of cement & 12 pans of fine sand & water in proportion. -then mortar is taken into pans & applied to the surface. -then surface is planed with ‘reza’ -then if anywhere uniform level is not form then again mortar is apploed& finished.
Details of the Construction Materials learned today For tiling- Vetrified tile ,granite,kadappa. Vetrified tile 300Rs/- per box which contains 4 tiles. 1.46 sq.mtr. & nominal size of each tile is 605mm *605mm. Aluminium is used for sliding window. Sliding window fitting rate 120Rs/- per sq.ft. Powder coated window fitting rate 22Rs/- sq.ft. extra. - Plain and bazri glass is used for window. 18Rs/- bajri glass, 50Rs/- plane glass, one way glass 85 to 95 Rs/-, - Eco friendly plywood and sunmica
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Ecofriendly plywood is used for furniture work which reduces the deforestation
Details of the Construction / Engineering Drawings observed today Furniture and electrification plans. -Floor plans of proposed building (i.e. 2nd phase of sanghavi builders & developers)
Details of the Bye Laws referred today Compound wall 2.5m is provided which is according to the bye laws of Kolhapur.
Details of any Managerial Skill learned today We met various contractors . They gave us brief information about tender work & detail information of project site. They cooperated with us very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. Beam For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Steel 150 * 43 =6450 Rs./- Labour 40*35.28= 1411 Rs./- 10642.0 Rs./- per cub.m. Builders profit including Service tax,VAT etc VATetc 20% 10642* 1.20 = 12770 Rs./- This is according to the current rate of material and labour charges
Result of RATE ANALYSIS ( Rs per Unit ) 12770Rs./- per cub.m
Todays BUZZ Word Todays Buzz word “Contractors” Different types of Contractors are: Types of Contractors Name of contractor - plumbing contractor Dhavale - Painting Contractor - Plastering Contractor - POP finshing Contractor Nessar - Electrification Contractor Sachin More - Furniture Contractor - Fabrication Contractor Sawant - Glass work Contractor Subhash Mestri - Wi-fi Contractor Prashant More - Brick work Contractor - tilling Contractor - Gas Contractor Prasad Salvekar Scope of Contractors: Entire project work is divided into no. of departments like plumbing , Tiling,painting, electrificationetc. Therefore this dividation of work is done for better quality construction and fast rate of construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: Rameshkharat1987@gmail.com
Subject: 13532-03

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) KHARAT RAMESH LAXMAN
Exam No. 13532
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.00
Site Leaving Time (HH:MM am/pm) 4.00
Details of the Work Allotted to you today by the Site In-Charge To observe the details of one way slab, two way slab, cantilever, sunk slab, different sizes of beam. To inspect proportion of ingradients of concrete.
Details of how you Planned & Executed the allotted work By observing steel design drawing provided by structural engg. we checked all the details of various slab. Cantilever slab have alternate steel spring design. It does not have any supported columns. Then we distributed the work among ourself for checking mix proportion. one of us checked fine aggregete proportion, other one check coarse aggregate proportion & cement proportion.
Details of the Construction Procedure / Activity / Technology learned today Removal of form work according to curring of respective concrete structure; for slab = 7days (1 week) for plinth beam = 1day for bottom of beam= 21days (3 weeks)
Details of the Construction Materials learned today SHIKHANJA- It is used to fit form work. It is made up of cast iron. TRANSIT MIXER- It has speed of 16 r.p.m. It is used to mix concrete ingradients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of GUNNY BAGS instead of plastic bags for curring because plastic is not decomposed by invironment.
Details of the Construction / Engineering Drawings observed today ELEVATION DRAWING- Architect has provided good appearence to building, suitable balconies & windows. Attractive colour combination is done.
Details of the Bye Laws referred today Height of floor- min. 2.75m Cielling height for window- 0.9m Cielling height for ventiletor- 1.2m
Details of any Managerial Skill learned today Good time managment.
RATE ANALYSIS (Detailed Stepwise Calculations required) p.c.c (1:3:6) for 1cu.m volume, 1.52/(1+3+6)= 0.152 cu.m for cement = (0.152/0.035)*1= 4.34 say 5 bags 250*5= 1250Rs for sand = 0.152*3= 0.456 0.456*1060= 483.36Rs for aggregate = 0.152*6 = 0.912 0.912*600 = 547.2Rs for steel = 2448Rs Total amount = 1250+483.60+547.2+2448 = 4728Rs Add 15% contractors proffit total amount = 5437.2Rs say 5500Rs per cu.m
Result of RATE ANALYSIS ( Rs per Unit ) 5500Rs per cu.m
Todays BUZZ Word CONTRACTORS 1) Labour contractor- Provide all labours required for construction work. 2) Centring contractor- They construct all steel frameworks. 3) Plumbing contractors- Provide all types of plumbing & sanitory work. 4) Electrical contractors- Provide all electrification work. 5) Painting contractors- Provide painting of inner & outer surface of construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. MILIND MAGDUM mob.no.- 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-03

Company Name Rajesh Constructions
Project Name & Site Address cloud 9
Students Name (Surname_First Name_Middle Name) PATIL VRISHALI VITHAL
Exam No. 13541
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.00
Site Leaving Time (HH:MM am/pm) 4.00
Details of the Work Allotted to you today by the Site In-Charge To observe the details of one way slab, two way slab, cantilever, sunk slab, different sizes of beam. To inspect proportion of ingradients of concrete.
Details of how you Planned & Executed the allotted work By observing steel design drawing provided by structural engg. we checked all the details of various slab. Cantilever slab have alternate steel spring design. It does not have any supported columns. Then we distributed the work among ourself for checking mix proportion. one of us checked fine aggregete proportion, other one check coarse aggregate proportion & cement proportion.
Details of the Construction Procedure / Activity / Technology learned today Removal of form work according to curring of respective concrete structure; for slab = 7days (1 week) for plinth beam = 1day for bottom of beam= 21days (3 weeks)
Details of the Construction Materials learned today SHIKHANJA- It is used to fit form work. It is made up of cast iron. TRANSIT MIXER- It has speed of 16 r.p.m. It is used to mix concrete ingradients.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of GUNNY BAGS instead of plastic bags for curring because plastic is not decomposed by invironment.
Details of the Construction / Engineering Drawings observed today ELEVATION DRAWING- Architect has provided good appearence to building, suitable balconies & windows. Attractive colour combination is done.
Details of the Bye Laws referred today Height of floor- min. 2.75m Cielling height for window- 0.9m Cielling height for ventiletor- 1.2m
Details of any Managerial Skill learned today Good time managment.
RATE ANALYSIS (Detailed Stepwise Calculations required) p.c.c (1:3:6) for 1cu.m volume, 1.52/(1+3+6)= 0.152 cu.m for cement = (0.152/0.035)*1= 4.34 say 5 bags 250*5= 1250Rs for sand = 0.152*3= 0.456 0.456*1060= 483.36Rs for aggregate = 0.152*6 = 0.912 0.912*600 = 547.2Rs for steel = 2448Rs Total amount = 1250+483.60+547.2+2448 = 4728Rs Add 15% contractors proffit total amount = 5437.2Rs say 5500Rs per cu.m
Result of RATE ANALYSIS ( Rs per Unit ) 5500Rs per cu.m
Todays BUZZ Word CONTRACTORS 1) Labour contractor- Provide all labours required for construction work. 2) Centring contractor- They construct all steel frameworks. 3) Plumbing contractors- Provide all types of plumbing & sanitory work. 4) Electrical contractors- Provide all electrification work. 5) Painting contractors- Provide painting of inner & outer surface of construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. MILIND MAGDUM mob.no.- 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-03

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Desai Akshay Prakash
Exam No. 10890
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.03 p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge He allowed the work to see tileing work going in row bunglow C-8. -After visiting the row bunglow C-8 we seen all the tileing work with all details. - Milind Patil – Site incharge engineer He allowed the work to see external plastering work of D-8 row bunglow.
Details of how you Planned & Executed the allotted work First we divided into two groups. -alternately we visited both row bunglow no C-8 &D-8. We see all the tile work & external plastering work & internal POP finishing work & took all the details.
Details of the Construction Procedure / Activity / Technology learned today For Tiling- First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. For external plastering- -First mortar is prepared with proportion like 1-bag of cement & 12 pans of fine sand & water in proportion. -then mortar is taken into pans & applied to the surface. -then surface is planed with ‘reza’ -then if anywhere uniform level is not form then again mortar is apploed& finished.
Details of the Construction Materials learned today For tiling- Vetrified tile ,granite,kadappa. Vetrified tile 300Rs/- per box which contains 4 tiles. 1.46 sq.mtr. & nominal size of each tile is 605mm *605mm. Aluminium is used for sliding window. Sliding window fitting rate 120Rs/- per sq.ft. Powder coated window fitting rate 22Rs/- sq.ft. extra. - Plain and bazri glass is used for window. 18Rs/- bajri glass, 50Rs/- plane glass, one way glass 85 to 95 Rs/-, - Eco friendly plywood and sunmica
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Ecofriendly plywood is used for furniture work which reduces the deforestation
Details of the Construction / Engineering Drawings observed today Furniture and electrification plans. -Floor plans of proposed building (i.e. 2nd phase of sanghavi builders & developers)
Details of the Bye Laws referred today Compound wall 2.5m is provided which is according to the bye laws of Kolhapur.
Details of any Managerial Skill learned today We met various contractors . They gave us brief information about tender work & detail information of project site. They cooperated with us very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. Beam For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Steel 150 * 43 =6450 Rs./- Labour 40*35.28= 1411 Rs./- 10642.0 Rs./- per cub.m. Builders profit including Service tax,VAT etc VATetc 20% 10642* 1.20 = 12770 Rs./- This is according to the current rate of material and labour charges
Result of RATE ANALYSIS ( Rs per Unit ) 12770Rs./- per cub.m
Todays BUZZ Word Todays Buzz word “Contractors” Different types of Contractors are: Types of Contractors Name of contractor - plumbing contractor Dhavale - Painting Contractor - Plastering Contractor - POP finshing Contractor Nessar - Electrification Contractor Sachin More - Furniture Contractor - Fabrication Contractor Sawant - Glass work Contractor Subhash Mestri - Wi-fi Contractor Prashant More - Brick work Contractor - tilling Contractor - Gas Contractor Prasad Salvekar Scope of Contractors: Entire project work is divided into no. of departments like plumbing , Tiling,painting, electrificationetc. Therefore this dividation of work is done for better quality construction and fast rate of construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-03

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bauchakar Deepak Yuvraj
Exam No. 13554
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:45pm
Details of the Work Allotted to you today by the Site In-Charge - Told us to find the no. of bricks required quantity of sand , Cement etc and thus find the amount required for contruction of wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today - We learnt about the Rebaring of beams. 1)First holes of 7\" are drilled by using drilling machine. 2)Than a solution of Adhesoin known as \"GERMAN FISHER CHEMICALS\" was appilied in the hole.
Details of the Construction Materials learned today - Adhesion material known as \"GERMAN FISHER CHEMICAL\" - Quantity of tube avaliable is 345ml of cost 1150/- per tube.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today - For the purpose of Rebaring we observed the structural design(SLAB) of that particular floor.
Details of the Bye Laws referred today - loft - lintel.
Details of any Managerial Skill learned today 1) Brickwork 2) Lintels 3) Lofts
RATE ANALYSIS (Detailed Stepwise Calculations required) Size of Beam = 11\'*9\"*6\" Total volume of the Beam = 5.94 cu.ft Matreial Required. 1. Cement = 2 Bags 2. Sand = 4.1 cu.ft 3. Aggregate = 4.25 cu.ft 4. Steel= 20kg 5. Labour charge = 500/- Total= 2406/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 406
Todays BUZZ Word \"CONTRACTORS\" 1.Centering contractor 2. Labour contractor 3. Material supply contractor. 4.Plumbing contractor 5. Water-proofing contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-03

Company Name Rajesh Constructions
Project Name & Site Address Cloud-9,Nagala Park
Students Name (Surname_First Name_Middle Name) Lad Manoj Sadashiv
Exam No. 13534
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 8:55am
Site Leaving Time (HH:MM am/pm) 4:10pm
Details of the Work Allotted to you today by the Site In-Charge To observe details of one-way and two-way slab,cantilever and sunk slab and different sizes of beam Inspection of praportion of concrete ingradient
Details of how you Planned & Executed the allotted work By viewing the steel design drawing provided by structural engineer. We check the all details of various slab. Cantilever slab have alternate spring steel design. Cantiliver slab have has not supported the beams or column. We distributed the work among ourselves for checking mix proportion.one of us checked fine agg. and other checked coarse agg. and cement.
Details of the Construction Procedure / Activity / Technology learned today Removal of formwork allowing to the curing of period of structural member. slab - 7 days plinth beam - 1 day bottom of beam - 21 days
Details of the Construction Materials learned today SHIKANJA - To fit the formwork. It is made up of cast iron. TRANSIT MIXER - Having speed 16 r.p.m.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today We gunny bags insted of plastic bags because plastic is not decompose by environment.
Details of the Construction / Engineering Drawings observed today Elevation drawing- side elevation and rear elevation ornamental view architect provide good appearance of the building. alternative colouring is done.
Details of the Bye Laws referred today Height of floor - 2.75 m ( min.) Sill height - 0.9 m (min.)
Details of any Managerial Skill learned today Good time management.
RATE ANALYSIS (Detailed Stepwise Calculations required) MIX PROPORTION 1:3:6 Volume = 1.00 m3 dry volume increses 52% = 1.52/(1+3+6) = 0.152 m3 Cement = (1.52 / 0.035) x 1 = 4.34 say 5 bags.x 250 = 1250/- Sand = 0.152 x 3 = 0.456 m3 x 1060 = 483.36/- Aggregate = 0.152 x 6 = 0.912 m3 x 600 = 547.20/- Steel- * stirrups = 34 x 9 = 306 /- * Top bars = 2 x 34 x 3.075 = 252/- * Bottom bars = 2 x 34 x 4.73 = 320/- * total steel budget = 878/- TOTAL AMOUNT = 1250 + 483.50 + 547.20 + 878.00 = 3198.00/- RS.
Result of RATE ANALYSIS ( Rs per Unit ) 3200.00 /- per cumec.
Todays BUZZ Word CONTRACTORS: Centering contractor - all types of frame work ( slab, column, lintel, beam ) Labour contractor - provide mason and mestri on site Plumbing contractor - all types of sanitary and plumbing works. Painting & electrical contractor - all finishing works and light connection fronm transformer
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Milind Magdum mob no. - 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-03

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bhoite Vishal Rajaram
Exam No. 13555
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 4:45pm
Details of the Work Allotted to you today by the Site In-Charge - Told us to find the no. of bricks required quantity of sand , Cement etc and thus find the amount required for contruction of wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today - We learnt about the Rebaring of beams. 1)First holes of 7\" are drilled by using drilling machine. 2)Than a solution of Adhesoin known as \"GERMAN FISHER CHEMICALS\" was appilied in the hole. 3)Than steel bars of 12mm were hammered and thus rebarring was done.
Details of the Construction Materials learned today - Adhesion material known as \"GERMAN FISHER CHEMICAL\" - Quantity of tube avaliable is 345ml of cost 1150/- per tube.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today - For the purpose of Rebaring we observed the structural design(SLAB) of that particular floor.
Details of the Bye Laws referred today About loft - lintel.
Details of any Managerial Skill learned today 1) Brickwork 2) Lintels 3) Lofts
RATE ANALYSIS (Detailed Stepwise Calculations required) Size of Beam = 11\'*9\"*6\" Total volume of the Beam = 5.94 cu.ft Matreial Required. 1. Cement = 2 Bags 2. Sand = 4.1 cu.ft 3. Aggregate = 4.25 cu.ft 4. Steel= 20kg 5. Labour charge = 500/- Total= 2406/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 406
Todays BUZZ Word \"CONTRACTORS\" 1.Centering contractor 2. Labour contractor 3. Material supply contractor. 4.Plumbing contractor 5. Water-proofing contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-03

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.03 p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge He allowed the work to see tileing work going in row bunglow C-8. -After visiting the row bunglow C-8 we seen all the tileing work with all details. - Milind Patil – Site incharge engineer He allowed the work to see external plastering work of D-8 row bunglow.
Details of how you Planned & Executed the allotted work First we divided into two groups. -alternately we visited both row bunglow no C-8 &D-8. We see all the tile work & external plastering work & internal POP finishing work & took all the details.
Details of the Construction Procedure / Activity / Technology learned today For Tiling- First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. For external plastering- -First mortar is prepared with proportion like 1-bag of cement & 12 pans of fine sand & water in proportion. -then mortar is taken into pans & applied to the surface. -then surface is planed with ‘reza’ -then if anywhere uniform level is not form then again mortar is apploed& finished.
Details of the Construction Materials learned today For tiling- Vetrified tile ,granite,kadappa. Vetrified tile 300Rs/- per box which contains 4 tiles. 1.46 sq.mtr. & nominal size of each tile is 605mm *605mm. Aluminium is used for sliding window. Sliding window fitting rate 120Rs/- per sq.ft. Powder coated window fitting rate 22Rs/- sq.ft. extra. - Plain and bazri glass is used for window. 18Rs/- bajri glass, 50Rs/- plane glass, one way glass 85 to 95 Rs/-, - Eco friendly plywood and sunmica
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Ecofriendly plywood is used for furniture work which reduces the deforestation
Details of the Construction / Engineering Drawings observed today Furniture and electrification plans. -Floor plans of proposed building (i.e. 2nd phase of sanghavi builders & developers)
Details of the Bye Laws referred today Compound wall 2.5m is provided which is according to the bye laws of Kolhapur.
Details of any Managerial Skill learned today We met various contractors . They gave us brief information about tender work & detail information of project site. They cooperated with us very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. Beam For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Steel 150 * 43 =6450 Rs./- Labour 40*35.28= 1411 Rs./- 10642.0 Rs./- per cub.m. Builders profit including Service tax,VAT etc VATetc 20% 10642* 1.20 = 12770 Rs./- This is according to the current rate of material and labour charges
Result of RATE ANALYSIS ( Rs per Unit ) 12770Rs./- per cub.m
Todays BUZZ Word Todays Buzz word “Contractors” Different types of Contractors are: Types of Contractors Name of contractor - plumbing contractor Dhavale - Painting Contractor - Plastering Contractor - POP finshing Contractor Nessar - Electrification Contractor Sachin More - Furniture Contractor - Fabrication Contractor Sawant - Glass work Contractor Subhash Mestri - Wi-fi Contractor Prashant More - Brick work Contractor - tilling Contractor - Gas Contractor Prasad Salvekar Scope of Contractors: Entire project work is divided into no. of departments like plumbing , Tiling,painting, electrificationetc. Therefore this dividation of work is done for better quality construction and fast rate of construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-03

Company Name Sanghavi Sons & Constructions
Project Name & Site Address sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Students Name (Surname_First Name_Middle Name) Mohite Nitish Arun
Exam No. 13537
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00 a.m.
Site Leaving Time (HH:MM am/pm) 4.03 p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge He allowed the work to see tileing work going in row bunglow C-8. -After visiting the row bunglow C-8 we seen all the tileing work with all details. - Milind Patil – Site incharge engineer He allowed the work to see external plastering work of D-8 row bunglow.
Details of how you Planned & Executed the allotted work First we divided into two groups. -alternately we visited both row bunglow no C-8 &D-8. We see all the tile work & external plastering work & internal POP finishing work & took all the details.
Details of the Construction Procedure / Activity / Technology learned today For Tiling- First they prepared base surface for tiling. -in this moist sand is spread on the surface with uniform level. -Then cement slurry is applied over it. -then tile is fitted over the prepared surface. -if there is any corner then the tile is cutted according to size & is fitted. -then for fixing purpose blows are given to the tiles with the help of wooden rod. For external plastering- -First mortar is prepared with proportion like 1-bag of cement & 12 pans of fine sand & water in proportion. -then mortar is taken into pans & applied to the surface. -then surface is planed with ‘reza’ -then if anywhere uniform level is not form then again mortar is apploed& finished.
Details of the Construction Materials learned today For tiling- Vetrified tile ,granite,kadappa. Vetrified tile 300Rs/- per box which contains 4 tiles. 1.46 sq.mtr. & nominal size of each tile is 605mm *605mm. Aluminium is used for sliding window. Sliding window fitting rate 120Rs/- per sq.ft. Powder coated window fitting rate 22Rs/- sq.ft. extra. - Plain and bazri glass is used for window. 18Rs/- bajri glass, 50Rs/- plane glass, one way glass 85 to 95 Rs/-, - Eco friendly plywood and sunmica
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Ecofriendly plywood is used for furniture work which reduces the deforestation
Details of the Construction / Engineering Drawings observed today Furniture and electrification plans. -Floor plans of proposed building (i.e. 2nd phase of sanghavi builders & developers)
Details of the Bye Laws referred today Compound wall 2.5m is provided which is according to the bye laws of Kolhapur.
Details of any Managerial Skill learned today We met various contractors . They gave us brief information about tender work & detail information of project site. They cooperated with us very well.
RATE ANALYSIS (Detailed Stepwise Calculations required) R.C.C. Beam For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Steel 150 * 43 =6450 Rs./- Labour 40*35.28= 1411 Rs./- 10642.0 Rs./- per cub.m. Builders profit including Service tax,VAT etc VATetc 20% 10642* 1.20 = 12770 Rs./- This is according to the current rate of material and labour charges
Result of RATE ANALYSIS ( Rs per Unit ) 12770Rs./- per cub.m
Todays BUZZ Word Todays Buzz word “Contractors” Different types of Contractors are: Types of Contractors Name of contractor - plumbing contractor Dhavale - Painting Contractor - Plastering Contractor - POP finshing Contractor Nessar - Electrification Contractor Sachin More - Furniture Contractor - Fabrication Contractor Sawant - Glass work Contractor Subhash Mestri - Wi-fi Contractor Prashant More - Brick work Contractor - tilling Contractor - Gas Contractor Prasad Salvekar Scope of Contractors: Entire project work is divided into no. of departments like plumbing , Tiling,painting, electrificationetc. Therefore this dividation of work is done for better quality construction and fast rate of construction.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-03

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SALOKHE SUDARSHAN ANIL
Exam No. 13544
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge TO Check the electrification details of the various types of flats.
Details of how you Planned & Executed the allotted work we first collected the electrification drawings from the site supervisor and after that throughly studied those drawings.we went to the flats and having the drawing of that floor.then with help of the wireman we collected the information.
Details of the Construction Procedure / Activity / Technology learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of the Construction Materials learned today About the pipe material used for conduit wiring. steel boxes/switch board materials. various types of wires according to their power capacity and switch board types according to the no. of points connected to that. fan box in concealed wiring.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater is utilised for ground water recharging through the soak pits. utilisation of crushed sand instead of natural sand.
Details of the Construction / Engineering Drawings observed today Detailed drawings of electrification according to the flats.
Details of the Bye Laws referred today height of the door, opening area for the windows, ventilation (artificial/natural).
Details of any Managerial Skill learned today Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BEAM PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 Cu.m ADDITION FOR DRY VOLUME: 52% VOLUME BECOMES: 1.52 CU.M CEMENT 1.52/1+1.5+3=0.2763 CU.M NUMBER OF CEMENT BAGS REQUIRED: 0.2763/0.035=7.89=8 BAGS COST= (8X260)=2080 Rs SAND: 0.2763X1.5=0.4144 CU.M COST=(0.4144X742.04)=307.50 Rs AGGREGATE: 0.2763 X 3=0.8289 CU.M COST = (0.8289 X 636.04)=527.21 Rs TOTAL COST OF MATERIAL: 2080+307.50+527.21 =2914.71 Rs REINFORCEMENT/STEEL COST 92 Kg/cu.m x 32 = 2944 Rs LABOUR CHARGES: PERSON NO. RATE 1) MISTRI: 1/2 125 Rs 2) MASON : 2 2 X 250 =500 Rs 3) BOY/WOMAN COOLIE: 2 2 X 140 = 280 Rs TOTAL LABOUR COST: =905 RS WATER: 1.5 % 2914.71 X (1.5/100)=41.30 Rs CENTERING AND SHUTTERING: TIMBER PLANKS: LUMP-SUMP 65 RS CARPENTER: 1 150 RS MAZDOOR: 1 80 RS TOTAL COST = 300 RS TOTAL COST OF WORK : 7104.3 RS CONTRACTORS PROFIT: 15 % = 1.15 X 7104.3 = 8169.94 RS CONTRACTORS PROFIT: 15 %
Result of RATE ANALYSIS ( Rs per Unit ) 8169.94 Rs/cu.m
Todays BUZZ Word DIFFERENT TYPES OF CONTRACTOR REQUIRED ARE AS FOLLOWS: Contractor means the person who provide workers to do their particular work and take whole responsibility for that particular work until the completion. 1)R.C.C. -it is the actual construction work related to concrete ,steel and no. of persons required for that construction. 2)plumbing- To provide the various type of drainage facilities and water supply required to fulfill the requirement of the various units of the buildings such as for sink, toilet , bathrooms,utility. 3) electrification- to provide electric fittings required for the buildings. 4)carpenter- do the work related to the wood work such as doors, furnitures, windows frames. 5)tile fitter- to provide floorings and dado work in all the rooms , toilet,kitchen,balcony in the surrounding of buildings also. 6) centering- the work of the contractor is to provide the support/ formwork required before doing further work of steel and concreting. 7)mason- to provide the no. of masons required for doing the work. 8)mild steel contractor- provides only steel required for the windows grills ,safety doors,railings , gate. 9)painter- to give the final finishing to the building for decorative purposes and to apply the wall putty also. 10)aluminium works for windows- to provide the glass windows.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. RAJESH CHOUGALE 9822502199
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-03

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER, PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SHAIKH RIZWAN KHALIL
Exam No. 13545
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge TO Check the electrification details of the various types of flats.
Details of how you Planned & Executed the allotted work we first collected the electrification drawings from the site supervisor and after that throughly studied those drawings.we went to the flats and having the drawing of that floor.then with help of the wireman we collected the information.
Details of the Construction Procedure / Activity / Technology learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of the Construction Materials learned today About the pipe material used for conduit wiring. steel boxes/switch board materials. various types of wires according to their power capacity and switch board types according to the no. of points connected to that. fan box in concealed wiring.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater is utilised for ground water recharging through the soak pits. utilisation of crushed sand instead of natural sand.
Details of the Construction / Engineering Drawings observed today Detailed drawings of electrification according to the flats.
Details of the Bye Laws referred today height of the door, opening area for the windows, ventilation (artificial/natural).
Details of any Managerial Skill learned today Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BEAM PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 Cu.m ADDITION FOR DRY VOLUME: 52% VOLUME BECOMES: 1.52 CU.M CEMENT 1.52/1+1.5+3=0.2763 CU.M NUMBER OF CEMENT BAGS REQUIRED: 0.2763/0.035=7.89=8 BAGS COST= (8X260)=2080 Rs SAND: 0.2763X1.5=0.4144 CU.M COST=(0.4144X742.04)=307.50 Rs AGGREGATE: 0.2763 X 3=0.8289 CU.M COST = (0.8289 X 636.04)=527.21 Rs TOTAL COST OF MATERIAL: 2080+307.50+527.21 =2914.71 Rs REINFORCEMENT/STEEL COST 92 Kg/cu.m x 32 = 2944 Rs LABOUR CHARGES: PERSON NO. RATE 1) MISTRI: 1/2 125 Rs 2) MASON : 2 2 X 250 =500 Rs 3) BOY/WOMAN COOLIE: 2 2 X 140 = 280 Rs TOTAL LABOUR COST: =905 RS WATER: 1.5 % 2914.71 X (1.5/100)=41.30 Rs CENTERING AND SHUTTERING: TIMBER PLANKS: LUMP-SUMP 65 RS CARPENTER: 1 150 RS MAZDOOR: 1 80 RS TOTAL COST = 300 RS TOTAL COST OF WORK : 7104.3 RS CONTRACTORS PROFIT: 15 % = 1.15 X 7104.3 = 8169.94 RS CONTRACTORS PROFIT: 15 %
Result of RATE ANALYSIS ( Rs per Unit ) 8169.94 Rs/cu.m
Todays BUZZ Word DIFFERENT TYPES OF CONTRACTOR REQUIRED ARE AS FOLLOWS: Contractor means the person who provide workers to do their particular work and take whole responsibility for that particular work until the completion. 1)R.C.C. -it is the actual construction work related to concrete ,steel and no. of persons required for that construction. 2)plumbing- To provide the various type of drainage facilities and water supply required to fulfill the requirement of the various units of the buildings such as for sink, toilet , bathrooms,utility. 3) electrification- to provide electric fittings required for the buildings. 4)carpenter- do the work related to the wood work such as doors, furnitures, windows frames. 5)tile fitter- to provide floorings and dado work in all the rooms , toilet,kitchen,balcony in the surrounding of buildings also. 6) centering- the work of the contractor is to provide the support/ formwork required before doing further work of steel and concreting. 7)mason- to provide the no. of masons required for doing the work. 8)mild steel contractor- provides only steel required for the windows grills ,safety doors,railings , gate. 9)painter- to give the final finishing to the building for decorative purposes and to apply the wall putty also. 10)aluminium works for windows- to provide the glass windows.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. RAJESH CHOUGALE 9822502199
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-03

Company Name Deshmukh Developers
Project Name & Site Address GOLDEN SHELTER , PRATIBHA NAGAR
Students Name (Surname_First Name_Middle Name) SINGH RAJAN RAJENDRA BAHADUR
Exam No. 13538
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9 am
Site Leaving Time (HH:MM am/pm) 4 pm
Details of the Work Allotted to you today by the Site In-Charge TO Check the electrification details of the various types of flats.
Details of how you Planned & Executed the allotted work we first collected the electrification drawings from the site supervisor and after that throughly studied those drawings.we went to the flats and having the drawing of that floor.then with help of the wireman we collected the information.
Details of the Construction Procedure / Activity / Technology learned today first the supply is taken from the MSEB then it is given to the transformer then to the meter unit provided at the ground floor-from this ducts are provided to bring those wires to the main circuit board in the flat. then from this supply is given to the all the rooms separately to the boards provided in the rooms and from board to the equipments. such as fans, tube, bulb requires 5 amp board and mixers required 15 amp board according to their capacity of load. wires of the various thickness are used depend upon the current carrying capacity.
Details of the Construction Materials learned today About the pipe material used for conduit wiring. steel boxes/switch board materials. various types of wires according to their power capacity and switch board types according to the no. of points connected to that. fan box in concealed wiring.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater is utilised for ground water recharging through the soak pits. utilisation of crushed sand instead of natural sand.
Details of the Construction / Engineering Drawings observed today Detailed drawings of electrification according to the flats.
Details of the Bye Laws referred today height of the door, opening area for the windows, ventilation (artificial/natural).
Details of any Managerial Skill learned today Good co-ordination is required between the site supervisor and the Engineer progress and quality of the work depend on that.
RATE ANALYSIS (Detailed Stepwise Calculations required) RATE ANALYSIS FOR BEAM PROPORTION USED: 1:1.5:3 VOLUME TO BE MADE: 1 Cu.m ADDITION FOR DRY VOLUME: 52% VOLUME BECOMES: 1.52 CU.M CEMENT 1.52/1+1.5+3=0.2763 CU.M NUMBER OF CEMENT BAGS REQUIRED: 0.2763/0.035=7.89=8 BAGS COST= (8X260)=2080 Rs SAND: 0.2763X1.5=0.4144 CU.M COST=(0.4144X742.04)=307.50 Rs AGGREGATE: 0.2763 X 3=0.8289 CU.M COST = (0.8289 X 636.04)=527.21 Rs TOTAL COST OF MATERIAL: 2080+307.50+527.21 =2914.71 Rs REINFORCEMENT/STEEL COST 92 Kg/cu.m x 32 = 2944 Rs LABOUR CHARGES: PERSON NO. RATE 1) MISTRI: 1/2 125 Rs 2) MASON : 2 2 X 250 =500 Rs 3) BOY/WOMAN COOLIE: 2 2 X 140 = 280 Rs TOTAL LABOUR COST: =905 RS WATER: 1.5 % 2914.71 X (1.5/100)=41.30 Rs CENTERING AND SHUTTERING: TIMBER PLANKS: LUMP-SUMP 65 RS CARPENTER: 1 150 RS MAZDOOR: 1 80 RS TOTAL COST = 300 RS TOTAL COST OF WORK : 7104.3 RS CONTRACTORS PROFIT: 15 % = 1.15 X 7104.3 = 8169.94 RS CONTRACTORS PROFIT: 15 %
Result of RATE ANALYSIS ( Rs per Unit ) 8169.94 Rs/cu.m
Todays BUZZ Word DIFFERENT TYPES OF CONTRACTOR REQUIRED ARE AS FOLLOWS: Contractor means the person who provide workers to do their particular work and take whole responsibility for that particular work until the completion. 1)R.C.C. -it is the actual construction work related to concrete ,steel and no. of persons required for that construction. 2)plumbing- To provide the various type of drainage facilities and water supply required to fulfill the requirement of the various units of the buildings such as for sink, toilet , bathrooms,utility. 3) electrification- to provide electric fittings required for the buildings. 4)carpenter- do the work related to the wood work such as doors, furnitures, windows frames. 5)tile fitter- to provide floorings and dado work in all the rooms , toilet,kitchen,balcony in the surrounding of buildings also. 6) centering- the work of the contractor is to provide the support/ formwork required before doing further work of steel and concreting. 7)mason- to provide the no. of masons required for doing the work. 8)mild steel contractor- provides only steel required for the windows grills ,safety doors,railings , gate. 9)painter- to give the final finishing to the building for decorative purposes and to apply the wall putty also. 10)aluminium works for windows- to provide the glass windows.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. RAJESH CHOUGALE 9822502199
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-03

Company Name S. S. Developers & Builders
Project Name & Site Address bluebell near kadam wadi
Students Name (Surname_First Name_Middle Name) rathod sunil ram
Exam No. 10881
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) to checking the dimensions of beam 2) to checking the dimensions of rcc.septic tank 3) checking how to apply paint on internal wall
Details of how you Planned & Executed the allotted work 1) we seen painting in that first they apply primer on the putty. then finish the wall or rubbed by ghissi. for smooth surface 2) then apply oil paint of one coat on the wall by roller 3) after that the final coat apply 4) then we measure the dimenation of septic tank 5) for beam dimenation we go through by plan sheet
Details of the Construction Procedure / Activity / Technology learned today 1) for apply paint on the wall used rollers consist of long pipe for oprating 2) used steel formwrk except wood material by safety of labour and long time durability
Details of the Construction Materials learned today 1) protect admixture used for casting the rcc beam of septic tank 2) used s.s. fastenings for doors and windows and kitchen trowly
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1) the wastage from the building collact outside arrangment space. for clean and healthy life
Details of the Construction / Engineering Drawings observed today 1) we seen the drawing of beam in main building plan . their are many different sizes of beams are provided
Details of the Bye Laws referred today 1) the minimum cler height of canopy be 2.2m 2) for fire protection requirements . the open space on all side up to 6m
Details of any Managerial Skill learned today we learn,how to love our work from the benifits is we learn all in short time
RATE ANALYSIS (Detailed Stepwise Calculations required) r.c.c. beam material quantity(kg) rate(rs) 1) cement 310 1281 2) aggregats 180 680 3) sand 120 380 4) steel 55 1925 total= 4265 Rs a) 2% for wastage b) labour cost =1100 rs c) 10% for contractors profit net total =5936 rs
Result of RATE ANALYSIS ( Rs per Unit ) 5936 rs
Todays BUZZ Word their are many contractor for 1) masonary 2) centring 3) plumbing 4) labour a) labour insurance are by contractor b) contractors getting work in lumsum of m3
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge KETAN CHARPALE MOB NO : 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-02

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bauchakar Deepak Yuvraj
Exam No. 13554
Working Day No. 02
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 04:45pm
Details of the Work Allotted to you today by the Site In-Charge - Told us to find the no. of bricks required quantity of sand , Cement etc and thus find the amount required for contruction of wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today We learnt about the Rebaring of beams. 1)First holes of 7\" are drilled by using drilling machine. 2)Than a solution of Adhesoin known as \"GERMAN FISHER CHEMICALS\" was appilied in the hole. 3)Than steel bars of 12mm were hammered and thus rebarring was done.
Details of the Construction Materials learned today - Adhesion material known as \"GERMAN FISHER CHEMICAL\" - Quantity of tube avaliable is 345ml of cost 1150/- per tube.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today - For the purpose of Rebaring we observed the structural design(SLAB) of that particular floor.
Details of the Bye Laws referred today - About loft - lintel.
Details of any Managerial Skill learned today 1) Brickwork 2) Lintels 3) Lofts
RATE ANALYSIS (Detailed Stepwise Calculations required) Size of Beam = 11\'*9\"*6\" Total volume of the Beam = 5.94 cu.ft Matreial Required. 1. Cement = 2 Bags 2. Sand = 4.1 cu.ft 3. Aggregate = 4.25 cu.ft 4. Steel= 20kg 5. Labour charge = 500/- Total= 2406/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 406
Todays BUZZ Word \"CONTRACTORS\" 1.Centering contractor 2. Labour contractor 3. Material supply contractor. 4.Plumbing contractor 5. Water-proofing contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-02

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Bhoite Vishal Rajaram
Exam No. 13555
Working Day No. 02
Date (DD/MM/YYYY) 10/12/2010.
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 04:45pm
Details of the Work Allotted to you today by the Site In-Charge - Told us to find the no. of bricks required quantity of sand , Cement etc and thus find the amount required for contruction of wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today - We learnt about the Rebaring of beams. 1)First holes of 7\" are drilled by using drilling machine. 2)Than a solution of Adhesoin known as \"GERMAN FISHER CHEMICALS\" was appilied in the hole. 3)Than steel bars of 12mm were hammered and thus rebarring was done.
Details of the Construction Materials learned today - Adhesion material known as \"GERMAN FISHER CHEMICAL\" - Quantity of tube avaliable is 345ml of cost 1150/- per tube.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today - For the purpose of Rebaring we observed the structural design(SLAB) of that particular floor.
Details of the Bye Laws referred today - About loft - lintel.
Details of any Managerial Skill learned today 1) Brickwork 2) Lintels 3) Lofts
RATE ANALYSIS (Detailed Stepwise Calculations required) Size of Beam = 11\'*9\"*6\" Total volume of the Beam = 5.94 cu.ft Matreial Required. 1. Cement = 2 Bags 2. Sand = 4.1 cu.ft 3. Aggregate = 4.25 cu.ft 4. Steel= 20kg 5. Labour charge = 500/- Total= 2406/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 406
Todays BUZZ Word \"CONTRACTORS\" 1.Centering contractor 2. Labour contractor 3. Material supply contractor. 4.Plumbing contractor 5. Water-proofing contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: shinde_shital7@yahoo.com
Subject: 10884-03

Company Name S. S. Developers & Builders
Project Name & Site Address BLUEBELL CIRCUITHOUSE KOLHAPUR
Students Name (Surname_First Name_Middle Name) shinde shital vilasrao
Exam No. 10884
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge OBSERVE THE PAINTING WORK.
Details of how you Planned & Executed the allotted work WE HAVE PLAN TAKE DIMENSION OF SEPTIC TANK. THREE BLOCK OF SEPTIC TANK. LENGTH=2.1M,WIDTH=3M,DEPTH=2M.
Details of the Construction Procedure / Activity / Technology learned today WE LEARNED HOW TO ADD ADMIXTURE(L.W.S &S.B.R) IN THE MASONRY. AND HOW TO PAINT THE WALL BY ROLLERS.
Details of the Construction Materials learned today WE LEARNED THAT FOR BETTER APPEARANCE USE POWER COATED ALUMINIUM SLIDING DOOR.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today ENVIRONMENT CARING TECHNOLOGY USED SOLAR PANEL .FOR PARKING LIGHT PURPOSE.
Details of the Construction / Engineering Drawings observed today WE OBSERVED ENGINEERING DRAWING OF R.C.C BEAM.
Details of the Bye Laws referred today WE REFERRED BYE-LAWS REGARDING SEPTIC TANK.
Details of any Managerial Skill learned today THERE IS BIG DIFFERENCE BETWEEN TO SPEAK US &TO SPEAK LABOUR .AND THEY USE ROUGH LANGUAGE WHILE SPEAKING LABOURS &THEY SPEAK US WITH POLITE.
RATE ANALYSIS (Detailed Stepwise Calculations required) SIZE OF BEAM 450*150*3000 CONCRETE 1:1.5:3 1cu.m =1.52=0.152% 1) cement=1.52/(1+1.5+3)=0.277 No. of bags =0.277/0.035=7.918 bags =8*260=2080 Rs 2) sand=0.152*1.5=0.288 . . =0.288*725=165Rs 3) aggregate0.152*3=0.456 0.456*450=205Rs Total cost of concrete =2080+165+205+125+200+80=2855Rs 4) Steel cost weight of 12 mm diameter bar 886.15gm,for 3 m=2.66kg, 2No.bar =159.6Rs weight of 10mm diameter bar0.615kg,for 3m=1.84kg, 2NO. OF of bar=110.76Rs total length of stirrup 580mm Wt. of stirrup=0.128kg, 0.128*23=88.32 Total steel cost=160+111+22+90=383 total cost for beam for 3 meter=3238Rs Total cost for beam for 1 meter=1080Rs
Result of RATE ANALYSIS ( Rs per Unit ) 1080RS
Todays BUZZ Word MASONRY CONTRACTORS CENTERING CONTRACTORS PAINTING CONTRACTORS LABOUR CONTRACTORS PLUMBING CONTRACTOR
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Ketan Charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-03

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Jadhav Nilam Jaywant
Exam No. 13528
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00
Site Leaving Time (HH:MM am/pm) 4.00
Details of the Work Allotted to you today by the Site In-Charge to check the dimensions of the slab formwork. we had to check the length by breadth of the formwork.
Details of how you Planned & Executed the allotted work we referred the designed plan given by the architect.according to that we checked whether the formwork was erected properly.
Details of the Construction Procedure / Activity / Technology learned today concrete lifting machine used for casting slabs.
Details of the Construction Materials learned today steel bars: tor steel:8,10,12,16,20,25 mm used for column reinforcement. mild steel:8 mm used for stirrups.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today extra reinforcement pieces are used for curtailment in the beams.
Details of the Construction / Engineering Drawings observed today Beam drawings and floor drawings for the corresponding floor.
Details of the Bye Laws referred today bye laws referred today: room dimensions- living room-3300*3900 kitchen-3000*2700 bedroom-3000*3450 toilet-2700*1500
Details of any Managerial Skill learned today we should be after the workers.they should not be given any concessions in their work.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for beam: we used the proportion:1:1.5:3 a) cement-0.2763 cu.m no. of bags-(0.2763/0.035)7.85 8 bags=8*260=Rs.2080 b) sand-0.2763*1.5=0.4144=750*0.4144=Rs.310 c) aggregate-0.2763*3=0.8289=450*0.8289=Rs.373 total cost of material=Rs.2763. e) for beam reinforcement-92kg/cu.m*Rs.36=Rs.3312 f) labour-mestri-half day Rs.150 mason-1 no.-Rs.250 Boy or woman-Rs.140*2no.=Rs.280 g) water-1.5%=total cost*(1.5/100)=Rs.41.445 centering and shuttering cost.-lump sump.-Rs.65 carpenter=Rs.200 mazdoor=Rs.75 Total-Rs.(2763+3312+150+250+280+65+200+75)= Rs.4178 contractor profit=total cost*profit(15% profit) =Rs.4178*1.15 =Rs.4805
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4805
Todays BUZZ Word contractors: R.C.C contractor- foundation to slab. masonry contractor- brickwork and grillings electrical contractor- electrification plumbing contractor- plumbing work polish contractor-polishing work painting contractor-painting work plastering contractor-plastering tiling contractor-fitting of tiles window fitter contractor- fitting of windows
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-03

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Suyvanshi patil Pratiksinh Vilas
Exam No. 13549
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 04:45pm
Details of the Work Allotted to you today by the Site In-Charge - Told us to find the no. of bricks required quantity of sand , Cement etc and thus find the amount required for contruction of wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today - We learnt about the Rebaring of beams. 1)First holes of 7\" are drilled by using drilling machine. 2)Than a solution of Adhesoin known as \"GERMAN FISHER CHEMICALS\" was appilied in the hole. 3)Than steel bars of 12mm were hammered and thus rebarring was done.
Details of the Construction Materials learned today - Adhesion material known as \"GERMAN FISHER CHEMICAL\" - Quantity of tube avaliable is 345ml of cost 1150/- per tube.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today - For the purpose of Rebaring we observed the structural design(SLAB) of that particular floor.
Details of the Bye Laws referred today - About loft - lintel.
Details of any Managerial Skill learned today 1) Brickwork 2) Lintels 3) Lofts
RATE ANALYSIS (Detailed Stepwise Calculations required) Size of Beam = 11\'*9\"*6\" Total volume of the Beam = 5.94 cu.ft Matreial Required. 1. Cement = 2 Bags 2. Sand = 4.1 cu.ft 3. Aggregate = 4.25 cu.ft 4. Steel= 20kg 5. Labour charge = 500/- Total= 2406/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 406
Todays BUZZ Word \"CONTRACTORS\" 1.Centering contractor 2. Labour contractor 3. Material supply contractor. 4.Plumbing contractor 5. Water-proofing contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: ashvanijagadale@yahoo.com
Subject: 13530-03

Company Name Tirupati / Vertex Constructions
Project Name & Site Address varun vihar
Students Name (Surname_First Name_Middle Name) Jagadale Ashvani ramrao
Exam No. 13530
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9pm
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge checking the measurement of plot A according to RCC plan of plot A
Details of how you Planned & Executed the allotted work then we planed that both of us will take measurement by using tape and other tow will guide them according to plan of plot A
Details of the Construction Procedure / Activity / Technology learned today today we learned about the precaution to be taken like checking of no of roads ,checking the form-work before the concrete is placed , we saw the work of slap by using R.M.C which was placed by using pump. we also learned about vibration of filling . we also learned use of plumb-bob .
Details of the Construction Materials learned today we learned about the R.M.C. and its use , we also learned about block brick having size 9*6*4 ,its prize is 6.30Rs per brick a,a truck can hold 1500 tractor can hold 1000 brick,.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today they have used marine plank for form-work Thus reducing use of ordinary wood for the purpose ,as they r very durable they in reduce cutting of trees,
Details of the Construction / Engineering Drawings observed today we today observed R.R.C drawing of R.C.C. plan building giving details about side margin an center to center distance of column .
Details of the Bye Laws referred today the minimum distance between two column is kept greater then 6m as bye-law say.
Details of any Managerial Skill learned today today we learned about the command of Mr Ram Purohita sir he knows all the dimensions by heat of the varies plot . Though they have many plot being develop there but they have very good control over every work going on
RATE ANALYSIS (Detailed Stepwise Calculations required) material quantity rate RS cement 6bag 1560 sand 0.2835 327.7 Agg 0.567 760 mistri 6*70 420 water - 100 steel 101.47 555.4 per 1 cum=683.46Rs
Result of RATE ANALYSIS ( Rs per Unit ) 683.46 Rs
Todays BUZZ Word there are various contractor depending upon the work they do centering contractor plumbing contractor electrical contractor plastering contractor they have have to do there accordingly They are responsible for there
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge J.J. chaugule . 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-03

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Gholkar Akshay Purushottam
Exam No. 13525
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to check the dimensions of the slab formwork. we had to check the length by breadth of the formwork.
Details of how you Planned & Executed the allotted work we referred the designed plan given by the architect.according to that we checked whether the formwork was erected properly.
Details of the Construction Procedure / Activity / Technology learned today concrete lifting machine used for casting slabs.
Details of the Construction Materials learned today steel bars: tor steel:8,10,12,16,20,25 mm used for column reinforcement. mild steel:8 mm used for stirrups.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today extra reinforcement pieces are used for curtailment in the beams.
Details of the Construction / Engineering Drawings observed today Beam drawings and floor drawings for the corresponding floor.
Details of the Bye Laws referred today bye laws referred today: room dimensions- living room-3300*3900 kitchen-3000*2700 bedroom-3000*3450 toilet-2700*1500
Details of any Managerial Skill learned today we should be after the workers.they should not be given any concessions in their work.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for beam: we used the proportion:1:1.5:3 a) cement-0.2763 cu.m no. of bags-(0.2763/0.035)7.85 8 bags=8*260=Rs.2080 b) sand-0.2763*1.5=0.4144=750*0.4144=Rs.310 c) aggregate-0.2763*3=0.8289=450*0.8289=Rs.373 total cost of material=Rs.2763. e) for beam reinforcement-92kg/cu.m*Rs.36=Rs.3312 f) labour-mestri-half day Rs.150 mason-1 no.-Rs.250 Boy or woman-Rs.140*2no.=Rs.280 g) water-1.5%=total cost*(1.5/100)=Rs.41.445 centering and shuttering cost.-lump sump.-Rs.65 carpenter=Rs.200 mazdoor=Rs.75 Total-Rs.(2763+3312+150+250+280+65+200+75)= Rs.4178 contractor profit=total cost*profit(15% profit) =Rs.4178*1.15 =Rs.4805
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4805
Todays BUZZ Word contractors: R.C.C contractor- foundation to slab. masonry contractor- brickwork and grillings electrical contractor- electrification plumbing contractor- plumbing work polish contractor-polishing work painting contractor-painting work plastering contractor-plastering tiling contractor-fitting of tiles window fitter contractor- fitting of windows
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-03

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Jadhav Swapnil Ashok
Exam No. 13529
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00
Site Leaving Time (HH:MM am/pm) 4.00
Details of the Work Allotted to you today by the Site In-Charge to check the dimensions of the slab formwork. we had to check the length by breadth of the formwork.
Details of how you Planned & Executed the allotted work we referred the designed plan given by the architect.according to that we checked whether the formwork was erected properly.
Details of the Construction Procedure / Activity / Technology learned today concrete lifting machine used for casting slabs.
Details of the Construction Materials learned today steel bars: tor steel:8,10,12,16,20,25 mm used for column reinforcement. mild steel:8 mm used for stirrups.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today extra reinforcement pieces are used for curtailment in the beams.
Details of the Construction / Engineering Drawings observed today Beam drawings and floor drawings for the corresponding floor.
Details of the Bye Laws referred today bye laws referred today: room dimensions- living room-3300*3900 kitchen-3000*2700 bedroom-3000*3450 toilet-2700*1500
Details of any Managerial Skill learned today we should be after the workers.they should not be given any concessions in their work.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for beam: we used the proportion:1:1.5:3 a) cement-0.2763 cu.m no. of bags-(0.2763/0.035)7.85 8 bags=8*260=Rs.2080 b) sand-0.2763*1.5=0.4144=750*0.4144=Rs.310 c) aggregate-0.2763*3=0.8289=450*0.8289=Rs.373 total cost of material=Rs.2763. e) for beam reinforcement-92kg/cu.m*Rs.36=Rs.3312 f) labour-mestri-half day Rs.150 mason-1 no.-Rs.250 Boy or woman-Rs.140*2no.=Rs.280 g) water-1.5%=total cost*(1.5/100)=Rs.41.445 centering and shuttering cost.-lump sump.-Rs.65 carpenter=Rs.200 mazdoor=Rs.75 Total-Rs.(2763+3312+150+250+280+65+200+75)= Rs.4178 contractor profit=total cost*profit(15% profit) =Rs.4178*1.15 =Rs.4805
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4805
Todays BUZZ Word contractors: R.C.C contractor- foundation to slab. masonry contractor- brickwork and grillings electrical contractor- electrification plumbing contractor- plumbing work polish contractor-polishing work painting contractor-painting work plastering contractor-plastering tiling contractor-fitting of tiles window fitter contractor- fitting of windows
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-03

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Ghorapade Amit Prakash
Exam No. 13526
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00
Site Leaving Time (HH:MM am/pm) 4.00
Details of the Work Allotted to you today by the Site In-Charge to check the dimensions of the slab formwork. we had to check the length by breadth of the formwork.
Details of how you Planned & Executed the allotted work we referred the designed plan given by the architect.according to that we checked whether the formwork was erected properly.
Details of the Construction Procedure / Activity / Technology learned today concrete lifting machine used for casting slabs.
Details of the Construction Materials learned today steel bars: tor steel:8,10,12,16,20,25 mm used for column reinforcement. mild steel:8 mm used for stirrups.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today extra reinforcement pieces are used for curtailment in the beams.
Details of the Construction / Engineering Drawings observed today Beam drawings and floor drawings for the corresponding floor.
Details of the Bye Laws referred today bye laws referred today: room dimensions- living room-3300*3900 kitchen-3000*2700 bedroom-3000*3450 toilet-2700*1500
Details of any Managerial Skill learned today we should be after the workers.they should not be given any concessions in their work.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for beam: we used the proportion:1:1.5:3 a) cement-0.2763 cu.m no. of bags-(0.2763/0.035)7.85 8 bags=8*260=Rs.2080 b) sand-0.2763*1.5=0.4144=750*0.4144=Rs.310 c) aggregate-0.2763*3=0.8289=450*0.8289=Rs.373 total cost of material=Rs.2763. e) for beam reinforcement-92kg/cu.m*Rs.36=Rs.3312 f) labour-mestri-half day Rs.150 mason-1 no.-Rs.250 Boy or woman-Rs.140*2no.=Rs.280 g) water-1.5%=total cost*(1.5/100)=Rs.41.445 centering and shuttering cost.-lump sump.-Rs.65 carpenter=Rs.200 mazdoor=Rs.75 Total-Rs.(2763+3312+150+250+280+65+200+75)= Rs.4178 contractor profit=total cost*profit(15% profit) =Rs.4178*1.15 =Rs.4805
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4805
Todays BUZZ Word contractors: R.C.C contractor- foundation to slab. masonry contractor- brickwork and grillings electrical contractor- electrification plumbing contractor- plumbing work polish contractor-polishing work painting contractor-painting work plastering contractor-plastering tiling contractor-fitting of tiles window fitter contractor- fitting of windows
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: v.g.ayyar@gmail.com
Subject: 13553-03

Company Name Shendre Associates
Project Name & Site Address Mallhar Heigts,Near N.C.C Bhavan Kolhapur
Students Name (Surname_First Name_Middle Name) Ayyar Vignesh Gopal
Exam No. 13553
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010.
Site Reporting Time (HH:MM am/pm) 10:00am
Site Leaving Time (HH:MM am/pm) 04:45pm
Details of the Work Allotted to you today by the Site In-Charge - Told us to find the no. of bricks required quantity of sand , Cement etc and thus find the amount required for contruction of wall.
Details of how you Planned & Executed the allotted work - The team of five was divided in two groups. - One for measurment of the wall and second for calculation purpose.
Details of the Construction Procedure / Activity / Technology learned today - We learnt about the Rebaring of beams. 1)First holes of 7\" are drilled by using drilling machine. 2)Than a solution of Adhesoin known as \"GERMAN FISHER CHEMICALS\" was appilied in the hole. 3)Than steel bars of 12mm were hammered and thus rebarring was done.
Details of the Construction Materials learned today - Adhesion material known as \"GERMAN FISHER CHEMICAL\" - Quantity of tube avaliable is 345ml of cost 1150/- per tube.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today none
Details of the Construction / Engineering Drawings observed today - For the purpose of Rebaring we observed the structural design(SLAB) of that particular floor.
Details of the Bye Laws referred today - About loft - lintel.
Details of any Managerial Skill learned today - To find the estimate on the site 1) Brickwork 2) Lintels 3) Lofts
RATE ANALYSIS (Detailed Stepwise Calculations required) For Beam Size of Beam = 11\'*9\"*6\" Total volume of the Beam = 5.94 cu.ft Matreial Required. 1. Cement = 2 Bags 2. Sand = 4.1 cu.ft 3. Aggregate = 4.25 cu.ft 4. Steel= 20kg 5. Labour charge = 500/- Total= 2406/-
Result of RATE ANALYSIS ( Rs per Unit ) Rs 406
Todays BUZZ Word \"CONTRACTORS\" 1.Centering contractor 2. Labour contractor 3. Material supply contractor. 4.Plumbing contractor 5. Water-proofing contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Vivek Randive (8805494033)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-03

Company Name Vishwakarma Builders
Project Name & Site Address vishwakarma builders,pratibhanagar,kolhapur
Students Name (Surname_First Name_Middle Name) Dsouza Agnel Santan
Exam No. 13524
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00
Site Leaving Time (HH:MM am/pm) 4.00
Details of the Work Allotted to you today by the Site In-Charge to check the dimensions of the slab formwork. we had to check the length by breadth of the formwork.
Details of how you Planned & Executed the allotted work we referred the designed plan given by the architect.according to that we checked whether the formwork was erected properly.
Details of the Construction Procedure / Activity / Technology learned today concrete lifting machine used for casting slabs.
Details of the Construction Materials learned today steel bars: tor steel:8,10,12,16,20,25 mm used for column reinforcement. mild steel:8 mm used for stirrups.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today extra reinforcement pieces are used for curtailment in the beams.
Details of the Construction / Engineering Drawings observed today Beam drawings and floor drawings for the corresponding floor.
Details of the Bye Laws referred today bye laws referred today: room dimensions- living room-3300*3900 kitchen-3000*2700 bedroom-3000*3450 toilet-2700*1500
Details of any Managerial Skill learned today we should be after the workers.they should not be given any concessions in their work.
RATE ANALYSIS (Detailed Stepwise Calculations required) rate analysis for beam: we used the proportion:1:1.5:3 a) cement-0.2763 cu.m no. of bags-(0.2763/0.035)7.85 8 bags=8*260=Rs.2080 b) sand-0.2763*1.5=0.4144=750*0.4144=Rs.310 c) aggregate-0.2763*3=0.8289=450*0.8289=Rs.373 total cost of material=Rs.2763. e) for beam reinforcement-92kg/cu.m*Rs.36=Rs.3312 f) labour-mestri-half day Rs.150 mason-1 no.-Rs.250 Boy or woman-Rs.140*2no.=Rs.280 g) water-1.5%=total cost*(1.5/100)=Rs.41.445 centering and shuttering cost.-lump sump.-Rs.65 carpenter=Rs.200 mazdoor=Rs.75 Total-Rs.(2763+3312+150+250+280+65+200+75)= Rs.4178 contractor profit=total cost*profit(15% profit) =Rs.4178*1.15 =Rs.4805
Result of RATE ANALYSIS ( Rs per Unit ) Rs.4805
Todays BUZZ Word contractors: R.C.C contractor- foundation to slab. masonry contractor- brickwork and grillings electrical contractor- electrification plumbing contractor- plumbing work polish contractor-polishing work painting contractor-painting work plastering contractor-plastering tiling contractor-fitting of tiles window fitter contractor- fitting of windows
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-03

Company Name Chougule Sawant Developers
Project Name & Site Address shree samarth nagar,fulewadi ringroad, near Balinga.
Students Name (Surname_First Name_Middle Name) Jade Madhavrao Anil.
Exam No. 13560
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00am
Site Leaving Time (HH:MM am/pm) 04:00pm
Details of the Work Allotted to you today by the Site In-Charge The work alloted by the site In-charge was, 1) Observation of cube test report. 2) Observation of shuttering work for R.C.C. beam, slab,plinth beam. 3) Obsarvation & checking of bar bending schedule. 4) Observation of centering of column & footing.
Details of how you Planned & Executed the allotted work Before the lunch we observed the cube test report as well as centering of column & footing. And after the lunch we observed the bar bending schedule & shuttering of slab, beam & plinth beam etc.
Details of the Construction Procedure / Activity / Technology learned today They introduce internet wi-fi system in their whole project.
Details of the Construction Materials learned today We learned that the algae proof liquid used for the joints of beam & slab.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today For environment caring they introduce the tree plantation in their whole project.
Details of the Construction / Engineering Drawings observed today we observed that the design drawing of plinth beam for apartments & footing drawing for 2.5 bhk bunglow.
Details of the Bye Laws referred today All the internal dimensions of the rooms of apartments are taking by reffering the BYE-LAWS. FOR e.g. ROOM Minimum(sq.m.) Maximum(sq.m.) bed room 15 20 Leaving room 15 20 Kitchen 12 16 Toilet 2.00 2.5
Details of any Managerial Skill learned today we learned that how to divide the work in the systematic pattern to do the work in the small time.
RATE ANALYSIS (Detailed Stepwise Calculations required) for R.C.C. Beam, rate= 6000 Rs/cu.m. Material Quantity(kg) Rate(Rs.) 1) cement 310 1281 2) aggregate 180 680 3) sand 120 380 4) steel 55 1925 TOTAL =4265 Rs. add a) 2% for wastage. b) labor cost = 1100 Rs. c) 10% for contractor\'s profit, NET TOTAL = 5895 Rs.
Result of RATE ANALYSIS ( Rs per Unit ) 5895 Rs./cu.m.
Todays BUZZ Word Types of contractor\'s are 1)Labor contractor- this contractor is done only following tasks a) R.C.C. Work includes of beam, slab, column, footing, plinth beam etc. b) masonry & plastering work. 2) Tiling contractor- this contractor is done only tiling work in the project. 3) Plastering contractor- this contractor is done only plumbing work concern woth the project. 4) Electrical contractor- this contractor is done only the work of electification. 5) Painting contractor- this contractor is done only work of painting . 6) Road contractor. 7) Landscape contractor.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Swapnil Raut sir & Mob. No.-8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-03

Company Name Chougule Sawant Developers
Project Name & Site Address shri samarth nagar, zakat naka,back of matoshri vrudhashram
Students Name (Surname_First Name_Middle Name) tirmare pradnya ashok
Exam No. 13572
Working Day No. 03
Date (DD/MM/YYYY) 10-12-2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check the alignment of beam formwork.
Details of how you Planned & Executed the allotted work The no. of beam is noted.by using wire alignment is checked.
Details of the Construction Procedure / Activity / Technology learned today The plinth filling by hard murum.the space between beams are filled by hard murum by double compaction &then pcc bed is laid on it.
Details of the Construction Materials learned today Steel bar of tor 415 is used for construction. 16mm,18mm,&20mm dia.are used. The rate is varying. kalika steel bar are used.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Solar water heater are been provided. Therefore energy is saved.
Details of the Construction / Engineering Drawings observed today Appartment drg are stuided in detail.
Details of the Bye Laws referred today Parking space provided is as per byelaws.
Details of any Managerial Skill learned today How to convance client.
RATE ANALYSIS (Detailed Stepwise Calculations required) steel=55kg=1925rs cemant=310=1280rs agg=180kg=680rs sand=120kg=380rs 5815+2%wastage. total=6000rs.
Result of RATE ANALYSIS ( Rs per Unit ) 6000rs
Todays BUZZ Word \'contractor; -1- Labour contractor a)R.C.C work b)Masonary & plastering work. 2-Tiling contractor 3-Plumbing contractor 4-Electrical contractor 5-Carpentry contractor
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge swapnil rauth - 8805173173
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-03

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) patil sangram madhukar
Exam No. 13540
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.00pm
Details of the Work Allotted to you today by the Site In-Charge take leval with respect to foundation level and ground level for road levelling and drainage system
Details of how you Planned & Executed the allotted work observation various beams with referance to the RCC design of that bunglow (bunglow no-10)
Details of the Construction Procedure / Activity / Technology learned today construction of slab and beam 1.preapration of formwork 2.oiling to the formwork 3.arrangement and binding of steel bars with respect to RCC desingn 4.arrangement of covers for steel bars 5.casting of slab and beam
Details of the Construction Materials learned today 1.various types of cover sample 2.various materials for plumbing 3.various types of tiles
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1.RCC design of slab and beams -one way slab -two way slab 2.RCC design of beam -hidden beam -inverted beam -vertical beam
Details of the Bye Laws referred today 1.two storayed building have width of stair case should be minimum 0.75m
Details of any Managerial Skill learned today 1.good cummunication with customers and also with us
RATE ANALYSIS (Detailed Stepwise Calculations required) M20 mix 1.cement 23 bags x 250 =5750Rs 2.aggregate 90cuft x 15 =1350Rs 3.sand 50cuft x 37 =1850Rs 4.water curing =70Rs TOTAL =9420Rs for one cu.ft. =94.20Rs RCC BEAMS 1.basic rate =94.20Rs 2. steel 3.5Kg x 37 =129.5Rs 3. labour =28Rs TOTAL =251.7Rs with C.P.TOTAL =302.04Rs per cuft total for cu.mt.=11186.66Rs
Result of RATE ANALYSIS ( Rs per Unit ) 11187 Rs
Todays BUZZ Word TYPE OF CONTRACTERS SCOPE 1.EXCAVATER -digging for column footing 2.CENTRING -bar bending and prepration of formwork 3.CONCRETE MIXER -do all work of concrete (castingofslab,beams column .) 4.PLUMBER -fittings of all pipe works and plumbing work 5.GAVANDI -constuction of brick walls, partitions etc 6.ELECTRICIAN -electric fittings and wiring 7.CARPENTER -fitting of doors, furnitures etc 8.FABRICATER -fabricates frame of windows & fittings, parapet railing stair railing 9.TILES FITTER -fittings of tiles and floor finishing 10.PAINTER -painting work
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Bhapat sir, Ph no -9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: rajendrapawar54@gmail.com
Subject: 13542-03

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) pawar rajendra eknath
Exam No. 13542
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge take leval with respect to foundation level and ground level for road levelling and drainage system
Details of how you Planned & Executed the allotted work observation various beams with referance to the RCC design of that bunglow (bunglow no-10)
Details of the Construction Procedure / Activity / Technology learned today construction of slab and beam 1.preapration of formwork 2.oiling to the formwork 3.arrangement and binding of steel bars with respect to RCC desingn 4.arrangement of covers for steel bars 5.casting of slab and beam
Details of the Construction Materials learned today 1.various types of cover sample 2.various materials for plumbing 3.various types of tiles
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1.RCC design of slab and beams -one way slab -two way slab 2.RCC design of beam -hidden beam -inverted beam -vertical beam
Details of the Bye Laws referred today 1.two storayed building have width of stair case should be minimum 0.75m
Details of any Managerial Skill learned today 1.good cummunication with customers and also with us
RATE ANALYSIS (Detailed Stepwise Calculations required) M20 mix 1.cement 23 bags x 250 =5750Rs 2.aggregate 90cuft x 15 =1350Rs 3.sand 50cuft x 37 =1850Rs 4.water curing =70Rs TOTAL =9420Rs for one cu.ft. =94.20Rs RCC BEAMS 1.basic rate =94.20Rs 2. steel 3.5Kg x 37 =129.5Rs 3. labour =28Rs TOTAL =251.7Rs with C.P.TOTAL =302.04Rs per cuft total for cu.mt.=11186.66Rs
Result of RATE ANALYSIS ( Rs per Unit ) 11187 Rs
Todays BUZZ Word TYPE OF CONTRACTERS SCOPE 1.EXCAVATER -digging for column footing 2.CENTRING -bar bending and prepration of formwork 3.CONCRETE MIXER -do all work of concrete (castingofslab,beams column .) 4.PLUMBER -fittings of all pipe works and plumbing work 5.GAVANDI -constuction of brick walls, partitions etc 6.ELECTRICIAN -electric fittings and wiring 7.CARPENTER -fitting of doors, furnitures etc 8.FABRICATER -fabricates frame of windows & fittings, parapet railing stair railing 9.TILES FITTER -fittings of tiles and floor finishing 10.PAINTER -painting work
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Bhapat sir, Ph no -9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: vishwajit.p09@gmail.com
Subject: 13543-03

Company Name S. N. Builders
Project Name & Site Address aminesh nagar,near shahu naka,dadu chougle nagar
Students Name (Surname_First Name_Middle Name) paymal vishwajit shamarao
Exam No. 13543
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9:00am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge take leval with respect to foundation level and ground level for road levelling and drainage system
Details of how you Planned & Executed the allotted work observation various beams with referance to the RCC design of that bunglow (bunglow no-10)
Details of the Construction Procedure / Activity / Technology learned today construction of slab and beam 1.preapration of formwork 2.oiling to the formwork 3.arrangement and binding of steel bars with respect to RCC desingn 4.arrangement of covers for steel bars 5.casting of slab and beam
Details of the Construction Materials learned today 1.various types of cover sample 2.various materials for plumbing 3.various types of tiles
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1.RCC design of slab and beams -one way slab -two way slab 2.RCC design of beam -hidden beam -inverted beam -vertical beam
Details of the Bye Laws referred today 1.two storayed building have width of stair case should be minimum 0.75m
Details of any Managerial Skill learned today 1.good cummunication with customers and also with us
RATE ANALYSIS (Detailed Stepwise Calculations required) M20 mix 1.cement 23 bags x 250 =5750Rs 2.aggregate 90cuft x 15 =1350Rs 3.sand 50cuft x 37 =1850Rs 4.water curing =70Rs TOTAL =9420Rs for one cu.ft. =94.20Rs RCC BEAMS 1.basic rate =94.20Rs 2. steel 3.5Kg x 37 =129.5Rs 3. labour =28Rs TOTAL =251.7Rs with C.P.TOTAL =302.04Rs per cuft total for cu.mt.=11186.66Rs
Result of RATE ANALYSIS ( Rs per Unit ) 11187 Rs
Todays BUZZ Word TYPE OF CONTRACTERS SCOPE 1.EXCAVATER -digging for column footing 2.CENTRING -bar bending and prepration of formwork 3.CONCRETE MIXER -do all work of concrete (castingofslab,beams column .) 4.PLUMBER -fittings of all pipe works and plumbing work 5.GAVANDI -constuction of brick walls, partitions etc 6.ELECTRICIAN -electric fittings and wiring 7.CARPENTER -fitting of doors, furnitures etc 8.FABRICATER -fabricates frame of windows & fittings, parapet railing stair railing 9.TILES FITTER -fittings of tiles and floor finishing 10.PAINTER -painting work
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Bhapat sir, Ph no -9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-03

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) patil sachin dhanaji
Exam No. 13539
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 8:50am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge take leval with respect to foundation level and ground level for road levelling and drainage system
Details of how you Planned & Executed the allotted work observation various beams with referance to the RCC design of that bunglow (bunglow no-10)
Details of the Construction Procedure / Activity / Technology learned today construction of slab and beam 1.preapration of formwork 2.oiling to the formwork 3.arrangement and binding of steel bars with respect to RCC desingn 4.arrangement of covers for steel bars 5.casting of slab and beam
Details of the Construction Materials learned today 1.various types of cover sample 2.various materials for plumbing 3.various types of tiles
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1.RCC design of slab and beams -one way slab -two way slab 2.RCC design of beam -hidden beam -inverted beam -vertical beam
Details of the Bye Laws referred today 1.two storayed building have width of stair case should be minimum 0.75m
Details of any Managerial Skill learned today 1.good cummunication with customers and also with us
RATE ANALYSIS (Detailed Stepwise Calculations required) M20 mix 1.cement 23 bags x 250 =5750Rs 2.aggregate 90cuft x 15 =1350Rs 3.sand 50cuft x 37 =1850Rs 4.water curing =70Rs TOTAL =9420Rs for one cu.ft. =94.20Rs RCC BEAMS 1.basic rate =94.20Rs 2. steel 3.5Kg x 37 =129.5Rs 3. labour =28Rs TOTAL =251.7Rs with C.P.TOTAL =302.04Rs per cuft total for cu.mt.=11186.66Rs
Result of RATE ANALYSIS ( Rs per Unit ) 11187 Rs
Todays BUZZ Word TYPE OF CONTRACTERS SCOPE 1.EXCAVATER -digging for column footing 2.CENTRING -bar bending and prepration of formwork 3.CONCRETE MIXER -do all work of concrete (castingofslab,beams column .) 4.PLUMBER -fittings of all pipe works and plumbing work 5.GAVANDI -constuction of brick walls, partitions etc 6.ELECTRICIAN -electric fittings and wiring 7.CARPENTER -fitting of doors, furnitures etc 8.FABRICATER -fabricates frame of windows & fittings, parapet railing stair railing 9.TILES FITTER -fittings of tiles and floor finishing 10.PAINTER -painting work
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Bhapat sir, Ph no -9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: viju128@gmail.com
Subject: 3638-03

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.water tank rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) shinde vijay namdeo
Exam No. 3638
Working Day No. 03
Date (DD/MM/YYYY) 10/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge -Painting –internal wall-oil bond -steel gate – oil paints -Centering work of beam:- Removal of the shuttering work after the setting of the concrete and also another shuteering first checked the level before the shuttering first checked the level before the shuttering for the beam -point first they apply the putty to plane the surface of the door so that ,it will give the smooth finish also avoiding moisture.
Details of how you Planned & Executed the allotted work We observed that painting work done by the workers.They use the rollers so that it will get smooth finish is less time and use rollers is less lavorious.
Details of the Construction Procedure / Activity / Technology learned today Tube levelling & shuttering have to pack & open the shuttering work.
Details of the Construction Materials learned today Oil paint,oil bond,putty(They have used the company sunlight)
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no
Details of the Construction / Engineering Drawings observed today Rcc beams & columns
Details of the Bye Laws referred today Internal room stress. Bathroom,toiletsliving room,bedroom,kitchen
Details of any Managerial Skill learned today No management skills
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for Rcc beam for 1m3 For 1m3 Rcc cost =3300rs/1m3 Labour cost for 1ft3 of Rcc beam=35rs For 1m3=35*35.28=1235rs/1m3 Total cost=3300+1235=4535 Add 5% wastage = 227rs =4762 rs Using 75 kg steel bar =2775 =7537 rs Add 20% contractor’s profit =1507 =9044 rs/1m3 beam
Result of RATE ANALYSIS ( Rs per Unit ) 9044 rs/1m3 beam
Todays BUZZ Word Different type of Contractors in detail required their scope small scale and large scale -small scale works and handle by an individual contractor -but for the large scale work are no of people working on it and it for the team & it’s team. Distribute the day to day work and give the direction to the work on site as well asthey maintain the office works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883-03

Company Name Star Tech Infra
Project Name & Site Address star aashiyana nr.water tank rajendra nagar kolhapur
Students Name (Surname_First Name_Middle Name) Saurabh Arora
Exam No. 10883
Working Day No. 2
Date (DD/MM/YYYY) 10/12/10
Site Reporting Time (HH:MM am/pm) 9am
Site Leaving Time (HH:MM am/pm) 4pm
Details of the Work Allotted to you today by the Site In-Charge -Painting –internal wall-oil bond -steel gate – oil paints -Centering work of beam:- Removal of the shuttering work after the setting of the concrete and also another shuteering first checked the level before the shuttering first checked the level before the shuttering for the beam -point first they apply the putty to plane the surface of the door so that ,it will give the smooth finish also avoiding moisture.
Details of how you Planned & Executed the allotted work We observed that painting work done by the workers.They use the rollers so that it will get smooth finish is less time and use rollers is less lavorious.
Details of the Construction Procedure / Activity / Technology learned today Tube levelling & shuttering have to pack & open the shuttering work.
Details of the Construction Materials learned today Oil paint,oil bond,putty(They have used the company sunlight)
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No
Details of the Construction / Engineering Drawings observed today Rcc beams & columns
Details of the Bye Laws referred today Internal room stress. Bathroom,toiletsliving room,bedroom,kitchen
Details of any Managerial Skill learned today No management skills
RATE ANALYSIS (Detailed Stepwise Calculations required) Rate analysis for Rcc beam for 1m3 For 1m3 Rcc cost =3300rs/1m3 Labour cost for 1ft3 of Rcc beam=35rs For 1m3=35*35.28=1235rs/1m3 Total cost=3300+1235=4535 Add 5% wastage = 227rs =4762 rs Using 75 kg steel bar =2775 =7537 rs Add 20% contractor’s profit =1507 =9044 rs/1m3 beam
Result of RATE ANALYSIS ( Rs per Unit ) 9044rs/1m3 beAM
Todays BUZZ Word Different type of Contractors in detail required their scope small scale and large scale -small scale works and handle by an individual contractor -but for the large scale work are no of people working on it and it for the team & it’s team. Distribute the day to day work and give the direction to the work on site as well asthey maintain the office works.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge SATISH 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: nikitashinde15@gmail.com
Subject: 13547-03

Company Name S. N. Builders
Project Name & Site Address animesh nagar
Students Name (Surname_First Name_Middle Name) shinde nikita eknath
Exam No. 13547
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 8:55am
Site Leaving Time (HH:MM am/pm) 4:00pm
Details of the Work Allotted to you today by the Site In-Charge take leval with respect to foundation level and ground level for road levelling and drainage system
Details of how you Planned & Executed the allotted work observation various beams with referance to the RCC design of that bunglow (bunglow no-10)
Details of the Construction Procedure / Activity / Technology learned today construction of slab and beam 1.preapration of formwork 2.oiling to the formwork 3.arrangement and binding of steel bars with respect to RCC desingn 4.arrangement of covers for steel bars 5.casting of slab and beam
Details of the Construction Materials learned today 1.various types of cover sample 2.various materials for plumbing 3.various types of tiles
Details of Environment Caring Technology / Methodology / Procedure / Product learned today rain water harvesting system
Details of the Construction / Engineering Drawings observed today 1.RCC design of slab and beams -one way slab -two way slab 2.RCC design of beam -hidden beam -inverted beam -vertical beam
Details of the Bye Laws referred today 1.two storayed building have width of stair case should be minimum 0.75m
Details of any Managerial Skill learned today 1.good cummunication with customers and also with us
RATE ANALYSIS (Detailed Stepwise Calculations required) M20 mix 1.cement 23 bags x 250 =5750Rs 2.aggregate 90cuft x 15 =1350Rs 3.sand 50cuft x 37 =1850Rs 4.water curing =70Rs TOTAL =9420Rs for one cu.ft. =94.20Rs RCC BEAMS 1.basic rate =94.20Rs 2. steel 3.5Kg x 37 =129.5Rs 3. labour =28Rs TOTAL =251.7Rs with C.P.TOTAL =302.04Rs per cuft total for cu.mt.=11186.66Rs
Result of RATE ANALYSIS ( Rs per Unit ) 11187 Rs
Todays BUZZ Word TYPE OF CONTRACTERS SCOPE 1.EXCAVATER -digging for column footing 2.CENTRING -bar bending and prepration of formwork 3.CONCRETE MIXER -do all work of concrete (castingofslab,beams column .) 4.PLUMBER -fittings of all pipe works and plumbing work 5.GAVANDI -constuction of brick walls, partitions etc 6.ELECTRICIAN -electric fittings and wiring 7.CARPENTER -fitting of doors, furnitures etc 8.FABRICATER -fabricates frame of windows & fittings, parapet railing stair railing 9.TILES FITTER -fittings of tiles and floor finishing 10.PAINTER -painting work
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Bhapat sir, Ph no -9028466630
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: bsalamn75@yahoo.com
Subject: 10888-03

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage,r.s.no.950/1b,plotno-44,sardar prk devkar panand kolhapur.
Students Name (Surname_First Name_Middle Name) Baig Salman samad
Exam No. 10888
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for staircase and beam bottoms, and check their levels, heights and dimensions as per drawings and details.
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions, level and clear distance between two beams with reference to details given
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the bottom of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs.
Details of the Construction Materials learned today \"Margo\" film faced shuttering plywood of size 8ft*4ft and thickness of 12mm and having rate of 55/- per square ft
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material or technology is adopted on the site
Details of the Construction / Engineering Drawings observed today Detail drawing of beams and beam sections.
Details of the Bye Laws referred today Passage width provided at the site is 1.30m. As per bye law it is 1.20m.
Details of any Managerial Skill learned today checking the work with reference to drawing and the way of talking with labours for correction of mistakes.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for R.C.C. Beam no.211“ 1. Quantity of concrete=0.411cu.m. 2. Quantity of cement=0.36 cu.m. =1 bag 3. Quantity of sand=0.15 cu.m. 4. Quantity of coarse aggregate=0.31 cu.m. 5. Quantity of steel considering 10%as wastage Tor steel Fe-415 =56.617kg =0.0566 tonne 6. Quantity of binding wire for 10 cu.m. =15.7 kg So for 0.411cu.m.= 0.64kg “Rate Analysis for R.C.C. beam using M20 concrete” (Considering local rates of material) (beam size-150*530*5182) 1. Cost of cement=1*250=250/-………..(250/- per bag) 2. Cost of sand=0.15*1600=240/-…………(1600/- per cu.m.) 3. Cost of coarse aggregate=0.31*625=200/-…………(625/- per cu.m.) 4. Cost of tor steel= 0.0566*32,000=1811/-…………(32000/- per tonne.) 5.Cost of binding wire=30*0.64=20/-………… (30/- per kg) 6. Labour charges=500/- 7. Total cost= 3021/- 8.10% profit of total cost for the contractor=302.1/- 9. Total cost=3323/- 10. Rate per cu.m.= 8085/-
Result of RATE ANALYSIS ( Rs per Unit ) 8085/-
Todays BUZZ Word “Contractors and their Scope” Centring contactor- This contractor has its team of 20 fitters and carpenters all shuttering, fixing of centring plates and binding of steel for slabs column and beams is done by them. Contract of the whole building is given to the contractor on per square feet rate. Labour contractor- This contractor supplies all male and female labours for concreting works of slabs, beams and columns. Electrical contractor- This contractor does all the concealed wiring work and fitting of all types of electrical appliances and switch mains etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-03

Company Name Shree Developers & Builders
Project Name & Site Address karan heritage,r.s.no.950/1b,plotno-44,sardar prk devkar panand kolhapur.
Students Name (Surname_First Name_Middle Name) Yadav Hrishikesh Deepak
Exam No. 10885
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for staircase and beam bottoms, and check their levels, heights and dimensions as per drawings and details
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions, level and clear distance between two beams with reference to details given
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the bottom of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs.
Details of the Construction Materials learned today \"Margo\" film faced shuttering plywood of size 8ft*4ft and thickness of 12mm and having rate of 55/- per square ft
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material or technology is adopted on the site
Details of the Construction / Engineering Drawings observed today Detail drawing of beams and beam sections.
Details of the Bye Laws referred today Passage width provided at the site is 1.30m. As per bye law it is 1.20m
Details of any Managerial Skill learned today checking the work with reference to drawing and the way of talking with labours for correction of mistakes.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for R.C.C. Beam no.211“ 1. Quantity of concrete=0.411cu.m. 2. Quantity of cement=0.36 cu.m. =1 bag 3. Quantity of sand=0.15 cu.m. 4. Quantity of coarse aggregate=0.31 cu.m. 5. Quantity of steel considering 10%as wastage Tor steel Fe-415 =56.617kg =0.0566 tonne 6. Quantity of binding wire for 10 cu.m. =15.7 kg So for 0.411cu.m.= 0.64kg “Rate Analysis for R.C.C. beam using M20 concrete” (Considering local rates of material) (beam size-150*530*5182) 1. Cost of cement=1*250=250/-………..(250/- per bag) 2. Cost of sand=0.15*1600=240/-…………(1600/- per cu.m.) 3. Cost of coarse aggregate=0.31*625=200/-…………(625/- per cu.m.) 4. Cost of tor steel= 0.0566*32,000=1811/-…………(32000/- per tonne.) 5.Cost of binding wire=30*0.64=20/-………… (30/- per kg) 6. Labour charges=500/- 7. Total cost= 3021/- 8.10% profit of total cost for the contractor=302.1/- 9. Total cost=3323/- 10. Rate per cu.m.= 8085/-
Result of RATE ANALYSIS ( Rs per Unit ) 8085/
Todays BUZZ Word “Contractors and their Scope” Centring contactor- This contactor has its team of 20 fitters and carpenters all shuttering, fixing of centring plates and binding of steel for slabs column and beams is done by them. Contract of the whole building is given to the contactor on per square feet rate. Labour contractor- This contractor supplies all male and female labours for concreting works of slabs, beams and columns. Electrical contractor- This contractor does all the concealed wiring work and fitting of all types of electrical appliances and switch mains etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: vishalsapakal124@gmail.com
Subject: 10882-03

Company Name Shree Developers & Builders
Project Name & Site Address Karan Heritage,plot no.44,sardar park,devkar panand,kolhapur.
Students Name (Surname_First Name_Middle Name) Sapkal Vishal Manohar
Exam No. 10882
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for staircase and beam bottoms, and check their levels, heights and dimensions as per drawings and details.
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions, level and clear distance between two beams with reference to details given
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the bottom of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs.
Details of the Construction Materials learned today \"Margo\" film faced shuttering plywood of size 8ft*4ft and thickness of 12mm and having rate of 55/- per square ft
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material or technology is adopted on the site
Details of the Construction / Engineering Drawings observed today Detail drawing of beams and beam sections.
Details of the Bye Laws referred today Passage width provided at the site is 1.30m. As per bye law it is 1.20m.
Details of any Managerial Skill learned today checking the work with reference to drawing and the way of talking with labours for correction of mistakes.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for R.C.C. Beam no.211“ 1. Quantity of concrete=0.411cu.m. 2. Quantity of cement=0.36 cu.m. =1 bag 3. Quantity of sand=0.15 cu.m. 4. Quantity of coarse aggregate=0.31 cu.m. 5. Quantity of steel considering 10%as wastage Tor steel Fe-415 =56.617kg =0.0566 tonne 6. Quantity of binding wire for 10 cu.m. =15.7 kg So for 0.411cu.m.= 0.64kg “Rate Analysis for R.C.C. beam using M20 concrete” (Considering local rates of material) (beam size-150*530*5182) 1. Cost of cement=1*250=250/-………..(250/- per bag) 2. Cost of sand=0.15*1600=240/-…………(1600/- per cu.m.) 3. Cost of coarse aggregate=0.31*625=200/-…………(625/- per cu.m.) 4. Cost of tor steel= 0.0566*32,000=1811/-…………(32000/- per tonne.) 5.Cost of binding wire=30*0.64=20/-………… (30/- per kg) 6. Labour charges=500/- 7. Total cost= 3021/- 8.10% profit of total cost for the contractor=302.1/- 9. Total cost=3323/- 10. Rate per cu.m.= 8085/-
Result of RATE ANALYSIS ( Rs per Unit ) 8085/-
Todays BUZZ Word “Contractors and their Scope” Centring contactor- This contactor has its team of 20 fitters and carpenters all shuttering, fixing of centring plates and binding of steel for slabs column and beams is done by them. Contract of the whole building is given to the contactor on per square feet rate. Labour contractor- This contractor supplies all male and female labours for concreting works of slabs, beams and columns. Electrical contractor- This contractor does all the concealed wiring work and fitting of all types of electrical appliances and switch mains etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-03

Company Name Shree Developers & Builders
Project Name & Site Address Karan Heritage,plot no.44,sardar park,devkar panand,kolhapur.
Students Name (Surname_First Name_Middle Name) Babar Moreshwar Mahipati
Exam No. 10873
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for staircase and beam bottoms, and check their levels, heights and dimensions as per drawings and details.
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions, level and clear distance between two beams with reference to details given
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the bottom of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs.
Details of the Construction Materials learned today \"Margo\" film faced shuttering plywood of size 8ft*4ft and thickness of 12mm and having rate of 55/- per square ft
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material or technology is adopted on the site
Details of the Construction / Engineering Drawings observed today Detail drawing of beams and beam sections.
Details of the Bye Laws referred today Passage width provided at the site is 1.30m. As per bye law it is 1.20m.
Details of any Managerial Skill learned today checking the work with reference to drawing and the way of talking with labours for correction of mistakes.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for R.C.C. Beam no.211“ 1. Quantity of concrete=0.411cu.m. 2. Quantity of cement=0.36 cu.m. =1 bag 3. Quantity of sand=0.15 cu.m. 4. Quantity of coarse aggregate=0.31 cu.m. 5. Quantity of steel considering 10%as wastage Tor steel Fe-415 =56.617kg =0.0566 tonne 6. Quantity of binding wire for 10 cu.m. =15.7 kg So for 0.411cu.m.= 0.64kg “Rate Analysis for R.C.C. beam using M20 concrete” (Considering local rates of material) (beam size-150*530*5182) 1. Cost of cement=1*250=250/-………..(250/- per bag) 2. Cost of sand=0.15*1600=240/-…………(1600/- per cu.m.) 3. Cost of coarse aggregate=0.31*625=200/-…………(625/- per cu.m.) 4. Cost of tor steel= 0.0566*32,000=1811/-…………(32000/- per tonne.) 5.Cost of binding wire=30*0.64=20/-………… (30/- per kg) 6. Labour charges=500/- 7. Total cost= 3021/- 8.10% profit of total cost for the contractor=302.1/- 9. Total cost=3323/- 10. Rate per cu.m.= 8085/-
Result of RATE ANALYSIS ( Rs per Unit ) 8085/-
Todays BUZZ Word “Contractors and their Scope” Centring contactor- This contactor has its team of 20 fitters and carpenters all shuttering, fixing of centring plates and binding of steel for slabs column and beams is done by them. Contract of the whole building is given to the contactor on per square feet rate. Labour contractor- This contractor supplies all male and female labours for concreting works of slabs, beams and columns. Electrical contractor- This contractor does all the concealed wiring work and fitting of all types of electrical appliances and switch mains etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: patilpratibha7070@yahoo.in
Subject: 10896-03

Company Name Shree Developers & Builders
Project Name & Site Address Karan Heritage,plot no.44,sardar park,devkar panand,kolhapur.
Students Name (Surname_First Name_Middle Name) Patil Pratibha Dilip
Exam No. 10896
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 9.00am
Site Leaving Time (HH:MM am/pm) 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To observe the fixing of shuttering for staircase and beam bottoms, and check their levels, heights and dimensions as per drawings and details.
Details of how you Planned & Executed the allotted work Firstly we decided to check the dimensions, level and clear distance between two beams with reference to details given
Details of the Construction Procedure / Activity / Technology learned today Fixing of shuttering plywood’s at the bottom of the beams, cutting of timber supports for supporting beam bottoms, and shuttering of stairs.
Details of the Construction Materials learned today \"Margo\" film faced shuttering plywood of size 8ft*4ft and thickness of 12mm and having rate of 55/- per square ft
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such material or technology is adopted on the site
Details of the Construction / Engineering Drawings observed today Detail drawing of beams and beam sections.
Details of the Bye Laws referred today Passage width provided at the site is 1.30m. As per bye law it is 1.20m.
Details of any Managerial Skill learned today checking the work with reference to drawing and the way of talking with labours for correction of mistakes.
RATE ANALYSIS (Detailed Stepwise Calculations required) “Quantity calculation for R.C.C. Beam no.211“ 1. Quantity of concrete=0.411cu.m. 2. Quantity of cement=0.36 cu.m. =1 bag 3. Quantity of sand=0.15 cu.m. 4. Quantity of coarse aggregate=0.31 cu.m. 5. Quantity of steel considering 10%as wastage Tor steel Fe-415 =56.617kg =0.0566 tonne 6. Quantity of binding wire for 10 cu.m. =15.7 kg So for 0.411cu.m.= 0.64kg “Rate Analysis for R.C.C. beam using M20 concrete” (Considering local rates of material) (beam size-150*530*5182) 1. Cost of cement=1*250=250/-………..(250/- per bag) 2. Cost of sand=0.15*1600=240/-…………(1600/- per cu.m.) 3. Cost of coarse aggregate=0.31*625=200/-…………(625/- per cu.m.) 4. Cost of tor steel= 0.0566*32,000=1811/-…………(32000/- per tonne.) 5.Cost of binding wire=30*0.64=20/-………… (30/- per kg) 6. Labour charges=500/- 7. Total cost= 3021/- 8.10% profit of total cost for the contractor=302.1/- 9. Total cost=3323/- 10. Rate per cu.m.= 8085/-
Result of RATE ANALYSIS ( Rs per Unit ) 8085/-
Todays BUZZ Word “Contractors and their Scope” Centring contractor- This contractor has its team of 20 fitters and carpenters all shuttering, fixing of centring plates and binding of steel for slabs column and beams is done by them. Contract of the whole building is given to the contractor on per square feet rate. Labour contractor- This contractor supplies all male and female labours for concreting works of slabs, beams and columns. Electrical contractor- This contractor does all the concealed wiring work and fitting of all types of electrical appliances and switch mains etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-03

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) KHADE AMARDEEP BHAGWAN
Exam No. 13563
Working Day No. 03
Date (DD/MM/YYYY) 10 / 12 / 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge * To observe the formwork of ground level beam and ground water tank. * Take the dimension of ground beam. * How to construct ground level beam.
Details of how you Planned & Executed the allotted work * First we take the details of ground level beam. * Then observe the position of beam.and we observe the formwork and casting of beam.
Details of the Construction Procedure / Activity / Technology learned today * First level the ground. * Then mark position of beam with respect to plan on ground. * Then P.C.C laid on ground to position of beam. * Then steel bar arranged to the size and depth of beam. * Stirrups are placed at equal distance to the length of beam. * Then formwork is done by applying oil . * For beam side top and bottom cover 25 mm and end cover 40 mm are used. * Then concreting is done around the beam.
Details of the Construction Materials learned today * Murum filling side of beam. * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Superplasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Small size of bar are provided . So large amount of steel will be reduced.
Details of the Construction / Engineering Drawings observed today * First we observed working drawing the beam layout plan. * According to this plan position is selected. * After this actual quantity of steel require from steel structure drawing provided.
Details of the Bye Laws referred today STAIWAYS: * Flight- No flight shall contain more than 12 risers, but in residential building, in gaothan or congestade area a single flight staircase may be permitted. * Risers- The maximum height of a riser shall be 19 cm. in a recidential building and 15 cm. in any other occupancy. However on an internal stircase within a dwelling unit a riser may be 25 cm. high. * Treads- The maximum width of the tread without nosing shall be 25 cm. for staircase of a residential building.
Details of any Managerial Skill learned today * To check the workdone of beam and water tank. * With the help of linedori, tape, gunya, etc.we mark distance of main bar, anchor bar, stirrups etc. * Then the fixing the exist position of beam
RATE ANALYSIS (Detailed Stepwise Calculations required) M 20 (7.4 BAGS) (1:1.5:3) BEAM SIZE- 540X230X6050 MM Top bars- 2no. 10.00mm dia. Bottom bar- 2 no. 12.00mm dia Bent up bar- 1 no. 12.00 mm dia stirrups- 6.00 mm @ 150 mm c/c CALCULATION- Cement- 7.4 x 250 = 1850/- Sand - 1.25 x 7.4 x 1.5 x 35 = 490/- Aggregate- 1.25 x 7.4 x 3 x 18 = 500/- Steel- 12.68 kg.x 35 = 450/- Labour- 1 cu.ft. 5.50 rs taken = 1400/-
Result of RATE ANALYSIS ( Rs per Unit ) 6253.33 /-
Todays BUZZ Word Types of contractor- * Labour contractor * Material contractor Scope of labour contractor- The scope of the contractor\'s work including all R.C.C. work connected with the building such as fotting, column, beam, lintel, overhead water tank, chajja, plinth level, staircase, slab, removal of material, plinth filling, soiling, p.c.c. work. etc. Scope of material contractor- To supply the construction material on site such as, brick, steel, aggregate, sand, murum, tiles, plywood, wood, sanitary materials, etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-03

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) MOHARE VISHAL BHALCHANDRA
Exam No. 13564
Working Day No. 03
Date (DD/MM/YYYY) 10 / 12 / 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge * To observe the formwork of ground level beam and ground water tank. * Take the dimension of ground beam. * How to construct ground level beam.
Details of how you Planned & Executed the allotted work * First we take the details of ground level beam. * Then observe the position of beam.and we observe the formwork and casting of beam.
Details of the Construction Procedure / Activity / Technology learned today * First level the ground. * Then mark position of beam with respect to plan on ground. * Then P.C.C laid on ground to position of beam. * Then steel bar arranged to the size and depth of beam. * Stirrups are placed at equal distance to the length of beam. * Then formwork is done by applying oil . * For beam side top and bottom cover 25 mm and end cover 40 mm are used. * Then concreting is done around the beam.
Details of the Construction Materials learned today * Murum filling side of beam. * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Superplasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Small size of bar are provided . So large amount of steel will be reduced.
Details of the Construction / Engineering Drawings observed today * First we observed working drawing the beam layout plan. * According to this plan position is selected. * After this actual quantity of steel require from steel structure drawing provided.
Details of the Bye Laws referred today STAIWAYS: * Flight- No flight shall contain more than 12 risers, but in residential building, in gaothan or congestade area a single flight staircase may be permitted. * Risers- The maximum height of a riser shall be 19 cm. in a recidential building and 15 cm. in any other occupancy. However on an internal stircase within a dwelling unit a riser may be 25 cm. high. * Treads- The maximum width of the tread without nosing shall be 25 cm. for staircase of a residential building.
Details of any Managerial Skill learned today * To check the workdone of beam and water tank. * With the help of linedori, tape, gunya, etc.we mark distance of main bar, anchor bar, stirrups etc. * Then the fixing the exist position of beam
RATE ANALYSIS (Detailed Stepwise Calculations required) M 20 (7.4 BAGS) (1:1.5:3) BEAM SIZE- 540X230X6050 MM Top bars- 2no. 10.00mm dia. Bottom bar- 2 no. 12.00mm dia Bent up bar- 1 no. 12.00 mm dia stirrups- 6.00 mm @ 150 mm c/c CALCULATION- Cement- 7.4 x 250 = 1850/- Sand - 1.25 x 7.4 x 1.5 x 35 = 490/- Aggregate- 1.25 x 7.4 x 3 x 18 = 500/- Steel- 12.68 kg.x 35 = 450/- Labour- 1 cu.ft. 5.50 rs taken = 1400/-
Result of RATE ANALYSIS ( Rs per Unit ) 6253.33 /-
Todays BUZZ Word Types of contractor- * Labour contractor * Material contractor Scope of labour contractor- The scope of the contractor\'s work including all R.C.C. work connected with the building such as fotting, column, beam, lintel, overhead water tank, chajja, plinth level, staircase, slab, removal of material, plinth filling, soiling, p.c.c. work. etc. Scope of material contractor- To supply the construction material on site such as, brick, steel, aggregate, sand, murum, tiles, plywood, wood, sanitary materials, etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-03

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) BULBULE KHANDOBA RAMCHANDRA
Exam No. 13557
Working Day No. 03
Date (DD/MM/YYYY) 10 / 12 / 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge * To observe the formwork of ground level beam and ground water tank. * Take the dimension of ground beam. * How to construct ground level beam.
Details of how you Planned & Executed the allotted work * First we take the details of ground level beam. * Then observe the position of beam.and we observe the formwork and casting of beam.
Details of the Construction Procedure / Activity / Technology learned today * First level the ground. * Then mark position of beam with respect to plan on ground. * Then P.C.C laid on ground to position of beam. * Then steel bar arranged to the size and depth of beam. * Stirrups are placed at equal distance to the length of beam. * Then formwork is done by applying oil . * For beam side top and bottom cover 25 mm and end cover 40 mm are used. * Then concreting is done around the beam.
Details of the Construction Materials learned today * Murum filling side of beam. * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Superplasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Small size of bar are provided . So large amount of steel will be reduced.
Details of the Construction / Engineering Drawings observed today * First we observed working drawing the beam layout plan. * According to this plan position is selected. * After this actual quantity of steel require from steel structure drawing provided.
Details of the Bye Laws referred today STAIWAYS: * Flight- No flight shall contain more than 12 risers, but in residential building, in gaothan or congestade area a single flight staircase may be permitted. * Risers- The maximum height of a riser shall be 19 cm. in a recidential building and 15 cm. in any other occupancy. However on an internal stircase within a dwelling unit a riser may be 25 cm. high. * Treads- The maximum width of the tread without nosing shall be 25 cm. for staircase of a residential building.
Details of any Managerial Skill learned today * To check the workdone of beam and water tank. * With the help of linedori, tape, gunya, etc.we mark distance of main bar, anchor bar, stirrups etc. * Then the fixing the exist position of beam
RATE ANALYSIS (Detailed Stepwise Calculations required) M 20 (7.4 BAGS) (1:1.5:3) BEAM SIZE- 540X230X6050 MM Top bars- 2no. 10.00mm dia. Bottom bar- 2 no. 12.00mm dia Bent up bar- 1 no. 12.00 mm dia stirrups- 6.00 mm @ 150 mm c/c CALCULATION- Cement- 7.4 x 250 = 1850/- Sand - 1.25 x 7.4 x 1.5 x 35 = 490/- Aggregate- 1.25 x 7.4 x 3 x 18 = 500/- Steel- 12.68 kg.x 35 = 450/- Labour- 1 cu.ft. 5.50 rs taken = 1400/-
Result of RATE ANALYSIS ( Rs per Unit ) 6253.33 /-
Todays BUZZ Word Types of contractor- * Labour contractor * Material contractor Scope of labour contractor- The scope of the contractor\'s work including all R.C.C. work connected with the building such as fotting, column, beam, lintel, overhead water tank, chajja, plinth level, staircase, slab, removal of material, plinth filling, soiling, p.c.c. work. etc. Scope of material contractor- To supply the construction material on site such as, brick, steel, aggregate, sand, murum, tiles, plywood, wood, sanitary materials, etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-03

Company Name Bhima Builders & Developers
Project Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Students Name (Surname_First Name_Middle Name) REDEKAR SHANTANU RAVINDRA
Exam No. 13566
Working Day No. 03
Date (DD/MM/YYYY) 10 / 12 / 2010
Site Reporting Time (HH:MM am/pm) 09:00 am
Site Leaving Time (HH:MM am/pm) 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge * To observe the formwork of ground level beam and ground water tank. * Take the dimension of ground beam. * How to construct ground level beam.
Details of how you Planned & Executed the allotted work * First we take the details of ground level beam. * Then observe the position of beam.and we observe the formwork and casting of beam.
Details of the Construction Procedure / Activity / Technology learned today * First level the ground. * Then mark position of beam with respect to plan on ground. * Then P.C.C laid on ground to position of beam. * Then steel bar arranged to the size and depth of beam. * Stirrups are placed at equal distance to the length of beam. * Then formwork is done by applying oil . * For beam side top and bottom cover 25 mm and end cover 40 mm are used. * Then concreting is done around the beam.
Details of the Construction Materials learned today * Murum filling side of beam. * Formwork material. * Concrete ( 1:1.5:3) M20 * Cement - 43 grade OPC. * Sand - River sand. * Aggregate - 20 to 25 mm size * Water from bore well. * Steel--- MAIN BAR- Anchor bar- 10.00 mm Straight bar- 12.00 mm Bent up bar- 12.00 mm Stirrups- 6.00 mm @ 150 mm c/c 42 nos. * Superplasticizers (admixture). * Tamping Rod and Needle vibrator
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Small size of bar are provided . So large amount of steel will be reduced.
Details of the Construction / Engineering Drawings observed today * First we observed working drawing the beam layout plan. * According to this plan position is selected. * After this actual quantity of steel require from steel structure drawing provided.
Details of the Bye Laws referred today STAIWAYS: * Flight- No flight shall contain more than 12 risers, but in residential building, in gaothan or congestade area a single flight staircase may be permitted. * Risers- The maximum height of a riser shall be 19 cm. in a recidential building and 15 cm. in any other occupancy. However on an internal stircase within a dwelling unit a riser may be 25 cm. high. * Treads- The maximum width of the tread without nosing shall be 25 cm. for staircase of a residential building.
Details of any Managerial Skill learned today * To check the workdone of beam and water tank. * With the help of linedori, tape, gunya, etc.we mark distance of main bar, anchor bar, stirrups etc. * Then the fixing the exist position of beam
RATE ANALYSIS (Detailed Stepwise Calculations required) M 20 (7.4 BAGS) (1:1.5:3) BEAM SIZE- 540 X 230 X 6050 MM Top bars- 2no. 10.00mm dia. Bottom bar- 2 no. 12.00mm dia Bent up bar- 1 no. 12.00 mm dia stirrups- 6.00 mm @ 150 mm c/c CALCULATION- Cement- 7.4 x 250 = 1850/- Sand - 1.25 x 7.4 x 1.5 x 35 = 490/- Aggregate- 1.25 x 7.4 x 3 x 18 = 500/- Steel- 12.68 kg.x 35 = 450/- Labour- 1 sqm. 5.50 rs taken = 1400/-
Result of RATE ANALYSIS ( Rs per Unit ) 6253.33 /-
Todays BUZZ Word Types of contractor- * Labour contractor * Material contractor Scope of labour contractor- The scope of the contractor\'s work including all R.C.C. work connected with the building such as fotting, column, beam, lintel, overhead water tank, chajja, plinth level, staircase, slab, removal of material, plinth filling, soiling, p.c.c. work. etc. Scope of material contractor- To supply the construction material on site such as, brick, steel, aggregate, sand, murum, tiles, plywood, wood, sanitary materials, etc.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 13567-03

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Students Name (Surname_First Name_Middle Name) Sawant Ganesh Rajendra
Exam No. 13567
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Work allotted :- 1)Quantity analysis of Beam. 2)Preparing check list for column casting. .
Details of how you Planned & Executed the allotted work We prepare the check list (as per IS 456:2000) of allotted work and execute the work as per check list and drawings. Check list:- Precautions before Concreting:- Size & diagonals to ensure right angles of column. (ii) Plumb (Olamba) of column. (iii) Covering to reinforcement. (iv) Concreting (Bharai) should be up to plinth beam bottom. Carry out concreting of column with specified mix. During concreting don\'t allow labours to pull or push the reinforcements. Check List for Column shuttering:- a. Proper covering must be provided for column reinforcement preferably on the ring. b. The casting level must be marked on the column before casting. c. Before casting cement slurry must be poured on the joint. d. The casted top must be maintained rough so as to have good joint with beam. e. There should be a master ring at the top of filling level. f. Before fixing the formwork, the material used for shuttering should have a coat of an oil so as to have good finishing. g. The care should be taken that the reinforcement should free from oil. h. Channel should be always of 3\"x 3\" or of standard size available and should be fixed at 1\'3\"C/C. i. First Channel & last channel should be fixed 6\" C/C at top and bottom respectively. j. Shikanjas should be fixed on upper side, on both side of Channel. k. Modia should not be greater than 9\" size. l. Starter should be cast before starting the column so as to prevent segregation at the joint between slab & column. m. Centre to centre distance to be checked at starter point and at the top of column. n. Column alignment should be at right angle at top of column. o. Before & after casting the verticality of column must be checked. p. Column face and side should be parallel in line dori. q. Plank supports should not be normally allowed for columns. Props with choti at top should be fixed Channel. r. Top of column should be always be maintained rough or chipped off after casting of columns to remove laitance. s. Starter shuttering is done in channels preferably. t. Minimum Cover:- u. Minimum cover for different structural element: v. (i) Footing - 75 mm (iii) Beam - 20mm w. (ii) Column - 45mm (IV) Slab - 15mm
Details of the Construction Procedure / Activity / Technology learned today Casting of column:- STARTERS 1) After casting plinth slab, column is casted up to 4” height as a starter for column. By checking its size, position and center line distances for more accuracy of column position & location before casting full column. Proper cover for steel reinforcement is maintained. Right angle (katkona) of starter & line should be checked.Remove the laitance at plinth top in column area. 2) Erect column shuttering of specified size. Support it & do it tight by channels, nut-bolts or scanteling (chavi) & shikanja at 6\" from bottom & top intermediates should be at 1\' 3\" center to center. 3) Mark the filling level on the Column steel or formwork. 4) Pour the cement slurry on the starter, so as to have sufficient cement paste at joint. 5) Place the concrete and do the vibration with the help of needle vibrator. 6) When column is filled to required depth stop pouring concrete, vibrate the last layer and make the top surface rough. . .
Details of the Construction Materials learned today Vibrator:- It is used to compact the concrete up to maximum possible density. Types:- 1)Needle Vibrator 2)Surface Vibrator 3)Screed Vibrator 4)Platform Vibrator 5)Table Vibrator We use Needle vibrator on site. We have both electric and diesel vibrator as stand-by. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today On our site special efforts are taken regarding use of water. Water becomes scare in summer. Therefore we use water very carefully.
Details of the Construction / Engineering Drawings observed today 1)R.C.C. drawing of beam and slab. 2)Working drawing of respective drawing. .
Details of the Bye Laws referred today Minimum dimensions of doors and windows, and slab height. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Beam size:-300x450 R.C.C Design of beam:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Span of beam: - Assume 3m . Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 9923.72 /-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-03

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Students Name (Surname_First Name_Middle Name) Shivtare Prabhakar Chandrakant
Exam No. 13569
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Work allotted :- 1)Quantity analysis of Beam. 2)Preparing check list for column casting. .
Details of how you Planned & Executed the allotted work We prepare the check list (as per IS 456:2000) of allotted work and execute the work as per check list and drawings. Check list:- Precautions before Concreting:- Size & diagonals to ensure right angles of column. (ii) Plumb (Olamba) of column. (iii) Covering to reinforcement. (iv) Concreting (Bharai) should be up to plinth beam bottom. Carry out concreting of column with specified mix. During concreting don\'t allow labours to pull or push the reinforcements. Check List for Column shuttering:- a. Proper covering must be provided for column reinforcement preferably on the ring. b. The casting level must be marked on the column before casting. c. Before casting cement slurry must be poured on the joint. d. The casted top must be maintained rough so as to have good joint with beam. e. There should be a master ring at the top of filling level. f. Before fixing the formwork, the material used for shuttering should have a coat of an oil so as to have good finishing. g. The care should be taken that the reinforcement should free from oil. h. Channel should be always of 3\"x 3\" or of standard size available and should be fixed at 1\'3\"C/C. i. First Channel & last channel should be fixed 6\" C/C at top and bottom respectively. j. Shikanjas should be fixed on upper side, on both side of Channel. k. Modia should not be greater than 9\" size. l. Starter should be cast before starting the column so as to prevent segregation at the joint between slab & column. m. Centre to centre distance to be checked at starter point and at the top of column. n. Column alignment should be at right angle at top of column. o. Before & after casting the verticality of column must be checked. p. Column face and side should be parallel in line dori. q. Plank supports should not be normally allowed for columns. Props with choti at top should be fixed Channel. r. Top of column should be always be maintained rough or chipped off after casting of columns to remove laitance. s. Starter shuttering is done in channels preferably. t. Minimum Cover:- u. Minimum cover for different structural element: v. (i) Footing - 75 mm (iii) Beam - 20mm w. (ii) Column - 45mm (IV) Slab - 15mm
Details of the Construction Procedure / Activity / Technology learned today Casting of column:- STARTERS 1) After casting plinth slab, column is casted up to 4” height as a starter for column. By checking its size, position and center line distances for more accuracy of column position & location before casting full column. Proper cover for steel reinforcement is maintained. Right angle (katkona) of starter & line should be checked.Remove the laitance at plinth top in column area. 2) Erect column shuttering of specified size. Support it & do it tight by channels, nut-bolts or scanteling (chavi) & shikanja at 6\" from bottom & top intermediates should be at 1\' 3\" center to center. 3) Mark the filling level on the Column steel or formwork. 4) Pour the cement slurry on the starter, so as to have sufficient cement paste at joint. 5) Place the concrete and do the vibration with the help of needle vibrator. 6) When column is filled to required depth stop pouring concrete, vibrate the last layer and make the top surface rough. . .
Details of the Construction Materials learned today Vibrator:- It is used to compact the concrete up to maximum possible density. Types:- 1)Needle Vibrator 2)Surface Vibrator 3)Screed Vibrator 4)Platform Vibrator 5)Table Vibrator We use Needle vibrator on site. We have both electric and diesel vibrator as stand-by. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today On our site special efforts are taken regarding use of water. Water becomes scare in summer. Therefore we use water very carefully.
Details of the Construction / Engineering Drawings observed today 1)R.C.C. drawing of beam and slab. 2)Working drawing of respective drawing. .
Details of the Bye Laws referred today Minimum dimensions of doors and windows, and slab height. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Beam size:-300x450 R.C.C Design of beam:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Span of beam: - Assume 3m . Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 9923.72 /-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: mayur.sonawane61@gmail.com
Subject: 13570-03

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Students Name (Surname_First Name_Middle Name) Sonawane Mayur Madhukar
Exam No. 13570
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Work allotted :- 1)Quantity analysis of Beam. 2)Preparing check list for column casting. .
Details of how you Planned & Executed the allotted work We prepare the check list (as per IS 456:2000) of allotted work and execute the work as per check list and drawings. Check list:- Precautions before Concreting:- Size & diagonals to ensure right angles of column. (ii) Plumb (Olamba) of column. (iii) Covering to reinforcement. (iv) Concreting (Bharai) should be up to plinth beam bottom. Carry out concreting of column with specified mix. During concreting don\'t allow labours to pull or push the reinforcements. Check List for Column shuttering:- a. Proper covering must be provided for column reinforcement preferably on the ring. b. The casting level must be marked on the column before casting. c. Before casting cement slurry must be poured on the joint. d. The casted top must be maintained rough so as to have good joint with beam. e. There should be a master ring at the top of filling level. f. Before fixing the formwork, the material used for shuttering should have a coat of an oil so as to have good finishing. g. The care should be taken that the reinforcement should free from oil. h. Channel should be always of 3\"x 3\" or of standard size available and should be fixed at 1\'3\"C/C. i. First Channel & last channel should be fixed 6\" C/C at top and bottom respectively. j. Shikanjas should be fixed on upper side, on both side of Channel. k. Modia should not be greater than 9\" size. l. Starter should be cast before starting the column so as to prevent segregation at the joint between slab & column. m. Centre to centre distance to be checked at starter point and at the top of column. n. Column alignment should be at right angle at top of column. o. Before & after casting the verticality of column must be checked. p. Column face and side should be parallel in line dori. q. Plank supports should not be normally allowed for columns. Props with choti at top should be fixed Channel. r. Top of column should be always be maintained rough or chipped off after casting of columns to remove laitance. s. Starter shuttering is done in channels preferably. t. Minimum Cover:- u. Minimum cover for different structural element: v. (i) Footing - 75 mm (iii) Beam - 20mm w. (ii) Column - 45mm (IV) Slab - 15mm
Details of the Construction Procedure / Activity / Technology learned today Casting of column:- STARTERS 1) After casting plinth slab, column is casted up to 4” height as a starter for column. By checking its size, position and center line distances for more accuracy of column position & location before casting full column. Proper cover for steel reinforcement is maintained. Right angle (katkona) of starter & line should be checked.Remove the laitance at plinth top in column area. 2) Erect column shuttering of specified size. Support it & do it tight by channels, nut-bolts or scanteling (chavi) & shikanja at 6\" from bottom & top intermediates should be at 1\' 3\" center to center. 3) Mark the filling level on the Column steel or formwork. 4) Pour the cement slurry on the starter, so as to have sufficient cement paste at joint. 5) Place the concrete and do the vibration with the help of needle vibrator. 6) When column is filled to required depth stop pouring concrete, vibrate the last layer and make the top surface rough. . .
Details of the Construction Materials learned today Vibrator:- It is used to compact the concrete up to maximum possible density. Types:- 1)Needle Vibrator 2)Surface Vibrator 3)Screed Vibrator 4)Platform Vibrator 5)Table Vibrator We use Needle vibrator on site. We have both electric and diesel vibrator as stand-by. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today On our site special efforts are taken regarding use of water. Water becomes scare in summer. Therefore we use water very carefully.
Details of the Construction / Engineering Drawings observed today 1)R.C.C. drawing of beam and slab. 2)Working drawing of respective drawing. .
Details of the Bye Laws referred today Minimum dimensions of doors and windows, and slab height. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Beam size:-300x450 R.C.C Design of beam:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Span of beam: - Assume 3m . Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 9923.72 /-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-03

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Students Name (Surname_First Name_Middle Name) Sutar Namdev Rangnath
Exam No. 13571
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Work allotted :- 1)Quantity analysis of Beam. 2)Preparing check list for column casting. .
Details of how you Planned & Executed the allotted work We prepare the check list (as per IS 456:2000) of allotted work and execute the work as per check list and drawings. Check list:- Precautions before Concreting:- Size & diagonals to ensure right angles of column. (ii) Plumb (Olamba) of column. (iii) Covering to reinforcement. (iv) Concreting (Bharai) should be up to plinth beam bottom. Carry out concreting of column with specified mix. During concreting don\'t allow labours to pull or push the reinforcements. Check List for Column shuttering:- a. Proper covering must be provided for column reinforcement preferably on the ring. b. The casting level must be marked on the column before casting. c. Before casting cement slurry must be poured on the joint. d. The casted top must be maintained rough so as to have good joint with beam. e. There should be a master ring at the top of filling level. f. Before fixing the formwork, the material used for shuttering should have a coat of an oil so as to have good finishing. g. The care should be taken that the reinforcement should free from oil. h. Channel should be always of 3\"x 3\" or of standard size available and should be fixed at 1\'3\"C/C. i. First Channel & last channel should be fixed 6\" C/C at top and bottom respectively. j. Shikanjas should be fixed on upper side, on both side of Channel. k. Modia should not be greater than 9\" size. l. Starter should be cast before starting the column so as to prevent segregation at the joint between slab & column. m. Centre to centre distance to be checked at starter point and at the top of column. n. Column alignment should be at right angle at top of column. o. Before & after casting the verticality of column must be checked. p. Column face and side should be parallel in line dori. q. Plank supports should not be normally allowed for columns. Props with choti at top should be fixed Channel. r. Top of column should be always be maintained rough or chipped off after casting of columns to remove laitance. s. Starter shuttering is done in channels preferably. t. Minimum Cover:- u. Minimum cover for different structural element: v. (i) Footing - 75 mm (iii) Beam - 20mm w. (ii) Column - 45mm (IV) Slab - 15mm
Details of the Construction Procedure / Activity / Technology learned today Casting of column:- STARTERS 1) After casting plinth slab, column is casted up to 4” height as a starter for column. By checking its size, position and center line distances for more accuracy of column position & location before casting full column. Proper cover for steel reinforcement is maintained. Right angle (katkona) of starter & line should be checked.Remove the laitance at plinth top in column area. 2) Erect column shuttering of specified size. Support it & do it tight by channels, nut-bolts or scanteling (chavi) & shikanja at 6\" from bottom & top intermediates should be at 1\' 3\" center to center. 3) Mark the filling level on the Column steel or formwork. 4) Pour the cement slurry on the starter, so as to have sufficient cement paste at joint. 5) Place the concrete and do the vibration with the help of needle vibrator. 6) When column is filled to required depth stop pouring concrete, vibrate the last layer and make the top surface rough. . .
Details of the Construction Materials learned today Vibrator:- It is used to compact the concrete up to maximum possible density. Types:- 1)Needle Vibrator 2)Surface Vibrator 3)Screed Vibrator 4)Platform Vibrator 5)Table Vibrator We use Needle vibrator on site. We have both electric and diesel vibrator as stand-by. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today On our site special efforts are taken regarding use of water. Water becomes scare in summer. Therefore we use water very carefully.
Details of the Construction / Engineering Drawings observed today 1)R.C.C. drawing of beam and slab. 2)Working drawing of respective drawing. .
Details of the Bye Laws referred today Minimum dimensions of doors and windows, and slab height. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Beam size:-300x450 R.C.C Design of beam:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Span of beam: - Assume 3m . Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 9923.72 /-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-03

Company Name P. B. Builders & Developers
Project Name & Site Address P.B.DEVELOPERS , PREETAM RESIDENCY , SAMRAT-NAGAR
Students Name (Surname_First Name_Middle Name) Shinde Sagar Arvind
Exam No. 13568
Working Day No. 03
Date (DD/MM/YYYY) 10/12/2010
Site Reporting Time (HH:MM am/pm) 09:00 AM
Site Leaving Time (HH:MM am/pm) 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge Work allotted :- 1)Quantity analysis of Beam. 2)Preparing check list for column casting. .
Details of how you Planned & Executed the allotted work We prepare the check list (as per IS 456:2000) of allotted work and execute the work as per check list and drawings. Check list:- Precautions before Concreting:- Size & diagonals to ensure right angles of column. (ii) Plumb (Olamba) of column. (iii) Covering to reinforcement. (iv) Concreting (Bharai) should be up to plinth beam bottom. Carry out concreting of column with specified mix. During concreting don\'t allow labours to pull or push the reinforcements. Check List for Column shuttering:- a. Proper covering must be provided for column reinforcement preferably on the ring. b. The casting level must be marked on the column before casting. c. Before casting cement slurry must be poured on the joint. d. The casted top must be maintained rough so as to have good joint with beam. e. There should be a master ring at the top of filling level. f. Before fixing the formwork, the material used for shuttering should have a coat of an oil so as to have good finishing. g. The care should be taken that the reinforcement should free from oil. h. Channel should be always of 3\"x 3\" or of standard size available and should be fixed at 1\'3\"C/C. i. First Channel & last channel should be fixed 6\" C/C at top and bottom respectively. j. Shikanjas should be fixed on upper side, on both side of Channel. k. Modia should not be greater than 9\" size. l. Starter should be cast before starting the column so as to prevent segregation at the joint between slab & column. m. Centre to centre distance to be checked at starter point and at the top of column. n. Column alignment should be at right angle at top of column. o. Before & after casting the verticality of column must be checked. p. Column face and side should be parallel in line dori. q. Plank supports should not be normally allowed for columns. Props with choti at top should be fixed Channel. r. Top of column should be always be maintained rough or chipped off after casting of columns to remove laitance. s. Starter shuttering is done in channels preferably. t. Minimum Cover:- u. Minimum cover for different structural element: v. (i) Footing - 75 mm (iii) Beam - 20mm w. (ii) Column - 45mm (IV) Slab - 15mm
Details of the Construction Procedure / Activity / Technology learned today Casting of column:- STARTERS 1) After casting plinth slab, column is casted up to 4” height as a starter for column. By checking its size, position and center line distances for more accuracy of column position & location before casting full column. Proper cover for steel reinforcement is maintained. Right angle (katkona) of starter & line should be checked.Remove the laitance at plinth top in column area. 2) Erect column shuttering of specified size. Support it & do it tight by channels, nut-bolts or scanteling (chavi) & shikanja at 6\" from bottom & top intermediates should be at 1\' 3\" center to center. 3) Mark the filling level on the Column steel or formwork. 4) Pour the cement slurry on the starter, so as to have sufficient cement paste at joint. 5) Place the concrete and do the vibration with the help of needle vibrator. 6) When column is filled to required depth stop pouring concrete, vibrate the last layer and make the top surface rough. . .
Details of the Construction Materials learned today Vibrator:- It is used to compact the concrete up to maximum possible density. Types:- 1)Needle Vibrator 2)Surface Vibrator 3)Screed Vibrator 4)Platform Vibrator 5)Table Vibrator We use Needle vibrator on site. We have both electric and diesel vibrator as stand-by. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today On our site special efforts are taken regarding use of water. Water becomes scare in summer. Therefore we use water very carefully.
Details of the Construction / Engineering Drawings observed today 1)R.C.C. drawing of beam and slab. 2)Working drawing of respective drawing. .
Details of the Bye Laws referred today Minimum dimensions of doors and windows, and slab height. .
Details of any Managerial Skill learned today Motivation and encouragement given to workers can help in getting better output. .
RATE ANALYSIS (Detailed Stepwise Calculations required) Beam size:-300x450 R.C.C Design of beam:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Span of beam: - Assume 3m . Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /- .
Result of RATE ANALYSIS ( Rs per Unit ) Rs. 9923.72 /-
Todays BUZZ Word Contractors:- 1) Labor contractor: - In the construction industry labor supply in mainly from West Bengal and other stated from north. During summer season in Maharashtra when construction activities are going on, there’s a harvesting and sowing season in north region. This leads to acute shortage of labor and this problem is solved by Labor Contractor. 2) Carpenter/Formwork contractor:- This contractor does the all work regarding formwork. He finds the skilled labors and executes the work. 3) Fitter/Steel Contractor:- This contractor does all the work regarding reinforcement. He finds skilled labor and executes the work. 4) Masonry Work Contractor:- This contractor does all masonry related work, including brickwork, plaster and water-proofing. A specialist water-proofing agency or contractor may be appointed if required. 5) Plumbing Contractor:- This contractor executed all work related plumbing. He laid the pips, does the fitting work of taps, WC pans, wash basins etc. 6) A/C Contractor:- This is the special type of contractor. Appointed only in special situations or requirements. He does the air conditioning work. 7) Painting Contractor:- This contractor executes all painting related work, like painting, POP, etc. 8) Electrical Contractor:- This contractor does all the electrification related work. 9) Material Contractor:- This contractor keeps the good supply of material as and when required. 10) All in one Contractor:- Some contractors execute all construction related work under one head. Those are all in one contractors. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal 9423281981 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/10/2010
E-mail Address: profiipathan@gmail.com
Subject: Testing 10.12.2010 - 1

Company Name Star Tech Infra
Project Name & Site Address p
Students Name (Surname_First Name_Middle Name) p
Exam No. p
Working Day No. p
Date (DD/MM/YYYY) p
Site Reporting Time (HH:MM am/pm) p
Site Leaving Time (HH:MM am/pm) p
Details of the Work Allotted to you today by the Site In-Charge p
Details of how you Planned & Executed the allotted work p
Details of the Construction Procedure / Activity / Technology learned today p
Details of the Construction Materials learned today p
Details of Environment Caring Technology / Methodology / Procedure / Product learned today p
Details of the Construction / Engineering Drawings observed today p
Details of the Bye Laws referred today p
Details of any Managerial Skill learned today p
RATE ANALYSIS (Detailed Stepwise Calculations required) p
Result of RATE ANALYSIS ( Rs per Unit ) p
Todays BUZZ Word p
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge p
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: rameshkharat1987@gmail.com
Subject: 13532-02

Exam No. 13532
Company Name & Site Address rajesh construction
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 09:00 am
Site Leaving Time 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1.to fix the level of building with respect to road level 2 to observes centre line plan (building. Line out )
Details of how you Planned & Executed the allotted work Take the level tube,fill it with water. Remove the air bubbles. To take accurate result and to transfer the road level we took one steel rod & mark accurate hight on it transfered that level on the plinth level of building we observed the center line plan among ourself. Given by site incharg and asked him all the detail of construction of wood strips,bamboo for desiding column position
Details of the Construction Procedure / Activity / Technology learned today 1.to deside the length of stirrups bar 2.fixing of column position with the help of plumb bob 3.details of cantiliver slab steel design and hanging beam
Details of the Construction Materials learned today Levelling pipe-to transfer the road level to construct plinth hight
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Using of steel supporting formwork insted of wood formwork, it will reduce the deforestation
Details of the Construction / Engineering Drawings observed today 1.centre line plan-fixing outline plot bondry,margin 2.column layout plan-position of column 3.steel design plan of second floor slab and beam
Details of the Bye Laws referred today 1.plinth hight-minimum 600 mm. 2.hight of door-2100 mm.
Details of any Managerial Skill learned today Site incharge is very co- operative,friendly and enthusiastic he has comand on the worker
RATE ANALYSIS Proportion 1: 1.5:3 Volume of concreat 1 cu.m. Total volume=1.52 Cement=1.52/5.5=0.2763 cu.m. No of bags=0.2763/0.035=7.89=8*260=2080 Rs. Sand=0.2763*1.5=0.4144*725=300.44 Rs. Agg.=0.2763*3=0.8289*450=373 Rs. Cost of material =2753 Labour=600 Reinforcement=2880 Total=6233
Todays BUZZ Word Building line out is nothing but the centre line plan.There are column position and centre lines,plot bondry, distance frpm plot bondry,distance between the column are given in the layout plan
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: v.g.ayyar@gmail.com
Subject: 13553-02

Exam No. 13553
Company Name & Site Address Shendre Associates
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 10:00am
Site Leaving Time 5:00pm
Details of the Work Allotted to you today by the Site In-Charge To shift the level of the road on the site with the help of Level tube.
Details of how you Planned & Executed the allotted work -First we distributed ourselves into two groups -Than we executed the work.
Details of the Construction Procedure / Activity / Technology learned today About the \'Paint House\'. We studied the plans and thus are acquinted with paint house.
Details of the Construction Materials learned today About the \"BRICK MASONARY\" and various bonds of brick masonary.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today About the \'PAINT HOUSE\".
Details of the Bye Laws referred today Heights of residential buildings.
Details of any Managerial Skill learned today Today we learnt about the utilization of various avalible materials.
RATE ANALYSIS Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 3. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 4. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. =41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000 days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 = 262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. =45173.99 Unit Cost per cu.mt is : Rs4517.399.
Todays BUZZ Word \"Building Line Out\" 1. Cleaning the site & levelling it. 2. Demarcation of plot & marking actual boundaries by theodolite survey. 3. Preparing contour survey. 4. Checking all levels with respect to fixed Bench Mark. 5. Checking with concerned authorities. 6. Checking Center line Drawings. 7. Construction of boundary walls. 8. Checking required dimensions & Set backs.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vivek Randive. 8805494033.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: sujata.fulari@gmail.com
Subject: 13559-02

Exam No. 13559
Company Name & Site Address Shendre Associates
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 10:00am
Site Leaving Time 05:00 pm
Details of the Work Allotted to you today by the Site In-Charge To shift the level of the road on the site with the help of Level tube.
Details of how you Planned & Executed the allotted work -First we distributed ourselves into two groups -Than we executed the work.
Details of the Construction Procedure / Activity / Technology learned today About the \'Paint House\'. We studied the plans and thus are acquinted with paint house.
Details of the Construction Materials learned today About the \"BRICK MASONARY\" and various bonds of brick masonary.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today About the \'PAINT HOUSE\".
Details of the Bye Laws referred today Heights of residential buildings.
Details of any Managerial Skill learned today Today we learnt about the utilization of various avalible materials.
RATE ANALYSIS Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 3. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 4. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. =41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000 days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 = 262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. =45173.99 Unit Cost per cu.mt is : Rs4517.399.
Todays BUZZ Word \"Building Line Out\" 1. Cleaning the site & levelling it. 2. Demarcation of plot & marking actual boundaries by theodolite survey. 3. Preparing contour survey. 4. Checking all levels with respect to fixed Bench Mark. 5. Checking with concerned authorities. 6. Checking Center line Drawings. 7. Construction of boundary walls. 8. Checking required dimensions & Set backs.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vivek Randive. 8805494033.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: pratikpatil5555@gmail.com
Subject: 13549-02

Exam No. 13549
Company Name & Site Address Shendre Associates
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 10:00am
Site Leaving Time 05:00 pm
Details of the Work Allotted to you today by the Site In-Charge To shift the level of the road on the site with the help of Level tube.
Details of how you Planned & Executed the allotted work -First we distributed ourselves into two groups -Than we executed the work.
Details of the Construction Procedure / Activity / Technology learned today About the \'Paint House\'. We studied the plans and thus are acquinted with paint house.
Details of the Construction Materials learned today About the \"BRICK MASONARY\" and various bonds of brick masonary.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today About the \'PAINT HOUSE\".
Details of the Bye Laws referred today Heights of residential buildings.
Details of any Managerial Skill learned today Today we learnt about the utilization of various avalible materials.
RATE ANALYSIS Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 3. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 4. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. =41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000 days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 = 262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. =45173.99 Unit Cost per cu.mt is : Rs4517.399.
Todays BUZZ Word \"Building Line Out\" 1. Cleaning the site & levelling it. 2. Demarcation of plot & marking actual boundaries by theodolite survey. 3. Preparing contour survey. 4. Checking all levels with respect to fixed Bench Mark. 5. Checking with concerned authorities. 6. Checking Center line Drawings. 7. Construction of boundary walls. 8. Checking required dimensions & Set backs.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vivek Randive. 8805494033.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: dbauchakar@gmail.com
Subject: 13554-01

Exam No. 13554
Company Name & Site Address Shendre Associates
Working Day No. 01
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 10:00am
Site Leaving Time 05:00 pm
Details of the Work Allotted to you today by the Site In-Charge To shift the level of the road on the site with the help of Level tube.
Details of how you Planned & Executed the allotted work -First we distributed ourselves into two groups -Than we executed the work.
Details of the Construction Procedure / Activity / Technology learned today About the \'Paint House\'. We studied the plans and thus are acquinted with paint house.
Details of the Construction Materials learned today About the \"BRICK MASONARY\" and various bonds of brick masonary.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today About the \'PAINT HOUSE\".
Details of the Bye Laws referred today Heights of residential buildings.
Details of any Managerial Skill learned today Today we learnt about the utilization of various avalible materials.
RATE ANALYSIS Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 3. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 4. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. =41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000 days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 = 262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. =45173.99 Unit Cost per cu.mt is : Rs4517.399.
Todays BUZZ Word \"Building Line Out\" 1. Cleaning the site & levelling it. 2. Demarcation of plot & marking actual boundaries by theodolite survey. 3. Preparing contour survey. 4. Checking all levels with respect to fixed Bench Mark. 5. Checking with concerned authorities. 6. Checking Center line Drawings. 7. Construction of boundary walls. 8. Checking required dimensions & Set backs.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vivek Randive. 8805494033.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: vishalr2844@gmail.com
Subject: 13555-01

Exam No. 13555
Company Name & Site Address Shendre Associates
Working Day No. 01
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 10:00am
Site Leaving Time 05:00 pm
Details of the Work Allotted to you today by the Site In-Charge To shift the level of the road on the site with the help of Level tube.
Details of how you Planned & Executed the allotted work -First we distributed ourselves into two groups -Than we executed the work.
Details of the Construction Procedure / Activity / Technology learned today About the \'Paint House\'. We studied the plans and thus are acquinted with paint house.
Details of the Construction Materials learned today About the \"BRICK MASONARY\" and various bonds of brick masonary.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None
Details of the Construction / Engineering Drawings observed today About the \'PAINT HOUSE\".
Details of the Bye Laws referred today Heights of residential buildings.
Details of any Managerial Skill learned today Today we learnt about the utilization of various avalible materials.
RATE ANALYSIS Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 3. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 4. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. =41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000 days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 = 262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. =45173.99 Unit Cost per cu.mt is : Rs4517.399.
Todays BUZZ Word \"Building Line Out\" 1. Cleaning the site & levelling it. 2. Demarcation of plot & marking actual boundaries by theodolite survey. 3. Preparing contour survey. 4. Checking all levels with respect to fixed Bench Mark. 5. Checking with concerned authorities. 6. Checking Center line Drawings. 7. Construction of boundary walls. 8. Checking required dimensions & Set backs.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr.Vivek Randive. 8805494033.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: ayyar.vignesh@gmail.com
Subject: 13553-02

Exam No. 13553
Company Name & Site Address Shendre Associates
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 10:00am
Site Leaving Time 05:00 pm
Details of the Work Allotted to you today by the Site In-Charge To shift the level of the road on the site with the help of Level tube.
Details of how you Planned & Executed the allotted work -First we distributed ourselves into two groups -Than we executed the work.
Details of the Construction Procedure / Activity / Technology learned today About the \'Paint House\'. We studied the plans and thus are acquinted with paint house.
Details of the Construction Materials learned today About the \"BRICK MASONARY\" and various bonds of brick masonary.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today None.
Details of the Construction / Engineering Drawings observed today About the \'PAINT HOUSE\".
Details of the Bye Laws referred today Heights of residential buildings.
Details of any Managerial Skill learned today Today we learnt about the utilization of various avalible materials.
RATE ANALYSIS Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 3. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 4. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. =41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000 days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 = 262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. =45173.99 Unit Cost per cu.mt is : Rs4517.399.
Todays BUZZ Word \"Building Line Out\" 1. Cleaning the site & levelling it. 2. Demarcation of plot & marking actual boundaries by theodolite survey. 3. Preparing contour survey. 4. Checking all levels with respect to fixed Bench Mark. 5. Checking with concerned authorities. 6. Checking Center line Drawings. 7. Construction of boundary walls. 8. Checking required dimensions & Set backs.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vivek Randive. 8805494033.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: ketaki.hasabnis@gmail.com
Subject: 13527-02

Exam No. 13527
Company Name & Site Address Pooja Developers & Builders
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00 a.m.
Site Leaving Time 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge To check dimensions and location of column according to the given plan.
Details of how you Planned & Executed the allotted work We are five of us. We were given 3 sheets . First sheet contained the plan . Second sheet contained the details of columns. Third contained the location of columns.Three of us studied these sheets and other two checked the dimensions of columns on site.
Details of the Construction Procedure / Activity / Technology learned today We learnt how to remove the form work. We studied weigh packing of aggregates, mixing of aggregates, cement and water to prepare concrete, placing of concrete, compaction by rod.
Details of the Construction Materials learned today 1) Aggregate of 12.5mm. 2) Sieved sand of 1.18mm size. 3) Cement of 53grade 4) Using Fly Ash bricks for construction of compund wall
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Chew(chute) system for recycling the Garbage and unusable material
Details of the Construction / Engineering Drawings observed today Detail column plan with its sizes,numbers and position from X&Y-axis
Details of the Bye Laws referred today To measure floor to floor distance and referred to bye laws according to type of building
Details of any Managerial Skill learned today Inspection of the work by site incharge, communication by supervisor with workers.
RATE ANALYSIS ----------------------------------------------------------------------- Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 4. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 5. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. = 41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000 days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 = 262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. = 45173.99 Unit Cost per cu.mt is : Rs. = 4517.399
Todays BUZZ Word We were given drawing of Center line plan was given to us and we were asked to study it. We observed the line out which was done by labourers. Line is nothing but simply putting out the drawing onto the ground and carrying out the work.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: sachinepatilthk@gmail.com
Subject: 13539-02

Exam No. 13539
Company Name & Site Address SN Builders-Animash Nagar
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. line out of building 2. observation of steel work for slab 3. observation of column position
Details of how you Planned & Executed the allotted work 1. observed the plan & position of column 2. study the column sizes & marked the center
Details of the Construction Procedure / Activity / Technology learned today 1. arrangement of steel bar according to design 2. proper binding of bar 3. observation of specific position of curtal bar
Details of the Construction Materials learned today 1.various sizes of steel bar 2. various sizes cover sample
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. solar water heater provided according to owner requirement
Details of the Construction / Engineering Drawings observed today 1. section drawing 2. plinth drawing 3. line out plan
Details of the Bye Laws referred today 1. height of building
Details of any Managerial Skill learned today 1.good communication with custmer 2. command on lebour
RATE ANALYSIS for column M20 mix 1. cement =23 x 250RS =5750RS 2. aggregate =90cu.ft.x 15 =1350RS 3. sand =50 cu.ft.x37=1850RS 4. labour =400RS 5. water curing =70RS total=9420RS with c.p.20% =11304RS for 1 cu. ft.=113.04RS 6. basic rate =113.04RS 7. steel 3Kg x37RS=111RS 8. labour =28RS with c.p.20%=302.448RS 9. total in cu. mt. =11201.77RS
Todays BUZZ Word building line out 1. building is parallel to selected face 1. select the face of building 1. select face of building 2. select other side diagonal to that side 3. mark the position of column on ground 4. mark the center of the column 5. select the zero line 6. measure the distance between the column from that zero line
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Sagar Nalang Sir - 9423043044
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: vishwajit.pog@gmail.com
Subject: 13543-02

Exam No. 13543
Company Name & Site Address SN Builders-Animash Nagar
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. line out of building 2. observation of steel work for slab 3. observation of column position
Details of how you Planned & Executed the allotted work 1. observed the plan & position of column 2. study the column sizes & marked the center
Details of the Construction Procedure / Activity / Technology learned today 1. arrangement of steel bar according to design 2. proper binding of bar 3. observation of specific position of curtal bar
Details of the Construction Materials learned today 1.various sizes of steel bar 2. various sizes cover sample
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. solar water heater provided according to owner requirement
Details of the Construction / Engineering Drawings observed today 1. section drawing 2. plinth drawing 3. line out plan
Details of the Bye Laws referred today 1. height of building
Details of any Managerial Skill learned today 1.good communication with custmer 2. command on lebour
RATE ANALYSIS M20 mix 1. cement =23 x 250RS =5750RS 2. aggregate =90cu.ft.x 15 =1350RS 3. sand =50 cu.ft.x37=1850RS 4. labour =400RS 5. water curing =70RS total=9420RS with c.p.20% =11304RS for 1 cu. ft.=113.04RS 6. basic rate =113.04RS 7. steel 3Kg x37RS=111RS 8. labour =28RS with c.p.20%=302.448RS 9. total in cu. mt. =11201.77RS
Todays BUZZ Word 1. select face of building 2. select other side diagonal to that side 3. mark the position of column on ground 4. mark the center of the column 5. select the zero line 6. measure the distance between the column from that zero line
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Sagar Nalang Sir - 9423043044
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: ankitraje9@gmail.com
Subject: 10893-02

Exam No. 10893
Company Name & Site Address Vishwa Enclave - V.S,Joshi Associates
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:30 am
Site Leaving Time 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - Study of various components like electrification, plumbing, sanitary fittings, floorings, doors & windows, fastenings and fixtures etc of a ready duplex flat with their specifications.
Details of how you Planned & Executed the allotted work - Grouping of work with respective indivisual study of component was done. - Complete study of these components with their specifications like nos., sizes, orientation from floor level, colour, & type of material was done.
Details of the Construction Procedure / Activity / Technology learned today - \"Finishing Of Brick Bat Coba with Cement Sand Mortar\" - Materials Used: Cement, Sand, Water - Equipments Used: Floats, Trowels, Spades, Ghamelas etc. - Procedure: The mortar mixture of sand & cement was mixed properly on a water tight Container. Then mortar was placed on the required surface using ghamelas & the mortared surface was equally spread & leveled using Floats. Then it was left for drying.
Details of the Construction Materials learned today - \"Fastenings & Fixtures\" for doors & windows which includes Tower Bolt, Safety Chain, Eye Piece, D Type Handle, Night Latch, PVC Gattu, Aldrop, Door Stopper, Tadi Patti.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not observed such Methodology today.
Details of the Construction / Engineering Drawings observed today Plans For Flat No 104, C-Wing, Vishwa Enclave - 4 BHK Flat. - Duplex Flat. - 1 Master Bed with Attached Toilet. - Individual Toilet cum Bath at Each Floor. - Total Carpet Area: (FF:675.50 Sq.Ft, SF:628.37 Sq.Ft) 1303.87 Sq.Ft - Terrace Area: 136.50Sq.Ft - Salable Area: 1763.28 Sq.Ft
Details of the Bye Laws referred today 1. Sizes of Bath & WC 2. Sizes of Kitchen
Details of any Managerial Skill learned today To Control Wastage of materials like cement, sand etc. Also how to store Materials.
RATE ANALYSIS \"Rate Analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/-
Todays BUZZ Word \"Building Line Out\" 1. Cleaning the site & levelling it. 2. Demarcation of plot & marking actual boundaries by theodolite survey. 3. Preparing contour survey. 4. Checking all levels with respect to fixed Bench Mark. 5. Checking with concerned authorities. 6. Checking Center line Drawings. 7. Construction of boundary walls. 8. Checking required dimensions & Set backs.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: gauravdesai75@gmail.com
Subject: 13522-02

Exam No. 13522
Company Name & Site Address Pooja Builders and Developers, near jay prabha studio,Kolhapur
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00 AM
Site Leaving Time 4.00 PM
Details of the Work Allotted to you today by the Site In-Charge To check the position & size of column for according to plan. To watch the process of concreting of stair-case for third floor.
Details of how you Planned & Executed the allotted work *Out of we five students one holded the main plan. *Second student holded detail plan of column i.e. dia.& number of bar. *Third student holded column position plan i.e. location from X-axis & Y-axis. *Rest two students measured and checked the details according to plan.
Details of the Construction Procedure / Activity / Technology learned today 1) Manual weigh batching. 2) Mixing concrete with mixer. 3) Transporting concrete with two methods: a) Bucket(skip) & hoist type from ground floor to second floor transporting b) Wheel barrows for transporting concrete on same floor. 4) Compaction with rodding for stairs.
Details of the Construction Materials learned today 1) Aggregate of 12.5mm. 2) Sieved sand of 1.18mm size. 3) Cement of 53grade.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Garbage chew (chute) system: All solid waste materials like plastic will get disposed and regenerated.
Details of the Construction / Engineering Drawings observed today * Detail Column Plan with all its sizes,numbers and position from X&Y-axis for different floor.
Details of the Bye Laws referred today To measure floor to floor distance and referred to bye laws according to type of building. According to bye laws, minimum head requirement for garage is 2.4m. On site it is provided 3.8m. According to bye laws, maximum height of riser is 190 mm. On site it is provided 160 mm. According to bye laws,minimum width of treads is 250 mm. On site it is provided 300 mm.
Details of any Managerial Skill learned today He inspect building work and good communication with labourers. He inspects at the place where concreting is done. He inspects the place where the materials are mixed in the mixer whether they are in correct proportion or not.
RATE ANALYSIS Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 4. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 5. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material :Rs. = 41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 = 262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. = 45173.99 Unit Cost per cu.mt is : Rs. = 4517.399
Todays BUZZ Word First the drawing of Center line plan was given to us and asked us study it. then we saw the line out which was done by labours. Line is nothing but simply putting out the drawing onto the ground and carrying out the work. The Site plan showing the details of F.S.I.,Rear Margins,Front margins,Side margins etc was not available at the site for reference.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.SUTAR PH NO.9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: vishwajeetjape@gmail.com
Subject: 10892-02

Exam No. 10892
Company Name & Site Address Vishwa Enclave - V.S,Joshi Associates
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:30 am
Site Leaving Time 05:30 pm
Details of the Work Allotted to you today by the Site In-Charge - Study of various components like electrification, plumbing, sanitary fittings, floorings, doors & windows, fastenings and fixtures etc of a ready duplex flat with their specifications.
Details of how you Planned & Executed the allotted work - Grouping of work with respective indivisual study of component was done. - Complete study of these components with their specifications like nos., sizes, orientation from floor level, colour, & type of material was done.
Details of the Construction Procedure / Activity / Technology learned today - \"Finishing Of Brick Bat Coba with Cement Sand Mortar\" - Materials Used: Cement, Sand, Water - Equipments Used: Floats, Trowels, Spades, Ghamelas etc. - Procedure: The mortar mixture of sand & cement was mixed properly on a water tight Container. Then mortar was placed on the required surface using ghamelas & the mortared surface was equally spread & leveled using Floats. Then it was left for drying.
Details of the Construction Materials learned today - \"Fastenings & Fixtures\" for doors & windows which includes Tower Bolt, Safety Chain, Eye Piece, D Type Handle, Night Latch, PVC Gattu, Aldrop, Door Stopper, Tadi Patti.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not observed such Methodology today.
Details of the Construction / Engineering Drawings observed today Plans For Flat No 104, C-Wing, Vishwa Enclave - 4 BHK Flat. - Duplex Flat. - 1 Master Bed with Attached Toilet. - Individual Toilet cum Bath at Each Floor. - Total Carpet Area: (FF:675.50 Sq.Ft, SF:628.37 Sq.Ft) 1303.87 Sq.Ft - Terrace Area: 136.50Sq.Ft - Salable Area: 1763.28 Sq.Ft
Details of the Bye Laws referred today 1. Sizes of Bath & WC 2. Sizes of Kitchen
Details of any Managerial Skill learned today To Control Wastage of materials like cement, sand etc. Also how to store Materials.
RATE ANALYSIS \"Rate Analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/-
Todays BUZZ Word \"Building Line Out\" 1. Cleaning the site & levelling it. 2. Demarcation of plot & marking actual boundaries by theodolite survey. 3. Preparing contour survey. 4. Checking all levels with respect to fixed Bench Mark. 5. Checking with concerned authorities. 6. Checking Center line Drawings. 7. Construction of boundary walls. 8. Checking required dimensions & Set backs.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523-02

Exam No. 13523
Company Name & Site Address Pooja Developers & Builders
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:00am
Site Leaving Time 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To check the position & size of column according to plan.
Details of how you Planned & Executed the allotted work *Out of we five student one holded the main plan. *Second student holded detail plan of column i.e. dia.& number of bar. *Third student holded column position plan i.e. location from X-axis & Y-axis. *Rest two student measured the detail according to plan.
Details of the Construction Procedure / Activity / Technology learned today 1) Manual weigh batching. 2) Mixing concrete with mixer. 3) Transporting concrete with two methods: a) Bucket & hoist type from ground floor to second floor transporting b) Wheel barrows for transporting concrete on same floor. 4) Compaction with rodding for stairs.
Details of the Construction Materials learned today 1) Aggregate of 12.5mm. 2) Sieved sand of 1.18mm size. 3) Cement of 53grade
Details of Environment Caring Technology / Methodology / Procedure / Product learned today * Garbage chew (chute) system: All solid waste materials through plastic will get disposed and regenerated
Details of the Construction / Engineering Drawings observed today * Detail column plan with all its sizes,numbers and position from
Details of the Bye Laws referred today * To measure floor to floor distance and referred to bye laws according to type of building.
Details of any Managerial Skill learned today He inspect building work and good communication with laboures
RATE ANALYSIS ----------------------------------------------------------------------- Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 4. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 5. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. = 41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000 days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 =262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. = 45173.99 Unit Cost per cu.mt is : Rs. = 4517.399
Todays BUZZ Word First the drawing of Center line plan was given to us and asked us study it. then we saw the line out which was done by labours. Line is nothing but simply putting out the drawing onto the ground and carrying out the work
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: nikitashinde15@gmail.com
Subject: 13547-02

Exam No. 13547
Company Name & Site Address SN Builders-Animash Nagar
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. line out of building 2. observation of steel work for slab 3. observation of column position
Details of how you Planned & Executed the allotted work 1. observed the plan & position of column 2. study the column sizes & marked the center
Details of the Construction Procedure / Activity / Technology learned today 1. arrangement of steel bar according to design 2. proper binding of bar 3. observation of specific position of curtal bar
Details of the Construction Materials learned today 1.various sizes of steel bar 2. various sizes cover sample
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. solar water heater provided according to owner requirement
Details of the Construction / Engineering Drawings observed today 1. section drawing 2. plinth drawing 3. line out plan
Details of the Bye Laws referred today 1. height of building
Details of any Managerial Skill learned today 1.good communication with custmer 2. command on lebour
RATE ANALYSIS M20 mix 1. cement =23 x 250RS =5750RS 2. aggregate =90cu.ft.x 15 =1350RS 3. sand =50 cu.ft.x37=1850RS 4. labour =400RS 5. water curing =70RS total=9420RS with c.p.20% =11304RS for 1 cu. ft.=113.04RS 6. basic rate =113.04RS 7. steel 3Kg x37RS=111RS 8. labour =28RS with c.p.20%=302.448RS 9. total in cu. mt. =11201.77RS
Todays BUZZ Word 1. select face of building 2. select other side diagonal to that side 3. mark the position of column on ground 4. mark the center of the column 5. select the zero line 6. measure the distance between the column from that zero line
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Sagar Nalang Sir - 9423043044
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: yogesh200512@gmail.com
Subject: 10894-02

Exam No. 10894
Company Name & Site Address Vishwa Enclave - V.S,Joshi Associates
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:30 am
Site Leaving Time 5:30 pm
Details of the Work Allotted to you today by the Site In-Charge - Study of various components like electrification, plumbing, sanitary fittings, floorings, doors & windows, fastenings and fixtures etc of a ready duplex flat with their specifications.
Details of how you Planned & Executed the allotted work - Grouping of work with respective indivisual study of component was done. - Complete study of these components with their specifications like nos., sizes, orientation from floor level, colour, & type of material was done.
Details of the Construction Procedure / Activity / Technology learned today - \"Finishing Of Brick Bat Coba with Cement Sand Mortar\" - Materials Used: Cement, Sand, Water - Equipments Used: Floats, Trowels, Spades, Ghamelas etc. - Procedure: The mortar mixture of sand & cement was mixed properly on a water tight Container. Then mortar was placed on the required surface using ghamelas & the mortared surface was equally spread & leveled using Floats. Then it was left for drying.
Details of the Construction Materials learned today - \"Fastenings & Fixtures\" for doors & windows which includes Tower Bolt, Safety Chain, Eye Piece, D Type Handle, Night Latch, PVC Gattu, Aldrop, Door Stopper, Tadi Patti.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not observed such Methodology today.
Details of the Construction / Engineering Drawings observed today Plans For Flat No 104, C-Wing, Vishwa Enclave - 4 BHK Flat. - Duplex Flat. - 1 Master Bed with Attached Toilet. - Individual Toilet cum Bath at Each Floor. - Total Carpet Area: (FF:675.50 Sq.Ft, SF:628.37 Sq.Ft) 1303.87 Sq.Ft - Terrace Area: 136.50Sq.Ft - Salable Area: 1763.28 Sq.Ft
Details of the Bye Laws referred today 1. Sizes of Bath & WC 2. Sizes of Kitchen
Details of any Managerial Skill learned today To Control Wastage of materials like cement, sand etc. Also how to store Materials.
RATE ANALYSIS \"Rate Analysis For Safety Door\" Size Of Door: 7\' x 5\'6\" Material Quantity Rate Rs(per Sq.Ft) Amount(Rs) 1. Rectangular Tube 19\'6\" 44.00/- 858.00/- 2. Square Bar 22\'6\" 12.25/- 275.60/- 3. 1.5\" x 3/4\" Rectangular Tube 64\'0\" 38.50/- 2464.00/- 4. Perforated sheet 18 Sq Ft 50.00/- 900.00/- 5. Hinges, Tower Bolts etc. 550.00/- Total = 5047.60/- + 5% Wastage = 252.38/- Total = 5299.98/- + Transportation = 70.00/- Total = 5369.98/- Labour Charges 38.50 Sq.Ft 60.00/- = 7679.98/- Area of Door = 7\'x 5\'6\" = 39\'2\" = 3.64 Sq.m Rate For 1Sq.m = 7679.98/3.64 = 2109.88/-
Todays BUZZ Word \"Building Line Out\" 1. Cleaning the site & levelling it. 2. Demarcation of plot & marking actual boundaries by theodolite survey. 3. Preparing contour survey. 4. Checking all levels with respect to fixed Bench Mark. 5. Checking with concerned authorities. 6. Checking Center line Drawings. 7. Construction of boundary walls. 8. Checking required dimensions & Set backs.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol A Mulay (9922507376)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: dineshbagmare@gmail.com
Subject: 13521-01

Exam No. 13521
Company Name & Site Address pooja developers & builders
Working Day No. 01
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:00 am
Site Leaving Time 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge To check the position & size of column according to plan.
Details of how you Planned & Executed the allotted work *Out of we five student one holded the main plan. *Second student holded detail plan of column i.e. dia.& number of bar. *Third student holded column position plan i.e. location from X-axis & Y-axis. *Rest two student measured the detail according to plan.
Details of the Construction Procedure / Activity / Technology learned today 1) Manual weigh batching. 2) Mixing concrete with mixer. 3) Transporting concrete with two methods: a) Bucket & hoist type from ground floor to second floor transporting b) Wheel barrows for transporting concrete on same floor. 4) Compaction with rodding for stairs
Details of the Construction Materials learned today 1) Aggregate of 12.5mm. 2) Sieved sand of 1.18mm size. 3) Cement of 53grade
Details of Environment Caring Technology / Methodology / Procedure / Product learned today * Garbage chew (chute) system: All solid waste materials through plastic will get disposed and regenerated.
Details of the Construction / Engineering Drawings observed today * Detail column plan with all its sizes,numbers and position from X&Y-axis.
Details of the Bye Laws referred today * To measure floor to floor distance and referred to bye laws according to type of building.
Details of any Managerial Skill learned today * He inspect building work and good communication with laboures.
RATE ANALYSIS ----------------------------------------------------------------------- Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 4. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 5. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. = 41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000 days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 = 262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. = 45173.99 Unit Cost per cu.mt is : Rs. =4517.399
Todays BUZZ Word First the drawing of Center line plan was given to us and asked us study it. then we saw the line out which was done by labours. Line is nothing but simply putting out the drawing onto the ground and carrying out the work.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-02

Exam No. 13540
Company Name & Site Address SN Builders-Animash Nagar
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. line out of building 2. observation of steel work for slab 3. observation of column position
Details of how you Planned & Executed the allotted work 1. observed the plan & position of column 2. study the column sizes & marked the center
Details of the Construction Procedure / Activity / Technology learned today 1. arrangement of steel bar according to design 2. proper binding of bar 3. observation of specific position of curtal bar
Details of the Construction Materials learned today 1.various sizes of steel bar 2. various sizes cover sample
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. solar water heater provided according to owner requirement
Details of the Construction / Engineering Drawings observed today 1. section drawing 2. plinth drawing 3. line out plan
Details of the Bye Laws referred today 1. height of building
Details of any Managerial Skill learned today 1.good communication with custmer 2. command on lebour
RATE ANALYSIS M20 mix 1. cement =23 x 250RS =5750RS 2. aggregate =90cu.ft.x 15 =1350RS 3. sand =50 cu.ft.x37=1850RS 4. labour =400RS 5. water curing =70RS total=9420RS with c.p.20% =11304RS for 1 cu. ft.=113.04RS 6. basic rate =113.04RS 7. steel 3Kg x37RS=111RS 8. labour =28RS with c.p.20%=302.448RS 9. total in cu. mt. =11201.77RS
Todays BUZZ Word 1. select face of building 2. select other side diagonal to that side 3. mark the position of column on ground 4. mark the center of the column 5. select the zero line 6. measure the distance between the column from that zero line
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Sagar Nalang Sir - 9423043044
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: shyamkolekar14@rediffmail.com
Subject: 13533-02

Exam No. 13533
Company Name & Site Address rajesh construction
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 09:00 am
Site Leaving Time 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge 1.to fix the level of building with respect to road level. 2.to observe the center line plan
Details of how you Planned & Executed the allotted work Take level pipe,fill it with water, remove air bubble to take accurate fresult and to transfer the road level, we took one rod and marked at required hight and transfer that level on the construction site we just observe the centre line plan among ourself given by site incharge and asked him all the details to construct wood strips,bamboo for desiding column posion
Details of the Construction Procedure / Activity / Technology learned today 1.to deside the length of stirrups bar 2.fixing of column position with the help of plumb bob 3.details of cantiliver slab steel design and hanging beam
Details of the Construction Materials learned today Levelling pipe-to transfer the road level to construct plinth hight
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Using of steel supporting formwork instead of wood formwork it will reduce the cutting of trees
Details of the Construction / Engineering Drawings observed today 1.centre line plan-fixing out line plot bondry,margin 2.column layout plan-posion of column 3.steel design plan of second floor plan and beam
Details of the Bye Laws referred today 1.plinth hight-min-600 mm 2.hight of door-2100 mm
Details of any Managerial Skill learned today Site incharge is very co-oprative, friendly& enthusiastic. He has command on the worker
RATE ANALYSIS praportion- 1:1.5:3 For 1 cu.m. Volume of concreat is 1.52 Cement content is 0.2763 No of bags 7.89=8 8*260=2080 Rs sand=0.2763*1.5=0.4144cu m 0.4144*725=300.44 Agg. 0.2763*3=0.8289*450=373 Cost of material is 2753 Labour=600 Reinforcement is 90 kg *32=2880 Total cost is 623
Todays BUZZ Word Building line out is nothing but centre line plan.there are column position and centre lines,plote bondry,distance from plot bondry distances between the columns are given in the lay out plan
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Milind Magdum 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: rajendrapawar54@gmail.com
Subject: 13542-02

Exam No. 13542
Company Name & Site Address SN Builders-Animash Nagar
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge 1. line out of building 2. observation of steel work for slab 3. observation of column position
Details of how you Planned & Executed the allotted work 1. observed the plan & position of column 2. study the column sizes & marked the center
Details of the Construction Procedure / Activity / Technology learned today 1. arrangement of steel bar according to design 2. proper binding of bar 3. observation of specific position of curtal bar
Details of the Construction Materials learned today 1.various sizes of steel bar 2. various sizes cover sample
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1. solar water heater provided according to owner requirement
Details of the Construction / Engineering Drawings observed today 1. section drawing 2. plinth drawing 3. line out plan
Details of the Bye Laws referred today 1. height of building
Details of any Managerial Skill learned today 1.good communication with customer 2. command on laboure
RATE ANALYSIS for column M20 mix 1. cement =23 x 250RS =5750RS 2. aggregate =90cu.ft.x 15 =1350RS 3. sand =50 cu.ft.x37=1850RS 4. labour =400RS 5. water curing =70RS total=9420RS with c.p.20% =11304RS for 1 cu. ft.=113.04RS 6. basic rate =113.04RS 7. steel 3Kg x37RS=111RS 8. labour =28RS with c.p.20%=302.448RS 9. total in cu. mt. =11201.77RS
Todays BUZZ Word 1. select face of building 2. select other side diagonal to that side 3. mark the position of column on ground 4. mark the center of the column 5. select the zero line 6. measure the distance between the column from that zero line
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Sagar Nalang Sir - 9423043044
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: swaroopsardar144@gmail.com
Subject: 13561-02

Exam No. 13561
Company Name & Site Address Chougale Sawant Developers Shree Samarth Nagar
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 09:00am
Site Leaving Time 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To study the how the columns are fixed in vertical right angled position
Details of how you Planned & Executed the allotted work we discous with sineor engg,then go to site.
Details of the Construction Procedure / Activity / Technology learned today We saw the starters of columns first.The steel reinforcement of column & around shuttering procedure is seen. The clips known as \"shikanja\" in labour language are used to hold the shuttering tightly and also the \"props\" are used to support the column shuttering. The small concrete cylinder blocks are used to check exact 90degree vertical position.for this nails fixed top most part of shuttering, block cylinder with string tie to nail and adjusting shuttering as the horizontal distance at top & bottom is same.this means column is in exact vertical position.
Details of the Construction Materials learned today We observed the crush sand.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of fly ash brick.
Details of the Construction / Engineering Drawings observed today We studied the footing drawing.
Details of the Bye Laws referred today For fixing plot boundary side margins are kept as For Front - 4.5m, Rare - 3.0m, Side - 2.25m
Details of any Managerial Skill learned today How to communicate with contractors
RATE ANALYSIS For R.C.C. Column, Qty.= 1 metercube Material Quantity(kg) Rate(Rs.) 1.Cement 310 1280 2.Aggregate 150 680 3.Sand 120 380 4.Steel 165 5700 Total Rs.= 8040 Add wastage 2% & labour charges Grand Total Rs.= 10000
Todays BUZZ Word Building Line Out - Procedure 1.As per approved drawing of building plot boundary is fixed. 2.Then base line marked on field. 3.Then nails are fixed on both ends of base line. 4.String is tie around nail 5.Then chock pit sprayed on ground exactly below tied string. 6.In this way the line is marked on ground.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Suhas Jadhav,Mo.No.8007415015
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: viju128@gmail.com
Subject: 3638-02

Exam No. 3638
Company Name & Site Address starinfratech-star aashiyana
Working Day No. 02
Date (DD/MM/YYYY) 09/12/10
Site Reporting Time 9am
Site Leaving Time 4pm
Details of the Work Allotted to you today by the Site In-Charge -PCC work done which was laid below the pavment -Site margins of the building -inspection chamber -lift guard laid(Rcc guard 4mm thickness)
Details of how you Planned & Executed the allotted work -for pcc we planned that it should be truly horizontal therefore we made sure that it is fully compacted with 4inch thickness -we arranged a 6meter tape for measuring all the lenths -we made sure that it is on which point and located from our bylaws book for further details -we discussed the method could be used for com[paction and how to operate them along being economical
Details of the Construction Procedure / Activity / Technology learned today -for pcc hammer randha and thappi were used along with trowel -simple tapes were used along with leveling tube -pipes and turn elbows were used along with it -to support plywood squares along with shikangas
Details of the Construction Materials learned today -pcc(plain concrete cement) 1:3:6 was used - tapes -steel bars -shikanjas -different types of pipes
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panel was used for water heating above the roof
Details of the Construction / Engineering Drawings observed today parking drawing along with garden provided side margins in side plan and set back line along the center of the road
Details of the Bye Laws referred today side margins in side plan and set back line along the center of the road
Details of any Managerial Skill learned today hand compaction work used through rammers and vertical plywood is horizontally beaten
RATE ANALYSIS Rate analysis for column /1 m3 concrete rate = 3300 Rs labour cost = 33 Rs/Ft3 1 m3 = 35.28 Ft3 so, 1 m3 = 35.28 * 33 = 1165 labour cost / 1 m3 total cost = 3300+1165=4465 add 5%wastage 223=4688 add 20% profit of contractor=938 total=5626 using 75kg steel bar in 1m3 rcc=2775 total=5626+2775 =8401per 1m3 for column
Todays BUZZ Word building line out front margin=4.5 meter rare margin =3meter side margin=2.25meter
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish mob no.9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: pinkrosee4u@yahoo.com
Subject: 10878

Exam No. 10878
Company Name & Site Address star tec infra (rajendar nagar)
Working Day No. 2
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9:00 am
Site Leaving Time 4:00 pm
Details of the Work Allotted to you today by the Site In-Charge work alloted ,jus 2 observe d pcc work....n rate analysis 4 rcc column...
Details of how you Planned & Executed the allotted work v observed mixing , placing....n compacting actions...4 pcc.n then calculate rate 4 column
Details of the Construction Procedure / Activity / Technology learned today v observed form work , dey wer working 4 lift n then placing of concrete in fomwork n compacting.
Details of the Construction Materials learned today nothig....jus pcc work
Details of Environment Caring Technology / Methodology / Procedure / Product learned today v observed dat solar water heater used at one bounglow
Details of the Construction / Engineering Drawings observed today parking drawings....
Details of the Bye Laws referred today v observed bye laws of set back line.
Details of any Managerial Skill learned today u sud b loyel 2 ur work
RATE ANALYSIS rate analiysis: rcc 4 colum per m^3 concrete rate = 3300/- per m^3 labour cost =38 rs/ft^3 1^3 =35.28 ft^3 1m^3 = 35.28*33= 1165 Rs/m^3 total cost=3300 +1165=4465 add 5% wastage =4465+223 =4688 add 20% profit of contractor+steel 100 kg = 9326/m^3
Todays BUZZ Word building out line..... front margin =4.5m rare margin = 3m side margin = 2.25 m according 2 bye laws
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge shateesh mistree
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: saurabh.arora.yo@gmail.com
Subject: 10883-1

Exam No. 10883
Company Name & Site Address starinfartech-star aashiyana
Working Day No. 1
Date (DD/MM/YYYY) 09/12/10
Site Reporting Time 9am
Site Leaving Time 4pm
Details of the Work Allotted to you today by the Site In-Charge -PCC work done which was laid below the pavment -Site margins of the building -inspection chamber -lift guard laid(Rcc guard 4mm thickness)
Details of how you Planned & Executed the allotted work -for pcc we planned that it should be truly horizontal therefore we made sure that it is fully compacted with 4inch thickness -we arranged a 6meter tape for measuring all the lenths -we made sure that it is on which point and located from our bylaws book for further details -we discussed the method could be used for com[paction and how to operate them along being economical
Details of the Construction Procedure / Activity / Technology learned today -for pcc hammer randha and thappi were used along with trowel -simple tapes were used along with leveling tube -pipes and turn elbows were used along with it -to support plywood squares along with shikangas
Details of the Construction Materials learned today -pcc(plain concrete cement) 1:3:6 was used - tapes -steel bars -shikanjas -different types of pipes
Details of Environment Caring Technology / Methodology / Procedure / Product learned today solar panel was used for water heating above the roof
Details of the Construction / Engineering Drawings observed today parking drawing along with garden provided side margins in side plan and set back line along the center of the road
Details of the Bye Laws referred today parking drawing along with garden provided side margins in side plan and set back line along the center of the road
Details of any Managerial Skill learned today hand compaction work used through rammers and vertical plywood is horizontally beaten
RATE ANALYSIS Rate analysis for column /1 m3 concrete rate = 3300 Rs labour cost = 33 Rs/Ft3 1 m3 = 35.28 Ft3 so, 1 m3 = 35.28 * 33 = 1165 labour cost / 1 m3 total cost = 3300+1165=4465 add 5%wastage 223=4688 add 20% profit of contractor=938 total=5626 using 75kg steel bar in 1m3 rcc=2775 total=5626+2775 =8401per 1m3 for column
Todays BUZZ Word building line out front margin=4.5 meter rare margin =3meter side margin=2.25meter
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge satish 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: manoj31989@gmail.com
Subject: 13536-02

Exam No. 13536
Company Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 a.m.
Site Leaving Time 4 p.m.
Details of the Work Allotted to you today by the Site In-Charge * TO CHECK LINE-OUT WORK OF BUILDING-\'A\'(1-BHK)
Details of how you Planned & Executed the allotted work * We devided our work. * Two were refering R.C.C. plan & two were taking measurment.
Details of the Construction Procedure / Activity / Technology learned today * We learn about how to mark footing. * Curring of R.C.C. slab by ponding method. * Working of tilting type mixture.
Details of the Construction Materials learned today *STEEL* Diameter(mm) Weight(kg/m) Use 6 0.222 stirrups 8 0.395 extra top 10 0.616 extra bottom 12 0.888 extra bottom 16 1.578 main column bar
Details of Environment Caring Technology / Methodology / Procedure / Product learned today * Use of P.P.C. (Zuari cement-43) containing fly ash. * They use excavated murum for filling.
Details of the Construction / Engineering Drawings observed today * We observe R.C.C. plan, site plan, working plan for building-\'a\'(1-bhk).
Details of the Bye Laws referred today * For \'ROW HOUSE\' floor height is 2.7m (min). * They provided setback distance as per BYE-LAWS. * They have provided toilet sizes ass per BYE-LAWS.
Details of any Managerial Skill learned today * Manager used to inform main worker as per todays working plan.
RATE ANALYSIS *R.C.C. column* MATERIAL QUANTITY COST(RS) CEMENT 8 BAG 2080 SAND 0.46CuM 520 AGG. 0.84CuM 1134 STEEL 93.04(Kg) 2800 MISTRI - 560 WATER - 100 TOTAL - 7194 FOR 1 CuM - 6000
Todays BUZZ Word *PROCEDURE OF LINE OUT* * According to Site-Plan first fix boundary of plot with respect to road. * Then entire boundary line is cover by wooden bamboo & planks. * According to R.C.C. plan mark center of each column by plumb bob & nylon string. * Excavated the box with some extra margin for formwork adjustment. * After P.C.C. work to mark size column by taking reference from cross nylon string & plumb bob. In this way they complete their work.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. Chougale Mob.no. 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: prashant152011@gmail.com
Subject: 13535-02

Exam No. 13535
Company Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 a.m.
Site Leaving Time 4 p.m.
Details of the Work Allotted to you today by the Site In-Charge * TO CHECK LINE-OUT WORK OF BUILDING-\'A\'(1-BHK)
Details of how you Planned & Executed the allotted work * We devided our work. * Two were refering R.C.C. plan & two were taking measurment.
Details of the Construction Procedure / Activity / Technology learned today * We learn about how to mark footing. * Curring of R.C.C. slab by ponding method. * Working of tilting type mixture.
Details of the Construction Materials learned today *STEEL* Diameter(mm) Weight(kg/m) Use 6 0.222 stirrups 8 0.395 extra top 10 0.616 extra bottom 12 0.888 extra bottom 16 1.578 main column bar
Details of Environment Caring Technology / Methodology / Procedure / Product learned today * Use of P.P.C. (Zuari cement-43) containing fly ash. * They use excavated murum for filling.
Details of the Construction / Engineering Drawings observed today * We observe R.C.C. plan, site plan, working plan for building-\'a\'(1-bhk).
Details of the Bye Laws referred today * For \'ROW HOUSE\' floor height is 2.7m (min). * They provided setback distance as per BYE-LAWS. * They have provided toilet sizes ass per BYE-LAWS.
Details of any Managerial Skill learned today * Manager used to inform main worker as per todays working plan.
RATE ANALYSIS *R.C.C. column* MATERIAL QUANTITY COST(RS) CEMENT 8 BAG 2080 SAND 0.46CuM 520 AGG. 0.84CuM 1134 STEEL 93.04(Kg) 2800 MISTRI - 560 WATER - 100 TOTAL - 7194 FOR 1 CuM - 6000
Todays BUZZ Word *PROCEDURE OF LINE OUT* * According to Site-Plan first fix boundary of plot with respect to road. * Then entire boundary line is cover by wooden bamboo & planks. * According to R.C.C. plan mark center of each column by plumb bob & nylon string. * Excavated the box with some extra margin for formwork adjustment. * After P.C.C. work to mark size column by taking reference from cross nylon string & plumb bob. In this way they complete their work.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. Chougale Mob.no. 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: adionline16jan@gmail.com
Subject: 13538-02

Exam No. 13538
Company Name & Site Address Vetex/Tirupati Construction Varun Vihar Uchagaon kolhapur
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 a.m.
Site Leaving Time 4 p.m.
Details of the Work Allotted to you today by the Site In-Charge * TO CHECK LINE-OUT WORK OF BUILDING-\'A\'(1-BHK)
Details of how you Planned & Executed the allotted work * We devided our work. * Two were refering R.C.C. plan & two were taking measurment.
Details of the Construction Procedure / Activity / Technology learned today * We learn about how to mark footing. * Curring of R.C.C. slab by ponding method. * Working of tilting type mixture.
Details of the Construction Materials learned today *STEEL* Diameter(mm) Weight(kg/m) Use 6 0.222 stirrups 8 0.395 extra top 10 0.616 extra bottom 12 0.888 extra bottom 16 1.578 main column bar
Details of Environment Caring Technology / Methodology / Procedure / Product learned today * Use of P.P.C. (Zuari cement-43) containing fly ash. * They use excavated murum for filling.
Details of the Construction / Engineering Drawings observed today * We observe R.C.C. plan, site plan, working plan for building-\'a\'(1-bhk).
Details of the Bye Laws referred today * For \'ROW HOUSE\' floor height is 2.7m (min). * They provided setback distance as per BYE-LAWS. * They have provided toilet sizes ass per BYE-LAWS.
Details of any Managerial Skill learned today * Manager used to inform main worker as per todays working plan.
RATE ANALYSIS *R.C.C. column* MATERIAL QUANTITY COST(RS) CEMENT 8 BAG 2080 SAND 0.46CuM 520 AGG. 0.84CuM 1134 STEEL 93.04(Kg) 2800 MISTRI - 560 WATER - 100 TOTAL - 7194 FOR 1 CuM - 6000
Todays BUZZ Word *PROCEDURE OF LINE OUT* * According to Site-Plan first fix boundary of plot with respect to road. * Then entire boundary line is cover by wooden bamboo & planks. * According to R.C.C. plan mark center of each column by plumb bob & nylon string. * Excavated the box with some extra margin for formwork adjustment. * After P.C.C. work to mark size column by taking reference from cross nylon string & plumb bob. In this way they complete their work.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. J.J. Chougale Mob.no. 9763414876
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: minakshi.b2011@gmail.com
Subject: 13556-02

Exam No. 13556
Company Name & Site Address DESHMUKH DEVELOPMENTS, PRATIBHA NAGAR
Working Day No. 02
Date (DD/MM/YYYY) 9/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today we are observe how to steel bars are placed in a slab place. how to bind together and bend at end of the bars.
Details of how you Planned & Executed the allotted work Note down the observing important things.The Main bars are placed always parallel to shorter span and Distribution bars are always parallel to longer span.
Details of the Construction Procedure / Activity / Technology learned today Main bars are placed at a distance of 150mm and Distribution bars are placed at a distance of 200mm .After placing both bars they are bind each other by wire with help of hook equipment. Firstly they bind side bars and then central bars because does not disturb the position of bars.
Details of the Construction Materials learned today Today we learned new equipments namely they are wire,hook, crude oil which is used for remoulding and tape is used for marking dimensions.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rain Water Harvesting is provided on every terrace.Work is in progress.Due to this increasing ground water table.
Details of the Construction / Engineering Drawings observed today We are observe all sections for e.g sections A,A1,A2 and sections B,B1,B2,B3 etc.With respective plans and also understanding it.
Details of the Bye Laws referred today We are referred bye laws for spacing between Main bars and Distribution bars for e.g 150mm for main bar, 200mm for distribution bar.
Details of any Managerial Skill learned today The Manager told the workers the slab work is done before tuesday but the work slab work is on thursday. This shows Managerial skill how to the work made by workers before he planned.He has grate time managing skill.
RATE ANALYSIS The propotion is taken as 1:1 1/2:3 For 1m3 52% for dry volume cement=1.52/(1+1.5+3) =0.2763m3 Number of cement bags, =0.2763/0.035 =7.89 =8bags/cum Then Multiply no.of bags with cost /bag =8*260 =2080 sand =0.2763*1.5 =0.4144 m3 Then Multiply above value with cost of sand =0.4144*725 =300.44 Rs Aggregate=0.2763*3 =0.8289*450 =373 Rs cost of material=2753 Rs labour=600 Rs Add 15% profit Total cost=3855.95 And For reinforcements=90kg/cum Multiply above value with cost, =90*32 =2880 Total Net Cost= 3855.95+2880.00 =6733.95 Rs Then
Todays BUZZ Word Firstly marked the boundary of the site,level the ground. Mark the center line of column with help of plumb bob.Placing at each point a big stone or wooden stands are dugged into the ground for identification of center line of column,position of column.Further construct the P.C.C Foundation etc.In this way we are concluded the concept of \"Building Line Out\"
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Abhijit Bhosale
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: nitinpatil22.2010@rediffmail.com
Subject: 10879-02

Exam No. 10879
Company Name & Site Address s.s.builders & developers
Working Day No. 02
Date (DD/MM/YYYY) 9/12/2010
Site Reporting Time 9.00AM
Site Leaving Time 4.00PM
Details of the Work Allotted to you today by the Site In-Charge 1)checking the dimension of buildind block 2)observing the curing
Details of how you Planned & Executed the allotted work 1)first we divided in two groups,then tking yhe readings on two floors . one group in First floor & another 2nd floor
Details of the Construction Procedure / Activity / Technology learned today 1)use the water proofing material for roof or seling insted of planks,steel plates 2)water profing material is NORTHEN 3)due to this plastering & labour cost reduced
Details of the Construction Materials learned today 1)cement block are used for the constuction of the parapet wall & compound wall 2)size of the cement block-(400mm*200mm*150mm)
Details of Environment Caring Technology / Methodology / Procedure / Product learned today 1)septik tank 2)garden & small green trees surrounds the bld
Details of the Construction / Engineering Drawings observed today 1)observing the raw banglows plans -(3BHK flat 6no)
Details of the Bye Laws referred today rear margin,front side rear-3m front-4.9m side-4.3m
Details of any Managerial Skill learned today talking skill with client, talking with the labour or builders.
RATE ANALYSIS 1 cu.m = 1.52 = 0.152 % cement = 1.52 / 1+2+3 = 0.3 No. of Bags = 0.3 / 0.035 = 8.51 Approx 9 Bags = 2340 Rs. Sand = 0.152 x 2 = 0.304 x 725 = 220.4 Rs. Aggregate = 0.152 x 3 = 0.456 = 0.456 x 455 = 295.2 Rs. = 2340 + 2204 + 205.2 + 125 + 200 + 80 = 3170 Column size = (230 x 530 x 3000) mm = 0.3657 cu.m for 1 cu.m = 3170 Rs. 0.3657- ? = 1160 = for 3 meters (1160 x 3) = 3480 Rs. for Steel 16 mm = 10 no. Stirrups = 8 \" @ centre 8 \" ht.= 3 meter wt. = d x d / 162.5 = 16 x 16 / 162.5 = 1600 gm. for 3 m = 1.6 x 3 = 4.8 kg. for 10 nos. = 4.8 x 10 = 48 kg. = 48 x 30 = 1440 Rs. Stirrups = 15 Nos., 3000 8 \" x 25.4 mm Length = 735 mm = 735 x 15 = 11025 mm = 4.41 kg. = 132.3 Rs. Total = 3480 + 1440 + 132 = 5052 Rs. 1) 450 mm x 230 mm x 3000 mm = 15 Nos. of column cost of the one column = 3310 Rs. = 3310 x 15 = 49650 Rs. 2) 610 mm x 230 mm x 3000 mm = 17 Nos. of column cost of the one column = 5863 x 17 = 99671 Rs. 3) 530 mm x 230 mm x 3000 mm = 14 Nos. of column cost of the one column = 5052 x 14 = 70725 Rs. 4) 230 mm x 300 mm x 3000 mm = 4 Nos. of column cost of the one column = 3310 x 4 = 13240 Rs. Total ground floor column cost upto height 3 meter = 233289 Rs.
Todays BUZZ Word Buzzword - Layout - center line method.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Ketan Patil - Site Incharge Mob. No. 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: buntyphonde@gmail.com
Subject: 10899-02

Exam No. 10899
Company Name & Site Address Chandra Milla, Shivshakti Developers
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 09am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today also we have supervised the plastering work. .
Details of how you Planned & Executed the allotted work firstly we went on spot,where plastering was going on.we observed how ingredients are mixed and how much proportion are taken.also we observed how the tools of plastering like trowels,floats are used for plastering. .
Details of the Construction Procedure / Activity / Technology learned today materials- cement,sand,water. on the site internal plastering is going on. tools-pan,spade,trowel,wooden float,aluminium box,plumb bob etc. procedure-first 15 pans sand is spread on the surface.then 1 bag cement is spread over the sand.then it is mixed for 10-15 min.then water is added approx.5 buckets for 1 bag cement.then all the ingredients throughly mixed.then it is applied in two coats.1st coat is applied in thick layer &2nd coat is applied in thin layer. and then finshing is done. .
Details of the Construction Materials learned today the size of steel bar used are 6,10,12,16,20,25mm.steel used is tor415.the rates of steel bar per kg are always varying.the length of steel bar used are about 12-13m. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today less no.of bamboos & more no.of props are used for scaffolding and support. .
Details of the Construction / Engineering Drawings observed today Detail study of line-out drawing is learned today. .
Details of the Bye Laws referred today In bye-laws today we referred provision of lift.it is given that at least one lift shall be provided in building more than16m height. In our site the height is more than 16m and 1 lift is provided. The lift provided in site is from basement to terrace. .
Details of any Managerial Skill learned today The proper communication with the labour on site. .
RATE ANALYSIS Material:- Cement=6.9 bags/ cu.m. @ Rs.260/ bag Rs. 1794/- Sand=0.45 cu.m @ Rs.115/ cu.m Rs. 520/- Aggregate=0.85 cu.m @ Rs. 304/cu.m Rs. 258/- steel=180kg @ Rs. 35/kg Rs. 6300/- Labor cost:- Cement shifting= 6.9bags @ Rs. 1/bag Rs. 6.9/- Sand/Metal shifting @ Rs. 20/cu.m Rs. 20/- Manufacturing and pouring @ Rs. 40/bag Rs. 276/- Finishing Rs. 10/- Formwork material 10.36sq m @Rs.53/sq.m Rs. 599.09/- Formwork making Rs. 10/- Formwork labor with avg. lift 10.36 sq.m Rs. 10/- Tool Plants:- Mixing, vibrator and plant @Rs.14/bag Rs. 96.60/- Fuel charges @ Rs. 2.5/bag Rs. 17.25/- Nails and binding wire, D\'oil @Rs.4/sq m Rs. 41.44/- Plastic cover blocks @Rs.1/ block Rs. 10.36/- Total= Rs. 11700/- .
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Centre-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-2

Exam No. 10876
Company Name & Site Address Star Tech Infra
Working Day No. 2
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9.00 am
Site Leaving Time 4.00 am
Details of the Work Allotted to you today by the Site In-Charge To Watch PCC going on site
Details of how you Planned & Executed the allotted work Observe PCC work going on. Its type of lean concrete.
Details of the Construction Procedure / Activity / Technology learned today Method of appling PCC for flooring.
Details of the Construction Materials learned today Type of lean concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Solar water heater.
Details of the Construction / Engineering Drawings observed today General plan of Building.
Details of the Bye Laws referred today Check Building margins which are as per bye-laws.
Details of any Managerial Skill learned today No.
RATE ANALYSIS Rate for 1cu.m. R,C.C.column. Concrete for 1 cu.m.=3300Rs steel 75kg*37=2775Rs Labour cost 33Rs/sq.ft*35.28=1165Rs t.t.=7240Rs wastage 5%=362Rs t.t.=7602Rs Contractor profit 20%=1520Rs Total price=9122Rs.
Todays BUZZ Word Building lineout Front- 10.5m Rear- 5,5m Side- 7.5m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Satish Mestri 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: prasadkolekar83@rediffmail.com
Subject: 10876-2

Exam No. 10876
Company Name & Site Address Star Tech Infra
Working Day No. 2
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9.00 am
Site Leaving Time 4.00 am
Details of the Work Allotted to you today by the Site In-Charge To Watch PCC going on site
Details of how you Planned & Executed the allotted work Observe PCC work going on. Its type of lean concrete.
Details of the Construction Procedure / Activity / Technology learned today Method of appling PCC for flooring.
Details of the Construction Materials learned today Type of lean concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Solar water heater.
Details of the Construction / Engineering Drawings observed today General plan of Building.
Details of the Bye Laws referred today Check Building margins which are as per bye-laws.
Details of any Managerial Skill learned today No.
RATE ANALYSIS Rate for 1cu.m. R,C.C.column. Concrete for 1 cu.m.=3300Rs steel 75kg*37=2775Rs Labour cost 33Rs/sq.ft*35.28=1165Rs t.t.=7240Rs wastage 5%=362Rs t.t.=7602Rs Contractor profit 20%=1520Rs Total price=9122Rs.
Todays BUZZ Word Building lineout Front- 10.5m Rear- 5,5m Side- 7.5m
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Satish Mestri 9011039689
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-02

Exam No. 10897
Company Name & Site Address Chandra Milla, Shivshakti Developers
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 AM
Site Leaving Time 4 PM
Details of the Work Allotted to you today by the Site In-Charge Today also we have supervised the plastering work. .
Details of how you Planned & Executed the allotted work firstly we went on spot,where plastering was going on.we observed how ingredients are mixed and how much proportion are taken.also we observed how the tools of plastering like trowels,floats are used for plastering. .
Details of the Construction Procedure / Activity / Technology learned today materials- cement,sand,water. on the site internal plastering is going on. tools-pan,spade,trowel,wooden float,aluminium box,plumb bob etc. procedure-first 15 pans sand is spread on the surface.then 1 bag cement is spread over the sand.then it is mixed for 10-15 min.then water is added approx.5 buckets for 1 bag cement.then all the ingredients throughly mixed.then it is applied in two coats.1st coat is applied in thick layer &2nd coat is applied in thin layer. and then finshing is done. .
Details of the Construction Materials learned today the size of steel bar used are 6,10,12,16,20,25mm.steel used is tor415.the rates of steel bar per kg are always varying.the length of steel bar used are about 12-13m. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today less no.of bamboos & more no.of props are used for scaffolding and support. .
Details of the Construction / Engineering Drawings observed today Detail study of line-out drawing is learned today. .
Details of the Bye Laws referred today In bye-laws today we referred provision of lift.it is given that at least one lift shall be provided in building more than16m height. In our site the height is more than 16m and 1 lift is provided. The lift provided in site is from basement to terrace. .
Details of any Managerial Skill learned today The proper communication with the labour on site. .
RATE ANALYSIS Material:- Cement=6.9 bags/ cu.m. @ Rs.260/ bag Rs. 1794/- Sand=0.45 cu.m @ Rs.115/ cu.m Rs. 520/- Aggregate=0.85 cu.m @ Rs. 304/cu.m Rs. 258/- steel=180kg @ Rs. 35/kg Rs. 6300/- Labor cost:- Cement shifting= 6.9bags @ Rs. 1/bag Rs. 6.9/- Sand/Metal shifting @ Rs. 20/cu.m Rs. 20/- Manufacturing and pouring @ Rs. 40/bag Rs. 276/- Finishing Rs. 10/- Formwork material 10.36sq m @Rs.53/sq.m Rs. 599.09/- Formwork making Rs. 10/- Formwork labor with avg. lift 10.36 sq.m Rs. 10/- Tool Plants:- Mixing, vibrator and plant @Rs.14/bag Rs. 96.60/- Fuel charges @ Rs. 2.5/bag Rs. 17.25/- Nails and binding wire, D\'oil @Rs.4/sq m Rs. 41.44/- Plastic cover blocks @Rs.1/ block Rs. 10.36/- Total= Rs. 11700/- .
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Centre-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: abhishekpatil777@gmail.com
Subject: 10895-02

Exam No. 10895
Company Name & Site Address Chandra Milla, Shivshakti Developers
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 09am
Site Leaving Time 4 PM
Details of the Work Allotted to you today by the Site In-Charge Today also we have supervised the plastering work. .
Details of how you Planned & Executed the allotted work firstly we went on spot,where plastering was going on.we observed how ingredients are mixed and how much proportion are taken.also we observed how the tools of plastering like trowels,floats are used for plastering. .
Details of the Construction Procedure / Activity / Technology learned today materials- cement,sand,water. on the site internal plastering is going on. tools-pan,spade,trowel,wooden float,aluminium box,plumb bob etc. procedure-first 15 pans sand is spread on the surface.then 1 bag cement is spread over the sand.then it is mixed for 10-15 min.then water is added approx.5 buckets for 1 bag cement.then all the ingredients throughly mixed.then it is applied in two coats.1st coat is applied in thick layer &2nd coat is applied in thin layer. and then finshing is done. .
Details of the Construction Materials learned today the size of steel bar used are 6,10,12,16,20,25mm.steel used is tor415.the rates of steel bar per kg are always varying.the length of steel bar used are about 12-13m. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today less no.of bamboos & more no.of props are used for scaffolding and support. .
Details of the Construction / Engineering Drawings observed today Detail study of line-out drawing is learned today. .
Details of the Bye Laws referred today In bye-laws today we referred provision of lift.it is given that at least one lift shall be provided in building more than16m height. In our site the height is more than 16m and 1 lift is provided. The lift provided in site is from basement to terrace. .
Details of any Managerial Skill learned today The proper communication with the labour on site. .
RATE ANALYSIS Material:- Cement=6.9 bags/ cu.m. @ Rs.260/ bag Rs. 1794/- Sand=0.45 cu.m @ Rs.115/ cu.m Rs. 520/- Aggregate=0.85 cu.m @ Rs. 304/cu.m Rs. 258/- steel=180kg @ Rs. 35/kg Rs. 6300/- Labor cost:- Cement shifting= 6.9bags @ Rs. 1/bag Rs. 6.9/- Sand/Metal shifting @ Rs. 20/cu.m Rs. 20/- Manufacturing and pouring @ Rs. 40/bag Rs. 276/- Finishing Rs. 10/- Formwork material 10.36sq m @Rs.53/sq.m Rs. 599.09/- Formwork making Rs. 10/- Formwork labor with avg. lift 10.36 sq.m Rs. 10/- Tool Plants:- Mixing, vibrator and plant @Rs.14/bag Rs. 96.60/- Fuel charges @ Rs. 2.5/bag Rs. 17.25/- Nails and binding wire, D\'oil @Rs.4/sq m Rs. 41.44/- Plastic cover blocks @Rs.1/ block Rs. 10.36/- Total= Rs. 11700/- .
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Centre-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: tambetrusha@yahoo.com
Subject: 10902-02

Exam No. 10902
Company Name & Site Address Chandra Milla, Shivshakti Developers
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 AM
Site Leaving Time 4 PM
Details of the Work Allotted to you today by the Site In-Charge Today also we have supervised the plastering work. .
Details of how you Planned & Executed the allotted work firstly we went on spot,where plastering was going on.we observed how ingredients are mixed and how much proportion are taken.also we observed how the tools of plastering like trowels,floats are used for plastering. .
Details of the Construction Procedure / Activity / Technology learned today materials- cement,sand,water. on the site internal plastering is going on. tools-pan,spade,trowel,wooden float,aluminium box,plumb bob etc. procedure-first 15 pans sand is spread on the surface.then 1 bag cement is spread over the sand.then it is mixed for 10-15 min.then water is added approx.5 buckets for 1 bag cement.then all the ingredients throughly mixed.then it is applied in two coats.1st coat is applied in thick layer &2nd coat is applied in thin layer. and then finshing is done. .
Details of the Construction Materials learned today the size of steel bar used are 6,10,12,16,20,25mm.steel used is tor415.the rates of steel bar per kg are always varying.the length of steel bar used are about 12-13m. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today less no.of bamboos & more no.of props are used for scaffolding and support. .
Details of the Construction / Engineering Drawings observed today Detail study of line-out drawing is learned today. .
Details of the Bye Laws referred today In bye-laws today we referred provision of lift.it is given that at least one lift shall be provided in building more than16m height. In our site the height is more than 16m and 1 lift is provided. The lift provided in site is from basement to terrace. .
Details of any Managerial Skill learned today The proper communication with the labour on site. .
RATE ANALYSIS Material:- Cement=6.9 bags/ cu.m. @ Rs.260/ bag Rs. 1794/- Sand=0.45 cu.m @ Rs.115/ cu.m Rs. 520/- Aggregate=0.85 cu.m @ Rs. 304/cu.m Rs. 258/- steel=180kg @ Rs. 35/kg Rs. 6300/- Labor cost:- Cement shifting= 6.9bags @ Rs. 1/bag Rs. 6.9/- Sand/Metal shifting @ Rs. 20/cu.m Rs. 20/- Manufacturing and pouring @ Rs. 40/bag Rs. 276/- Finishing Rs. 10/- Formwork material 10.36sq m @Rs.53/sq.m Rs. 599.09/- Formwork making Rs. 10/- Formwork labor with avg. lift 10.36 sq.m Rs. 10/- Tool Plants:- Mixing, vibrator and plant @Rs.14/bag Rs. 96.60/- Fuel charges @ Rs. 2.5/bag Rs. 17.25/- Nails and binding wire, D\'oil @Rs.4/sq m Rs. 41.44/- Plastic cover blocks @Rs.1/ block Rs. 10.36/- Total= Rs. 11700/- .
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Centre-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: sagar_tekwani@yahoo.com
Subject: 10903-02

Exam No. 10903
Company Name & Site Address Pooja Developers & Builders
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:00am
Site Leaving Time 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To check the position & size of column according to plan.
Details of how you Planned & Executed the allotted work *Out of we five student one holded the main plan. *Second student holded detail plan of column i.e. dia.& number of bar. *Third student holded column position plan i.e. location from X-axis & Y-axis. *Rest two student measured the detail according to plan.
Details of the Construction Procedure / Activity / Technology learned today 1) Manual weigh batching. 2) Mixing concrete with mixer. 3) Transporting concrete with two methods: a) Bucket & hoist type from ground floor to second floor transporting b) Wheel barrows for transporting concrete on same floor. 4) Compaction with rodding for stairs.
Details of the Construction Materials learned today 1) Aggregate of 12.5mm. 2) Sieved sand of 1.18mm size. 3) Cement of 53grade
Details of Environment Caring Technology / Methodology / Procedure / Product learned today * Garbage chew (chute) system: All solid waste materials through plastic will get disposed and regenerated.
Details of the Construction / Engineering Drawings observed today * Detail column plan with all its sizes,numbers and position from X&Y-axis.
Details of the Bye Laws referred today * To measure floor to floor distance and referred to bye laws according to type of building.
Details of any Managerial Skill learned today * He inspect building work and good communication with laboures.
RATE ANALYSIS ----------------------------------------------------------------------- Item : Reinforced Concrete Works Rate Analysis for : 10.000 cu.mt of RCC-M20-1 ----------------------------------------------------------------------- Sr. Description Qty Unit Rate(Rs./Unit) Amount(Rs.) ----------------------------------------------------------------------- ** Material ** Quantity Rate Total 1. 53grade opc cement 61.706 bags 265.00 = 16352.09 2. River sand 5.060 cu.mt 1230.00 = 6223.80 3. Aggregate 10.12cu.mt 1200 = 12144 4. Metal-1 of size 10mm 4.430 cu.mt 795.00 = 3521.85 5. Metal no 1 of size 20mm 4.430 cu.mt 775.00 = 3433.25 Total of Material : Rs. = 41674.99 ** Labour ** 1. Foreman 1.250 days 170.00 = 212.50 2. Mason concreting works 1.500 days 106.00 = 159.00 3. Male Mazdoor 9.000 days 140.00 = 1260.00 4. Female Mazdoor 12.000 days 120.00 = 1440.00 5. Waterman 1.500 days 110.00 = 165.00 6. Labour.Add 1.750 days 150.00 = 262.50 Total of Labour : Rs. = 3499.00 Grand Total Cost for 10.000 cu.mt: Rs. = 45173.99 Unit Cost per cu.mt is : Rs. = 4517.399
Todays BUZZ Word First the drawing of Center line plan was given to us and asked us study it. then we saw the line out which was done by labours. Line is nothing but simply putting out the drawing onto the ground and carrying out the work.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar 9922313712
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: www.shraddha4@gmail.com
Subject: 10901-02

Exam No. 10901
Company Name & Site Address V.S.JOSHI & ASSOCIATES
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.30AM
Site Leaving Time 5.30PM
Details of the Work Allotted to you today by the Site In-Charge Site Incharge: Mr. Amol Muley Sir had given us work for taking internal room dimensions of flat 104 which was ready. He had also asked to observe electrical fittings, doors & windows, fixture provided on doors.
Details of how you Planned & Executed the allotted work First we had taken the internal dimensions of living room. Then observed types of doors & windows, electrification, flooring,taken dimensions of tiles, observed detailed fittings done in toilets as mixer, shower, wallen hung commode,etc.We took the dimensions of one by one room as the Flat was 4 BHK.
Details of the Construction Procedure / Activity / Technology learned today We learnt & observed about the construction of the walls which are yet to be painted.Laying of concrete bedding was going on, fixing of window frames & windows.
Details of the Construction Materials learned today Teak wood door frame. Making of concrete. Cutting of vitrified tiles.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today No such methodology is adopted.
Details of the Construction / Engineering Drawings observed today Today, sir showed us the drawing of safety door. Safety door has components like perforated sheet, square bars, aldrop.
Details of the Bye Laws referred today Dimension sizes of doors & windows are as per bye-laws. Door size: 1.2mx2.1m Window size:1.2mx1.2m(one panel)
Details of any Managerial Skill learned today Sir are very co-operative.They behave in a profressional way with their clients and are freindly with labours & also supervises work very properly.
RATE ANALYSIS As we had not yet studied about the RCC column & also the work of it not going on, We had done rate analysis of safety door. RATE ANALYSIS OF SAFETY DOOR MATERIALS QTY RATE(RS.) AMOUNT(RS.) 1) Rec. tube 19\'.6\" 44.00 858.00 2) Sq. bar 22\'.6\" 12.25 275.60 3) 1.5\"x3/4 rec.tube 64\' 38.50 2464.00 4) Perforated sheet 18 sq.ft 50.00 900.00 5) Hinges, tower bolt, 500.00 aldrop primar, etc. TOTAL 5047.60 Wastage 5% 252.38 TOTAL 5299.98 Transportation 70.00 Labour charges 38.50 60.00 5369.98 sq.ft sq.ft 2310.00 TOTAL 7679.98
Todays BUZZ Word BUILDING LINEOUT: First,the position of footings is fixed, then the excavation is done. the foundation is build & columns are erected. Survey work is being made to take offsets and seeing that the members are are in sane straight line.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Amol Muley sir.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: cool.sushant007@gmail.com
Subject: 10880-02

Exam No. 10880
Company Name & Site Address S S developers & Builder
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 am
Site Leaving Time 4 pm
Details of the Work Allotted to you today by the Site In-Charge To check the dimension of the block-B
Details of how you Planned & Executed the allotted work we divide ourself into two groups and then one group is going to the first floor and other is on second floor.and record the dimension.
Details of the Construction Procedure / Activity / Technology learned today we learned about the plastering work.
Details of the Construction Materials learned today concrete blocks of size-190x40x60 cm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today To dispose sewage waste septic tank is provided.
Details of the Construction / Engineering Drawings observed today Plans of row bunglows.
Details of the Bye Laws referred today Margins and set-backs distances.
Details of any Managerial Skill learned today Catch up the main worker give him the instruction about the work has to be done throughout the day in planned manner and that worker has good control over all the workers.
RATE ANALYSIS RATE ANALYSIS FOR R.C.C. COLUMN proportion used: 1:2:3 volume to be made: 1 cu.m addition for dry volume: 52% total volume: 1.52 cu.m cement: 1.52/1+2+3=0.3 cu.m no. of bags: 0.3/0.035=8.57=9 no. (9x260)=2340 Rs sand 0.3x2=0.6 cu.m (0.6x725)=435 Rs Aggregate: 0.3x3=0.9 cu.m (450x0.9)=405 Rs cost of material: =3180 Rs all labours cost: =600 Rs steel cost: 90 kg/cu.m x 32=2880 Rs cost: 6660 Rs total cost including profit: 1.15x6660=7659 Rs
Todays BUZZ Word According to plan provided by architect, fix the position of outline and fix the bamboo props on the outline, mark one same level on all the props and attach ropes on that from both sides in perpendicular to each other then intersection of that is transfer on the ground and from that do the further excavation work for the footing
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr, Ketan charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: misal81289@gmail.com
Subject: 10877-02

Exam No. 10877
Company Name & Site Address S S developers & Builder
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 am
Site Leaving Time 4 pm
Details of the Work Allotted to you today by the Site In-Charge To check the dimension of the block-B
Details of how you Planned & Executed the allotted work we divide ourself into two groups and then one group is going to the first floor and other is on second floor.and record the dimension.
Details of the Construction Procedure / Activity / Technology learned today we learned about the plastering work.
Details of the Construction Materials learned today concrete blocks of size-190x40x60 cm
Details of Environment Caring Technology / Methodology / Procedure / Product learned today To dispose sewage waste septic tank is provided.
Details of the Construction / Engineering Drawings observed today Plans of row bunglows.
Details of the Bye Laws referred today Margins and set-backs distances.
Details of any Managerial Skill learned today Catch up the main worker give him the instruction about the work has to be done throughout the day in planned manner and that worker has good control over all the workers.
RATE ANALYSIS RATE ANALYSIS FOR R.C.C. COLUMN proportion used: 1:2:3 volume to be made: 1 cu.m addition for dry volume: 52% total volume: 1.52 cu.m cement: 1.52/1+2+3=0.3 cu.m no. of bags: 0.3/0.035=8.57=9 no. (9x260)=2340 Rs sand 0.3x2=0.6 cu.m (0.6x725)=435 Rs Aggregate: 0.3x3=0.9 cu.m (450x0.9)=405 Rs cost of material: =3180 Rs all labours cost: =600 Rs steel cost: 90 kg/cu.m x 32=2880 Rs cost: 6660 Rs total cost including profit: 1.15x6660=7659 Rs
Todays BUZZ Word According to plan provided by architect, fix the position of outline and fix the bamboo props on the outline, mark one same level on all the props and attach ropes on that from both sides in perpendicular to each other then intersection of that is transfer on the ground and from that do the further excavation work for the footing. this is the purpose of line out.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr, Ketan charapale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: paragdhapodkar25@gmail.com
Subject: 10891-02

Exam No. 10891
Company Name & Site Address sangavi builder & devlopers
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To supervise Plumbing fittings and Column formwork and wall finishing. .
Details of how you Planned & Executed the allotted work First we see plumbing in D-5 bunglow and tale the details. And we also observed the shuttering work for formwork. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing:- 1)Hot water pipes:- 20mm dia. (Ashirvad Company) 2)Cold water pipes:- 15mm dia. (Phinolex company) The pipingg were built-in masnory i.e. concealed piping. At the end of pipes taps were fitted. W.C. pipes were connected to the soil water pipe. Nhani traps were also provided. Column:- 1)Size:230*300 2)Shuttering material was cut to the required dimensions. 3)It was erected in plumb and alignment as per center-line plan. 4) Proper supports were given to the formwork. .
Details of the Construction Materials learned today 1) PVC pipes 2) W.C. pans .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly ash bricks were used. It solved the disposal problem of fly ash, as it is the waste product from thermal power plant. .
Details of the Construction / Engineering Drawings observed today Center-line plan Foundation plan. .
Details of the Bye Laws referred today We observed the diameters of pipes provided and compare with the bye-laws. They were as per bye-laws. .
Details of any Managerial Skill learned today Our in-charge prepares the working schedule and executes the work as per schedule. It helps in faster and proper execution of work. .
RATE ANALYSIS Concrete Grade: M-20 (1:1.5:3) 1 cu.m= 35.28 CFT Cement=6.9*255= Rs. 1759.5/- Sand=0.035*1.5*6.9*44*35.28=Rs.562.327/- Metal=0.035*3*6.9*18*35.28= Rs. 460.08/- Labour cost=40*35.28=Rs.1411/- Steel=75*35+250=Rs.2875/- Total=Rs.7100/- per cu m .
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Centre-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil 9890997979 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: Rathod2211@gmail.com
Subject: 10881-02

Exam No. 10881
Company Name & Site Address S.s.builders and devlopers
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9:00 Am
Site Leaving Time 4:00 Pm
Details of the Work Allotted to you today by the Site In-Charge Checking the dimension of columns, beams, and septic tank dimension, checking the cement test available at site. And how to steel placed for concreting of beams.
Details of how you Planned & Executed the allotted work We divide in two groups, one group at 1st floor and another one is at 2nd floor, and taking all dimensions of coluns, beams, sill level height, and taking parapet wall height 1.2 meters, and cheking cement test, 1st inserted hand in full of cement bag, we feel cool, then rubbed in fingers, then feel smooth, and thoroug full of hand cement in full of water bucket, then cement float sometimes on the surface of bucket.
Details of the Construction Procedure / Activity / Technology learned today Before casting the slab, genrally for shuttering the steel plates are used, but now a days the advanced waterproof plywood (northern compnay) used, used like this ply, the ceiling surface should be smooth, good appearance and not necessory plastering for ceiling, only apply putty after that.
Details of the Construction Materials learned today Use of cement block, Size(400*200*150) and cost is 18 rps. For one brick. Used for compnund wall, parapet wall, for good appearance.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Providing septic tank common for every block in total area. And waste water directly connected to muncipal line.
Details of the Construction / Engineering Drawings observed today Observing plans of row houses, their are 6 row bunglows, in that 3 bhk flats are provided.
Details of the Bye Laws referred today Regarding by bye laws, front margin=5m, rear margin=3m, side margin=4.5m
Details of any Managerial Skill learned today How to manage total feild.
RATE ANALYSIS For 1:2:3, for 1m3=0.152% *cement= 1.52/1 2 3=0.3 No. Of bags= 0.3/0.035 =8.5 bags = 9 bags For 1 bag 250 rps. =2340 rps. ¤ for sand 0..152*2= 0.304*725 =220.4 rps ¤for aggregates 0.152*3=0.456 =0.456*450=205.2 rps. TOTAL=2340 220.4 205.2 125 200 80 =3170.6 rps. ¤ for steel 16 mm dia. 10 nos. Stirrups=8 inch @ center 8 inch Height= 3m Weight=d2/162.5 16*16/162.5=1600 gm For 3m= 1.6*3=4.8 kg For 10 nos.=4.8*10=48 kg 48*30=1440 rps Stirrtps=15 nos. Length=735 735*15=11025 mm =4.41kg=132.3 rps TOTAL=3480 1440 132 =5052 rps Total g.f columns cost 1) 450*230*3000 =3310 rps.=3310*15=49650rps. 2)610*230*3000=17 nos. Of columns. Cost=5863*17=99671rps. 3)530*230*3000=14 nos. Cost=5052*14=70728 rps. 4)230*300*3000=4 nos. Cost=3310*4=13240rps. TOTAL(For 3m)=2,33,289 rupess. Indicate * = multiply
Todays BUZZ Word Layout of building by center line method. Used chock pits for this method.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: Rathod2211@gmail.com
Subject: 10881-02

Exam No. 10881
Company Name & Site Address S.s.builders and devlopers
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9:00 Am
Site Leaving Time 4:00 Pm
Details of the Work Allotted to you today by the Site In-Charge Checking the dimension of columns, beams, and septic tank dimension, checking the cement test available at site. And how to steel placed for concreting of beams.
Details of how you Planned & Executed the allotted work We divide in two groups, one group at 1st floor and another one is at 2nd floor, and taking all dimensions of coluns, beams, sill level height, and taking parapet wall height 1.2 meters, and cheking cement test, 1st inserted hand in full of cement bag, we feel cool, then rubbed in fingers, then feel smooth, and thoroug full of hand cement in full of water bucket, then cement float sometimes on the surface of bucket.
Details of the Construction Procedure / Activity / Technology learned today Before casting the slab, genrally for shuttering the steel plates are used, but now a days the advanced waterproof plywood (northern compnay) used, used like this ply, the ceiling surface should be smooth, good appearance and not necessory plastering for ceiling, only apply putty after that.
Details of the Construction Materials learned today Use of cement block, Size(400*200*150) and cost is 18 rps. For one brick. Used for compnund wall, parapet wall, for good appearance.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Providing septic tank common for every block in total area. And waste water directly connected to muncipal line.
Details of the Construction / Engineering Drawings observed today Observing plans of row houses, their are 6 row bunglows, in that 3 bhk flats are provided.
Details of the Bye Laws referred today Regarding by bye laws, front margin=5m, rear margin=3m, side margin=4.5m
Details of any Managerial Skill learned today How to manage total feild.
RATE ANALYSIS For 1:2:3, for 1m3=0.152% *cement= 1.52/1 2 3=0.3 No. Of bags= 0.3/0.035 =8.5 bags = 9 bags For 1 bag 250 rps. =2340 rps. ¤ for sand 0..152*2= 0.304*725 =220.4 rps ¤for aggregates 0.152*3=0.456 =0.456*450=205.2 rps. TOTAL=2340 220.4 205.2 125 200 80 =3170.6 rps. ¤ for steel 16 mm dia. 10 nos. Stirrups=8 inch @ center 8 inch Height= 3m Weight=d2/162.5 16*16/162.5=1600 gm For 3m= 1.6*3=4.8 kg For 10 nos.=4.8*10=48 kg 48*30=1440 rps Stirrtps=15 nos. Length=735 735*15=11025 mm =4.41kg=132.3 rps TOTAL=3480 1440 132 =5052 rps Total g.f columns cost 1) 450*230*3000 =3310 rps.=3310*15=49650rps. 2)610*230*3000=17 nos. Of columns. Cost=5863*17=99671rps. 3)530*230*3000=14 nos. Cost=5052*14=70728 rps. 4)230*300*3000=4 nos. Cost=3310*4=13240rps. TOTAL(For 3m)=2,33,289 rupess. Indicate * = multiply
Todays BUZZ Word Layout of building by center line method. Used chock pits for this method.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-02

Exam No. 10900
Company Name & Site Address Chandra Milla, Shivshakti Developers
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9.30am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Today also we have supervised the plastering work. .
Details of how you Planned & Executed the allotted work firstly we went on spot,where plastering was going on.we observed how ingredients are mixed and how much proportion are taken.also we observed how the tools of plastering like trowels,floats are used for plastering. .
Details of the Construction Procedure / Activity / Technology learned today materials- cement,sand,water. on the site internal plastering is going on. tools-pan,spade,trowel,wooden float,aluminium box,plumb bob etc. procedure-first 15 pans sand is spread on the surface.then 1 bag cement is spread over the sand.then it is mixed for 10-15 min.then water is added approx.5 buckets for 1 bag cement.then all the ingredients throughly mixed.then it is applied in two coats.1st coat is applied in thick layer &2nd coat is applied in thin layer. and then finshing is done. .
Details of the Construction Materials learned today the size of steel bar used are 6,10,12,16,20,25mm.steel used is tor415.the rates of steel bar per kg are always varying.the length of steel bar used are about 12-13m. .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today less no.of bamboos & more no.of props are used for scaffolding and support. .
Details of the Construction / Engineering Drawings observed today Detail study of line-out drawing is learned today. .
Details of the Bye Laws referred today In bye-laws today we referred provision of lift.it is given that at least one lift shall be provided in building more than16m height. In our site the height is more than 16m and 1 lift is provided. The lift provided in site is from basement to terrace. .
Details of any Managerial Skill learned today The proper communication with the labour on site. .
RATE ANALYSIS Material:- Cement=6.9 bags/ cu.m. @ Rs.260/ bag Rs. 1794/- Sand=0.45 cu.m @ Rs.115/ cu.m Rs. 520/- Aggregate=0.85 cu.m @ Rs. 304/cu.m Rs. 258/- steel=180kg @ Rs. 35/kg Rs. 6300/- Labor cost:- Cement shifting= 6.9bags @ Rs. 1/bag Rs. 6.9/- Sand/Metal shifting @ Rs. 20/cu.m Rs. 20/- Manufacturing and pouring @ Rs. 40/bag Rs. 276/- Finishing Rs. 10/- Formwork material 10.36sq m @Rs.53/sq.m Rs. 599.09/- Formwork making Rs. 10/- Formwork labor with avg. lift 10.36 sq.m Rs. 10/- Tool Plants:- Mixing, vibrator and plant @Rs.14/bag Rs. 96.60/- Fuel charges @ Rs. 2.5/bag Rs. 17.25/- Nails and binding wire, D\'oil @Rs.4/sq m Rs. 41.44/- Plastic cover blocks @Rs.1/ block Rs. 10.36/- Total= Rs. 11700/- .
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Centre-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9881497688
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: Rohit_Patil361@rediffmail.com
Subject: 13565-02

Exam No. 13565
Company Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09 / 12 / 2010
Site Reporting Time 09:00 am
Site Leaving Time 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about layout plans of column.
Details of how you Planned & Executed the allotted work First we observed the plan of column layout then see the actual marking of column on site. First we selected the main base line. this main line w.r.t. plan mark the offsetting of that column. Then obtain perfect location of footing
Details of the Construction Procedure / Activity / Technology learned today For wing b they constuct starter. After footing construction they construct starter. They mark the starter position from the offseting from main with the help of tape, plumb bob, line dori, etc. They markline on top of fotting by white coloured oil paint pencil. From this marking they situate right angle(gunnya) and draw line along column as rectangul. Along this line they situate small formwork and fix their. After formworking they place concrete then starter will be done.
Details of the Construction Materials learned today Murum filing around the foungation of fotting by using pokhland(jcb) Formwork for starter and column Steel bars 8.00 mm dia. Concrete 1:1 1/5:3 Cement- 43 grade opc Sand- river sand Aggregate- 20.00 to 25.00 mm Water- 12.00 liters Admixture- super plastisiser 30% add w.r.t water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Nothing
Details of the Construction / Engineering Drawings observed today Lineout of fotting and column By obsevrving plan we selected the required column fotting.on that plan they mark and fix the column distance on the ground. Actual position of stairs, column, beams, and also position of lift.
Details of the Bye Laws referred today Open space separate for each building or wing- The open space required under these regulation shall be separete or distinct for each building and where a building has two or more wings, each wing shall have separate or distinct open space as required under these regulation. rovide that if one of the wings does not depend for light and ventilation on the open space between the two wings, the open space shall be the one required for the higher wing.
Details of any Managerial Skill learned today To check the done of footing, column by workers. The position of column is same as in reference plan. The starter is parllal to the another starter.
RATE ANALYSIS Rate analysis For R.C.C Column Column size 600 X 300 mm. Height - 2400mm. Steel for column - Main bars - 12 mm Dia. 10 Nos. Stirrups - 8 mm Dia. 9 Nos. For R.C.C Column ( 1 : 1.5 : 3 ) Cement = 6.4 bags X 250 =1600 /- Aggregate = 1.25 X 6.4 X 3 X 18 = 432 /- Sand = 1.25 X 6.4 X 1.5 X 35 = 420 /- Steel = 26.08 X 40 = 1043 /- Labour = 1280 /- Total = 4775 /-
Todays BUZZ Word Building line out- * Study the working drawing and center line drawing before starting the line out. * Check all the measurement and distances and tally them each other. * Take required side margin and set up the dumpy level. * Mrak a parallel line from all the four sides of plot. Precaution to be taken for lineout- * All wooden post should be fixed properly in concrete. Seven days curing period should be allowed, before fixing the railing. * Railing should be straight and of a standard size. * Wooden post should be fixed at same level. * Railing fixing should be done by 50.00 mm nails.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-02

Exam No. 13560
Company Name & Site Address Chougale Sawant Developers,Shree Samarth Nagar,Balinga.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:00am
Site Leaving Time 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1) column shuttering checking, 2) Trial pit observation, 3)To work out the quantity & rate analysis of R.C.C Column, 4)To observation of the building line out.
Details of how you Planned & Executed the allotted work before the lunch break we done the column shuttering checking as well as observation of Trial pit & then after lunch we saw the building line out & calculate the rate of R.C.C Column.
Details of the Construction Procedure / Activity / Technology learned today we learned about the weigh batch mixer & the electrical vibrator.
Details of the Construction Materials learned today We learned about the crushed sand.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today In their project they mixed the fly ash in concrete to reduce the pollution.
Details of the Construction / Engineering Drawings observed today We observed the building line out drawing & footing drawing.
Details of the Bye Laws referred today they reffed the Bye Law that front margin =4.5 m side margin =2.25 m rare margin=3 m to their project.
Details of any Managerial Skill learned today we learned that how to arrange the work which has to be done.
RATE ANALYSIS for R.C.C. Column the rate =11000 Rs/cubic meter, Material Quantity(kg) Rate(Rs) 1) Cement 310 1281 2) aggregate 180 680 3) sand 120 380 4) steel 165 5700 TOTAL = 8040 add 2% for wastage & labor cost 1100 Rs & add 10% contractors profit then TOTAL =11000 Rs/cubic meter.
Todays BUZZ Word 1) As per the building drawing plot boundary is fixed. 2) Then consider the base line & fixed it on the ground with the help of the nails & line string. 3) Then powder is poured on that string. 4) With help of this base line fix the other line by taking diagonals. 5) Make the complete square or rectangle. In this way building line out is done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Suhas Jadhav & Mob No.=8007415015.
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: abkhade@yahoo.co.in
Subject: 13563-02

Exam No. 13563
Company Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09 / 12 / 2010
Site Reporting Time 09:00 am
Site Leaving Time 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about layout plans of column.
Details of how you Planned & Executed the allotted work First we observed the plan of column layout then see the actual marking of column on site. First we selected the main base line. this main line w.r.t. plan mark the offsetting of that column. Then obtain perfect location of footing
Details of the Construction Procedure / Activity / Technology learned today For wing b they constuct starter. After footing construction they construct starter. They mark the starter position from the offseting from main with the help of tape, plumb bob, line dori, etc. They markline on top of fotting by white coloured oil paint pencil. From this marking they situate right angle(gunnya) and draw line along column as rectangul. Along this line they situate small formwork and fix their. After formworking they place concrete then starter will be done.
Details of the Construction Materials learned today Murum filing around the foungation of fotting by using pokhland(jcb) Formwork for starter and column Steel bars 8.00 mm dia. Concrete 1:1 1/5:3 Cement- 43 grade opc Sand- river sand Aggregate- 20.00 to 25.00 mm Water- 12.00 liters Admixture- super plastisiser 30% add w.r.t water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Nothing
Details of the Construction / Engineering Drawings observed today Lineout of fotting and column By obsevrving plan we selected the required column fotting.on that plan they mark and fix the column distance on the ground. Actual position of stairs, column, beams, and also position of lift.
Details of the Bye Laws referred today Open space separate for each building or wing- The open space required under these regulation shall be separete or distinct for each building and where a building has two or more wings, each wing shall have separate or distinct open space as required under these regulation. rovide that if one of the wings does not depend for light and ventilation on the open space between the two wings, the open space shall be the one required for the higher wing.
Details of any Managerial Skill learned today To check the done of footing, column by workers. The position of column is same as in reference plan. The starter is parllal to the another starter.
RATE ANALYSIS Rate analysis For R.C.C Column Column size 600 X 300 mm. Height - 2400mm. Steel for column - Main bars - 12 mm Dia. 10 Nos. Stirrups - 8 mm Dia. 9 Nos. For R.C.C Column ( 1 : 1.5 : 3 ) Cement = 6.4 bags X 250 =1600 /- Aggregate = 1.25 X 6.4 X 3 X 18 = 432 /- Sand = 1.25 X 6.4 X 1.5 X 35 = 420 /- Steel = 26.08 X 40 = 1043 /- Labour = 1280 /- Total = 4775 /-
Todays BUZZ Word Building line out- * Study the working drawing and center line drawing before starting the line out. * Check all the measurement and distances and tally them each other. * Take required side margin and set up the dumpy level. * Mrak a parallel line from all the four sides of plot. Precaution to be taken for lineout- * All wooden post should be fixed properly in concrete. Seven days curing period should be allowed, before fixing the railing. * Railing should be straight and of a standard size. * Wooden post should be fixed at same level. * Railing fixing should be done by 50.00 mm nails.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: sudsalokhe2011@gmail.com
Subject: 13544-02

Exam No. 13544
Company Name & Site Address Deshmukh Developements
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 am
Site Leaving Time 4 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the detail construction of steel reinforcement going on fifth floor of the building.
Details of how you Planned & Executed the allotted work We first collected the information about the type of work means wheather it is for slab,column,beams.then accordingly collected the drawings from site incharge and studied those drawings after that we go the fifth floor to observe the work.
Details of the Construction Procedure / Activity / Technology learned today In case of the beams in addition to the top and bottom bars extra top and extra bottom bars are provided to restrict the movement of the beam against bending,shear. stirrups are provided closer near the support and wider in between.as we go on the top from the ground floor the thickness of the bars get reduced as the load is goes on decreasing.in slabs two way ,one way is provided and the bent up bars are used at l/4 distance to distribute the load and main and distribution are provided to transfer the load safely to the columns.
Details of the Construction Materials learned today About the type of steel bars and where they are provided according to their properties. and cutting tools used for them
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater Harvesting pits are provided which is used for the gardening purpose.
Details of the Construction / Engineering Drawings observed today Steel drawings.
Details of the Bye Laws referred today Height of the floors including slabs thickness.
Details of any Managerial Skill learned today Catch up the main worker give him the instruction about the work has to be done throughout the day in planned manner and that worker has good control over all the workers.
RATE ANALYSIS RATE ANALYSIS FOR R.C.C. COLUMN proportion used: 1:1.5:3 volume to be made: 1 cu.m addition for dry volume: 52% total volume: 1.52 cu.m cement: 1.52/1+1.5+3=0.2763 cu.m no. of bags: 0.2763/0.035=7.89=8 no. (8x260)=2080 Rs sand 0.2763x1.5=0.4144 cu.m (0.4144x725)=300.44 Rs Aggregate: 0.2763x3=0.8289 cu.m (450x0.8289)=373 Rs cost of material: =2753 Rs all labours cost: =600 Rs steel cost: 90 kg/cu.m x 32=2880 Rs cost: 6233 Rs total cost including profit: 1.15x6233=7167.95 Rs
Todays BUZZ Word According to plan provided by architect, fix the position of outline and fix the bamboo props on the outline, mark one same level on all the props and attach ropes on that from both sides in perpendicular to each other then intersection of that is transfer on the ground and from that do the further excavation work for the footing. this is the purpose of line out.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. Rajesh chougale
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: shivaprchavan@gmail.com
Subject: 13558 - 02

Exam No. 13558
Company Name & Site Address chaugle-sawant builders, new balinga,kolhapur
Working Day No. 02
Date (DD/MM/YYYY) 9.12.2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge to observe shuttering work,excavation work,line out.
Details of how you Planned & Executed the allotted work first we saw all the drawings related to above work and then we observe it on site.
Details of the Construction Procedure / Activity / Technology learned today shuttering,line out,excavation,curing,concreting.
Details of the Construction Materials learned today fly ash,cement, steel of grade 415 and 500 ,plywood formwork
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of pavement blocks to reduce site erosion.
Details of the Construction / Engineering Drawings observed today r.c.c. drawings, center line plan ,detailed drawings.
Details of the Bye Laws referred today floor to floor height = 3.15m
Details of any Managerial Skill learned today speking clearly with contractor to clarrify all things.
RATE ANALYSIS R.C.C. COLUMN ; Per cu.m 1.steel = 165kg = 5700 Rs. 2.cement = 310kg =1281 Rs. 3.sand = 120kg =380 Rs. 4.aggregate = 180kg =680Rs. TOTAL =8040 + 2% wastage + labour cost =10000.00 Rs.
Todays BUZZ Word BUILDING LINE-OUT : 1. Marking plot boundery by seeing plans and control points. 2. Marking outline of building by knowing center line plans,with wooden planks 3. All center lines are marked with strings as per center line plans. 4. column positions are fixed on center line and diagonal checking is done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Suhas Jadhav, mo no.8007415015
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: rizwanshaikhcvl@gmail.com
Subject: 13545-02

Exam No. 13545
Company Name & Site Address Deshmukh Developements
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 am
Site Leaving Time 4 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the detail construction of steel reinforcement going on fifth floor of the building.
Details of how you Planned & Executed the allotted work We first collected the information about the type of work means wheather it is for slab,column,beams.then accordingly collected the drawings from site incharge and studied those drawings after that we go the fifth floor to observe the work.
Details of the Construction Procedure / Activity / Technology learned today In case of the beams in addition to the top and bottom bars extra top and extra bottom bars are provided to restrict the movement of the beam against bending,shear. stirrups are provided closer near the support and wider in between.as we go on the top from the ground floor the thickness of the bars get reduced as the load is goes on decreasing.in slabs two way ,one way is provided and the bent up bars are used at l/4 distance to distribute the load and main and distribution are provided to transfer the load safely to the columns.
Details of the Construction Materials learned today About the type of steel bars and where they are provided according to their properties. and cutting tools used for them
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater Harvesting pits are provided which is used for the gardening purpose.
Details of the Construction / Engineering Drawings observed today Steel drawings.
Details of the Bye Laws referred today Height of the floors including slabs thickness.
Details of any Managerial Skill learned today Catch up the main worker give him the instruction about the work has to be done throughout the day in planned manner and that worker has good control over all the workers.
RATE ANALYSIS RATE ANALYSIS FOR R.C.C. COLUMN proportion used: 1:1.5:3 volume to be made: 1 cu.m addition for dry volume: 52% total volume: 1.52 cu.m cement: 1.52/1+1.5+3=0.2763 cu.m no. of bags: 0.2763/0.035=7.89=8 no. (8x260)=2080 Rs sand 0.2763x1.5=0.4144 cu.m (0.4144x725)=300.44 Rs Aggregate: 0.2763x3=0.8289 cu.m (450x0.8289)=373 Rs cost of material: =2753 Rs all labours cost: =600 Rs steel cost: 90 kg/cu.m x 32=2880 Rs cost: 6233 Rs total cost including profit: 1.15x6233=7167.95 Rs
Todays BUZZ Word According to plan provided by architect, fix the position of outline and fix the bamboo props on the outline, mark one same level on all the props and attach ropes on that from both sides in perpendicular to each other then intersection of that is transfer on the ground and from that do the further excavation work for the footing. this is the purpose of line out.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. Rajesh chougale
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: khandobabulbule@rediffmail.com
Subject: 13557-02

Exam No. 13557
Company Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09 / 12 / 2010
Site Reporting Time 09:00 am
Site Leaving Time 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about layout plans of column.
Details of how you Planned & Executed the allotted work First we observed the plan of column layout then see the actual marking of column on site. First we selected the main base line. this main line w.r.t. plan mark the offsetting of that column. Then obtain perfect location of footing
Details of the Construction Procedure / Activity / Technology learned today - For wing b they constuct starter. After footing construction they construct starter. They mark the starter position from the offseting from main with the help of tape, plumb bob, line dori, etc. They markline on top of fotting by white coloured oil paint pencil. From this marking they situate right angle(gunnya) and draw line along column as rectangul. Along this line they situate small formwork and fix their. After formworking they place concrete then starter will be done.
Details of the Construction Materials learned today Murum filing around the foungation of fotting by using pokhland(jcb) Formwork for starter and column Steel bars 8.00 mm dia. Concrete 1:1 1/5:3 Cement- 43 grade opc Sand- river sand Aggregate- 20.00 to 25.00 mm Water- 12.00 liters Admixture- super plastisiser 30% add w.r.t water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Nothing
Details of the Construction / Engineering Drawings observed today Lineout of fotting and column By obsevrving plan we selected the required column fotting.on that plan they mark and fix the column distance on the ground. Actual position of stairs, column, beams, and also position of lift.
Details of the Bye Laws referred today Open space separate for each building or wing- The open space required under these regulation shall be separete or distinct for each building and where a building has two or more wings, each wing shall have separate or distinct open space as required under these regulation. rovide that if one of the wings does not depend for light and ventilation on the open space between the two wings, the open space shall be the one required for the higher wing.
Details of any Managerial Skill learned today To check the done of footing, column by workers. The position of column is same as in reference plan. The starter is parllal to the another starter.
RATE ANALYSIS Rate analysis For R.C.C Column Column size 600 X 300 mm. Height - 2400mm. Steel for column - Main bars - 12 mm Dia. 10 Nos. Stirrups - 8 mm Dia. 9 Nos. For R.C.C Column ( 1 : 1.5 : 3 ) Cement = 6.4 bags X 250 =1600 /- Aggregate = 1.25 X 6.4 X 3 X 18 = 432 /- Sand = 1.25 X 6.4 X 1.5 X 35 = 420 /- Steel = 26.08 X 40 = 1043 /- Labour = 1280 /- Total = 4775 /-
Todays BUZZ Word Building line out- * Study the working drawing and center line drawing before starting the line out. * Check all the measurement and distances and tally them each other. * Take required side margin and set up the dumpy level. * Mrak a parallel line from all the four sides of plot. Precaution to be taken for lineout- * All wooden post should be fixed properly in concrete. Seven days curing period should be allowed, before fixing the railing. * Railing should be straight and of a standard size. * Wooden post should be fixed at same level. * Railing fixing should be done by 50.00 mm nails.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: rajan3535@gmail.com
Subject: 13548-01

Exam No. 13548
Company Name & Site Address Deshmukh Developements
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 am
Site Leaving Time 4 pm
Details of the Work Allotted to you today by the Site In-Charge To observe the detail construction of steel reinforcement going on fifth floor of the building.
Details of how you Planned & Executed the allotted work We first collected the information about the type of work means wheather it is for slab,column,beams.then accordingly collected the drawings from site incharge and studied those drawings after that we go the fifth floor to observe the work.
Details of the Construction Procedure / Activity / Technology learned today In case of the beams in addition to the top and bottom bars extra top and extra bottom bars are provided to restrict the movement of the beam against bending,shear. stirrups are provided closer near the support and wider in between.as we go on the top from the ground floor the thickness of the bars get reduced as the load is goes on decreasing.in slabs two way ,one way is provided and the bent up bars are used at l/4 distance to distribute the load and main and distribution are provided to transfer the load safely to the columns.
Details of the Construction Materials learned today About the type of steel bars and where they are provided according to their properties. and cutting tools used for them
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Rainwater Harvesting pits are provided which is used for the gardening purpose.
Details of the Construction / Engineering Drawings observed today Steel drawings.
Details of the Bye Laws referred today Height of the floors including slabs thickness.
Details of any Managerial Skill learned today Catch up the main worker give him the instruction about the work has to be done throughout the day in planned manner and that worker has good control over all the workers.
RATE ANALYSIS RATE ANALYSIS FOR R.C.C. COLUMN proportion used: 1:1.5:3 volume to be made: 1 cu.m addition for dry volume: 52% total volume: 1.52 cu.m cement: 1.52/1+1.5+3=0.2763 cu.m no. of bags: 0.2763/0.035=7.89=8 no. (8x260)=2080 Rs sand 0.2763x1.5=0.4144 cu.m (0.4144x725)=300.44 Rs Aggregate: 0.2763x3=0.8289 cu.m (450x0.8289)=373 Rs cost of material: =2753 Rs all labours cost: =600 Rs steel cost: 90 kg/cu.m x 32=2880 Rs cost: 6233 Rs total cost including profit: 1.15x6233=7167.95 Rs
Todays BUZZ Word According to plan provided by architect, fix the position of outline and fix the bamboo props on the outline, mark one same level on all the props and attach ropes on that from both sides in perpendicular to each other then intersection of that is transfer on the ground and from that do the further excavation work for the footing. this is the purpose of line out.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge Mr. Rajesh chougale
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: shanooredekar9@gmail.com
Subject: 13566-02

Exam No. 13566
Company Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09 / 12 / 2010
Site Reporting Time 09:00 am
Site Leaving Time 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about layout plans of column.
Details of how you Planned & Executed the allotted work First we observed the plan of column layout then see the actual marking of column on site. First we selected the main base line. this main line w.r.t. plan mark the offsetting of that column. Then obtain perfect location of footing
Details of the Construction Procedure / Activity / Technology learned today For wing b they constuct starter. After footing construction they construct starter. They mark the starter position from the offseting from main with the help of tape, plumb bob, line dori, etc. They markline on top of fotting by white coloured oil paint pencil. From this marking they situate right angle(gunnya) and draw line along column as rectangul. Along this line they situate small formwork and fix their. After formworking they place concrete then starter will be done.
Details of the Construction Materials learned today Murum filing around the foungation of fotting by using pokhland(jcb) Formwork for starter and column Steel bars 8.00 mm dia. Concrete 1:1 1/5:3 Cement- 43 grade opc Sand- river sand Aggregate- 20.00 to 25.00 mm Water- 12.00 liters Admixture- super plastisiser 30% add w.r.t water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Nothing
Details of the Construction / Engineering Drawings observed today Lineout of fotting and column By obsevrving plan we selected the required column fotting.on that plan they mark and fix the column distance on the ground. Actual position of stairs, column, beams, and also position of lift.
Details of the Bye Laws referred today Open space separate for each building or wing- The open space required under these regulation shall be separete or distinct for each building and where a building has two or more wings, each wing shall have separate or distinct open space as required under these regulation. rovide that if one of the wings does not depend for light and ventilation on the open space between the two wings, the open space shall be the one required for the higher wing.
Details of any Managerial Skill learned today To check the done of footing, column by workers. The position of column is same as in reference plan. The starter is parllal to the another starter.
RATE ANALYSIS Rate analysis For R.C.C Column Column size 600 X 300 mm. Height - 2400mm. Steel for column - Main bars - 12 mm Dia. 10 Nos. Stirrups - 8 mm Dia. 9 Nos. For R.C.C Column ( 1 : 1.5 : 3 ) Cement = 6.4 bags X 250 =1600 /- Aggregate = 1.25 X 6.4 X 3 X 18 = 432 /- Sand = 1.25 X 6.4 X 1.5 X 35 = 420 /- Steel = 26.08 X 40 = 1043 /- Labour = 1280 /- Total = 4775 /-
Todays BUZZ Word Building line out- * Study the working drawing and center line drawing before starting the line out. * Check all the measurement and distances and tally them each other. * Take required side margin and set up the dumpy level. * Mrak a parallel line from all the four sides of plot. Precaution to be taken for lineout- * All wooden post should be fixed properly in concrete. Seven days curing period should be allowed, before fixing the railing. * Railing should be straight and of a standard size. * Wooden post should be fixed at same level. * Railing fixing should be done by 50.00 mm nails.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: vishal.mohare67@gmail.com
Subject: 13564-02

Exam No. 13564
Company Name & Site Address WIND GATE at R.S No.83 Near New Palace, New nagala park, Kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09 / 12 / 2010
Site Reporting Time 09:00 am
Site Leaving Time 04:00 pm
Details of the Work Allotted to you today by the Site In-Charge To understand about layout plans of column.
Details of how you Planned & Executed the allotted work First we observed the plan of column layout then see the actual marking of column on site. First we selected the main base line. this main line w.r.t. plan mark the offsetting of that column. Then obtain perfect location of footing
Details of the Construction Procedure / Activity / Technology learned today For wing b they constuct starter. After footing construction they construct starter. They mark the starter position from the offseting from main with the help of tape, plumb bob, line dori, etc. They markline on top of fotting by white coloured oil paint pencil. From this marking they situate right angle(gunnya) and draw line along column as rectangul. Along this line they situate small formwork and fix their. After formworking they place concrete then starter will be done.
Details of the Construction Materials learned today Murum filing around the foungation of fotting by using pokhland(jcb) Formwork for starter and column Steel bars 8.00 mm dia. Concrete 1:1 1/5:3 Cement- 43 grade opc Sand- river sand Aggregate- 20.00 to 25.00 mm Water- 12.00 liters Admixture- super plastisiser 30% add w.r.t water
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Nothing
Details of the Construction / Engineering Drawings observed today Lineout of fotting and column By obsevrving plan we selected the required column fotting.on that plan they mark and fix the column distance on the ground. Actual position of stairs, column, beams, and also position of lift.
Details of the Bye Laws referred today Open space separate for each building or wing- The open space required under these regulation shall be separete or distinct for each building and where a building has two or more wings, each wing shall have separate or distinct open space as required under these regulation. rovide that if one of the wings does not depend for light and ventilation on the open space between the two wings, the open space shall be the one required for the higher wing.
Details of any Managerial Skill learned today To check the done of footing, column by workers. The position of column is same as in reference plan. The starter is parllal to the another starter.
RATE ANALYSIS Rate analysis For R.C.C Column Column size 600 X 300 mm. Height - 2400mm. Steel for column - Main bars - 12 mm Dia. 10 Nos. Stirrups - 8 mm Dia. 9 Nos. For R.C.C Column ( 1 : 1.5 : 3 ) Cement = 6.4 bags X 250 =1600 /- Aggregate = 1.25 X 6.4 X 3 X 18 = 432 /- Sand = 1.25 X 6.4 X 1.5 X 35 = 420 /- Steel = 26.08 X 40 = 1043 /- Labour = 1280 /- Total = 4775 /-
Todays BUZZ Word Building line out- * Study the working drawing and center line drawing before starting the line out. * Check all the measurement and distances and tally them each other. * Take required side margin and set up the dumpy level. * Mrak a parallel line from all the four sides of plot. Precaution to be taken for lineout- * All wooden post should be fixed properly in concrete. Seven days curing period should be allowed, before fixing the railing. * Railing should be straight and of a standard size. * Wooden post should be fixed at same level. * Railing fixing should be done by 50.00 mm nails.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr.Vikrant Pise. 9823332040
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: akshaygholkar@rediffmail.com
Subject: 13525-02

Exam No. 13525
Company Name & Site Address vishvakarma builders,pratibhanagar,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00
Site Leaving Time 4.00
Details of the Work Allotted to you today by the Site In-Charge to check the dimensions of the columns.
Details of how you Planned & Executed the allotted work we worked individually.
Details of the Construction Procedure / Activity / Technology learned today tiles fitting and railing.
Details of the Construction Materials learned today cross were used to keep distance between tiles.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no technology yet used.
Details of the Construction / Engineering Drawings observed today columns drawings.
Details of the Bye Laws referred today no bye laws have been referred today.
Details of any Managerial Skill learned today no skills observed.
RATE ANALYSIS calculation for p.c.c column(1:2:4) cement-0.2171cu.m sand-0.4342cu.m aggregate-0.8684cu.m cost: cement-7 bags-7*260=Rs.1820 sand-725*0.4342=Rs.314 aggregate-450*0.8684=Rs.381 labour-Rs.600 reinforcement-Rs.36*90=Rs.3240 total cost:Rs.6355
Todays BUZZ Word building line layout: first it is checked whether the plan given by the architect is accumulated in the plot available.then according to the bye laws set back margins are left.then the wooden planks are attached to the bamboo poles and lines are laid across each other and then ucing plumb bob column points are marked.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir. mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: agydsouza14@gmail.com
Subject: 13524-02

Exam No. 13524
Company Name & Site Address vishvakarma builders,pratibhanagar,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00
Site Leaving Time 4.00
Details of the Work Allotted to you today by the Site In-Charge to check the dimensions of the columns.
Details of how you Planned & Executed the allotted work we worked individually.
Details of the Construction Procedure / Activity / Technology learned today tiles fitting and railing.
Details of the Construction Materials learned today cross were used to keep distance between tiles.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no technology yet used.
Details of the Construction / Engineering Drawings observed today columns drawings.
Details of the Bye Laws referred today no bye laws have been referred today.
Details of any Managerial Skill learned today no skills observed.
RATE ANALYSIS calculation for p.c.c column(1:2:4) cement-0.2171cu.m sand-0.4342cu.m aggregate-0.8684cu.m cost: cement-7 bags-7*260=Rs.1820 sand-725*0.4342=Rs.314 aggregate-450*0.8684=Rs.381 labour-Rs.600 reinforcement-Rs.36*90=Rs.3240 total cost:Rs.6355
Todays BUZZ Word building line layout: first it is checked whether the plan given by the architect is accumulated in the plot available.then according to the bye laws set back margins are left.then the wooden planks are attached to the bamboo poles and lines are laid across each other and then ucing plumb bob column points are marked.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir. mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: sssvvv777@gmail.com
Subject: 13529-02

Exam No. 13529
Company Name & Site Address vishvakarma builders,pratibhanagar,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00
Site Leaving Time 4.00
Details of the Work Allotted to you today by the Site In-Charge to check the dimensions of the columns.
Details of how you Planned & Executed the allotted work we worked individually.
Details of the Construction Procedure / Activity / Technology learned today tiles fitting and railing.
Details of the Construction Materials learned today cross were used to keep distance between tiles.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no technology yet used.
Details of the Construction / Engineering Drawings observed today columns drawings.
Details of the Bye Laws referred today no bye laws have been referred today.
Details of any Managerial Skill learned today no skills observed.
RATE ANALYSIS calculation for p.c.c column(1:2:4) cement-0.2171cu.m sand-0.4342cu.m aggregate-0.8684cu.m cost: cement-7 bags-7*260=Rs.1820 sand-725*0.4342=Rs.314 aggregate-450*0.8684=Rs.381 labour-Rs.600 reinforcement-Rs.36*90=Rs.3240 total cost:Rs.6355
Todays BUZZ Word building line layout: first it is checked whether the plan given by the architect is accumulated in the plot available.then according to the bye laws set back margins are left.then the wooden planks are attached to the bamboo poles and lines are laid across each other and then ucing plumb bob column points are marked.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir. mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: nlmjadhav18@gmail.com
Subject: 13528-02

Exam No. 13528
Company Name & Site Address vishvakarma builders,pratibhanagar,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00
Site Leaving Time 4.00
Details of the Work Allotted to you today by the Site In-Charge to check the dimensions of the columns.
Details of how you Planned & Executed the allotted work we worked individually.
Details of the Construction Procedure / Activity / Technology learned today tiles fitting and railing.
Details of the Construction Materials learned today cross were used to keep distance between tiles.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no technology yet used.
Details of the Construction / Engineering Drawings observed today columns drawings.
Details of the Bye Laws referred today no bye laws have been referred today.
Details of any Managerial Skill learned today no skills observed.
RATE ANALYSIS calculation for p.c.c column(1:2:4) cement-0.2171cu.m sand-0.4342cu.m aggregate-0.8684cu.m cost: cement-7 bags-7*260=Rs.1820 sand-725*0.4342=Rs.314 aggregate-450*0.8684=Rs.381 labour-Rs.600 reinforcement-Rs.36*90=Rs.3240 total cost:Rs.6355
Todays BUZZ Word building line layout: first it is checked whether the plan given by the architect is accumulated in the plot available.then according to the bye laws set back margins are left.then the wooden planks are attached to the bamboo poles and lines are laid across each other and then ucing plumb bob column points are marked.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir. mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-02

Exam No. 10890
Company Name & Site Address sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00 a.m.
Site Leaving Time 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge He allowed the work to see plumbing details like different fittings used , pipe material used , method of working -After visiting the plumbing site of row bunglow D-5 & D-8 we took all details - Milind Patil – Site incharge engineer He allowed the work to see details of column casting like formwork , placing of concrete, compaction etc.
Details of how you Planned & Executed the allotted work We all visited to row bunglow D-5 & D-8 and saw the pipe fitting work going on with all details. - Then we visited another site which is nearby our site, there we saw details of concreting of column
Details of the Construction Procedure / Activity / Technology learned today We saw how the plumbing work is done. • Procedure; - Ist position of the pipe is decided. - Then pipes are laid in wall. - Then connections are done to supply line. - Cold & Hot water pipes are placed for heater .For cold water 15mm dia. Pipe and for hot water 20mm dia. Pipes are used. - Hot water pipe is insulated with the help of thread so as to avoid cracking of overlaid tiles. - Taps & various valves are fitted to openings. - Also sanitary fittings is done . - European W.C. pans are connected to soil pipes. - Nahani traps are also fitted to escape the bathroom water. • Column • Procedure: - Ist formwork is prepared and strutting is done. - Then placing the concrete in the prepared formwork. - After placing the concrete compaction is done by wooden flank New Technology used: - Superplasticisers are used for concreting work. - Murum compacter is used. 450kg. - Rollers and JCB are also used. - Rented per hour.
Details of the Construction Materials learned today -pipe fittings-pvc pipes;w.c. pans. -valves-mixer cock &bib cock etc. Ashirwad & finolex pipes are used.G.I.pipes are used for drainage works. Column-M-20 concrete is used. Proportion used is 1:1.5:3.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today We learnt about - Waste product from thermal power plant i.e. fly ash is used for manufacturing of bricks. - This bricks are used for entire project work. - Fly ash bricks reduces vibration load.
Details of the Construction / Engineering Drawings observed today Centre line plan of building line out. Foundation plan & column position.
Details of the Bye Laws referred today For row bunglows floor to floor height is 3.2m. For apartment floor to floor height is 3m.
Details of any Managerial Skill learned today They cooperated with us very well & they gave us detail information of building line out and level transferring. Also workers gave us information about actual work.
RATE ANALYSIS R.C.C. Column For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Labour 40*35.28= 1411 Rs./- 4192.0 Rs./- per cub.m. Builders profit including Service tax , VAT etc 4192* 1.20 = 5030 Rs./- 20 % This is according to the current rate of material and labour charge. Reinforcement quantity is not calculated here because this quantity is calculated under separate head. They have not given the details about this.
Todays BUZZ Word Todays Buzz word “Building line out” According to R.C.C. design work whole building lineout work is done R.C.C. designer provide the detail steps. -cleaning the site & leveling it. -first with the help of bamboos & wooden flanks boundary of is marked. -then with the help of R.C.C.design provided the position of the column is marked on wooden planks. -then with help of nylon thread the exact position of column is marked on the ground. -then with the help of this marking ,excavation is done for foundation according to site conditions & columns are erected.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-02

Exam No. 13537
Company Name & Site Address sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00 a.m.
Site Leaving Time 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge He allowed the work to see plumbing details like different fittings used , pipe material used , method of working -After visiting the plumbing site of row bunglow D-5 & D-8 we took all details - Milind Patil – Site incharge engineer He allowed the work to see details of column casting like formwork , placing of concrete, compaction etc.
Details of how you Planned & Executed the allotted work We all visited to row bunglow D-5 & D-8 and saw the pipe fitting work going on with all details. - Then we visited another site which is nearby our site, there we saw details of concreting of column
Details of the Construction Procedure / Activity / Technology learned today We saw how the plumbing work is done. • Procedure; - Ist position of the pipe is decided. - Then pipes are laid in wall. - Then connections are done to supply line. - Cold & Hot water pipes are placed for heater .For cold water 15mm dia. Pipe and for hot water 20mm dia. Pipes are used. - Hot water pipe is insulated with the help of thread so as to avoid cracking of overlaid tiles. - Taps & various valves are fitted to openings. - Also sanitary fittings is done . - European W.C. pans are connected to soil pipes. - Nahani traps are also fitted to escape the bathroom water. • Column • Procedure: - Ist formwork is prepared and strutting is done. - Then placing the concrete in the prepared formwork. - After placing the concrete compaction is done by wooden flank New Technology used: - Superplasticisers are used for concreting work. - Murum compacter is used. 450kg. - Rollers and JCB are also used. - Rented per hour.
Details of the Construction Materials learned today -pipe fittings-pvc pipes;w.c. pans. -valves-mixer cock &bib cock etc. Ashirwad & finolex pipes are used.G.I.pipes are used for drainage works. Column-M-20 concrete is used. Proportion used is 1:1.5:3.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today We learnt about - Waste product from thermal power plant i.e. fly ash is used for manufacturing of bricks. - This bricks are used for entire project work. - Fly ash bricks reduces vibration load.
Details of the Construction / Engineering Drawings observed today Centre line plan of building line out. Foundation plan & column position.
Details of the Bye Laws referred today For row bunglows floor to floor height is 3.2m. For apartment floor to floor height is 3m.
Details of any Managerial Skill learned today They cooperated with us very well & they gave us detail information of building line out and level transferring. Also workers gave us information about actual work.
RATE ANALYSIS R.C.C. Column For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Labour 40*35.28= 1411 Rs./- 4192.0 Rs./- per cub.m. Builders profit including Service tax , VAT etc 4192* 1.20 = 5030 Rs./- 20 % This is according to the current rate of material and labour charge. Reinforcement quantity is not calculated here because this quantity is calculated under separate head. They have not given the details about this.
Todays BUZZ Word Todays Buzz word “Building line out” According to R.C.C. design work whole building lineout work is done R.C.C. designer provide the detail steps. -cleaning the site & leveling it. -first with the help of bamboos & wooden flanks boundary of is marked. -then with the help of R.C.C.design provided the position of the column is marked on wooden planks. -then with help of nylon thread the exact position of column is marked on the ground. -then with the help of this marking ,excavation is done for foundation according to site conditions & columns are erected.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: akshaydesai32@yahoo.in
Subject: 10890-02

Exam No. 10890
Company Name & Site Address sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00 a.m.
Site Leaving Time 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge He allowed the work to see plumbing details like different fittings used , pipe material used , method of working -After visiting the plumbing site of row bunglow D-5 & D-8 we took all details - Milind Patil – Site incharge engineer He allowed the work to see details of column casting like formwork , placing of concrete, compaction etc.
Details of how you Planned & Executed the allotted work We all visited to row bunglow D-5 & D-8 and saw the pipe fitting work going on with all details. - Then we visited another site which is nearby our site, there we saw details of concreting of column
Details of the Construction Procedure / Activity / Technology learned today We saw how the plumbing work is done. • Procedure; - Ist position of the pipe is decided. - Then pipes are laid in wall. - Then connections are done to supply line. - Cold & Hot water pipes are placed for heater .For cold water 15mm dia. Pipe and for hot water 20mm dia. Pipes are used. - Hot water pipe is insulated with the help of thread so as to avoid cracking of overlaid tiles. - Taps & various valves are fitted to openings. - Also sanitary fittings is done . - European W.C. pans are connected to soil pipes. - Nahani traps are also fitted to escape the bathroom water. • Column • Procedure: - Ist formwork is prepared and strutting is done. - Then placing the concrete in the prepared formwork. - After placing the concrete compaction is done by wooden flank New Technology used: - Superplasticisers are used for concreting work. - Murum compacter is used. 450kg. - Rollers and JCB are also used. - Rented per hour.
Details of the Construction Materials learned today -pipe fittings-pvc pipes;w.c. pans. -valves-mixer cock &bib cock etc. Ashirwad & finolex pipes are used.G.I.pipes are used for drainage works. Column-M-20 concrete is used. Proportion used is 1:1.5:3.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today We learnt about - Waste product from thermal power plant i.e. fly ash is used for manufacturing of bricks. - This bricks are used for entire project work. - Fly ash bricks reduces vibration load.
Details of the Construction / Engineering Drawings observed today Centre line plan of building line out. Foundation plan & column position.
Details of the Bye Laws referred today For row bunglows floor to floor height is 3.2m. For apartment floor to floor height is 3m.
Details of any Managerial Skill learned today They cooperated with us very well & they gave us detail information of building line out and level transferring. Also workers gave us information about actual work.
RATE ANALYSIS R.C.C. Column For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Labour 40*35.28= 1411 Rs./- 4192.0 Rs./- per cub.m. Builders profit including Service tax , VAT etc 4192* 1.20 = 5030 Rs./- 20 % This is according to the current rate of material and labour charge. Reinforcement quantity is not calculated here because this quantity is calculated under separate head. They have not given the details about this.
Todays BUZZ Word Todays Buzz word “Building line out” According to R.C.C. design work whole building lineout work is done R.C.C. designer provide the detail steps. -cleaning the site & leveling it. -first with the help of bamboos & wooden flanks boundary of is marked. -then with the help of R.C.C.design provided the position of the column is marked on wooden planks. -then with help of nylon thread the exact position of column is marked on the ground. -then with the help of this marking ,excavation is done for foundation according to site conditions & columns are erected.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: nitish.mohite@yahoo.in
Subject: 13537-02

Exam No. 13537
Company Name & Site Address sanghavi builders & developers,80A/2 new palace road ,nagala park,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00 a.m.
Site Leaving Time 4.00 p.m.
Details of the Work Allotted to you today by the Site In-Charge Pritam Patil-Site incharge He allowed the work to see plumbing details like different fittings used , pipe material used , method of working -After visiting the plumbing site of row bunglow D-5 & D-8 we took all details - Milind Patil – Site incharge engineer He allowed the work to see details of column casting like formwork , placing of concrete, compaction etc.
Details of how you Planned & Executed the allotted work We all visited to row bunglow D-5 & D-8 and saw the pipe fitting work going on with all details. - Then we visited another site which is nearby our site, there we saw details of concreting of column
Details of the Construction Procedure / Activity / Technology learned today We saw how the plumbing work is done. • Procedure; - Ist position of the pipe is decided. - Then pipes are laid in wall. - Then connections are done to supply line. - Cold & Hot water pipes are placed for heater .For cold water 15mm dia. Pipe and for hot water 20mm dia. Pipes are used. - Hot water pipe is insulated with the help of thread so as to avoid cracking of overlaid tiles. - Taps & various valves are fitted to openings. - Also sanitary fittings is done . - European W.C. pans are connected to soil pipes. - Nahani traps are also fitted to escape the bathroom water. • Column • Procedure: - Ist formwork is prepared and strutting is done. - Then placing the concrete in the prepared formwork. - After placing the concrete compaction is done by wooden flank New Technology used: - Superplasticisers are used for concreting work. - Murum compacter is used. 450kg. - Rollers and JCB are also used. - Rented per hour.
Details of the Construction Materials learned today -pipe fittings-pvc pipes;w.c. pans. -valves-mixer cock &bib cock etc. Ashirwad & finolex pipes are used.G.I.pipes are used for drainage works. Column-M-20 concrete is used. Proportion used is 1:1.5:3.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today We learnt about - Waste product from thermal power plant i.e. fly ash is used for manufacturing of bricks. - This bricks are used for entire project work. - Fly ash bricks reduces vibration load.
Details of the Construction / Engineering Drawings observed today Centre line plan of building line out. Foundation plan & column position.
Details of the Bye Laws referred today For row bunglows floor to floor height is 3.2m. For apartment floor to floor height is 3m.
Details of any Managerial Skill learned today They cooperated with us very well & they gave us detail information of building line out and level transferring. Also workers gave us information about actual work.
RATE ANALYSIS R.C.C. Column For R.C.C. 1bag = 1.25 cub. Ft.. = 0.035 cub.m. proportion - 1:1.5:3 M-20 concrete For 1m³ R.C.C. 6.90 no. of cement bags are used according to the DSR chart. Cement 6.90 * 255 = 1759.5 Rs./- 0.035* 1.5 = 0.0525 Sand 0.035*1.5*6.90* 44*35.28= 562.32 Rs./- 0.0525 * 6.90 =0.3622 0.035* 3 = 0. 105 Metal 0.035 * 3 *6.90*18*35.28 =460.08 Rs./- 0.105* 6.90 =0.7245 Labour 40*35.28= 1411 Rs./- 4192.0 Rs./- per cub.m. Builders profit including Service tax , VAT etc 4192* 1.20 = 5030 Rs./- 20 % This is according to the current rate of material and labour charge. Reinforcement quantity is not calculated here because this quantity is calculated under separate head. They have not given the details about this.
Todays BUZZ Word Todays Buzz word “Building line out” According to R.C.C. design work whole building lineout work is done R.C.C. designer provide the detail steps. -cleaning the site & leveling it. -first with the help of bamboos & wooden flanks boundary of is marked. -then with the help of R.C.C.design provided the position of the column is marked on wooden planks. -then with help of nylon thread the exact position of column is marked on the ground. -then with the help of this marking ,excavation is done for foundation according to site conditions & columns are erected.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Milind Patil - 9860445661 Pritam Patil - 9225837979
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-02

Exam No. 10889
Company Name & Site Address sangavi builder & devlopers
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9 AM
Site Leaving Time 4 PM
Details of the Work Allotted to you today by the Site In-Charge To supervise Plumbing fittings and Column formwork and wall finishing. .
Details of how you Planned & Executed the allotted work First we see plumbing in D-5 bunglow and tale the details. And we also observed the shuttering work for formwork. .
Details of the Construction Procedure / Activity / Technology learned today Plumbing:- 1)Hot water pipes:- 20mm dia. (Ashirvad Company) 2)Cold water pipes:- 15mm dia. (Phinolex company) The pipingg were built-in masnory i.e. concealed piping. At the end of pipes taps were fitted. W.C. pipes were connected to the soil water pipe. Nhani traps were also provided. Column:- 1)Size:230*300 2)Shuttering material was cut to the required dimensions. 3)It was erected in plumb and alignment as per center-line plan. 4) Proper supports were given to the formwork. . .
Details of the Construction Materials learned today 1) PVC pipes 2) W.C. pans .
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly ash bricks were used. It solved the disposal problem of fly ash, as it is the waste product from thermal power plant. .
Details of the Construction / Engineering Drawings observed today Center-line plan Foundation plan. .
Details of the Bye Laws referred today We observed the diameters of pipes provided and compare with the bye-laws. They were as per bye-laws. .
Details of any Managerial Skill learned today Our in-charge prepares the working schedule and executes the work as per schedule. It helps in faster and proper execution of work. .
RATE ANALYSIS Concrete Grade: M-20 (1:1.5:3) 1 cu.m= 35.28 CFT Cement=6.9*255= Rs. 1759.5/- Sand=0.035*1.5*6.9*44*35.28=Rs.562.327/- Metal=0.035*3*6.9*18*35.28= Rs. 460.08/- Labour cost=40*35.28=Rs.1411/- Steel=75*35+250=Rs.2875/- Total=Rs.7100/- per cu m .
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Centre-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done. .
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Pritam Patil 9890997979 .
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: amitghorapade@rediffmail.com
Subject: 13526-02

Exam No. 13526
Company Name & Site Address vishwakarma builders,pratibhanagar,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09.00
Site Leaving Time 4.00
Details of the Work Allotted to you today by the Site In-Charge To check the dimensions of the columns.
Details of how you Planned & Executed the allotted work we individually carried out the measurements.
Details of the Construction Procedure / Activity / Technology learned today Tiles fitting and railing.
Details of the Construction Materials learned today A cross bar was used to keep gap to be filled later by white cement in between two tiles.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today no any technolgy used yet.
Details of the Construction / Engineering Drawings observed today column drawings.
Details of the Bye Laws referred today we have not referred any bye law today.
Details of any Managerial Skill learned today no skills learned today.
RATE ANALYSIS calculation for p.c.c. of 1:2:4(for 1 cu.m) cement-0.2171 cu.m sand-2*0.2171=0.4342 cu.m aggregate-4*0.2171=0.8684 cu.m rate: cement-7 bags=7*260 Rs.=Rs. 1820 sand-Rs. 725*0.4342=Rs. 314 aggregate-Rs. 450*0.8684=Rs.381 labour-Rs.600 Reinforcement-90*36=Rs.3240 total cost=Rs(1820+314+381+3240+600)=Rs.6355
Todays BUZZ Word As per the rough plan given by the architect it is checked whether the plan can be accomodated within the area provided.if yes, the wooden bars are placed are attached to bamboo poles throughout the boundary of the plot and keeping the particular distance, nylon ropes are laid across each other. and then the lineout is prepared.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, 3m Measurement Tape, Bye Law Book, Water Bottle
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge nitin gawade sir mob.9422046584
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-02

Exam No. 13572
Company Name & Site Address Shri samarth nagar by chaugale sawant developer
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check the coloum formwork erected on site.
Details of how you Planned & Executed the allotted work The no of coloum are divided.After checking it is been replaced.
Details of the Construction Procedure / Activity / Technology learned today How to detact hard murum by excavation and how it is identify.
Details of the Construction Materials learned today Fly ash brick-size 230*150*100 per day 2000 brick are manufactured fly ash & water is used.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The proper drainage system is adopted.The wastage is recycled.
Details of the Construction / Engineering Drawings observed today The appartment drawing. the footing detail.
Details of the Bye Laws referred today The witdh of road provided.
Details of any Managerial Skill learned today How they plan the work.
RATE ANALYSIS RCC (M25) CEMENT- 310-1281RS AGG-680RS/M3 SAND-380RS/M3 STEEL-164.398Kg-5700RS TOTAL-8041RS
Todays BUZZ Word BUILDING LINE OUT-Boundary line are marked by erecting the wooden plank. The position of column are marked by using lime putty & thread The tread are tied to wooden plank by placing nail on it. Then the excavation start.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SUHASH JADHAV 8007415015
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: pradnyatirmare@yahoo.in
Subject: 13572-02

Exam No. 13572
Company Name & Site Address Shri samarth nagar by chaugale sawant developer
Working Day No. 02
Date (DD/MM/YYYY) 09-12-2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge To check the coloum formwork erected on site.
Details of how you Planned & Executed the allotted work The no of coloum are divided.After checking it is been replaced.
Details of the Construction Procedure / Activity / Technology learned today How to detact hard murum by excavation and how it is identify.
Details of the Construction Materials learned today Fly ash brick-size 230*150*100 per day 2000 brick are manufactured fly ash & water is used.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The proper drainage system is adopted.The wastage is recycled.
Details of the Construction / Engineering Drawings observed today The appartment drawing. the footing detail.
Details of the Bye Laws referred today The witdh of road provided.
Details of any Managerial Skill learned today How they plan the work.
RATE ANALYSIS RCC (M25) CEMENT- 310-1281RS AGG-680RS/M3 SAND-380RS/M3 STEEL-164.398Kg-5700RS TOTAL-8041RS
Todays BUZZ Word BUILDING LINE OUT-Boundary line are marked by erecting the wooden plank. The position of column are marked by using lime putty & thread The tread are tied to wooden plank by placing nail on it. Then the excavation start.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge SUHASH JADHAV 8007415015
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: vrishalipatil@rocketmail.com
Subject: 13541-02

Exam No. 13541
Company Name & Site Address rajesh constructions
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00
Site Leaving Time 4.00
Details of the Work Allotted to you today by the Site In-Charge to take the level of building with respect to road level & to observe the central line plan.
Details of how you Planned & Executed the allotted work we ferstly take the level pipe & fill it with water. the air bubbles which are in pipe are then removed. then with the helpe of that pipe mark is made on the bar at same level of plinth level with respect to raod level on actual plan area. After it we just observe central line plan given by site incharge & ask him all the details to construct wood strip bamboo for decidingcolumn position.
Details of the Construction Procedure / Activity / Technology learned today Fixing of column position with the helpe of plumb bob on excavated box, Details of cantilever slab steel design, construction of hanging beam, to deside lenth of bar for making stirrups.
Details of the Construction Materials learned today Levelling pipe- to transfer the road level to construct plinth hieght.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of steel form work instead of bamboos due to which by reducing cutting of trees consumes forest trees.
Details of the Construction / Engineering Drawings observed today central line plan- fixing out plot boundry, margins. column layout- to fix positions of columns. steel design plan of second floor slab.
Details of the Bye Laws referred today plinth hieght- min.600 mm hight of door- 2100 mm
Details of any Managerial Skill learned today site incharge is very co-operative, freindly & inthusiastic. he has command on the workers.
RATE ANALYSIS masonry- 200per day mistri- 50per day
Todays BUZZ Word building line out is nothing but central line plan. there are column positions & central lines, plot boundry, distances from plot boundry & distences between columns are given in the layout plan.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. MILIND MAGDUM, Mob. no. 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: ladmanojs@gmail.com
Subject: 13534-02

Exam No. 13534
Company Name & Site Address rajesh constructions
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00
Site Leaving Time 400
Details of the Work Allotted to you today by the Site In-Charge to take the level of building with respect to road level & to observe the central line plan.
Details of how you Planned & Executed the allotted work we ferstly take the level pipe & fill it with water. the air bubbles which are in pipe are then removed. then with the helpe of that pipe mark is made on the bar at same level of plinth level with respect to raod level on actual plan area. After it we just observe central line plan given by site incharge & ask him all the details to construct wood strip bamboo for decidingcolumn position.
Details of the Construction Procedure / Activity / Technology learned today Fixing of column position with the helpe of plumb bob on excavated box, Details of cantilever slab steel design, construction of hanging beam, to deside lenth of bar for making stirrups.
Details of the Construction Materials learned today Levelling pipe- to transfer the road level to construct plinth hieght.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of steel form work instead of bamboos due to which by reducing cutting of trees consumes forest trees.
Details of the Construction / Engineering Drawings observed today central line plan- fixing out plot boundry, margins. column layout- to fix positions of columns. steel design plan of second floor slab.
Details of the Bye Laws referred today plinth hieght- min.600 mm hight of door- 2100 mm
Details of any Managerial Skill learned today site incharge is very co-operative, freindly & inthusiastic. he has command on the workers.
RATE ANALYSIS masonry- 200per day mistri- 50per day
Todays BUZZ Word building line out is nothing but central line plan. there are column positions & central lines, plot boundry, distances from plot boundry & distences between columns are given in the layout plan.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. MILIND MAGDUM, Mob. no. 9850508669
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: shraddha4@gmail.com
Subject: 10901-02

Exam No. 10901
Company Name & Site Address V.S.JOSHI & ASSOCIATES
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.30AM
Site Leaving Time 5.00PM
Details of the Work Allotted to you today by the Site In-Charge Today sir had alloted us to take measurement of the flat which was ready for use. Sir had told to give the detailed information about electrification, doors & windows, painting, flooring, fixtures & fastenings, etc.
Details of how you Planned & Executed the allotted work We proceeded to our work first by taking all the dimensions according to the rooms. we had first written all specifications, & detailing of rooms one by one. it is 4 BHK flat. like this we had observed the detailings alloted regarding to our work.
Details of the Construction Procedure / Activity / Technology learned today We had learned about electric wirings, fixtures & fastenings, placing of tiles & skirting to the floors, placing of windows.
Details of the Construction Materials learned today Door frames, fixtures &fastenings, windows, bed concrete.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Floor bed concrete to prevent dampness.
Details of the Construction / Engineering Drawings observed today Drawing of safety door which included components like square bars & perforated sheet.
Details of the Bye Laws referred today Providing doors & windows According to bye laws.
Details of any Managerial Skill learned today How to behave the clients & labours.
RATE ANALYSIS Rate analysis for Safety door : (size- 7\'x5\'.6\") MATERIALS QTY RATE AMOUNT 1) Rec. tube 19\'.6\" RS.44.00 RS.858.00 2) Square bar 22\'.6\" RS.12.25 RS.275.60 3) 1.5\"X3/4 Rec. tube 64\'0\" RS.38.50 RS.2464.00 4) Perforated sheet 18sq.ft RS.50.00 RS.900.00 5) Hinges, tower RS.550.00 bolt, aldrop, primar,etc TOTAL RS.5047.60 Wastage 5% RS.252.38 TOTAl RS.5299.98 Transportation RS.70.00 Labour charges 38.50sq.ft RS.60.00 RS.2310.00 TOTAL RS.7679.98
Todays BUZZ Word Building layout: How to measure dimensions of the rooms size, wall, open space surrounding building, approach road to building.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Amol Muley Sir
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: patilpratibha7070@yahoo.com
Subject: 10896-02

Exam No. 10896
Company Name & Site Address R.S.No.905/18 plotno.44,karan heritage,sardar park devkar panand,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.10pm
Details of the Work Allotted to you today by the Site In-Charge To observe the manufacturing of m20 concrete for slab and its compaction,placement.
Details of how you Planned & Executed the allotted work Three of us observed the manufacturing and two saw the compaction and placement and then inter changed our position.
Details of the Construction Procedure / Activity / Technology learned today Fixing of formwork planks at the sides of the beams, bar bending, binding of reinforcement bars, concealed wiring.
Details of the Construction Materials learned today Conduits of electrical wiring, junctions (assembly) used for connecting conduits in different directions.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not yet adopted.
Details of the Construction / Engineering Drawings observed today Centre line plan (building layout plan), typical floor plan, and footing plan column details.
Details of the Bye Laws referred today Stair case width provided at the site is 1.225m. As per bye law it is 1.20m.
Details of any Managerial Skill learned today Convincing talk with the customers with regards to site features and explaining the amenities provided in the building. Soft communication with the labours and inspection of slabs, beams reinforcement before concreting.
RATE ANALYSIS “Quantity calculation for R.C.C. column stilt slab to ground floor slabs bottom” 1.Quantity of concrete=40 cu.m. 2.Quantity of cement =58.64 cu.m. =172 bags 3.Quantity of sand =176 cu.m. 4.Quantity of coarse aggregate=352 cu.m. 5.Quantity of steel considering 10%as wastage Tor steel Fe-415 =2213.23kg =2.213 tonne Mild steel Fe-250 =530.34kg =0.534 tonne 6.Quantity of binding wire for 10 cu.m. =15.7 kg So for 40 cu.m.=62.8kg “Rate Analysis for R.C.C. column using M20 concrete” (Considering local rates of material) 1. Cost of cement =172*250=43,000/-....(250/- per bag) 2. Cost of sand =176*1600=2,81,600/-...(1600/- per cu.m.) 3. Cost of coarse aggregate=352*625=2,20,000/-...(1600/- per cu.m.) 4. Cost of tor steel = 2.213*32,000=70816/-....(1600/- per cu.m.) 5. Cost of mild steel =0.534*30,000=16,020/-.....(1600/- per cu.m.) 6. Cost of binding wire =30*62.8=1,884/-.... (1600/- per cu.m.) 7. Labour charges =11,840/- 8. Total cost = 6,45,160/- 9.10% profit of total cost for the contractor=64,516/- 10. Total cost =7,09,676/- 11. Rate per cu.m. = 17,741/-
Todays BUZZ Word “Building Line out” On the site base line method have been used for marking building line out. Total station has been used for fixing the origin points. The origin point is fixed at the face of column no.1 on the stilt floor and all the other respective ordinates’ and centre points have been fixed horizontally and perpendicularly with reference to the origin point.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: vishalsapkal124@gmail.com
Subject: 10882-02

Exam No. 10882
Company Name & Site Address R.S.No.905/18 plotno.44,karan heritage,sardar park devkar panand,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.10pm
Details of the Work Allotted to you today by the Site In-Charge To observe the manufacturing of m20 concrete for slab and its compaction,placement.
Details of how you Planned & Executed the allotted work Three of us observed the manufacturing and two saw the compaction and placement and then inter changed our position.
Details of the Construction Procedure / Activity / Technology learned today Fixing of formwork planks at the sides of the beams, bar bending, binding of reinforcement bars, concealed wiring.
Details of the Construction Materials learned today Conduits of electrical wiring, junctions (assembly) used for connecting conduits in different directions.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not yet adopted.
Details of the Construction / Engineering Drawings observed today Centre line plan (building layout plan), typical floor plan, and footing plan column details.
Details of the Bye Laws referred today Stair case width provided at the site is 1.225m. As per bye law it is 1.20m.
Details of any Managerial Skill learned today Convincing talk with the customers with regards to site features and explaining the amenities provided in the building. Soft communication with the labours and inspection of slabs, beams reinforcement before concreting.
RATE ANALYSIS “Quantity calculation for R.C.C. column stilt slab to ground floor slabs bottom” 1.Quantity of concrete=40 cu.m. 2.Quantity of cement =58.64 cu.m. =172 bags 3.Quantity of sand =176 cu.m. 4.Quantity of coarse aggregate=352 cu.m. 5.Quantity of steel considering 10%as wastage Tor steel Fe-415 =2213.23kg =2.213 tonne Mild steel Fe-250 =530.34kg =0.534 tonne 6.Quantity of binding wire for 10 cu.m. =15.7 kg So for 40 cu.m.=62.8kg “Rate Analysis for R.C.C. column using M20 concrete” (Considering local rates of material) 1. Cost of cement =172*250=43,000/-....(250/- per bag) 2. Cost of sand =176*1600=2,81,600/-...(1600/- per cu.m.) 3. Cost of coarse aggregate=352*625=2,20,000/-...(1600/- per cu.m.) 4. Cost of tor steel = 2.213*32,000=70816/-....(1600/- per cu.m.) 5. Cost of mild steel =0.534*30,000=16,020/-.....(1600/- per cu.m.) 6. Cost of binding wire =30*62.8=1,884/-.... (1600/- per cu.m.) 7. Labour charges =11,840/- 8. Total cost = 6,45,160/- 9.10% profit of total cost for the contractor=64,516/- 10. Total cost =7,09,676/- 11. Rate per cu.m. = 17,741/-
Todays BUZZ Word “Building Line out” On the site base line method have been used for marking building line out. Total station has been used for fixing the origin points. The origin point is fixed at the face of column no.1 on the stilt floor and all the other respective ordinates’ and centre points have been fixed horizontally and perpendicularly with reference to the origin point.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: hrishi116@rediffmail.com
Subject: 10885-01

Exam No. 10885
Company Name & Site Address R.S.No.905/18 plotno.44,karan heritage,sardar park devkar panand,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.10pm
Details of the Work Allotted to you today by the Site In-Charge To observe the manufacturing of m20 concrete for slab and its compaction,placement.
Details of how you Planned & Executed the allotted work Three of us observed the manufacturing and two saw the compaction and placement and then inter changed our position.
Details of the Construction Procedure / Activity / Technology learned today Fixing of formwork planks at the sides of the beams, bar bending, binding of reinforcement bars, concealed wiring.
Details of the Construction Materials learned today Conduits of electrical wiring, junctions (assembly) used for connecting conduits in different directions.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not yet adopted.
Details of the Construction / Engineering Drawings observed today Centre line plan (building layout plan), typical floor plan, and footing plan column details.
Details of the Bye Laws referred today Stair case width provided at the site is 1.225m. As per bye law it is 1.20m.
Details of any Managerial Skill learned today Convincing talk with the customers with regards to site features and explaining the amenities provided in the building. Soft communication with the labours and inspection of slabs, beams reinforcement before concreting.
RATE ANALYSIS “Quantity calculation for R.C.C. column stilt slab to ground floor slabs bottom” 1.Quantity of concrete=40 cu.m. 2.Quantity of cement =58.64 cu.m. =172 bags 3.Quantity of sand =176 cu.m. 4.Quantity of coarse aggregate=352 cu.m. 5.Quantity of steel considering 10%as wastage Tor steel Fe-415 =2213.23kg =2.213 tonne Mild steel Fe-250 =530.34kg =0.534 tonne 6.Quantity of binding wire for 10 cu.m. =15.7 kg So for 40 cu.m.=62.8kg “Rate Analysis for R.C.C. column using M20 concrete” (Considering local rates of material) 1. Cost of cement =172*250=43,000/-....(250/- per bag) 2. Cost of sand =176*1600=2,81,600/-...(1600/- per cu.m.) 3. Cost of coarse aggregate=352*625=2,20,000/-...(1600/- per cu.m.) 4. Cost of tor steel = 2.213*32,000=70816/-....(1600/- per cu.m.) 5. Cost of mild steel =0.534*30,000=16,020/-.....(1600/- per cu.m.) 6. Cost of binding wire =30*62.8=1,884/-.... (1600/- per cu.m.) 7. Labour charges =11,840/- 8. Total cost = 6,45,160/- 9.10% profit of total cost for the contractor=64,516/- 10. Total cost =7,09,676/- 11. Rate per cu.m. = 17,741/-
Todays BUZZ Word “Building Line out” On the site base line method have been used for marking building line out. Total station has been used for fixing the origin points. The origin point is fixed at the face of column no.1 on the stilt floor and all the other respective ordinates’ and centre points have been fixed horizontally and perpendicularly with reference to the origin point.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-02

Exam No. 10873
Company Name & Site Address R.S.No.905/18 plotno.44,karan heritage,sardar park devkar panand,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.10pm
Details of the Work Allotted to you today by the Site In-Charge To observe the manufacturing of m20 concrete for slab and its compaction,placement.
Details of how you Planned & Executed the allotted work Three of us observed the manufacturing and two saw the compaction and placement and then inter changed our position.
Details of the Construction Procedure / Activity / Technology learned today Fixing of formwork planks at the sides of the beams, bar bending, binding of reinforcement bars, concealed wiring.
Details of the Construction Materials learned today Conduits of electrical wiring, junctions (assembly) used for connecting conduits in different directions.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not yet adopted.
Details of the Construction / Engineering Drawings observed today Centre line plan (building layout plan), typical floor plan, and footing plan column details.
Details of the Bye Laws referred today Stair case width provided at the site is 1.225m. As per bye law it is 1.20m.
Details of any Managerial Skill learned today Convincing talk with the customers with regards to site features and explaining the amenities provided in the building. Soft communication with the labours and inspection of slabs, beams reinforcement before concreting.
RATE ANALYSIS “Quantity calculation for R.C.C. column stilt slab to ground floor slabs bottom” 1.Quantity of concrete=40 cu.m. 2.Quantity of cement =58.64 cu.m. =172 bags 3.Quantity of sand =176 cu.m. 4.Quantity of coarse aggregate=352 cu.m. 5.Quantity of steel considering 10%as wastage Tor steel Fe-415 =2213.23kg =2.213 tonne Mild steel Fe-250 =530.34kg =0.534 tonne 6.Quantity of binding wire for 10 cu.m. =15.7 kg So for 40 cu.m.=62.8kg “Rate Analysis for R.C.C. column using M20 concrete” (Considering local rates of material) 1. Cost of cement =172*250=43,000/-....(250/- per bag) 2. Cost of sand =176*1600=2,81,600/-...(1600/- per cu.m.) 3. Cost of coarse aggregate=352*625=2,20,000/-...(1600/- per cu.m.) 4. Cost of tor steel = 2.213*32,000=70816/-....(1600/- per cu.m.) 5. Cost of mild steel =0.534*30,000=16,020/-.....(1600/- per cu.m.) 6. Cost of binding wire =30*62.8=1,884/-.... (1600/- per cu.m.) 7. Labour charges =11,840/- 8. Total cost = 6,45,160/- 9.10% profit of total cost for the contractor=64,516/- 10. Total cost =7,09,676/- 11. Rate per cu.m. = 17,741/-
Todays BUZZ Word “Building Line out” On the site base line method have been used for marking building line out. Total station has been used for fixing the origin points. The origin point is fixed at the face of column no.1 on the stilt floor and all the other respective ordinates’ and centre points have been fixed horizontally and perpendicularly with reference to the origin point.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: bsalman75@yahoo.com
Subject: 10888-02

Exam No. 10888
Company Name & Site Address R.S.No.905/18 plotno.44,karan heritage,sardar park devkar panand,kolhapur.
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.10pm
Details of the Work Allotted to you today by the Site In-Charge To observe the manufacturing of m20 concrete for slab and its compaction,placement.
Details of how you Planned & Executed the allotted work Three of us observed the manufacturing and two saw the compaction and placement and then inter changed our position.
Details of the Construction Procedure / Activity / Technology learned today Fixing of formwork planks at the sides of the beams, bar bending, binding of reinforcement bars, concealed wiring.
Details of the Construction Materials learned today Conduits of electrical wiring, junctions (assembly) used for connecting conduits in different directions.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Not yet adopted.
Details of the Construction / Engineering Drawings observed today Centre line plan (building layout plan), typical floor plan, and footing plan column details.
Details of the Bye Laws referred today Stair case width provided at the site is 1.225m. As per bye law it is 1.20m.
Details of any Managerial Skill learned today Convincing talk with the customers with regards to site features and explaining the amenities provided in the building. Soft communication with the labours and inspection of slabs, beams reinforcement before concreting.
RATE ANALYSIS “Quantity calculation for R.C.C. column stilt slab to ground floor slabs bottom” 1.Quantity of concrete=40 cu.m. 2.Quantity of cement =58.64 cu.m. =172 bags 3.Quantity of sand =176 cu.m. 4.Quantity of coarse aggregate=352 cu.m. 5.Quantity of steel considering 10%as wastage Tor steel Fe-415 =2213.23kg =2.213 tonne Mild steel Fe-250 =530.34kg =0.534 tonne 6.Quantity of binding wire for 10 cu.m. =15.7 kg So for 40 cu.m.=62.8kg “Rate Analysis for R.C.C. column using M20 concrete” (Considering local rates of material) 1. Cost of cement =172*250=43,000/-....(250/- per bag) 2. Cost of sand =176*1600=2,81,600/-...(1600/- per cu.m.) 3. Cost of coarse aggregate=352*625=2,20,000/-...(1600/- per cu.m.) 4. Cost of tor steel = 2.213*32,000=70816/-....(1600/- per cu.m.) 5. Cost of mild steel =0.534*30,000=16,020/-.....(1600/- per cu.m.) 6. Cost of binding wire =30*62.8=1,884/-.... (1600/- per cu.m.) 7. Labour charges =11,840/- 8. Total cost = 6,45,160/- 9.10% profit of total cost for the contractor=64,516/- 10. Total cost =7,09,676/- 11. Rate per cu.m. = 17,741/-
Todays BUZZ Word “Building Line out” On the site base line method have been used for marking building line out. Total station has been used for fixing the origin points. The origin point is fixed at the face of column no.1 on the stilt floor and all the other respective ordinates’ and centre points have been fixed horizontally and perpendicularly with reference to the origin point.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap 9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: PNFEELINGS@gmail.com
Subject: 13569-02

Exam No. 13569
Company Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:00AM
Site Leaving Time 04:00PM
Details of the Work Allotted to you today by the Site In-Charge 1)Quantity calculation for R.C.C. footing 2)Quantity calculation for R.C.C. column
Details of how you Planned & Executed the allotted work 1)We go through the plans of steel design. 2)Then we find the total length of reinforcement. 3)Then we workout the weight of each bar used, and then sumed them up to get total weight of reinforcement. 4)Multiplying it with the market rate + labour cost give the total cost.
Details of the Construction Procedure / Activity / Technology learned today Line out Work:- Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done.
Details of the Construction Materials learned today Steel Reinforcement:- Steel:-1)Mild-Steel 2)Tor-steel Diameter available in market. Their weight per meter. Their market cost per kg.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of straight cut bar over U-cut bar saves the wastage of steel and thereby saving the natural minerals of steel.
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing: correlating with bye-laws 2)Line out plan:- contents:- a)c-c distance between all columns b)footing details c)R.C.C. column details i.e. size and reinforcement. d)Ground beam and Plinth beam details with floor level
Details of the Bye Laws referred today Minimum area of reinforcement required per cu.m of concrete Permissible limit:- Min 0.8% to Max 6.0%
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS Rate analysis for R.C.C Column Column size: 300x450 R.C.C Design of column:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Height of column: - Assume 3m height of column from footing up to plinth level. Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /-
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Center-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal. Mob. 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: ganeshsawant52@gmail.com
Subject: 13567-02

Exam No. 13567
Company Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:00 AM
Site Leaving Time 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge 1)Quantity calculation for R.C.C. footing 2)Quantity calculation for R.C.C. column
Details of how you Planned & Executed the allotted work 1)We go through the plans of steel design. 2)Then we find the total length of reinforcement. 3)Then we workout the weight of each bar used, and then sumed them up to get total weight of reinforcement. 4)Multiplying it with the market rate + labour cost give the total cost.
Details of the Construction Procedure / Activity / Technology learned today Line out Work:- Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done.
Details of the Construction Materials learned today Steel Reinforcement:- Steel:-1)Mild-Steel 2)Tor-steel Diameter available in market. Their weight per meter. Their market cost per kg.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of straight cut bar over U-cut bar saves the wastage of steel and thereby saving the natural minerals of steel.
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing: correlating with bye-laws 2)Line out plan:- contents:- a)c-c distance between all columns b)footing details c)R.C.C. column details i.e. size and reinforcement. d)Ground beam and Plinth beam details with floor level
Details of the Bye Laws referred today Minimum area of reinforcement required per cu.m of concrete Permissible limit:- Min 0.8% to Max 6.0%
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS Rate analysis for R.C.C Column Column size: 300x450 R.C.C Design of column:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Height of column: - Assume 3m height of column from footing up to plinth level. Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /-
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Center-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal. Mob. 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: rajukatral8@gmail.com
Subject: 13562-02

Exam No. 13562
Company Name & Site Address chaugle sawant developers, new balinga.
Working Day No. 02
Date (DD/MM/YYYY) 9.12.2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge checking of column shuttering, observation of excavation of pits, observation of plinth beam casting.
Details of how you Planned & Executed the allotted work first we saw all the drawings related to above work and then we observed execution of above works.
Details of the Construction Procedure / Activity / Technology learned today how ti excavate, line out of the building ,concreting in plinth beam , estabilishment of formwork for columns.
Details of the Construction Materials learned today formwork materials like ply,timber planks, fly ash, steel of grade 415 nd 500.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of pavement blocks to avoid soil erosion.
Details of the Construction / Engineering Drawings observed today r.c.c. drawings of columns and center line plans, r.c.c,drawing of footing.
Details of the Bye Laws referred today floor to floor height 3.15 m.
Details of any Managerial Skill learned today handelling labours skillfully and efficiently to carry out speedy work.
RATE ANALYSIS R.C.C. COLUMN ; For 1 cu.m steel = 165 kg =5700.00 Rs cement = 310 kg =1280.00 Rs sand = 120 kg = 380.00 Rs metal = 180 kg = 680.00 Rs total = 8140.00 RS. + 2% wastage + labour charges = 10000.00 Rs
Todays BUZZ Word Building line out ; 1. Plot boundary is fixed and marked. 2. As per detailed plan outline of building is fixed. 3. As per center line plan all positions of center line are marked by chalk pit. 4. Position of columns are marked. 5. Before marking position of column diagonals are checked.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Suhas Jadhav. mo no. 8007415015
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: mayur.sonawane61@gmail.com
Subject: 13570-02

Exam No. 13570
Company Name & Site Address P.B.DEVELOPERS , PREETAM RESIDENCY , SAMRAT-NAGAR
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:00 AM
Site Leaving Time 04:00 PM
Details of the Work Allotted to you today by the Site In-Charge 1)Quantity calculation for R.C.C. footing 2)Quantity calculation for R.C.C. column
Details of how you Planned & Executed the allotted work 1)We go through the plans of steel design. 2)Then we find the total length of reinforcement. 3)Then we workout the weight of each bar used, and then sumed them up to get total weight of reinforcement. 4)Multiplying it with the market rate + labour cost give the total cost.
Details of the Construction Procedure / Activity / Technology learned today Line out Work:- Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done.
Details of the Construction Materials learned today Steel Reinforcement:- Steel:-1)Mild-Steel 2)Tor-steel Diameter available in market. Their weight per meter. Their market cost per kg.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of straight cut bar over U-cut bar saves the wastage of steel and thereby saving the natural minerals of steel.
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing: correlating with bye-laws 2)Line out plan:- contents:- a)c-c distance between all columns b)footing details c)R.C.C. column details i.e. size and reinforcement. d)Ground beam and Plinth beam details with floor level
Details of the Bye Laws referred today Minimum area of reinforcement required per cu.m of concrete Permissible limit:- Min 0.8% to Max 6.0%
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS Rate analysis for R.C.C Column Column size: 300x450 R.C.C Design of column:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Height of column: - Assume 3m height of column from footing up to plinth level. Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /-
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Centre-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal. Mob. 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: sutar.namu@gmail.com
Subject: 13571-02

Exam No. 13571
Company Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:00am
Site Leaving Time 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1)Quantity calculation for R.C.C. footing 2)Quantity calculation for R.C.C. column
Details of how you Planned & Executed the allotted work 1)We go through the plans of steel design. 2)Then we find the total length of reinforcement. 3)Then we workout the weight of each bar used, and then sumed them up to get total weight of reinforcement. 4)Multiplying it with the market rate + labour cost give the total cost.
Details of the Construction Procedure / Activity / Technology learned today Line out Work:- Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done.
Details of the Construction Materials learned today Steel Reinforcement:- Steel:-1)Mild-Steel 2)Tor-steel Diameter available in market. Their weight per meter. Their market cost per kg.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of straight cut bar over U-cut bar saves the wastage of steel and thereby saving the natural minerals of steel.
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing: correlating with bye-laws 2)Line out plan:- contents:- a)c-c distance between all columns b)footing details c)R.C.C. column details i.e. size and reinforcement. d)Ground beam and Plinth beam details with floor level
Details of the Bye Laws referred today Minimum area of reinforcement required per cu.m of concrete Permissible limit:- Min 0.8% to Max 6.0%
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS Rate analysis for R.C.C Column Column size: 300x450 R.C.C Design of column:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Height of column: - Assume 3m height of column from footing up to plinth level. Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /-
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Center-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal. Mob. 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: shindesagara@gmail.com
Subject: 13568-02

Exam No. 13568
Company Name & Site Address P.B.Developers, Pritam residancy, Samrat Nagar
Working Day No. 02
Date (DD/MM/YYYY) 09/12/2010
Site Reporting Time 09:00am
Site Leaving Time 04:00pm
Details of the Work Allotted to you today by the Site In-Charge 1)Quantity calculation for R.C.C. footing 2)Quantity calculation for R.C.C. column
Details of how you Planned & Executed the allotted work 1)We go through the plans of steel design. 2)Then we find the total length of reinforcement. 3)Then we workout the weight of each bar used, and then sumed them up to get total weight of reinforcement. 4)Multiplying it with the market rate + labour cost give the total cost.
Details of the Construction Procedure / Activity / Technology learned today Line out Work:- Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done.
Details of the Construction Materials learned today Steel Reinforcement:- Steel:-1)Mild-Steel 2)Tor-steel Diameter available in market. Their weight per meter. Their market cost per kg.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Use of straight cut bar over U-cut bar saves the wastage of steel and thereby saving the natural minerals of steel.
Details of the Construction / Engineering Drawings observed today 1)Municipal drawing: correlating with bye-laws 2)Line out plan:- contents:- a)c-c distance between all columns b)footing details c)R.C.C. column details i.e. size and reinforcement. d)Ground beam and Plinth beam details with floor level
Details of the Bye Laws referred today Minimum area of reinforcement required per cu.m of concrete Permissible limit:- Min 0.8% to Max 6.0%
Details of any Managerial Skill learned today Convey work to be done to Mukadam/ supervisor instead of talking to the worker.
RATE ANALYSIS Rate analysis for R.C.C Column Column size: 300x450 R.C.C Design of column:- Main Steel: - 16mm bar 8no. Stirrups:-8mm bar 150mm c-c. Concrete Cover:- 25mm QUANTITIES Height of column: - Assume 3m height of column from footing up to plinth level. Length of each steel bar: - Length (1) = (0.05+0.3+3.0+0.8)*4 =16.6m Length (2) = (0.05+0.3+3.0+1.8)*4 =20.6m Total =37.2m Length of stirrups:- Length = (0.4*2)+(0.25*2)+(0.05*2)+(0.06*2)+(0.25*2)+(0.05*2)= 2.12m No of stirrups= 3/0.15=20nos. Total Length= 2.12*20=42.4m Bar Dia. Cutting Length Weight/meter Total 16mm 37.2m 1.58kg 58.77kg 8mm 42.4m 0.39kg 16.53kg TOTAL WT.= 75.30kg COST OF MATERIAL MATERIAL QUANTITY(cu.m) RATE /10 cu.m COST Cement 0.086 7575.75/- 651.51/- Sand 0.129 2400/- 309.6/- Aggregate 0.258 535/- 138.03/- TOTAL = 1099.15/- COST OF LABOUR LABOUR QUANTITY/10 CU.M RATE/DAY COST MASON 02 250 500 /- M.MAZDOOR 10 150 1500/- F.MAZDOOR 12 120 1440/- BHISTY 06 120 720/- TOTAL QUANTITY FOR 10 CU.M IS = 4160/- TOTAL COST FOR 0.472 CU.M IS 196.353 TOTAL COST OF MATERIAL + LABOUR = 1099.15+196.35 = 1295.5 /- COST OF R/F Quantity of steel used = 75.30 kg Rate per kg = Rs. 45 /- TOTAL COST OF STEEL = 75.30 x 45 = Rs. 3388.5 /- TOTAL COST FOR 0.472 cu.m = cost of material + labour+steel Rs. 1099.15 + Rs. 196.353 + Rs. 3388.5 = Rs. 4684 /- Total cost for 1 cu.m = Rs. 9923.72 /-
Todays BUZZ Word Line out:- Line out is nothing but plotting of Column and Foundation positions as per Center-line plan. Drawings Required:- 1) Centre-line plan for column position. 2) Municipal Plan/ Site plan for side margins. Procedure:- 1) Clean site. 2) Mark the actual boundaries. 3) Make arrangement for marking of column Centre just away from building line. 4) Mark the position of Centers of column on each of four sides. 5) Tie the line-dory from the centres marked on X & Y direction. 6) The point of intersection of the two line-dory is the centre of the column on the field. 7) Mark that point point on ground. 8) Repeat the same procedure for all columns and get the line out done.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Mr. Pradip Bharamal. Mob. 9423281981
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/09/2010
E-mail Address: profiipathan@gmail.com
Subject: Testing 9.12.2010 - 1

Exam No. p
Company Name & Site Address p
Working Day No. p
Date (DD/MM/YYYY) p
Site Reporting Time p
Site Leaving Time p
Details of the Work Allotted to you today by the Site In-Charge p
Details of how you Planned & Executed the allotted work p
Details of the Construction Procedure / Activity / Technology learned today p
Details of the Construction Materials learned today p
Details of Environment Caring Technology / Methodology / Procedure / Product learned today p
Details of the Construction / Engineering Drawings observed today p
Details of the Bye Laws referred today p
Details of any Managerial Skill learned today p
RATE ANALYSIS p
Todays BUZZ Word p
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) No
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet
Daily Site Work Form filled, stamped & signed by the Site In-Charge? No
Name & Mobile No. of the Site In-charge p
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: devkar241090@gmail.com
Subject: 13523-01

Exam No. 13523
Project Name Pooja Developers & Builders
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 09:00am
Site Leaving Time 04:00pm
Details of the Work Allotted to you today by the Site In-Charge To check beam reinforcement according to plan & to mark position of plumbing units according to plumbing plan.
Details of how you Planned & Executed the allotted work To read plan and then check the beam reinforcement provided according to plan.
Details of the Construction Procedure / Activity / Technology learned today How beam reinforcement is made and laid in formwork. How leakage is detected with pressure test.
Details of the Construction Materials learned today To know the pipe (class \"C\") used in reticulated L.P.G. system with maximum discharge(half kg/hr). Joints are done with Socket weld.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly ash bricks were used at compound wall.
Details of the Construction / Engineering Drawings observed today Beam reinforcement plan and plumbing plan with details.
Details of the Bye Laws referred today To check rise and trade of stairs provided at site.
Details of any Managerial Skill learned today How to convince customer with regards of building comfort and safety.
RATE ANALYSIS Quantity calculation for p.c.c of 1:3:6 Quantity of concrete-36.66cu.m cement Quantity -53.74 cu.m (163 bags) sand Quantity -161.30 cu.m Aggregate Quantity -322.60 cu.m Rate calculations cement- 265*163=43195/- sand- 48*161.30=7742.4/- Aggregate- 47.6*322.60=15355.76/- total amount-66293.16/- rate for 1cu.m=1808.32/-
Todays BUZZ Word -Empty Cement bags were used for electric covering. -Leakage test was done to avoid leakage of pipe before plumbing. -Cello tape was used at joints of form work to avoid leakage of concrete material.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge P.B.Sutar
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: sharadpatil143@rediffmail.com
Subject: 10897-01

Exam No. 10897
Project Name Chandra Milla, Shivshakti Developers
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 09.30am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plaster work.
Details of how you Planned & Executed the allotted work We prepare the check list with the help of site in-charge and followed the same while executing the work.
Details of the Construction Procedure / Activity / Technology learned today Preperation of Fly ash bricks:- Material required:- Stone dust, lime, cement, water, fly ash. Mixing:- Mix above ingredients in appropriate proportion in mixing machine. Moulding:- Pour that mix in hydraulic press machine. Brick size:-0.23*0.15*0.15. Capacity of Machine:- 10 bricks at a time.
Details of the Construction Materials learned today Fly ash brick. 4 pans stone dust. 1 pan lime. 1 pan cement. 1 pan fly ash. water as per design.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly ash is the waste product of Thermal Power Plants. Earlier there was a big problem of it\'s disposal. But use of fly ash in construction has reduced the problem.
Details of the Construction / Engineering Drawings observed today Parking and Garden Drawing.
Details of the Bye Laws referred today Height and size of mezzanine floor and also the requirement of mezzanine floor we refered from by-laws.
Details of any Managerial Skill learned today Punctuality helps in better work.
RATE ANALYSIS Item Quantity(Cu.M) Cost(Rs) 1)Cement 4.5 bags 1170 2)Sand 0.5 578 3)Aggregate 0.9 274 4)Labor Rate Cost(Rs.) a)cement shifting/bag 1 5 b)concrete pouring/bag 40 180 c)concrete mixing/bag 20 90 d)form-work/cumec 35 35 e)wooden patti material 20 20 Total:-2350/-
Todays BUZZ Word Material wastage reduction:- Material which falls down while plastering can be reused again but before 30min. 2% wastage is considered.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9822846878
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: rathod2211@gmail.com
Subject: 10881-01

Exam No. 10881
Project Name s.s.builders and developers
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 9:00 AM
Site Leaving Time 4:00 PM
Details of the Work Allotted to you today by the Site In-Charge To observation the total constructed area
Details of how you Planned & Executed the allotted work We did planned, swa how to do brick work, brick bonding, nd how to applying birla putty on internal wall.
Details of the Construction Procedure / Activity / Technology learned today Electric Steel cutter mechine= We learn how to cut steel on mechanical device
Details of the Construction Materials learned today Admixture, Protect sbr coat, lws coat, for water proofing
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Providing big garden in plot area
Details of the Construction / Engineering Drawings observed today In the drawing total 72 flats are there In that 60- 2 Bhk 12-3 Bhk, nd 6 row houses
Details of the Bye Laws referred today Restriction of room height 3 meters
Details of any Managerial Skill learned today How to speak with client
RATE ANALYSIS For pcc. Total area=17.93 m3 1m3= 9938 rupess Total area=178188 rupess
Todays BUZZ Word For plaster external lws For rcc. Sbr coat+cement
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Ketan charpale 9552597474
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: amitcivil52@gmail.com
Subject: 10900-01

Exam No. 10900
Project Name Chandra Milla, Shivshakti Developers
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 9.30am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge Supervision of plaster work.
Details of how you Planned & Executed the allotted work We prepare the check list with the help of site in-charge and followed the same while executing the work.
Details of the Construction Procedure / Activity / Technology learned today Preperation of Fly ash bricks:- Material required:- Stone dust, lime, cement, water, fly ash. Mixing:- Mix above ingredients in appropriate proportion in mixing machine. Moulding:- Pour that mix in hydraulic press machine. Brick size:-0.23*0.15*0.15. Capacity of Machine:- 10 bricks at a time.
Details of the Construction Materials learned today Fly ash brick. 4 pans stone dust. 1 pan lime. 1 pan cement. 1 pan fly ash. water as per design.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today Fly ash is the waste product of Thermal Power Plants. Earlier there was a big problem of it\'s disposal. But use of fly ash in construction has reduced the problem.
Details of the Construction / Engineering Drawings observed today Parking and Garden Drawing.
Details of the Bye Laws referred today Height and size of mezzanine floor and also the requirement of mezzanine floor we refered from by-laws.
Details of any Managerial Skill learned today Punctuality helps in better work.
RATE ANALYSIS Item Quantity(Cu.M) Cost(Rs) 1)Cement 4.5 bags 1170 2)Sand 0.5 578 3)Aggregate 0.9 274 4)Labor Rate Cost(Rs.) a)cement shifting/bag 1 5 b)concrete pouring/bag 40 180 c)concrete mixing/bag 20 90 d)form-work/cumec 35 35 e)wooden patti material 20 20 Total:-2350/-
Todays BUZZ Word Material wastage reduction:- Material which falls down while plastering can be reused again but before 30min. 2% wastage is considered.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Jagtap M.S. 9822846878
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: rajendrapawar54@gmail.com
Subject: 13542-01

Exam No. 13542
Project Name animesh nagar
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge observation of site with site incharge
Details of how you Planned & Executed the allotted work 1.we selected building one by one and observed in group
Details of the Construction Procedure / Activity / Technology learned today 1.study of formework 2.painting
Details of the Construction Materials learned today 1.portland pozzolona cement contain fly ash
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of spunge doors for toilets which are coted with fibre materials
Details of the Construction / Engineering Drawings observed today 1.plans of row bunglows
Details of the Bye Laws referred today observation of site margines and sizes of doors and windows
Details of any Managerial Skill learned today impressive communication with us and good command on labours and site incharge
RATE ANALYSIS for PCC PCC -10\'x10\' 1.cement- 3.50 bag x 250Rs = 875Rs 2.aggregate - 90 cu.ft x 15 =1350Rs 3.sand - 50 cu.ft x 37 =1850Rs 4.labour- =400Rs 5.water charges =70Rs total =4545Rs contracter profit 20% =909Rs total with prifit =4636Rs rate for per sq.ft=46.36Rs=47Rs
Todays BUZZ Word construction materials wastage reduction 1.use of RMC for R.C.C. slab 2. proper method used for stored materials for cement, sand ,aggregate
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Nilesh Bhapat
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: yogesh.dalvi67@gmail.com
Subject: 10889-01

Exam No. 10889
Project Name sunlight residancy
Working Day No. 01
Date (DD/MM/YYYY) 08-12-2010
Site Reporting Time 9AM
Site Leaving Time 4.30PM
Details of the Work Allotted to you today by the Site In-Charge intaranal finishing ,wall/& p.c.c information
Details of how you Planned & Executed the allotted work first all work to done is obasered.then take information about this work to site incharge ..then follow this procedure to give us.& condut whole work of finishing
Details of the Construction Procedure / Activity / Technology learned today firstcement plaster wall scrabed properly then applay WHITE CEMENT coat in proper mix(POP)
Details of the Construction Materials learned today white cement (POP) of25kg bag lambi(gelly material) primer ACE pait(Oil bond paint)
Details of Environment Caring Technology / Methodology / Procedure / Product learned today not any caring technology is use for painting work.. only sanitary water are used after chemical tretment for gardaning..& save more water.
Details of the Construction / Engineering Drawings observed today all residancy of working drawing are seen;such as row house, appartment,bungalo(2 bhk/3bhk) basemet, parking..
Details of the Bye Laws referred today wall surface are preperd properly for first coat
Details of any Managerial Skill learned today handaling of worker...
RATE ANALYSIS from given information of past... p c c-1:4:8 are used 1cm3=1.25c f t cement=3.40*255=867/- (cement=255Rs) metal=34*181=621/- sand=17*441=748/- (2.75Brass=12000/-) labour for 1m3*857=857 total= 3084/- per m3
Todays BUZZ Word mix in proper praportion,alo for mixing carry on metal plate therfore save mixing ingredient.i.g soil not absorb any ingredient of mix.sanitary water are re used for gardning purpose.also fly ash are used in mixing it save cement withaut disturb quality.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge mr pritam patil
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: nikitashinde15@gmail.com
Subject: 13547-01

Exam No. 13547
Project Name animesh nagar
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge observation of site with site incharge
Details of how you Planned & Executed the allotted work 1.we selected building one by one and observed in group
Details of the Construction Procedure / Activity / Technology learned today 1.study of formework 2.painting
Details of the Construction Materials learned today 1.portland pozzolona cement contain fly ash
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of spunge doors for toilets which are coted with fibre materials
Details of the Construction / Engineering Drawings observed today 1.plans of row bunglows
Details of the Bye Laws referred today observation of site margines and sizes of doors and windows
Details of any Managerial Skill learned today impressive communication with us and good command on labours and site incharge
RATE ANALYSIS for PCC PCC -10\'x10\' 1.cement- 3.50 bag x 250Rs = 875Rs 2.aggregate - 90 cu.ft x 15 =1350Rs 3.sand - 50 cu.ft x 37 =1850Rs 4.labour- =400Rs 5.water charges =70Rs total =4545Rs contracter profit 20% =909Rs total with prifit =4636Rs rate for per sq.ft=46.36Rs=47Rs
Todays BUZZ Word construction materials wastage reduction 1.use of RMC for R.C.C. slab 2. proper method used for stored materials for cement, sand ,aggregate
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge (Delete this Sentence & Keep this 1st line BLANK for better appearance of your report)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: madhavjade@gmail.com
Subject: 13560-01

Exam No. 13560
Project Name Chaugule Sawant Developers,Shree samarth nagar.
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 09:00AM
Site Leaving Time 04:00PM
Details of the Work Allotted to you today by the Site In-Charge To understand the whole site with the drawings.
Details of how you Planned & Executed the allotted work First we saw the drawings and then we went to the site to saw the actual construction work.
Details of the Construction Procedure / Activity / Technology learned today We learned about the needle vibrator, generator etc .
Details of the Construction Materials learned today We learned about Fly ash brick & koromandal cement etc.
Details of Environment Caring Technology / Methodology / Procedure / Product learned today The project has sufficient drainage system.
Details of the Construction / Engineering Drawings observed today Working drawing of whole project.
Details of the Bye Laws referred today Excavation for Footing having 6\" extra on both side.
Details of any Managerial Skill learned today We learned that How to communicate with labour on site.
RATE ANALYSIS For P.C.C. RATE =3500 Rs/Cubic Metre MATERIAL QUANTITY RATE 1 CEMENT 310Kg 1281Rs 2 AGGREGATE 930Kg 680Rs 3 SAND 465Kg 381Rs TOTAL= 2151Rs Add 2% for wastage and add labour cost 1100Rs Total = 3500Rs/cumec
Todays BUZZ Word Don\'t use more than 2% extra material.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? Yes
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box, Book : A to Z of Building Construction
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Suhas Jadhav Sir, Mob : 8007415015
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: vishwajit.p09@gmail.com
Subject: 13543-01

Exam No. 13543
Project Name animesh nagar
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge observation of site with site incharge
Details of how you Planned & Executed the allotted work 1.we selected building one by one and observed in group
Details of the Construction Procedure / Activity / Technology learned today 1.study of formework 2.painting
Details of the Construction Materials learned today 1.portland pozzolona cement contain fly ash
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of spunge doors for toilets which are coted with fibre materials
Details of the Construction / Engineering Drawings observed today 1.plans of row bunglows
Details of the Bye Laws referred today observation of site margines and sizes of doors and windows
Details of any Managerial Skill learned today impressive communication with us and good command on labours and site incharge
RATE ANALYSIS for PCC PCC -10\'x10\' 1.cement- 3.50 bag x 250Rs = 875Rs 2.aggregate - 90 cu.ft x 15 =1350Rs 3.sand - 50 cu.ft x 37 =1850Rs 4.labour- =400Rs 5.water charges =70Rs total =4545Rs contracter profit 20% =909Rs total with prifit =4636Rs rate for per sq.ft=46.36Rs=47Rs
Todays BUZZ Word construction materials wastage reduction 1.use of RMC for R.C.C. slab 2. proper method used for stored materials for cement, sand ,aggregate
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge (Delete this Sentence & Keep this 1st line BLANK for better appearance of your report)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: sachinpatilthk@gmail.com
Subject: 13539-01

Exam No. 13539
Project Name animesh nagar
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge observation of site with site incharge
Details of how you Planned & Executed the allotted work 1.we selected building one by one and observed in group
Details of the Construction Procedure / Activity / Technology learned today 1.study of formework 2.painting
Details of the Construction Materials learned today 1.portland pozzolona cement contain fly ash
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of spunge doors for toilets which are coted with fibre materials
Details of the Construction / Engineering Drawings observed today 1.plans of row bunglows
Details of the Bye Laws referred today observation of site margines and sizes of doors and windows
Details of any Managerial Skill learned today impressive communication with us and good command on labours and site incharge
RATE ANALYSIS for PCC PCC -10\'x10\' 1.cement- 3.50 bag x 250Rs = 875Rs 2.aggregate - 90 cu.ft x 15 =1350Rs 3.sand - 50 cu.ft x 37 =1850Rs 4.labour- =400Rs 5.water charges =70Rs total =4545Rs contracter profit 20% =909Rs total with prifit =4636Rs rate for per sq.ft=46.36Rs=47Rs
Todays BUZZ Word construction materials wastage reduction 1.use of RMC for R.C.C. slab 2. proper method used for stored materials for cement, sand ,aggregate
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge (Delete this Sentence & Keep this 1st line BLANK for better appearance of your report)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: sangrampatil7767@gmail.com
Subject: 13540-01

Exam No. 13540
Project Name animesh nagar
Working Day No. 01
Date (DD/MM/YYYY) 8-12-2010
Site Reporting Time 9.00am
Site Leaving Time 4.00pm
Details of the Work Allotted to you today by the Site In-Charge observation of site with site incharge
Details of how you Planned & Executed the allotted work 1.we selected building one by one and observed in group
Details of the Construction Procedure / Activity / Technology learned today 1.study of formework 2.painting
Details of the Construction Materials learned today 1.portland pozzolona cement contain fly ash
Details of Environment Caring Technology / Methodology / Procedure / Product learned today use of spunge doors for toilets which are coted with fibre materials
Details of the Construction / Engineering Drawings observed today 1.plan of row bunglow
Details of the Bye Laws referred today observation of site margines and sizes of doors and windows
Details of any Managerial Skill learned today impressive communication with us and good command on labours and site incharge
RATE ANALYSIS for PCC PCC -10\'x10\' 1.cement- 3.50 bag x 250Rs = 875Rs 2.aggregate - 90 cu.ft x 15 =1350Rs 3.sand - 50 cu.ft x 37 =1850Rs 4.labour- =400Rs 5.water charges =70Rs total =4545Rs contracter profit 20% =909Rs total with prifit =4636Rs rate for per sq.ft=46.36Rs=47Rs
Todays BUZZ Word construction materials wastage reduction 1.use of RMC for R.C.C. slab 2. proper method used for stored materials for cement, sand ,aggregate
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Eye Protectors / Goggles, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge (Delete this Sentence & Keep this 1st line BLANK for better appearance of your report)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: moreshwar1989@gmail.com
Subject: 10873-01

Exam No. 10873
Project Name R.S.No.905/18 plotno.44,karan heritage,sardar park devkar panand,kolhapur.
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To check dimensions of beams,columns,slabs.
Details of how you Planned & Executed the allotted work firstly we have distributed sections amongst us and interchanged our sections for cross checking.
Details of the Construction Procedure / Activity / Technology learned today preparation of concrete for casting sunk slab using weigh batchers and tilting type mixers and transporting concrete by means of lift and bucket arrangement.Use of needle vibrator for compaction
Details of the Construction Materials learned today cement-43grade of coromandal packed in 25 kg bags. Aggregate-20mm-15mm steel bars- Tor steel-8mm,12mm,16mm,20mm. sand of silt content not exceeding not more than 6%. conventional bricks
Details of Environment Caring Technology / Methodology / Procedure / Product learned today still no such methodology adopted
Details of the Construction / Engineering Drawings observed today Stilt floor drawing. Footing drawing.
Details of the Bye Laws referred today bye law for building facing <15m road are used. marginal spacing provided are-front margin-3.0m,right side-4.875.left side-3.675mto 5.4m,rear margin-5.75m. the above dimensions are more than minimum provided in bye laws.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS Quantity calculation for p.c.c of 1:3:6 Quantity of concrete-36.66cu.m cement Quantity -53.74 cu.m (163 bags) sand Quantity -161.30 cu.m Aggregate Quantity -322.60 cu.m Rate calculations cement- 250*163=40,750/- sand- 1600*161.30=2,58,080/- Aggregate- 625*322.60=2,01,625/- labour charges- 9000/- total amount-5,09,455/- rate for 1cu.m=13,919.53/-
Todays BUZZ Word construction material wastage reduction\"- on site small cut pieces of steel bars have been used in intermediate sections for reinforcement.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap Mo No.9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: vishalsapkal124@gmail.com
Subject: 10882-01

Exam No. 10882
Project Name R.S.No.905/18 plotno.44,karan heritage,sardar park devkar panand,kolhapur.
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To check dimensions of beams,columns,slabs.
Details of how you Planned & Executed the allotted work firstly we have distributed sections amongst us and interchanged our sections for cross checking.
Details of the Construction Procedure / Activity / Technology learned today preparation of concrete for casting sunk slab using weigh batchers and tilting type mixers and transporting concrete by means of lift and bucket arrangement.Use of needle vibrator for compaction
Details of the Construction Materials learned today cement-43grade of coromandal packed in 25 kg bags. Aggregate-20mm-15mm steel bars- Tor steel-8mm,12mm,16mm,20mm. sand of silt content not exceeding not more than 6%. conventional bricks
Details of Environment Caring Technology / Methodology / Procedure / Product learned today still no such methodology adopted
Details of the Construction / Engineering Drawings observed today Stilt floor drawing. Footing drawing.
Details of the Bye Laws referred today bye law for building facing <15m road are used. marginal spacing provided are-front margin-3.0m,right side-4.875.left side-3.675mto 5.4m,rear margin-5.75m. the above dimensions are more than minimum provided in bye laws.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS Quantity calculation for p.c.c of 1:3:6 Quantity of concrete-36.66cu.m cement Quantity -53.74 cu.m (163 bags) sand Quantity -161.30 cu.m Aggregate Quantity -322.60 cu.m Rate calculations cement- 250*163=40,750/- sand- 1600*161.30=2,58,080/- Aggregate- 625*322.60=2,01,625/- labour charges- 9000/- total amount-5,09,455/- rate for 1cu.m=13,919.53/-
Todays BUZZ Word construction material wastage reduction\"- on site small cut pieces of steel bars have been used in intermediate sections for reinforcement.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge Rajiv Jagtap Mo No.9423039898
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it


Sent: 12/08/2010
E-mail Address: bsalman75@yahoo.com
Subject: 10888-01

Exam No. 10888
Project Name R.S.No.905/18 plotno.44,karan heritage,sardar park devkar panand,kolhapur.
Working Day No. 01
Date (DD/MM/YYYY) 08/12/2010
Site Reporting Time 9.00am
Site Leaving Time 4.15pm
Details of the Work Allotted to you today by the Site In-Charge To check dimensions of beams,columns,slabs.
Details of how you Planned & Executed the allotted work firstly we have distributed sections amongst us and interchanged our sections for cross checking.
Details of the Construction Procedure / Activity / Technology learned today preparation of concrete for casting sunk slab using weigh batchers and tilting type mixers and transporting concrete by means of lift and bucket arrangement.Use of needle vibrator for compaction.
Details of the Construction Materials learned today cement-43grade of coromandal packed in 25 kg bags. Aggregate-20mm-15mm steel bars- Tor steel-8mm,12mm,16mm,20mm. sand of silt content not exceeding not more than 6%. conventional bricks
Details of Environment Caring Technology / Methodology / Procedure / Product learned today still no such methodology adopted
Details of the Construction / Engineering Drawings observed today Stilt floor drawing. Footing drawing.
Details of the Bye Laws referred today bye law for building facing <15m road are used. marginal spacing provided are-front margin-3.0m,right side-4.875.left side-3.675mto 5.4m,rear margin-5.75m. the above dimensions are more than minimum provided in bye laws.
Details of any Managerial Skill learned today regular inspection of various works.
RATE ANALYSIS Quantity calculation for p.c.c of 1:3:6 Quantity of concrete-36.66cu.m cement Quantity -53.74 cu.m (163 bags) sand Quantity -161.30 cu.m Aggregate Quantity -322.60 cu.m Rate calculations cement- 250*163=40,750/- sand- 1600*161.30=2,58,080/- Aggregate- 625*322.60=2,01,625/- labour charges- 9000/- total amount-5,09,455/- rate for 1cu.m=13,919.53/-
Todays BUZZ Word \"construction material wastage reduction\"- on site small cut pieces of steel bars have been used in intermediate sections for reinforcement.
Taken Site Photographs today? (You can also share these pics online. Read Instructions given in this blog) Yes
Faced any Accident / Injury today? No
I carried & used following accessories on the site today Safety Helmet, Shoes, Cap, 3m Measurement Tape, Camera, Bye Law Book, Note Pad, Water Bottle, Lunch Box
Daily Site Work Form filled, stamped & signed by the Site In-Charge? Yes
Name & Mobile No. of the Site In-charge (Delete this Sentence & Keep this 1st line BLANK for better appearance of your report)
Disclaimer : I am aware that, if information provided in this form, by me, found untrue, at the time of assessment, the institute may disqualify my entire work done Yes, I am aware of it